This document provides information about a citizens information meeting on June 15, 2017 regarding improvements to Jefferson Manor Phase IIIA along Albemarle Drive and Edgehill Drive. The meeting will include a presentation on the proposed design plans followed by Q&A. Improvements will include replacing curb and gutters, upgrading sidewalks, adding a new storm sewer system, repaving roads, and relocating utilities. Construction is scheduled to begin in late 2018 and be completed by summer 2019. Citizens are encouraged to provide comments to help inform the final design plans.
Fairfax County Commercial and Industrial Property Tax for TransportationFairfax County
The Fairfax County Board of Supervisors approved an ordinance establishing the commercial and industrial property tax for transportation in September 2007. Collection of this revenue source began in 2008 (FY 2009). This revenue is just one source of many revenue sources that are needed to fund transportation improvements.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Fairfax County Commercial and Industrial Property Tax for TransportationFairfax County
The Fairfax County Board of Supervisors approved an ordinance establishing the commercial and industrial property tax for transportation in September 2007. Collection of this revenue source began in 2008 (FY 2009). This revenue is just one source of many revenue sources that are needed to fund transportation improvements.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Subdivision Design covers different phases of the land development process. We study Florida subdivision laws, site evaluation, boundaries, topographic and control surveys, and environmental and cultural considerations. Students design lot and building arrangements, all streets, and drainage channels and detention basins.
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
The Purpose
Inform the community about the upcoming project,
Phase 1 of the project is eminent
Gravity Sewer on Langley Lane
Force main from Langley High School to Georgetown Pike
Lakevale Sewer Improvements Community MeetingFairfax County
During the Preliminary Engineering
We are currently revising our website to match the recent revisions with the project (Same Location)
Mid-November we will have a Public Input Meeting via Zoom
Mid December we will make the Final Recommend of the Alternative available on out website
During the Detailed Design
Maintain and update the website
Public Input at the 35% design (March 2022)
Public Outreach Meeting at the 95% design summer/fall 2022
During the Construction
Install a Project Sign
Hold a Preconstruction meeting and routine status meetings as we proceed
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
The first public meeting for the Clifton Boulevard Transportation Enhancement Program. The meeting was held at Emerson Elementary School in Lakewood, OH on 4/07/2010.
Visit www.EnhanceClifton.com for more information.
Congress Parkway Construction Overview, January 2010Daniel X. O'Neil
Congress Parkway improvement project
Michigan Avenue to Wells Street.
Includes history, background, project goals & scope, as well as schedule and public outreach tactics
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
31052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
In a May 9, 2024 paper, Juri Opitz from the University of Zurich, along with Shira Wein and Nathan Schneider form Georgetown University, discussed the importance of linguistic expertise in natural language processing (NLP) in an era dominated by large language models (LLMs).
The authors explained that while machine translation (MT) previously relied heavily on linguists, the landscape has shifted. “Linguistics is no longer front and center in the way we build NLP systems,” they said. With the emergence of LLMs, which can generate fluent text without the need for specialized modules to handle grammar or semantic coherence, the need for linguistic expertise in NLP is being questioned.
01062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
हम आग्रह करते हैं कि जो भी सत्ता में आए, वह संविधान का पालन करे, उसकी रक्षा करे और उसे बनाए रखे।" प्रस्ताव में कुल तीन प्रमुख हस्तक्षेप और उनके तंत्र भी प्रस्तुत किए गए। पहला हस्तक्षेप स्वतंत्र मीडिया को प्रोत्साहित करके, वास्तविकता पर आधारित काउंटर नैरेटिव का निर्माण करके और सत्तारूढ़ सरकार द्वारा नियोजित मनोवैज्ञानिक हेरफेर की रणनीति का मुकाबला करके लोगों द्वारा निर्धारित कथा को बनाए रखना और उस पर कार्यकरना था।
‘वोटर्स विल मस्ट प्रीवेल’ (मतदाताओं को जीतना होगा) अभियान द्वारा जारी हेल्पलाइन नंबर, 4 जून को सुबह 7 बजे से दोपहर 12 बजे तक मतगणना प्रक्रिया में कहीं भी किसी भी तरह के उल्लंघन की रिपोर्ट करने के लिए खुला रहेगा।
role of women and girls in various terror groupssadiakorobi2
Women have three distinct types of involvement: direct involvement in terrorist acts; enabling of others to commit such acts; and facilitating the disengagement of others from violent or extremist groups.
03062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
1. Jefferson Manor Phase IIIA
(Albemarle Drive and Portions
of Edgehill Drive)
Citizens Information Meeting
June 15, 2017, 7:00PM to 9:00PM (Mount Eagle Elem. School)
(Brief Formal Presentation Starts at 7:15)
1
2. Project Team
Supervisor McKay’s office
Fairfax County Department of Transportation (FCDOT)
• Transportation Design (TDD)
• Capital Projects and Operations (CPOD)
Fairfax County Department of Public Works & Environmental Services
(DPWES)
• Construction (UDCD)
• Land Acquisition (LAD)
Design Consultant (RDA)
2
3. Meeting Schedule
Tonight’s Agenda
• Jefferson Manor Phase IIIA Design Plan
presentation followed by general Q&A
• Return to display boards, one-on-one discussion,
individual questions
• Meeting Ends – 9:00PM
3
4. Meeting Purpose
Tonight’s Purpose:
• Provide an overview of the project improvements
• Provide the public an update on on-going activities related to
project, current status, and next steps
• Provide an opportunity for the public to review the current
design and provide input
4
5. Project Background
• Part of Jefferson Manor Master Plan (1992)
• Locally Funded Project: Est. Project Cost = $2.6 Million
• Proposed roadway and drainage improvements will meet VDOT
Standards, for VDOT maintenance
• Pedestrian facility will meet all VDOT & County Standards for
maintenance and for ADA accessibility compliance.
5
7. Project Overview
Existing Conditions:
Albemarle Drive / Edgehill Drive
• Substandard Width Sidewalks
• Lack of Drainage Infrastructure
• Existing Utility Poles in Sidewalk
• Private Retaining Walls Leaning
into Sidewalk Space
7
8. Proposed Design
8
Proposed Design:
• Curb and Gutter to be replaced with
current VDOT standard
• Existing Sidewalks upgraded from 4’
Width to 5’ Width, in compliance with
current VDOT Standards
• New concrete steps meeting current
VDOT Standards
• New concrete driveway aprons
9. Proposed Design
9
Proposed Design Continued:
• New Storm Sewer/Drainage System
• New Road Pavement and Striping
• Maintain Existing On-Street Parking
• Relocation and/or Upgrade of Existing Utilities (underground and
overhead)
• Upgrade Street Lighting
10. Proposed Design
10
Proposed Design Continued:
• Potential Impacts to Private Property
o Tree and Vegetation Impacts are anticipated
o Existing non-standard structures (i.e. retaining walls, steps etc.) within
VDOT right-of-way will be removed and/or rebuilt on private property, in
coordination with property owners.
o If property is to be impacted during construction, we will obtain
easements or right-of-way before work begins.
11. Land Acquisition
Land Acquisition Process:
• Plats will be prepared showing easements and/or right-of-way
needed.
• Land Acquisition Agent will contact property owners to negotiate.
11
12. Construction
Construction
• We will coordinate with you well in advance of construction start.
• Vehicle access to properties may be temporarily unavailable.
• On-street parking will be limited in construction areas.
12
13. Project Schedule
Tentative Project Schedule:
Pre-Final Design: Current
Land Acquisition Schedule : Fall 2017 to Spring 2018
Utility Relocation Schedule: Spring 2018
Final Design: Summer 2018
Begin Construction: Late 2018
Construction Completion: Summer 2019
13
14. Citizen Input
14
Ways to Comment
• Fill out & submit a comment sheet tonight (Comment Box Provided)
• Comment section on project website:
http://www.fairfaxcounty.gov/fcdot/jefferson_manor.htm
• Email Latesa Turner: Latesa.Turner@fairfaxcounty.gov
• Fill out and mail a comment sheet:
Latesa Turner
Fairfax County Dept. of Transportation
4050 Legato Road, Suite 400
Fairfax, VA 22033