SlideShare a Scribd company logo
1 of 62
Download to read offline
1
IIT Delhi
Department of Civil Engineering
Airport Runway Construction
Prepared by:- Abdul Habib
Subject: Construction Equipment & Method
Instructor: Pro. A K Jain
2
TABLE OF CONTENTS
 Introduction
 Objectives
 Construction processes of Airport
Runway
 Airport
 Airport History
 Typical Layout of an Airport
 Components of Airport
 Airport Runway
 Runway Configuration
 Runway Orientation
 Factors Affecting Runway Orientation
 Runway Markings
 Runway signs
 Runway Numbering
 Runway Numbers
 Runway Lighting
 Equipment Which Will be used in Airport
Runway Construction
1. Trench Excavation
2. Backfilling Equipment
3. Soil Transport Equipment (Load Tipper Truck)
4. Grader Equipment used for the Grading of soil
5. Dozer Pushing Clay
6. Hydraulic Rock breaker
7. Asphalt paving
8. Bitumen Emulsion Sprayer Equipment
 Runway pavement
 Runway Cleaning
 Runway Tests
 Repair of Airport Runway
 References
3
INTRODUCTION
Airport engineering is the planning, design, construction, and
operation and maintenance of facilities providing for the landing and
takeoff, loading and unloading servicing, maintenance, and storage of
aircraft.
This Engineering encompasses the planning, design, and construction
of terminals, runways, and navigation aids to provide for passenger
and freight service.
An airport is a facility where people connect from ground
transportation to air transportation
In the airport, runway is an area where an aircraft can land and take
off, which may or may not be equipped with any navigational aids or
markings
4
Objectives
The purpose of this presentation is to give an understanding of the Methods,
Plant and Sequence to construct a Runway which will be shown in the next
slide.
This presentation can be used to engage Stakeholders and to get the Site
Teams commitment to the program. Also can be used for Induction Training
and as a way to capture and share knowledge.
5
Construction processes of Airport Runway
Runway Construction
Sequence & Methods
Earthworks
Crushed Aggregate Base Course
Asphalt Paving
Pavement Marking
Cleaning Pavement
Airfield Ground Lights
Glide Path & DVOR
Electrical Substation
Taxi Guidance Signs
Concrete Paving
Milling/Planning Machine
Cable Laying
Directional Drilling
Fencing
Operational Restrictions
Article on Runway Pavement
Pavement Details & Mixes
Concrete, Rebar & Shuttering
Concrete Wall Construction
Culvert & Head Walls
Oil Interceptor
Pump Station
Concrete Mix Design
Compacting Concrete
Safety & Environmental
Emergency Numbers & Response
Dashboard for Monitoring & Reporting HSE
Safety Generally
Personal Protective Equipment
Excavation Safety
Trench Safety
Training
Emergency Response Drill
Safety documents
Environmental Measures
Hazardous Substances Symbols
Water Pollution Prevention
Segregation of Waste
Using Waste Concrete
Contractor Site Facilities
Methods
Checks
Airside Restrictions
Stakeholders Engagement
Contractor Site Facilities
Offices, Stores and etc.
Welfare facilities
Hoarding
Fencing
Dewatering
Wheel Wash
Electricity & Lighting
Asphalt Batching Plant
Concrete Batching Plant
Crushed Aggregating Batching
Quarry & Aggregate Production
Reinforcement Cutting & Bending
Administration
Organogram
Staff Responsibilities Matrix
Staff Directory
Daily Work Record
Quotation Comparison Sheet
Digital Filling System
Quality Assurance
Dashboard For Monitoring &
Reporting QA / QC
Tests
Site Laboratory
Program & Progress
Monitoring
Reporting Progress
Histograms
Resources – Plant & Manpower List
Programs
Miscellaneous
Terminal Building
Air Traffic Control Tower
6
Airport
 A place from which aircraft operate that usually has paved runways
and maintenance facilities and often serves as a terminal.
 A place where aircraft regularly take off and land, passengers.
 An airport is a location where aircraft such as fixed-wing aircraft,
helicopters, and blimps take off and land.
 An airport consists of at least one surface such as runway for a plane
to take off and land, a helipad, or water for takeoff and landings, and
often includes buildings such as control towers, hangers and terminal
buildings.
7
Airport History
 The world’s first airport was built in 1928 at Croydon near London
(England).
 It was the main airport for London till it was closed down in 1959,
after the World War 2.
 It is now open as a visitor center for aviation.
8
Typical Layout of an Airport
9
Components of Airport
An airport has two major components;
1. Airfield
 Runway: used for takeoffs and landings.
 Taxiway
2. Buildings
 Terminal buildings
 Control towers
 Helipads
 Apron
 Aircraft stand
 Parking
10
Airport Runway
Runway is a paved land strip on which landing and
takeoff operations of aircrafts takes place. It can be
grass, or packed dirt, or a hard surface such as asphalt
or concrete.
Special markings are made on the runway to differ it
from the normal roadways. Similarly, after sunset,
specially provided lightings are helped the aircrafts
for safe landing.
Runway can be laid using bitumen or concrete.
11
Cont…
12
RUNWAY CONFIGURATION
According to Federal Aviation Administration (FAA) there are
four common types of runway
Single runway
Parallel runway
Two parallel runways
Two parallel runways with staggered thresholds
Four parallel runways
Open-v runways
Intersecting runways
13
Cont…
 Runway configuration depends on CAPACITY.
14
Runway Orientation
Runway orientation is important in airport planning
Current practice is to layout a runway in the direction of
prevailing wind
It is very important for safe take offs and approaches
The width and sloping of runway also play a role in safe
approaches
15
Factors Affecting Runway Orientation
WIND
Airspace availability
Environmental factors
Obstructions to navigation
Air traffic control visibility
Wind lift hazards
Terrain and consideration
16
Runway Markings
These are provided with different purposes like
1. Runway centerline marking
2. Runway edge stripe
3. Runway numbering
4. Touch down or landing zone marking
5. Threshold marking
 Defines specific height by which aircraft should cross it
6. Two or more parallel runways
17
Cont…
Runway Centerline Marking
1. It is represented by a broken strip running along the entire
length of runway
2. Length of strip should be equal to length of gap or 30m
whichever is higher.
3. Length of strip plus gap shall not be less than 50m and
more than 75m
4. The width of strip shall not be less than 90cm on precision
approach runway and 30cm to 45cm on non-precision
approach runway.
18
Cont…
1. Blast pad: The area marked with yellow chevrons (V
shaped) also referred to overrun areas or stop ways.
• Constructed to reduce the erosion of earth by the jet blast
produced during power up to take off
19
Cont…
Run way Threshold Markings: it consists of pattern of
longitudinal stripes of uniform dimensions placed symmetrically
about the centerline of a runway.
Touch down zone: it is the target area for pilots to stick the wheels
of aircraft on to the runway
20
RUNWAY SIGNS
These runway signs are used for various purposes.
21
RUNWAY NUMBERING
The end of runway is marked with a number that indicates magnetic
azimuth.
East end of East-West runway will be marked 27 (for 270 degree)
and the west end is marked 9 for 90 degree.
Every runway is numbered between 01 and 36 at each end of runway.
Angle between the direction of the centerline of the runway and the
magnetic north.
Or simply, 360° means north, 90° means east, 180° means south and
270° means west
For more than one runway going in the same direction, letters are
added to the end of the number R for right, C for center, and L for
left.
22
Cont…
A runway 16/34 would be (160°=16) pronounced as one six.
The number at the other end of the runway is the opposite
number on the compass and that would be (340° = 34)
pronounced three four.
The difference between 340° and 160° is 180° or put another
way, 34 minus 16 equals 18.
23
RUNWAY NUMBERS
24
Runway Lighting
These lights are used to assist pilot in to identify the
runway
GREEN THRESHOLD LIGHTS: Line the runway
edge
RED LIGHTS : Mark the end of runway
BLUE LIGHTS : Run alongside taxiways
While runways have YELLOW or WHITE lights
marking their edges
25
Cont…
26
Runway Construction and
Construction Equipment Working
on an Airport Runway
27
Runway Construction Sequence & Methods
28
Runway Construction Pavement Details & Mixes
29
Cont…
 Runway Asphalt.
30
Cont…
 Runway Ends Concrete
• APC (Asphalt pavement
concrete)
• HDPE (High Density
Polyethylene)
• CSBC(crushed surfacing
base course)
• SBC(surfacing base
course)
31
Earth works
Subgrade preparation
1. Soil investigation
2. Survey and setting out works
3. Excavation and filling
4. Grading
5. Compaction
Excavation of soil as per required level with an excavator
Damping of excavated soil by dumpers at suitable places
Grading of excavated area
Compaction by rolling
32
Equipment Which Will be
Used in Airport Runway
Construction
33
Cont…
 Trench Excavation
34
Cont…
 Backfilling Equipment
35
Cont…
 Soil Transport Equipment (Load Tipper Truck)
36
Cont…
 Grader Equipment used for the Grading of soil
o Subgrade is to be prepared in layers
o After dumping of soil, dozing is to be done with a dozer
o Grading is to be done with a grader as per the required
slopes and gradients
37
Cont…
o Spreading and compaction clay fill
o Dozer Pushing Clay
38
Cont…
o Dozer Ripping Ground
39
Cont…
o Excavator with Hydraulic Rock breaker
Earthworks
40
Cont…
Compaction
o After grading, rolling is to be done with a roller of 8-10 tons
capacity
o Rolling should be done at OMC(optimize moisture content) of the
soil
o There should be at least 6 passes (1 plain+2 low vibration +2 high
vibration +1 plain pass)
o Rolling should be started from outer edge of the pavement and
should proceed towards center
o There should be 1/3 overlap in the previous pass
o The compaction should be at least 98%
41
Cont…
o CABC (Crushed aggregate base course ): CABC is produced by
the accurate proportioning and blending of four agg. Sizes and
water using agg. Stabilizer batching plant, after verification that the
sub base layer is within the specified tolerances the surveyors
establish string lines with support pins at 10m centers.
o The mixed agg. Base course is delivered by tipper trucks to the job
site and tipped into the pavers hopper.
o Generally 6 to 7 trucks are required, the material is applied in
layers not exceeding 150mm compacted thickness
o The agg. Base course is spread using tracked pavers fitted with
automatic screed control to the required width, thickness, profile,
camber and cross fall.
42
Cont…
For Crushed aggregate used for base course a crush plant is
required
43
Cont…
Spreading & Compaction CABC ( Crushed aggregate base course )
44
Asphalt paving
Asphalt pavers: The asphalt paver is a self-propelled
formless laydown machine with a floating screed.
45
Cont…
Prime Coat Site Trials: prior to starting paving all the
materials are pre-tested in and a site trial is curried out to
familiarize the crew with the equipment and characteristics
of the particular asphalt mix and to ensure that the
workmanship as will as the material complies with the
specification requirements.
The polymer modified bitumen asphalt mix is laid with two
trucks paver equipped with extending screed tamper and
vibrator and conveyer.
46
Bitumen Emulsion Sprayer Equipment
Bituminous Prime Coat shall consist of supplying and applying
bituminous material to a previously prepared and approved base
course in accordance with the Specification to ensure a bond
between this surface and the overlying course.
47
Cont…
Paving methodology
o Prior to paving, the GSB surface should be cleaned of roots, grass,
stones etc.
o GSB surface should be made slightly moist and should be rolled
for 2 passes
o After the paver has been positioned properly, paving should be
started
o Rolling should be done completely prior to setting of concrete.
The pattern of rolling should be same as that of subgrade
48
Cont…
o The pavers operate using an automatic screed control which
controls the screed height using the string line or the
matching shoe as a level reference.
o The un-compacted asphalt level behind the paver is checked
by pulling a sting lone between the longitudinal string lines
at the 10m pin location and taking dip measurements using a
tape measure.
49
Cont…
o Level control is maintained by two string lines as a great
reference system for the lead paver and matching shoe and
one string line for the following paver.
50
Cont…
Runway Asphalt Pavement Line and Level
o String line used for level and line reference
51
Cont…
o Runway Asphalt Pavement
52
Cont…
R A P -4 Pavers working together
53
Cont…
o The asphalt after compaction reduces in thickness by
approximately 20% dot the jointing and laying the
sequence across the runway is design to insure that the
longitudinal joints are staggered by 300mm between
layers.
o Free edges that will form joints are cut back by 100mm,
the level tolerance is +6mm and the smoothness
tolerance is a max 6mm with a 3m long straight edge.
54
Cont…
o Cutting Joint
55
Cont…
o Average output is 4 to 5 loads per hour, that is equal to
120tons/hour.
56
Runway pavement
 Marking
o Pavement marking to runway using an emulsion paint.
57
Runway Cleaning
Cleaning surface with rotating water jets
o High pressure spinning water jets are used to remove rubber
from runways that builds up as result of planes landing.
58
Runway Tests
Test for Skid Resistance
o Using the Douglas Mu-Meter Continues friction
measuring equipment
59
Cont…
Test for smoothness using Rolling Straight Edge
60
Repair of Airport Runway
After the construction of airport runway, and other structures
(Buildings, Towers, and etc.) regular maintenance is required
for the service life those structures. And the following
recommendations have to be followed.
1. Airport structures must be safe as much as possible from
deteriorations (cracks, deterioration of clear cover and
etc.)
2. Cracks maintenance has to done regularly.
3. After seeing a deteriorated place the maintenance has to
be done on time.
61
Thank you
62
References
• Airport Planning and Design
• Runway Contraction Project
• Field Guide for the Airport Pavement Maintenance
Recommendation tool for ACRP Report 159
• Fast and Permanent repair for airport structures
• Google Images
• https://www.scopus.com

More Related Content

What's hot

Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneNIKHIL PAKWANNE
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Airport planning
Airport planning Airport planning
Airport planning Sonali99999
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Factors influence site selection of an airport
Factors influence site selection of an airportFactors influence site selection of an airport
Factors influence site selection of an airportMaddelaSiddhardha
 
Airport component & layout seminar report
Airport component & layout seminar reportAirport component & layout seminar report
Airport component & layout seminar reportvikram malviya
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airportHarshit P Jain
 
1.introduction
1.introduction1.introduction
1.introductionMani Vel
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport EngineeringArbaz Kazi
 
Airport engineering
Airport engineeringAirport engineering
Airport engineeringsaibabu48
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2RAMPRASAD KUMAWAT
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNNiranjan Varma
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bayssrinivas2036
 
Runway orientation
Runway orientationRunway orientation
Runway orientationjagadish108
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineeringAbhishekChavan63
 

What's hot (20)

Airport runway By Nikhil Pakwanne
Airport runway By Nikhil PakwanneAirport runway By Nikhil Pakwanne
Airport runway By Nikhil Pakwanne
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Airport planning
Airport planning Airport planning
Airport planning
 
Airport Engineering
Airport Engineering Airport Engineering
Airport Engineering
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Airport engineering PART-1
Airport engineering PART-1 Airport engineering PART-1
Airport engineering PART-1
 
Factors influence site selection of an airport
Factors influence site selection of an airportFactors influence site selection of an airport
Factors influence site selection of an airport
 
Airport component & layout seminar report
Airport component & layout seminar reportAirport component & layout seminar report
Airport component & layout seminar report
 
Design and planning of airport
Design and planning of airportDesign and planning of airport
Design and planning of airport
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
1.introduction
1.introduction1.introduction
1.introduction
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Airport engineering
Airport engineeringAirport engineering
Airport engineering
 
Factors in Airport site selection PART-2
Factors in Airport site selection PART-2Factors in Airport site selection PART-2
Factors in Airport site selection PART-2
 
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
10-Runway Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
Airport marking
Airport markingAirport marking
Airport marking
 
AIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGNAIRPORT PLANNING AND DESIGN
AIRPORT PLANNING AND DESIGN
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 
Runway orientation
Runway orientationRunway orientation
Runway orientation
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineering
 

Similar to Airport Runway Construction Methods & Equipment

Runway orientation
Runway orientationRunway orientation
Runway orientationrehan5c
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANNiranjan Varma
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptxAnujyadav514462
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdfSaqib Imran
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport markingIsmailQubaisMotiya
 
Compartive study of surface heliport and elevated heliport
Compartive study of surface heliport and elevated heliportCompartive study of surface heliport and elevated heliport
Compartive study of surface heliport and elevated heliportJayakrishnan Jayarajan
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unitT.Naga Anusha
 
Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiwayAsok999
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristicssrinivas2036
 
Road way condition survey presentation final
Road way condition survey presentation finalRoad way condition survey presentation final
Road way condition survey presentation finalStone Rayhan
 
Terminal Design
Terminal DesignTerminal Design
Terminal DesignMal Mai
 
airports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxairports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxNeha Kajulkar
 
airports-140217060642-phpapp01 .pptx
airports-140217060642-phpapp01     .pptxairports-140217060642-phpapp01     .pptx
airports-140217060642-phpapp01 .pptxcuhp21rdtt12
 

Similar to Airport Runway Construction Methods & Equipment (20)

Runway orientation
Runway orientationRunway orientation
Runway orientation
 
AIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJANAIRPORT PLANNING AND DESIGN BY NIRANJAN
AIRPORT PLANNING AND DESIGN BY NIRANJAN
 
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptxAIRPORT PAVEMENT -  CONSTRUCTION & REPAIR.pptx
AIRPORT PAVEMENT - CONSTRUCTION & REPAIR.pptx
 
Airport
AirportAirport
Airport
 
Airport layout
Airport layoutAirport layout
Airport layout
 
Airport engineering
Airport engineering Airport engineering
Airport engineering
 
Airport & railways engineering ce467 pdf
Airport & railways engineering   ce467 pdfAirport & railways engineering   ce467 pdf
Airport & railways engineering ce467 pdf
 
Airports
AirportsAirports
Airports
 
Airport capacity and airport marking
Airport capacity and airport markingAirport capacity and airport marking
Airport capacity and airport marking
 
Compartive study of surface heliport and elevated heliport
Compartive study of surface heliport and elevated heliportCompartive study of surface heliport and elevated heliport
Compartive study of surface heliport and elevated heliport
 
Airfield ground lighting (AGL)
Airfield ground lighting (AGL)Airfield ground lighting (AGL)
Airfield ground lighting (AGL)
 
Airport presentation 5th unit
Airport presentation 5th unitAirport presentation 5th unit
Airport presentation 5th unit
 
Design elements of airport taxiway
Design elements of airport taxiwayDesign elements of airport taxiway
Design elements of airport taxiway
 
Airport.pptx
Airport.pptxAirport.pptx
Airport.pptx
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Road way condition survey presentation final
Road way condition survey presentation finalRoad way condition survey presentation final
Road way condition survey presentation final
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
 
airports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptxairports-140217060642-phpapp01.pptx
airports-140217060642-phpapp01.pptx
 
airports-140217060642-phpapp01 .pptx
airports-140217060642-phpapp01     .pptxairports-140217060642-phpapp01     .pptx
airports-140217060642-phpapp01 .pptx
 
Airpot design
Airpot designAirpot design
Airpot design
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Airport Runway Construction Methods & Equipment

  • 1. 1 IIT Delhi Department of Civil Engineering Airport Runway Construction Prepared by:- Abdul Habib Subject: Construction Equipment & Method Instructor: Pro. A K Jain
  • 2. 2 TABLE OF CONTENTS  Introduction  Objectives  Construction processes of Airport Runway  Airport  Airport History  Typical Layout of an Airport  Components of Airport  Airport Runway  Runway Configuration  Runway Orientation  Factors Affecting Runway Orientation  Runway Markings  Runway signs  Runway Numbering  Runway Numbers  Runway Lighting  Equipment Which Will be used in Airport Runway Construction 1. Trench Excavation 2. Backfilling Equipment 3. Soil Transport Equipment (Load Tipper Truck) 4. Grader Equipment used for the Grading of soil 5. Dozer Pushing Clay 6. Hydraulic Rock breaker 7. Asphalt paving 8. Bitumen Emulsion Sprayer Equipment  Runway pavement  Runway Cleaning  Runway Tests  Repair of Airport Runway  References
  • 3. 3 INTRODUCTION Airport engineering is the planning, design, construction, and operation and maintenance of facilities providing for the landing and takeoff, loading and unloading servicing, maintenance, and storage of aircraft. This Engineering encompasses the planning, design, and construction of terminals, runways, and navigation aids to provide for passenger and freight service. An airport is a facility where people connect from ground transportation to air transportation In the airport, runway is an area where an aircraft can land and take off, which may or may not be equipped with any navigational aids or markings
  • 4. 4 Objectives The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Runway which will be shown in the next slide. This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the program. Also can be used for Induction Training and as a way to capture and share knowledge.
  • 5. 5 Construction processes of Airport Runway Runway Construction Sequence & Methods Earthworks Crushed Aggregate Base Course Asphalt Paving Pavement Marking Cleaning Pavement Airfield Ground Lights Glide Path & DVOR Electrical Substation Taxi Guidance Signs Concrete Paving Milling/Planning Machine Cable Laying Directional Drilling Fencing Operational Restrictions Article on Runway Pavement Pavement Details & Mixes Concrete, Rebar & Shuttering Concrete Wall Construction Culvert & Head Walls Oil Interceptor Pump Station Concrete Mix Design Compacting Concrete Safety & Environmental Emergency Numbers & Response Dashboard for Monitoring & Reporting HSE Safety Generally Personal Protective Equipment Excavation Safety Trench Safety Training Emergency Response Drill Safety documents Environmental Measures Hazardous Substances Symbols Water Pollution Prevention Segregation of Waste Using Waste Concrete Contractor Site Facilities Methods Checks Airside Restrictions Stakeholders Engagement Contractor Site Facilities Offices, Stores and etc. Welfare facilities Hoarding Fencing Dewatering Wheel Wash Electricity & Lighting Asphalt Batching Plant Concrete Batching Plant Crushed Aggregating Batching Quarry & Aggregate Production Reinforcement Cutting & Bending Administration Organogram Staff Responsibilities Matrix Staff Directory Daily Work Record Quotation Comparison Sheet Digital Filling System Quality Assurance Dashboard For Monitoring & Reporting QA / QC Tests Site Laboratory Program & Progress Monitoring Reporting Progress Histograms Resources – Plant & Manpower List Programs Miscellaneous Terminal Building Air Traffic Control Tower
  • 6. 6 Airport  A place from which aircraft operate that usually has paved runways and maintenance facilities and often serves as a terminal.  A place where aircraft regularly take off and land, passengers.  An airport is a location where aircraft such as fixed-wing aircraft, helicopters, and blimps take off and land.  An airport consists of at least one surface such as runway for a plane to take off and land, a helipad, or water for takeoff and landings, and often includes buildings such as control towers, hangers and terminal buildings.
  • 7. 7 Airport History  The world’s first airport was built in 1928 at Croydon near London (England).  It was the main airport for London till it was closed down in 1959, after the World War 2.  It is now open as a visitor center for aviation.
  • 8. 8 Typical Layout of an Airport
  • 9. 9 Components of Airport An airport has two major components; 1. Airfield  Runway: used for takeoffs and landings.  Taxiway 2. Buildings  Terminal buildings  Control towers  Helipads  Apron  Aircraft stand  Parking
  • 10. 10 Airport Runway Runway is a paved land strip on which landing and takeoff operations of aircrafts takes place. It can be grass, or packed dirt, or a hard surface such as asphalt or concrete. Special markings are made on the runway to differ it from the normal roadways. Similarly, after sunset, specially provided lightings are helped the aircrafts for safe landing. Runway can be laid using bitumen or concrete.
  • 12. 12 RUNWAY CONFIGURATION According to Federal Aviation Administration (FAA) there are four common types of runway Single runway Parallel runway Two parallel runways Two parallel runways with staggered thresholds Four parallel runways Open-v runways Intersecting runways
  • 13. 13 Cont…  Runway configuration depends on CAPACITY.
  • 14. 14 Runway Orientation Runway orientation is important in airport planning Current practice is to layout a runway in the direction of prevailing wind It is very important for safe take offs and approaches The width and sloping of runway also play a role in safe approaches
  • 15. 15 Factors Affecting Runway Orientation WIND Airspace availability Environmental factors Obstructions to navigation Air traffic control visibility Wind lift hazards Terrain and consideration
  • 16. 16 Runway Markings These are provided with different purposes like 1. Runway centerline marking 2. Runway edge stripe 3. Runway numbering 4. Touch down or landing zone marking 5. Threshold marking  Defines specific height by which aircraft should cross it 6. Two or more parallel runways
  • 17. 17 Cont… Runway Centerline Marking 1. It is represented by a broken strip running along the entire length of runway 2. Length of strip should be equal to length of gap or 30m whichever is higher. 3. Length of strip plus gap shall not be less than 50m and more than 75m 4. The width of strip shall not be less than 90cm on precision approach runway and 30cm to 45cm on non-precision approach runway.
  • 18. 18 Cont… 1. Blast pad: The area marked with yellow chevrons (V shaped) also referred to overrun areas or stop ways. • Constructed to reduce the erosion of earth by the jet blast produced during power up to take off
  • 19. 19 Cont… Run way Threshold Markings: it consists of pattern of longitudinal stripes of uniform dimensions placed symmetrically about the centerline of a runway. Touch down zone: it is the target area for pilots to stick the wheels of aircraft on to the runway
  • 20. 20 RUNWAY SIGNS These runway signs are used for various purposes.
  • 21. 21 RUNWAY NUMBERING The end of runway is marked with a number that indicates magnetic azimuth. East end of East-West runway will be marked 27 (for 270 degree) and the west end is marked 9 for 90 degree. Every runway is numbered between 01 and 36 at each end of runway. Angle between the direction of the centerline of the runway and the magnetic north. Or simply, 360° means north, 90° means east, 180° means south and 270° means west For more than one runway going in the same direction, letters are added to the end of the number R for right, C for center, and L for left.
  • 22. 22 Cont… A runway 16/34 would be (160°=16) pronounced as one six. The number at the other end of the runway is the opposite number on the compass and that would be (340° = 34) pronounced three four. The difference between 340° and 160° is 180° or put another way, 34 minus 16 equals 18.
  • 24. 24 Runway Lighting These lights are used to assist pilot in to identify the runway GREEN THRESHOLD LIGHTS: Line the runway edge RED LIGHTS : Mark the end of runway BLUE LIGHTS : Run alongside taxiways While runways have YELLOW or WHITE lights marking their edges
  • 26. 26 Runway Construction and Construction Equipment Working on an Airport Runway
  • 30. 30 Cont…  Runway Ends Concrete • APC (Asphalt pavement concrete) • HDPE (High Density Polyethylene) • CSBC(crushed surfacing base course) • SBC(surfacing base course)
  • 31. 31 Earth works Subgrade preparation 1. Soil investigation 2. Survey and setting out works 3. Excavation and filling 4. Grading 5. Compaction Excavation of soil as per required level with an excavator Damping of excavated soil by dumpers at suitable places Grading of excavated area Compaction by rolling
  • 32. 32 Equipment Which Will be Used in Airport Runway Construction
  • 35. 35 Cont…  Soil Transport Equipment (Load Tipper Truck)
  • 36. 36 Cont…  Grader Equipment used for the Grading of soil o Subgrade is to be prepared in layers o After dumping of soil, dozing is to be done with a dozer o Grading is to be done with a grader as per the required slopes and gradients
  • 37. 37 Cont… o Spreading and compaction clay fill o Dozer Pushing Clay
  • 39. 39 Cont… o Excavator with Hydraulic Rock breaker Earthworks
  • 40. 40 Cont… Compaction o After grading, rolling is to be done with a roller of 8-10 tons capacity o Rolling should be done at OMC(optimize moisture content) of the soil o There should be at least 6 passes (1 plain+2 low vibration +2 high vibration +1 plain pass) o Rolling should be started from outer edge of the pavement and should proceed towards center o There should be 1/3 overlap in the previous pass o The compaction should be at least 98%
  • 41. 41 Cont… o CABC (Crushed aggregate base course ): CABC is produced by the accurate proportioning and blending of four agg. Sizes and water using agg. Stabilizer batching plant, after verification that the sub base layer is within the specified tolerances the surveyors establish string lines with support pins at 10m centers. o The mixed agg. Base course is delivered by tipper trucks to the job site and tipped into the pavers hopper. o Generally 6 to 7 trucks are required, the material is applied in layers not exceeding 150mm compacted thickness o The agg. Base course is spread using tracked pavers fitted with automatic screed control to the required width, thickness, profile, camber and cross fall.
  • 42. 42 Cont… For Crushed aggregate used for base course a crush plant is required
  • 43. 43 Cont… Spreading & Compaction CABC ( Crushed aggregate base course )
  • 44. 44 Asphalt paving Asphalt pavers: The asphalt paver is a self-propelled formless laydown machine with a floating screed.
  • 45. 45 Cont… Prime Coat Site Trials: prior to starting paving all the materials are pre-tested in and a site trial is curried out to familiarize the crew with the equipment and characteristics of the particular asphalt mix and to ensure that the workmanship as will as the material complies with the specification requirements. The polymer modified bitumen asphalt mix is laid with two trucks paver equipped with extending screed tamper and vibrator and conveyer.
  • 46. 46 Bitumen Emulsion Sprayer Equipment Bituminous Prime Coat shall consist of supplying and applying bituminous material to a previously prepared and approved base course in accordance with the Specification to ensure a bond between this surface and the overlying course.
  • 47. 47 Cont… Paving methodology o Prior to paving, the GSB surface should be cleaned of roots, grass, stones etc. o GSB surface should be made slightly moist and should be rolled for 2 passes o After the paver has been positioned properly, paving should be started o Rolling should be done completely prior to setting of concrete. The pattern of rolling should be same as that of subgrade
  • 48. 48 Cont… o The pavers operate using an automatic screed control which controls the screed height using the string line or the matching shoe as a level reference. o The un-compacted asphalt level behind the paver is checked by pulling a sting lone between the longitudinal string lines at the 10m pin location and taking dip measurements using a tape measure.
  • 49. 49 Cont… o Level control is maintained by two string lines as a great reference system for the lead paver and matching shoe and one string line for the following paver.
  • 50. 50 Cont… Runway Asphalt Pavement Line and Level o String line used for level and line reference
  • 52. 52 Cont… R A P -4 Pavers working together
  • 53. 53 Cont… o The asphalt after compaction reduces in thickness by approximately 20% dot the jointing and laying the sequence across the runway is design to insure that the longitudinal joints are staggered by 300mm between layers. o Free edges that will form joints are cut back by 100mm, the level tolerance is +6mm and the smoothness tolerance is a max 6mm with a 3m long straight edge.
  • 55. 55 Cont… o Average output is 4 to 5 loads per hour, that is equal to 120tons/hour.
  • 56. 56 Runway pavement  Marking o Pavement marking to runway using an emulsion paint.
  • 57. 57 Runway Cleaning Cleaning surface with rotating water jets o High pressure spinning water jets are used to remove rubber from runways that builds up as result of planes landing.
  • 58. 58 Runway Tests Test for Skid Resistance o Using the Douglas Mu-Meter Continues friction measuring equipment
  • 59. 59 Cont… Test for smoothness using Rolling Straight Edge
  • 60. 60 Repair of Airport Runway After the construction of airport runway, and other structures (Buildings, Towers, and etc.) regular maintenance is required for the service life those structures. And the following recommendations have to be followed. 1. Airport structures must be safe as much as possible from deteriorations (cracks, deterioration of clear cover and etc.) 2. Cracks maintenance has to done regularly. 3. After seeing a deteriorated place the maintenance has to be done on time.
  • 62. 62 References • Airport Planning and Design • Runway Contraction Project • Field Guide for the Airport Pavement Maintenance Recommendation tool for ACRP Report 159 • Fast and Permanent repair for airport structures • Google Images • https://www.scopus.com