SlideShare a Scribd company logo
© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Transformer MVA Sizing
Slide 2© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Transformer MVA Sizing
• Based on ANSI C57 and IEC 60076 standards
• Considers multiple cooling stages and transformer
types (3-phase & 1-phase)
• Considers altitude correction factors
• Considers temperature correction factors
• Load variation
• Considers short-circuit impedance requirements
• Use connected load or operating load to size the
transformer
Slide 3© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
MVA Sizing Page
Transformer
MVA Loading
Correction
Factors & Load
Variation
Sizing Results
Section
•Larger
•Required
•Smaller
•Impedance
Short-Circuit
Impedance
limits
Consider
Growth Factor
for Max. MVA
Slide 4© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Temperature Correction
• Ambient temperature in degree Celsius
• For air cooled transformers use the air
ambient temperature
• For water cooled transformers use the water
temperature
• Based on C57.92-1981 and IEC 76-2
Slide 5© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Altitude Correction
• Derate the transformer capacity based on
altitude of the installation
• Derating starts above 1000 m or 3300 ft
• Based on C57.92-1981 and IEC 76-2
1000
meter
1100
meter
900
meter
800
meter
1200
meter
Slide 6© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Load Variation
• Growth Factor
– Allowance for future load growth
• Load Factor
– The ratio of the average load to the peak load
over a designated period of time
– Load Factor = 100 x ( kWi x Ti ) / ( kWp x Tt )%
– Load Factor = 100 x E / ( kWi x Tt )%
Slide 7© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Where:
I = interval of time when the load is non-zero
kWi = load at interval i
Ti = number of hours of interval i
kWp = peak load
Tt = Ton + Toff
Ton = total hours when the load is on
Toff = total hours when the load is off
E = energy (kWh) consumed by load over the
interval
Slide 8© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Short-Circuit Impedance
Size Requirement
• Use Primary Short-Circuit kA and FLA to
Calculate Impedance
• Primary 3-Phase FLA = MVA / (kVLL * 3)
• Primary 1-Phase FLA= MVA / (kVprimary)
• Zcalculated =100*(FLAprimary / ISC_primary)
Slide 9© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Connected or Operating Load
• Connected Load
– Determine the radial load connected to the transformer
secondary
– Can include spare loads for conservative results
• Operating Load
– PowerStation’s load flow program determines the power
flow through the transformer
– Automatically updated in the transformer required MVA
field (load flow study case info page option)
– Can determine loading in radial or looped systems
Slide 10© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Sizing Results and
Automatic Updating
• Sizing results include MVA and % Z for
– Required Size (Actual calculated Size)
– Next Standard Larger Size
– Next Standard Smaller Size
• Automatically Update the calculated rated
MVA, Max MVA and % Z into the Rating
page of the transformer
Slide 11© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Update automatically
when you press these
buttons
Transformer Rating Page
Transformer Rating Page
Transformer MVA Sizing Page
© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Unit Transformer Sizing
Presented by Farrokh Shokooh
Slide 13© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Unit Transformer Sizing
• Based on IEEE C5F-116 Standard
• Optimize unit transformer turn ratio
• Consider system voltage variation
• Consider generation station auxiliary load
• Automatically detect generator, cable
impedance and bus nominal kV
• Generator reactive vs. capacitive plots
• Optimization reports
Slide 14© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Transformer Tap Optimization
Page
Primary / Secondary
Cable Impedance
Optimization
Results Section
Transformer
Impedance
Section System kV
Information
Generator
Information
Auxiliary Load
Information
Slide 15© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Automatic System Parameter
Update
Slide 16© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Primary Fixed Tap Editor
• Use 0.1% Tap Step to obtain best
Optimization results
• Set the maximum/minimum fixed tap range
Slide 17© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
MVAR Delivery Curve
Slide 18© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes
Unit Transformer Tap
Optimization Reports
• Input Data
• Optimal Tap Position
• Transformer Power Input and output at
different system voltage levels (system
voltage variation)
• Generator Power Output at different system
voltage levels
• Generator and System voltage at different
system voltage levels
Slide 19© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes

More Related Content

What's hot

ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
Himmelstern
 
ETAP - Harmonics Analysis
ETAP - Harmonics AnalysisETAP - Harmonics Analysis
ETAP - Harmonics Analysis
Himmelstern
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systems
Himmelstern
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
Himmelstern
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
Himmelstern
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
Himmelstern
 
ETAP - Ac networks
ETAP - Ac networksETAP - Ac networks
ETAP - Ac networks
Himmelstern
 
ETAP - unbalanced load flow
ETAP - unbalanced load flowETAP - unbalanced load flow
ETAP - unbalanced load flow
Himmelstern
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
michaeljmack
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
Himmelstern
 
Lecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptxLecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptx
ssuserb444c3
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
Power System Operation
 
Fault level calculations
Fault level calculationsFault level calculations
Fault level calculations
Shyamkant Vasekar
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
SARAVANAN A
 
Excitation System & capability curve of synchronous generator
Excitation System &  capability curve of synchronous generatorExcitation System &  capability curve of synchronous generator
Excitation System & capability curve of synchronous generator
MANOJ KUMAR MAHARANA
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
Shaik Abdullah Adam
 
Time current curves
Time current curvesTime current curves
Time current curves
Rabah Zaimeddine
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 

What's hot (20)

ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
 
ETAP - Harmonics Analysis
ETAP - Harmonics AnalysisETAP - Harmonics Analysis
ETAP - Harmonics Analysis
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systems
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
 
ETAP - Ac networks
ETAP - Ac networksETAP - Ac networks
ETAP - Ac networks
 
ETAP - unbalanced load flow
ETAP - unbalanced load flowETAP - unbalanced load flow
ETAP - unbalanced load flow
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
 
Lecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptxLecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptx
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Fault level calculations
Fault level calculationsFault level calculations
Fault level calculations
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
Excitation System & capability curve of synchronous generator
Excitation System &  capability curve of synchronous generatorExcitation System &  capability curve of synchronous generator
Excitation System & capability curve of synchronous generator
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 
Time current curves
Time current curvesTime current curves
Time current curves
 
Out of step
Out of stepOut of step
Out of step
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 

Similar to ETAP - Transformer mva sizing

ETAP - ocp - Optimal Capacitor Placement
ETAP -  ocp - Optimal Capacitor PlacementETAP -  ocp - Optimal Capacitor Placement
ETAP - ocp - Optimal Capacitor Placement
Himmelstern
 
ETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & DuschargeETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & Duscharge
Himmelstern
 
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-CircuitETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
Himmelstern
 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesment
Himmelstern
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System Diagram
Himmelstern
 
Shortcircuit-IEC.pdf
Shortcircuit-IEC.pdfShortcircuit-IEC.pdf
Shortcircuit-IEC.pdf
Wilfredo870952
 
ETAP - Cable pulling
ETAP - Cable pullingETAP - Cable pulling
ETAP - Cable pulling
Himmelstern
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
ssusera5c9a31
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
Himmelstern
 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done Right
Himmelstern
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
Himmelstern
 
C18808 elc tech
C18808 elc techC18808 elc tech
C18808 elc techEDWIN S
 
Whats new in Medium Voltage Drives
Whats new in Medium Voltage Drives Whats new in Medium Voltage Drives
Whats new in Medium Voltage Drives
Juan Cordova
 
BASICS+OF+ASM+WITH+VSD.ppt
BASICS+OF+ASM+WITH+VSD.pptBASICS+OF+ASM+WITH+VSD.ppt
BASICS+OF+ASM+WITH+VSD.ppt
KhairulBashar83
 
LV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS InformatikLV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS Informatik
Andreea Solomon
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1
Ray Beebe
 
Design and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiersDesign and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiers
Grace Abraham
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...
Bowman Power
 

Similar to ETAP - Transformer mva sizing (20)

ETAP - ocp - Optimal Capacitor Placement
ETAP -  ocp - Optimal Capacitor PlacementETAP -  ocp - Optimal Capacitor Placement
ETAP - ocp - Optimal Capacitor Placement
 
ETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & DuschargeETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & Duscharge
 
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-CircuitETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesment
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System Diagram
 
Shortcircuit-IEC.pdf
Shortcircuit-IEC.pdfShortcircuit-IEC.pdf
Shortcircuit-IEC.pdf
 
ETAP - Cable pulling
ETAP - Cable pullingETAP - Cable pulling
ETAP - Cable pulling
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done Right
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
 
Arc flash example4
Arc flash example4Arc flash example4
Arc flash example4
 
C18808 elc tech
C18808 elc techC18808 elc tech
C18808 elc tech
 
Mid Year Review
Mid Year ReviewMid Year Review
Mid Year Review
 
Whats new in Medium Voltage Drives
Whats new in Medium Voltage Drives Whats new in Medium Voltage Drives
Whats new in Medium Voltage Drives
 
BASICS+OF+ASM+WITH+VSD.ppt
BASICS+OF+ASM+WITH+VSD.pptBASICS+OF+ASM+WITH+VSD.ppt
BASICS+OF+ASM+WITH+VSD.ppt
 
LV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS InformatikLV 124 & LV 148 Solutions - WKS Informatik
LV 124 & LV 148 Solutions - WKS Informatik
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1
 
Design and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiersDesign and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiers
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...
 

Recently uploaded

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

ETAP - Transformer mva sizing

  • 1. © 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Transformer MVA Sizing
  • 2. Slide 2© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Transformer MVA Sizing • Based on ANSI C57 and IEC 60076 standards • Considers multiple cooling stages and transformer types (3-phase & 1-phase) • Considers altitude correction factors • Considers temperature correction factors • Load variation • Considers short-circuit impedance requirements • Use connected load or operating load to size the transformer
  • 3. Slide 3© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes MVA Sizing Page Transformer MVA Loading Correction Factors & Load Variation Sizing Results Section •Larger •Required •Smaller •Impedance Short-Circuit Impedance limits Consider Growth Factor for Max. MVA
  • 4. Slide 4© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Temperature Correction • Ambient temperature in degree Celsius • For air cooled transformers use the air ambient temperature • For water cooled transformers use the water temperature • Based on C57.92-1981 and IEC 76-2
  • 5. Slide 5© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Altitude Correction • Derate the transformer capacity based on altitude of the installation • Derating starts above 1000 m or 3300 ft • Based on C57.92-1981 and IEC 76-2 1000 meter 1100 meter 900 meter 800 meter 1200 meter
  • 6. Slide 6© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Load Variation • Growth Factor – Allowance for future load growth • Load Factor – The ratio of the average load to the peak load over a designated period of time – Load Factor = 100 x ( kWi x Ti ) / ( kWp x Tt )% – Load Factor = 100 x E / ( kWi x Tt )%
  • 7. Slide 7© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Where: I = interval of time when the load is non-zero kWi = load at interval i Ti = number of hours of interval i kWp = peak load Tt = Ton + Toff Ton = total hours when the load is on Toff = total hours when the load is off E = energy (kWh) consumed by load over the interval
  • 8. Slide 8© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Short-Circuit Impedance Size Requirement • Use Primary Short-Circuit kA and FLA to Calculate Impedance • Primary 3-Phase FLA = MVA / (kVLL * 3) • Primary 1-Phase FLA= MVA / (kVprimary) • Zcalculated =100*(FLAprimary / ISC_primary)
  • 9. Slide 9© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Connected or Operating Load • Connected Load – Determine the radial load connected to the transformer secondary – Can include spare loads for conservative results • Operating Load – PowerStation’s load flow program determines the power flow through the transformer – Automatically updated in the transformer required MVA field (load flow study case info page option) – Can determine loading in radial or looped systems
  • 10. Slide 10© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Sizing Results and Automatic Updating • Sizing results include MVA and % Z for – Required Size (Actual calculated Size) – Next Standard Larger Size – Next Standard Smaller Size • Automatically Update the calculated rated MVA, Max MVA and % Z into the Rating page of the transformer
  • 11. Slide 11© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Update automatically when you press these buttons Transformer Rating Page Transformer Rating Page Transformer MVA Sizing Page
  • 12. © 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Unit Transformer Sizing Presented by Farrokh Shokooh
  • 13. Slide 13© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Unit Transformer Sizing • Based on IEEE C5F-116 Standard • Optimize unit transformer turn ratio • Consider system voltage variation • Consider generation station auxiliary load • Automatically detect generator, cable impedance and bus nominal kV • Generator reactive vs. capacitive plots • Optimization reports
  • 14. Slide 14© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Transformer Tap Optimization Page Primary / Secondary Cable Impedance Optimization Results Section Transformer Impedance Section System kV Information Generator Information Auxiliary Load Information
  • 15. Slide 15© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Automatic System Parameter Update
  • 16. Slide 16© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Primary Fixed Tap Editor • Use 0.1% Tap Step to obtain best Optimization results • Set the maximum/minimum fixed tap range
  • 17. Slide 17© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes MVAR Delivery Curve
  • 18. Slide 18© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes Unit Transformer Tap Optimization Reports • Input Data • Optimal Tap Position • Transformer Power Input and output at different system voltage levels (system voltage variation) • Generator Power Output at different system voltage levels • Generator and System voltage at different system voltage levels
  • 19. Slide 19© 1996-2010 ETAP/Operation Technology, Inc. – ETAP Workshop Notes