The summary provides an update on the status of Phase 1 and Phase 2 of the Silver Line project in Fairfax County, Virginia. Phase 1 is nearing completion with punchlist items ongoing and closeout anticipated by the end of 2015. Phase 2 design is 24% complete overall and construction is 8% complete. Recent county activities include completing Kiss and Ride lot clean up, approving plans for a pavilion at Innovation Center Station, coordinating garage design at Herndon and Innovation Station, and acquiring land needed for the Herndon Station garage.
Shirley Gate Road Extended Corridor Planning StudyFairfax County
This presentation on the Shirley Gate Road extension was presented to the Fairfax County Board of Supervisors Transportation Committee on July 19, 2016.
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
The Reston Network Analysis is to conduct a detailed analysis of the grid of streets, assign urban street types and modal emphasis based on Department of Rail and Public Transportation Multimodal System Design Guidelines, and conduct a phasing analysis of when larger projects are needed.
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update
Fairfax County Board of Supervisors
Transportation Committee
May 7, 2013
Shirley Gate Road Extended Corridor Planning StudyFairfax County
This presentation on the Shirley Gate Road extension was presented to the Fairfax County Board of Supervisors Transportation Committee on July 19, 2016.
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
The Reston Network Analysis is to conduct a detailed analysis of the grid of streets, assign urban street types and modal emphasis based on Department of Rail and Public Transportation Multimodal System Design Guidelines, and conduct a phasing analysis of when larger projects are needed.
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update
Fairfax County Board of Supervisors
Transportation Committee
May 7, 2013
Reston Funding Plan
Potential Sources of Revenue for Funding Reston Transportation Improvements
Reston Network Analysis & Funding Plan Advisory Group
Dec. 14, 2015
Reston Transportation Funding Plan: July 15, 2016Fairfax County
This presentation was delivered to stakeholder on July 15, 2016, covering the purpose of the plan, improvements to be funded, preliminary cost estimates, and overview of the funding plan.
Director of Infrastructure and Development Services Lisa Pyles and Parks and Recreation Director Slade Strickland provided City Council with a quarterly update on Addison's Capital Improvement Program and other Town projects on February 10, 2015.
Similar to Silver Line Update-Board Transportation Committee: Oct. 13, 2015 (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
01062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
03062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
In a May 9, 2024 paper, Juri Opitz from the University of Zurich, along with Shira Wein and Nathan Schneider form Georgetown University, discussed the importance of linguistic expertise in natural language processing (NLP) in an era dominated by large language models (LLMs).
The authors explained that while machine translation (MT) previously relied heavily on linguists, the landscape has shifted. “Linguistics is no longer front and center in the way we build NLP systems,” they said. With the emergence of LLMs, which can generate fluent text without the need for specialized modules to handle grammar or semantic coherence, the need for linguistic expertise in NLP is being questioned.
Future Of Fintech In India | Evolution Of Fintech In IndiaTheUnitedIndian
Navigating the Future of Fintech in India: Insights into how AI, blockchain, and digital payments are driving unprecedented growth in India's fintech industry, redefining financial services and accessibility.
Welcome to the new Mizzima Weekly !
Mizzima Media Group is pleased to announce the relaunch of Mizzima Weekly. Mizzima is dedicated to helping our readers and viewers keep up to date on the latest developments in Myanmar and related to Myanmar by offering analysis and insight into the subjects that matter. Our websites and our social media channels provide readers and viewers with up-to-the-minute and up-to-date news, which we don’t necessarily need to replicate in our Mizzima Weekly magazine. But where we see a gap is in providing more analysis, insight and in-depth coverage of Myanmar, that is of particular interest to a range of readers.
31052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
हम आग्रह करते हैं कि जो भी सत्ता में आए, वह संविधान का पालन करे, उसकी रक्षा करे और उसे बनाए रखे।" प्रस्ताव में कुल तीन प्रमुख हस्तक्षेप और उनके तंत्र भी प्रस्तुत किए गए। पहला हस्तक्षेप स्वतंत्र मीडिया को प्रोत्साहित करके, वास्तविकता पर आधारित काउंटर नैरेटिव का निर्माण करके और सत्तारूढ़ सरकार द्वारा नियोजित मनोवैज्ञानिक हेरफेर की रणनीति का मुकाबला करके लोगों द्वारा निर्धारित कथा को बनाए रखना और उस पर कार्यकरना था।
27052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
‘वोटर्स विल मस्ट प्रीवेल’ (मतदाताओं को जीतना होगा) अभियान द्वारा जारी हेल्पलाइन नंबर, 4 जून को सुबह 7 बजे से दोपहर 12 बजे तक मतगणना प्रक्रिया में कहीं भी किसी भी तरह के उल्लंघन की रिपोर्ट करने के लिए खुला रहेगा।
role of women and girls in various terror groupssadiakorobi2
Women have three distinct types of involvement: direct involvement in terrorist acts; enabling of others to commit such acts; and facilitating the disengagement of others from violent or extremist groups.
ys jagan mohan reddy political career, Biography.pdfVoterMood
Yeduguri Sandinti Jagan Mohan Reddy, often referred to as Y.S. Jagan Mohan Reddy, is an Indian politician who currently serves as the Chief Minister of the state of Andhra Pradesh. He was born on December 21, 1972, in Pulivendula, Andhra Pradesh, to Yeduguri Sandinti Rajasekhara Reddy (popularly known as YSR), a former Chief Minister of Andhra Pradesh, and Y.S. Vijayamma.
HISTORY- XII-Theme 3 - Kinship, Caste and Class.pptx
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
1. County of Fairfax, Virginia
Department of Transportation
Silver Line
Board Transportation Committee
October 13, 2015
Mark Canale
Fairfax County Department of Transportation
2. County of Fairfax, Virginia
Status
• Phase 1
• VDOT, WMATA, Fairfax Punchlist – Ongoing
• Fairfax County – 38 open items
• VDOT with majority of remaining punchlist
items
• Project Closeout anticipated at the end of 2015
• Fairfax County completed clean up of kiss and ride
lots and Route 7 median stormwater (MWAA to
reimburse the County) – County to maintain Route 7
SWM
• County Maintaining Mclean, Spring Hill K/R lots
• Art in Transit Task Order issued
• Phase 1 close out - $2.982B
• Phase 2
• Total Project Status (all bid packages)
• Overall Project – 24%
• Design – 93%
• Construction – 8%
• Highlights
• Tower crane at Innovation Center Station
• All Stations in Fairfax County have
construction and/or utility work ongoing
• Loudoun County Stations in design
• Aerial Guideway at Dulles Airport under
construction
• Rail Yard at Dulles Airport in design
• Centreville Road Girders Placement ongoing
• Upcoming Public Meeting on Innovation Center Station
(north side) – Oct 13 at Herndon Middle School
• Budget - $2.775B
• Total Contingency - $551.4M (Remaining $502M)
• Contract extension costs under negotiations
between MWAA and CRC
County Activities – Past 60 Days
• Centreville Road Construction Public Meeting Sept. 24
• Girders at Centreville Road for rail track – Installation
Completed
• SE for Pavilion at Innovation Center Station (south) PC
• Approved Oct 1
• BOS scheduled Oct 20
• Phase 2 Design Reviews
• County Coordination
• Project Partners (MWAA, VDOT, DRPT, WMATA,
Loudoun County, Town of Herndon, Landowners)
• Completed Phase 1 Kiss and Ride and RT 7 SWM Clean up
• Herndon and Innovation Center Stations Garages –
Ongoing design work
• Closed on the Sprint Property – Land needed for
Herndon Garage
• Herndon Station – Coordinated maintenance of traffic with
MWAA, CRC, and Fairfax Connector for utility work
2
October 13, 2015