The Little River Turnpike walkway pedestrian improvement project was completed on June 29, 2020. The project increases pedestrian safety from Columbia Rd. to Mayhunt Ct. with 2580 linear feet of 5-foot wide concrete sidewalk.
Dead Run Force Main Rehabilitation ProjectFairfax County
The document summarizes a project to rehabilitate an existing 14-inch cast iron force main in Fairfax County, Virginia. The project involved lining the 2,700 linear feet of force main with cured-in-place pipe lining, installing storm culverts under five driveways to improve drainage, replacing an existing concrete culvert, restoring ditches and driveways, and adding safety measures. The project was substantially completed in September 2016 to repair the 60-year old force main running from Dead Run Drive to Dolly Madison Boulevard.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
Silverbrook Road and Southrun Road Intersection improvements project was substantially completed on April 12, 2021. The overall project scope was to the increase in pedestrian safety along Silverbrook Road and its intersection with Southrun Road. The new pedestrian walkway consisted of 83 lineal feet of 5-foot-wide concrete sidewalk along with 224 lineal feet of 6-foot-wide asphalt walking path. Additionally, the Right Turn from Silverbrook Road onto Southrun Road was improved and lengthened. Along with the access improvements upgrades were made to the storm drain system and minor re-alignments of waterlines.
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County
Old Courthouse Rd. walkway improvements were substantially completed on July 15, 2020. 1,300 linear feet of concrete sidewalk and other related improvements are included in this project.
Workhouse Arts Foundation Cross-County TrailFairfax County
The document summarizes a project to construct pedestrian and bicycle trails at the Workhouse Arts Foundation Center in Fairfax County, VA. The project included building 2,850 feet of asphalt trail and 450 feet of stone dust trail, along with curb cuts, signage, and other safety improvements. The project was completed on June 26, 2018 and involved the Department of Transportation, Utilities Design and Construction Division, and other county teams and branches. Photos document the construction process and final results of the new trails.
Silverbrook Road at Monacan Road Walkway ProjectFairfax County
The scope of this project included 460 feet of five-foot wide concrete sidewalk and curb and gutter along the west side of Silverbrook Road south of Monacan Road connecting to the existing sidewalk. The improvements provide a new pedestrian access to the sidewalk, trails, signage, pavement markings and two new curb ramps along with a crosswalk at the Silverbrook Road and Monacan Road intersection.
The document summarizes plans to widen Route 1 between Mary's Way and Annapolis Way in Virginia from four to six lanes. The project will include widening the road, constructing a new bridge over Marumsco Creek, adding sidewalks and trails, and undergrounding utilities. Construction is scheduled to be completed in six stages by November 2019. The project aims to introduce the construction team, present the scope of work, construction elements, timeline, and contact information for questions.
Dead Run Force Main Rehabilitation ProjectFairfax County
The document summarizes a project to rehabilitate an existing 14-inch cast iron force main in Fairfax County, Virginia. The project involved lining the 2,700 linear feet of force main with cured-in-place pipe lining, installing storm culverts under five driveways to improve drainage, replacing an existing concrete culvert, restoring ditches and driveways, and adding safety measures. The project was substantially completed in September 2016 to repair the 60-year old force main running from Dead Run Drive to Dolly Madison Boulevard.
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
Westmoreland Street bike lanes project was substantially completed on April 12, 2021. The project scope was the extension of road bike lanes along both sides of Westmoreland Street north of Rosemont Drive toward Old Chesterbrook Road. Works on the project included roadway widening, approximately 400 feet long concrete variable width sidewalk, curb and gutters, driveway entrances, bus stop loading pad, milling and paving, pavement marking and signs.
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
Silverbrook Road and Southrun Road Intersection improvements project was substantially completed on April 12, 2021. The overall project scope was to the increase in pedestrian safety along Silverbrook Road and its intersection with Southrun Road. The new pedestrian walkway consisted of 83 lineal feet of 5-foot-wide concrete sidewalk along with 224 lineal feet of 6-foot-wide asphalt walking path. Additionally, the Right Turn from Silverbrook Road onto Southrun Road was improved and lengthened. Along with the access improvements upgrades were made to the storm drain system and minor re-alignments of waterlines.
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County
Old Courthouse Rd. walkway improvements were substantially completed on July 15, 2020. 1,300 linear feet of concrete sidewalk and other related improvements are included in this project.
Workhouse Arts Foundation Cross-County TrailFairfax County
The document summarizes a project to construct pedestrian and bicycle trails at the Workhouse Arts Foundation Center in Fairfax County, VA. The project included building 2,850 feet of asphalt trail and 450 feet of stone dust trail, along with curb cuts, signage, and other safety improvements. The project was completed on June 26, 2018 and involved the Department of Transportation, Utilities Design and Construction Division, and other county teams and branches. Photos document the construction process and final results of the new trails.
Silverbrook Road at Monacan Road Walkway ProjectFairfax County
The scope of this project included 460 feet of five-foot wide concrete sidewalk and curb and gutter along the west side of Silverbrook Road south of Monacan Road connecting to the existing sidewalk. The improvements provide a new pedestrian access to the sidewalk, trails, signage, pavement markings and two new curb ramps along with a crosswalk at the Silverbrook Road and Monacan Road intersection.
The document summarizes plans to widen Route 1 between Mary's Way and Annapolis Way in Virginia from four to six lanes. The project will include widening the road, constructing a new bridge over Marumsco Creek, adding sidewalks and trails, and undergrounding utilities. Construction is scheduled to be completed in six stages by November 2019. The project aims to introduce the construction team, present the scope of work, construction elements, timeline, and contact information for questions.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...Fairfax County
The Fairfax County Department of Public Works and Environmental Services completed five bus stop safety and accessibility improvement projects in September 2015. The projects installed concrete pads, sidewalks, and other items to improve pedestrian safety at bus stops located on Lawyers Road, Coffer Woods Road, Old Keene Mill Road, and Telegraph Road. The document provides details on the project locations, teams, and contact information for additional questions.
Kennedy Station Design Update Meeting PresentationCrosstown TO
Metrolinx invites you to attend a meeting for information on the preliminary station and stop designs for the Eglinton Crosstown project. Specifically, the station design concept for the Crosstown Kennedy Station, including the mobility hub study, will be presented. As well, the surface stop design concepts and surface alignment from Bermondsey to Kennedy will be available for review.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
This document summarizes a spot improvement project at the intersection of North Beauregard Street and North Chambliss Street in Fairfax County, VA. The project constructed a new concrete island, curb, sidewalk, and pedestrian flashing beacon to reduce the crossing distance and improve pedestrian safety. Construction was completed in October 2021 by contractor M&F Concrete. The project was managed by Fairfax County Department of Transportation and the Construction Division.
Braddock Road Walkway - Carlbern Drive to Clubside LaneFairfax County
The scope of this pedestrian safety improvement project included construction of approximately 1,150 linear feet of 5-foot wide concrete sidewalk, storm drainpipes and structures, curb cut ramps, mill and overlay, and pavement marking and signage.
Great Falls St. Sidewalk Improvements December 2020Fairfax County
In Fairfax County, from North West Street to Osborn Street, the project provides pedestrian access improvements including installation of concrete sidewalk, curb and gutter, curb ramps, driveway reconstruction, gravity retaining walls, drainage improvements, watermain relocation, paving, pavement marking and signage.
Chain Bridge Road Walkway from Niblick Drive to Horse Shoe DriveFairfax County
This document provides details about the Chain Bridge Road Walkway Improvements project in Fairfax County, VA. The project involved constructing approximately 3,300 feet of new 5-foot wide sidewalk along the east side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive. It also included stormwater drainage, curb and gutter works, and signal modifications. The project was substantially completed on September 24, 2019.
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleFairfax County
The Sunrise Valley Dr. Sidewalk Improvements – River Birch Road to Legacy Circle project included construction of approximately 387 linear feet of concrete sidewalk along Sunrise Valley Drive connecting River Birch Road to Legacy Circle, a new concrete bus pad and 5 pedestrian accessible ramps.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
Old Keene Mill Road Walkway at Carrleigh PkwyFairfax County
The Old Keene Mill Road Walkway at Carrleigh Parkway included the construction of pedestrian access improvements along westbound Old Keene Mill Road at Carrleigh Parkway to include full-depth asphalt pavement on a turn lane extension, sidewalk , curb and gutter, pavement mill and overlay, pavement markings and signing, and drainage improvements.
8th Street Bridge Community Information Session November 19th, 2015City Brandon
Presentation provided by City of Brandon Administration at the 8th Street Bridge Community Information Session held November 19th, 2015, at Brandon City Hall.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Elm Street at Dolley Madison Boulevard Pedestrian ImprovementsFairfax County
This document provides details about pedestrian improvement projects completed at Elm Street and Dolley Madison Boulevard in Fairfax County, VA. The project included construction of brick walkways, curb ramps, handrails, signs, and pavement markings. A project team led by the Department of Transportation and Utilities Design and Construction Division completed the work, which was finished in July 2016. Before and after photos show the upgrades to the brick walkway. Contact information is provided for additional details.
Pohick Road - South Run Road Walkway Pedestrian ImprovementsFairfax County
The scope of this project included construction of concrete sidewalk, curb and gutter, curb-cut ramps, concrete bus pads, pavement mill and overlay, pavement marking and signings, drainage improvements, watermain relocation, guardrail system improvements, and pedestrian signals.
Braddock Rd. and Roberts Rd. Intersection and Sidewalk ImprovementsFairfax County
The project included an additional right turning lane, a segment of 5-foot-wide concrete sidewalk and curb and gutter approximately 340 feet in length, storm sewer installations and storm drainage facility.
Intersection Sight Distance Improvement: Old Dominion Drive at Bellview RoadFairfax County
The Old Dominion Drive at Bellview Road Project in Fairfax County, VA was substantially completed in December 2015. The project involved removing existing embankments and trees along Old Dominion Drive to improve sight distance at the intersection, and installing concrete pipes to improve runoff. The project team removed embankments and vegetation, installed reinforced concrete pipes, implemented soil stabilization techniques, and graded ditches to complete the work.
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook TrailFairfax County
Description:
HMSAMS-Innovation Center to Arrowbrook Trail was substantially completed on March 1, 2021. The project included the construction of 600 linear feet of 10-foot-wide asphalt trail, nine trail lights, a HAWK signal across Sunrise Valley Drive, pavement mill and overlay, pavement markings and signage, pedestrian ramp and sidewalk.
Project Overview:
Project Delivery: Annual Project
Contract: Unit Price
This document provides information about an open house held by Metrolinx to discuss plans for the Finch West Light Rail Transit project in Toronto. It summarizes that Metrolinx was created to improve regional transportation and reduce traffic congestion, which costs the Toronto region billions annually. The proposed Finch West LRT would be an 11km line extending west from Finch Station, serving over 46,000 daily passengers with 18 stops. It discusses benefits like increased capacity and reliability over buses. The project is fully funded and approved, with construction from 2017-2021 and service beginning in late 2021.
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
The Cinder Bed Road Realignment Project in Fairfax County, VA was substantially completed in July 2017. The project realigned a portion of Cinder Bed Road and installed a triple box culvert to improve traffic flow and access to the Newington DVS Maintenance Facility. It also included stream restoration, construction of a sidewalk, trail, and drainage improvements. The project team consisted of members from the Department of Transportation, Land Acquisition Division, and Utilities Design and Construction Division.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...Fairfax County
The Fairfax County Department of Public Works and Environmental Services completed five bus stop safety and accessibility improvement projects in September 2015. The projects installed concrete pads, sidewalks, and other items to improve pedestrian safety at bus stops located on Lawyers Road, Coffer Woods Road, Old Keene Mill Road, and Telegraph Road. The document provides details on the project locations, teams, and contact information for additional questions.
Kennedy Station Design Update Meeting PresentationCrosstown TO
Metrolinx invites you to attend a meeting for information on the preliminary station and stop designs for the Eglinton Crosstown project. Specifically, the station design concept for the Crosstown Kennedy Station, including the mobility hub study, will be presented. As well, the surface stop design concepts and surface alignment from Bermondsey to Kennedy will be available for review.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
This document summarizes a spot improvement project at the intersection of North Beauregard Street and North Chambliss Street in Fairfax County, VA. The project constructed a new concrete island, curb, sidewalk, and pedestrian flashing beacon to reduce the crossing distance and improve pedestrian safety. Construction was completed in October 2021 by contractor M&F Concrete. The project was managed by Fairfax County Department of Transportation and the Construction Division.
Braddock Road Walkway - Carlbern Drive to Clubside LaneFairfax County
The scope of this pedestrian safety improvement project included construction of approximately 1,150 linear feet of 5-foot wide concrete sidewalk, storm drainpipes and structures, curb cut ramps, mill and overlay, and pavement marking and signage.
Great Falls St. Sidewalk Improvements December 2020Fairfax County
In Fairfax County, from North West Street to Osborn Street, the project provides pedestrian access improvements including installation of concrete sidewalk, curb and gutter, curb ramps, driveway reconstruction, gravity retaining walls, drainage improvements, watermain relocation, paving, pavement marking and signage.
Chain Bridge Road Walkway from Niblick Drive to Horse Shoe DriveFairfax County
This document provides details about the Chain Bridge Road Walkway Improvements project in Fairfax County, VA. The project involved constructing approximately 3,300 feet of new 5-foot wide sidewalk along the east side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive. It also included stormwater drainage, curb and gutter works, and signal modifications. The project was substantially completed on September 24, 2019.
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleFairfax County
The Sunrise Valley Dr. Sidewalk Improvements – River Birch Road to Legacy Circle project included construction of approximately 387 linear feet of concrete sidewalk along Sunrise Valley Drive connecting River Birch Road to Legacy Circle, a new concrete bus pad and 5 pedestrian accessible ramps.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
Old Keene Mill Road Walkway at Carrleigh PkwyFairfax County
The Old Keene Mill Road Walkway at Carrleigh Parkway included the construction of pedestrian access improvements along westbound Old Keene Mill Road at Carrleigh Parkway to include full-depth asphalt pavement on a turn lane extension, sidewalk , curb and gutter, pavement mill and overlay, pavement markings and signing, and drainage improvements.
8th Street Bridge Community Information Session November 19th, 2015City Brandon
Presentation provided by City of Brandon Administration at the 8th Street Bridge Community Information Session held November 19th, 2015, at Brandon City Hall.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Elm Street at Dolley Madison Boulevard Pedestrian ImprovementsFairfax County
This document provides details about pedestrian improvement projects completed at Elm Street and Dolley Madison Boulevard in Fairfax County, VA. The project included construction of brick walkways, curb ramps, handrails, signs, and pavement markings. A project team led by the Department of Transportation and Utilities Design and Construction Division completed the work, which was finished in July 2016. Before and after photos show the upgrades to the brick walkway. Contact information is provided for additional details.
Pohick Road - South Run Road Walkway Pedestrian ImprovementsFairfax County
The scope of this project included construction of concrete sidewalk, curb and gutter, curb-cut ramps, concrete bus pads, pavement mill and overlay, pavement marking and signings, drainage improvements, watermain relocation, guardrail system improvements, and pedestrian signals.
Braddock Rd. and Roberts Rd. Intersection and Sidewalk ImprovementsFairfax County
The project included an additional right turning lane, a segment of 5-foot-wide concrete sidewalk and curb and gutter approximately 340 feet in length, storm sewer installations and storm drainage facility.
Intersection Sight Distance Improvement: Old Dominion Drive at Bellview RoadFairfax County
The Old Dominion Drive at Bellview Road Project in Fairfax County, VA was substantially completed in December 2015. The project involved removing existing embankments and trees along Old Dominion Drive to improve sight distance at the intersection, and installing concrete pipes to improve runoff. The project team removed embankments and vegetation, installed reinforced concrete pipes, implemented soil stabilization techniques, and graded ditches to complete the work.
Substantial Completion - HMSAMS-Innovation Center to Arrowbrook TrailFairfax County
Description:
HMSAMS-Innovation Center to Arrowbrook Trail was substantially completed on March 1, 2021. The project included the construction of 600 linear feet of 10-foot-wide asphalt trail, nine trail lights, a HAWK signal across Sunrise Valley Drive, pavement mill and overlay, pavement markings and signage, pedestrian ramp and sidewalk.
Project Overview:
Project Delivery: Annual Project
Contract: Unit Price
This document provides information about an open house held by Metrolinx to discuss plans for the Finch West Light Rail Transit project in Toronto. It summarizes that Metrolinx was created to improve regional transportation and reduce traffic congestion, which costs the Toronto region billions annually. The proposed Finch West LRT would be an 11km line extending west from Finch Station, serving over 46,000 daily passengers with 18 stops. It discusses benefits like increased capacity and reliability over buses. The project is fully funded and approved, with construction from 2017-2021 and service beginning in late 2021.
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
Fairfax County walkway construction of 1,600 linear feet of concrete sidewalk, curb ramps, curb and gutter, retaining wall, pavement markings and signage, drainage improvements and utility adjustments.
The Cinder Bed Road Realignment Project in Fairfax County, VA was substantially completed in July 2017. The project realigned a portion of Cinder Bed Road and installed a triple box culvert to improve traffic flow and access to the Newington DVS Maintenance Facility. It also included stream restoration, construction of a sidewalk, trail, and drainage improvements. The project team consisted of members from the Department of Transportation, Land Acquisition Division, and Utilities Design and Construction Division.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
Substantial Completion: Lorton Road ProjectFairfax County
The Lorton Road Improvement Project in Fairfax County, VA widened portions of Lorton Road, Furnace Road, and Workhouse Road to 4 lanes with medians, turn lanes, bike lanes, and stormwater management features. The $30 million project was completed in March 2017 and included constructing new bridges over Giles Run and the Greenway Trail. The project improved safety and traffic flow along 2.5 miles of roadway.
Scotts Run Trail to McLean Metro Station January 2021Fairfax County
The project consists of the design and construction of a half-mile long, eight-foot-wide asphalt trail connecting Magarity Road to Chain Bridge Road (previously Colshire Meadow Drive) and provides the residential communities safe access to the McLean Metro Station. The project includes two pedestrian bridges (50 feet and 90 feet long) over Scotts Run, stormwater drainage, asphalt paving, trail lighting, handrail, pavement markings and related signage.
The Quander Road Walkway project in Fairfax County, Virginia involved constructing 1,800 feet of sidewalk, curb and gutter, a refuge island with ramps, drainage improvements, and road widening along Quander Road between Emmett Drive and Stokes Lane. The project was completed in June 2021 to provide safer connectivity for schools and neighborhoods. It was delivered using a design-bid-build approach and included relocating utilities, laying concrete, and replacing landscaping.
Hunter Mill Road and Sunrise Valley Drive Pedestrian ImprovementsFairfax County
The project provides pedestrian improvements at the intersection of Hunter Mill Road (Route 674) and Sunrise Valley Drive (Route 6320). Improvements include installing 1,037 linear feet of concrete sidewalk, curb and gutter, concrete sidewalks, curb ramps, refuge island, realigning the southbound right turn lane, and milling and asphalt paving near the intersection. Drainage improvements include installing 1,069 linear feet of storm drain pipes, curb drop inlets, and a Filterra unit.
Guinea Road and Lakepointe Drive Sidewalk and Intersection ImprovementsFairfax County
This project consisted of construction of approximately 800 feet of 5-foot wide concrete sidewalk, curb and gutter, curb ramps, concrete bus pads, and an upgrade of the existing storm water conveyance system along with storm water control features. This project will enhance the safety of pedestrian traffic through the intersection of Guinea Road and Lakepointe Drive.
Lee Highway, U.S. Route 29 Phase III WideningFairfax County
This project consisted of construction of a box culvert extension, concrete sidewalk, asphalt trail, curb and gutter, 24-inch water line relocation, 8,650 feet of additional asphalt pavement, two bio-retention filters, five signalized intersections, and other related items.
Fairfax County Glade Dr. Walkway Improvements August 2020Fairfax County
The document summarizes a sidewalk improvement project along Glade Drive in Fairfax County, Virginia. The project involved constructing approximately 1,050 feet of concrete sidewalk, installing curb ramps, curb and gutter, a pedestrian signal, milling and overlaying asphalt, and utility adjustments. It was substantially completed in June 2020. The project aims to improve pedestrian access and safety along Glade Drive between Freetown Drive and Colts Neck Road.
Substantial Completion: Franconia Road SidewalkFairfax County
The Franconia Road Sidewalk project in Fairfax County, VA was completed on April 16, 2017. The project included 870 feet of new concrete sidewalk, curb and gutter, 4 curb ramps, 3 tree box filters, 400 feet of new storm drainage pipe and 9 drainage structures to improve safety, accessibility and link existing sidewalks along Franconia Road. The project was led by the Department of Transportation and Utilities Design and Construction Division.
Newington Forest Ave Walkway from Hooes Road to Treasure Tree CourtFairfax County
The project included construction of pedestrian access improvements on Newington Forest Avenue to include approximately 400 linear feet of five-foot concrete sidewalk, curb ramps, curb and gutter, pedestrian signal, mill and overlay, pavement markings and signage, and drainage improvement.
Lukens Lane Intersection Improvements Phase IIFairfax County
Lukens Lane Intersection Improvements - Phase II project provides pedestrian improvements at the intersection of Richmond Highway and Lukens Lane. The improvements include, but are not limited to, new concrete median and island, CG-12 curb ramps, modification to curb and gutter returns, sidewalk, reconstruction of entrances, mill and overlay, pavement marking, signage, signal modification and fire hydrant relocation.
Chichester Lane at Lismore Lane Walkway extended a five-foot wide concrete walkway 91 linear feet. The improvements include construction of sidewalk, adjusting an existing sanitary manhole to grade, and applying topsoil, seed and matting to disturbed areas.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Lanier St. Bicycle and Pedestrian ConnectionFairfax County
This bicycle/pedestrian improvement project included construction of approximately 170 linear feet of six-foot asphalt walkway connecting Lanier Street to Carrico Drive and associated drainage improvements.
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...Fairfax County
The document summarizes a pedestrian intersection improvement project in Fairfax County, VA. The project involved constructing 500 feet of curb and gutter, handicap ramps, updated pedestrian signals, asphalt paving, and a stormwater BMP facility at the intersections of Highland St, Backlick Rd, and Amherst Ave. The project scope and timeline, including pre-construction, construction, and post-construction phases are described. Contact information is provided for additional details.
This project involved constructing a raised median with a cut through, curb ramp, pedestrian crosswalk, milling and overlay, pavement markings and signage along Chain Bridge Road in Fairfax County, VA. The project was federally funded and aimed to provide safer access to a bus stop and improve pedestrian access at an intersection. Key members of the project team included the Department of Transportation, Utilities Design and Construction Division, a project inspector consultant, and the Land Survey Branch. The project was substantially completed on October 26, 2018.
The Vesper Street Shared Use project was substantially completed within budget on January 24, 2019. This project provided of a 10’ft wide asphalt shared use path approximately 2030’ft in length from the end of Vesper Street to the intersection of Leesburg Pike and the Spring Hill Metro Station. The project includes a 90’ft pedestrian bridge over Courthouse Spring Branch, storm water drainage, asphalt paving, light poles, handrails, guardrails bollards, pavement markings and related signage.
The Sunset Hills Road Walkway project in Fairfax County, VA was substantially completed on May 2, 2016. The project included constructing 1,570 feet of pedestrian walkway and curb ramps, installing 136 feet of stormwater pipe and structures, resurfacing 303 feet of the W&OD trail, and adding a rest area with bench and water fountain and two bus pads for future bus service. The project was led by the Department of Transportation and Utilities Design and Construction Division of Fairfax County.
Similar to Fairfax County Little River Turnpike Walkway August 2020 (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
A review on techniques and modelling methodologies used for checking electrom...nooriasukmaningtyas
The proper function of the integrated circuit (IC) in an inhibiting electromagnetic environment has always been a serious concern throughout the decades of revolution in the world of electronics, from disjunct devices to today’s integrated circuit technology, where billions of transistors are combined on a single chip. The automotive industry and smart vehicles in particular, are confronting design issues such as being prone to electromagnetic interference (EMI). Electronic control devices calculate incorrect outputs because of EMI and sensors give misleading values which can prove fatal in case of automotives. In this paper, the authors have non exhaustively tried to review research work concerned with the investigation of EMI in ICs and prediction of this EMI using various modelling methodologies and measurement setups.
Fairfax County Little River Turnpike Walkway August 2020
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Little River Turnpike Walkway
Task Order No. 13
Contract No. CN19304163
Project No. 5G25-060-045
Mason District
Tax Map No. 71-2, 72-1
August 17, 2020
2. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
3. Project Details
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Description:
Little River Turnpike Walkway pedestrian improvement project was substantially completed on
June 29, 2020. The project provides increased pedestrian safety along Little River Turnpike with
installation of approximately 2,580 Lineal Feet of 5-Foot wide concrete sidewalk from Columbia
Road to Mayhunt Court. Additionally, 7 Commercial entrances were upgraded to current VDOT
standards along with upgrades to the storm drain system and minor re-alignments of waterlines.
• Contractor
• Finley Asphalt & Sealing, Inc.
• Fairfax County
• Department of Transportation – Francesco Lauretti
• Department of Transportation Utilities– Tan Nquyen
• Construction Manager, UDCD – Michael J. Stevens
• Project Inspector, UDCD – Hammad Hashmi
• Land Survey Branch, UDCD – Cody Harp-Taylor and Kevin Lugo-Nunez
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
4. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Mason District, Tax Map No. 71-2, 72-1
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
Installation of Concrete Curb and Gutter Forms
6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
Installation of Concrete Ramp & Curb and Gutter
7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
Milling and Removal of Existing Asphalt Pavement
8. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
Installation of New Asphalt Pavement
9. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
10. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
11. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
12. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
13. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
14. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Little River Turnpike Walkway – Columbia Road to Mayhunt Court
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Irene Haske, Public Information Officer
703-324-5500, TTY 711
Irene.Haske@fairfaxcounty.gov