SlideShare a Scribd company logo
1 of 18
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED
ACTION: Perform a power load survey
CONDITIONS: Given a classroom an field environment, an
understanding of electrical theory, regulatory guidance, and applicable
personal protective equipment
STANDARD: Perform a load survey applying theory, regulatory
guidance, and principles of electrical design.
UNCLASSIFIED
UNCLASSIFIED
• Safety Requirements: None
• Risk Assessment Level: Low
• Environmental Considerations: None
• Evaluation: Students will be evaluated on this
block of instruction during the Electrical Systems
Design Examination 4. Students must receive a
score of 80 percent or above to receive a GO.
UNCLASSIFIED
UNCLASSIFIED
EM385-1-1
NFPA 70
NFPA 70E
Safety and Health Requirements
NEC 2017
Standard for Electrical Safety in the Workplace
UNCLASSIFIED
UNCLASSIFIED
What is it and what is it used for?
1. It’s an analysis of power requirements, and a vital step in
providing electrical power support. The recommended power
source is determined based on the load survey.
3. It determines the required level of reliability and identifies any
special power demands or problems. A thorough load survey
must be completed before installing a power plant or
designing a distribution system.
2. Personnel conducting an Infrastructure Recon conduct the
load survey to determine the supported power and distribution
requirements of a unit.
UNCLASSIFIED
UNCLASSIFIED
Types of load surveys:
1. New Construction
2. Disaster Relief
3. Circuit Upgrade
4. Field Exercises
UNCLASSIFIED
UNCLASSIFIED
Determine Building or Site Load
1. Calculate the loads
2. Generator Sizing
-single phase/three phase
-prime/standby/continuous
-voltage and frequency
-altitude and temperature
3. Distribution Equipment and Material Requirements
-organic or non-organic
-cables, panels, etc
4. Load Balancing
5. Tie in location
UNCLASSIFIED
UNCLASSIFIED
Acquire electrical data
-electrical plans
-equipment specifications
-on site visual inspections
Determine the total connected load
Calculate the demand load
UNCLASSIFIED
UNCLASSIFIED
1. General lighting
2. Receptacles
3. Motors
4. Major appliances
UNCLASSIFIED
UNCLASSIFIED
You are currently TCS’d to Camp Arifjan, Kuwait with your local BEB. A mission has
come down to deploy your unit to Ramadi, Iraq in order to win the hearts and minds of
the local population. During the PDSS, three local buildings have been identified as
hard stand structures that will be occupied during this mission. These will be used as a
barracks, TOC and DFAC. They already have local electrical panels, wiring and
equipment installed in them that will be used, but the local power is very unreliable and
will not be used. The BC doesn’t want to install anything new if possible since this will
be a short term mission. Organic electrical equipment that will be used in these
buildings, along with existing installed local equipment have already been identified
during the PDSS.
Perform a load assessment of these buildings. How will you power these buildings-
what size/type generator and distributions system will you use? Where will it/they be
located? Take into account voltage drop and load balancing. Design a system in
AutoDISE to accomplish this.
UNCLASSIFIED
UNCLASSIFIED
Kitchen
CUOPS
Sleeping Area
S2 S1/3/4
Conference
Room
10m
7m
7m
7m
24m
5m
21m
20m
24m
Dining Area10m
7m
200A Panel Box
100A Panel Box
Panel Box
60A Panel Box
50m
50m
75m
UNCLASSIFIED
UNCLASSIFIED
Dining Area
-50ea florescent lights w/ 1.2A ballasts
-10ea duplex outlets on each long wall and 4ea outlets on each short wall
-1ea split unit AC (model PU-2.5VAKD.TD) connected to each wall outlet on the long walls
Kitchen
-18ea florescent lights w/ 1.2A ballasts
-3ea ovens and stove combo, each on dedicated circuits
-3ea vent hoods each on dedicated circuits; 230V @ 8A
-1ea mixer
-3ea duplex outlets on each of the side walls
-1ea split unit AC (model PU-2.5VAKD.TD) connected to each wall outlet on the side walls
-3ea duplex outlets on each of the other two walls
UNCLASSIFIED
UNCLASSIFIED
Sleeping Area
-80ea florescent lights w/ 1.1A ballasts
-10ea duplex outlets on each wall
-1ea split unit AC (model PU-2VAKD.TD) connected to each wall outlet on two of the side walls
S1/3/4
-12ea florescent lights w/ 1.1A ballasts
-1ea duplex outlet on each wall that has doors; 4ea duplex outlets on each of the other two walls
-1ea split unit AC (model PU-2VAKD.TD) connected to each wall outlet on two of the side walls
-2ea laserjet printers @120V 8A
-1ea coffee pot @ 120V 10a
-2ea CPOFs
-10ea laptops, dual voltage
UNCLASSIFIED
UNCLASSIFIED
S2
-8ea florescent lights w/ 1.1A ballasts
-1ea duplex outlet on each wall that has doors; 4ea duplex outlets on the other wall
-2ea split unit Acs (model PU-2VAKD.TD) connected to two wall outlets
-1ea server rack, 120v @13.5A
-6ea laptops, dual voltage
CUOPS
-8ea florescent lights w/ 1.1A ballasts
-1ea duplex outlet on each wall that has doors; 4ea duplex outlets on each of the other three walls
-2ea split unit ACs (model PU-2VAKD.TD) connected to two wall outlets
-2ea CPOFs, dual voltage
-6ea laptops, dual voltage
-1ea radio w/ power amp 120V @ 6.5A
-2ea 60” monitors, dual voltage @ 4A
Conference Room
-6ea florescent lights w/ 1.1A ballasts
-1ea duplex outlet on each wall that has doors; 2ea duplex outlets on each of the other three walls
-2ea split unit ACs (model PU-2VAKD.TD) connected to two wall outlets
-1ea 60” monitors, dual voltage @ 4A
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED
60” TV
Oven and Stove
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED
UNCLASSIFIED

More Related Content

What's hot

Parallel Operation of Transformers
Parallel Operation of TransformersParallel Operation of Transformers
Parallel Operation of TransformersRama Jalamanchili
 
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLC
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLCDESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLC
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLCMohamed Riyasudeen
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training pptShubham Patel
 
Surge arrester and surge suppressor on transformer
Surge arrester and surge suppressor on transformerSurge arrester and surge suppressor on transformer
Surge arrester and surge suppressor on transformerVIKAS KUMAR MANJHI
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation Madeen Kumar
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
power quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcompower quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcom7867867869
 
INTERLEAVED BOOST CONVERTER FOR PV APPLICATION
INTERLEAVED BOOST CONVERTER FOR PV APPLICATIONINTERLEAVED BOOST CONVERTER FOR PV APPLICATION
INTERLEAVED BOOST CONVERTER FOR PV APPLICATIONDr. Bibhu Prasad Ganthia
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
Transformers seminar
Transformers seminarTransformers seminar
Transformers seminarvinayvickky
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNikhil Kachare
 
Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)jawaharramaya
 
Digital energy meter
Digital energy meter Digital energy meter
Digital energy meter preeti naga
 

What's hot (20)

Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Parallel Operation of Transformers
Parallel Operation of TransformersParallel Operation of Transformers
Parallel Operation of Transformers
 
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLC
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLCDESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLC
DESIGN AND IMPLEMENTATION OF AUTOMATIC CHANGE OVER USING PLC
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Substation
Substation Substation
Substation
 
Surge arrester and surge suppressor on transformer
Surge arrester and surge suppressor on transformerSurge arrester and surge suppressor on transformer
Surge arrester and surge suppressor on transformer
 
Power Electronics
Power ElectronicsPower Electronics
Power Electronics
 
Full transformer
Full transformerFull transformer
Full transformer
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
Power Quality
Power QualityPower Quality
Power Quality
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
power quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcompower quality improvement in distrution system using D statcom
power quality improvement in distrution system using D statcom
 
INTERLEAVED BOOST CONVERTER FOR PV APPLICATION
INTERLEAVED BOOST CONVERTER FOR PV APPLICATIONINTERLEAVED BOOST CONVERTER FOR PV APPLICATION
INTERLEAVED BOOST CONVERTER FOR PV APPLICATION
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
Transformers seminar
Transformers seminarTransformers seminar
Transformers seminar
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)
 
Digital energy meter
Digital energy meter Digital energy meter
Digital energy meter
 
Electric Motors
Electric MotorsElectric Motors
Electric Motors
 

Similar to H07 Power Load Survey

H08 Principles of Power Systems Design
H08 Principles of Power Systems Design H08 Principles of Power Systems Design
H08 Principles of Power Systems Design phase3-120A
 
JPE Packet Power, Starline Power and Environmental, jpe slide share
JPE Packet Power, Starline Power and Environmental,  jpe slide shareJPE Packet Power, Starline Power and Environmental,  jpe slide share
JPE Packet Power, Starline Power and Environmental, jpe slide shareEd Hahn
 
premanent emergency light system
premanent emergency light systempremanent emergency light system
premanent emergency light systemrushi1234rap
 
213164961_219958790_218460453.pptx
213164961_219958790_218460453.pptx213164961_219958790_218460453.pptx
213164961_219958790_218460453.pptxEmmanuelMigabo
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manualCyber4Tech
 
New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal KristyDyer
 
Solar rooftop projects primotech
Solar rooftop projects primotechSolar rooftop projects primotech
Solar rooftop projects primotechvimalranaprimotech
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxMohanakumarMP3
 
Minor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelMinor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelDebasis patel
 
Minor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelMinor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelDebasis patel
 
Earthing and disconnecting panel report.pdf
Earthing and disconnecting panel report.pdfEarthing and disconnecting panel report.pdf
Earthing and disconnecting panel report.pdfMohitKumar989420
 
5 Reasons You Need the Latest Generation of iPDU
5 Reasons You Need the Latest Generation of iPDU5 Reasons You Need the Latest Generation of iPDU
5 Reasons You Need the Latest Generation of iPDURaritan
 

Similar to H07 Power Load Survey (20)

H08 Principles of Power Systems Design
H08 Principles of Power Systems Design H08 Principles of Power Systems Design
H08 Principles of Power Systems Design
 
Electrical17OCT
Electrical17OCTElectrical17OCT
Electrical17OCT
 
F04844043
F04844043F04844043
F04844043
 
JPE Packet Power, Starline Power and Environmental, jpe slide share
JPE Packet Power, Starline Power and Environmental,  jpe slide shareJPE Packet Power, Starline Power and Environmental,  jpe slide share
JPE Packet Power, Starline Power and Environmental, jpe slide share
 
premanent emergency light system
premanent emergency light systempremanent emergency light system
premanent emergency light system
 
DESIGN
DESIGNDESIGN
DESIGN
 
213164961_219958790_218460453.pptx
213164961_219958790_218460453.pptx213164961_219958790_218460453.pptx
213164961_219958790_218460453.pptx
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manual
 
LumenCACHE Proposal Print 102916 1332
LumenCACHE Proposal Print 102916 1332LumenCACHE Proposal Print 102916 1332
LumenCACHE Proposal Print 102916 1332
 
New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal New Mexico Statewide Standards for Solar PV and Solar Thermal
New Mexico Statewide Standards for Solar PV and Solar Thermal
 
UDC_Solar-Dc
UDC_Solar-DcUDC_Solar-Dc
UDC_Solar-Dc
 
Solar rooftop projects primotech
Solar rooftop projects primotechSolar rooftop projects primotech
Solar rooftop projects primotech
 
SOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptxSOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptx
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsx
 
Minor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelMinor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patel
 
Minor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patelMinor project ppt by Debasis kumar patel
Minor project ppt by Debasis kumar patel
 
Solar doc
Solar docSolar doc
Solar doc
 
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
 
Earthing and disconnecting panel report.pdf
Earthing and disconnecting panel report.pdfEarthing and disconnecting panel report.pdf
Earthing and disconnecting panel report.pdf
 
5 Reasons You Need the Latest Generation of iPDU
5 Reasons You Need the Latest Generation of iPDU5 Reasons You Need the Latest Generation of iPDU
5 Reasons You Need the Latest Generation of iPDU
 

More from phase3-120A

Power Circuits and Transforers-Unit 6 Labvolt Student Manual
Power Circuits and Transforers-Unit 6 Labvolt Student ManualPower Circuits and Transforers-Unit 6 Labvolt Student Manual
Power Circuits and Transforers-Unit 6 Labvolt Student Manualphase3-120A
 
Power Circuits and Transformers-Unit 4 Labvolt Student Manual
Power Circuits and Transformers-Unit 4 Labvolt Student ManualPower Circuits and Transformers-Unit 4 Labvolt Student Manual
Power Circuits and Transformers-Unit 4 Labvolt Student Manualphase3-120A
 
Power Circuits and Transformers-Unit 2 Labvolt Student Manual
Power Circuits and Transformers-Unit 2 Labvolt Student ManualPower Circuits and Transformers-Unit 2 Labvolt Student Manual
Power Circuits and Transformers-Unit 2 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 9 Labvolt Student Manual
Power Circuits and Transforers-Unit 9 Labvolt Student ManualPower Circuits and Transforers-Unit 9 Labvolt Student Manual
Power Circuits and Transforers-Unit 9 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 8 Labvolt Student Manual
Power Circuits and Transforers-Unit 8 Labvolt Student ManualPower Circuits and Transforers-Unit 8 Labvolt Student Manual
Power Circuits and Transforers-Unit 8 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 7 Labvolt Student Manual
Power Circuits and Transforers-Unit 7 Labvolt Student ManualPower Circuits and Transforers-Unit 7 Labvolt Student Manual
Power Circuits and Transforers-Unit 7 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 5 Labvolt Student Manual
Power Circuits and Transforers-Unit 5 Labvolt Student ManualPower Circuits and Transforers-Unit 5 Labvolt Student Manual
Power Circuits and Transforers-Unit 5 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 1 Labvolt Student Manual
Power Circuits and Transforers-Unit 1 Labvolt Student ManualPower Circuits and Transforers-Unit 1 Labvolt Student Manual
Power Circuits and Transforers-Unit 1 Labvolt Student Manualphase3-120A
 
Power Circuits and Transforers-Unit 3 Labvolt Student Manual
Power Circuits and Transforers-Unit 3 Labvolt Student ManualPower Circuits and Transforers-Unit 3 Labvolt Student Manual
Power Circuits and Transforers-Unit 3 Labvolt Student Manualphase3-120A
 
H21 operational energy
H21 operational energyH21 operational energy
H21 operational energyphase3-120A
 
120A beb PE occupation plans
 120A beb PE occupation plans 120A beb PE occupation plans
120A beb PE occupation plansphase3-120A
 
H33 ac dc motors and generators
H33 ac dc motors and generatorsH33 ac dc motors and generators
H33 ac dc motors and generatorsphase3-120A
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Designphase3-120A
 
Civil 3d surface import
Civil 3d surface importCivil 3d surface import
Civil 3d surface importphase3-120A
 
Career maps for da pam 600 3 update
Career maps for da pam 600 3 updateCareer maps for da pam 600 3 update
Career maps for da pam 600 3 updatephase3-120A
 
Fall 2018 engineer branch newsletter
Fall 2018 engineer branch newsletterFall 2018 engineer branch newsletter
Fall 2018 engineer branch newsletterphase3-120A
 
Act career maps (warrant officer) en-us-120 a
Act career maps (warrant officer) en-us-120 aAct career maps (warrant officer) en-us-120 a
Act career maps (warrant officer) en-us-120 aphase3-120A
 
120A- WOBC H05 Electrical safety day 3
120A- WOBC H05 Electrical safety day 3120A- WOBC H05 Electrical safety day 3
120A- WOBC H05 Electrical safety day 3phase3-120A
 
120A- WOBC H05 Electrical safety day 2
120A- WOBC H05 Electrical safety day 2120A- WOBC H05 Electrical safety day 2
120A- WOBC H05 Electrical safety day 2phase3-120A
 
120A- WOBC H05 Electrical safety day 1
120A- WOBC H05 Electrical safety day 1120A- WOBC H05 Electrical safety day 1
120A- WOBC H05 Electrical safety day 1phase3-120A
 

More from phase3-120A (20)

Power Circuits and Transforers-Unit 6 Labvolt Student Manual
Power Circuits and Transforers-Unit 6 Labvolt Student ManualPower Circuits and Transforers-Unit 6 Labvolt Student Manual
Power Circuits and Transforers-Unit 6 Labvolt Student Manual
 
Power Circuits and Transformers-Unit 4 Labvolt Student Manual
Power Circuits and Transformers-Unit 4 Labvolt Student ManualPower Circuits and Transformers-Unit 4 Labvolt Student Manual
Power Circuits and Transformers-Unit 4 Labvolt Student Manual
 
Power Circuits and Transformers-Unit 2 Labvolt Student Manual
Power Circuits and Transformers-Unit 2 Labvolt Student ManualPower Circuits and Transformers-Unit 2 Labvolt Student Manual
Power Circuits and Transformers-Unit 2 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 9 Labvolt Student Manual
Power Circuits and Transforers-Unit 9 Labvolt Student ManualPower Circuits and Transforers-Unit 9 Labvolt Student Manual
Power Circuits and Transforers-Unit 9 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 8 Labvolt Student Manual
Power Circuits and Transforers-Unit 8 Labvolt Student ManualPower Circuits and Transforers-Unit 8 Labvolt Student Manual
Power Circuits and Transforers-Unit 8 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 7 Labvolt Student Manual
Power Circuits and Transforers-Unit 7 Labvolt Student ManualPower Circuits and Transforers-Unit 7 Labvolt Student Manual
Power Circuits and Transforers-Unit 7 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 5 Labvolt Student Manual
Power Circuits and Transforers-Unit 5 Labvolt Student ManualPower Circuits and Transforers-Unit 5 Labvolt Student Manual
Power Circuits and Transforers-Unit 5 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 1 Labvolt Student Manual
Power Circuits and Transforers-Unit 1 Labvolt Student ManualPower Circuits and Transforers-Unit 1 Labvolt Student Manual
Power Circuits and Transforers-Unit 1 Labvolt Student Manual
 
Power Circuits and Transforers-Unit 3 Labvolt Student Manual
Power Circuits and Transforers-Unit 3 Labvolt Student ManualPower Circuits and Transforers-Unit 3 Labvolt Student Manual
Power Circuits and Transforers-Unit 3 Labvolt Student Manual
 
H21 operational energy
H21 operational energyH21 operational energy
H21 operational energy
 
120A beb PE occupation plans
 120A beb PE occupation plans 120A beb PE occupation plans
120A beb PE occupation plans
 
H33 ac dc motors and generators
H33 ac dc motors and generatorsH33 ac dc motors and generators
H33 ac dc motors and generators
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Design
 
Civil 3d surface import
Civil 3d surface importCivil 3d surface import
Civil 3d surface import
 
Career maps for da pam 600 3 update
Career maps for da pam 600 3 updateCareer maps for da pam 600 3 update
Career maps for da pam 600 3 update
 
Fall 2018 engineer branch newsletter
Fall 2018 engineer branch newsletterFall 2018 engineer branch newsletter
Fall 2018 engineer branch newsletter
 
Act career maps (warrant officer) en-us-120 a
Act career maps (warrant officer) en-us-120 aAct career maps (warrant officer) en-us-120 a
Act career maps (warrant officer) en-us-120 a
 
120A- WOBC H05 Electrical safety day 3
120A- WOBC H05 Electrical safety day 3120A- WOBC H05 Electrical safety day 3
120A- WOBC H05 Electrical safety day 3
 
120A- WOBC H05 Electrical safety day 2
120A- WOBC H05 Electrical safety day 2120A- WOBC H05 Electrical safety day 2
120A- WOBC H05 Electrical safety day 2
 
120A- WOBC H05 Electrical safety day 1
120A- WOBC H05 Electrical safety day 1120A- WOBC H05 Electrical safety day 1
120A- WOBC H05 Electrical safety day 1
 

Recently uploaded

Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...gragchanchal546
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Recently uploaded (20)

Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

H07 Power Load Survey

  • 2. UNCLASSIFIED UNCLASSIFIED ACTION: Perform a power load survey CONDITIONS: Given a classroom an field environment, an understanding of electrical theory, regulatory guidance, and applicable personal protective equipment STANDARD: Perform a load survey applying theory, regulatory guidance, and principles of electrical design.
  • 3. UNCLASSIFIED UNCLASSIFIED • Safety Requirements: None • Risk Assessment Level: Low • Environmental Considerations: None • Evaluation: Students will be evaluated on this block of instruction during the Electrical Systems Design Examination 4. Students must receive a score of 80 percent or above to receive a GO.
  • 4. UNCLASSIFIED UNCLASSIFIED EM385-1-1 NFPA 70 NFPA 70E Safety and Health Requirements NEC 2017 Standard for Electrical Safety in the Workplace
  • 5. UNCLASSIFIED UNCLASSIFIED What is it and what is it used for? 1. It’s an analysis of power requirements, and a vital step in providing electrical power support. The recommended power source is determined based on the load survey. 3. It determines the required level of reliability and identifies any special power demands or problems. A thorough load survey must be completed before installing a power plant or designing a distribution system. 2. Personnel conducting an Infrastructure Recon conduct the load survey to determine the supported power and distribution requirements of a unit.
  • 6. UNCLASSIFIED UNCLASSIFIED Types of load surveys: 1. New Construction 2. Disaster Relief 3. Circuit Upgrade 4. Field Exercises
  • 7. UNCLASSIFIED UNCLASSIFIED Determine Building or Site Load 1. Calculate the loads 2. Generator Sizing -single phase/three phase -prime/standby/continuous -voltage and frequency -altitude and temperature 3. Distribution Equipment and Material Requirements -organic or non-organic -cables, panels, etc 4. Load Balancing 5. Tie in location
  • 8. UNCLASSIFIED UNCLASSIFIED Acquire electrical data -electrical plans -equipment specifications -on site visual inspections Determine the total connected load Calculate the demand load
  • 9. UNCLASSIFIED UNCLASSIFIED 1. General lighting 2. Receptacles 3. Motors 4. Major appliances
  • 10. UNCLASSIFIED UNCLASSIFIED You are currently TCS’d to Camp Arifjan, Kuwait with your local BEB. A mission has come down to deploy your unit to Ramadi, Iraq in order to win the hearts and minds of the local population. During the PDSS, three local buildings have been identified as hard stand structures that will be occupied during this mission. These will be used as a barracks, TOC and DFAC. They already have local electrical panels, wiring and equipment installed in them that will be used, but the local power is very unreliable and will not be used. The BC doesn’t want to install anything new if possible since this will be a short term mission. Organic electrical equipment that will be used in these buildings, along with existing installed local equipment have already been identified during the PDSS. Perform a load assessment of these buildings. How will you power these buildings- what size/type generator and distributions system will you use? Where will it/they be located? Take into account voltage drop and load balancing. Design a system in AutoDISE to accomplish this.
  • 11. UNCLASSIFIED UNCLASSIFIED Kitchen CUOPS Sleeping Area S2 S1/3/4 Conference Room 10m 7m 7m 7m 24m 5m 21m 20m 24m Dining Area10m 7m 200A Panel Box 100A Panel Box Panel Box 60A Panel Box 50m 50m 75m
  • 12. UNCLASSIFIED UNCLASSIFIED Dining Area -50ea florescent lights w/ 1.2A ballasts -10ea duplex outlets on each long wall and 4ea outlets on each short wall -1ea split unit AC (model PU-2.5VAKD.TD) connected to each wall outlet on the long walls Kitchen -18ea florescent lights w/ 1.2A ballasts -3ea ovens and stove combo, each on dedicated circuits -3ea vent hoods each on dedicated circuits; 230V @ 8A -1ea mixer -3ea duplex outlets on each of the side walls -1ea split unit AC (model PU-2.5VAKD.TD) connected to each wall outlet on the side walls -3ea duplex outlets on each of the other two walls
  • 13. UNCLASSIFIED UNCLASSIFIED Sleeping Area -80ea florescent lights w/ 1.1A ballasts -10ea duplex outlets on each wall -1ea split unit AC (model PU-2VAKD.TD) connected to each wall outlet on two of the side walls S1/3/4 -12ea florescent lights w/ 1.1A ballasts -1ea duplex outlet on each wall that has doors; 4ea duplex outlets on each of the other two walls -1ea split unit AC (model PU-2VAKD.TD) connected to each wall outlet on two of the side walls -2ea laserjet printers @120V 8A -1ea coffee pot @ 120V 10a -2ea CPOFs -10ea laptops, dual voltage
  • 14. UNCLASSIFIED UNCLASSIFIED S2 -8ea florescent lights w/ 1.1A ballasts -1ea duplex outlet on each wall that has doors; 4ea duplex outlets on the other wall -2ea split unit Acs (model PU-2VAKD.TD) connected to two wall outlets -1ea server rack, 120v @13.5A -6ea laptops, dual voltage CUOPS -8ea florescent lights w/ 1.1A ballasts -1ea duplex outlet on each wall that has doors; 4ea duplex outlets on each of the other three walls -2ea split unit ACs (model PU-2VAKD.TD) connected to two wall outlets -2ea CPOFs, dual voltage -6ea laptops, dual voltage -1ea radio w/ power amp 120V @ 6.5A -2ea 60” monitors, dual voltage @ 4A Conference Room -6ea florescent lights w/ 1.1A ballasts -1ea duplex outlet on each wall that has doors; 2ea duplex outlets on each of the other three walls -2ea split unit ACs (model PU-2VAKD.TD) connected to two wall outlets -1ea 60” monitors, dual voltage @ 4A