Embark Richmond Highway
Comprehensive Plan Amendment
and Transportation Projects
Update on
Vanessa Aguayo-Thomas, AJ Hamidi, and Bob Pikora, Dept. of Transportation
Meghan Van Dam, Dept. of Planning and Zoning
Board Transportation Committee
February 27, 2018
Presentation Overview
Embark Components
• Richmond Highway Comprehensive Plan
Amendment
• Richmond Highway Corridor Improvements
• Bus Rapid Transit (BRT) System
2
Richmond Highway Corridor
Active Projects:
• Richmond Highway Comprehensive Plan
Amendment (Huntington Metrorail
Station to Fort Belvoir)
• Richmond Highway Corridor
Improvements Project (Mt. Vernon Hwy
to Napper Road)
• Richmond Highway BRT Program
(Huntington Metrorail Station to Fort
Belvoir)
Route 1 Multimodal Alternatives Analysis
• Virginia Department of Rail and Public
Transportation (DRPT) completed in
February 2015
• Included 16-mile segment of Route 1
from Huntington Metrorail Station to
Woodbridge
• Recommended BRT along the entire
length of Richmond Highway corridor
and long term plan to extend the
Metrorail Yellow Line to Hybla Valley/
Gum Springs
4
7.3 mi
Phase I:
Bus Rapid Transit (BRT)
Huntington to Hybla Valley
Phase II:
BRT Hybla Valley to Fort
Belvoir
BRT Phase III:
Fort Belvoir to
Woodbridge
Phase IV:
Metrorail Yellow Line
Extension to Hybla
Valley
Route 1 Multimodal Alternatives Analysis
(Virginia Dept. of Rail and Public Transit,
2015)
Route 1 Multimodal Alternatives Analysis
• Consistent 6 lanes – Richmond Highway
• Continuous bike/pedestrian facilities – both sides of Richmond Hwy
• Median-running Bus Rapid Transit (BRT) system for Richmond Hwy
• Future Metrorail extension to Hybla Valley
5
Richmond Highway
Comprehensive Plan Amendment
6
Board
Authorization
Scoping;
Existing
Conditions
Corridor-wide
Planning
Objectives;
BRT and
Metrorail
Policy
Guidance
Station
Locations,
Land Uses,
Cross-
section
Transportation, Public
Facilities Assessment;
Station Area Planning
Public
Hearings
Early 2018
Spring-Fall 2017
Fall-Winter 2016
Summer 2016
Fall-Spring 2016
PUBLIC OUTREACH
6 Community Meetings
24 Advisory Group
Meetings
Comprehensive Plan Amendment Process
COMMUNITY ENGAGEMENT
Spring 2015
7
Guiding Planning Principles
• Revitalization
• Interconnected transportation
modes
• High-quality urban design
• Health and leisure
• Economic success of the
corridor
• Environmental restoration
• Stewardship of historic
resources
• Communities stability 8
Transportation Principles
Safe, reliable, effective, interconnected
modes:
• Reserve exclusive right-of-way for BRT and
re-purpose Richmond Highway service
drives
• Provide infrastructure to encourage public
transit use, walking, and bicycling for all ages
and abilities, to reduce vehicular traffic
• Provide complete street network (grids of
streets) within CBCs and connect to adjacent
neighborhoods
• Consolidate entrances, reduce curb cuts,
improve access and enhance signage
9
Richmond Highway Cross-Section
10
• Majority of redevelopment remains
planned within CBCs
• Clearer definition of identity and
place for each of the CBCs
• Areas in between remain planned for
primarily residential and institutional
uses
Community Business Centers (CBCs)
11
Comprehensive Plan Vision for the CBCs
“The vision for the Richmond Highway CBCs honors
the legacy of the corridor and the area’s unique
ecological features to achieve a series of well-
connected, transit-oriented activity nodes that
celebrate the corridor’s history, embrace its
environmental features, and strengthen the greater
Richmond Highway community.”
12
Multimodal Connectivity within CBCs
Existing Beacon Groveton
Shopping Center Proposed Beacon Groveton
Concept
Potential
BRT Station* Illustrative image of a
complete street designed
for walking, biking and
vehicles
13
Richmond Highway Corridor Improvements
14
• Jeff Todd Way to Napper
Road – 2.9 Miles
• Last remaining four-lane
section north of Fort Belvoir
• Planned improvements:
• Widen to 6 lanes
• Reserve ROW in median
for BRT system
• Bike & Pedestrian
improvements on both
sides of ROW
Richmond Highway Corridor Improvements
15
• Administered by VDOT in coordination with FCDOT
• Purpose and Need:
• Accommodate existing and future travel demand
• Accommodate future BRT system
• Improve safety for all users
• Status and Schedule:
• Currently in preliminary engineering
• Design Public Hearing – Fall 2018
• Construction planned from 2023 to 2025 (overlaps BRT Project)
• Plan to open to traffic in late 2025
Richmond Highway Corridor Improvements (Cont.)
16
• Current Activities:
• Establishing Preferred Intersection Design Option at Two Locations
• Sacramento/Cooper intersection
• Buckman Road/Mount Vernon Memorial Highway
• Preparing for Public Information Meeting #3 – April 4, 2018
• Conducting Environmental and Stormwater Management Analysis
• Cost:
• Overall Cost approximately $215 M
• Funds currently available = $44 M
Richmond Highway Corridor Improvements (Cont.)
17
Richmond Highway Corridor Improvements (Cont.)
The intent of this exhibit is to depict the configuration of elements within the
Proposed right-of-way. For clarity, potential landscaping is not depicted.
18
Bus Rapid Transit (BRT) System
19
Richmond Highway BRT Program (Phase I & II)
• Limits: Huntington Metrorail Station to Fort
Belvoir
• Two dedicated lanes in median
• Nine potential stations
• Two Phases:
• Phase I: Huntington Metrorail to Hybla
Valley/Gum Springs
• 5 stations
• Phase II: Hybla Valley/Gum Springs to Fort
Belvoir
• 4 stations
20
BRT Program
• Staff is working with a specialized team of
Consultants known as the Program Management
Consultant (PMC)
• Set-up with a governance structure and includes
an executive committee to go over key BRT
milestones
• Advisory group has been set up to provide input
on BRT issues such as community impacts,
station concepts, etc. Consists of 14 members
from both Lee and Mount Vernon Districts
• BRT kick off meetings anticipated for April 2018
21
BRT Activities
• Submitted NVTA Application for funding -
November 2017
• Technical Working groups such as design, public
involvement, station design, etc. meet on
regular basis
• Met with FTA - November 7, 2017 and January
24, 2018
• Scope of work for next phase of effort includes
Environmental Review, 20% Design and Branding
to be executed in March 2018
22
BRT Activities (Cont.)
• Scope of work for next phase of effort includes:
• Environmental Review
• 20% Design
• Branding
• Cost:
• Overall Cost approximately $524 M*
• Funds currently available = $45 M
23*Based on DRPT Multimodal AA Study
4
Richmond Highway Corridor Projects
24
Questions?
25

More Related Content

What's hot

Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031
Toronto Public Consultation Unit
 
Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016
Toronto Public Consultation Unit
 
Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2
StittsvilleCentral.ca
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Fairfax County
 
Scarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 PresentationScarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 Presentation
Toronto Public Consultation Unit
 
Briefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning UpdateBriefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning Update
Toronto Public Consultation Unit
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County
 
Scarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of ReferenceScarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of Reference
Toronto Public Consultation Unit
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016
VDOT Northern Virginia
 
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Toronto Public Consultation Unit
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
StittsvilleCentral.ca
 
Toronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting PresentationToronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting Presentation
Toronto Public Consultation Unit
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
Fairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County
 
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
Fairfax County
 
SmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display BoardsSmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display Boards
Toronto Public Consultation Unit
 
2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG
Toronto Public Consultation Unit
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
Toronto Public Consultation Unit
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Fairfax County
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost Allocations
Fairfax County
 

What's hot (20)

Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031
 
Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016
 
Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
Scarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 PresentationScarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 Presentation
 
Briefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning UpdateBriefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning Update
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
 
Scarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of ReferenceScarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of Reference
 
Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016Fairfax County Parkway Study Meeting, June 2016
Fairfax County Parkway Study Meeting, June 2016
 
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 
Toronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting PresentationToronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting Presentation
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
 
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
Update on Tysons Transportation Projects: Board Transportation Committee: Feb...
 
SmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display BoardsSmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display Boards
 
2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost Allocations
 

Similar to Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects

Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives Analysis
Fairfax County
 
Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)
Fairfax County
 
VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014
SCVTA
 
2015 06-15 relief line presentation
2015 06-15 relief line presentation2015 06-15 relief line presentation
2015 06-15 relief line presentation
Toronto Public Consultation Unit
 
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Fairfax County
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County
 
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax County
 
2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review
City of College Station
 
Miami-Dade MPO 2015 Transportation Summit Presentation
Miami-Dade MPO 2015 Transportation Summit PresentationMiami-Dade MPO 2015 Transportation Summit Presentation
Miami-Dade MPO 2015 Transportation Summit Presentation
Miami-Dade Transportation Planning Organization
 
East San Fernando Valley Transit Corridor presentation
East San Fernando Valley Transit Corridor presentationEast San Fernando Valley Transit Corridor presentation
East San Fernando Valley Transit Corridor presentation
Steven Rosenberg
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Fairfax County
 
Comp Plan - UDO Annual Review
Comp Plan - UDO Annual ReviewComp Plan - UDO Annual Review
Comp Plan - UDO Annual Review
City of College Station
 
New Developments in Transit Oriented Development
New Developments in Transit Oriented DevelopmentNew Developments in Transit Oriented Development
New Developments in Transit Oriented Development
Virtual ULI
 
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
Fairfax County
 
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Fairfax County
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
Toronto Public Consultation Unit
 
South Fraser transit plan
South Fraser transit planSouth Fraser transit plan
South Fraser transit plan
jgabateman
 
Cycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity PresentationCycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity Presentation
directionsto2050
 

Similar to Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects (20)

Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018Richmond Highway Bus Rapid TransitPublic Meeting #1:April 17 & 18, 2018
Richmond Highway Bus Rapid Transit Public Meeting #1: April 17 & 18, 2018
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives Analysis
 
Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)
 
VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014VTA North County Open House Presentation April 2014
VTA North County Open House Presentation April 2014
 
2015 06-15 relief line presentation
2015 06-15 relief line presentation2015 06-15 relief line presentation
2015 06-15 relief line presentation
 
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
 
2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review
 
Miami-Dade MPO 2015 Transportation Summit Presentation
Miami-Dade MPO 2015 Transportation Summit PresentationMiami-Dade MPO 2015 Transportation Summit Presentation
Miami-Dade MPO 2015 Transportation Summit Presentation
 
East San Fernando Valley Transit Corridor presentation
East San Fernando Valley Transit Corridor presentationEast San Fernando Valley Transit Corridor presentation
East San Fernando Valley Transit Corridor presentation
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
 
Comp Plan - UDO Annual Review
Comp Plan - UDO Annual ReviewComp Plan - UDO Annual Review
Comp Plan - UDO Annual Review
 
New Developments in Transit Oriented Development
New Developments in Transit Oriented DevelopmentNew Developments in Transit Oriented Development
New Developments in Transit Oriented Development
 
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
Fairfax County Countywide Transit Network Study: Board of Supervisors Transpo...
 
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
Reston Network Analysis - Community Kick-Off: Feb. 1, 2016
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
South Fraser transit plan
South Fraser transit planSouth Fraser transit plan
South Fraser transit plan
 
Cycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity PresentationCycle 2 Environmental and Social Equity Presentation
Cycle 2 Environmental and Social Equity Presentation
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
Fairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Fairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
Fairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Fairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
Fairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Fairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Fairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Fairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Fairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
ckn2izdm
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
Abdul-Hakim Shabazz
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
LUMINATIVE MEDIA/PROJECT COUNSEL MEDIA GROUP
 
Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
Pragencyuk
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
VoterMood
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
Filippo64
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
CIkumparan
 

Recently uploaded (8)

13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
 
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
 
Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
 

Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects

  • 1. Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects Update on Vanessa Aguayo-Thomas, AJ Hamidi, and Bob Pikora, Dept. of Transportation Meghan Van Dam, Dept. of Planning and Zoning Board Transportation Committee February 27, 2018
  • 2. Presentation Overview Embark Components • Richmond Highway Comprehensive Plan Amendment • Richmond Highway Corridor Improvements • Bus Rapid Transit (BRT) System 2
  • 3. Richmond Highway Corridor Active Projects: • Richmond Highway Comprehensive Plan Amendment (Huntington Metrorail Station to Fort Belvoir) • Richmond Highway Corridor Improvements Project (Mt. Vernon Hwy to Napper Road) • Richmond Highway BRT Program (Huntington Metrorail Station to Fort Belvoir)
  • 4. Route 1 Multimodal Alternatives Analysis • Virginia Department of Rail and Public Transportation (DRPT) completed in February 2015 • Included 16-mile segment of Route 1 from Huntington Metrorail Station to Woodbridge • Recommended BRT along the entire length of Richmond Highway corridor and long term plan to extend the Metrorail Yellow Line to Hybla Valley/ Gum Springs 4 7.3 mi Phase I: Bus Rapid Transit (BRT) Huntington to Hybla Valley Phase II: BRT Hybla Valley to Fort Belvoir BRT Phase III: Fort Belvoir to Woodbridge Phase IV: Metrorail Yellow Line Extension to Hybla Valley Route 1 Multimodal Alternatives Analysis (Virginia Dept. of Rail and Public Transit, 2015)
  • 5. Route 1 Multimodal Alternatives Analysis • Consistent 6 lanes – Richmond Highway • Continuous bike/pedestrian facilities – both sides of Richmond Hwy • Median-running Bus Rapid Transit (BRT) system for Richmond Hwy • Future Metrorail extension to Hybla Valley 5
  • 7. Board Authorization Scoping; Existing Conditions Corridor-wide Planning Objectives; BRT and Metrorail Policy Guidance Station Locations, Land Uses, Cross- section Transportation, Public Facilities Assessment; Station Area Planning Public Hearings Early 2018 Spring-Fall 2017 Fall-Winter 2016 Summer 2016 Fall-Spring 2016 PUBLIC OUTREACH 6 Community Meetings 24 Advisory Group Meetings Comprehensive Plan Amendment Process COMMUNITY ENGAGEMENT Spring 2015 7
  • 8. Guiding Planning Principles • Revitalization • Interconnected transportation modes • High-quality urban design • Health and leisure • Economic success of the corridor • Environmental restoration • Stewardship of historic resources • Communities stability 8
  • 9. Transportation Principles Safe, reliable, effective, interconnected modes: • Reserve exclusive right-of-way for BRT and re-purpose Richmond Highway service drives • Provide infrastructure to encourage public transit use, walking, and bicycling for all ages and abilities, to reduce vehicular traffic • Provide complete street network (grids of streets) within CBCs and connect to adjacent neighborhoods • Consolidate entrances, reduce curb cuts, improve access and enhance signage 9
  • 11. • Majority of redevelopment remains planned within CBCs • Clearer definition of identity and place for each of the CBCs • Areas in between remain planned for primarily residential and institutional uses Community Business Centers (CBCs) 11
  • 12. Comprehensive Plan Vision for the CBCs “The vision for the Richmond Highway CBCs honors the legacy of the corridor and the area’s unique ecological features to achieve a series of well- connected, transit-oriented activity nodes that celebrate the corridor’s history, embrace its environmental features, and strengthen the greater Richmond Highway community.” 12
  • 13. Multimodal Connectivity within CBCs Existing Beacon Groveton Shopping Center Proposed Beacon Groveton Concept Potential BRT Station* Illustrative image of a complete street designed for walking, biking and vehicles 13
  • 14. Richmond Highway Corridor Improvements 14
  • 15. • Jeff Todd Way to Napper Road – 2.9 Miles • Last remaining four-lane section north of Fort Belvoir • Planned improvements: • Widen to 6 lanes • Reserve ROW in median for BRT system • Bike & Pedestrian improvements on both sides of ROW Richmond Highway Corridor Improvements 15
  • 16. • Administered by VDOT in coordination with FCDOT • Purpose and Need: • Accommodate existing and future travel demand • Accommodate future BRT system • Improve safety for all users • Status and Schedule: • Currently in preliminary engineering • Design Public Hearing – Fall 2018 • Construction planned from 2023 to 2025 (overlaps BRT Project) • Plan to open to traffic in late 2025 Richmond Highway Corridor Improvements (Cont.) 16
  • 17. • Current Activities: • Establishing Preferred Intersection Design Option at Two Locations • Sacramento/Cooper intersection • Buckman Road/Mount Vernon Memorial Highway • Preparing for Public Information Meeting #3 – April 4, 2018 • Conducting Environmental and Stormwater Management Analysis • Cost: • Overall Cost approximately $215 M • Funds currently available = $44 M Richmond Highway Corridor Improvements (Cont.) 17
  • 18. Richmond Highway Corridor Improvements (Cont.) The intent of this exhibit is to depict the configuration of elements within the Proposed right-of-way. For clarity, potential landscaping is not depicted. 18
  • 19. Bus Rapid Transit (BRT) System 19
  • 20. Richmond Highway BRT Program (Phase I & II) • Limits: Huntington Metrorail Station to Fort Belvoir • Two dedicated lanes in median • Nine potential stations • Two Phases: • Phase I: Huntington Metrorail to Hybla Valley/Gum Springs • 5 stations • Phase II: Hybla Valley/Gum Springs to Fort Belvoir • 4 stations 20
  • 21. BRT Program • Staff is working with a specialized team of Consultants known as the Program Management Consultant (PMC) • Set-up with a governance structure and includes an executive committee to go over key BRT milestones • Advisory group has been set up to provide input on BRT issues such as community impacts, station concepts, etc. Consists of 14 members from both Lee and Mount Vernon Districts • BRT kick off meetings anticipated for April 2018 21
  • 22. BRT Activities • Submitted NVTA Application for funding - November 2017 • Technical Working groups such as design, public involvement, station design, etc. meet on regular basis • Met with FTA - November 7, 2017 and January 24, 2018 • Scope of work for next phase of effort includes Environmental Review, 20% Design and Branding to be executed in March 2018 22
  • 23. BRT Activities (Cont.) • Scope of work for next phase of effort includes: • Environmental Review • 20% Design • Branding • Cost: • Overall Cost approximately $524 M* • Funds currently available = $45 M 23*Based on DRPT Multimodal AA Study