SlideShare a Scribd company logo
Dulles Corridor Metrorail Project
Silver Line Phase 2 Implementation
Board Transportation Committee Update
February 27, 2018
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2
Project Status
Phase 1
• Old Meadow Road Realignment – 90% design complete.
Construction completion scheduled for the end of 2018.
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 78% complete
• Package A (Rail line, system, and stations) – 78%
• Package B (Rail yard at Dulles) – 79%
• Contractual Substantial Completion – August 2019
• WMATA Board to establish Revenue Operations Date
3
• Reston Town Center Station – Mechanical/electrical/plumbing
rough-in, pavilion area work ongoing
• Herndon Station – Electrical work and skylight installation, south
pavilion construction, pedestrian bridge decks poured
• Innovation Station – Detailing work, pedestrian bridge erection,
pavilion construction, skylights installed, electrical and plumbing
Phase 2 – Station Construction
4
• Dulles Airport Station – Canopy steel erection complete, station
mechanical/electrical/plumbing work, tunnel tie-in
• Loudoun Gateway Station – Station precast, roof erection,
foundation and columns forming for north pavilion, pedestrian
bridge assembled and erected
• Ashburn Station - Station concrete work, precast erection, pavilion
work and pedestrian bridge assembled and erected
Phase 2 – Station Construction
5
• Pedestrian bridges set at Herndon, Reston Town Center,
and Innovation Center Station
• Aerial guideway rail and concrete ties, switch work, track
• Utility Relocation ongoing
• Traction Power Feeders – continue to install manholes
and duct bank to tie into Traction Power Substations
(TPSS) and Tie Breaker Stations (TBS)
• Ground grids being installed to TPSS and TBS, continue
34.5kV cable installation and conduit installation
• Three TPSS structures delivered and assembled on slab
Phase 2 – Aerial, Track, Utilities, Systems
6
• Under Construction - Service and Inspection Building,
Maintenance Way Building, Transit Police Building, Train
Wash Facility, Warehouse Facility, Vehicle Storage Facility
• Ongoing - Track work in rail yard, utility installation, duct
bank, storm lines, sanitary lines, water lines, site lighting,
and site road work.
Phase 2 – Rail Yard at Dulles Airport
7
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.628B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $198.0M
• Remaining Contingency $353.5M
Phase 2 – Cost Summary
8
• Total Project Estimate: $44.5M
• Construction Progress: 70% complete
• Garage Bridge Erection: Completed Nov 2017
-Access road re-opened as scheduled-
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): February 2019 – March 2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
Herndon Monroe Bridge Construction
9
10
Herndon Metrorail Garage
PHOTOS
11
• Total Project Estimate: $52 million
• Construction Progress: 30% complete
• Precast Fabrication: October 2017
• Precast Erection: April 2018
Schedule
• Construction Award: March 2017
• Construction: April 2017
• Ready for Occupancy: April/May 2019
Innovation Metrorail Garage
12
Innovation Metrorail Garage
13
Reston Town Center Station
Reston Town Center Pavilions
Reston Town Center Pavilions
14
Herndon Station
Herndon Station Pavilions
Herndon Station Pedestrian Bridge
Herndon Station South Pavilion
15
Innovation Center Station
16
Dulles Airport Station
17
Rail Yard Dulles Airport
18
QUESTIONS?

More Related Content

What's hot

rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
Robert Lee - CEng, MICE, PMP
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
Crosstown TO
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
Crosstown TO
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
Fairfax County
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
Fairfax County
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Fairfax County
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
Fairfax County
 
Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017
Devyn Barrie
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
Pablo Miguel Jurado
 
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
Embark Richmond Highway Comprehensive Plan Amendment and Transportation ProjectsEmbark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
Fairfax County
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPOFDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
Miami-Dade Transportation Planning Organization
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
Fairfax County
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Fairfax County
 
Station Design Update Meeting: Open House Avenue Road to Bayview
Station Design Update Meeting: Open House Avenue Road to BayviewStation Design Update Meeting: Open House Avenue Road to Bayview
Station Design Update Meeting: Open House Avenue Road to Bayview
Crosstown TO
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
Fairfax County
 
Disinfection System
Disinfection SystemDisinfection System
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)
Parag Chaubey
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
Crosstown TO
 

What's hot (20)

rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
Embark Richmond Highway Comprehensive Plan Amendment and Transportation ProjectsEmbark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPOFDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
Station Design Update Meeting: Open House Avenue Road to Bayview
Station Design Update Meeting: Open House Avenue Road to BayviewStation Design Update Meeting: Open House Avenue Road to Bayview
Station Design Update Meeting: Open House Avenue Road to Bayview
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
 

Similar to Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Fairfax County
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Fairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
TownofAddison
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
Fairfax County
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
Fairfax County
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Crosstown TO
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Fairfax County
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014
WaterfrontTO
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
Toronto Public Consultation Unit
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Fairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
Fairfax County
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Crosstown TO
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
Crosstown TO
 

Similar to Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
Fairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Fairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
Fairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Fairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
Fairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Fairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Fairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Fairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Fairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
ckn2izdm
 
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
bhavenpr
 
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
The Lifesciences Magazine
 
projet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdfprojet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdf
EdouardHusson
 
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
SABC News
 
Organisations.pdf k[poikdip-jhhohuhejhnjhn
Organisations.pdf k[poikdip-jhhohuhejhnjhnOrganisations.pdf k[poikdip-jhhohuhejhnjhn
Organisations.pdf k[poikdip-jhhohuhejhnjhn
bhavenpr
 
The Rise of Christian Persecution In Islamic Countries (1).pdf
The Rise of Christian Persecution In Islamic Countries (1).pdfThe Rise of Christian Persecution In Islamic Countries (1).pdf
The Rise of Christian Persecution In Islamic Countries (1).pdf
ECSPE - Saving the Persecuted and Enslaved
 
13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
VoterMood
 
12062024_First India Newspaper Jaipur.pdf
12062024_First India Newspaper Jaipur.pdf12062024_First India Newspaper Jaipur.pdf
12062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
MadholalHussain
 
16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHYलालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
VoterMood
 
Reuters Institute Digital News Report 2024
Reuters Institute Digital News Report 2024Reuters Institute Digital News Report 2024
Reuters Institute Digital News Report 2024
Reuters Institute for the Study of Journalism, Oxford University
 
15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
rittaajmal71
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
Filippo64
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
LUMINATIVE MEDIA/PROJECT COUNSEL MEDIA GROUP
 
A draft Ukraine-Russia treaty from April 2022
A draft Ukraine-Russia treaty from April 2022A draft Ukraine-Russia treaty from April 2022
A draft Ukraine-Russia treaty from April 2022
dynamo777
 

Recently uploaded (19)

在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
 
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
Snigdha-Sreenath-Minor-v-Travancore-Devaswom-Board-WPCNO-39847-OF-2023-2024-L...
 
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
Federal Authorities Urge Vigilance Amid Bird Flu Outbreak | The Lifesciences ...
 
projet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdfprojet de traité négocié à Istanbul (anglais).pdf
projet de traité négocié à Istanbul (anglais).pdf
 
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
ACSA confirms operational readiness ahead the arrival of Heads of State at OR...
 
Organisations.pdf k[poikdip-jhhohuhejhnjhn
Organisations.pdf k[poikdip-jhhohuhejhnjhnOrganisations.pdf k[poikdip-jhhohuhejhnjhn
Organisations.pdf k[poikdip-jhhohuhejhnjhn
 
The Rise of Christian Persecution In Islamic Countries (1).pdf
The Rise of Christian Persecution In Islamic Countries (1).pdfThe Rise of Christian Persecution In Islamic Countries (1).pdf
The Rise of Christian Persecution In Islamic Countries (1).pdf
 
13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
 
12062024_First India Newspaper Jaipur.pdf
12062024_First India Newspaper Jaipur.pdf12062024_First India Newspaper Jaipur.pdf
12062024_First India Newspaper Jaipur.pdf
 
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
Saraikistan; unveiling the demand for a seperate province._20240522_011317_00...
 
16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf16062024_First India Newspaper Jaipur.pdf
16062024_First India Newspaper Jaipur.pdf
 
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHYलालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
लालू यादव की जीवनी LALU PRASAD YADAV BIOGRAPHY
 
Reuters Institute Digital News Report 2024
Reuters Institute Digital News Report 2024Reuters Institute Digital News Report 2024
Reuters Institute Digital News Report 2024
 
15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf15062024_First India Newspaper Jaipur.pdf
15062024_First India Newspaper Jaipur.pdf
 
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...#WenguiGuo#WashingtonFarm  Guo Wengui Wolf son ambition exposed to open a far...
#WenguiGuo#WashingtonFarm Guo Wengui Wolf son ambition exposed to open a far...
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
 
A draft Ukraine-Russia treaty from April 2022
A draft Ukraine-Russia treaty from April 2022A draft Ukraine-Russia treaty from April 2022
A draft Ukraine-Russia treaty from April 2022
 

Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation

  • 1. Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update February 27, 2018 Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation
  • 2. 2 Project Status Phase 1 • Old Meadow Road Realignment – 90% design complete. Construction completion scheduled for the end of 2018. • VDOT punch list ongoing – MWAA and Bechtel to complete • Phase 1 close out - $2.982B (no change) Phase 2 • Overall Phase 2 – 78% complete • Package A (Rail line, system, and stations) – 78% • Package B (Rail yard at Dulles) – 79% • Contractual Substantial Completion – August 2019 • WMATA Board to establish Revenue Operations Date
  • 3. 3 • Reston Town Center Station – Mechanical/electrical/plumbing rough-in, pavilion area work ongoing • Herndon Station – Electrical work and skylight installation, south pavilion construction, pedestrian bridge decks poured • Innovation Station – Detailing work, pedestrian bridge erection, pavilion construction, skylights installed, electrical and plumbing Phase 2 – Station Construction
  • 4. 4 • Dulles Airport Station – Canopy steel erection complete, station mechanical/electrical/plumbing work, tunnel tie-in • Loudoun Gateway Station – Station precast, roof erection, foundation and columns forming for north pavilion, pedestrian bridge assembled and erected • Ashburn Station - Station concrete work, precast erection, pavilion work and pedestrian bridge assembled and erected Phase 2 – Station Construction
  • 5. 5 • Pedestrian bridges set at Herndon, Reston Town Center, and Innovation Center Station • Aerial guideway rail and concrete ties, switch work, track • Utility Relocation ongoing • Traction Power Feeders – continue to install manholes and duct bank to tie into Traction Power Substations (TPSS) and Tie Breaker Stations (TBS) • Ground grids being installed to TPSS and TBS, continue 34.5kV cable installation and conduit installation • Three TPSS structures delivered and assembled on slab Phase 2 – Aerial, Track, Utilities, Systems
  • 6. 6 • Under Construction - Service and Inspection Building, Maintenance Way Building, Transit Police Building, Train Wash Facility, Warehouse Facility, Vehicle Storage Facility • Ongoing - Track work in rail yard, utility installation, duct bank, storm lines, sanitary lines, water lines, site lighting, and site road work. Phase 2 – Rail Yard at Dulles Airport
  • 7. 7 • Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.628B • Contingency Utilization • Total Contingency $551.5M • Total Contingency Utilized $198.0M • Remaining Contingency $353.5M Phase 2 – Cost Summary
  • 8. 8 • Total Project Estimate: $44.5M • Construction Progress: 70% complete • Garage Bridge Erection: Completed Nov 2017 -Access road re-opened as scheduled- Schedule • Construction Award: October 2016 • Construction (new garage): November 2016 – March 2019 • Construction (existing garage): February 2019 – March 2019 • Ready for Occupancy: April 2019 Herndon Metrorail Garage
  • 9. Herndon Monroe Bridge Construction 9
  • 11. 11 • Total Project Estimate: $52 million • Construction Progress: 30% complete • Precast Fabrication: October 2017 • Precast Erection: April 2018 Schedule • Construction Award: March 2017 • Construction: April 2017 • Ready for Occupancy: April/May 2019 Innovation Metrorail Garage
  • 13. 13 Reston Town Center Station Reston Town Center Pavilions Reston Town Center Pavilions
  • 14. 14 Herndon Station Herndon Station Pavilions Herndon Station Pedestrian Bridge Herndon Station South Pavilion