SlideShare a Scribd company logo
Reactor Building
Excavation Work
. Your company has been awarded to carry out the excavation work for the
proposed
Reactor building (RB) near the sea shore. The area is covered with vegetation
and the
suitable dewatering system shall be provided by others as per the requirement.
A brief
description of RB is given below.
RB is a rectangular building conglomerate (Oriented NS) and measuring 80m
along EW
by 100m along NS in plan at FGL (Finished Ground Level). RB Comprises of a
BG-1
situated centrally, flanked between BG-2 ( on North side ) and BG-3 ( on South
side) as
well as BG -4 (on East side ) and BG-5 (on West side). Remaining three utility
buildings BG-6 (Northeast corner), BG-7 (Southeast Corner), BG-8 (Southwest
Corner)
and BG-9 (Northwest corner) are situated along the diagonals of the BG-1
All the buildings are founded on the common base raft with top of raft at two
different
levels of 2m difference BG-1, 2 &3 at lower level and other buildings & BG-
4,5,6,7,8 &9
at higher level.
The mile stone for starting the raft work by other contractor shall be 120 days
from your
start date. The dumping yard is 1000m from the site. The necessary road work
copyright@Amit kumar2
Site demarcation
copyright@Amit kumar3
Top view of buildings after completion of whole
work
9 2 6
5 1 4
8 3 7
E
N
copyright@Amit kumar4
Sectional elevation of site
Fig. Earth pressure diagram
Dry sand
Density=1542kg/cum
Wet sand
Density:1600kg/cum
Cohesive soil
Coefficient of cohesion C=60KN/sq.m
copyright@Amit kumar5
Assumed schedule of work
copyright@Amit kumar6
Assumptions
 Operator is of average skill with operation factor of
0.80.
 Visibility is good
 Factor of machine transmission is fair
 Rolling resistance is 100lb/ton
 Vegetation is present in the form of trees and bushes
at sea shore with light density
 Trees assumed are:
 Hard woods is less than 25%
copyright@Amit kumar7
 Water table is at 4.5m below ground
level(G.L)
 Soil type is changing below water table and
dredge level of 13m
 Upto water table sand is dry hving bank unit
wt = 1542 kg/cum
 Below W.T soil is wet sandy having unit wt.1600 b
kg/cum
 Below dredge level of 13m soil is cohesive having
coefficient of cohesion 60 kN/sq.m
 Percent swell for dry sand = 15%
 For wet sand = 15%
copyright@Amit kumar8
Reconnaissance
 SURVEYING
 Setting the R.L
 Marking the bounderies
 FENCING THE BOUNDERIES
 Placing cones etc.
 PLACING THE SIGNBOARDS
 ARRANGEMENTS FOR NIGHT LIGHTINGS
copyright@Amit kumar9
TIME REQUIRED
 SURVEYING - 2 DAYS
 FENCING - 1 DAY
 SIGNBOARDS AND NIGHT LIGHTINGS - 1 DAY
 PROCURE EQUIPMENT – 1 DAY
copyright@Amit kumar10
Site cleaning
 Crawler dozers equipped with special clearing
blades are excellent machines for land clearing
 Clearing land operations:
 Removing all vegetation above the ground
 Piling-up the removed materials in windrows
direction
 Selling the vegetation and removed trees
Required productivity= area/time = (14000
+8000)/8*3
= 917sq.m /hr
copyright@Amit kumar11
Outside to center cleaning method
copyright@Amit kumar12
Equipment selection
 Production factor for felling trees(power shift
dozer):
Table 1
copyright@Amit kumar13
Considering 165 hp Dozer
copyright@Amit kumar14
copyright@Amit kumar15
Calculation sheet for land cleaning
 Taking 165 hp dozer (Medium dozer) CAT D6R
 Tree count method:
 Time(in min) per acre for
cutting=H(AB+M1N1+M2N2+M3N3+M4N4+DF)
Where,
A=effect of Tree density per acre(<400) on base
time=.70
H=hard wood factor affecting total
time=0.70(Assuming 0 to 25% hardwoods)
B=base time for dozer used per acre depend on size
and capacity for normal efficiency(49.5 mins-
hr)=34.41mins
M=minutes per tree in each diameter range
M1=.70, M2=3.40, M3=6.80, M4=0
copyright@Amit kumar16
 N=no. of trees in each diameter range, from field survey
N1=50, N2=02, N3=0, N4=0
D=0, F=0
 Time in minutes per
acre=0.7(.7*34.41+.7*50+3.4*2+0+0+0)
=46.121 mins
 Increase time by 25% for grubbing operation because
separate provision for grubbing will increase time by
50%
 Time in mins per acre in cutting=1.25*46.121=57.651
mins=60
 Time in mins per acre for piling up the materials in
windrows=B+M1N1+M2N2+M3N3+M4N4+DF
=63.56+.5*50+1*2=90.56 mins
copyright@Amit kumar17
 Total time in clearing=Time in cutting + time in
piling
=area of clearing*(time per acre+
time per acre in
piling)
=5.931(60+114)=1031.994 mins=17.2
hrs
 Days=17.2/8=2.15
=3 days(Matched to schedule)
Under assumed value, so no need to go for other.
 Provide extra time for selling and shifting of trees
etc.copyright@Amit kumar18
Haul road construction
 For 850 metres(Providing WBM)
 Stripping of top soil- 2 days
 Dust and other loose materials are cleaned-1 day
 Spreading coarse aggregates-1day
 Compacting laid aggregates- 0.5 day
 Spreading dry screening-1
 Compacting along with water-1
 Spreading of laterite soil/binder material-1
 Compaction using roller-1
 Allow layer to dry overnight
 Patch the hungry spots, holes ,ruts etc and roll those
spots- 1daycopyright@Amit kumar19
Material requirements for WBM
 The approximate loose quantity of materials
required for 75mm thick WBM grading-2 for base
coarse layer in cum per 10sq.m are(As per IRC):
 a)coarse aggregate size 63 to 45 mm=.91to 1.07
 b)stone screening type-B, 11.2 mm size=.18 to .21
for base course And 0.14 to 0.17 for surface
course layer
 Now quantity of material for total 1000m x 14m
length:
 Coarse aggregate=1.00*14000/10=1400cum
 Stone screening=.2*1400+ .15*1400=490cum
 Binder material=490cumcopyright@Amit kumar20
 Production of roller in compacted cubic yards per
hour=(16.3*W*S*L*efficiency)/n
 Where W=Effective compacted width per roller
pass in feet=7ft.
 S=avg. roller speed in mph=2.5mph(generally for
WBM)
 L=compacted lift thickness in inches=2.953
(75mm)
 N=no. of roller passes required to achieve
required density
copyright@Amit kumar21
Specification of vibratory roller matching with
requirement:
TATA HITACHI BM3
Smooth Drum Vibratory Roller
copyright@Amit kumar22
For base course
•Time taken in spreading of aggregate=1 day
•Production=(16.3*7*2.5*2.953*50/60)/2=350.976ccy/
hr=266.742ccum/hr
•Production in bank cu m/hr=266.742/0.7=381.06b
cum/hr
•Time taken in compaction=1400/381.06=3.674 hrcopyright@Amit kumar23
Steel drum
vibratory roller
Steel drum vibratory roller
doing compaction
copyright@Amit kumar24
For binder course:
•screening compaction(two times dry and wet rolling)
Production=(16.3*7*2.5*2.953*50/60)/4=175.488ccy/hr
=133.371cum/hr
•Production in bank cum/hr =133.371/0.83=160.61b cum/hr
•Time taken in compaction=490/160.61=3.051 hr=0.5 day
Time taken to compact screening=2x3.051=6.102hrs=1 day
•Binder material(laterite soil in two layers) compaction is done
in wet
Time=6.1hrs=1day
copyright@Amit kumar25
After 10 working days from the
start of construction of WBM
road
copyright@Amit kumar26
Sheet piling
 Sheet piles are normally used to retain earth.
 Sheet pile used: section
900 mm
300
mm
• By considering 30% extra depth of embedment (for safety)
•Depth of embedment of sheet pile=20m
copyright@Amit kumar27
Determination of depth of
embedment
 Submerged unit wt.=15.696-9.81=5.886kn/sq.m=¥
 Ka=(1-Sinᶲ)/(1+Sinᶲ)=(1-sin30)/(1+sin30)=.333
 Kp=1/ka=3; K’= Kp - Ka=2.67
 Pa
’=active pressure intensity at the dredge line=1/3
*4*1542 + 1/3 *9*(1600-1000) kg/sq.m
=20.169+17.658=37.827kn/sq.m
 a=depth of point of zero pressure below the dredge
line
i.e., a= Pa
’/(¥K’)=37.827/(5.886*2.67)=2.407m
 q at dredge line=15.127*4+17.658*9=219.43kn/sq.m
 Depth of embedment for the cohesive soil below
dredge line is given as,copyright@Amit kumar28
 So ,∑ Ray1-D(4C-q)(h+ D/2)=0
=>-
30.254*(1.33+.5)+141.264*4+26.487*5.5+45.525(8.5
+ 2.407/3) – D(4*60-219.43)(8.5+ d/2)=0
=>1078.844-175.78D-10.34D2=0 => D=4.789 m
 Provide 30% extra for safety, D=1.3*4.789=6.226m
 Total length of sheet pile at a
point=13+6.226=19.226m
 Provide depth of embedment 20m with steel sheet
pile.
copyright@Amit kumar29
Contd..
 Required sheet piles =
= 166+133+166+110+250+250
= 1075 sheet piles
Estimated duration =20 days
= 1075/20 = 53 piles /day
copyright@Amit kumar30
 Maximum capacity available is 20 piles /day for
20 m depth
 Taking two vibratory pile driver = 40 piles /day
No. of days= 1075/40
= 26 days
• 6 day more than the allocated time period.
copyright@Amit kumar31
Specification of pile driver
LRB 155
copyright@Amit kumar32
Excavation
 Time allocated to excavation work=65
days(excluding holidays)
 Required productivity of excavator=volume to be
excavated/no.of hours allocated
=(volume of excavated earth from site + volume
of excavated earth for haul road preparation)in
cum/time in hrs
=(109440 + 13650)/(65*8)
=236.712b cum/hr =236.712bcum/hr
0.76bcum/blcy
=311.463blcy/hr
copyright@Amit kumar33
 Available excavators: Back hoe, Front shovel
 We have to do excavation below ground level so
we have selected backhoe for our excavation
purpose.
 Method of excavation used is excavating earth
and moving backward.
copyright@Amit kumar34
copyright@Amit kumar35
 Selecting 2.5cy bucket size,
Productivity=277.78bcy/hr
<reqd productivity
 Selecting 3.0 cy bucket size,
 bucket fill factor=100%=1.00(not in percent)
 Efficiency=45min-hr=45/60=.75
 Cycle time=20sec(from table 2)
 Volume correction=1.15
 Hoe productivity=(3600*3*1.00*0.75)/(20*1.150
=352.350bcy/hr
• To dump earth we need hauling equipment
• Select truck of 18.3 cy heaped capacitycopyright@Amit kumar36
Hoe ZAXIS 470H
Brand: Tata Hitachi
copyright@Amit kumar37
Specification of truck:
TATA tipper LPK 2518HD9S Engine 239
flywheel horse power
Struck capacity:12cum-=14.9cuyd
Heaped capacity=18.3 cuyd
copyright@Amit kumar38
No. of buckets required to fill truck
=size of truck/volume of one bucket with
correction for fill
=18.3/3=6.1=6 or 7
copyright@Amit kumar39
Truck cycle time
copyright@Amit kumar40
Calculation for production with 6
buckets
 Production ( 6 buckets and 4 trucks) = (4 x 18 x
60 ) / 8.28 = 522 lcy / hr
 Production ( 6 buckets and 5 trucks) = (18 x 60)/
2 = 540 lcy/hr
copyright@Amit kumar41
Calculation for production with 7
buckets
 Production ( 7 buckets and 4 trucks) = (18.3 x
60)/2.33 = 472 lcy/hr
 Production ( 7 buckets and 3 trucks) = (3 x 18.3x
60)/8.5 = 388 lcy/hr
 Case is time constrained:
so selecting maximum value from both cases
Maximum value case: 6 buckets and 5 trucks
Productivity=540lcy/hr
=540 x 0.87=405 bcy/hr
With 45 min-hr efficiency, P=405 x45/60=353 bcy/hr
= 268b cum/ hr
copyright@Amit kumar42
 Time required for excavation=
volume to be excavated /
productivity
= 123090/268 = 460 hr. = 58
days
copyright@Amit kumar43
Planned schedule:
Activity Duration(days
excluding holidays)
Equipments
Site visit 1
Reconnaissance &
sample collection
1
Planning for work
procedure
1
Procurement of
equipment & human
resources
1
Site cleaning 3 Dozer:D6R model 3306T
Sheet piling 26 Pile driver: LRB 155
Haul road 10 Roller: HITACHI BM3
Excavation 58 Hoe: ZAXIS 470H
Truck :TATA tipper LPK
2518HD9S
Site hand over 1
Total=102copyright@Amit kumar44
THANK
YOU
copyright@Amit kumar45

More Related Content

What's hot

Soil Exploration
Soil ExplorationSoil Exploration
Soil Exploration
Muhammad Faisal
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
Sharmeesh Arvind
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
Japtyesh Singh
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
hlksd
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
Begum Emte Ajom
 
Field density test
Field density testField density test
Field density test
EngrMahmud3
 
Void Ratio Correlations
Void Ratio CorrelationsVoid Ratio Correlations
Void Ratio Correlations
Ali Rehman
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Construction Tech. and Mgmt., VNIT Nagpur
 
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniques
JNTUK
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
Rizwan Khurram
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
Luke D'Arcy
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Muhammad Irfan
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
Shivarajteggi
 
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
BahadarKhan8
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway Construction
Hafizullah Sadat
 
Atterberg
AtterbergAtterberg
Atterberg
Natalie Ulza
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
pradip dangar
 
Trenching machine
Trenching machineTrenching machine
Trenching machine
sravankumarreddy9
 
Atterberg Limit Test
Atterberg Limit Test  Atterberg Limit Test
Atterberg Limit Test
Sanduli Weerasekara
 
CONSOLIDATION.pptx
CONSOLIDATION.pptxCONSOLIDATION.pptx
CONSOLIDATION.pptx
Doctor Sadaf Qasim
 

What's hot (20)

Soil Exploration
Soil ExplorationSoil Exploration
Soil Exploration
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
 
Field density test
Field density testField density test
Field density test
 
Void Ratio Correlations
Void Ratio CorrelationsVoid Ratio Correlations
Void Ratio Correlations
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
 
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniques
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
 
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
Methods to Determine the Immediate or Elastic Settlement (الهبوط الفورى)
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway Construction
 
Atterberg
AtterbergAtterberg
Atterberg
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
 
Trenching machine
Trenching machineTrenching machine
Trenching machine
 
Atterberg Limit Test
Atterberg Limit Test  Atterberg Limit Test
Atterberg Limit Test
 
CONSOLIDATION.pptx
CONSOLIDATION.pptxCONSOLIDATION.pptx
CONSOLIDATION.pptx
 

Viewers also liked

Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
Prabhat chhirolya
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
Anne Allan
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
Anne Allan
 
Structural excavation and backfill
Structural excavation and backfillStructural excavation and backfill
Structural excavation and backfill
mamilli
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1
Anne Allan
 
EXCAVATIONS
EXCAVATIONSEXCAVATIONS
EXCAVATIONS
YAJAIRA CARDENAS
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
Minh Bui Si
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
Bt Lee
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
Minh Bui Si
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
Rohaidah Aida
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
Colleen True
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentation
Anjali Khandelwal
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
Ashish Parihar
 

Viewers also liked (13)

Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Structural excavation and backfill
Structural excavation and backfillStructural excavation and backfill
Structural excavation and backfill
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1
 
EXCAVATIONS
EXCAVATIONSEXCAVATIONS
EXCAVATIONS
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentation
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 

Similar to Excavation work

Cseb
CsebCseb
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA LtdGeosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Sirmoi Wekesa
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Roshan Kumar Patel
 
Manufacturing of fly-ash brick
Manufacturing of fly-ash brickManufacturing of fly-ash brick
Manufacturing of fly-ash brick
Basitali Nevarekar
 
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
RajeshKumar25548
 
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET Journal
 
M.i tank
M.i  tankM.i  tank
M.i tank
beerappa143
 
Memorial Hall- Design Project
Memorial Hall- Design ProjectMemorial Hall- Design Project
Memorial Hall- Design Project
Martha Jennifer
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
Aman Jain
 
Tillage
TillageTillage
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
dhineshkumar002
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
bala506586
 
Casement Type Wind Turbine
Casement Type Wind TurbineCasement Type Wind Turbine
Casement Type Wind Turbine
Kaustubh Khandagale
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
ZIyeeTan
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
ZIyeeTan
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
ZIyeeTan
 
McsfBudget
McsfBudgetMcsfBudget
McsfBudget
Mcsf Projects
 
Influence of Micro Silica and GGBS on mechanical properties on high strength...
Influence of  Micro Silica and GGBS on mechanical properties on high strength...Influence of  Micro Silica and GGBS on mechanical properties on high strength...
Influence of Micro Silica and GGBS on mechanical properties on high strength...
Harish kumar Lekkala
 
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar PradeshSoil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
Nitin Kumar
 
IRJET- Replacement of Sand in Mortar
IRJET- Replacement of Sand in MortarIRJET- Replacement of Sand in Mortar
IRJET- Replacement of Sand in Mortar
IRJET Journal
 

Similar to Excavation work (20)

Cseb
CsebCseb
Cseb
 
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA LtdGeosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
 
Manufacturing of fly-ash brick
Manufacturing of fly-ash brickManufacturing of fly-ash brick
Manufacturing of fly-ash brick
 
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
 
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
 
M.i tank
M.i  tankM.i  tank
M.i tank
 
Memorial Hall- Design Project
Memorial Hall- Design ProjectMemorial Hall- Design Project
Memorial Hall- Design Project
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Tillage
TillageTillage
Tillage
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
Casement Type Wind Turbine
Casement Type Wind TurbineCasement Type Wind Turbine
Casement Type Wind Turbine
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
McsfBudget
McsfBudgetMcsfBudget
McsfBudget
 
Influence of Micro Silica and GGBS on mechanical properties on high strength...
Influence of  Micro Silica and GGBS on mechanical properties on high strength...Influence of  Micro Silica and GGBS on mechanical properties on high strength...
Influence of Micro Silica and GGBS on mechanical properties on high strength...
 
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar PradeshSoil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
Soil Compaction: A case study of Anpara Thermal Power Plant, Uttar Pradesh
 
IRJET- Replacement of Sand in Mortar
IRJET- Replacement of Sand in MortarIRJET- Replacement of Sand in Mortar
IRJET- Replacement of Sand in Mortar
 

Recently uploaded

Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 

Recently uploaded (20)

Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 

Excavation work

  • 2. . Your company has been awarded to carry out the excavation work for the proposed Reactor building (RB) near the sea shore. The area is covered with vegetation and the suitable dewatering system shall be provided by others as per the requirement. A brief description of RB is given below. RB is a rectangular building conglomerate (Oriented NS) and measuring 80m along EW by 100m along NS in plan at FGL (Finished Ground Level). RB Comprises of a BG-1 situated centrally, flanked between BG-2 ( on North side ) and BG-3 ( on South side) as well as BG -4 (on East side ) and BG-5 (on West side). Remaining three utility buildings BG-6 (Northeast corner), BG-7 (Southeast Corner), BG-8 (Southwest Corner) and BG-9 (Northwest corner) are situated along the diagonals of the BG-1 All the buildings are founded on the common base raft with top of raft at two different levels of 2m difference BG-1, 2 &3 at lower level and other buildings & BG- 4,5,6,7,8 &9 at higher level. The mile stone for starting the raft work by other contractor shall be 120 days from your start date. The dumping yard is 1000m from the site. The necessary road work copyright@Amit kumar2
  • 4. Top view of buildings after completion of whole work 9 2 6 5 1 4 8 3 7 E N copyright@Amit kumar4
  • 5. Sectional elevation of site Fig. Earth pressure diagram Dry sand Density=1542kg/cum Wet sand Density:1600kg/cum Cohesive soil Coefficient of cohesion C=60KN/sq.m copyright@Amit kumar5
  • 6. Assumed schedule of work copyright@Amit kumar6
  • 7. Assumptions  Operator is of average skill with operation factor of 0.80.  Visibility is good  Factor of machine transmission is fair  Rolling resistance is 100lb/ton  Vegetation is present in the form of trees and bushes at sea shore with light density  Trees assumed are:  Hard woods is less than 25% copyright@Amit kumar7
  • 8.  Water table is at 4.5m below ground level(G.L)  Soil type is changing below water table and dredge level of 13m  Upto water table sand is dry hving bank unit wt = 1542 kg/cum  Below W.T soil is wet sandy having unit wt.1600 b kg/cum  Below dredge level of 13m soil is cohesive having coefficient of cohesion 60 kN/sq.m  Percent swell for dry sand = 15%  For wet sand = 15% copyright@Amit kumar8
  • 9. Reconnaissance  SURVEYING  Setting the R.L  Marking the bounderies  FENCING THE BOUNDERIES  Placing cones etc.  PLACING THE SIGNBOARDS  ARRANGEMENTS FOR NIGHT LIGHTINGS copyright@Amit kumar9
  • 10. TIME REQUIRED  SURVEYING - 2 DAYS  FENCING - 1 DAY  SIGNBOARDS AND NIGHT LIGHTINGS - 1 DAY  PROCURE EQUIPMENT – 1 DAY copyright@Amit kumar10
  • 11. Site cleaning  Crawler dozers equipped with special clearing blades are excellent machines for land clearing  Clearing land operations:  Removing all vegetation above the ground  Piling-up the removed materials in windrows direction  Selling the vegetation and removed trees Required productivity= area/time = (14000 +8000)/8*3 = 917sq.m /hr copyright@Amit kumar11
  • 12. Outside to center cleaning method copyright@Amit kumar12
  • 13. Equipment selection  Production factor for felling trees(power shift dozer): Table 1 copyright@Amit kumar13
  • 14. Considering 165 hp Dozer copyright@Amit kumar14
  • 16. Calculation sheet for land cleaning  Taking 165 hp dozer (Medium dozer) CAT D6R  Tree count method:  Time(in min) per acre for cutting=H(AB+M1N1+M2N2+M3N3+M4N4+DF) Where, A=effect of Tree density per acre(<400) on base time=.70 H=hard wood factor affecting total time=0.70(Assuming 0 to 25% hardwoods) B=base time for dozer used per acre depend on size and capacity for normal efficiency(49.5 mins- hr)=34.41mins M=minutes per tree in each diameter range M1=.70, M2=3.40, M3=6.80, M4=0 copyright@Amit kumar16
  • 17.  N=no. of trees in each diameter range, from field survey N1=50, N2=02, N3=0, N4=0 D=0, F=0  Time in minutes per acre=0.7(.7*34.41+.7*50+3.4*2+0+0+0) =46.121 mins  Increase time by 25% for grubbing operation because separate provision for grubbing will increase time by 50%  Time in mins per acre in cutting=1.25*46.121=57.651 mins=60  Time in mins per acre for piling up the materials in windrows=B+M1N1+M2N2+M3N3+M4N4+DF =63.56+.5*50+1*2=90.56 mins copyright@Amit kumar17
  • 18.  Total time in clearing=Time in cutting + time in piling =area of clearing*(time per acre+ time per acre in piling) =5.931(60+114)=1031.994 mins=17.2 hrs  Days=17.2/8=2.15 =3 days(Matched to schedule) Under assumed value, so no need to go for other.  Provide extra time for selling and shifting of trees etc.copyright@Amit kumar18
  • 19. Haul road construction  For 850 metres(Providing WBM)  Stripping of top soil- 2 days  Dust and other loose materials are cleaned-1 day  Spreading coarse aggregates-1day  Compacting laid aggregates- 0.5 day  Spreading dry screening-1  Compacting along with water-1  Spreading of laterite soil/binder material-1  Compaction using roller-1  Allow layer to dry overnight  Patch the hungry spots, holes ,ruts etc and roll those spots- 1daycopyright@Amit kumar19
  • 20. Material requirements for WBM  The approximate loose quantity of materials required for 75mm thick WBM grading-2 for base coarse layer in cum per 10sq.m are(As per IRC):  a)coarse aggregate size 63 to 45 mm=.91to 1.07  b)stone screening type-B, 11.2 mm size=.18 to .21 for base course And 0.14 to 0.17 for surface course layer  Now quantity of material for total 1000m x 14m length:  Coarse aggregate=1.00*14000/10=1400cum  Stone screening=.2*1400+ .15*1400=490cum  Binder material=490cumcopyright@Amit kumar20
  • 21.  Production of roller in compacted cubic yards per hour=(16.3*W*S*L*efficiency)/n  Where W=Effective compacted width per roller pass in feet=7ft.  S=avg. roller speed in mph=2.5mph(generally for WBM)  L=compacted lift thickness in inches=2.953 (75mm)  N=no. of roller passes required to achieve required density copyright@Amit kumar21
  • 22. Specification of vibratory roller matching with requirement: TATA HITACHI BM3 Smooth Drum Vibratory Roller copyright@Amit kumar22
  • 23. For base course •Time taken in spreading of aggregate=1 day •Production=(16.3*7*2.5*2.953*50/60)/2=350.976ccy/ hr=266.742ccum/hr •Production in bank cu m/hr=266.742/0.7=381.06b cum/hr •Time taken in compaction=1400/381.06=3.674 hrcopyright@Amit kumar23
  • 24. Steel drum vibratory roller Steel drum vibratory roller doing compaction copyright@Amit kumar24
  • 25. For binder course: •screening compaction(two times dry and wet rolling) Production=(16.3*7*2.5*2.953*50/60)/4=175.488ccy/hr =133.371cum/hr •Production in bank cum/hr =133.371/0.83=160.61b cum/hr •Time taken in compaction=490/160.61=3.051 hr=0.5 day Time taken to compact screening=2x3.051=6.102hrs=1 day •Binder material(laterite soil in two layers) compaction is done in wet Time=6.1hrs=1day copyright@Amit kumar25
  • 26. After 10 working days from the start of construction of WBM road copyright@Amit kumar26
  • 27. Sheet piling  Sheet piles are normally used to retain earth.  Sheet pile used: section 900 mm 300 mm • By considering 30% extra depth of embedment (for safety) •Depth of embedment of sheet pile=20m copyright@Amit kumar27
  • 28. Determination of depth of embedment  Submerged unit wt.=15.696-9.81=5.886kn/sq.m=¥  Ka=(1-Sinᶲ)/(1+Sinᶲ)=(1-sin30)/(1+sin30)=.333  Kp=1/ka=3; K’= Kp - Ka=2.67  Pa ’=active pressure intensity at the dredge line=1/3 *4*1542 + 1/3 *9*(1600-1000) kg/sq.m =20.169+17.658=37.827kn/sq.m  a=depth of point of zero pressure below the dredge line i.e., a= Pa ’/(¥K’)=37.827/(5.886*2.67)=2.407m  q at dredge line=15.127*4+17.658*9=219.43kn/sq.m  Depth of embedment for the cohesive soil below dredge line is given as,copyright@Amit kumar28
  • 29.  So ,∑ Ray1-D(4C-q)(h+ D/2)=0 =>- 30.254*(1.33+.5)+141.264*4+26.487*5.5+45.525(8.5 + 2.407/3) – D(4*60-219.43)(8.5+ d/2)=0 =>1078.844-175.78D-10.34D2=0 => D=4.789 m  Provide 30% extra for safety, D=1.3*4.789=6.226m  Total length of sheet pile at a point=13+6.226=19.226m  Provide depth of embedment 20m with steel sheet pile. copyright@Amit kumar29
  • 30. Contd..  Required sheet piles = = 166+133+166+110+250+250 = 1075 sheet piles Estimated duration =20 days = 1075/20 = 53 piles /day copyright@Amit kumar30
  • 31.  Maximum capacity available is 20 piles /day for 20 m depth  Taking two vibratory pile driver = 40 piles /day No. of days= 1075/40 = 26 days • 6 day more than the allocated time period. copyright@Amit kumar31
  • 32. Specification of pile driver LRB 155 copyright@Amit kumar32
  • 33. Excavation  Time allocated to excavation work=65 days(excluding holidays)  Required productivity of excavator=volume to be excavated/no.of hours allocated =(volume of excavated earth from site + volume of excavated earth for haul road preparation)in cum/time in hrs =(109440 + 13650)/(65*8) =236.712b cum/hr =236.712bcum/hr 0.76bcum/blcy =311.463blcy/hr copyright@Amit kumar33
  • 34.  Available excavators: Back hoe, Front shovel  We have to do excavation below ground level so we have selected backhoe for our excavation purpose.  Method of excavation used is excavating earth and moving backward. copyright@Amit kumar34
  • 36.  Selecting 2.5cy bucket size, Productivity=277.78bcy/hr <reqd productivity  Selecting 3.0 cy bucket size,  bucket fill factor=100%=1.00(not in percent)  Efficiency=45min-hr=45/60=.75  Cycle time=20sec(from table 2)  Volume correction=1.15  Hoe productivity=(3600*3*1.00*0.75)/(20*1.150 =352.350bcy/hr • To dump earth we need hauling equipment • Select truck of 18.3 cy heaped capacitycopyright@Amit kumar36
  • 37. Hoe ZAXIS 470H Brand: Tata Hitachi copyright@Amit kumar37
  • 38. Specification of truck: TATA tipper LPK 2518HD9S Engine 239 flywheel horse power Struck capacity:12cum-=14.9cuyd Heaped capacity=18.3 cuyd copyright@Amit kumar38
  • 39. No. of buckets required to fill truck =size of truck/volume of one bucket with correction for fill =18.3/3=6.1=6 or 7 copyright@Amit kumar39
  • 41. Calculation for production with 6 buckets  Production ( 6 buckets and 4 trucks) = (4 x 18 x 60 ) / 8.28 = 522 lcy / hr  Production ( 6 buckets and 5 trucks) = (18 x 60)/ 2 = 540 lcy/hr copyright@Amit kumar41
  • 42. Calculation for production with 7 buckets  Production ( 7 buckets and 4 trucks) = (18.3 x 60)/2.33 = 472 lcy/hr  Production ( 7 buckets and 3 trucks) = (3 x 18.3x 60)/8.5 = 388 lcy/hr  Case is time constrained: so selecting maximum value from both cases Maximum value case: 6 buckets and 5 trucks Productivity=540lcy/hr =540 x 0.87=405 bcy/hr With 45 min-hr efficiency, P=405 x45/60=353 bcy/hr = 268b cum/ hr copyright@Amit kumar42
  • 43.  Time required for excavation= volume to be excavated / productivity = 123090/268 = 460 hr. = 58 days copyright@Amit kumar43
  • 44. Planned schedule: Activity Duration(days excluding holidays) Equipments Site visit 1 Reconnaissance & sample collection 1 Planning for work procedure 1 Procurement of equipment & human resources 1 Site cleaning 3 Dozer:D6R model 3306T Sheet piling 26 Pile driver: LRB 155 Haul road 10 Roller: HITACHI BM3 Excavation 58 Hoe: ZAXIS 470H Truck :TATA tipper LPK 2518HD9S Site hand over 1 Total=102copyright@Amit kumar44