SlideShare a Scribd company logo
1 of 21
Dulles Corridor Metrorail Project
Silver Line Phase 2 Implementation
Board Transportation Committee Update
October 2, 2018
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2
Project Status
Phase 1
• Old Meadow Road Realignment – 90% design complete.
• Construction completion scheduled for the end of 2018
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Bus bays at Spring Hill and McLean are complete
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 85% complete
• Package A (Rail line, system, and stations) – 86%
• Package B (Rail yard at Dulles) – 87%
• Contractual Substantial Completion – August 2019
• WMATA Board to establish Revenue Operations Date
3
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.758B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $241.9M
• Remaining Contingency $309.6M
Phase 2 – Cost Summary
4
• Reston Town Center Station – Mechanical/electrical/plumbing
rough-in, station roofing, and pavilion area work ongoing.
• Herndon Station – Electrical and steel welding work, south
pavilion construction, and stair tower foundation.
• Innovation Station – Pedestrian bridge detailing work, station
finishes, electrical rough-in and plumbing continues.
Phase 2 – Station Construction
5
• Dulles Airport Station – Station lighting, HVAC duct work, granite
edging, and platform waterproofing.
• Loudoun Gateway Station – Vault roof welding, skylight framing
and glazing, and MEP rough-in.
• Ashburn Station - Station roof work, MEP rough-in, pavilion work,
and pedestrian bridge detailing.
Phase 2 – Station Construction
6
• 1598 precast panels provided
• 60 Panels rejected (42 installed 18 not installed). All rejected panels
have been replaced.
• Issues with the panels
• High water to cement ratio, air entrainment, insufficient concrete cover
over the rebar, and may not meet non-reactivity to alkali-silica reaction
(unknown until the whistleblower court documents unsealed)
• MWAA and CRC commenced an independent evaluation of the
panels and materials used in the fabrication. Final results from the
investigation show material used in the fabrication of the panels
meet contract specifications. No finding of alkali-silica reaction.
• All panels provided by UPC will be coated with a sealant.
Phase 2 – Universal Concrete Products (UPC)
7
• WMATA IG is doing an independent investigation.
• UPC panels are not structure panels. The concern was meeting
the 100 year durability of the panels.
• MWAA proposes a sinking fund established by the contractor to
provide money to coat the panels. This would improve durability
and life of the panels to meet the contract 100 year requirement.
WMATA is working with MWAA on the proposed solution.
• The costs for the “fix” is the responsibility of the Phase 2
contractor
Phase 2 – Universal Concrete Products (UPC) cont.
8
• Aerial guideway finish painting girder bearings and clean up work
• Power and communication lines relocation ongoing
• Completed all 34.5kV cable and conduit installation
• All primary and secondary feeders tested and energized from
Dominion Energy substation to project.
• Rail and switches being installed along the at grade guideway in
the DIAAH median from the Reston Town Center Station to Yard
Leads.
Phase 2 – Aerial, Track, Utilities, Systems
9
• Perimeter fence installation, interior work for Service and
Inspection Building, Maintenance Way Building, and Transit
Police Building. Construction continues at Train Wash
Facility, Warehouse Facility, and Vehicle Storage Facility.
• Ongoing – Track approaches to SIB and MWB as well as
special track work.
Phase 2 – Rail Yard at Dulles Airport
10
• Total Project Estimate: $44.5M
• Construction Progress: 91% complete
• Existing garage repair work scope and cost under review
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): February 2019 – March 2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
11
Herndon Metrorail Garage
Herndon Metrorail Garage
12
13
• Total Project Estimate: $52 million
• Construction Progress: 65% complete
• Precast Fabrication: October 2017
• Precast Erection: April 5, 2018
Schedule
• Construction Award: March 2017
• Construction: April 2017
• Ready for Occupancy: April/May 2019*
* Will be updated as needed pending the lifting of the stop work order
Innovation Metrorail Garage
14
• 64% of precast panels installed
• Stop Work Order issued by DPWES and LDS
• Settlement of four foundation caissons (135 caissons installed)
• Successfully stabilized the caissons by injecting remedial grout
• Additional steps underway to install a redundant foundation system
• Electronic monitoring of the structure
• Investigative work ongoing, a total of 13 caissons have been identified as
requiring remedial work.
• Independent geotechnical firm contracted by DPWES
• Garage remains on schedule to be operational with the start of
Phase 2 revenue operations.
Innovation Station Garage
15
Innovation Metrorail Garage
16
Reston Town Center Station
Reston Town Center Pavilions
17
Herndon Station
Herndon Station Pavilions
Herndon Station South Pavilion
Herndon Station South Pavilion
18
Innovation Center Station
Innovation North Entrance Canopy
Innovation Pedestrian Bridge
19
Dulles Airport Station
20
Rail Yard Dulles Airport
21
QUESTIONS?

More Related Content

What's hot

Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
 
Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside  Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside  Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside Laird Construction Liaison Committee (CLC) Meeting PresentationCrosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15VDOT Northern Virginia
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House SlidesCrosstown TO
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 

What's hot (20)

Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside  Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside  Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
 
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 

Similar to Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC Update Oct. 2, 2018

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationFairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)Pablo Miguel Jurado
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Crosstown TO
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgradeRobert Lee - CEng, MICE, PMP
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Fairfax County
 
East Virtual Open House
East Virtual Open HouseEast Virtual Open House
East Virtual Open HouseCrosstown TO
 
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)James Herrmann
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale BridgeZeynepUla2
 

Similar to Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC Update Oct. 2, 2018 (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Western works final
Western works final Western works final
Western works final
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
East Virtual Open House
East Virtual Open HouseEast Virtual Open House
East Virtual Open House
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
6559163.ppt
6559163.ppt6559163.ppt
6559163.ppt
 
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
Resume and Project History - Jim Herrmann (Rev. 05-11-2016)
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale Bridge
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Pooja Nehwal
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadershipanjanibaddipudi1
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...Axel Bruns
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docxkfjstone13
 
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct CommiteemenRoberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemenkfjstone13
 
Vashi Escorts, {Pooja 09892124323}, Vashi Call Girls
Vashi Escorts, {Pooja 09892124323}, Vashi Call GirlsVashi Escorts, {Pooja 09892124323}, Vashi Call Girls
Vashi Escorts, {Pooja 09892124323}, Vashi Call GirlsPooja Nehwal
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...Muhammad Shamsaddin Megalommatis
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Krish109503
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docxkfjstone13
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...AlexisTorres963861
 
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCollege Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCall girls in Ahmedabad High profile
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docxkfjstone13
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书Fi L
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxAwaiskhalid96
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...Diya Sharma
 
29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Ismail Fahmi
 

Recently uploaded (20)

Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
 
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct CommiteemenRoberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
 
Vashi Escorts, {Pooja 09892124323}, Vashi Call Girls
Vashi Escorts, {Pooja 09892124323}, Vashi Call GirlsVashi Escorts, {Pooja 09892124323}, Vashi Call Girls
Vashi Escorts, {Pooja 09892124323}, Vashi Call Girls
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...
Beyond Afrocentrism: Prerequisites for Somalia to lead African de-colonizatio...
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCollege Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptx
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
 
29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024
 

Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC Update Oct. 2, 2018

  • 1. Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update October 2, 2018 Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation
  • 2. 2 Project Status Phase 1 • Old Meadow Road Realignment – 90% design complete. • Construction completion scheduled for the end of 2018 • VDOT punch list ongoing – MWAA and Bechtel to complete • Bus bays at Spring Hill and McLean are complete • Phase 1 close out - $2.982B (no change) Phase 2 • Overall Phase 2 – 85% complete • Package A (Rail line, system, and stations) – 86% • Package B (Rail yard at Dulles) – 87% • Contractual Substantial Completion – August 2019 • WMATA Board to establish Revenue Operations Date
  • 3. 3 • Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.758B • Contingency Utilization • Total Contingency $551.5M • Total Contingency Utilized $241.9M • Remaining Contingency $309.6M Phase 2 – Cost Summary
  • 4. 4 • Reston Town Center Station – Mechanical/electrical/plumbing rough-in, station roofing, and pavilion area work ongoing. • Herndon Station – Electrical and steel welding work, south pavilion construction, and stair tower foundation. • Innovation Station – Pedestrian bridge detailing work, station finishes, electrical rough-in and plumbing continues. Phase 2 – Station Construction
  • 5. 5 • Dulles Airport Station – Station lighting, HVAC duct work, granite edging, and platform waterproofing. • Loudoun Gateway Station – Vault roof welding, skylight framing and glazing, and MEP rough-in. • Ashburn Station - Station roof work, MEP rough-in, pavilion work, and pedestrian bridge detailing. Phase 2 – Station Construction
  • 6. 6 • 1598 precast panels provided • 60 Panels rejected (42 installed 18 not installed). All rejected panels have been replaced. • Issues with the panels • High water to cement ratio, air entrainment, insufficient concrete cover over the rebar, and may not meet non-reactivity to alkali-silica reaction (unknown until the whistleblower court documents unsealed) • MWAA and CRC commenced an independent evaluation of the panels and materials used in the fabrication. Final results from the investigation show material used in the fabrication of the panels meet contract specifications. No finding of alkali-silica reaction. • All panels provided by UPC will be coated with a sealant. Phase 2 – Universal Concrete Products (UPC)
  • 7. 7 • WMATA IG is doing an independent investigation. • UPC panels are not structure panels. The concern was meeting the 100 year durability of the panels. • MWAA proposes a sinking fund established by the contractor to provide money to coat the panels. This would improve durability and life of the panels to meet the contract 100 year requirement. WMATA is working with MWAA on the proposed solution. • The costs for the “fix” is the responsibility of the Phase 2 contractor Phase 2 – Universal Concrete Products (UPC) cont.
  • 8. 8 • Aerial guideway finish painting girder bearings and clean up work • Power and communication lines relocation ongoing • Completed all 34.5kV cable and conduit installation • All primary and secondary feeders tested and energized from Dominion Energy substation to project. • Rail and switches being installed along the at grade guideway in the DIAAH median from the Reston Town Center Station to Yard Leads. Phase 2 – Aerial, Track, Utilities, Systems
  • 9. 9 • Perimeter fence installation, interior work for Service and Inspection Building, Maintenance Way Building, and Transit Police Building. Construction continues at Train Wash Facility, Warehouse Facility, and Vehicle Storage Facility. • Ongoing – Track approaches to SIB and MWB as well as special track work. Phase 2 – Rail Yard at Dulles Airport
  • 10. 10 • Total Project Estimate: $44.5M • Construction Progress: 91% complete • Existing garage repair work scope and cost under review Schedule • Construction Award: October 2016 • Construction (new garage): November 2016 – March 2019 • Construction (existing garage): February 2019 – March 2019 • Ready for Occupancy: April 2019 Herndon Metrorail Garage
  • 13. 13 • Total Project Estimate: $52 million • Construction Progress: 65% complete • Precast Fabrication: October 2017 • Precast Erection: April 5, 2018 Schedule • Construction Award: March 2017 • Construction: April 2017 • Ready for Occupancy: April/May 2019* * Will be updated as needed pending the lifting of the stop work order Innovation Metrorail Garage
  • 14. 14 • 64% of precast panels installed • Stop Work Order issued by DPWES and LDS • Settlement of four foundation caissons (135 caissons installed) • Successfully stabilized the caissons by injecting remedial grout • Additional steps underway to install a redundant foundation system • Electronic monitoring of the structure • Investigative work ongoing, a total of 13 caissons have been identified as requiring remedial work. • Independent geotechnical firm contracted by DPWES • Garage remains on schedule to be operational with the start of Phase 2 revenue operations. Innovation Station Garage
  • 16. 16 Reston Town Center Station Reston Town Center Pavilions
  • 17. 17 Herndon Station Herndon Station Pavilions Herndon Station South Pavilion Herndon Station South Pavilion
  • 18. 18 Innovation Center Station Innovation North Entrance Canopy Innovation Pedestrian Bridge