SlideShare a Scribd company logo
1 of 102
Download to read offline
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIALĀ© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection and Coordination
Pirooz Barkhordar, PE
Operation Technology, Inc.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Agenda
ā€¢ Objectives
ā€¢ Equipment Protection
ā€¢ Protection Types
ā€¢ Overcurrent Protection
ā€¢ STAR Overview
ā€¢ Features and Capabilities
ā€¢ Protective Device Types
ā€¢ TCC Curves
ā€¢ STAR Short-circuit
ā€¢ PD Sequence of Operation
ā€¢ Normalized TCC curves
ā€¢ TCC Print and Settings Report
ā€¢ Examples and Assignments
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Objectives
ā€¢ Human Safety
ā€¢ Prevent injury and fatality
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Real Side of Failure in Safety
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Objectives
ā€¢ Protection of Equipment
ā€¢ Permit normal operation
ā€¢ Isolate the equipment in case of abnormal conditions
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Objectives
ā€¢ Protection of System (Stability Protection)
ā€¢ Over / Under Voltage
ā€¢ Over / Under Frequency
ā€¢ Rate of Frequency Change
ā€¢ Islanding of System
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Objectives
ā€¢ Selectivity
ā€¢ Minimal isolation of network with abnormal conditions
ā€¢ Permit normal operation for rest of electrical network
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection & Coordination
ā€¢ Objectives
ā€¢ Reasonable Cost
ā€¢ Maximum achievable reliability for protection and
coordination at minimal cost
ā€¢ Science, Experience, and Art
ā€¢ Sensitivity to faults and insensitivity to normal operation
ā€¢ Fast fault clearance with proper selectivity
ā€¢ Minimal isolation of faulty area
ā€¢ Capability to operate correctly under all predictable
power system conditions
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
References
ā€¢ IEEE Std. 242-2001, IEEE Recommended Practice
for Protection and Coordination of Industrial and
Commercial Power Systems (IEEE Buff Book)
ā€¢ IEEE Std. 141-1993, IEEE Recommended Practice
for Electric Power Distribution for Industrial Plants
(IEEE Red Book)
ā€¢ IEEE Std. 399-1997, IEEE Recommended Practice
for Industrial and Commercial Power Systems
Analysis (IEEE Brown Book)
ā€¢ Other technical references
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Study Procedure
ā€¢ Prepare an accurate one-line diagram (relay
diagrams)
ā€¢ Obtain the available system current spectrum
(operating load, overloads, fault kA)
ā€¢ Determine the equipment protection criteria
ā€¢ Select the appropriate protective devices / settings
ā€¢ Plot the fixed points (operating/damage curves, FLA,
ampacity, etc.)
ā€¢ Obtain / plot the device characteristics curves
ā€¢ Analyze the results
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Required Data
ā€¢ One-line diagrams (Relay diagrams)
ā€¢ Power Grid Fault Current Data and Protective Device Settings
ā€¢ Generator Data
ā€¢ Transformer Data
ā€¢ Motor Data
ā€¢ Load Data
ā€¢ Fault Currents
ā€¢ Cable / Conductor Data
ā€¢ Bus / Switchgear Data
ā€¢ Instrument Transformer Data (CT, VT)
ā€¢ Protective Device (PD) Data
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection of Equipments
ā€¢ Major Equipments (apparatus)
ā€¢ Induction Motor
ā€¢ Synchronous Motor
ā€¢ Cable
ā€¢ Transformer
ā€¢ Generator
ā€¢ Bus
ā€¢ Transmission/Distribution Line
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Equipment Protection Criteria
ā€¢ Permit: Normal Running Condition
ā€¢ Max permitted current at working conditions
ā€¢ Environment temperature, cooling media, elevation, etc.
ā€¢ Protect: Abnormal Fault Condition
ā€¢ Excessive through fault current caused by:
ā€¢ Improper design, installation, or operation of equipment
ā€¢ Incidents
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Excessive Currents
ā€¢ Excessive currents in abnormal conditions
ā€¢ Overload current
ā€¢ (100-160% Full Load Amps)
ā€¢ Short-time overload current
ā€¢ (300-1000% Full Load Amps)
ā€¢ Short-circuit current
ā€¢ (300-1200% Full Load Amps)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Capability / Damage Curves
t
I
I2
2
t
Gen
I2
t
Motor
Xfmr
I2
t
Cable
I2
t
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection Types
ā€¢ Overcurrent
ā€¢ Inverse Time Over Current (TOC)
ā€¢ Instantaneous Over Current (IOC)
ā€¢ Directional
ā€¢ Differential
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protection Types
ā€¢ Impedance
ā€¢ Distance
ā€¢ Voltage
ā€¢ Under/Over Voltage
ā€¢ Frequency
ā€¢ Under/Over Frequency
ā€¢ Mechanical
ā€¢ Pressure (Buchholz Relay)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Overcurrent Protection
Overcurrent Characteristics
ā€¢ Inverse Time Over Current (TOC)
ā€¢ Simple, cheap, and large
application in LV, and MV
ā€¢ LV Breakers
ā€¢ Represent tolerance band
ā€¢ MCB, MCCB, ICCB, PCB
ā€¢ Fuses
ā€¢ Overload Heater
ā€¢ Overload Relay
Time-Current-Characteristics (TCC)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Overcurrent Protection
Relay TOC Characteristics Relay TOC Curves
ā€¢ Curve Shape Adaptation
ā€¢ Equipment Protection
ā€¢ Selectivity
ā€¢ Time Margin at higher fault
currents
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
ETAP Star Overview
ā€¢ Star Mode
ā€¢ Creation of TCC and Star View
ā€¢ Addition of devices to existing TCC
ā€¢ Graphical and Editor adjustments
ā€¢ Star View Options (top)
ā€¢ Combine Curve (ETAP 11 enahncement)
ā€¢ Star Mode and Star View difference
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
ETAP Star Overview
ā€¢ Supported Protective Devices and Functions
ā€¢ Overload - CT based & Inline (49)
ā€¢ Phase, neutral, ground, and negative sequence overcurrent
(51/50)
ā€¢ Voltage control and restraint overcurrent (51VC/51VR)
ā€¢ Directional overcurrent (67)
ā€¢ High impedance & percentage differential (87)
ā€¢ Electronic & hydraulic reclosers (79)
ā€¢ Relay interlock with HVCB, switch and contactor
ā€¢ CT Ratio and multiple connections
*Reverse power (32) and under/over voltage (27/59) are supported in
Transient Stability
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Low Voltage Protective Devices
ā€¢ Low Voltage Circuit Breaker (LVCB)
ā€¢ Power Circuit Breaker (PCB)
ā€¢ UL 1066, ANSI C37.13, ANSI C37.16, ANSI C37.17
ā€¢ IEC60947-2
ā€¢ Insulated Case Circuit Breaker (ICCB)
ā€¢ UL489 (Non-fused MCCB, 2 step stored energy closing mechanism,
electronic trip, and drawout construction)
ā€¢ IEC60947-2
ā€¢ Molded Case Circuit Breaker (MCCB)
ā€¢ UL489 (integral unit and enclosed housing of insulating material)
ā€¢ IEC60947-2
ā€¢ Miniature Circuit Breaker (MCB)
ā€¢ UL489, UL508, UL1077
ā€¢ IEC60898
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
LVCB Differences
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Low Voltage Protective Devices
ā€¢ LVCB Trip Units
ā€¢ Thermal Magnetic
ā€¢ Motor Circuit Protector (MCP)
ā€¢ Solid State Trip (SST) or microprocessor based
ā€¢ Electro-mechanical
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
LV Protective Devices
ā€¢ MCCB Trip Units
ā€“ Thermal-Magnetic
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
LV Protective Devices
ā€¢ MCCB Trip Units
ā€“ Magnetic Only
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Low Voltage Protective Devices
ā€¢ LVCB Trip Units
ā€¢ Solid State Trip (SST) or
microprocessor based
ā€¢ Electro-mechanical
ā€¢ Trip Unit Segments
ā€¢ Long Time (LT ANSI; I> IEC)
ā€¢ Short Time (ST ANSI; I>> IEC)
ā€¢ Instantaneous (IT ANSI; I>>> IEC)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Fuse (Power Fuse)
ā€¢ Non Adjustable Device (unless electronic)
ā€¢ Continuous and Interrupting Rating
ā€¢ Voltage Levels (Max kV)
ā€¢ Interrupting Rating (sym, asym)
ā€¢ Characteristic Curves
ā€¢ Min. Melting
ā€¢ Total Clearing
ā€¢ Application (rating type: R, E, X, ā€¦)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Fuse Types
ā€¢ Expulsion Fuse (Non-CLF)
ā€¢ Current Limiting Fuse (CLF)
ā€¢ Electronic Fuse (S&C Fault Fiter)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Minimum Melting
Time Curve
Total Clearing
Time Curve
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Current Limiting Fuse (CLF)
ā€¢ Limits the peak current of short-circuit
ā€¢ Reduces magnetic stresses (mechanical damage)
ā€¢ Reduces thermal energy
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Current Limiting ActionCurrent(peakamps)
tm ta
Ipā€™
Ip
tc
ta = tc ā€“ tm
ta = Arcing Time
tm = Melting Time
tc = Clearing Time
Ip = Peak Current
Ipā€™ = Peak Let-thru Current
Time (cycles)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
CLF Let-Through Chart
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
CLF Let-Through Chart
ā€¢ Assumptions:
1. Short-circuit X/R ā‰¤ Tested Short-circuit X/R, or
Short-circuit power factor ā‰„ tested power factor
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
CLF Let-Through Chart
ā€¢ Assumptions
2. The fault is on the load terminal
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
CLF Let-Through Chart
ā€¢ Impact of Downstream Breaker
ā€¢ The fault current passing through both PDs
ā€¢ The breaker may start to open representing a
dynamic impedance causing reduced let-through
current with different trip time
ā€¢ A combination test is needed to make sure this is
not happening. This is a series rating test.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
CLF Let-Through Chart
ā€¢ Assumptions
3. The sum of motor full load currents contribution between the
series rated devices should not exceeds 1 percent of
interrupting rating of lowest rated device.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Symmetrical RMS Amperes
PeakLet-ThroughAmperes
100 A
60 A
7% PF (X/R = 14.3)
12,500
5,200
230,000
300 A
100,000
Let-Through Chart
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Fuse
Generally:
ā€¢ CLF is a better short-circuit protection
ā€¢ Non-CLF (expulsion fuse) is a better Overload
protection
ā€¢ Electronic fuses are typically easier to coordinate
due to the electronic control adjustments
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Zones of Protection
ā€¢ Protective devices and protected equipment
represent the ā€œProtection Zoneā€
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Protection
ā€¢ Motor Starting Curve
ā€¢ Thermal Protection
ā€¢ Locked Rotor Protection
ā€¢ Fault Protection
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Inrush Current
First half cycle current showing
current offset.
Beginning of run up current
showing load torque pulsations.
Starting Current of a 4000Hp, 12 kV, 1800 rpm Motor
Motor pull in current showing motor
reaching synchronous speed
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Protection
LV Motor Protection MV Motor Protection
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Protection
ā€¢ Standards & References
ā€¢ IEEE Std 620-1996 IEEE Guide for the Presentation of
Thermal Limit Curves for Squirrel Cage Induction
Machines.
ā€¢ IEEE Std 1255-2000 IEEE Guide for Evaluation of Torque
Pulsations During Starting of Synchronous Motors
ā€¢ ANSI/ IEEE C37.96-2000 Guide for AC Motor Protection
ā€¢ NEMA MG-1 Motors and Generators
ā€¢ The Art of Protective Relaying ā€“ General Electric
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Overload Relay / Heater
ā€¢ Motor overload protection is provided by a
device that models the temperature rise of the
winding
ā€¢ When the temperature rise reaches a point
that will damage the motor, the motor is de-
energized
ā€¢ Overload relays are either bimetallic, melting
alloy or electronic
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Question
What is Class 10 and
Class 20 Thermal
OLR curves?
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Answer
ā€¢ At 600% Current Rating:
ā€“ Class 10 for fast trip, 10
seconds or less
ā€“ Class 20 for, 20 seconds or less
(commonly used)
ā€“ There is also Class 15, 30 for
long trip time (typically
provided with electronic
overload relays)
6
20
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Answer
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Overload Relay / Heater
ā€¢ When the temperature at the combination motor starter is more than Ā±10
Ā°C (Ā±18 Ā°F) different than the temperature at the motor, ambient
temperature correction of the motor current is required.
ā€¢ An adjustment is required because the output that a motor can safely
deliver varies with temperature.
ā€¢ The motor can deliver its full rated horsepower at an ambient temperature
specified by the motor manufacturers, normally + 40 Ā°C. At high
temperatures (higher than + 40 Ā°C) less than 100% of the normal rated
current can be drawn from the motor without shortening the insulation
life.
ā€¢ At lower temperatures (less than + 40 Ā°C) more than 100% of the normal
rated current could be drawn from the motor without shortening the
insulation life.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Starting and Thermal Limit
Sample data provided by the manufacturer
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Protection - Overload Pickup
(NEC Art 430.32 ā€“ Continuous-Duty Motors)
ā€¢ Thermal O/L (Device 49) Pickup
ā€¢ Motors with marked Service Factor ā‰„ 1.15
ā€¢ Pickup = 125% of FLA
ā€¢ Motors with temp. rise not over 40Ā°C
ā€¢ Pickup = 125% of FLA
ā€¢ All other motors
ā€¢ 115% of FLA
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Motor Protection ā€“ Inst. Pickup
LOCKED
ROTOR S d
1
I
X X "
PICK UP
LOCKED ROTOR
I
RELAY PICK UP 1.2 TO 1.2
I
PICK UP
LOCKED ROTOR
I
RELAY PICK UP 1.6 TO 2
I
with a time delay of 0.10 s (six cycles at 60 Hz)
Recommended Instantaneous Setting:
If the recommended setting criteria cannot be met, or where more sensitive
protection is desired, the instantaneous relay (or a second relay) can be set more
sensitively if delayed by a timer. This permits the asymmetrical starting component
to decay out. A typical setting for this is:
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Locked Rotor Protection
ā€¢ Thermal Locked Rotor (Device 51)
ā€¢ Starting Time (TS < TLR)
ā€¢ LRA
ā€¢ LRA sym
ā€¢ LRA asym (1.5-1.6 x LRA sym) + 10% margin
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Fault Protection
(NEC Art / Table 430-52)
ā€¢ Non-Time Delay Fuses
ā€¢ 300% of FLA
ā€¢ Dual Element (Time-Delay Fuses)
ā€¢ 175% of FLA
ā€¢ Instantaneous Trip Breaker
ā€¢ 800% - 1300% of FLA*
ā€¢ Inverse Time Breakers
ā€¢ 250% of FLA
*can be set up to 1700% for Design B (energy efficient) Motor
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Low Voltage Motor Protection
ā€¢ Usually pre-engineered (selected from
Catalogs)
ā€¢ Typically, motors larger than 2 Hp are
protected by combination starters
ā€¢ Overload / Short-circuit protection
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
200 HP
MCP
O/L
Starting Curve
I
2
T
(49)
MCP (50)
(51)
ts
tLR
LRAs LRAasym
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Low-voltage Motor
Ratings Range of ratings
Continuous amperes 9-250 ā€”
Nominal voltage (V) 240-600 ā€”
Horsepower 1.5-1000 ā€”
Starter size (NEMA) ā€” 00-9
Types of protection Quantity NEMA
designation
Overload: overload
relay elements
3 OL
Short circuit:
circuit breaker current
trip elements
3 CB
Fuses 3 FU
Undervoltage: inherent
with integral control
supply and three-wire
control circuit ā€” ā€”
Ground fault (when
specified): ground relay
with toroidal CT ā€” ā€”
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Minimum Required Sizes of a NEMA Combination Motor
Starter System
MAXIMUM CONDUCTOR LENGTH FOR ABOVE AND
BELOW GROUND CONDUIT SYSTEMS. ABOVE GROUND
SYSTEMS HAVE DIRECT SOLAR EXPOSURE. 750
C
CONDUCTOR TEMPERATURE, 450
C AMBIENT
CIRCUIT BREAKER
SIZE
FUSESIZE
CLASSJ
FUSE
MOTORHP
460VNECFLC
STARTER
SIZE
MINIMUM
SIZE
GROUNDING
CONDUCTOR
FORA50%CURRENTCAPACITY
MINIMUM
WIRE
SIZE
MAXIMUM
LENGTHFOR1%
VOLTAGE
DROP
NEXT
LARGEST
WIRE
SIZE
USENEXT
LARGERGROUND
CONDUCTOR
MAXIMUM
LENGTHFOR1%
VOLTAGE
DROPWITH
LARGERWIRE
250% 200% 150%
1 2.1 0 12 12 759 10 1251 15 15 15 5
1Ā½ 3 0 12 12 531 10 875 15 15 15 6
2 3.4 0 12 12 468 10 772 15 15 15 7
3 4.8 0 12 12 332 10 547 20 20 15 10
5 7.6 0 12 12 209 10 345 20 20 15 15
7Ā½ 11 1 12 10 144 8 360 30 25 20 20
10 14 1 10 8 283 6 439 35 30 25 30
15 21 2 10 8 189 6 292 50 40 30 45
20 27 2 10 6 227 4 347 70 50 40 60
25 34 2 8 4 276 2 407 80 70 50 70
30 40 3 6 2 346 2/0 610 100 70 60 90
40 52 3 6 2 266 2/0 469 150 110 90 110
50 65 3 2 2/0 375 4/0 530 175 150 100 125
60 77 4 2 2/0 317 4/0 447 200 175 125 150
75 96 4 2 4/0 358 250 393 250 200 150 200
100 124 4 1 250 304 350 375 350 250 200 250
125 156 5 2/0 350 298 500 355 400 300 250 350
150 180 5 4/0 500 307 750 356 450 350 300 400
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Required Data - Protection of a Medium Voltage
Motor
ā€¢ Rated full load current
ā€¢ Service factor
ā€¢ Locked rotor current
ā€¢ Maximum locked rotor time (thermal limit curve) with the motor at ambient and/or operating
temperature
ā€¢ Minimum no load current
ā€¢ Starting power factor
ā€¢ Running power factor
ā€¢ Motor and connected load accelerating time
ā€¢ System phase rotation and nominal frequency
ā€¢ Type and location of resistance temperature devices (RTDs), if used
ā€¢ Expected fault current magnitudes
ā€¢ First Ā½ cycle current
ā€¢ Maximum motor starts per hour
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Medium-Voltage Class E Motor Controller
Ratings
Class El (without
fuses)
Class E2 (with fuses)
Nominal system voltage 2300-6900 2300-6900
Horsepower 0-8000 0-8000
Symmetrical MVA interrupting capacity
at nominal system voltage
25-75 160-570
Types of Protective Devices Quantity NEMA Designation
Overload, or locked Rotor, or both:
Thermal overload relay
TOC relay
IOC relay plus time delay
3
3
3
OL OC TR/O
Thermal overload relay 3 OL
TOC relay 3 OC
IOC relay plus time delay 3 TR/OC
Short Circuit:
Fuses, Class E2 3 FU
IOC relay, Class E1 3 OC
Ground Fault
TOC residual relay 1 GP
Overcurrent relay with toroidal CT 1 GP
NEMA Class E2 medium
voltage starter
NEMA Class E1
medium voltage starter
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Thermal Limit Curve
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Thermal Limit Curve
Typical Curve
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Cable Protection
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Cable Protection
ā€¢ Standards & References
ā€¢ IEEE Std. 242-2001, IEEE Recommended Practice for
Protection and Coordination of Industrial and Commercial
Power Systems (IEEE Buff Book)
ā€¢ IEEE Std 835-1994 IEEE Standard Power Cable Ampacity
Tables
ā€¢ IEEE Std 848-1996 IEEE Standard Procedure for the
Determination of the Ampacity Derating of Fire-Protected
Cables
ā€¢ IEEE Std 738-1993 IEEE Standard for Calculating the
Current- Temperature Relationship of Bare Overhead
Conductors
ā€¢ The Okonite Company Engineering Data for Copper and
Aluminum Conductor Electrical Cables, Bulletin EHB-98
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Cable Protection
2
2
1
t
A
T 234
0.0297log
T 234
The actual temperature rise of a cable when exposed to
a short circuit current for a known time is calculated by:
Where:
A= Conductor area in circular-mils
I = Short circuit current in amps
t = Time of short circuit in seconds
T1= Initial operation temperature (750C)
T2=Maximum short circuit temperature
(1500C)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Cable Short-Circuit Heating Limits
Recommended
temperature rise:
B) CU 75-200C
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Shielded
Cable
The normal tape
width is 1Ā½
inches
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
NEC Section 110-14 C
ā€¢ (c) Temperature limitations. The temperature rating associated with the ampacity
of a conductor shall be so selected and coordinated as to not exceed the lowest
temperature rating of any connected termination, conductor, or device. Conductors
with temperature ratings higher than specified for terminations shall be permitted
to be used for ampacity adjustment, correction, or both.
ā€¢ (1) Termination provisions of equipment for circuits rated 100 amperes or less, or
marked for Nos. 14 through 1 conductors, shall be used only for conductors rated
60C (140F).
ā€¢ Exception No. 1: Conductors with higher temperature ratings shall be permitted to
be used, provided the ampacity of such conductors is determined based on the
6OC (140F) ampacity of the conductor size used.
ā€¢ Exception No. 2: Equipment termination provisions shall be permitted to be used
with higher rated conductors at the ampacity of the higher rated conductors,
provided the equipment is listed and identified for use with the higher rated
conductors.
ā€¢ (2) Termination provisions of equipment for circuits rated over 100 amperes, or
marked for conductors larger than No. 1, shall be used only with conductors rated
75C (167F).
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Protection
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Protection
ā€¢ Standards & References
ā€¢ National Electric Code 2011 Edition
ā€¢ IEEE Std 242-1986; IEEE Recommended Practice for Protection and
Coordination of Industrial and Commercial Power Systems
ā€¢ C37.91-2000; IEEE Guide for Protective Relay Applications to Power
Transformers
ā€¢ C57.12.59; IEEE Guide for Dry-Type Transformer Through-Fault
Current Duration.
ā€¢ C57.109-1985; IEEE Guide for Liquid-Immersed Transformer Through-
Fault-Current Duration
ā€¢ APPLIED PROCTIVE RELAYING; J.L. Blackburn; Westinghouse Electric
Corp; 1976
ā€¢ PROTECTIVE RELAYING, PRINCIPLES AND APPLICATIONS; J.L.
Blackburn; Marcel Dekker, Inc; 1987
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Categories
ANSI/IEEE C-57.109
Minimum nameplate (kVA)
Category Single-phase Three-phase
I 5-500 15-500
II 501-1667 501-5000
III 1668-10,000 5001-30,000
IV above 10,000 above 30,000
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Categories I, II
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Category III
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Category IV
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer
t
(sec)
I (pu)
Thermal200
2.5
I
2
t = 1250
2
25Isc
Mechanical
K=(1/Z)
2
t
(D-D LL) 0.87
(D-R LG) 0.58
Frequent Fault
Infrequent Fault
Inrush
FLA
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Protection
MAXIMUM RATING OR SETTING FOR OVERCURRENT DEVICE
PRIMARY SECONDARY
Over 600 Volts Over 600 Volts 600 Volts or Below
Transformer
Rated
Impedance
Circuit
Breaker
Setting
Fuse
Rating
Circuit
Breaker
Setting
Fuse
Rating
Circuit Breaker
Setting or Fuse
Rating
Not more than
6%
600 % 300 % 300 % 250% 125%
(250% supervised)
More than 6%
and not more
than 10%
400 % 300 % 250% 225% 125%
(250% supervised)
Table 450-3(A) source: NEC
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Recommended Minimum
Transformer Protection
Protective system
Winding and/or power system
grounded neutral grounded
Winding and/or power system
neutral ungrounded
Up to 10 MVA Above 10 MVA Up to 10 MVA
Above
10 MVA
Differential - āˆš - āˆš
Time over current āˆš āˆš āˆš āˆš
Instantaneous restricted
ground fault āˆš āˆš - -
Time delayed ground
fault āˆš āˆš - -
Gas detection
āˆš -
āˆš
Over excitation -
āˆš āˆš āˆš
Overheating -
āˆš -
āˆš
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Question
What is ANSI Transformer Shift Curve?
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Transformer Shift Factor
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Dyg Transformer Through Fault
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Question
What is meant by Frequent and
Infrequent Faults for transformers?
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Frequent and Infrequent Faults
* Should be selected by reference to the frequent-fault-incidence protection curve or for transformers
serving industrial, commercial and institutional power systems with secondary-side conductors
enclosed in conduit, bus duct, etc., the feeder protective device may be selected by reference to the
infrequent-fault-incidence protection curve.
(Frequent Fault = More than 10 through faults (lifetime) for category II and 5 faults for category III)
Source
Transformer primary-side protective device
(fuses, relayed circuit breakers, etc.) may be
selected by reference to the infrequent-fault-
incidence protection curve
Category II or III Transformer
Fault will be cleared by transformer
primary-side protective device
Optional main secondary ā€“side protective device.
May be selected by reference to the infrequent-fault-
incidence protection curve
Feeder protective device
Fault will be cleared by transformer primary-side
protective device or by optional main secondary-
side protection device
Fault will be cleared by
feeder protective device
Infrequent-Fault
Incidence Zone*
Feeders
Frequent-Fault
Incidence Zone*
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Selective Coordination
ā€¢ Inherent Selective Devices
ā€¢ Examples
ā€¢ Differential Relays
ā€¢ Pilot Wire Relays
ā€¢ Transformer Sudden Pressure Relays
ā€¢ More expensive
ā€¢ Justified based on value or role of protected
equipment in supply of power
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Selective Coordination
ā€¢ Overcurrent Selectivity Rules
ā€¢ Downstream device curve is located to the left and below
of upstream device curve for range of applicable currents
ā€¢ Sufficient time margin for operation of downstream before
upstream
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Selective Coordination
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Margins for Selectivity
ā€¢ Relay - Relay coordination requires
ā€¢ Minimum of 0.25 to 0.40 seconds time margin between the relay curves at the
maximum fault current to account for the interrupting time of the circuit
breaker, relay over-travel time, relay tolerances, and a safety factor
ā€¢ For induction disk relays, the minimum desired time margin for a 5 cycle
breaker is generally 0.30 seconds
ā€¢ 5 cycle breaker 0.08 seconds
ā€¢ relay over-travel 0.10 seconds
ā€¢ CT ratio & safety factor 0.12 seconds
ā€¢ Total = 0.30 seconds
ā€¢ For digital relays, the minimum desired time margin for a 5 cycle breaker is
generally 0.25 seconds
ā€¢ 5 cycle breaker 0.08 seconds
ā€¢ relay accuracy +.02 sec. 0.04 seconds
ā€¢ CT ratio & safety factor 0.13 seconds
ā€¢ Total = 0.25 seconds
ā€¢ Margin between pickup levels of > 10% for two devices in series.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Margins for Selectivity
ā€¢ Electromechanical Relay - Fuse coordination requires a minimum 0.22 second time
margin between the curves.
ā€¢ Electromechanical Relay - Low Voltage Breaker coordination requires a minimum
0.22 second time margin between the curves.
ā€¢ Static Relay - Fuse coordination requires a minimum 0.12 second time margin
between the curves.
ā€¢ Static Relay - Low Voltage Breaker coordination requires a minimum 0.12
second time margin between the curves.
ā€¢ Fuse - Fuse coordination requires that the total clearing time of the downline
fuse curve be less than 75% of the minimum melt time of the upline fuse curve
to account for pre-loading.
ā€¢ Fuse - Low Voltage Breaker coordination requires that the down-line breaker
maximum time curve be less than 75% of the minimum melt time of the up-line
fuse curve to account for pre-loading.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Margins for Selectivity
ā€¢ Fuse - Relay coordination requires a minimum 0.3 second time margin
between the curves.
ā€¢ Low Voltage Breaker - Fuse coordination requires a minimum 0.1 second
time margin between the curves to allow for temperature variations in
the fuse.
ā€¢ Low Voltage Breaker - Low Voltage Breaker coordination requires only
that the plotted curves do not intersect since all tolerances and operating
times are included in the published characteristics.
ā€¢ Low Voltage Breaker - Relay coordination requires a minimum 0.2 second
time margin between the curves.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Protection
ā€¢ NEC Requirements for Solidly Grounded System
ā€¢ Articles 215.10 (feeders), 230.95 (services), 240.13
(overcurrent protection), etc.
ā€¢ 260 V (150 V, L-G) ā‰¤ Line-Line Voltage ā‰¤ 600 V
ā€¢ Main disconnect is rated 1000 A or more
ā€¢ GF Settings is limited to 1200 A pickup and 1 sec for
ground faults > 3000 A
ā€¢ Industry Practice
ā€¢ Grounded wye systems 2400 V or more
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Detection
ā€¢ General Concept
ā€¢ Measurement of Residual (IR)
or Zero Sequence current (3I0)
ā€¢ IR = 3I0 = Ia + Ib + Ic
(Vector Summation)
ā€¢ Balanced Fault: Ia = Ib = Ic and
IR = 3I0 = 0
ā€¢ Unbalanced system Ia ā‰  Ib ā‰  Ic
and IR = 3I0 > 0
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Detection
ā€¢ Direct (Ground, 50G/51G)
ā€¢ Grounded-phase (3I0) current is detected directly
with a current transformer installed in the
grounded neutral conductor.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Detection
ā€¢ Balance Flux (Ground, 50G/51G)
(Core Balance or Zero Sequence CT)
ā€¢ Grounded-phase current (IR) is directly detected by a
doughnut-type current transformer installed around
the three phase conductors
Note: The equipment grounding conductors (including conductor shields)
must not be installed through the current transformer.
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Detection
ā€¢ Residual
ā€¢ Grounded-phase current is detected as the
unbalance in the current produced by the phase
current transformers
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
ETAP Terminology
ā€¢ Relay Ground Function
ā€¢ Externally measured residual current (2 inputs)
ā€¢ Relay Neutral Function
ā€¢ Relay internally measured residual current (6 inputs)
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Relay Ground Inputs
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Relay Sensitive Ground Inputs
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Relay Neutral Inputs
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Relay Function Diagram
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Coordination
ā€¢ GF Selective Coordination
ā€¢ Device ground fault overcurrent coordination with:
ā€¢ Other devices with ground detection
ā€¢ Other devices with phase overcurrent detection
ā€¢ Combination of phase and ground fault detection
ā€¢ Minimum and Maximum Fault
ā€¢ Phase and single-line to ground fault coordination
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Ground Fault Coordination
Individual Phase and GF Curves Phase and GF Curve Combination
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Protective Devices
ā€¢ Relays
ā€¢ Microprocessor/electronic
ā€¢ More expensive, faster, multiple functionality
ā€¢ Electromechanical
ā€¢ Simple, cheap, slower, limited functionality
Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL
Relay ANSI Device Numbers
ā€¢ 21 ā€“ Distance
ā€¢ 27 ā€“ Under Voltage
ā€¢ 32 ā€“ Directional Power
ā€¢ 49 ā€“ Thermal Overload
ā€¢ 50 ā€“ Instantaneous Over Current
ā€¢ 51 ā€“ AC Inverse Over Current
ā€¢ 52 ā€“ AC Circuit Breaker
ā€¢ 59 ā€“ Overvoltage
ā€¢ 67 ā€“ AC Directional Over Current
ā€¢ 79 ā€“ AC Recloser
ā€¢ 81 ā€“ Frequency
ā€¢ 87 ā€“ Differential
ā€¢ P ā€“ Phase
ā€¢ N ā€“ Neutral
ā€¢ G ā€“ Ground
ā€¢ SG ā€“ Sensitive Ground
ā€¢ V ā€“ Voltage
ā€¢ VC ā€“ Voltage Control
ā€¢ VR ā€“ Voltage Restrained

More Related Content

What's hot

ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizingHimmelstern
Ā 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601SARAVANAN A
Ā 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardHimmelstern
Ā 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modelingHimmelstern
Ā 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptxMuhd Hafizi Idris
Ā 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stabilityHimmelstern
Ā 
ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12Himmelstern
Ā 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systemsHimmelstern
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
Ā 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settingsmichaeljmack
Ā 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introductionHimmelstern
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
Ā 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
Ā 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesmentHimmelstern
Ā 
6. curso de fallas y protecciones de ETAP
6. curso de fallas y protecciones de ETAP6. curso de fallas y protecciones de ETAP
6. curso de fallas y protecciones de ETAPHimmelstern
Ā 
Substation design-guideliness
Substation design-guidelinessSubstation design-guideliness
Substation design-guidelinessOSMAN SAYGIN AKKAYA
Ā 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationHimmelstern
Ā 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisPower System Operation
Ā 
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.BhideFundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.BhideSourabh Ghosh
Ā 

What's hot (20)

ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizing
Ā 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Ā 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
Ā 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
Ā 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
Ā 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
Ā 
ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stability
Ā 
ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12ETAP - Modelado de dispositivos de proteccion etap 12
ETAP - Modelado de dispositivos de proteccion etap 12
Ā 
ETAP - Ground grid systems
ETAP - Ground grid systemsETAP - Ground grid systems
ETAP - Ground grid systems
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
Ā 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
Ā 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
Ā 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
Ā 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
Ā 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesment
Ā 
6. curso de fallas y protecciones de ETAP
6. curso de fallas y protecciones de ETAP6. curso de fallas y protecciones de ETAP
6. curso de fallas y protecciones de ETAP
Ā 
Substation design-guideliness
Substation design-guidelinessSubstation design-guideliness
Substation design-guideliness
Ā 
ETAP - 09 motor-acceleration
ETAP - 09 motor-accelerationETAP - 09 motor-acceleration
ETAP - 09 motor-acceleration
Ā 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Ā 
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.BhideFundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Fundamentals of Power System protection by Y.G.Paithankar and S.R.Bhide
Ā 

Similar to ETAP - Coordination and protecion

Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basicsRajan Singh Tanwar
Ā 
Practical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansPractical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansLiving Online
Ā 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfYogeshGairola2
Ā 
OPAL-RT RT14 Conference: HIL testing using HYPERSIM
OPAL-RT RT14 Conference: HIL testing using HYPERSIMOPAL-RT RT14 Conference: HIL testing using HYPERSIM
OPAL-RT RT14 Conference: HIL testing using HYPERSIMOPAL-RT TECHNOLOGIES
Ā 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodinationmichaeljmack
Ā 
Relay and Indications by sgm for protection engineers.pdf
Relay and Indications by sgm for protection engineers.pdfRelay and Indications by sgm for protection engineers.pdf
Relay and Indications by sgm for protection engineers.pdfEngrSyedGhulamMustaf
Ā 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Vincent Wedelich, PE MBA
Ā 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodinationmichaeljmack
Ā 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Knowmilestoneseng
Ā 
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.pptVara Prasad
Ā 
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.pptelectrical1012000
Ā 
Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperJyoti Rawat
Ā 
Littelfuse Fuseology Basics
Littelfuse Fuseology BasicsLittelfuse Fuseology Basics
Littelfuse Fuseology BasicsLittelfuse
Ā 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfssusera5c9a31
Ā 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapHimmelstern
Ā 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightHimmelstern
Ā 
Electric Intelligent Actuators: Electric Smart Actuators: ICR
Electric Intelligent Actuators: Electric Smart Actuators: ICRElectric Intelligent Actuators: Electric Smart Actuators: ICR
Electric Intelligent Actuators: Electric Smart Actuators: ICRTolomatic
Ā 
Substation Occupation Health, Safety and Maintenances
Substation Occupation Health, Safety and MaintenancesSubstation Occupation Health, Safety and Maintenances
Substation Occupation Health, Safety and MaintenancesDileesh Wellala
Ā 
Lec 1_Introduction to Power System Protection.pdf
Lec 1_Introduction to Power System 
Protection.pdfLec 1_Introduction to Power System 
Protection.pdf
Lec 1_Introduction to Power System Protection.pdfAhmedHElashry
Ā 

Similar to ETAP - Coordination and protecion (20)

Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
Ā 
Practical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and TechniciansPractical Power System Protection for Engineers and Technicians
Practical Power System Protection for Engineers and Technicians
Ā 
Power_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdfPower_System_Protection Lecture-1.pdf
Power_System_Protection Lecture-1.pdf
Ā 
OPAL-RT RT14 Conference: HIL testing using HYPERSIM
OPAL-RT RT14 Conference: HIL testing using HYPERSIMOPAL-RT RT14 Conference: HIL testing using HYPERSIM
OPAL-RT RT14 Conference: HIL testing using HYPERSIM
Ā 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
Ā 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
Ā 
Relay and Indications by sgm for protection engineers.pdf
Relay and Indications by sgm for protection engineers.pdfRelay and Indications by sgm for protection engineers.pdf
Relay and Indications by sgm for protection engineers.pdf
Ā 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
Ā 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
Ā 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Know
Ā 
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
Ā 
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
5e361f6f7aa7cf6628a2bfda_Protection-Basics_r3.ppt
Ā 
Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapper
Ā 
Littelfuse Fuseology Basics
Littelfuse Fuseology BasicsLittelfuse Fuseology Basics
Littelfuse Fuseology Basics
Ā 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
Ā 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
Ā 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done Right
Ā 
Electric Intelligent Actuators: Electric Smart Actuators: ICR
Electric Intelligent Actuators: Electric Smart Actuators: ICRElectric Intelligent Actuators: Electric Smart Actuators: ICR
Electric Intelligent Actuators: Electric Smart Actuators: ICR
Ā 
Substation Occupation Health, Safety and Maintenances
Substation Occupation Health, Safety and MaintenancesSubstation Occupation Health, Safety and Maintenances
Substation Occupation Health, Safety and Maintenances
Ā 
Lec 1_Introduction to Power System Protection.pdf
Lec 1_Introduction to Power System 
Protection.pdfLec 1_Introduction to Power System 
Protection.pdf
Lec 1_Introduction to Power System Protection.pdf
Ā 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
Ā 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
Ā 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Ā 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
Ā 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
Ā 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
Ā 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
Ā 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
Ā 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
Ā 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
Ā 
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Serviceyoung call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
Ā 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Ā 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
Ā 
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCRā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
Ā 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
Ā 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
Ā 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Ā 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
Ā 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
Ā 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Ā 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
Ā 

ETAP - Coordination and protecion

  • 1. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIALĀ© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection and Coordination Pirooz Barkhordar, PE Operation Technology, Inc.
  • 2. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Agenda ā€¢ Objectives ā€¢ Equipment Protection ā€¢ Protection Types ā€¢ Overcurrent Protection ā€¢ STAR Overview ā€¢ Features and Capabilities ā€¢ Protective Device Types ā€¢ TCC Curves ā€¢ STAR Short-circuit ā€¢ PD Sequence of Operation ā€¢ Normalized TCC curves ā€¢ TCC Print and Settings Report ā€¢ Examples and Assignments
  • 3. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Objectives ā€¢ Human Safety ā€¢ Prevent injury and fatality
  • 4. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Real Side of Failure in Safety
  • 5. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Objectives ā€¢ Protection of Equipment ā€¢ Permit normal operation ā€¢ Isolate the equipment in case of abnormal conditions
  • 6. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Objectives ā€¢ Protection of System (Stability Protection) ā€¢ Over / Under Voltage ā€¢ Over / Under Frequency ā€¢ Rate of Frequency Change ā€¢ Islanding of System
  • 7. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Objectives ā€¢ Selectivity ā€¢ Minimal isolation of network with abnormal conditions ā€¢ Permit normal operation for rest of electrical network
  • 8. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection & Coordination ā€¢ Objectives ā€¢ Reasonable Cost ā€¢ Maximum achievable reliability for protection and coordination at minimal cost ā€¢ Science, Experience, and Art ā€¢ Sensitivity to faults and insensitivity to normal operation ā€¢ Fast fault clearance with proper selectivity ā€¢ Minimal isolation of faulty area ā€¢ Capability to operate correctly under all predictable power system conditions
  • 9. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL References ā€¢ IEEE Std. 242-2001, IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (IEEE Buff Book) ā€¢ IEEE Std. 141-1993, IEEE Recommended Practice for Electric Power Distribution for Industrial Plants (IEEE Red Book) ā€¢ IEEE Std. 399-1997, IEEE Recommended Practice for Industrial and Commercial Power Systems Analysis (IEEE Brown Book) ā€¢ Other technical references
  • 10. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Study Procedure ā€¢ Prepare an accurate one-line diagram (relay diagrams) ā€¢ Obtain the available system current spectrum (operating load, overloads, fault kA) ā€¢ Determine the equipment protection criteria ā€¢ Select the appropriate protective devices / settings ā€¢ Plot the fixed points (operating/damage curves, FLA, ampacity, etc.) ā€¢ Obtain / plot the device characteristics curves ā€¢ Analyze the results
  • 11. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Required Data ā€¢ One-line diagrams (Relay diagrams) ā€¢ Power Grid Fault Current Data and Protective Device Settings ā€¢ Generator Data ā€¢ Transformer Data ā€¢ Motor Data ā€¢ Load Data ā€¢ Fault Currents ā€¢ Cable / Conductor Data ā€¢ Bus / Switchgear Data ā€¢ Instrument Transformer Data (CT, VT) ā€¢ Protective Device (PD) Data
  • 12. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection of Equipments ā€¢ Major Equipments (apparatus) ā€¢ Induction Motor ā€¢ Synchronous Motor ā€¢ Cable ā€¢ Transformer ā€¢ Generator ā€¢ Bus ā€¢ Transmission/Distribution Line
  • 13. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Equipment Protection Criteria ā€¢ Permit: Normal Running Condition ā€¢ Max permitted current at working conditions ā€¢ Environment temperature, cooling media, elevation, etc. ā€¢ Protect: Abnormal Fault Condition ā€¢ Excessive through fault current caused by: ā€¢ Improper design, installation, or operation of equipment ā€¢ Incidents
  • 14. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Excessive Currents ā€¢ Excessive currents in abnormal conditions ā€¢ Overload current ā€¢ (100-160% Full Load Amps) ā€¢ Short-time overload current ā€¢ (300-1000% Full Load Amps) ā€¢ Short-circuit current ā€¢ (300-1200% Full Load Amps)
  • 15. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Capability / Damage Curves t I I2 2 t Gen I2 t Motor Xfmr I2 t Cable I2 t
  • 16. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection Types ā€¢ Overcurrent ā€¢ Inverse Time Over Current (TOC) ā€¢ Instantaneous Over Current (IOC) ā€¢ Directional ā€¢ Differential
  • 17. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protection Types ā€¢ Impedance ā€¢ Distance ā€¢ Voltage ā€¢ Under/Over Voltage ā€¢ Frequency ā€¢ Under/Over Frequency ā€¢ Mechanical ā€¢ Pressure (Buchholz Relay)
  • 18. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Overcurrent Protection Overcurrent Characteristics ā€¢ Inverse Time Over Current (TOC) ā€¢ Simple, cheap, and large application in LV, and MV ā€¢ LV Breakers ā€¢ Represent tolerance band ā€¢ MCB, MCCB, ICCB, PCB ā€¢ Fuses ā€¢ Overload Heater ā€¢ Overload Relay Time-Current-Characteristics (TCC)
  • 19. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Overcurrent Protection Relay TOC Characteristics Relay TOC Curves ā€¢ Curve Shape Adaptation ā€¢ Equipment Protection ā€¢ Selectivity ā€¢ Time Margin at higher fault currents
  • 20. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL ETAP Star Overview ā€¢ Star Mode ā€¢ Creation of TCC and Star View ā€¢ Addition of devices to existing TCC ā€¢ Graphical and Editor adjustments ā€¢ Star View Options (top) ā€¢ Combine Curve (ETAP 11 enahncement) ā€¢ Star Mode and Star View difference
  • 21. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL ETAP Star Overview ā€¢ Supported Protective Devices and Functions ā€¢ Overload - CT based & Inline (49) ā€¢ Phase, neutral, ground, and negative sequence overcurrent (51/50) ā€¢ Voltage control and restraint overcurrent (51VC/51VR) ā€¢ Directional overcurrent (67) ā€¢ High impedance & percentage differential (87) ā€¢ Electronic & hydraulic reclosers (79) ā€¢ Relay interlock with HVCB, switch and contactor ā€¢ CT Ratio and multiple connections *Reverse power (32) and under/over voltage (27/59) are supported in Transient Stability
  • 22. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Low Voltage Protective Devices ā€¢ Low Voltage Circuit Breaker (LVCB) ā€¢ Power Circuit Breaker (PCB) ā€¢ UL 1066, ANSI C37.13, ANSI C37.16, ANSI C37.17 ā€¢ IEC60947-2 ā€¢ Insulated Case Circuit Breaker (ICCB) ā€¢ UL489 (Non-fused MCCB, 2 step stored energy closing mechanism, electronic trip, and drawout construction) ā€¢ IEC60947-2 ā€¢ Molded Case Circuit Breaker (MCCB) ā€¢ UL489 (integral unit and enclosed housing of insulating material) ā€¢ IEC60947-2 ā€¢ Miniature Circuit Breaker (MCB) ā€¢ UL489, UL508, UL1077 ā€¢ IEC60898
  • 23. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL LVCB Differences
  • 24. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Low Voltage Protective Devices ā€¢ LVCB Trip Units ā€¢ Thermal Magnetic ā€¢ Motor Circuit Protector (MCP) ā€¢ Solid State Trip (SST) or microprocessor based ā€¢ Electro-mechanical
  • 25. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL LV Protective Devices ā€¢ MCCB Trip Units ā€“ Thermal-Magnetic
  • 26. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL LV Protective Devices ā€¢ MCCB Trip Units ā€“ Magnetic Only
  • 27. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Low Voltage Protective Devices ā€¢ LVCB Trip Units ā€¢ Solid State Trip (SST) or microprocessor based ā€¢ Electro-mechanical ā€¢ Trip Unit Segments ā€¢ Long Time (LT ANSI; I> IEC) ā€¢ Short Time (ST ANSI; I>> IEC) ā€¢ Instantaneous (IT ANSI; I>>> IEC)
  • 28. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Fuse (Power Fuse) ā€¢ Non Adjustable Device (unless electronic) ā€¢ Continuous and Interrupting Rating ā€¢ Voltage Levels (Max kV) ā€¢ Interrupting Rating (sym, asym) ā€¢ Characteristic Curves ā€¢ Min. Melting ā€¢ Total Clearing ā€¢ Application (rating type: R, E, X, ā€¦)
  • 29. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Fuse Types ā€¢ Expulsion Fuse (Non-CLF) ā€¢ Current Limiting Fuse (CLF) ā€¢ Electronic Fuse (S&C Fault Fiter)
  • 30. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Minimum Melting Time Curve Total Clearing Time Curve
  • 31. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Current Limiting Fuse (CLF) ā€¢ Limits the peak current of short-circuit ā€¢ Reduces magnetic stresses (mechanical damage) ā€¢ Reduces thermal energy
  • 32. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Current Limiting ActionCurrent(peakamps) tm ta Ipā€™ Ip tc ta = tc ā€“ tm ta = Arcing Time tm = Melting Time tc = Clearing Time Ip = Peak Current Ipā€™ = Peak Let-thru Current Time (cycles)
  • 33. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL CLF Let-Through Chart
  • 34. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL CLF Let-Through Chart ā€¢ Assumptions: 1. Short-circuit X/R ā‰¤ Tested Short-circuit X/R, or Short-circuit power factor ā‰„ tested power factor
  • 35. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL CLF Let-Through Chart ā€¢ Assumptions 2. The fault is on the load terminal
  • 36. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL CLF Let-Through Chart ā€¢ Impact of Downstream Breaker ā€¢ The fault current passing through both PDs ā€¢ The breaker may start to open representing a dynamic impedance causing reduced let-through current with different trip time ā€¢ A combination test is needed to make sure this is not happening. This is a series rating test.
  • 37. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL CLF Let-Through Chart ā€¢ Assumptions 3. The sum of motor full load currents contribution between the series rated devices should not exceeds 1 percent of interrupting rating of lowest rated device.
  • 38. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Symmetrical RMS Amperes PeakLet-ThroughAmperes 100 A 60 A 7% PF (X/R = 14.3) 12,500 5,200 230,000 300 A 100,000 Let-Through Chart
  • 39. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Fuse Generally: ā€¢ CLF is a better short-circuit protection ā€¢ Non-CLF (expulsion fuse) is a better Overload protection ā€¢ Electronic fuses are typically easier to coordinate due to the electronic control adjustments
  • 40. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Zones of Protection ā€¢ Protective devices and protected equipment represent the ā€œProtection Zoneā€
  • 41. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Protection ā€¢ Motor Starting Curve ā€¢ Thermal Protection ā€¢ Locked Rotor Protection ā€¢ Fault Protection
  • 42. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Inrush Current First half cycle current showing current offset. Beginning of run up current showing load torque pulsations. Starting Current of a 4000Hp, 12 kV, 1800 rpm Motor Motor pull in current showing motor reaching synchronous speed
  • 43. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Protection LV Motor Protection MV Motor Protection
  • 44. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Protection ā€¢ Standards & References ā€¢ IEEE Std 620-1996 IEEE Guide for the Presentation of Thermal Limit Curves for Squirrel Cage Induction Machines. ā€¢ IEEE Std 1255-2000 IEEE Guide for Evaluation of Torque Pulsations During Starting of Synchronous Motors ā€¢ ANSI/ IEEE C37.96-2000 Guide for AC Motor Protection ā€¢ NEMA MG-1 Motors and Generators ā€¢ The Art of Protective Relaying ā€“ General Electric
  • 45. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Overload Relay / Heater ā€¢ Motor overload protection is provided by a device that models the temperature rise of the winding ā€¢ When the temperature rise reaches a point that will damage the motor, the motor is de- energized ā€¢ Overload relays are either bimetallic, melting alloy or electronic
  • 46. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Question What is Class 10 and Class 20 Thermal OLR curves?
  • 47. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Answer ā€¢ At 600% Current Rating: ā€“ Class 10 for fast trip, 10 seconds or less ā€“ Class 20 for, 20 seconds or less (commonly used) ā€“ There is also Class 15, 30 for long trip time (typically provided with electronic overload relays) 6 20
  • 48. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Answer
  • 49. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Overload Relay / Heater ā€¢ When the temperature at the combination motor starter is more than Ā±10 Ā°C (Ā±18 Ā°F) different than the temperature at the motor, ambient temperature correction of the motor current is required. ā€¢ An adjustment is required because the output that a motor can safely deliver varies with temperature. ā€¢ The motor can deliver its full rated horsepower at an ambient temperature specified by the motor manufacturers, normally + 40 Ā°C. At high temperatures (higher than + 40 Ā°C) less than 100% of the normal rated current can be drawn from the motor without shortening the insulation life. ā€¢ At lower temperatures (less than + 40 Ā°C) more than 100% of the normal rated current could be drawn from the motor without shortening the insulation life.
  • 50. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Starting and Thermal Limit Sample data provided by the manufacturer
  • 51. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Protection - Overload Pickup (NEC Art 430.32 ā€“ Continuous-Duty Motors) ā€¢ Thermal O/L (Device 49) Pickup ā€¢ Motors with marked Service Factor ā‰„ 1.15 ā€¢ Pickup = 125% of FLA ā€¢ Motors with temp. rise not over 40Ā°C ā€¢ Pickup = 125% of FLA ā€¢ All other motors ā€¢ 115% of FLA
  • 52. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Motor Protection ā€“ Inst. Pickup LOCKED ROTOR S d 1 I X X " PICK UP LOCKED ROTOR I RELAY PICK UP 1.2 TO 1.2 I PICK UP LOCKED ROTOR I RELAY PICK UP 1.6 TO 2 I with a time delay of 0.10 s (six cycles at 60 Hz) Recommended Instantaneous Setting: If the recommended setting criteria cannot be met, or where more sensitive protection is desired, the instantaneous relay (or a second relay) can be set more sensitively if delayed by a timer. This permits the asymmetrical starting component to decay out. A typical setting for this is:
  • 53. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Locked Rotor Protection ā€¢ Thermal Locked Rotor (Device 51) ā€¢ Starting Time (TS < TLR) ā€¢ LRA ā€¢ LRA sym ā€¢ LRA asym (1.5-1.6 x LRA sym) + 10% margin
  • 54. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Fault Protection (NEC Art / Table 430-52) ā€¢ Non-Time Delay Fuses ā€¢ 300% of FLA ā€¢ Dual Element (Time-Delay Fuses) ā€¢ 175% of FLA ā€¢ Instantaneous Trip Breaker ā€¢ 800% - 1300% of FLA* ā€¢ Inverse Time Breakers ā€¢ 250% of FLA *can be set up to 1700% for Design B (energy efficient) Motor
  • 55. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Low Voltage Motor Protection ā€¢ Usually pre-engineered (selected from Catalogs) ā€¢ Typically, motors larger than 2 Hp are protected by combination starters ā€¢ Overload / Short-circuit protection
  • 56. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL 200 HP MCP O/L Starting Curve I 2 T (49) MCP (50) (51) ts tLR LRAs LRAasym
  • 57. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Low-voltage Motor Ratings Range of ratings Continuous amperes 9-250 ā€” Nominal voltage (V) 240-600 ā€” Horsepower 1.5-1000 ā€” Starter size (NEMA) ā€” 00-9 Types of protection Quantity NEMA designation Overload: overload relay elements 3 OL Short circuit: circuit breaker current trip elements 3 CB Fuses 3 FU Undervoltage: inherent with integral control supply and three-wire control circuit ā€” ā€” Ground fault (when specified): ground relay with toroidal CT ā€” ā€”
  • 58. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Minimum Required Sizes of a NEMA Combination Motor Starter System MAXIMUM CONDUCTOR LENGTH FOR ABOVE AND BELOW GROUND CONDUIT SYSTEMS. ABOVE GROUND SYSTEMS HAVE DIRECT SOLAR EXPOSURE. 750 C CONDUCTOR TEMPERATURE, 450 C AMBIENT CIRCUIT BREAKER SIZE FUSESIZE CLASSJ FUSE MOTORHP 460VNECFLC STARTER SIZE MINIMUM SIZE GROUNDING CONDUCTOR FORA50%CURRENTCAPACITY MINIMUM WIRE SIZE MAXIMUM LENGTHFOR1% VOLTAGE DROP NEXT LARGEST WIRE SIZE USENEXT LARGERGROUND CONDUCTOR MAXIMUM LENGTHFOR1% VOLTAGE DROPWITH LARGERWIRE 250% 200% 150% 1 2.1 0 12 12 759 10 1251 15 15 15 5 1Ā½ 3 0 12 12 531 10 875 15 15 15 6 2 3.4 0 12 12 468 10 772 15 15 15 7 3 4.8 0 12 12 332 10 547 20 20 15 10 5 7.6 0 12 12 209 10 345 20 20 15 15 7Ā½ 11 1 12 10 144 8 360 30 25 20 20 10 14 1 10 8 283 6 439 35 30 25 30 15 21 2 10 8 189 6 292 50 40 30 45 20 27 2 10 6 227 4 347 70 50 40 60 25 34 2 8 4 276 2 407 80 70 50 70 30 40 3 6 2 346 2/0 610 100 70 60 90 40 52 3 6 2 266 2/0 469 150 110 90 110 50 65 3 2 2/0 375 4/0 530 175 150 100 125 60 77 4 2 2/0 317 4/0 447 200 175 125 150 75 96 4 2 4/0 358 250 393 250 200 150 200 100 124 4 1 250 304 350 375 350 250 200 250 125 156 5 2/0 350 298 500 355 400 300 250 350 150 180 5 4/0 500 307 750 356 450 350 300 400
  • 59. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Required Data - Protection of a Medium Voltage Motor ā€¢ Rated full load current ā€¢ Service factor ā€¢ Locked rotor current ā€¢ Maximum locked rotor time (thermal limit curve) with the motor at ambient and/or operating temperature ā€¢ Minimum no load current ā€¢ Starting power factor ā€¢ Running power factor ā€¢ Motor and connected load accelerating time ā€¢ System phase rotation and nominal frequency ā€¢ Type and location of resistance temperature devices (RTDs), if used ā€¢ Expected fault current magnitudes ā€¢ First Ā½ cycle current ā€¢ Maximum motor starts per hour
  • 60. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Medium-Voltage Class E Motor Controller Ratings Class El (without fuses) Class E2 (with fuses) Nominal system voltage 2300-6900 2300-6900 Horsepower 0-8000 0-8000 Symmetrical MVA interrupting capacity at nominal system voltage 25-75 160-570 Types of Protective Devices Quantity NEMA Designation Overload, or locked Rotor, or both: Thermal overload relay TOC relay IOC relay plus time delay 3 3 3 OL OC TR/O Thermal overload relay 3 OL TOC relay 3 OC IOC relay plus time delay 3 TR/OC Short Circuit: Fuses, Class E2 3 FU IOC relay, Class E1 3 OC Ground Fault TOC residual relay 1 GP Overcurrent relay with toroidal CT 1 GP NEMA Class E2 medium voltage starter NEMA Class E1 medium voltage starter
  • 61. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Thermal Limit Curve
  • 62. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Thermal Limit Curve Typical Curve
  • 63. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Cable Protection
  • 64. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Cable Protection ā€¢ Standards & References ā€¢ IEEE Std. 242-2001, IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (IEEE Buff Book) ā€¢ IEEE Std 835-1994 IEEE Standard Power Cable Ampacity Tables ā€¢ IEEE Std 848-1996 IEEE Standard Procedure for the Determination of the Ampacity Derating of Fire-Protected Cables ā€¢ IEEE Std 738-1993 IEEE Standard for Calculating the Current- Temperature Relationship of Bare Overhead Conductors ā€¢ The Okonite Company Engineering Data for Copper and Aluminum Conductor Electrical Cables, Bulletin EHB-98
  • 65. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Cable Protection 2 2 1 t A T 234 0.0297log T 234 The actual temperature rise of a cable when exposed to a short circuit current for a known time is calculated by: Where: A= Conductor area in circular-mils I = Short circuit current in amps t = Time of short circuit in seconds T1= Initial operation temperature (750C) T2=Maximum short circuit temperature (1500C)
  • 66. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Cable Short-Circuit Heating Limits Recommended temperature rise: B) CU 75-200C
  • 67. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Shielded Cable The normal tape width is 1Ā½ inches
  • 68. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL NEC Section 110-14 C ā€¢ (c) Temperature limitations. The temperature rating associated with the ampacity of a conductor shall be so selected and coordinated as to not exceed the lowest temperature rating of any connected termination, conductor, or device. Conductors with temperature ratings higher than specified for terminations shall be permitted to be used for ampacity adjustment, correction, or both. ā€¢ (1) Termination provisions of equipment for circuits rated 100 amperes or less, or marked for Nos. 14 through 1 conductors, shall be used only for conductors rated 60C (140F). ā€¢ Exception No. 1: Conductors with higher temperature ratings shall be permitted to be used, provided the ampacity of such conductors is determined based on the 6OC (140F) ampacity of the conductor size used. ā€¢ Exception No. 2: Equipment termination provisions shall be permitted to be used with higher rated conductors at the ampacity of the higher rated conductors, provided the equipment is listed and identified for use with the higher rated conductors. ā€¢ (2) Termination provisions of equipment for circuits rated over 100 amperes, or marked for conductors larger than No. 1, shall be used only with conductors rated 75C (167F).
  • 69. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Protection
  • 70. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Protection ā€¢ Standards & References ā€¢ National Electric Code 2011 Edition ā€¢ IEEE Std 242-1986; IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems ā€¢ C37.91-2000; IEEE Guide for Protective Relay Applications to Power Transformers ā€¢ C57.12.59; IEEE Guide for Dry-Type Transformer Through-Fault Current Duration. ā€¢ C57.109-1985; IEEE Guide for Liquid-Immersed Transformer Through- Fault-Current Duration ā€¢ APPLIED PROCTIVE RELAYING; J.L. Blackburn; Westinghouse Electric Corp; 1976 ā€¢ PROTECTIVE RELAYING, PRINCIPLES AND APPLICATIONS; J.L. Blackburn; Marcel Dekker, Inc; 1987
  • 71. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Categories ANSI/IEEE C-57.109 Minimum nameplate (kVA) Category Single-phase Three-phase I 5-500 15-500 II 501-1667 501-5000 III 1668-10,000 5001-30,000 IV above 10,000 above 30,000
  • 72. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Categories I, II
  • 73. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Category III
  • 74. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Category IV
  • 75. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer t (sec) I (pu) Thermal200 2.5 I 2 t = 1250 2 25Isc Mechanical K=(1/Z) 2 t (D-D LL) 0.87 (D-R LG) 0.58 Frequent Fault Infrequent Fault Inrush FLA
  • 76. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Protection MAXIMUM RATING OR SETTING FOR OVERCURRENT DEVICE PRIMARY SECONDARY Over 600 Volts Over 600 Volts 600 Volts or Below Transformer Rated Impedance Circuit Breaker Setting Fuse Rating Circuit Breaker Setting Fuse Rating Circuit Breaker Setting or Fuse Rating Not more than 6% 600 % 300 % 300 % 250% 125% (250% supervised) More than 6% and not more than 10% 400 % 300 % 250% 225% 125% (250% supervised) Table 450-3(A) source: NEC
  • 77. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Recommended Minimum Transformer Protection Protective system Winding and/or power system grounded neutral grounded Winding and/or power system neutral ungrounded Up to 10 MVA Above 10 MVA Up to 10 MVA Above 10 MVA Differential - āˆš - āˆš Time over current āˆš āˆš āˆš āˆš Instantaneous restricted ground fault āˆš āˆš - - Time delayed ground fault āˆš āˆš - - Gas detection āˆš - āˆš Over excitation - āˆš āˆš āˆš Overheating - āˆš - āˆš
  • 78. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Question What is ANSI Transformer Shift Curve?
  • 79. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Transformer Shift Factor
  • 80. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Dyg Transformer Through Fault
  • 81. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Question What is meant by Frequent and Infrequent Faults for transformers?
  • 82. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Frequent and Infrequent Faults * Should be selected by reference to the frequent-fault-incidence protection curve or for transformers serving industrial, commercial and institutional power systems with secondary-side conductors enclosed in conduit, bus duct, etc., the feeder protective device may be selected by reference to the infrequent-fault-incidence protection curve. (Frequent Fault = More than 10 through faults (lifetime) for category II and 5 faults for category III) Source Transformer primary-side protective device (fuses, relayed circuit breakers, etc.) may be selected by reference to the infrequent-fault- incidence protection curve Category II or III Transformer Fault will be cleared by transformer primary-side protective device Optional main secondary ā€“side protective device. May be selected by reference to the infrequent-fault- incidence protection curve Feeder protective device Fault will be cleared by transformer primary-side protective device or by optional main secondary- side protection device Fault will be cleared by feeder protective device Infrequent-Fault Incidence Zone* Feeders Frequent-Fault Incidence Zone*
  • 83. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Selective Coordination ā€¢ Inherent Selective Devices ā€¢ Examples ā€¢ Differential Relays ā€¢ Pilot Wire Relays ā€¢ Transformer Sudden Pressure Relays ā€¢ More expensive ā€¢ Justified based on value or role of protected equipment in supply of power
  • 84. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Selective Coordination ā€¢ Overcurrent Selectivity Rules ā€¢ Downstream device curve is located to the left and below of upstream device curve for range of applicable currents ā€¢ Sufficient time margin for operation of downstream before upstream
  • 85. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Selective Coordination
  • 86. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Margins for Selectivity ā€¢ Relay - Relay coordination requires ā€¢ Minimum of 0.25 to 0.40 seconds time margin between the relay curves at the maximum fault current to account for the interrupting time of the circuit breaker, relay over-travel time, relay tolerances, and a safety factor ā€¢ For induction disk relays, the minimum desired time margin for a 5 cycle breaker is generally 0.30 seconds ā€¢ 5 cycle breaker 0.08 seconds ā€¢ relay over-travel 0.10 seconds ā€¢ CT ratio & safety factor 0.12 seconds ā€¢ Total = 0.30 seconds ā€¢ For digital relays, the minimum desired time margin for a 5 cycle breaker is generally 0.25 seconds ā€¢ 5 cycle breaker 0.08 seconds ā€¢ relay accuracy +.02 sec. 0.04 seconds ā€¢ CT ratio & safety factor 0.13 seconds ā€¢ Total = 0.25 seconds ā€¢ Margin between pickup levels of > 10% for two devices in series.
  • 87. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Margins for Selectivity ā€¢ Electromechanical Relay - Fuse coordination requires a minimum 0.22 second time margin between the curves. ā€¢ Electromechanical Relay - Low Voltage Breaker coordination requires a minimum 0.22 second time margin between the curves. ā€¢ Static Relay - Fuse coordination requires a minimum 0.12 second time margin between the curves. ā€¢ Static Relay - Low Voltage Breaker coordination requires a minimum 0.12 second time margin between the curves. ā€¢ Fuse - Fuse coordination requires that the total clearing time of the downline fuse curve be less than 75% of the minimum melt time of the upline fuse curve to account for pre-loading. ā€¢ Fuse - Low Voltage Breaker coordination requires that the down-line breaker maximum time curve be less than 75% of the minimum melt time of the up-line fuse curve to account for pre-loading.
  • 88. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Margins for Selectivity ā€¢ Fuse - Relay coordination requires a minimum 0.3 second time margin between the curves. ā€¢ Low Voltage Breaker - Fuse coordination requires a minimum 0.1 second time margin between the curves to allow for temperature variations in the fuse. ā€¢ Low Voltage Breaker - Low Voltage Breaker coordination requires only that the plotted curves do not intersect since all tolerances and operating times are included in the published characteristics. ā€¢ Low Voltage Breaker - Relay coordination requires a minimum 0.2 second time margin between the curves.
  • 89. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Protection ā€¢ NEC Requirements for Solidly Grounded System ā€¢ Articles 215.10 (feeders), 230.95 (services), 240.13 (overcurrent protection), etc. ā€¢ 260 V (150 V, L-G) ā‰¤ Line-Line Voltage ā‰¤ 600 V ā€¢ Main disconnect is rated 1000 A or more ā€¢ GF Settings is limited to 1200 A pickup and 1 sec for ground faults > 3000 A ā€¢ Industry Practice ā€¢ Grounded wye systems 2400 V or more
  • 90. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Detection ā€¢ General Concept ā€¢ Measurement of Residual (IR) or Zero Sequence current (3I0) ā€¢ IR = 3I0 = Ia + Ib + Ic (Vector Summation) ā€¢ Balanced Fault: Ia = Ib = Ic and IR = 3I0 = 0 ā€¢ Unbalanced system Ia ā‰  Ib ā‰  Ic and IR = 3I0 > 0
  • 91. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Detection ā€¢ Direct (Ground, 50G/51G) ā€¢ Grounded-phase (3I0) current is detected directly with a current transformer installed in the grounded neutral conductor.
  • 92. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Detection ā€¢ Balance Flux (Ground, 50G/51G) (Core Balance or Zero Sequence CT) ā€¢ Grounded-phase current (IR) is directly detected by a doughnut-type current transformer installed around the three phase conductors Note: The equipment grounding conductors (including conductor shields) must not be installed through the current transformer.
  • 93. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Detection ā€¢ Residual ā€¢ Grounded-phase current is detected as the unbalance in the current produced by the phase current transformers
  • 94. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL ETAP Terminology ā€¢ Relay Ground Function ā€¢ Externally measured residual current (2 inputs) ā€¢ Relay Neutral Function ā€¢ Relay internally measured residual current (6 inputs)
  • 95. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Relay Ground Inputs
  • 96. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Relay Sensitive Ground Inputs
  • 97. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Relay Neutral Inputs
  • 98. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Relay Function Diagram
  • 99. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Coordination ā€¢ GF Selective Coordination ā€¢ Device ground fault overcurrent coordination with: ā€¢ Other devices with ground detection ā€¢ Other devices with phase overcurrent detection ā€¢ Combination of phase and ground fault detection ā€¢ Minimum and Maximum Fault ā€¢ Phase and single-line to ground fault coordination
  • 100. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Ground Fault Coordination Individual Phase and GF Curves Phase and GF Curve Combination
  • 101. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Protective Devices ā€¢ Relays ā€¢ Microprocessor/electronic ā€¢ More expensive, faster, multiple functionality ā€¢ Electromechanical ā€¢ Simple, cheap, slower, limited functionality
  • 102. Ā© 2011 Operation Technology, Inc. PROPRIETARY & CONFIDENTIAL Relay ANSI Device Numbers ā€¢ 21 ā€“ Distance ā€¢ 27 ā€“ Under Voltage ā€¢ 32 ā€“ Directional Power ā€¢ 49 ā€“ Thermal Overload ā€¢ 50 ā€“ Instantaneous Over Current ā€¢ 51 ā€“ AC Inverse Over Current ā€¢ 52 ā€“ AC Circuit Breaker ā€¢ 59 ā€“ Overvoltage ā€¢ 67 ā€“ AC Directional Over Current ā€¢ 79 ā€“ AC Recloser ā€¢ 81 ā€“ Frequency ā€¢ 87 ā€“ Differential ā€¢ P ā€“ Phase ā€¢ N ā€“ Neutral ā€¢ G ā€“ Ground ā€¢ SG ā€“ Sensitive Ground ā€¢ V ā€“ Voltage ā€¢ VC ā€“ Voltage Control ā€¢ VR ā€“ Voltage Restrained