Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
1. Route 1 Widening
PARDON OUR DUST BRIEFING
April 27th, 2016 – 6:30 PM
Freedom High School Auditorium
15201 Neabsco Mills Road
Woodbridge, VA 22191
2. Tonight's Objectives
• Introduction of the Construction Team
• Present Project Scope of Work
– Widen U.S. 1 from four to six lanes between Mary's Way and
Annapolis Way
– Enhance access to the Woodbridge VRE kiss-and-ride facility
– Construct new Route 1 bridge at Marumsco Creek
– Improvements to Route 1 and Occoquan Road to improve traffic
operations
– Construct a ten-foot shared-use path and six-foot sidewalk
– Underground utilities along Route 1 (duct bank work has been
completed)
• Construction Elements
– Sequence of Construction
– Detours
• Answer your Questions
2
3. Project Team
• Virginia Department of Transportation
• Prince William County
• Contractor: Fort Myer Construction
Corporation
3
4. ROUTE 1 WIDENING
Construction Team & Contact Information
VDOT Construction Management contact information:
• Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer
– (703) 259-2947 chan.basnayake@vdot.virginia.gov
• Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager
– (703) 259- 2769 oj.jamilla@vdot.virginia.gov
• Mike Hamp – Project Inspector
– (571) 722-6919 michael.hamp@vdot.virginia.gov
• Michelle Stubenbordt – Project Records Manager/Sr. Inspector
– (571) 289-8003 michelle.stubenbordt@vdot.virginia.gov
• Kathy Poole, P.E., CCM – Office Engineer
– (571) 319-6509 kathy.poole@vdot.virginia.gov
Contractor: Fort Myer Construction Corporation contact information:
• Ardie Kalantar – Project Manager
– (202) 497-5377 akalantar@fortmyer.com
• Fabio Fernandes – Project Engineer
– (202) 345-0695 ffernandes@fortmyer.com
• Rick Fernandes – Vice President
– (202) 437-4353 rfernandes@fortmyer.com
Field office location (open during normal business hours):
– 13408 Jefferson Davis Highway, Woodbridge, VA 22191
– Phone Number: TBD
4
Project updates will be posted on VDOT’s website at:
http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp
5. Project Timeline
• Contract Executed: March 25th, 2016
• Notice to Proceed Date: April 11th, 2016
• Start of Construction: April 12th, 2016
• Final Completion: November 29th, 2019
5
Contract Value = $43,246,647.92
11. 11
• Place Advance Warning Signs
• Clearing and Grubbing
• Building Demolitions
• Remove Existing Raised Concrete Medians
• Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound
Side of Route 1
• Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage
From Station 49+25 to Station 67+25
• Construct Temporary Pavement Wedge for Driveway Access
Construction Stage 1: thru Aug 2016
12. 12
Construction Stage 2-1: Sept 2016 – Dec 2016
• Install Temporary Signals at Occoquan Road Intersection
• Reroute Pedestrian Traffic to the Northbound Side of Route 1
• Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous
Stage
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to
Station 64+00 and Easy Street Connector
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage
From Station 64+00 to Station 67+75
MarysWay
13. 13
Construction Stage 2-2 and 2-3: Jan 2017 – June 2017MarysWay
• Close Easy Street South and Detour Traffic to Easy Street Connector and
Construct Easy Street South Entrance
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage
From Station 39+50 to Station 49+50
• Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)
14. 14
Construction Stage 3-1: July 2017 – Oct 2017
• Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2
• Construct SB Proposed Pavement from Station 42+50 to Station 51+25
• Construct Second Stage of the Bridge over Marumsco Creek
• Install Temporary Signals at Annapolis Way and Occoquan Road
• Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road
• Relocate Waterlines and Sanitary Sewers
MarysWay
15. 15
Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018
• Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75
and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00
• Construct WB Lanes of Annapolis Way
• Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3-
3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes)
• Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd
• Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A)
• Reroute Route 123 Traffic to Detour (Stage 3-4B)
• Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B)
Route 123 Detour
16. 16
Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018
• Install Temporary Signals at Annapolis Way and Route 123 Intersections
• Shift Route 123 Traffic to Newly Constructed Route 123 Pavement
• Detour Annapolis Way Traffic and Construct Remaining Annapolis Way
• Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3)
• Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to
Bridge and Pavement Placed in Previous Stages
• Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and
NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4)
US Route 1
17. 17
Construction Stage 4-5: Jan 2019 – Apr 2019
• Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from
Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00
• Construct Third Stage of the Bridge over Marumsco Creek
18. 18
Construction Stages 5 and 6: May 2019 – Nov 2019
STAGE 5
• Construct NB Proposed Pavement from Station 38+25 to Station 42+50
• Install Temporary Signal at Dawson Beach Road
• Construct Dawson Beach Road Intersection
• Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00
• Shift NB Traffic to Newly Constructed NB Lanes
• Construct Raised Median
STAGE 6
• Place Final Pavement Surface and Pavement Markings
19. Lane Closure Restrictions
19
Lane Closures will only be permitted:
Day Hours
Monday - Thursday
9:30 AM – 3:00 PM
10:00 PM – 5:00 AM
Friday
9:30 AM – 12:00 PM
10:00 PM – 9:00 AM
Saturday - Sunday 10:00 PM – 8:00 AM
Sunday - Monday 10:00 PM – 5:00 AM
Two-way Traffic Will Be Maintained At All Times!
20. Night Work
20
• Installation of Traffic Control Devices
• Traffic Shifts
• Pavement Milling and Overlays
• Pavement Striping
• Utility Relocations
• Lane Closures
22. Pedestrian Detours & Bus Stop Coordination
22
• There Will be Several Pedestrian Detours
• Pedestrian Detour Signs Will be Provided
• All Bus Stops Will be Maintained During All Phases of
Construction
• Bus Stops May be Temporarily Relocated But Will Remain ADA
Compliant
23. Kiss and Ride
23
• Facilities Will Remain Open
During Construction and
After Construction