The summary provides an update on the status of Phase 2 of the Dulles Corridor Metrorail Project Silver Line extension: 1) Construction of the five new stations along the rail line and the rail yard at Dulles Airport is 78% complete, with substantial completion scheduled for August 2019. 2) Work continues on station construction including mechanical, electrical and plumbing work, as well as canopy, platform, and pavilion erection. Guideway installation and utility relocation is also ongoing. 3) The project remains on budget at $2.778 billion with $353.5 million in contingency remaining unutilized from the $551.5 million total contingency budget.