SlideShare a Scribd company logo
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. III (Jan- Feb. 2015), PP 45-50
www.iosrjournals.org
DOI: 10.9790/1684-12134550 www.iosrjournals.org 45 | Page
Implementation of Lean Strategies in a Furniture Manufacturing
Factory
Sudipta Chowdhury1
,Kazi Aminul Haque2
,Musabbirhasan Sumon3
Department Of Industrial and Production Engineering, Shahjalal University of Science and Technology, Sylhet,
Bangladesh.
Abstract:This paper experiments application of different lean strategies to a real production problem at a
furniture manufacturing company. The objective of the study is to improve the productivity of the factory floor.
Initially, existing production process was analyzed to get a clear picture of the existing condition of the process.
It was observed that there were some redundant tasks performed by the workers which resulted in longer
waiting periods. Various lean strategies such as Single-Minute Exchange of Dies (SMED), Gemba (The real
place), and Short Interval Control etc were proposed and implemented on the floor which resulted in significant
improvement in both monetary terms and also in reduction of processing time of different lots. Multifactor
productivity increased from 1.85 to 2.26; average distance travelled by the workers, OEE, wastage of materials
and rejected quantity reduced significantly and an additional production equivalent to more than 1, 48705 taka
per day was made possible.
Keywords:Furniture factory, Lean strategies, Multifactor productivity
I. Introduction
Globalization has forced the furniture companies to increase their production flexibility. The existing
manufacturing scenario in furniture sector demands low quantity and high variety jobs. This type of production
leads to more setup frequency which means a significant increase on total setup times (non-value adding
activity). Due to highly competitive nature of the furniture manufacturing sector, the need to perform fast setup
process and reduce non value adding activity as much as possible has become paramount. Lean manufacturing
can provide a solution to this problem. Lean production aims to systematically identify and eliminate waste
through continuous improvement, enabling increased flexibility and organizations’ competitiveness[1]. Within
the Lean Production system there is a huge range of tools and techniques (e.g. SMED, Gemba and Short interval
control) that can be applied by manufacturing organizations to improve their performance.
Single-Minute Exchange of Die (SMED) refers to the theory and techniques used for the reduction of
equipment setup times. SMED has as its objective to accomplish setup times in less than ten minutes, i.e. a
number of minutes expressed by a single digit. Although not all setups can be literally reduced to this time,
between one and nine minutes, this is the goal of the SMED methodology[2]. The need for SMED and quick
changeover programs is more popular now than ever due to increased demand for product variability, reduced
product life cycles and the need to significantly reduce inventories.Short Interval Control (SIC) can be defined
as a structured process for identifying and acting on opportunities to improve the effectiveness and efficiency of
production. It can be thought of a kaizen process as it encourages teams to work together to achieve
improvements in the manufacturing process. Gemba is the process of making observations of the process in
action. It emphasizes on taking the managers or the people in charge to the real place where the action is
happening.
The effect of these three lean tools namely SMED, Gemba and Short interval control is observed and
analyzed on a leading furniture manufacturing factory in Bangladesh. This factory produces a wide variety of
products ranging from metal based furniture to various wood and board based furniture. It has 45 machines of
various kinds on the home furniture factory floor. This company makes over 300 models of home furniture (bed,
sofa, mini cabinet, dining table, showcase etc) alone and due to this huge variety this company was facing
problems in fulfilling the demand of the market.So a project was undertaken to implement lean strategies on the
home furniture factory floor to reduce non-value adding times as much as possible and increase the productivity
of the factory.
II. Literature Review
SMED, also known as Quick change over of tools was developed by Shingo [2], who characterized it
as a scientific approach for the reduction of setup times, and which can be applied to any industrial unit or
machine. It reduces the non-productive time by streamlining and standardizing the operations for exchange
tools, using simple techniques and easy applications[3]. Quick setup time ensures that the flexibility of the
response to the demand is adequate, as small batch production results in a significant increase in the setup
Implementation Of Lean Strategies In A Furniture Manufacturing Factory
DOI: 10.9790/1684-12134550 www.iosrjournals.org 46 | Page
frequency [4]. Gourbergen and Landeghem (2002) classify the different reasons for reducing setup times into
three main groups namely flexibility, bottleneck capacity and costs minimization [5].Shingo (1985) showed that
SMED consists of three conceptual stages namely separating internal and external setup, converting the internal
setup to external setup and streamlining all aspects of the setup operation [2]. Cakmakci(2008) concluded that
SMED is suitable not only for manufacturing improvement but also for equipment development[6]. Trovinger
and Bohn(2005) applied the principles of SMED to pick and place chip shooter machines and they were able to
reduce setup times by removing all activities that could be done online[7]. Michels(2007) applied the SMED
methodology to the punch press changeover and the researcher concluded that SMED is an effective tool to
provide improved changeover methods resulting in reduction in overall time and labor[8].Alves and
Tenera(2009) concluded that SMED methodology can be combined with other classic tools, providing very
positive results for companies [3].
Barraza et al (2012) used Gemba-Kaizen approach to develop a conceptual framework in a
multinational food company [9]. However, to the best knowledge of the authors no research work has been
found where SMED, Gemba and short interval control; these three lean strategies are used simultaneously to
improve the condition of the factory floor.
III. Research Methodology
In order to achieve the original goal proposed in the first section, it was decided that a case study would
be conducted based on a qualitative approach. This case study primarily consisted of eight steps which are
shown in figure 1.
Figure 1: Steps of the research
3.1 Industrial application
The first step involved a review of the literature and the selection of the target furniture manufacturing
firm. The second step involved the definition of the goals to be achieved at the firm through the implementation
of lean strategies. After that, an initial observation was made which made it possible to identify various
problems that affected the efficiency and productivity of the process. Thus the main problems registered were
high setup times, high quantity of work in process inventory, unnecessary movements made by the workers, lack
of supervision, lack of space in the factory floor and so forth. Operators of each machine were interviewed to get
their view on the problems of the factory floor. Then the whole factory floor was video recorded for a period of
one month to register all operations and movements of the workers. After that, sequence diagram and spaghetti
chart was constructed to describe each and every setup operation, the distance travelled by the workers, the
movements made by the workers(mainly machine operators) during the setup process and to identify areas
which needed improvement. It should be noted that steps from one to six from figure 1can be considered as the
preliminary stage of the project. However, it was decided to make this distinction to better illustrate the
sequence of steps used in this project to implement lean strategies. After the preliminary stage, SMED was the
first lean tool applied on the factory floor. At stage one of SMED implementation, a clear separation was made
between external and internal activities. It was realized during this period that all setup related operations were
Implementation Of Lean Strategies In A Furniture Manufacturing Factory
DOI: 10.9790/1684-12134550 www.iosrjournals.org 47 | Page
executed as internal setup, since they were performed with the machine stopped. Table 1 shows the list of
internal and external activities performed before SMED implementation.
Table 1: Internal and external activities during setup before SMED implementation
Internal activities External activities
Setting different cutting tools on the machine -
Removing different cutting tools from the machine. -
Bringing cutting tools from the tool store -
Returning cutting tools to the tool store -
Cleaning the machine with pneumatic air hose -
Lubricating the machine -
Making adjustments on the machine based on cutting measurements -
The techniques used for making this distinction was made by various techniques such as creation of a
checklist which was used to indicate the information essential for the setup execution and the planning of the
transportation of tools.In stage two of SMED implementation,some internal activities were converted into
external activities. Table 2 shows this list after SMED implementation.
Table 2: Internal and external activities during setup after SMED implementation
Internal activities External activities
Setting different cutting tools on the machine Bringing cutting tools from the tool store
Removing different cutting tools from the machine. Returning cutting tools to the tool store
Making adjustments on the machine based on cutting measurements Cleaning the machine with pneumatic air hose
- Lubricating the machine
Before, cleaning of the machine was done after a complete lot was processed. Now, the operators and
helpers of the machines were given instruction to do the cleaning while the machine was running. The same was
done for lubrication purpose. Another very time consuming task was bringing from and returning cutting tools
to the cutter store for each lot. For bigger lots, workers had to go to cutter store multiple times for changing or
sharpening the tools. Two additional helpers were assigned for every 15 machines and the workers no longer
needed to make trips to the cutter store. Whenever the new tools were needed, it was made available beforehand.
Standard setup procedures were also prepared and documented for each machine during this step.
For the improvement of supervision on the factory floor, a combined strategy of Gemba and short interval
control was proposed. OEE (overall equipment effectiveness), Downtime minutes, total reject quantity and
slower production rate by the workers were identified as the loss metrics. A supervision team was formed and
trained to take necessary steps to eliminate this loss metrics. The guidelines provided for the supervision are:
1. Line supervisors have to document each lot on each machine being processed with part name, part quantity,
starting time and finishing time on machine.
2. Shift in charges will collect report from line supervisors on every two hours and will make a call on
whether each machine operator is performing efficiently or not and visit the machine.
3. Shift in charge will visit the floor on at least every 40 minutes on a rotational basis and visit as many
machines as possible.
4. Each week there will be a periodic review of workers performances.
IV. Analysis And Discussion Of Results
4.1 SMED implementation
Table 3 shows the analysis of average setup time taken on each type of machine operating on the factory floor.
Table 3: Average time spent during setup on machines
Name of machine Time to remove tool
from machine(minutes)
Time to insert tool on
the machine(minutes)
Time taken on tool
adjustment(minutes)
Time taken to go and
return from tool
store(minutes)
Surface planer 5 7 3 5
Thickness planer 6 8 4 5
Mortising 3 3 8 5
Stand drill 2 2 6 5
Multi boring 3 8 8 5
Panel saw 4 4 6 5
DET 3 6 5 5
Stand router 2 5 3 5
Small router 2 5 2 5
Tenoner 5 6 10 5
Circular saw 3 5 7 5
Wide belt sander 5 8 6 5
Disc sander 4 9 2 5
Implementation Of Lean Strategies In A Furniture Manufacturing Factory
DOI: 10.9790/1684-12134550 www.iosrjournals.org 48 | Page
Block sander 4 9 2 5
Moulder 3 3 4 5
Jig saw 3 4 8 5
Band saw 3 4 5 5
Radial arm saw 4 7 4 5
Among those machines, cutting tool of surface planer, thickness planer, panel saw, DET, wide belt sander, disc
sander and block sander does not need changing for each successive lot. In case of these machines, every three
to four lots needs tool change; otherwise only tool adjustment time was needed. After SMED methodology was
applied in the machines, the results showed a significant improvement in time taken during setup which is
showed in table 4.
Table 4: Average time spent during setup on machines (after SMED implementation)
Another improvement attained was the reduction of operators’ movement during the setup process. Table 5
represents the results obtained for the distance travelled by the operators.
Table 5: Improvements obtained in average distance travelled
Preliminary stage(m) After SMED(m) Improvement (%)
35.9 14.7 59
Figure 2 represents the spaghetti chart to demonstrate the difference between operators’ movement before and
after SMED implementation.
Figure 2: workers movement during the setup (before and after) for one line.
It is evident from the chart that non value adding activities such as getting cutting tool from the store,
sharpening the tool etc are now performed during the external setup by additional helper.
It had been observed that for each lot processed in any machine, there was at least two setup times. On
average each machine had five lots processed in 16 hour period. Before SMED implementation average
machine setup time was 19.44 minute, and after SMED implementation this time reduced down to 11.47 minute.
So a total of 7.97 minute was saved for processing each lot. If surface planer, thickness planer, panel saw, DET,
wide belt sander, disc sander and block sander machines which needed fewer setups were excluded from the list,
there were 31 machines in total. So for 31 machines total machine hour saved was 31*10*7.97 minutes or 41.18
hours. If 45 machines run for 16 hours and produce products equivalent to 26,00000 Taka per day, then extra
Implementation Of Lean Strategies In A Furniture Manufacturing Factory
DOI: 10.9790/1684-12134550 www.iosrjournals.org 49 | Page
machine hour of at least 41.18 hours would bring the firm additional 148705 Taka per day. From the calculation
after SMED implementation, it was found that on average the daily production increased to almost 27, 59420
Taka per day.
1.2 Impact of GEMBA and Short interval control
Before the implementation of GEMBA and short interval control on the factory floor; OEE, total
downtime minutes, reject quantity and wastage of materials were calculated and analyzed for a two month
period. Mean time between failures(MTBF) was also calculated. Afterwards the supervision team started
conducting short meetings (8-10 minutes) on every two and a half hours discussing the condition of above three
loss metrics as well as solving them and following the general guidelines provided to them. This enabled them
to have an instant grasp of the existing condition of the factory floor. After two months, this showed an
impressive improvementwhich is showed in table 6.
Table 6: Improvements in OEE, total downtime minutes, reject quantity and wastage of materials
1.3 Improvement in productivity
Before implementation of SMED, Gemba and short interval control methodologies on the factory floor,
labor and material productivity was 3.19 and 4.35(calculated over a two month period). After implementing the
above mentioned lean strategies, labor and material productivity increased to 4.76 and 4.42; resulting in a higher
multifactor productivity of 2.26. Figure 3 depicts this improvement.
Figure 3: Labor, material and multifactor productivity
Labor productivity increased substantially due to increased supervision and reduction of setup times
through the implementation of SMED technique. Slight increase in material productivity was also due to
increased supervision which resulted in lower reject quantity and lower wastage of materials.
V. Conclusion
This study clearly shows that lean strategies such as SMED, Gemba and short interval control can be
effectively applied to improve the condition of a furniture manufacturing company. The main results achieved
were improvements in setup times of different machines on the factory floor, 59% improvement in the average
distance travelled by the workers resulting in an additional 148705 Taka per day. 12%,40%,14%,32%
improvement respectively was achieved in OEE, total downtime minutes, reject quantity and wastage of
materials. Both labor and material productivity increased resulting in a higher multifactor productivity of 2.26. It
was realized through this study that lean strategies can successfully be implemented in furniture manufacturing
industry.
References
[1]. J Womack, D Jones , Lean thinking: banish waste and create wealth in your corporation (Free press,1996).
[2]. S Shingo, A revolution in Manufacturing: the SMED System. Productivity Press(Cambridge, MA; 1985)
[3]. Ana Sofia Alves and Alexandra Tenera, Improving SMED in the Automotive Industry: A case study, Production and Operations
Management Society 20th
Annual conference Orlando,Florida US; 2009
[4]. R Mcintosh, G Owen, S Culley and T Mileham, Changeover improvement: reinterpreting Shingo’s “SMED” methodology, IEE
Transactions on Engineering Management, 2007, 54, p.98-111
[5]. D Goubergen, H Landeghem, Rules for integrating fast changeover capabilities into new equipment design, Robotics and Computer
Integrated Manufacturing, 2002,18, p.205-214
[6]. M Cakmacki, Process Improvement: Performance analysis of the setup time reduction-SMED in the automobile industry,
International Journal of Advanced Manufacturing Technology, 2009,41, p. 168-179
Implementation Of Lean Strategies In A Furniture Manufacturing Factory
DOI: 10.9790/1684-12134550 www.iosrjournals.org 50 | Page
[7]. Trovinger and Bohn, Setup time reduction for Electronics assembly: Combining simple SMED and IT based methods, Production
and Operations Management Society, 2005, 14(2), ISSN 1059-1478
[8]. T.B Michels, Application of Shingo’s Single Minute Exchange Of Dies(SMED) Methodology to reduce Punch Press Changeover
Times at Krueger International, Thesis, University of Wisconsin-Stout, 2007.
[9]. Manuel F. Suárez‐Barraza, Juan Ramis‐Pujol, Mariana Estrada‐Robles, Applying Gemba‐Kaizen in a multinational food company:
a process innovation framework, International Journal of Quality and Service Sciences, 2012, Vol. 4 Issue: 1, p.27 – 50.

More Related Content

What's hot

Jit ppt with case study
Jit ppt with case studyJit ppt with case study
Jit ppt with case study
omkar jagtap
 
Case Study: Mass Production in Small Scale Industries
Case Study: Mass Production in Small Scale IndustriesCase Study: Mass Production in Small Scale Industries
Case Study: Mass Production in Small Scale Industries
paperpublications3
 
types of production system
types of production systemtypes of production system
types of production system
ram4181
 
Definition of production and operation management
Definition of production and operation managementDefinition of production and operation management
Definition of production and operation management
Yamini Kahaliya
 
Process Planning
Process PlanningProcess Planning
Process Planning
Guhan M
 
Group Technology
Group TechnologyGroup Technology
Group Technology
sgrsoni45
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
omkar jagtap
 
Process planning (lesson 1)
Process planning (lesson 1)Process planning (lesson 1)
Process planning (lesson 1)
Hari Vignesh R
 
Manufacturing and Service Technologies
Manufacturing and Service TechnologiesManufacturing and Service Technologies
Manufacturing and Service Technologies
samer dofash
 
Zis layout
Zis  layoutZis  layout
Zis layout
zuha handoo
 
Facility & Layout Design Case Study
Facility & Layout Design Case StudyFacility & Layout Design Case Study
Facility & Layout Design Case Study
Nilam Kabra
 
Site selection and plant layout
Site selection and plant layoutSite selection and plant layout
Site selection and plant layout
Ratnadeepsinh Jadeja
 
Om
OmOm
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
Asha A
 
Types of production processes
Types of production processesTypes of production processes
Types of production processes
Anupam Kumar
 
Application of industrial engineering techniques in garments production
Application of industrial engineering techniques      in garments productionApplication of industrial engineering techniques      in garments production
Application of industrial engineering techniques in garments production
Md.Abdur Rahim Al Bahar
 

What's hot (17)

Jit ppt with case study
Jit ppt with case studyJit ppt with case study
Jit ppt with case study
 
Case Study: Mass Production in Small Scale Industries
Case Study: Mass Production in Small Scale IndustriesCase Study: Mass Production in Small Scale Industries
Case Study: Mass Production in Small Scale Industries
 
types of production system
types of production systemtypes of production system
types of production system
 
Definition of production and operation management
Definition of production and operation managementDefinition of production and operation management
Definition of production and operation management
 
Process Planning
Process PlanningProcess Planning
Process Planning
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
 
Process planning (lesson 1)
Process planning (lesson 1)Process planning (lesson 1)
Process planning (lesson 1)
 
Manufacturing and Service Technologies
Manufacturing and Service TechnologiesManufacturing and Service Technologies
Manufacturing and Service Technologies
 
Zis layout
Zis  layoutZis  layout
Zis layout
 
Facility & Layout Design Case Study
Facility & Layout Design Case StudyFacility & Layout Design Case Study
Facility & Layout Design Case Study
 
Site selection and plant layout
Site selection and plant layoutSite selection and plant layout
Site selection and plant layout
 
Om
OmOm
Om
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Types of production processes
Types of production processesTypes of production processes
Types of production processes
 
Application of industrial engineering techniques in garments production
Application of industrial engineering techniques      in garments productionApplication of industrial engineering techniques      in garments production
Application of industrial engineering techniques in garments production
 

Viewers also liked

B012410616
B012410616B012410616
B012410616
IOSR Journals
 
E017332733
E017332733E017332733
E017332733
IOSR Journals
 
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
IOSR Journals
 
F0552935
F0552935F0552935
F0552935
IOSR Journals
 
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
IOSR Journals
 
E010433640
E010433640E010433640
E010433640
IOSR Journals
 
Issues and Challenges in Distributed Sensor Networks- A Review
Issues and Challenges in Distributed Sensor Networks- A ReviewIssues and Challenges in Distributed Sensor Networks- A Review
Issues and Challenges in Distributed Sensor Networks- A Review
IOSR Journals
 
B017622430
B017622430B017622430
B017622430
IOSR Journals
 
Challenging Issues and Similarity Measures for Web Document Clustering
Challenging Issues and Similarity Measures for Web Document ClusteringChallenging Issues and Similarity Measures for Web Document Clustering
Challenging Issues and Similarity Measures for Web Document Clustering
IOSR Journals
 
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver DiseaseCore Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
IOSR Journals
 
B017660813
B017660813B017660813
B017660813
IOSR Journals
 
I012664954
I012664954I012664954
I012664954
IOSR Journals
 
I013165359
I013165359I013165359
I013165359
IOSR Journals
 
M1303017681
M1303017681M1303017681
M1303017681
IOSR Journals
 
K1303077376
K1303077376K1303077376
K1303077376
IOSR Journals
 
B012450408
B012450408B012450408
B012450408
IOSR Journals
 
A1302040105
A1302040105A1302040105
A1302040105
IOSR Journals
 
B010611115
B010611115B010611115
B010611115
IOSR Journals
 
K018117479
K018117479K018117479
K018117479
IOSR Journals
 
J012127176
J012127176J012127176
J012127176
IOSR Journals
 

Viewers also liked (20)

B012410616
B012410616B012410616
B012410616
 
E017332733
E017332733E017332733
E017332733
 
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
 
F0552935
F0552935F0552935
F0552935
 
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
Crack Detection for Various Loading Conditions in Beam Using Hilbert – Huang ...
 
E010433640
E010433640E010433640
E010433640
 
Issues and Challenges in Distributed Sensor Networks- A Review
Issues and Challenges in Distributed Sensor Networks- A ReviewIssues and Challenges in Distributed Sensor Networks- A Review
Issues and Challenges in Distributed Sensor Networks- A Review
 
B017622430
B017622430B017622430
B017622430
 
Challenging Issues and Similarity Measures for Web Document Clustering
Challenging Issues and Similarity Measures for Web Document ClusteringChallenging Issues and Similarity Measures for Web Document Clustering
Challenging Issues and Similarity Measures for Web Document Clustering
 
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver DiseaseCore Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
 
B017660813
B017660813B017660813
B017660813
 
I012664954
I012664954I012664954
I012664954
 
I013165359
I013165359I013165359
I013165359
 
M1303017681
M1303017681M1303017681
M1303017681
 
K1303077376
K1303077376K1303077376
K1303077376
 
B012450408
B012450408B012450408
B012450408
 
A1302040105
A1302040105A1302040105
A1302040105
 
B010611115
B010611115B010611115
B010611115
 
K018117479
K018117479K018117479
K018117479
 
J012127176
J012127176J012127176
J012127176
 

Similar to H012134550

Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
IRJET Journal
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET Journal
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET Journal
 
Guidelines industrial engineering
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineering
Syed Jafri
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
IRJET Journal
 
Group technolog1 assegment
Group technolog1 assegmentGroup technolog1 assegment
Group technolog1 assegment
Said Yakubu Issahaku
 
Lecture 1 and 2
Lecture 1 and 2Lecture 1 and 2
Lecture 1 and 2
Serajul Haque
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
ijsrd.com
 
A036501014
A036501014A036501014
A036501014
theijes
 
Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docx
adkinspaige22
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IRJET Journal
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in Foundries
IJMER
 
I012536474
I012536474I012536474
I012536474
IOSR Journals
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET Journal
 
Implementating just in-time production and procurement strategies
Implementating just in-time production and procurement  strategiesImplementating just in-time production and procurement  strategies
Implementating just in-time production and procurement strategies
Ajay Yadav
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
eSAT Publishing House
 
(a) (i) Re-organising the existing facility is an expensive exercise.pdf
(a) (i) Re-organising the existing facility is an expensive exercise.pdf(a) (i) Re-organising the existing facility is an expensive exercise.pdf
(a) (i) Re-organising the existing facility is an expensive exercise.pdf
arhamgarmentsdelhi
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
IRJET Journal
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
meijjournal
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methods
eSAT Journals
 

Similar to H012134550 (20)

Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
Guidelines industrial engineering
Guidelines industrial engineeringGuidelines industrial engineering
Guidelines industrial engineering
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
Group technolog1 assegment
Group technolog1 assegmentGroup technolog1 assegment
Group technolog1 assegment
 
Lecture 1 and 2
Lecture 1 and 2Lecture 1 and 2
Lecture 1 and 2
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
A036501014
A036501014A036501014
A036501014
 
Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docx
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in Foundries
 
I012536474
I012536474I012536474
I012536474
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
Implementating just in-time production and procurement strategies
Implementating just in-time production and procurement  strategiesImplementating just in-time production and procurement  strategies
Implementating just in-time production and procurement strategies
 
5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload5 s implementation and its effect on physical workload
5 s implementation and its effect on physical workload
 
(a) (i) Re-organising the existing facility is an expensive exercise.pdf
(a) (i) Re-organising the existing facility is an expensive exercise.pdf(a) (i) Re-organising the existing facility is an expensive exercise.pdf
(a) (i) Re-organising the existing facility is an expensive exercise.pdf
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methods
 

More from IOSR Journals

A011140104
A011140104A011140104
A011140104
IOSR Journals
 
M0111397100
M0111397100M0111397100
M0111397100
IOSR Journals
 
L011138596
L011138596L011138596
L011138596
IOSR Journals
 
K011138084
K011138084K011138084
K011138084
IOSR Journals
 
J011137479
J011137479J011137479
J011137479
IOSR Journals
 
I011136673
I011136673I011136673
I011136673
IOSR Journals
 
G011134454
G011134454G011134454
G011134454
IOSR Journals
 
H011135565
H011135565H011135565
H011135565
IOSR Journals
 
F011134043
F011134043F011134043
F011134043
IOSR Journals
 
E011133639
E011133639E011133639
E011133639
IOSR Journals
 
D011132635
D011132635D011132635
D011132635
IOSR Journals
 
C011131925
C011131925C011131925
C011131925
IOSR Journals
 
B011130918
B011130918B011130918
B011130918
IOSR Journals
 
A011130108
A011130108A011130108
A011130108
IOSR Journals
 
I011125160
I011125160I011125160
I011125160
IOSR Journals
 
H011124050
H011124050H011124050
H011124050
IOSR Journals
 
G011123539
G011123539G011123539
G011123539
IOSR Journals
 
F011123134
F011123134F011123134
F011123134
IOSR Journals
 
E011122530
E011122530E011122530
E011122530
IOSR Journals
 
D011121524
D011121524D011121524
D011121524
IOSR Journals
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
Alex Pruden
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
ScyllaDB
 
Y-Combinator seed pitch deck template PP
Y-Combinator seed pitch deck template PPY-Combinator seed pitch deck template PP
Y-Combinator seed pitch deck template PP
c5vrf27qcz
 
"Choosing proper type of scaling", Olena Syrota
"Choosing proper type of scaling", Olena Syrota"Choosing proper type of scaling", Olena Syrota
"Choosing proper type of scaling", Olena Syrota
Fwdays
 
What is an RPA CoE? Session 1 – CoE Vision
What is an RPA CoE?  Session 1 – CoE VisionWhat is an RPA CoE?  Session 1 – CoE Vision
What is an RPA CoE? Session 1 – CoE Vision
DianaGray10
 
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
Edge AI and Vision Alliance
 
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
Fwdays
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
Tatiana Kojar
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
Hiroshi SHIBATA
 
Essentials of Automations: Exploring Attributes & Automation Parameters
Essentials of Automations: Exploring Attributes & Automation ParametersEssentials of Automations: Exploring Attributes & Automation Parameters
Essentials of Automations: Exploring Attributes & Automation Parameters
Safe Software
 
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
Pitangent Analytics & Technology Solutions Pvt. Ltd
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Precisely
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Alpen-Adria-Universität
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
panagenda
 
Leveraging the Graph for Clinical Trials and Standards
Leveraging the Graph for Clinical Trials and StandardsLeveraging the Graph for Clinical Trials and Standards
Leveraging the Graph for Clinical Trials and Standards
Neo4j
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
saastr
 
JavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green MasterplanJavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green Masterplan
Miro Wengner
 

Recently uploaded (20)

zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
zkStudyClub - LatticeFold: A Lattice-based Folding Scheme and its Application...
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
 
Y-Combinator seed pitch deck template PP
Y-Combinator seed pitch deck template PPY-Combinator seed pitch deck template PP
Y-Combinator seed pitch deck template PP
 
"Choosing proper type of scaling", Olena Syrota
"Choosing proper type of scaling", Olena Syrota"Choosing proper type of scaling", Olena Syrota
"Choosing proper type of scaling", Olena Syrota
 
What is an RPA CoE? Session 1 – CoE Vision
What is an RPA CoE?  Session 1 – CoE VisionWhat is an RPA CoE?  Session 1 – CoE Vision
What is an RPA CoE? Session 1 – CoE Vision
 
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
“How Axelera AI Uses Digital Compute-in-memory to Deliver Fast and Energy-eff...
 
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk"Frontline Battles with DDoS: Best practices and Lessons Learned",  Igor Ivaniuk
"Frontline Battles with DDoS: Best practices and Lessons Learned", Igor Ivaniuk
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
 
Essentials of Automations: Exploring Attributes & Automation Parameters
Essentials of Automations: Exploring Attributes & Automation ParametersEssentials of Automations: Exploring Attributes & Automation Parameters
Essentials of Automations: Exploring Attributes & Automation Parameters
 
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
Crafting Excellence: A Comprehensive Guide to iOS Mobile App Development Serv...
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
 
Leveraging the Graph for Clinical Trials and Standards
Leveraging the Graph for Clinical Trials and StandardsLeveraging the Graph for Clinical Trials and Standards
Leveraging the Graph for Clinical Trials and Standards
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
 
JavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green MasterplanJavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green Masterplan
 

H012134550

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. III (Jan- Feb. 2015), PP 45-50 www.iosrjournals.org DOI: 10.9790/1684-12134550 www.iosrjournals.org 45 | Page Implementation of Lean Strategies in a Furniture Manufacturing Factory Sudipta Chowdhury1 ,Kazi Aminul Haque2 ,Musabbirhasan Sumon3 Department Of Industrial and Production Engineering, Shahjalal University of Science and Technology, Sylhet, Bangladesh. Abstract:This paper experiments application of different lean strategies to a real production problem at a furniture manufacturing company. The objective of the study is to improve the productivity of the factory floor. Initially, existing production process was analyzed to get a clear picture of the existing condition of the process. It was observed that there were some redundant tasks performed by the workers which resulted in longer waiting periods. Various lean strategies such as Single-Minute Exchange of Dies (SMED), Gemba (The real place), and Short Interval Control etc were proposed and implemented on the floor which resulted in significant improvement in both monetary terms and also in reduction of processing time of different lots. Multifactor productivity increased from 1.85 to 2.26; average distance travelled by the workers, OEE, wastage of materials and rejected quantity reduced significantly and an additional production equivalent to more than 1, 48705 taka per day was made possible. Keywords:Furniture factory, Lean strategies, Multifactor productivity I. Introduction Globalization has forced the furniture companies to increase their production flexibility. The existing manufacturing scenario in furniture sector demands low quantity and high variety jobs. This type of production leads to more setup frequency which means a significant increase on total setup times (non-value adding activity). Due to highly competitive nature of the furniture manufacturing sector, the need to perform fast setup process and reduce non value adding activity as much as possible has become paramount. Lean manufacturing can provide a solution to this problem. Lean production aims to systematically identify and eliminate waste through continuous improvement, enabling increased flexibility and organizations’ competitiveness[1]. Within the Lean Production system there is a huge range of tools and techniques (e.g. SMED, Gemba and Short interval control) that can be applied by manufacturing organizations to improve their performance. Single-Minute Exchange of Die (SMED) refers to the theory and techniques used for the reduction of equipment setup times. SMED has as its objective to accomplish setup times in less than ten minutes, i.e. a number of minutes expressed by a single digit. Although not all setups can be literally reduced to this time, between one and nine minutes, this is the goal of the SMED methodology[2]. The need for SMED and quick changeover programs is more popular now than ever due to increased demand for product variability, reduced product life cycles and the need to significantly reduce inventories.Short Interval Control (SIC) can be defined as a structured process for identifying and acting on opportunities to improve the effectiveness and efficiency of production. It can be thought of a kaizen process as it encourages teams to work together to achieve improvements in the manufacturing process. Gemba is the process of making observations of the process in action. It emphasizes on taking the managers or the people in charge to the real place where the action is happening. The effect of these three lean tools namely SMED, Gemba and Short interval control is observed and analyzed on a leading furniture manufacturing factory in Bangladesh. This factory produces a wide variety of products ranging from metal based furniture to various wood and board based furniture. It has 45 machines of various kinds on the home furniture factory floor. This company makes over 300 models of home furniture (bed, sofa, mini cabinet, dining table, showcase etc) alone and due to this huge variety this company was facing problems in fulfilling the demand of the market.So a project was undertaken to implement lean strategies on the home furniture factory floor to reduce non-value adding times as much as possible and increase the productivity of the factory. II. Literature Review SMED, also known as Quick change over of tools was developed by Shingo [2], who characterized it as a scientific approach for the reduction of setup times, and which can be applied to any industrial unit or machine. It reduces the non-productive time by streamlining and standardizing the operations for exchange tools, using simple techniques and easy applications[3]. Quick setup time ensures that the flexibility of the response to the demand is adequate, as small batch production results in a significant increase in the setup
  • 2. Implementation Of Lean Strategies In A Furniture Manufacturing Factory DOI: 10.9790/1684-12134550 www.iosrjournals.org 46 | Page frequency [4]. Gourbergen and Landeghem (2002) classify the different reasons for reducing setup times into three main groups namely flexibility, bottleneck capacity and costs minimization [5].Shingo (1985) showed that SMED consists of three conceptual stages namely separating internal and external setup, converting the internal setup to external setup and streamlining all aspects of the setup operation [2]. Cakmakci(2008) concluded that SMED is suitable not only for manufacturing improvement but also for equipment development[6]. Trovinger and Bohn(2005) applied the principles of SMED to pick and place chip shooter machines and they were able to reduce setup times by removing all activities that could be done online[7]. Michels(2007) applied the SMED methodology to the punch press changeover and the researcher concluded that SMED is an effective tool to provide improved changeover methods resulting in reduction in overall time and labor[8].Alves and Tenera(2009) concluded that SMED methodology can be combined with other classic tools, providing very positive results for companies [3]. Barraza et al (2012) used Gemba-Kaizen approach to develop a conceptual framework in a multinational food company [9]. However, to the best knowledge of the authors no research work has been found where SMED, Gemba and short interval control; these three lean strategies are used simultaneously to improve the condition of the factory floor. III. Research Methodology In order to achieve the original goal proposed in the first section, it was decided that a case study would be conducted based on a qualitative approach. This case study primarily consisted of eight steps which are shown in figure 1. Figure 1: Steps of the research 3.1 Industrial application The first step involved a review of the literature and the selection of the target furniture manufacturing firm. The second step involved the definition of the goals to be achieved at the firm through the implementation of lean strategies. After that, an initial observation was made which made it possible to identify various problems that affected the efficiency and productivity of the process. Thus the main problems registered were high setup times, high quantity of work in process inventory, unnecessary movements made by the workers, lack of supervision, lack of space in the factory floor and so forth. Operators of each machine were interviewed to get their view on the problems of the factory floor. Then the whole factory floor was video recorded for a period of one month to register all operations and movements of the workers. After that, sequence diagram and spaghetti chart was constructed to describe each and every setup operation, the distance travelled by the workers, the movements made by the workers(mainly machine operators) during the setup process and to identify areas which needed improvement. It should be noted that steps from one to six from figure 1can be considered as the preliminary stage of the project. However, it was decided to make this distinction to better illustrate the sequence of steps used in this project to implement lean strategies. After the preliminary stage, SMED was the first lean tool applied on the factory floor. At stage one of SMED implementation, a clear separation was made between external and internal activities. It was realized during this period that all setup related operations were
  • 3. Implementation Of Lean Strategies In A Furniture Manufacturing Factory DOI: 10.9790/1684-12134550 www.iosrjournals.org 47 | Page executed as internal setup, since they were performed with the machine stopped. Table 1 shows the list of internal and external activities performed before SMED implementation. Table 1: Internal and external activities during setup before SMED implementation Internal activities External activities Setting different cutting tools on the machine - Removing different cutting tools from the machine. - Bringing cutting tools from the tool store - Returning cutting tools to the tool store - Cleaning the machine with pneumatic air hose - Lubricating the machine - Making adjustments on the machine based on cutting measurements - The techniques used for making this distinction was made by various techniques such as creation of a checklist which was used to indicate the information essential for the setup execution and the planning of the transportation of tools.In stage two of SMED implementation,some internal activities were converted into external activities. Table 2 shows this list after SMED implementation. Table 2: Internal and external activities during setup after SMED implementation Internal activities External activities Setting different cutting tools on the machine Bringing cutting tools from the tool store Removing different cutting tools from the machine. Returning cutting tools to the tool store Making adjustments on the machine based on cutting measurements Cleaning the machine with pneumatic air hose - Lubricating the machine Before, cleaning of the machine was done after a complete lot was processed. Now, the operators and helpers of the machines were given instruction to do the cleaning while the machine was running. The same was done for lubrication purpose. Another very time consuming task was bringing from and returning cutting tools to the cutter store for each lot. For bigger lots, workers had to go to cutter store multiple times for changing or sharpening the tools. Two additional helpers were assigned for every 15 machines and the workers no longer needed to make trips to the cutter store. Whenever the new tools were needed, it was made available beforehand. Standard setup procedures were also prepared and documented for each machine during this step. For the improvement of supervision on the factory floor, a combined strategy of Gemba and short interval control was proposed. OEE (overall equipment effectiveness), Downtime minutes, total reject quantity and slower production rate by the workers were identified as the loss metrics. A supervision team was formed and trained to take necessary steps to eliminate this loss metrics. The guidelines provided for the supervision are: 1. Line supervisors have to document each lot on each machine being processed with part name, part quantity, starting time and finishing time on machine. 2. Shift in charges will collect report from line supervisors on every two hours and will make a call on whether each machine operator is performing efficiently or not and visit the machine. 3. Shift in charge will visit the floor on at least every 40 minutes on a rotational basis and visit as many machines as possible. 4. Each week there will be a periodic review of workers performances. IV. Analysis And Discussion Of Results 4.1 SMED implementation Table 3 shows the analysis of average setup time taken on each type of machine operating on the factory floor. Table 3: Average time spent during setup on machines Name of machine Time to remove tool from machine(minutes) Time to insert tool on the machine(minutes) Time taken on tool adjustment(minutes) Time taken to go and return from tool store(minutes) Surface planer 5 7 3 5 Thickness planer 6 8 4 5 Mortising 3 3 8 5 Stand drill 2 2 6 5 Multi boring 3 8 8 5 Panel saw 4 4 6 5 DET 3 6 5 5 Stand router 2 5 3 5 Small router 2 5 2 5 Tenoner 5 6 10 5 Circular saw 3 5 7 5 Wide belt sander 5 8 6 5 Disc sander 4 9 2 5
  • 4. Implementation Of Lean Strategies In A Furniture Manufacturing Factory DOI: 10.9790/1684-12134550 www.iosrjournals.org 48 | Page Block sander 4 9 2 5 Moulder 3 3 4 5 Jig saw 3 4 8 5 Band saw 3 4 5 5 Radial arm saw 4 7 4 5 Among those machines, cutting tool of surface planer, thickness planer, panel saw, DET, wide belt sander, disc sander and block sander does not need changing for each successive lot. In case of these machines, every three to four lots needs tool change; otherwise only tool adjustment time was needed. After SMED methodology was applied in the machines, the results showed a significant improvement in time taken during setup which is showed in table 4. Table 4: Average time spent during setup on machines (after SMED implementation) Another improvement attained was the reduction of operators’ movement during the setup process. Table 5 represents the results obtained for the distance travelled by the operators. Table 5: Improvements obtained in average distance travelled Preliminary stage(m) After SMED(m) Improvement (%) 35.9 14.7 59 Figure 2 represents the spaghetti chart to demonstrate the difference between operators’ movement before and after SMED implementation. Figure 2: workers movement during the setup (before and after) for one line. It is evident from the chart that non value adding activities such as getting cutting tool from the store, sharpening the tool etc are now performed during the external setup by additional helper. It had been observed that for each lot processed in any machine, there was at least two setup times. On average each machine had five lots processed in 16 hour period. Before SMED implementation average machine setup time was 19.44 minute, and after SMED implementation this time reduced down to 11.47 minute. So a total of 7.97 minute was saved for processing each lot. If surface planer, thickness planer, panel saw, DET, wide belt sander, disc sander and block sander machines which needed fewer setups were excluded from the list, there were 31 machines in total. So for 31 machines total machine hour saved was 31*10*7.97 minutes or 41.18 hours. If 45 machines run for 16 hours and produce products equivalent to 26,00000 Taka per day, then extra
  • 5. Implementation Of Lean Strategies In A Furniture Manufacturing Factory DOI: 10.9790/1684-12134550 www.iosrjournals.org 49 | Page machine hour of at least 41.18 hours would bring the firm additional 148705 Taka per day. From the calculation after SMED implementation, it was found that on average the daily production increased to almost 27, 59420 Taka per day. 1.2 Impact of GEMBA and Short interval control Before the implementation of GEMBA and short interval control on the factory floor; OEE, total downtime minutes, reject quantity and wastage of materials were calculated and analyzed for a two month period. Mean time between failures(MTBF) was also calculated. Afterwards the supervision team started conducting short meetings (8-10 minutes) on every two and a half hours discussing the condition of above three loss metrics as well as solving them and following the general guidelines provided to them. This enabled them to have an instant grasp of the existing condition of the factory floor. After two months, this showed an impressive improvementwhich is showed in table 6. Table 6: Improvements in OEE, total downtime minutes, reject quantity and wastage of materials 1.3 Improvement in productivity Before implementation of SMED, Gemba and short interval control methodologies on the factory floor, labor and material productivity was 3.19 and 4.35(calculated over a two month period). After implementing the above mentioned lean strategies, labor and material productivity increased to 4.76 and 4.42; resulting in a higher multifactor productivity of 2.26. Figure 3 depicts this improvement. Figure 3: Labor, material and multifactor productivity Labor productivity increased substantially due to increased supervision and reduction of setup times through the implementation of SMED technique. Slight increase in material productivity was also due to increased supervision which resulted in lower reject quantity and lower wastage of materials. V. Conclusion This study clearly shows that lean strategies such as SMED, Gemba and short interval control can be effectively applied to improve the condition of a furniture manufacturing company. The main results achieved were improvements in setup times of different machines on the factory floor, 59% improvement in the average distance travelled by the workers resulting in an additional 148705 Taka per day. 12%,40%,14%,32% improvement respectively was achieved in OEE, total downtime minutes, reject quantity and wastage of materials. Both labor and material productivity increased resulting in a higher multifactor productivity of 2.26. It was realized through this study that lean strategies can successfully be implemented in furniture manufacturing industry. References [1]. J Womack, D Jones , Lean thinking: banish waste and create wealth in your corporation (Free press,1996). [2]. S Shingo, A revolution in Manufacturing: the SMED System. Productivity Press(Cambridge, MA; 1985) [3]. Ana Sofia Alves and Alexandra Tenera, Improving SMED in the Automotive Industry: A case study, Production and Operations Management Society 20th Annual conference Orlando,Florida US; 2009 [4]. R Mcintosh, G Owen, S Culley and T Mileham, Changeover improvement: reinterpreting Shingo’s “SMED” methodology, IEE Transactions on Engineering Management, 2007, 54, p.98-111 [5]. D Goubergen, H Landeghem, Rules for integrating fast changeover capabilities into new equipment design, Robotics and Computer Integrated Manufacturing, 2002,18, p.205-214 [6]. M Cakmacki, Process Improvement: Performance analysis of the setup time reduction-SMED in the automobile industry, International Journal of Advanced Manufacturing Technology, 2009,41, p. 168-179
  • 6. Implementation Of Lean Strategies In A Furniture Manufacturing Factory DOI: 10.9790/1684-12134550 www.iosrjournals.org 50 | Page [7]. Trovinger and Bohn, Setup time reduction for Electronics assembly: Combining simple SMED and IT based methods, Production and Operations Management Society, 2005, 14(2), ISSN 1059-1478 [8]. T.B Michels, Application of Shingo’s Single Minute Exchange Of Dies(SMED) Methodology to reduce Punch Press Changeover Times at Krueger International, Thesis, University of Wisconsin-Stout, 2007. [9]. Manuel F. Suárez‐Barraza, Juan Ramis‐Pujol, Mariana Estrada‐Robles, Applying Gemba‐Kaizen in a multinational food company: a process innovation framework, International Journal of Quality and Service Sciences, 2012, Vol. 4 Issue: 1, p.27 – 50.