SlideShare a Scribd company logo
1 of 24
Route 1 Widening
PARDON OUR DUST BRIEFING
April 27th, 2016 – 6:30 PM
Freedom High School Auditorium
15201 Neabsco Mills Road
Woodbridge, VA 22191
Tonight's Objectives
• Introduction of the Construction Team
• Present Project Scope of Work
– Widen U.S. 1 from four to six lanes between Mary's Way and
Annapolis Way
– Enhance access to the Woodbridge VRE kiss-and-ride facility
– Construct new Route 1 bridge at Marumsco Creek
– Improvements to Route 1 and Occoquan Road to improve traffic
operations
– Construct a ten-foot shared-use path and six-foot sidewalk
– Underground utilities along Route 1 (duct bank work has been
completed)
• Construction Elements
– Sequence of Construction
– Detours
• Answer your Questions
2
Project Team
• Virginia Department of Transportation
• Prince William County
• Contractor: Fort Myer Construction
Corporation
3
ROUTE 1 WIDENING
Construction Team & Contact Information
VDOT Construction Management contact information:
• Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer
– (703) 259-2947 chan.basnayake@vdot.virginia.gov
• Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager
– (703) 259- 2769 oj.jamilla@vdot.virginia.gov
• Mike Hamp – Project Inspector
– (571) 722-6919 michael.hamp@vdot.virginia.gov
• Michelle Stubenbordt – Project Records Manager/Sr. Inspector
– (571) 289-8003 michelle.stubenbordt@vdot.virginia.gov
• Kathy Poole, P.E., CCM – Office Engineer
– (571) 319-6509 kathy.poole@vdot.virginia.gov
Contractor: Fort Myer Construction Corporation contact information:
• Ardie Kalantar – Project Manager
– (202) 497-5377 akalantar@fortmyer.com
• Fabio Fernandes – Project Engineer
– (202) 345-0695 ffernandes@fortmyer.com
• Rick Fernandes – Vice President
– (202) 437-4353 rfernandes@fortmyer.com
Field office location (open during normal business hours):
– 13408 Jefferson Davis Highway, Woodbridge, VA 22191
– Phone Number: TBD
4
Project updates will be posted on VDOT’s website at:
http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp
Project Timeline
• Contract Executed: March 25th, 2016
• Notice to Proceed Date: April 11th, 2016
• Start of Construction: April 12th, 2016
• Final Completion: November 29th, 2019
5
Contract Value = $43,246,647.92
6
Project Location
Project 0123-076-004, C501
7
Project Information
Phase 2 Future
Route 123 Interchange
Marumsco Creek
Bridge
Project Field Office
8
Project Information
Project Field Office
VRE Station
Marumsco Creek
Belmont Bay
I-95 Interchange
CSXT RailroadKiss And Ride
9
Project Information
Project Field Office
Ornamental Fence
Retaining Walls
10
Typical Section
11
• Place Advance Warning Signs
• Clearing and Grubbing
• Building Demolitions
• Remove Existing Raised Concrete Medians
• Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound
Side of Route 1
• Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage
From Station 49+25 to Station 67+25
• Construct Temporary Pavement Wedge for Driveway Access
Construction Stage 1: thru Aug 2016
12
Construction Stage 2-1: Sept 2016 – Dec 2016
• Install Temporary Signals at Occoquan Road Intersection
• Reroute Pedestrian Traffic to the Northbound Side of Route 1
• Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous
Stage
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to
Station 64+00 and Easy Street Connector
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage
From Station 64+00 to Station 67+75
MarysWay
13
Construction Stage 2-2 and 2-3: Jan 2017 – June 2017MarysWay
• Close Easy Street South and Detour Traffic to Easy Street Connector and
Construct Easy Street South Entrance
• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage
From Station 39+50 to Station 49+50
• Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)
14
Construction Stage 3-1: July 2017 – Oct 2017
• Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2
• Construct SB Proposed Pavement from Station 42+50 to Station 51+25
• Construct Second Stage of the Bridge over Marumsco Creek
• Install Temporary Signals at Annapolis Way and Occoquan Road
• Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road
• Relocate Waterlines and Sanitary Sewers
MarysWay
15
Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018
• Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75
and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00
• Construct WB Lanes of Annapolis Way
• Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3-
3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes)
• Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd
• Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A)
• Reroute Route 123 Traffic to Detour (Stage 3-4B)
• Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B)
Route 123 Detour
16
Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018
• Install Temporary Signals at Annapolis Way and Route 123 Intersections
• Shift Route 123 Traffic to Newly Constructed Route 123 Pavement
• Detour Annapolis Way Traffic and Construct Remaining Annapolis Way
• Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3)
• Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to
Bridge and Pavement Placed in Previous Stages
• Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and
NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4)
US Route 1
17
Construction Stage 4-5: Jan 2019 – Apr 2019
• Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from
Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00
• Construct Third Stage of the Bridge over Marumsco Creek
18
Construction Stages 5 and 6: May 2019 – Nov 2019
STAGE 5
• Construct NB Proposed Pavement from Station 38+25 to Station 42+50
• Install Temporary Signal at Dawson Beach Road
• Construct Dawson Beach Road Intersection
• Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00
• Shift NB Traffic to Newly Constructed NB Lanes
• Construct Raised Median
STAGE 6
• Place Final Pavement Surface and Pavement Markings
Lane Closure Restrictions
19
Lane Closures will only be permitted:
Day Hours
Monday - Thursday
9:30 AM – 3:00 PM
10:00 PM – 5:00 AM
Friday
9:30 AM – 12:00 PM
10:00 PM – 9:00 AM
Saturday - Sunday 10:00 PM – 8:00 AM
Sunday - Monday 10:00 PM – 5:00 AM
Two-way Traffic Will Be Maintained At All Times!
Night Work
20
• Installation of Traffic Control Devices
• Traffic Shifts
• Pavement Milling and Overlays
• Pavement Striping
• Utility Relocations
• Lane Closures
21
Annapolis Way Detour – Stage 4
Pedestrian Detours & Bus Stop Coordination
22
• There Will be Several Pedestrian Detours
• Pedestrian Detour Signs Will be Provided
• All Bus Stops Will be Maintained During All Phases of
Construction
• Bus Stops May be Temporarily Relocated But Will Remain ADA
Compliant
Kiss and Ride
23
• Facilities Will Remain Open
During Construction and
After Construction
Question & Answer Session
24

More Related Content

What's hot

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk Fairfax County
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road WalkwayFairfax County
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...Fairfax County
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open HouseCrosstown TO
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationCrosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
North Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementNorth Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 

What's hot (20)

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road Walkway
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...
Fairfax County Park Authority, Turkeycock Run Stream Valley - Pinecrest Golf ...
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
North Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementNorth Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot Improvement
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 

Similar to Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Silverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectSilverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectFairfax County
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern WorksCrosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016Pont Samuel-De Champlain Bridge
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Crosstown TO
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCrosstown TO
 
Comox Valley Community Information Meeting presentation Sept. 16, 2014
Comox Valley Community Information Meeting presentation Sept. 16, 2014Comox Valley Community Information Meeting presentation Sept. 16, 2014
Comox Valley Community Information Meeting presentation Sept. 16, 2014Island Health
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 

Similar to Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016 (20)

Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Silverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectSilverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway Project
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Comox Valley Community Information Meeting presentation Sept. 16, 2014
Comox Valley Community Information Meeting presentation Sept. 16, 2014Comox Valley Community Information Meeting presentation Sept. 16, 2014
Comox Valley Community Information Meeting presentation Sept. 16, 2014
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 

More from VDOT Northern Virginia

2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow BriefingVDOT Northern Virginia
 
2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow BriefingVDOT Northern Virginia
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016VDOT Northern Virginia
 

More from VDOT Northern Virginia (7)

2019-2020 NWS Winter Outlook
2019-2020 NWS Winter Outlook2019-2020 NWS Winter Outlook
2019-2020 NWS Winter Outlook
 
2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing
 
2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing2018 National Weather Service - VDOT Annual Snow Briefing
2018 National Weather Service - VDOT Annual Snow Briefing
 
2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing
 
Pikes Branch Stream Restoration
Pikes Branch Stream RestorationPikes Branch Stream Restoration
Pikes Branch Stream Restoration
 
2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016
 

Recently uploaded

Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urgesnarwatsonia7
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...ResolutionFoundation
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...Garima Khatri
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...narwatsonia7
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.pptsilvialandin2
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 

Recently uploaded (20)

Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual UrgesCall Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
Call Girl Benson Town - Phone No 7001305949 For Ultimate Sexual Urges
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...Powering Britain: Can we decarbonise electricity without disadvantaging poore...
Powering Britain: Can we decarbonise electricity without disadvantaging poore...
 
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
VIP Mumbai Call Girls Andheri West Just Call 9920874524 with A/C Room Cash on...
 
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
Premium Call Girls Btm Layout - 7001305949 Escorts Service with Real Photos a...
 
13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt13875446-Ballistic Missile Trajectories.ppt
13875446-Ballistic Missile Trajectories.ppt
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 

Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

  • 1. Route 1 Widening PARDON OUR DUST BRIEFING April 27th, 2016 – 6:30 PM Freedom High School Auditorium 15201 Neabsco Mills Road Woodbridge, VA 22191
  • 2. Tonight's Objectives • Introduction of the Construction Team • Present Project Scope of Work – Widen U.S. 1 from four to six lanes between Mary's Way and Annapolis Way – Enhance access to the Woodbridge VRE kiss-and-ride facility – Construct new Route 1 bridge at Marumsco Creek – Improvements to Route 1 and Occoquan Road to improve traffic operations – Construct a ten-foot shared-use path and six-foot sidewalk – Underground utilities along Route 1 (duct bank work has been completed) • Construction Elements – Sequence of Construction – Detours • Answer your Questions 2
  • 3. Project Team • Virginia Department of Transportation • Prince William County • Contractor: Fort Myer Construction Corporation 3
  • 4. ROUTE 1 WIDENING Construction Team & Contact Information VDOT Construction Management contact information: • Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer – (703) 259-2947 chan.basnayake@vdot.virginia.gov • Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager – (703) 259- 2769 oj.jamilla@vdot.virginia.gov • Mike Hamp – Project Inspector – (571) 722-6919 michael.hamp@vdot.virginia.gov • Michelle Stubenbordt – Project Records Manager/Sr. Inspector – (571) 289-8003 michelle.stubenbordt@vdot.virginia.gov • Kathy Poole, P.E., CCM – Office Engineer – (571) 319-6509 kathy.poole@vdot.virginia.gov Contractor: Fort Myer Construction Corporation contact information: • Ardie Kalantar – Project Manager – (202) 497-5377 akalantar@fortmyer.com • Fabio Fernandes – Project Engineer – (202) 345-0695 ffernandes@fortmyer.com • Rick Fernandes – Vice President – (202) 437-4353 rfernandes@fortmyer.com Field office location (open during normal business hours): – 13408 Jefferson Davis Highway, Woodbridge, VA 22191 – Phone Number: TBD 4 Project updates will be posted on VDOT’s website at: http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp
  • 5. Project Timeline • Contract Executed: March 25th, 2016 • Notice to Proceed Date: April 11th, 2016 • Start of Construction: April 12th, 2016 • Final Completion: November 29th, 2019 5 Contract Value = $43,246,647.92
  • 7. 7 Project Information Phase 2 Future Route 123 Interchange Marumsco Creek Bridge Project Field Office
  • 8. 8 Project Information Project Field Office VRE Station Marumsco Creek Belmont Bay I-95 Interchange CSXT RailroadKiss And Ride
  • 9. 9 Project Information Project Field Office Ornamental Fence Retaining Walls
  • 11. 11 • Place Advance Warning Signs • Clearing and Grubbing • Building Demolitions • Remove Existing Raised Concrete Medians • Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound Side of Route 1 • Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage From Station 49+25 to Station 67+25 • Construct Temporary Pavement Wedge for Driveway Access Construction Stage 1: thru Aug 2016
  • 12. 12 Construction Stage 2-1: Sept 2016 – Dec 2016 • Install Temporary Signals at Occoquan Road Intersection • Reroute Pedestrian Traffic to the Northbound Side of Route 1 • Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous Stage • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to Station 64+00 and Easy Street Connector • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 64+00 to Station 67+75 MarysWay
  • 13. 13 Construction Stage 2-2 and 2-3: Jan 2017 – June 2017MarysWay • Close Easy Street South and Detour Traffic to Easy Street Connector and Construct Easy Street South Entrance • Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 39+50 to Station 49+50 • Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)
  • 14. 14 Construction Stage 3-1: July 2017 – Oct 2017 • Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2 • Construct SB Proposed Pavement from Station 42+50 to Station 51+25 • Construct Second Stage of the Bridge over Marumsco Creek • Install Temporary Signals at Annapolis Way and Occoquan Road • Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road • Relocate Waterlines and Sanitary Sewers MarysWay
  • 15. 15 Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018 • Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75 and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00 • Construct WB Lanes of Annapolis Way • Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3- 3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes) • Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd • Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A) • Reroute Route 123 Traffic to Detour (Stage 3-4B) • Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B) Route 123 Detour
  • 16. 16 Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018 • Install Temporary Signals at Annapolis Way and Route 123 Intersections • Shift Route 123 Traffic to Newly Constructed Route 123 Pavement • Detour Annapolis Way Traffic and Construct Remaining Annapolis Way • Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3) • Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to Bridge and Pavement Placed in Previous Stages • Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4) US Route 1
  • 17. 17 Construction Stage 4-5: Jan 2019 – Apr 2019 • Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00 • Construct Third Stage of the Bridge over Marumsco Creek
  • 18. 18 Construction Stages 5 and 6: May 2019 – Nov 2019 STAGE 5 • Construct NB Proposed Pavement from Station 38+25 to Station 42+50 • Install Temporary Signal at Dawson Beach Road • Construct Dawson Beach Road Intersection • Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00 • Shift NB Traffic to Newly Constructed NB Lanes • Construct Raised Median STAGE 6 • Place Final Pavement Surface and Pavement Markings
  • 19. Lane Closure Restrictions 19 Lane Closures will only be permitted: Day Hours Monday - Thursday 9:30 AM – 3:00 PM 10:00 PM – 5:00 AM Friday 9:30 AM – 12:00 PM 10:00 PM – 9:00 AM Saturday - Sunday 10:00 PM – 8:00 AM Sunday - Monday 10:00 PM – 5:00 AM Two-way Traffic Will Be Maintained At All Times!
  • 20. Night Work 20 • Installation of Traffic Control Devices • Traffic Shifts • Pavement Milling and Overlays • Pavement Striping • Utility Relocations • Lane Closures
  • 21. 21 Annapolis Way Detour – Stage 4
  • 22. Pedestrian Detours & Bus Stop Coordination 22 • There Will be Several Pedestrian Detours • Pedestrian Detour Signs Will be Provided • All Bus Stops Will be Maintained During All Phases of Construction • Bus Stops May be Temporarily Relocated But Will Remain ADA Compliant
  • 23. Kiss and Ride 23 • Facilities Will Remain Open During Construction and After Construction
  • 24. Question & Answer Session 24