This document outlines the schedule for engineering activities related to Modules MM1 and MM2 for an FPSO project in Ghana. Key activities include commencement of basic and detailed engineering, HAZID and HAZOP reviews, model reviews at 30%, 60%, and 90% completion, and development of process documentation including basic design data, simulations, calculations, flow diagrams and utility summaries. Major milestones are completion of engineering, commencement of module fabrication, and modules being available at the Singapore Yard by April 2016. The schedule shows the planned timing of engineering activities and reviews from March 2015 through June 2016.