The Silver Line Phase 2 project is 88% complete overall. Substantial completion is scheduled for August 2019. The total budget remains $2.778 billion with $1.868 billion expended so far and $281.3 million in remaining contingency funds. Station construction is ongoing at Reston Town Center, Herndon, Innovation Center, Dulles Airport, Loudoun Gateway, and Ashburn. Work on the aerial guideway, track, utilities and systems is also in progress. Construction of support facilities at the rail yard at Dulles Airport is over 90% complete. The Herndon Metrorail garage is 96% complete and on schedule to be ready for occupancy in April 2019. The Innovation Center Metrorail garage is