SlideShare a Scribd company logo
NUE 505A Electrical systems safety Assessment preparation
Protection devices
10 -1 1 10 10 2 10 3 4.5 Time (sec) Current (x I RATED ) B Magnetic Section Thermal Section Circuit Breaker Types
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 7.5 C Thermal Section New Magnetic operation Circuit Breaker Types
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 12 D Thermal Section New Magnetic operation Circuit Breaker Types
RCD,s
Residual Current Device  RCD Safety Switch LOAD N A/s Supply When the circuit is in good condition. (No Earth Faults) (I  active =  I  neutral) = No Flux = No Induced EMF Supply to the Load is Maintained I A I N
RCD with Earth Fault LOAD N A/s Supply  When an Earth Faults occurs. (I  active     I  neutral) = Flux in Core = Induced EMF The fault is Isolated
Safety Switch N A/s Supply Not Earthed A person can receive a shock with a “Safety Switch” installed Another point to consider: An RCD rated at 40Amps will not trip (like a C/B) if say 52Amps will to flow through the device.
3   RCD  3   LOAD  N L1 Supply LOAD L2 L3
3   RCD  1   LOAD  N Supply LOAD A
 
 
 
 
Max Demand Calculations Domestic Lighting
 
 
 
 
Max Demand Calculations Domestic Power
 
 
 
 
Max Demand Calculations Domestic Appliances
 
 
Max Demand Calculations Domestic Multi-phase
 
 
 
Max Demand Calculations Non-Domestic Lighting
A Small motel installation contains the following
 
 
 
Max Demand Calculations Non-Domestic Power
A factory has the following loading, calculate the maximum demand consideration.
 
 
Max Demand Calculations Non-Domestic Appliances
A factory has the following three-phase loads,what would be the loading for a maximum demand calculation.
 
 
Cable selection
 
 
 
 
 
Cable selection based on voltage drop
 
 
 
 
 
 
Voltage drop Single-phase
 
 
 
 
 
Voltage drop Multi-phase
 
 
 
Conductor size based on voltage drop
 
 
 
 
 
 
 
Overall multi-phase voltage drop calculation
 
 
 
Fault loop impedance
AS/NZ 3000:2000 - 1.7.4.3.3 ,[object Object],[object Object],[object Object],[object Object],6.3.3.2.1 6.3.3.2.2 Amendment AS/NZS 3000:2000
The Fault Loop  1. The impedance needs to be low enough, to allow a high enough fault current, to operate the protective device, within a given time period. (6.3.3.2.2)  2. The Earth Loop Impedance is matched to the Protective Device Tripping Characteristics. 3 Phase Supply N/L
Earth System ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object]
Earth System ♦  Z LOOP  =  Z ACTIVE  + Z EARTH  + Z  NEUTRAL  + Z  TX ♦  All these will limit current and dictate the fault current that will flow. Load N/L 16A MEN Link must be left intact
Earth System AS3000: Wiring Rules
Earth System
10 -1 1 10 10 2 10 3 4 Time (sec) Current (x I RATED ) B Circuit Breaker Types 1x Magnetic Section Thermal Section
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 7.5 C Thermal Section New Magnetic operation
10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 12.5 D Thermal Section New Magnetic operation
Earth System Load 16A N/L MEN Link must be left intact
Earth System Load 16A N/L Active Earth MEN Link must be left intact
 
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object],2. Calculate the maximum length allowable  for the Final Sub Circuit and come in under that.
Earth System Load 16A N/L With 80% of voltage drop here in a fault,  the FSC must have 80% of the total Fault Loop Impedance. Where the length and CSA of the mains is  not known, we may assume that 80% of the voltage drop under fault conditions will occur in the final sub-circuit (B5.2.1b).
0.8 x V NOM  x CSA ACTIVE  x CSA  EARTH L MAX  =  I TRIP  x    x (CSA ACTIVE  + CSA  EARTH )    = 22.5 x 10 -3   ohm-mm 2 /metre for Copper = 36 x 10 -3  ohm-mm 2 /metre   for Aluminium ,[object Object],[object Object],[object Object],[object Object],(Page 237 AS3000)
 
Earth System 1 Measure the Fault Loop Impedance… ,[object Object],[object Object],2. Calculate the maximum length allowable  for the Final Sub Circuit and come in under that. 3.  Measure the A/A-E impedance. (Compare it to Table 3.2 AS3017)
AS3017: Testing and Inspection Guidlines ,[object Object],[object Object],[object Object],[object Object]
MAIN SWITCHBOARD Load
But what if the cable/CB size is not there on that table?
Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away.  C/B is 400A type “C”.  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  7.  Measure the actual loop impedance. MAIN SWITCHBOARD Load Z = V/I A V I    5A
[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  Note that including X L  of the cable only  comes into play above 120mm 2 Z R X L
[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…
[object Object],[object Object],[object Object],[object Object],Say, 300mm 2  orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away…  R A  + R E  =  0.0298  X A  + X E  = 0.02065  Z =  0.0362  R ACTIVE R EARTH X ACTIVE X EARTH
4.  Is Loop Z < Maximum Allowable Z? Last Step…: ,[object Object],[object Object],Z =  0.0362  Z = 0.0512 
Remember the last question? Q:  Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device. To ensure that we do create a high enough fault current, fault loop impedance must be low enough.
AS3017: Testing and Inspection Guidlines
A Simplified  Circuit We need to look at a complete loop (circuit) 3 Phase Supply The current path includes the: Supply Transformer, Distribution System, Mains, Protection Device, Final Sub-Circuit including the Load N/L
B5.1 Maximum Circuit Length ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
3 Phase Supply There will always be more than 80% of the Nominal Voltage AS/NZ3000:2000  B5.2.1 b Zext Zint Zint =  0.8 Uo I a B5.2.1
Isolation, disconnection and reconnection procedures
Safe Isolation   ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
 
MEN Connection
MEN SYSTEM
Recent studies have shown that 95% of electricians do not fully understand the MEN system.  This figure comes from the Electrical Contractors Association of Queensland who were conducting training sessions throughout Queensland during 1998.  They asked electricians to draw a MEN system and explain it. Only 5% could!!! MEN System
MEN Connection Consumer Mains MAIN SWITCHBOARD Circuit Protective Devices Earth Link Neutral Link Main Switch
MEN Connection Circuit Protective Devices Consumer Mains MAIN SWITCHBOARD Neutral Link Main Switch So why do we earth the  neutral at the board?
Load Direct Earthing System 16A Q: Will the  fuse blow? FAULT R TOTAL = 23.5  I FAULT  = V/R = 240/23.5    10A 0.3  0.2  23 
Load MEN Earthing System 0.3  0.2  16A R TOTAL = 1  Q: Will the  fuse blow? 0.5  I FAULT  = V/R = 240/1 = 240A N/L FAULT R RETURN  = 0.5//23      0.5  23 
Q:  Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device.
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link NORMAL LOAD CURRENT Typical  Earth stake to Earth resistance  = 30   - 2k  Main Switch Load Low R Consumer Mains
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link FAULT CURRENT Main Switch Load A Low Resistance earth  CREATES A high fault current. Low R
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link What are the values given by AS3000 on earth resistance? Main Switch Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link 2   maximum 2   maximum Main Switch Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link Main Switch < 0.5  (6.3.3.2.2) Load “ The resistance of the protective  earthing conductors shall be  low enough to permit the  passage of current  necessary to operate the  overcurrent protective device” (6.3.3.2.2)
Why Test
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link Load OPEN  CIRCUIT MEN Connection
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link NORMAL LOAD CURRENT Everything operates  OK!!! Load
THEREFORE FAULT  CURRENT WILL BE VERY LOW MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT But RESISTANCE TO EARTH IS  USUALLY HIGH. Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT AND PROTECTION WILL NOT TRIP. Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE  THAT IF ACTIVE IS SHORTED TO EARTH, ALL EARTHS ARE LIVE!!! Load
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE  ALSO THAT UNDER NORMAL CONDITIONS EVERYTHING ELSE WILL STILL WORK OK!!! Load
Open Circuit MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral Link Earthing Bar Main  Earthing  Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch What happens on  Distribution Boards  when the MSB MEN link open-circuits ? AS3000 5.6.6b(iv)
[object Object]
MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link A N LIVEN UP:  -Earth stake -Water pipes -Taps -Sink -Cases of appliances Load
MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral Link Earthing Bar Main  Earthing  Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch What happens on  Distribution Boards  when Main Active  and Main Neutral are swapped? N A
[object Object],[object Object]
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link OPEN  CIRCUIT Neutral Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30   - 2k  Load Voltages... High Voltage Low Voltage High Voltage  on  Earth System
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30   - 2k  High Voltage Low Voltage Livens: -Taps, -Sinks -Water pipes -Metal cases of appliances Load Voltages... High Voltage  on  Earth System
Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
Q: What causes “tingles” on taps? VD N =4V MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads 4V 0V
Testing
TEST  EQUIPMENT  REQUIRED  (AS3017 1.6.2) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TEST  EQUIPMENT  REQUIRED  (AS3017 1.6.2) ,[object Object],[object Object],[object Object],[object Object],[object Object]
TESTS ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Step 1: Visual Examination
General Requirements Clause No. What to look for 2.9.6  No exposed live parts.  E.g. no excessive removal of insulation at terminations, terminal covers in place etc. Double insulation maintained where required.  E.g. no single insulation in ceiling above light fittings, no more than 100mm single insulation in wall behind accessories, insulating shrouds installed where required. 1.9 All equipment is approved/compliant with Australian Standards and in good condition.  E.g. no unsafe/damaged or non-compliant equipment installed.
Consumer Mains Clause No. What to look for 3.4.1 Consumers Mains should be able to carry the maximum demand current of the installation with some capacity to spare.  As a guide: 16mm2 (or parallel 6mm2) for overhead mains, 10mm2 for underground mains.
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Initial Procedures ,[object Object],[object Object],[object Object]
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
[object Object],[object Object],[object Object],[object Object],STEP 2: Earth Continuity
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Known resistance
STEP 3: Insulation Resistance ,[object Object],[object Object],[object Object],[object Object],1. Consumer Mains: Disconnect any service bonding conductor:
STEP 3: Insulation Resistance ,[object Object],[object Object],[object Object],2. Final Subcircuits: With all C/B’s ON or fuse wedges IN, and all switches in the installation ON:
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Switched Active
STEP 3: Insulation Resistance ,[object Object]
[object Object],[object Object],[object Object],[object Object],STEP 4: Polarity Tests
STEP 5: Correct Circuit Connections ,[object Object],[object Object]
MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective  Devices Earthing Bar DISTRIBUTION BOARD  2 Circuit Protective Devices Neutral  Link Earthing Bar Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD  1 Main Switch A N Thank You The End
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety
Electrical Systems Safety

More Related Content

What's hot

Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
khongai
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
Ana Metaxas
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Ang Sovann
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
Rohini Haridas
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
Revathi Subramaniam
 
1_Intro + Per Unit.pdf
1_Intro + Per Unit.pdf1_Intro + Per Unit.pdf
1_Intro + Per Unit.pdf
LiewChiaPing
 
Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection System
HarshalJain48
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
Vinod Srivastava
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
yohannes feleke
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
ZuhairQadri
 
Electrical hazardous
Electrical hazardousElectrical hazardous
Electrical hazardous
Dashne DM
 
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
Mayank Velani
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
Muhd Hafizi Idris
 
Electrical fuse power point presentation
Electrical fuse power point presentation Electrical fuse power point presentation
Electrical fuse power point presentation
prasantakcs
 
Unsymmetrical Fault
Unsymmetrical FaultUnsymmetrical Fault
Unsymmetrical Fault
Mohd Zahid Mohammad Ali
 
Circuit breakers basics
Circuit breakers   basicsCircuit breakers   basics
Circuit breakers basics
AtheenaPandian Enterprises
 
Protection
ProtectionProtection
Protection
Ameen San
 
Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Protective relaying
Protective relayingProtective relaying
Protective relaying
Mark Anthony Enoy
 

What's hot (20)

Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
 
1_Intro + Per Unit.pdf
1_Intro + Per Unit.pdf1_Intro + Per Unit.pdf
1_Intro + Per Unit.pdf
 
Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection System
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
 
Electrical hazardous
Electrical hazardousElectrical hazardous
Electrical hazardous
 
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
IS : 3043 -1987 CODE OF PRACTICE FOR EARTHING(REACTANCE GROUNDING)
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
 
Electrical fuse power point presentation
Electrical fuse power point presentation Electrical fuse power point presentation
Electrical fuse power point presentation
 
Unsymmetrical Fault
Unsymmetrical FaultUnsymmetrical Fault
Unsymmetrical Fault
 
Circuit breakers basics
Circuit breakers   basicsCircuit breakers   basics
Circuit breakers basics
 
Protection
ProtectionProtection
Protection
 
Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Protective relaying
Protective relayingProtective relaying
Protective relaying
 

Similar to Electrical Systems Safety

Fire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC ConsiderationsFire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC Considerations
James S Nasby
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
MAHMOUDMOHAMED431205
 
Lecture 18
Lecture 18Lecture 18
Lecture 18
Forward2025
 
1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx
jackiewalcutt
 
3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf
LiewChiaPing
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1
Raymund Cortez
 
Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.
Mustafa Ismail
 
Si Intro(100413)
Si Intro(100413)Si Intro(100413)
Si Intro(100413)
imsong
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.ppt
Ahmed Ramadan
 
Ehv line design
Ehv line designEhv line design
Ehv line design
Demsew Mitiku
 
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
LiewChiaPing
 
Lecture_18.ppt
Lecture_18.pptLecture_18.ppt
Lecture_18.ppt
Kifle Godana
 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
Chandrabhan Sharma
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
Thorne & Derrick International
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicioPanasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
Anonimo Goncen
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
ingcortez
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
Jobin Abraham
 
Sub station design
Sub station designSub station design
Sub station design
JunaedulIslam
 

Similar to Electrical Systems Safety (20)

Fire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC ConsiderationsFire Pump Short Circuit and WIC Considerations
Fire Pump Short Circuit and WIC Considerations
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
 
Lecture 18
Lecture 18Lecture 18
Lecture 18
 
1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx1. Determine the voltage drop at the motor frame for an earth .docx
1. Determine the voltage drop at the motor frame for an earth .docx
 
DC Component of Fault Current
DC Component of Fault CurrentDC Component of Fault Current
DC Component of Fault Current
 
3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf3_Overcurrent Protection.pdf
3_Overcurrent Protection.pdf
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1
 
Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.
 
Si Intro(100413)
Si Intro(100413)Si Intro(100413)
Si Intro(100413)
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.ppt
 
Ehv line design
Ehv line designEhv line design
Ehv line design
 
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptxCHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
CHAPTER 3 Voltage Drop and Short Circuit Analysis.pptx
 
Lecture_18.ppt
Lecture_18.pptLecture_18.ppt
Lecture_18.ppt
 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicioPanasonic SA-AK450P SA-AK450PC - Manual de servicio
Panasonic SA-AK450P SA-AK450PC - Manual de servicio
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
 
Sub station design
Sub station designSub station design
Sub station design
 

More from Talia Carbis

4.1.13 Light Demand 3
4.1.13 Light Demand 34.1.13 Light Demand 3
4.1.13 Light Demand 3Talia Carbis
 
4.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part24.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part2Talia Carbis
 
4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 TableTalia Carbis
 
4.1.10 Light Demand 2
4.1.10 Light Demand 24.1.10 Light Demand 2
4.1.10 Light Demand 2Talia Carbis
 
4.1.9 Light Demand 1
4.1.9 Light Demand 14.1.9 Light Demand 1
4.1.9 Light Demand 1Talia Carbis
 
4.1.8 Light Demand
4.1.8 Light Demand4.1.8 Light Demand
4.1.8 Light DemandTalia Carbis
 
4.1.7 Example Domestic 3
4.1.7 Example Domestic 34.1.7 Example Domestic 3
4.1.7 Example Domestic 3Talia Carbis
 
4.1.6 Example Domestic 2
4.1.6 Example Domestic 24.1.6 Example Domestic 2
4.1.6 Example Domestic 2Talia Carbis
 
4.1.5 Example Domestic 1
4.1.5 Example Domestic 14.1.5 Example Domestic 1
4.1.5 Example Domestic 1Talia Carbis
 
4.1.3 Example Solution Three
4.1.3 Example Solution Three4.1.3 Example Solution Three
4.1.3 Example Solution ThreeTalia Carbis
 
4.1.2 Example Three
4.1.2 Example Three4.1.2 Example Three
4.1.2 Example ThreeTalia Carbis
 
4.1.1 Example Single
4.1.1 Example Single4.1.1 Example Single
4.1.1 Example SingleTalia Carbis
 
14.5.4 Example 1 Part 1
14.5.4 Example 1 Part 114.5.4 Example 1 Part 1
14.5.4 Example 1 Part 1Talia Carbis
 
14.5.8 Example 1 Part 5
14.5.8 Example 1 Part 514.5.8 Example 1 Part 5
14.5.8 Example 1 Part 5Talia Carbis
 

More from Talia Carbis (20)

7.4.6 slip
7.4.6 slip7.4.6 slip
7.4.6 slip
 
4.2.1 Better Load
4.2.1 Better Load4.2.1 Better Load
4.2.1 Better Load
 
4.1.13 Light Demand 3
4.1.13 Light Demand 34.1.13 Light Demand 3
4.1.13 Light Demand 3
 
4.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part24.1.12 Light Demand 2 Table Part2
4.1.12 Light Demand 2 Table Part2
 
4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table4.1.11 Light Demand 2 Table
4.1.11 Light Demand 2 Table
 
4.1.10 Light Demand 2
4.1.10 Light Demand 24.1.10 Light Demand 2
4.1.10 Light Demand 2
 
4.1.9 Light Demand 1
4.1.9 Light Demand 14.1.9 Light Demand 1
4.1.9 Light Demand 1
 
4.1.8 Light Demand
4.1.8 Light Demand4.1.8 Light Demand
4.1.8 Light Demand
 
4.1.7 Example Domestic 3
4.1.7 Example Domestic 34.1.7 Example Domestic 3
4.1.7 Example Domestic 3
 
4.1.6 Example Domestic 2
4.1.6 Example Domestic 24.1.6 Example Domestic 2
4.1.6 Example Domestic 2
 
4.1.5 Example Domestic 1
4.1.5 Example Domestic 14.1.5 Example Domestic 1
4.1.5 Example Domestic 1
 
4.1.4 Step 2
4.1.4 Step 24.1.4 Step 2
4.1.4 Step 2
 
4.1.3 Example Solution Three
4.1.3 Example Solution Three4.1.3 Example Solution Three
4.1.3 Example Solution Three
 
4.1.2 Example Three
4.1.2 Example Three4.1.2 Example Three
4.1.2 Example Three
 
4.1.1 Example Single
4.1.1 Example Single4.1.1 Example Single
4.1.1 Example Single
 
5.4.4 LR Circuits
5.4.4 LR Circuits5.4.4 LR Circuits
5.4.4 LR Circuits
 
14.5.4 Example 1 Part 1
14.5.4 Example 1 Part 114.5.4 Example 1 Part 1
14.5.4 Example 1 Part 1
 
14.5.3 Improve
14.5.3 Improve14.5.3 Improve
14.5.3 Improve
 
14.1.2 TRA Power
14.1.2 TRA Power14.1.2 TRA Power
14.1.2 TRA Power
 
14.5.8 Example 1 Part 5
14.5.8 Example 1 Part 514.5.8 Example 1 Part 5
14.5.8 Example 1 Part 5
 

Recently uploaded

Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 

Recently uploaded (20)

Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 

Electrical Systems Safety

  • 1. NUE 505A Electrical systems safety Assessment preparation
  • 2.
  • 4. 10 -1 1 10 10 2 10 3 4.5 Time (sec) Current (x I RATED ) B Magnetic Section Thermal Section Circuit Breaker Types
  • 5. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 7.5 C Thermal Section New Magnetic operation Circuit Breaker Types
  • 6. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) 12 D Thermal Section New Magnetic operation Circuit Breaker Types
  • 8. Residual Current Device RCD Safety Switch LOAD N A/s Supply When the circuit is in good condition. (No Earth Faults) (I active = I neutral) = No Flux = No Induced EMF Supply to the Load is Maintained I A I N
  • 9. RCD with Earth Fault LOAD N A/s Supply  When an Earth Faults occurs. (I active  I neutral) = Flux in Core = Induced EMF The fault is Isolated
  • 10. Safety Switch N A/s Supply Not Earthed A person can receive a shock with a “Safety Switch” installed Another point to consider: An RCD rated at 40Amps will not trip (like a C/B) if say 52Amps will to flow through the device.
  • 11. 3  RCD 3  LOAD N L1 Supply LOAD L2 L3
  • 12. 3  RCD 1  LOAD N Supply LOAD A
  • 13.  
  • 14.  
  • 15.  
  • 16.  
  • 17. Max Demand Calculations Domestic Lighting
  • 18.  
  • 19.  
  • 20.  
  • 21.  
  • 22. Max Demand Calculations Domestic Power
  • 23.  
  • 24.  
  • 25.  
  • 26.  
  • 27. Max Demand Calculations Domestic Appliances
  • 28.  
  • 29.  
  • 30. Max Demand Calculations Domestic Multi-phase
  • 31.  
  • 32.  
  • 33.  
  • 34. Max Demand Calculations Non-Domestic Lighting
  • 35. A Small motel installation contains the following
  • 36.  
  • 37.  
  • 38.  
  • 39. Max Demand Calculations Non-Domestic Power
  • 40. A factory has the following loading, calculate the maximum demand consideration.
  • 41.  
  • 42.  
  • 43. Max Demand Calculations Non-Domestic Appliances
  • 44. A factory has the following three-phase loads,what would be the loading for a maximum demand calculation.
  • 45.  
  • 46.  
  • 48.  
  • 49.  
  • 50.  
  • 51.  
  • 52.  
  • 53. Cable selection based on voltage drop
  • 54.  
  • 55.  
  • 56.  
  • 57.  
  • 58.  
  • 59.  
  • 61.  
  • 62.  
  • 63.  
  • 64.  
  • 65.  
  • 67.  
  • 68.  
  • 69.  
  • 70. Conductor size based on voltage drop
  • 71.  
  • 72.  
  • 73.  
  • 74.  
  • 75.  
  • 76.  
  • 77.  
  • 78. Overall multi-phase voltage drop calculation
  • 79.  
  • 80.  
  • 81.  
  • 83.
  • 84. The Fault Loop 1. The impedance needs to be low enough, to allow a high enough fault current, to operate the protective device, within a given time period. (6.3.3.2.2) 2. The Earth Loop Impedance is matched to the Protective Device Tripping Characteristics. 3 Phase Supply N/L
  • 85.
  • 86.
  • 87. Earth System ♦ Z LOOP = Z ACTIVE + Z EARTH + Z NEUTRAL + Z TX ♦ All these will limit current and dictate the fault current that will flow. Load N/L 16A MEN Link must be left intact
  • 88. Earth System AS3000: Wiring Rules
  • 90. 10 -1 1 10 10 2 10 3 4 Time (sec) Current (x I RATED ) B Circuit Breaker Types 1x Magnetic Section Thermal Section
  • 91. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 7.5 C Thermal Section New Magnetic operation
  • 92. 10 -1 1 10 10 2 10 3 Time (sec) Current (x I RATED ) Circuit Breaker Types 1x 12.5 D Thermal Section New Magnetic operation
  • 93. Earth System Load 16A N/L MEN Link must be left intact
  • 94. Earth System Load 16A N/L Active Earth MEN Link must be left intact
  • 95.  
  • 96.
  • 97.
  • 98. Earth System Load 16A N/L With 80% of voltage drop here in a fault, the FSC must have 80% of the total Fault Loop Impedance. Where the length and CSA of the mains is not known, we may assume that 80% of the voltage drop under fault conditions will occur in the final sub-circuit (B5.2.1b).
  • 99.
  • 100.  
  • 101.
  • 102.
  • 104. But what if the cable/CB size is not there on that table?
  • 105.
  • 106. Say, 300mm 2 orange circ. cable supplying a 415V, 350A, 3-phase motor through underground conduit 140mtrs away… 7. Measure the actual loop impedance. MAIN SWITCHBOARD Load Z = V/I A V I  5A
  • 107.
  • 108.
  • 109.
  • 110.
  • 111.
  • 112. Remember the last question? Q: Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device. To ensure that we do create a high enough fault current, fault loop impedance must be low enough.
  • 113. AS3017: Testing and Inspection Guidlines
  • 114. A Simplified Circuit We need to look at a complete loop (circuit) 3 Phase Supply The current path includes the: Supply Transformer, Distribution System, Mains, Protection Device, Final Sub-Circuit including the Load N/L
  • 115.
  • 116. 3 Phase Supply There will always be more than 80% of the Nominal Voltage AS/NZ3000:2000 B5.2.1 b Zext Zint Zint = 0.8 Uo I a B5.2.1
  • 117. Isolation, disconnection and reconnection procedures
  • 118.
  • 119.  
  • 122. Recent studies have shown that 95% of electricians do not fully understand the MEN system. This figure comes from the Electrical Contractors Association of Queensland who were conducting training sessions throughout Queensland during 1998. They asked electricians to draw a MEN system and explain it. Only 5% could!!! MEN System
  • 123. MEN Connection Consumer Mains MAIN SWITCHBOARD Circuit Protective Devices Earth Link Neutral Link Main Switch
  • 124. MEN Connection Circuit Protective Devices Consumer Mains MAIN SWITCHBOARD Neutral Link Main Switch So why do we earth the neutral at the board?
  • 125. Load Direct Earthing System 16A Q: Will the fuse blow? FAULT R TOTAL = 23.5  I FAULT = V/R = 240/23.5  10A 0.3  0.2  23 
  • 126. Load MEN Earthing System 0.3  0.2  16A R TOTAL = 1  Q: Will the fuse blow? 0.5  I FAULT = V/R = 240/1 = 240A N/L FAULT R RETURN = 0.5//23  0.5  23 
  • 127. Q: Why do we want a low resistance earth wire?  To CREATE a high enough fault current to trip the protective device.
  • 128. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link NORMAL LOAD CURRENT Typical Earth stake to Earth resistance = 30  - 2k  Main Switch Load Low R Consumer Mains
  • 129. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Earth Link Neutral Link FAULT CURRENT Main Switch Load A Low Resistance earth CREATES A high fault current. Low R
  • 130. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link What are the values given by AS3000 on earth resistance? Main Switch Load
  • 131. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link 2  maximum 2  maximum Main Switch Load
  • 132. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Consumer Mains Earth Link Neutral Link Main Switch < 0.5  (6.3.3.2.2) Load “ The resistance of the protective earthing conductors shall be low enough to permit the passage of current necessary to operate the overcurrent protective device” (6.3.3.2.2)
  • 134. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link Load OPEN CIRCUIT MEN Connection
  • 135. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Earth Link Neutral Link NORMAL LOAD CURRENT Everything operates OK!!! Load
  • 136. THEREFORE FAULT CURRENT WILL BE VERY LOW MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT But RESISTANCE TO EARTH IS USUALLY HIGH. Load
  • 137. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT AND PROTECTION WILL NOT TRIP. Load
  • 138. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE THAT IF ACTIVE IS SHORTED TO EARTH, ALL EARTHS ARE LIVE!!! Load
  • 139. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Earth Link Neutral Link FAULT CURRENT NOTE ALSO THAT UNDER NORMAL CONDITIONS EVERYTHING ELSE WILL STILL WORK OK!!! Load
  • 140. Open Circuit MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Main Earthing Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch What happens on Distribution Boards when the MSB MEN link open-circuits ? AS3000 5.6.6b(iv)
  • 141.
  • 142. MAIN SWITCHBOARD MEN Connection Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link A N LIVEN UP: -Earth stake -Water pipes -Taps -Sink -Cases of appliances Load
  • 143. MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Main Earthing Conductor Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch What happens on Distribution Boards when Main Active and Main Neutral are swapped? N A
  • 144.
  • 145. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link OPEN CIRCUIT Neutral Load
  • 146. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
  • 147. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link LOAD CURRENT Load
  • 148. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30  - 2k  Load Voltages... High Voltage Low Voltage High Voltage on Earth System
  • 149. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Lo load Resistance Hi stake - earth Resistance: 30  - 2k  High Voltage Low Voltage Livens: -Taps, -Sinks -Water pipes -Metal cases of appliances Load Voltages... High Voltage on Earth System
  • 150. Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
  • 151. Q: What causes “tingles” on taps? VD N =4V MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads
  • 152. Q: What causes “tingles” on taps? MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link All Loads 4V 0V
  • 154.
  • 155.
  • 156.
  • 157.
  • 158. General Requirements Clause No. What to look for 2.9.6 No exposed live parts. E.g. no excessive removal of insulation at terminations, terminal covers in place etc. Double insulation maintained where required. E.g. no single insulation in ceiling above light fittings, no more than 100mm single insulation in wall behind accessories, insulating shrouds installed where required. 1.9 All equipment is approved/compliant with Australian Standards and in good condition. E.g. no unsafe/damaged or non-compliant equipment installed.
  • 159. Consumer Mains Clause No. What to look for 3.4.1 Consumers Mains should be able to carry the maximum demand current of the installation with some capacity to spare. As a guide: 16mm2 (or parallel 6mm2) for overhead mains, 10mm2 for underground mains.
  • 160.
  • 161.
  • 162.
  • 163.
  • 164.
  • 165.
  • 166. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
  • 167.
  • 168. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Known resistance
  • 169.
  • 170.
  • 171. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light
  • 172. MAIN SWITCHBOARD Circuit Protective Devices Main Switch Consumer Mains Earth Link Neutral Link Light Switched Active
  • 173.
  • 174.
  • 175.
  • 176. MEN Connection MAIN SWITCHBOARD Circuit Protective Devices Neutral Link Sub Mains Sub Mains ` Neutral Link DISTRIBUTION BOARD 3 Circuit Protective Devices Earthing Bar DISTRIBUTION BOARD 2 Circuit Protective Devices Neutral Link Earthing Bar Sub Mains Circuit Protective Devices Neutral Link Earthing Bar DISTRIBUTION BOARD 1 Main Switch A N Thank You The End