Problem of Var Flow in
Power Systems
• Loads and delivery apparatus (e.g., lines
and transformers) are inductive in nature
• Most power systems operate at a lagging
power factor
• Resulting system capacity reduced, system
loss increased and system voltage
decreased
Slide 3© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Purposes of Shunt
Capacitor Applications
• Var support – Primary benefit for
transmission systems and secondary benefit
for distribution systems
• Voltage control – Primary benefit for both
transmission and distribution systems
• System capacity increase – Secondary
benefit for transmission systems and primary
benefit for distribution systems
Slide 4© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Purposes of Shunt
Capacitor Applications
• System power loss reduction – Secondary
benefit for transmission systems and primary
benefit for distribution systems
• Billing charge reduction – Not applied to
transmission systems but a primary benefit
for distribution systems
Slide 5© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
General Process for Placing
Shunt Capacitors
• Determine bank size in kvar
• Determine connection location
• Determine a control method
• Determine a connection type (wye or delta)
Slide 6© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
General Methods for
Capacitor Placement
• Rules of Thumb
• Power Flow
Based
• Optimal
Slide 7© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Optimal Capacitor
Placement in ETAP
• Genetic Algorithm - Use Genetic method to
find optimal (sub optimal) solution
• Expert System Initialization- Use power
system knowledge to find a good initial
solution
Slide 8© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Genetic Algorithm
• An optimization technique based on the
theory of nature selection
• An iterative procedure that maintains a
constant-size population of candidate
solutions
• Coding, initialization, fitness evaluation,
selection, crossover, mutation
Slide 9© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
ETAP OCP Capabilities
• Find capacitor’s best location and bank size
• Minimize the total cost of installation and operation
• Handle radial or meshed balanced networks (PS
5.0)
• User selectable capacitor placement purpose
• Global or individual constraints
Slide 10© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
ETAP OCP Capabilities
• Analysis capacitor control method and
review capacitor impact on the system with
load duration setting
• Speed and precision ratio control by users
• Determine available capacitor installation
locations by users
Slide 11© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
ETAP OCP Capabilities
• Determine maximum capacitor size using
maximum load and determine switchblade
capacitor size using minimum load
• Use average or source energy cost
• Focus on saving during the whole planning
period
Slide 12© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Display Results
• LF results for maximum loads
• New capacitor locations and sizes
Slide 13© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Plot Results
• Loss reduction savings during the planning
period
• Capacitor operation cost during the planning
period
• Profit during the planning period
Slide 14© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Report Results
• Load Flow related reports
• Capacitor locations and sizes
• Load flow results for maximum, average and
minimum loads
• Branch capacity release
Slide 15© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement
Example
• Run NR Load Flow and look at bus voltages
(critical under voltage is set to 95% and
marginal under voltage is set to 98%)
• Switch to OCP mode and look at the study
case settings
• Run OCP and look at the voltage
improvements

More Related Content

What's hot

ETAP - Harmonics Analysis
ETAP - Harmonics AnalysisETAP - Harmonics Analysis
ETAP - Harmonics AnalysisHimmelstern
 
ETAP - Ugs Underground Raceway Systems
ETAP - Ugs Underground Raceway SystemsETAP - Ugs Underground Raceway Systems
ETAP - Ugs Underground Raceway SystemsHimmelstern
 
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-CircuitETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-CircuitHimmelstern
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2Himmelstern
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systemsHimmelstern
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramHimmelstern
 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationHimmelstern
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introductionHimmelstern
 
ETAP - Ac networks
ETAP - Ac networksETAP - Ac networks
ETAP - Ac networksHimmelstern
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapHimmelstern
 
ETAP - etap real-time overview
ETAP -  etap real-time overviewETAP -  etap real-time overview
ETAP - etap real-time overviewHimmelstern
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methodsHimmelstern
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecionHimmelstern
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordinationHimmelstern
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapHimmelstern
 
ETAP - udm - User-Defined Dynamic Models
ETAP -  udm - User-Defined Dynamic ModelsETAP -  udm - User-Defined Dynamic Models
ETAP - udm - User-Defined Dynamic ModelsHimmelstern
 
ETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & DuschargeETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & DuschargeHimmelstern
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 
ETAP - parameter estimation
ETAP - parameter estimationETAP - parameter estimation
ETAP - parameter estimationHimmelstern
 

What's hot (20)

ETAP - Harmonics Analysis
ETAP - Harmonics AnalysisETAP - Harmonics Analysis
ETAP - Harmonics Analysis
 
ETAP - Ugs Underground Raceway Systems
ETAP - Ugs Underground Raceway SystemsETAP - Ugs Underground Raceway Systems
ETAP - Ugs Underground Raceway Systems
 
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-CircuitETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
ETAP - dc lf and dc sc | DC Load Flow & DC short-Circuit
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systems
 
ETAP - csd - Control System Diagram
ETAP - csd - Control System DiagramETAP - csd - Control System Diagram
ETAP - csd - Control System Diagram
 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-acceleration
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
 
ETAP - Ac networks
ETAP - Ac networksETAP - Ac networks
ETAP - Ac networks
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
 
ETAP - etap real-time overview
ETAP -  etap real-time overviewETAP -  etap real-time overview
ETAP - etap real-time overview
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methods
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
 
ETAP - udm - User-Defined Dynamic Models
ETAP -  udm - User-Defined Dynamic ModelsETAP -  udm - User-Defined Dynamic Models
ETAP - udm - User-Defined Dynamic Models
 
ETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & DuschargeETAP - bsd - Battery Sizing & Duscharge
ETAP - bsd - Battery Sizing & Duscharge
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
ETAP - parameter estimation
ETAP - parameter estimationETAP - parameter estimation
ETAP - parameter estimation
 

Similar to ETAP - ocp - Optimal Capacitor Placement

Cfx12 06 review_day1
Cfx12 06 review_day1Cfx12 06 review_day1
Cfx12 06 review_day1Marcushuynh66
 
Design and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiersDesign and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiersGrace Abraham
 
equipments like CT,PT SUBSTATION PPT.ppt
equipments like CT,PT SUBSTATION PPT.pptequipments like CT,PT SUBSTATION PPT.ppt
equipments like CT,PT SUBSTATION PPT.pptsrinjayjha
 
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsTPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsKey Engineering Solutions
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC (A Yokogawa Company)
 
Plant data for energy audit
Plant data for energy auditPlant data for energy audit
Plant data for energy auditUtpal SenGupta
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Bowman Power
 
Air 2015 aaae
Air 2015 aaaeAir 2015 aaae
Air 2015 aaaeStantec
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Raja Ratnam
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...AMI GE International
 
Artificial Lift Optimization - North America Congress 2016
Artificial Lift Optimization - North America Congress 2016Artificial Lift Optimization - North America Congress 2016
Artificial Lift Optimization - North America Congress 2016marketinglbcg
 
Experiential perspectives of air master+ for industrial compressed air systems
Experiential perspectives of air master+ for industrial compressed air systemsExperiential perspectives of air master+ for industrial compressed air systems
Experiential perspectives of air master+ for industrial compressed air systemsZondits
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systemsHimmelstern
 
Berlin presentation 20171023
Berlin presentation 20171023Berlin presentation 20171023
Berlin presentation 20171023Christie Pommier
 
Europe User Conference: Neste FCC-SIM model usage
Europe User Conference: Neste FCC-SIM model usageEurope User Conference: Neste FCC-SIM model usage
Europe User Conference: Neste FCC-SIM model usageKBC (A Yokogawa Company)
 
8A_5_RE_India19_079_presentation_Doug_Waters.pdf
8A_5_RE_India19_079_presentation_Doug_Waters.pdf8A_5_RE_India19_079_presentation_Doug_Waters.pdf
8A_5_RE_India19_079_presentation_Doug_Waters.pdfhiiarindam
 

Similar to ETAP - ocp - Optimal Capacitor Placement (20)

Cfx12 08 transient
Cfx12 08 transientCfx12 08 transient
Cfx12 08 transient
 
Cfx12 06 review_day1
Cfx12 06 review_day1Cfx12 06 review_day1
Cfx12 06 review_day1
 
Design and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiersDesign and implementation of cmos rail to-rail operational amplifiers
Design and implementation of cmos rail to-rail operational amplifiers
 
equipments like CT,PT SUBSTATION PPT.ppt
equipments like CT,PT SUBSTATION PPT.pptequipments like CT,PT SUBSTATION PPT.ppt
equipments like CT,PT SUBSTATION PPT.ppt
 
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering SolutionsTPM2015 Presentation by Andre Gibson - Key Engineering Solutions
TPM2015 Presentation by Andre Gibson - Key Engineering Solutions
 
KBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utilityKBC decision making tool optimal planning scheduling utility
KBC decision making tool optimal planning scheduling utility
 
Plant data for energy audit
Plant data for energy auditPlant data for energy audit
Plant data for energy audit
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...
 
Air 2015 aaae
Air 2015 aaaeAir 2015 aaae
Air 2015 aaae
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 
Artificial Lift Optimization - North America Congress 2016
Artificial Lift Optimization - North America Congress 2016Artificial Lift Optimization - North America Congress 2016
Artificial Lift Optimization - North America Congress 2016
 
Marathon Petro-SIM use at Marathon
Marathon Petro-SIM use at MarathonMarathon Petro-SIM use at Marathon
Marathon Petro-SIM use at Marathon
 
65 sutterlueti using_advanced_pv_and_bo_s_modelling_and_algorithms_to_optimiz...
65 sutterlueti using_advanced_pv_and_bo_s_modelling_and_algorithms_to_optimiz...65 sutterlueti using_advanced_pv_and_bo_s_modelling_and_algorithms_to_optimiz...
65 sutterlueti using_advanced_pv_and_bo_s_modelling_and_algorithms_to_optimiz...
 
Experiential perspectives of air master+ for industrial compressed air systems
Experiential perspectives of air master+ for industrial compressed air systemsExperiential perspectives of air master+ for industrial compressed air systems
Experiential perspectives of air master+ for industrial compressed air systems
 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systems
 
Berlin presentation 20171023
Berlin presentation 20171023Berlin presentation 20171023
Berlin presentation 20171023
 
Europe User Conference: Neste FCC-SIM model usage
Europe User Conference: Neste FCC-SIM model usageEurope User Conference: Neste FCC-SIM model usage
Europe User Conference: Neste FCC-SIM model usage
 
8A_5_RE_India19_079_presentation_Doug_Waters.pdf
8A_5_RE_India19_079_presentation_Doug_Waters.pdf8A_5_RE_India19_079_presentation_Doug_Waters.pdf
8A_5_RE_India19_079_presentation_Doug_Waters.pdf
 
Katerine Dykes: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Katerine Dykes: 2013 Sandia National Laboratoies Wind Plant Reliability WorkshopKaterine Dykes: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Katerine Dykes: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
 

Recently uploaded

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 

Recently uploaded (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 

ETAP - ocp - Optimal Capacitor Placement

  • 1. © 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Optimal Capacitor Placement
  • 2. Slide 2© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Problem of Var Flow in Power Systems • Loads and delivery apparatus (e.g., lines and transformers) are inductive in nature • Most power systems operate at a lagging power factor • Resulting system capacity reduced, system loss increased and system voltage decreased
  • 3. Slide 3© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Purposes of Shunt Capacitor Applications • Var support – Primary benefit for transmission systems and secondary benefit for distribution systems • Voltage control – Primary benefit for both transmission and distribution systems • System capacity increase – Secondary benefit for transmission systems and primary benefit for distribution systems
  • 4. Slide 4© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Purposes of Shunt Capacitor Applications • System power loss reduction – Secondary benefit for transmission systems and primary benefit for distribution systems • Billing charge reduction – Not applied to transmission systems but a primary benefit for distribution systems
  • 5. Slide 5© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement General Process for Placing Shunt Capacitors • Determine bank size in kvar • Determine connection location • Determine a control method • Determine a connection type (wye or delta)
  • 6. Slide 6© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement General Methods for Capacitor Placement • Rules of Thumb • Power Flow Based • Optimal
  • 7. Slide 7© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Optimal Capacitor Placement in ETAP • Genetic Algorithm - Use Genetic method to find optimal (sub optimal) solution • Expert System Initialization- Use power system knowledge to find a good initial solution
  • 8. Slide 8© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Genetic Algorithm • An optimization technique based on the theory of nature selection • An iterative procedure that maintains a constant-size population of candidate solutions • Coding, initialization, fitness evaluation, selection, crossover, mutation
  • 9. Slide 9© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement ETAP OCP Capabilities • Find capacitor’s best location and bank size • Minimize the total cost of installation and operation • Handle radial or meshed balanced networks (PS 5.0) • User selectable capacitor placement purpose • Global or individual constraints
  • 10. Slide 10© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement ETAP OCP Capabilities • Analysis capacitor control method and review capacitor impact on the system with load duration setting • Speed and precision ratio control by users • Determine available capacitor installation locations by users
  • 11. Slide 11© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement ETAP OCP Capabilities • Determine maximum capacitor size using maximum load and determine switchblade capacitor size using minimum load • Use average or source energy cost • Focus on saving during the whole planning period
  • 12. Slide 12© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Display Results • LF results for maximum loads • New capacitor locations and sizes
  • 13. Slide 13© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Plot Results • Loss reduction savings during the planning period • Capacitor operation cost during the planning period • Profit during the planning period
  • 14. Slide 14© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Report Results • Load Flow related reports • Capacitor locations and sizes • Load flow results for maximum, average and minimum loads • Branch capacity release
  • 15. Slide 15© 1996-2009 Operation Technology, Inc. – Workshop Notes: Optimal Capacitor Placement Example • Run NR Load Flow and look at bus voltages (critical under voltage is set to 95% and marginal under voltage is set to 98%) • Switch to OCP mode and look at the study case settings • Run OCP and look at the voltage improvements