SlideShare a Scribd company logo
Geotechnical risk on large scale
infrastructure projects
Dr Chris Bridges CEng FICE
(chris.bridges@smec.com)
19 November 20201
• https://australiangeomechanics.org/chapter/queensland/
2
Contents
• Introduction
• Understanding
• Impacts
• Recommendations
3
Introduction
4
Geotechnical engineering
Introduction
5
Geotechnical engineering
Introduction
6
What is risk?
“Risk is like love: we all know what it is, but we don’t know how to define it”
(Joseph Stiglitz quoted in (Nguyen, 2007))
“……the fear of an evil ought to be proportionate, not only to its magnitude,
but also to its probability…”.
(from 1662 by Arnaud (Arnaud, 1850))
Introduction
risco - danger
rischiare – run into danger risquer
risque
ITALIAN
FRENCH
RISK = LIKELIHOOD x CONSEQUENCE
7
Lower Risk Lower Risk
Higher Risk
8
Introduction
Understanding
9
Civil engineers do not understand
geotechnical engineering
“The major part of the college training of civil engineers consists in the
absorption of the laws and rules which apply to relatively simple and
well-defined materials, such as steel or concrete. This type of education
breeds the illusion that everything connected with engineering should
and can be computed on the basis of a priori assumptions.
Unfortunately, soils are made by nature and not by man, and the
products of nature are always complex.”
(Terzaghi, 1936)
10
Understanding
This lack of understanding continues today
(Kajastie, 2020)
“… lack of investment in earlier site investigation, … lack
of technical understanding among project managers and
a trend towards reduced quality across the industry.”
11
Understanding
A lack of appreciation of geotechnical risks
Project Management
(General Geotechnical Risks)
Line Management of Different Project Risks
Specific Geotechnical Risks
Contractural Technical
Geological Engineering
Material
Properties
Team
Leadership and
Experience
(Baynes, 2010)
High level risks –
General lack of
appreciation of
geotechnical risks – i.e
restrict geotechnical
budget
Specific risks
12
Understanding
Poor investment in investigation can have
impacts
0
20
40
60
80
100
120
140
160
180
0 2 4 6 8 10 12
As-builtconstructioncostas%ofengineers
estimate
Investigation cost as % of construction cost (excludes variations)
Engineers estimate = 100%
13
(National Research Council, 1984)
Understanding
Geotechnical risks
Project Management
(General Geotechnical Risks)
Line Management of Different Project Risks
Specific Geotechnical Risks
Contractural Technical
Geological Engineering
Material
Properties
Team
Leadership and
Experience
(Baynes, 2010)
High level risks –
General lack of
appreciation of
geotechnical risks – i.e
restrict geotechnical
budget
Specific risks
14
Understanding
Contractual risks are the foundations
for poor project performance
Contractual
• Risk transfer
• GBR - Crossrail
0 10 20 30 40 50 60 70 80 90 100
Cl
PM
Cons
PC
SC
Sup
Man
Percentage Risk Allocation
Organization
Cl PM Cons PC SC Sup Man
Cl = client; PM = project manager; Cons = consultants; PC = primary contractor;
SC = subcontractor; Sup = supplier; and Man = manufacturer
(Loosemore & McCarthy, 2008)
15
Understanding
Client: 35% PM 45% PC 10% Client
PC: 25% PM 35% PC 20% Client
Consult: 35% PM 25% PC 30% Client
Different parties to a contract view risks
differently
(Smith, 2019, Smith, 2018)
16
Understanding
Different parties to a contract view risks
differently
(Castro-Nova, Gad, Touran, Cetin, & Gransberg, 2018)
17
Understanding
Different parties to a contract view risks
differently
(Lo, Fung, & Tung, 2006 - Construction Delays in Hong Kong Civil Engineering Projects)
18
Understanding
Team risks are often forgotten
Team
• Leadership
• Availability
• Role separation
19
Geotechnical
Manager
Hydraulics/
Hydrology -
parameters for
scour
assessment,
climate change,
flooding
Environmental -
acid sulfate soils,
contaminated
land, cultural
heritage,
sensitive areas,
sustainability
Contractor -
constructability,
cost, temporary
works
Independent
Verifier /
Independent
Checking
Engineer -
design
verification &
compliance
Client - design
life,
maintenance,
compliance,
whole-of-life
cost,
stakeholders
Pavement -
subgrade
properties,
expansive soils
Structures -
earth pressures /
foundation
parameters,
retaining wall
and foundation
design
Alignment -
Shallow in cuts
to avoid blasting,
low
embankments on
soft soil, batter
slope angles,
cut/fill balance
Site
Investigation
Contractor -
ground
investigation
data
Geological risks are often considered as
the main geotechnical risks
• groundwater
• geological features
• compressible soils
• unstable slopes
• strength and stiffness
• anthropogenic materials
• geomorphology and landform
• problem soils
20
Understanding
Material properties are critical to design
(Bond & Harris, 2008)
-40
-35
-30
-25
-20
-15
-10
-5
0
0 20 40 60 80
Depthbelowgroundlevel(m)
Undrained shear strength (kPa)
21
Understanding
Material properties are critical to design
(Bond & Harris, 2008)
-40
-35
-30
-25
-20
-15
-10
-5
0
0 20 40 60 80
Depthbelowgroundlevel(m)
Undrained shear strength (kPa)
Range of interpretations
22
Understanding
Material properties are critical to design
23
Lower bound: c=0, f’=25
Upper bound: c=0, f’=39
Understanding
Can we be sure of the data we receive
24
Understanding
Laboratory testing: Revealing consistency concerns
31 January, 2018 By GE Editorial
c. 9% variation c. 15% variation
Understand where your data comes from
25
50mm (ID) x 500mm – 0.00098m3
Understanding
Understand its reliability
“Every experienced contractor knows that ground investigations can
only be 100% accurate in the precise locations in which they are carried
out. It is for an experienced contractor to fill in the gaps and take an
informed decision as to what the likely conditions would be overall”.
(Mr Justice Coulson (Van Oord UK Ltd & Anor v Allseas UK Ltd, 2015))
26
Understanding
Don’t believe all you see
27
Understanding
28
Understand the scale of your
information
29
Understanding
INB drilling accounted
for only about 10m3 of
soil/rock from
70,000m3 excavated
(0.015%)
Understand the scale of your
information
30
Sieffert & Bay-Gress (2000) Comparison of European bearing capacity calculation methods for shallow
foundations Proc. Instn Civ. Engrs Geotech. Engng, 143, 65-74
734kN
1297kN
31
Understand the limits of your analysis
Understanding
Understand the limits of your analysis
(Morgenstern, 2000)
Shallow foundation on sand
0 2 4 6 8 10 12 14
Bad (<50)
Poor (50-75)
Fair (75-85)
Good (85-95)
Excellent (95-105)
Good (105-115)
Fair (115-125)
Poor (125-150)
Bad (>150)
Bearing Capacity Settlement
Bearing - 66% Poor / Bad
Settlement - 90% Poor / BadWithin 25%
of the answer
Over-estimate
Under-estimate
32
Understanding
DESIGN ELEMENT UNDER DESIGN
(NO./%)
OVER DESIGN
(NO./%)
ACCEPTABLE
(NO./%)
REFERENCE
STEEL DRIVEN PILE CAPACITY: BASE
SHAFT
TOTAL
4 / 25
13 / 18.25
11 / 68.75
6 / 37.5
1 / 6.25
3 / 18.75
6 / 37.5
2 / 12.5
2 / 12.5
(Anon, 1999)
BASE GROUTED STEEL DRIVEN PILE
CAPACITY: BASE
SHAFT
TOTAL
3 / 18.75
4 / 25
2 / 12.5
10 / 62.75
7 / 43.75
11 / 68.75
3 / 18.75
5 / 31.25
3 / 18.75
(Anon, 1999)
SHALLOW FOUNDATION ON SOFT CLAY:
ULTIMATE CAPACITY
SETTLEMENT AT FAILURE
39 / 78
4 / 8
3 / 6
43 / 86
8 / 16
3 / 6
(Doherty et al.,
2018)
SHALLOW FOUNDATION ON SAND:
BEARING CAPACITY
SETTLEMENT
10 / 34
18 / 58
9 / 31
10 / 32.3
10 / 34
3 / 9.7
(Morgenstern,
2000)
EMBANKMENT COLLAPSE HEIGHT 21 / 48.8 4 / 9.3 18 / 41.9 (Morgenstern,
2000)
EMBANKMENT ON SOFT GROUND,
SETTLEMENT WITH TIME: 106 DAYS
1095 DAYS
15 / 44
17 / 55
4 / 12
1 / 3
15 / 44
13 / 42
(Kelly et al., 2018)
33
Impacts
34
Geotechnical risks cause project impacts
35
GEOTECHNICAL CAUSE RANK
(COST IMPACTS)
RANK
(DELAY IMPACTS)
Lack of sufficient boring locations 1 1
Misclassified / mischaracterized
soils
2 2
Higher groundwater table than
expected
3 3
Dewatering due to seepage 4 3
Design changes to
superstructure
4 2
Prescribed soil treatment not
suitable
5 4
Variation of piling quantities due
to wrong pile type
5 3
Mismatch in pile quantities 6 5
Erosion and sediment control 7 6
60.5
38.3
1.2
Negative No impact Positive
60.8
36.7
2.5
Negative No impact Positive
Cost overrun (%)
Schedule overrun (%)
Impacts
(Shrestha & Neupane, 2010)
How good is engineering judgement?
36
CAUSE
CLAIM
Failure of flood protection system >$60 bn
Construction claim on volume losses in dredge-fill >$400 m
Concerns over future failures of MSW systems >$100 m
Excessive settlement of high-rise building >$200 m
Settlement of homes >$100 m
Property damage from failure of dam over 10 m high >$100 m
Delays and damages from excavation support system >$100 m
Heave of pavement subgrade >$100 m
Failure of tailings dams – 2008, 2015, 2019 >$1 bn each
Impacts
(Marr, 2019)
Case study literature
Impacts
37
Mistakes can be expensive
Impacts
(Peracha & Pengelly, 2020)
38
The role of geotechnical sub-consultant
(temporary tunnel support)
• Geotechnical sub-consultant put forward 3 staff – only 1 accepted
(24/7 Operation)
• Provided with 3 juniors by the contractor who were not NATM
experienced
• Did not certify construction of the works they designed
• Inadequate computer software system for processing the monitoring
data
39
Impacts
Settlement at Camborne House
exceeded predicted settlement
(9mm) after only concourse
tunnel completed by about
20mm.
40
41
42
The findings
• lack of on-site NATM authority at Heathrow
• lack of experience among the field engineers, the tunnelling foremen
and the crews – design did not take this into account – poor
workmanship an issue
• lack of full-time geologists within an NATM supervision team
• Contractors geotechnical sub-contractor not kept in the loop
• Instrumentation - limited data available, poor quality, serious
omissions, "inadequate" computer software
• there was still enough data available to see what was happening
43
Impacts
Mistakes can be expensive
• Contractor fined £1.2M + £100k costs (contract value £60M)
• Recovery took nearly two years and cost around £150M - nearly
three times the cost of the original contract
44
Impacts
……and embarrassing
Impacts
(Anon, 2020)
45
Recommendations
46
47
Safetyindesignandprojectriskregisters
detailingriskprocess.Processtobeupdated
throughoutthedesignandconstruction
Establishing
the Context
• Project details - scope, alignment etc
• Desk study, historical records etc.
• Site investigation data
Risk
Identification
• Ground model development, parameter selection
• Developing concept design
• Identifying geotechnical risks
Risk
Analyses
• Combining identified risks with their likely consequences
Risk
Evaluation
• Evaluating which risks require treatment
Risk
Treatment
• Detailed design to eliminate or manage risks
• Instrumentation and ongoing monitoring to manage risks
Establishing
the Context
• Reviewing site data as construction proceeds and update models
/ design as necessary
• Review risk process and update as necessary
In developing solutions and presenting
these to our clients we must be aware of
the limitations
• Investigations sample a very small amount of the site
• Laboratory and insitu testing is subject to errors and inconsistencies
• Engineers can derive a range of interpretations for a single set of test data
• Design methods can give significantly different answers
• Software outputs are only as good as the information we put in and need to be checked against what
we consider to be reasonable
• Team leadership and inexperience can seriously affect project outcomes and magnify the likely risks
48
Recommendations
Geotechnical engineers should be
• Engaging senior professionals early as possible in the project
• Using independent reviewers or verifiers
• Communicating and building relationships with the various parties and stakeholders (establishing
trust) as early as possible
• Adopting procedures based on precedence so that methods of analysis etc. are the same for each
project i.e. Department of Transport and Main Roads (2015) and United States Army Corps of
Engineers (2003)
• Expressing results with likely variability
• Explaining the design and design intent to the relevant site engineers prior to construction,
including likely risks and uncertainty
• Supporting and mentoring Team Leaders throughout the project
49
Recommendations
Questions
• Introduction
• Understanding
• Impacts
• Recommendations
50
chris.bridges@smec.com
RecommendationsBridges, C.A. (2019) Geotechnical risk: it’s not only the ground. Australian Geomechanics
54(1) 27-38
References
• Anon. (2020). Piling design error leads to Sheffield building demolition. Ground Engineering(October), 6.
• Arnaud, A. (1850). Logic, or the Art of Thinking being the Port-Royal Logic (Translated from the French by Baynes) (T. S. Baynes, Trans.).
Edinburgh, UK: Sutherland and Knox.
• Baynes, F. J. (2010). Sources of geotechnical risk. Quarterly Journal of Engineering Geology and Hydrogeology, 43, 321-331.
• Bond, A., & Harris, A. (2008). Decoding Eurocode 7. Abingdon, UK: Taylor & Francis.
• Bridges, C. (2019). Geotechnical risk: it's not only the ground. Australian Geomechanics, 54(1), 27-38.
• Buxton, J. A., Henry, B., Crabtree, A., Waheed, A., & Coulthart, M. (2011). Using qualitative methods to investigate risk perception of
Canadian medical laboratory workers in relation to current prion disease infection control policies. Journal of Toxicology and Environmental
Health, Part A, 74, 241-247.
• Castro-Nova, I., Gad, G. M., Touran, A., Cetin, B., & Gransberg, D. D. (2018). Evaluating the Influence of Differing Geotechnical Risk
Perceptions on Design-Build Highway Projects. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering,
4(4). doi:10.1061/AJRUA6.0000993
• Committee of Inquiry. (2005). Report of the Committee of Inquiry into the Incident at the MRT Circle Line workste that led to the collapse of
the Nicoll Highway on 20 April 2004 (Volume 1 (Part I)).
• Douglas, M. (1970). Natural symbols: explorations in cosmology. London, UK: Barrie & Rockliff.
51
References
• Kahan, D. M., Braman, D., Slovic, P., Gastil, J., & Cohen, G. (2007). The Second National Risk and Culture Study: Making Sense of - and
Making Progress In - the American Culture War of Fact. Retrieved from New Haven, Connecticut, USA:
• Kajastie, N. (2020). Covid issues mask other concerns. Ground Engineering(October ), 3.
• Kasperson, R. E. (2012). A Perspective on the Social Amplification of Risk. The Bridge, 42(3), 23-27.
• Lo, D. O. K., & Cheung, W. M. (2005). Assessment of landslide risk of man-made slopes in Hong Kong (GEO Report No. 177). Retrieved from
Hong Kong Special Administrative Region, PRC:
• Lo, T. Y., Fung, I. W. H., & Tung, K. C. F. (2006). Construction Delays in Hong Kong Civil Engineering Projects. Journal of Construction
Engineering and Management, 132(6), 636-649. doi:10.1061/ASCE0733-93642006132:6636
• Loosemore, M., & McCarthy, C. S. (2008). Perceptions of Contractual Risk Allocation in Construction Supply Chains. Journal of Professional
Issues in Engineering Education and Practice, 134(1), 95-105.
• Marsden, E. (2017, 31 July 2017). Risk perception. Retrieved from https://risk-engineering.org/static/PDF/slides-risk-perception.pdf
• Morgenstern, N. R. (2000). Performance in Geotechnical Practice. Paper presented at the The Inaugural Lumb Lecture, Hong Kong.
• National Research Council. (1984). Geotechnical Site Investigations for Underground Projects: Volume 1: Overview of Practice and Legal
Issues, Evaluation of Cases, Conclusions and Recommendations. Retrieved from Washington, DC, USA:
• Nguyen, N. C. (2007). Risk management strategies and decision support tools for dry land farmers in southwest Queensland. Australia.
(PhD), University of Queensland, Gatton. Queensland. Australia.
52
References
• Peracha, Q., & Pengelly, E. (2020, 27 Jan 2020). The day tunnels below Heathrow collapsed and created giant crater between runways.
Retrieved from https://www.getsurrey.co.uk/news/surrey-news/day-tunnels-below-heathrow-collapsed-17601515
• Sbaraini, A., Carter, S. M., Evans, R. W., & Blinkhorn, A. (2011). How to do a grounded theory study: a worked example of a study of dental
practices. BMC Medical Research Methodology, 11(128). doi:https://doi.org/10.1186/1471-2288-11-128
• Slovic, P., Fischhoff, B., & Lichtenstein, S. (1979). Rating the Risks. Environment, 21(3), 14-39.
• Smith, C. (2018, 13 June 2018). HS2 £1bn over target costs following geotechnical risk warning. Retrieved from
https://www.geplus.co.uk/news/hs2-1bn-over-target-costs-following-geotechnical-risk-warning-13-06-2018/
• Smith, C. (2019). HS2 plans to reduce ground risk cost described as “carnage”. Retrieved from https://www.geplus.co.uk/news/hs2-plans-to-
reduce-ground-risk-cost-described-as-carnage-28-01-2019
• Willingham, R. (2019, 9 December 2019). Melbourne Metro Tunnel project grinds to a halt amid dispute over deadlines and costs. Retrieved
from https://www.abc.net.au/news/2019-12-09/melbourne-metro-tunnel-project-grinds-to-halt-amid-dispute/11779986
53
Appendices
54
0 2 4 6 8 10 12
Bad (<50)
Poor (50-75)
Fair (75-85)
Good (85-95)
Excellent (95-105)
Good (105-115)
Fair (115-125)
Poor (125-150)
Bad (>150)
Number of Predictions
AccuracyofPrediction(%)
Driven Steel Pile
Total Capacity (kN)
Base Capacity (kN)
Shaft Capacity (kN)
Under estimate
Over estimate
Shaft - 88% Poor / Bad
Base - 63% Poor / Bad
Total - 88% Poor / Bad
55
0 1 2 3 4 5 6 7 8 9 10
Bad (<50)
Poor (50-75)
Fair (75-85)
Good (85-95)
Excellent (95-105)
Good (105-115)
Fair (115-125)
Poor (125-150)
Bad (>150)
Number of Predictions
AccuracyofPrediction(%)
Jet Grouted Pile
Total Pile Capacity (kN)
Base Capacity (kN)
Shaft Capacity (kN)
Over estimate
Shaft - 69% Poor / Bad
Base - 81% Poor / Bad
Total - 81% Poor / Bad
Under estimate
56
0 2 4 6 8 10 12 14 16
Bad (<50)
Poor (50-75)
Fair (75-85)
Good (85-95)
Excellent (95-105)
Good (105-115)
Fair (115-125)
Poor (125-150)
Bad (>150)
Number of Predictions
AccuracyofPrediction(%)
Embankment Collapse Height
Muar Embankment
Prediction Competition
MIT Embankment
Prediction Competition
Non-conservative
Conservative
60% Poor / Bad – majority
on the conservative side of
prediction
57

More Related Content

What's hot

Stress distribution of the soil
Stress distribution of the soilStress distribution of the soil
Stress distribution of the soil
Dharmik Navadiya
 
Standard Penetration Test (SPT)
Standard Penetration Test (SPT)Standard Penetration Test (SPT)
Standard Penetration Test (SPT)
MachenLink
 
Trixial test
Trixial testTrixial test
Trixial test
ABHISHEK THAKKAE
 
Slope stability question answers
Slope stability question answersSlope stability question answers
Slope stability question answers
Jyoti Khatiwada
 
Shear strength of soil
Shear strength of soilShear strength of soil
Shear strength of soil
rajini24
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
Amit Jagtap
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Muhammad Irfan
 
Box culverts
Box culvertsBox culverts
Box culverts
sunil choudhary
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of Soil
Umang Parmar
 
Soil dynamics introduction
Soil dynamics introductionSoil dynamics introduction
Soil dynamics introduction
Sanjay Thakare
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement
Suez Halder
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Make Mannan
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Muhammad Irfan
 
Consolidation
ConsolidationConsolidation
Consolidation
MRINALJYOTI ADHYAPOK
 
Lecture 1 introduction & types of foundation
Lecture 1  introduction & types of foundationLecture 1  introduction & types of foundation
Lecture 1 introduction & types of foundation
Dr.Abdulmannan Orabi
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
Muftah Aljoat
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Muhammad Irfan
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
Simarpreet Singh
 
CPTu Dissipation Test
CPTu Dissipation TestCPTu Dissipation Test
CPTu Dissipation Test
Abolfazl Najafi
 

What's hot (20)

Stress distribution of the soil
Stress distribution of the soilStress distribution of the soil
Stress distribution of the soil
 
Standard Penetration Test (SPT)
Standard Penetration Test (SPT)Standard Penetration Test (SPT)
Standard Penetration Test (SPT)
 
Trixial test
Trixial testTrixial test
Trixial test
 
Slope stability question answers
Slope stability question answersSlope stability question answers
Slope stability question answers
 
Shear strength of soil
Shear strength of soilShear strength of soil
Shear strength of soil
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
 
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #27: Infinite Slope Stability Analysis]
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of Soil
 
Soil dynamics introduction
Soil dynamics introductionSoil dynamics introduction
Soil dynamics introduction
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
 
Consolidation
ConsolidationConsolidation
Consolidation
 
Lecture 1 introduction & types of foundation
Lecture 1  introduction & types of foundationLecture 1  introduction & types of foundation
Lecture 1 introduction & types of foundation
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
CPTu Dissipation Test
CPTu Dissipation TestCPTu Dissipation Test
CPTu Dissipation Test
 

Similar to Geotechnical risk on large scale infrastructure projects

2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment
Subhechha Sharma
 
2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment
Subhechha Sharma
 
Risk assessment of climate change impacts to built infrastructure - Identific...
Risk assessment of climate change impacts to built infrastructure - Identific...Risk assessment of climate change impacts to built infrastructure - Identific...
Risk assessment of climate change impacts to built infrastructure - Identific...
Svenska Betongföreningen
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET Journal
 
IRJET- Non-Destructive Test Application in Civil Infrastructure
IRJET- Non-Destructive Test Application in Civil InfrastructureIRJET- Non-Destructive Test Application in Civil Infrastructure
IRJET- Non-Destructive Test Application in Civil Infrastructure
IRJET Journal
 
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
IRJET Journal
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
nadeemovic
 
1 Geosynthetics&amp;Geosystems Pilarczyk Pres Final
1 Geosynthetics&amp;Geosystems  Pilarczyk Pres Final1 Geosynthetics&amp;Geosystems  Pilarczyk Pres Final
1 Geosynthetics&amp;Geosystems Pilarczyk Pres Final
Krystian Pilarczyk
 
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
IRJET Journal
 
AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
Audubon Engineering Company
 
Presentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergencyPresentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergency
Super Arc Consultant
 
IRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
IRJET-Experimental Study on Concrete Properties using Pet in Tension ZoneIRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
IRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
IRJET Journal
 
AC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDILAC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDIL
Patrick J. Morrissey
 
1 s2.0-s2212827114000377-main
1 s2.0-s2212827114000377-main1 s2.0-s2212827114000377-main
1 s2.0-s2212827114000377-main
Loli Kurniawati
 
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
Robert Muir
 
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET Journal
 
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
IRJET Journal
 

Similar to Geotechnical risk on large scale infrastructure projects (20)

2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment
 
2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment
 
Risk assessment of climate change impacts to built infrastructure - Identific...
Risk assessment of climate change impacts to built infrastructure - Identific...Risk assessment of climate change impacts to built infrastructure - Identific...
Risk assessment of climate change impacts to built infrastructure - Identific...
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
 
IRJET- Non-Destructive Test Application in Civil Infrastructure
IRJET- Non-Destructive Test Application in Civil InfrastructureIRJET- Non-Destructive Test Application in Civil Infrastructure
IRJET- Non-Destructive Test Application in Civil Infrastructure
 
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
IRJET- Study on Behaviour of Geopolymer Concrete by using Digital Image Corre...
 
Fracture Mechanics & Failure Analysis Lecture 1
Fracture Mechanics & Failure Analysis Lecture 1Fracture Mechanics & Failure Analysis Lecture 1
Fracture Mechanics & Failure Analysis Lecture 1
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
 
1 Geosynthetics&amp;Geosystems Pilarczyk Pres Final
1 Geosynthetics&amp;Geosystems  Pilarczyk Pres Final1 Geosynthetics&amp;Geosystems  Pilarczyk Pres Final
1 Geosynthetics&amp;Geosystems Pilarczyk Pres Final
 
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
IRJET- Experimental Study on Crack Detection and Damage Index in Conventional...
 
AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
 
Presentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergencyPresentation1 integrity problems of concrete piles-emergency
Presentation1 integrity problems of concrete piles-emergency
 
IRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
IRJET-Experimental Study on Concrete Properties using Pet in Tension ZoneIRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
IRJET-Experimental Study on Concrete Properties using Pet in Tension Zone
 
AC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDILAC 434 DESIGN CRITERIA - RUREDIL
AC 434 DESIGN CRITERIA - RUREDIL
 
1 s2.0-s2212827114000377-main
1 s2.0-s2212827114000377-main1 s2.0-s2212827114000377-main
1 s2.0-s2212827114000377-main
 
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
MNRF CWRA Technical Workshop March 6 2018 Rob Grech and Robert Muir City of M...
 
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
 
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
STUDY TO EFFECT OF DESIGN CHANGE OF EARTHQUAKE PERFORMANCE AND MITIGATION BY ...
 

More from Chris Bridges

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on project
Chris Bridges
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway construction
Chris Bridges
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projects
Chris Bridges
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
Chris Bridges
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8
Chris Bridges
 
Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7
Chris Bridges
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
Chris Bridges
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5
Chris Bridges
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4
Chris Bridges
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3
Chris Bridges
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2
Chris Bridges
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1
Chris Bridges
 

More from Chris Bridges (12)

Long-term geotechnical impacts of climate change on project
 Long-term geotechnical impacts of climate change on project Long-term geotechnical impacts of climate change on project
Long-term geotechnical impacts of climate change on project
 
The identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway constructionThe identification, treatment and use of expansive soils in railway construction
The identification, treatment and use of expansive soils in railway construction
 
The management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projectsThe management of geotechnical risk on major infrastructure projects
The management of geotechnical risk on major infrastructure projects
 
The design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankmentsThe design evolution of replacement motorway bridge approach embankments
The design evolution of replacement motorway bridge approach embankments
 
Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8Design of earth-retaining structures - Lecture 8
Design of earth-retaining structures - Lecture 8
 
Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7Design of earth-retaining structures - Lecture 7
Design of earth-retaining structures - Lecture 7
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
 
Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5Design of earth-retaining structures - Lecture 5
Design of earth-retaining structures - Lecture 5
 
The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4The design of earth retaining structures - Lecture 4
The design of earth retaining structures - Lecture 4
 
The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3The design of earth retaining structures - Lecture 3
The design of earth retaining structures - Lecture 3
 
The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2The design of earth-retaining structures - Lecture 2
The design of earth-retaining structures - Lecture 2
 
The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1The design of earth-retaining structures - Lecture 1
The design of earth-retaining structures - Lecture 1
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 

Geotechnical risk on large scale infrastructure projects

  • 1. Geotechnical risk on large scale infrastructure projects Dr Chris Bridges CEng FICE (chris.bridges@smec.com) 19 November 20201
  • 3. Contents • Introduction • Understanding • Impacts • Recommendations 3
  • 7. What is risk? “Risk is like love: we all know what it is, but we don’t know how to define it” (Joseph Stiglitz quoted in (Nguyen, 2007)) “……the fear of an evil ought to be proportionate, not only to its magnitude, but also to its probability…”. (from 1662 by Arnaud (Arnaud, 1850)) Introduction risco - danger rischiare – run into danger risquer risque ITALIAN FRENCH RISK = LIKELIHOOD x CONSEQUENCE 7
  • 8. Lower Risk Lower Risk Higher Risk 8 Introduction
  • 10. Civil engineers do not understand geotechnical engineering “The major part of the college training of civil engineers consists in the absorption of the laws and rules which apply to relatively simple and well-defined materials, such as steel or concrete. This type of education breeds the illusion that everything connected with engineering should and can be computed on the basis of a priori assumptions. Unfortunately, soils are made by nature and not by man, and the products of nature are always complex.” (Terzaghi, 1936) 10 Understanding
  • 11. This lack of understanding continues today (Kajastie, 2020) “… lack of investment in earlier site investigation, … lack of technical understanding among project managers and a trend towards reduced quality across the industry.” 11 Understanding
  • 12. A lack of appreciation of geotechnical risks Project Management (General Geotechnical Risks) Line Management of Different Project Risks Specific Geotechnical Risks Contractural Technical Geological Engineering Material Properties Team Leadership and Experience (Baynes, 2010) High level risks – General lack of appreciation of geotechnical risks – i.e restrict geotechnical budget Specific risks 12 Understanding
  • 13. Poor investment in investigation can have impacts 0 20 40 60 80 100 120 140 160 180 0 2 4 6 8 10 12 As-builtconstructioncostas%ofengineers estimate Investigation cost as % of construction cost (excludes variations) Engineers estimate = 100% 13 (National Research Council, 1984) Understanding
  • 14. Geotechnical risks Project Management (General Geotechnical Risks) Line Management of Different Project Risks Specific Geotechnical Risks Contractural Technical Geological Engineering Material Properties Team Leadership and Experience (Baynes, 2010) High level risks – General lack of appreciation of geotechnical risks – i.e restrict geotechnical budget Specific risks 14 Understanding
  • 15. Contractual risks are the foundations for poor project performance Contractual • Risk transfer • GBR - Crossrail 0 10 20 30 40 50 60 70 80 90 100 Cl PM Cons PC SC Sup Man Percentage Risk Allocation Organization Cl PM Cons PC SC Sup Man Cl = client; PM = project manager; Cons = consultants; PC = primary contractor; SC = subcontractor; Sup = supplier; and Man = manufacturer (Loosemore & McCarthy, 2008) 15 Understanding Client: 35% PM 45% PC 10% Client PC: 25% PM 35% PC 20% Client Consult: 35% PM 25% PC 30% Client
  • 16. Different parties to a contract view risks differently (Smith, 2019, Smith, 2018) 16 Understanding
  • 17. Different parties to a contract view risks differently (Castro-Nova, Gad, Touran, Cetin, & Gransberg, 2018) 17 Understanding
  • 18. Different parties to a contract view risks differently (Lo, Fung, & Tung, 2006 - Construction Delays in Hong Kong Civil Engineering Projects) 18 Understanding
  • 19. Team risks are often forgotten Team • Leadership • Availability • Role separation 19 Geotechnical Manager Hydraulics/ Hydrology - parameters for scour assessment, climate change, flooding Environmental - acid sulfate soils, contaminated land, cultural heritage, sensitive areas, sustainability Contractor - constructability, cost, temporary works Independent Verifier / Independent Checking Engineer - design verification & compliance Client - design life, maintenance, compliance, whole-of-life cost, stakeholders Pavement - subgrade properties, expansive soils Structures - earth pressures / foundation parameters, retaining wall and foundation design Alignment - Shallow in cuts to avoid blasting, low embankments on soft soil, batter slope angles, cut/fill balance Site Investigation Contractor - ground investigation data
  • 20. Geological risks are often considered as the main geotechnical risks • groundwater • geological features • compressible soils • unstable slopes • strength and stiffness • anthropogenic materials • geomorphology and landform • problem soils 20 Understanding
  • 21. Material properties are critical to design (Bond & Harris, 2008) -40 -35 -30 -25 -20 -15 -10 -5 0 0 20 40 60 80 Depthbelowgroundlevel(m) Undrained shear strength (kPa) 21 Understanding
  • 22. Material properties are critical to design (Bond & Harris, 2008) -40 -35 -30 -25 -20 -15 -10 -5 0 0 20 40 60 80 Depthbelowgroundlevel(m) Undrained shear strength (kPa) Range of interpretations 22 Understanding
  • 23. Material properties are critical to design 23 Lower bound: c=0, f’=25 Upper bound: c=0, f’=39 Understanding
  • 24. Can we be sure of the data we receive 24 Understanding Laboratory testing: Revealing consistency concerns 31 January, 2018 By GE Editorial c. 9% variation c. 15% variation
  • 25. Understand where your data comes from 25 50mm (ID) x 500mm – 0.00098m3 Understanding
  • 26. Understand its reliability “Every experienced contractor knows that ground investigations can only be 100% accurate in the precise locations in which they are carried out. It is for an experienced contractor to fill in the gaps and take an informed decision as to what the likely conditions would be overall”. (Mr Justice Coulson (Van Oord UK Ltd & Anor v Allseas UK Ltd, 2015)) 26 Understanding
  • 27. Don’t believe all you see 27 Understanding
  • 28. 28
  • 29. Understand the scale of your information 29 Understanding
  • 30. INB drilling accounted for only about 10m3 of soil/rock from 70,000m3 excavated (0.015%) Understand the scale of your information 30
  • 31. Sieffert & Bay-Gress (2000) Comparison of European bearing capacity calculation methods for shallow foundations Proc. Instn Civ. Engrs Geotech. Engng, 143, 65-74 734kN 1297kN 31 Understand the limits of your analysis Understanding
  • 32. Understand the limits of your analysis (Morgenstern, 2000) Shallow foundation on sand 0 2 4 6 8 10 12 14 Bad (<50) Poor (50-75) Fair (75-85) Good (85-95) Excellent (95-105) Good (105-115) Fair (115-125) Poor (125-150) Bad (>150) Bearing Capacity Settlement Bearing - 66% Poor / Bad Settlement - 90% Poor / BadWithin 25% of the answer Over-estimate Under-estimate 32 Understanding
  • 33. DESIGN ELEMENT UNDER DESIGN (NO./%) OVER DESIGN (NO./%) ACCEPTABLE (NO./%) REFERENCE STEEL DRIVEN PILE CAPACITY: BASE SHAFT TOTAL 4 / 25 13 / 18.25 11 / 68.75 6 / 37.5 1 / 6.25 3 / 18.75 6 / 37.5 2 / 12.5 2 / 12.5 (Anon, 1999) BASE GROUTED STEEL DRIVEN PILE CAPACITY: BASE SHAFT TOTAL 3 / 18.75 4 / 25 2 / 12.5 10 / 62.75 7 / 43.75 11 / 68.75 3 / 18.75 5 / 31.25 3 / 18.75 (Anon, 1999) SHALLOW FOUNDATION ON SOFT CLAY: ULTIMATE CAPACITY SETTLEMENT AT FAILURE 39 / 78 4 / 8 3 / 6 43 / 86 8 / 16 3 / 6 (Doherty et al., 2018) SHALLOW FOUNDATION ON SAND: BEARING CAPACITY SETTLEMENT 10 / 34 18 / 58 9 / 31 10 / 32.3 10 / 34 3 / 9.7 (Morgenstern, 2000) EMBANKMENT COLLAPSE HEIGHT 21 / 48.8 4 / 9.3 18 / 41.9 (Morgenstern, 2000) EMBANKMENT ON SOFT GROUND, SETTLEMENT WITH TIME: 106 DAYS 1095 DAYS 15 / 44 17 / 55 4 / 12 1 / 3 15 / 44 13 / 42 (Kelly et al., 2018) 33
  • 35. Geotechnical risks cause project impacts 35 GEOTECHNICAL CAUSE RANK (COST IMPACTS) RANK (DELAY IMPACTS) Lack of sufficient boring locations 1 1 Misclassified / mischaracterized soils 2 2 Higher groundwater table than expected 3 3 Dewatering due to seepage 4 3 Design changes to superstructure 4 2 Prescribed soil treatment not suitable 5 4 Variation of piling quantities due to wrong pile type 5 3 Mismatch in pile quantities 6 5 Erosion and sediment control 7 6 60.5 38.3 1.2 Negative No impact Positive 60.8 36.7 2.5 Negative No impact Positive Cost overrun (%) Schedule overrun (%) Impacts (Shrestha & Neupane, 2010)
  • 36. How good is engineering judgement? 36 CAUSE CLAIM Failure of flood protection system >$60 bn Construction claim on volume losses in dredge-fill >$400 m Concerns over future failures of MSW systems >$100 m Excessive settlement of high-rise building >$200 m Settlement of homes >$100 m Property damage from failure of dam over 10 m high >$100 m Delays and damages from excavation support system >$100 m Heave of pavement subgrade >$100 m Failure of tailings dams – 2008, 2015, 2019 >$1 bn each Impacts (Marr, 2019)
  • 38. Mistakes can be expensive Impacts (Peracha & Pengelly, 2020) 38
  • 39. The role of geotechnical sub-consultant (temporary tunnel support) • Geotechnical sub-consultant put forward 3 staff – only 1 accepted (24/7 Operation) • Provided with 3 juniors by the contractor who were not NATM experienced • Did not certify construction of the works they designed • Inadequate computer software system for processing the monitoring data 39 Impacts
  • 40. Settlement at Camborne House exceeded predicted settlement (9mm) after only concourse tunnel completed by about 20mm. 40
  • 41. 41
  • 42. 42
  • 43. The findings • lack of on-site NATM authority at Heathrow • lack of experience among the field engineers, the tunnelling foremen and the crews – design did not take this into account – poor workmanship an issue • lack of full-time geologists within an NATM supervision team • Contractors geotechnical sub-contractor not kept in the loop • Instrumentation - limited data available, poor quality, serious omissions, "inadequate" computer software • there was still enough data available to see what was happening 43 Impacts
  • 44. Mistakes can be expensive • Contractor fined £1.2M + £100k costs (contract value £60M) • Recovery took nearly two years and cost around £150M - nearly three times the cost of the original contract 44 Impacts
  • 47. 47 Safetyindesignandprojectriskregisters detailingriskprocess.Processtobeupdated throughoutthedesignandconstruction Establishing the Context • Project details - scope, alignment etc • Desk study, historical records etc. • Site investigation data Risk Identification • Ground model development, parameter selection • Developing concept design • Identifying geotechnical risks Risk Analyses • Combining identified risks with their likely consequences Risk Evaluation • Evaluating which risks require treatment Risk Treatment • Detailed design to eliminate or manage risks • Instrumentation and ongoing monitoring to manage risks Establishing the Context • Reviewing site data as construction proceeds and update models / design as necessary • Review risk process and update as necessary
  • 48. In developing solutions and presenting these to our clients we must be aware of the limitations • Investigations sample a very small amount of the site • Laboratory and insitu testing is subject to errors and inconsistencies • Engineers can derive a range of interpretations for a single set of test data • Design methods can give significantly different answers • Software outputs are only as good as the information we put in and need to be checked against what we consider to be reasonable • Team leadership and inexperience can seriously affect project outcomes and magnify the likely risks 48 Recommendations
  • 49. Geotechnical engineers should be • Engaging senior professionals early as possible in the project • Using independent reviewers or verifiers • Communicating and building relationships with the various parties and stakeholders (establishing trust) as early as possible • Adopting procedures based on precedence so that methods of analysis etc. are the same for each project i.e. Department of Transport and Main Roads (2015) and United States Army Corps of Engineers (2003) • Expressing results with likely variability • Explaining the design and design intent to the relevant site engineers prior to construction, including likely risks and uncertainty • Supporting and mentoring Team Leaders throughout the project 49 Recommendations
  • 50. Questions • Introduction • Understanding • Impacts • Recommendations 50 chris.bridges@smec.com RecommendationsBridges, C.A. (2019) Geotechnical risk: it’s not only the ground. Australian Geomechanics 54(1) 27-38
  • 51. References • Anon. (2020). Piling design error leads to Sheffield building demolition. Ground Engineering(October), 6. • Arnaud, A. (1850). Logic, or the Art of Thinking being the Port-Royal Logic (Translated from the French by Baynes) (T. S. Baynes, Trans.). Edinburgh, UK: Sutherland and Knox. • Baynes, F. J. (2010). Sources of geotechnical risk. Quarterly Journal of Engineering Geology and Hydrogeology, 43, 321-331. • Bond, A., & Harris, A. (2008). Decoding Eurocode 7. Abingdon, UK: Taylor & Francis. • Bridges, C. (2019). Geotechnical risk: it's not only the ground. Australian Geomechanics, 54(1), 27-38. • Buxton, J. A., Henry, B., Crabtree, A., Waheed, A., & Coulthart, M. (2011). Using qualitative methods to investigate risk perception of Canadian medical laboratory workers in relation to current prion disease infection control policies. Journal of Toxicology and Environmental Health, Part A, 74, 241-247. • Castro-Nova, I., Gad, G. M., Touran, A., Cetin, B., & Gransberg, D. D. (2018). Evaluating the Influence of Differing Geotechnical Risk Perceptions on Design-Build Highway Projects. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, 4(4). doi:10.1061/AJRUA6.0000993 • Committee of Inquiry. (2005). Report of the Committee of Inquiry into the Incident at the MRT Circle Line workste that led to the collapse of the Nicoll Highway on 20 April 2004 (Volume 1 (Part I)). • Douglas, M. (1970). Natural symbols: explorations in cosmology. London, UK: Barrie & Rockliff. 51
  • 52. References • Kahan, D. M., Braman, D., Slovic, P., Gastil, J., & Cohen, G. (2007). The Second National Risk and Culture Study: Making Sense of - and Making Progress In - the American Culture War of Fact. Retrieved from New Haven, Connecticut, USA: • Kajastie, N. (2020). Covid issues mask other concerns. Ground Engineering(October ), 3. • Kasperson, R. E. (2012). A Perspective on the Social Amplification of Risk. The Bridge, 42(3), 23-27. • Lo, D. O. K., & Cheung, W. M. (2005). Assessment of landslide risk of man-made slopes in Hong Kong (GEO Report No. 177). Retrieved from Hong Kong Special Administrative Region, PRC: • Lo, T. Y., Fung, I. W. H., & Tung, K. C. F. (2006). Construction Delays in Hong Kong Civil Engineering Projects. Journal of Construction Engineering and Management, 132(6), 636-649. doi:10.1061/ASCE0733-93642006132:6636 • Loosemore, M., & McCarthy, C. S. (2008). Perceptions of Contractual Risk Allocation in Construction Supply Chains. Journal of Professional Issues in Engineering Education and Practice, 134(1), 95-105. • Marsden, E. (2017, 31 July 2017). Risk perception. Retrieved from https://risk-engineering.org/static/PDF/slides-risk-perception.pdf • Morgenstern, N. R. (2000). Performance in Geotechnical Practice. Paper presented at the The Inaugural Lumb Lecture, Hong Kong. • National Research Council. (1984). Geotechnical Site Investigations for Underground Projects: Volume 1: Overview of Practice and Legal Issues, Evaluation of Cases, Conclusions and Recommendations. Retrieved from Washington, DC, USA: • Nguyen, N. C. (2007). Risk management strategies and decision support tools for dry land farmers in southwest Queensland. Australia. (PhD), University of Queensland, Gatton. Queensland. Australia. 52
  • 53. References • Peracha, Q., & Pengelly, E. (2020, 27 Jan 2020). The day tunnels below Heathrow collapsed and created giant crater between runways. Retrieved from https://www.getsurrey.co.uk/news/surrey-news/day-tunnels-below-heathrow-collapsed-17601515 • Sbaraini, A., Carter, S. M., Evans, R. W., & Blinkhorn, A. (2011). How to do a grounded theory study: a worked example of a study of dental practices. BMC Medical Research Methodology, 11(128). doi:https://doi.org/10.1186/1471-2288-11-128 • Slovic, P., Fischhoff, B., & Lichtenstein, S. (1979). Rating the Risks. Environment, 21(3), 14-39. • Smith, C. (2018, 13 June 2018). HS2 £1bn over target costs following geotechnical risk warning. Retrieved from https://www.geplus.co.uk/news/hs2-1bn-over-target-costs-following-geotechnical-risk-warning-13-06-2018/ • Smith, C. (2019). HS2 plans to reduce ground risk cost described as “carnage”. Retrieved from https://www.geplus.co.uk/news/hs2-plans-to- reduce-ground-risk-cost-described-as-carnage-28-01-2019 • Willingham, R. (2019, 9 December 2019). Melbourne Metro Tunnel project grinds to a halt amid dispute over deadlines and costs. Retrieved from https://www.abc.net.au/news/2019-12-09/melbourne-metro-tunnel-project-grinds-to-halt-amid-dispute/11779986 53
  • 55. 0 2 4 6 8 10 12 Bad (<50) Poor (50-75) Fair (75-85) Good (85-95) Excellent (95-105) Good (105-115) Fair (115-125) Poor (125-150) Bad (>150) Number of Predictions AccuracyofPrediction(%) Driven Steel Pile Total Capacity (kN) Base Capacity (kN) Shaft Capacity (kN) Under estimate Over estimate Shaft - 88% Poor / Bad Base - 63% Poor / Bad Total - 88% Poor / Bad 55
  • 56. 0 1 2 3 4 5 6 7 8 9 10 Bad (<50) Poor (50-75) Fair (75-85) Good (85-95) Excellent (95-105) Good (105-115) Fair (115-125) Poor (125-150) Bad (>150) Number of Predictions AccuracyofPrediction(%) Jet Grouted Pile Total Pile Capacity (kN) Base Capacity (kN) Shaft Capacity (kN) Over estimate Shaft - 69% Poor / Bad Base - 81% Poor / Bad Total - 81% Poor / Bad Under estimate 56
  • 57. 0 2 4 6 8 10 12 14 16 Bad (<50) Poor (50-75) Fair (75-85) Good (85-95) Excellent (95-105) Good (105-115) Fair (115-125) Poor (125-150) Bad (>150) Number of Predictions AccuracyofPrediction(%) Embankment Collapse Height Muar Embankment Prediction Competition MIT Embankment Prediction Competition Non-conservative Conservative 60% Poor / Bad – majority on the conservative side of prediction 57