SlideShare a Scribd company logo
1 of 16
Dulles Corridor Metrorail Project
Board Transportation Committee Update
July 18, 2017
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2
Phase 1
• Old Meadow Road Realignment – in design, construction
completion scheduled for the end of 2018 (contract award Oct.
2017)
• Remaining VDOT punchlist ongoing
• Phase 1 close out - $2.982B
Phase 2
• Overall Phase 2 – 64%
• Package A (Rail line, system, and stations)– 69%
• Package B (Rail yard at Dulles) – 60%
• Contractual Substantial Completion – August 2019
• WMATA to establish Revenue Operations Date
3
• Reston Town Center Station – Precast erection and structural steel
• Herndon Station – Structural steel, precast detailing, and south
pavilion construction
• Innovation Station – Precast detailing, structural steel painting,
electrical and plumbing, pedestrian bridge assembly for north and
south pavilions
• Dulles Airport Station – Precast and structural steel erection, station
mechanical/electrical/plumbing rough in work, tunnel tie-in
• Loudoun Gateway Station – Station precast erection
• Ashburn Station - Station foundation, support walls, and start of
precast erection
Phase 2 – Station Construction
4
• Columns and Pier Caps – 100%
• Deck Spans Poured – 86%
• Trackway Spans
• Precast girders have been erected and deck pours
work ongoing
Phase 2 – Aerial Guideway
5
• 100% Design Plans Submitted
• Installation of stormwater, sanitary, duct bank structures,
and retaining wall is ongoing
• Final grading, utilities and yard layout continues
• Structural steel, precast panels, and industrial equipment
installation for Service and Inspection
• Structural steel progressing on Maintenance Building
• Foundation work for Transit Police and Train Wash Facility
buildings is ongoing
Phase 2 – Rail Yard at Dulles Airport
6
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.199B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $173.2M
• Remaining Contingency $378.3M
Phase 2 – Cost Summary
7
• Total Project Estimate: $44.5M
• Construction Progress – appx 29% complete
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – January
2019
• Construction (existing garage): February 2019 – March
2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
8
Herndon Metrorail Garage
9
• Total Project Estimate: $52 million
• Construction Progress – appx 11% complete
Schedule
• Construction Award: March - April 2017
• Construction: April 2017
• Ready for Occupancy: April/May 2019
Innovation Metrorail Garage
10
Innovation Metrorail Garage
11
Reston Town Center Station
12
Herndon Station
13
Innovation Center Station
14
Dulles Airport Station
15
West Segment
16
QUESTIONS?

More Related Content

What's hot

Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting PresentationCrosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro GarageFairfax County
 
Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020RamaChilamkurthy
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationCrosstown TO
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseCrosstown TO
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 

What's hot (20)

Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro Garage
 
Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open House
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPOFDOT D6 395-836-95 Design-Build Project Presentation to the TPO
FDOT D6 395-836-95 Design-Build Project Presentation to the TPO
 

Similar to Dulles Corridor Metrorail Project: Board Transportation Committee Update- July 18, 2017

Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationFairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Fairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
Silver Line Update July 2016
Silver Line Update July 2016Silver Line Update July 2016
Silver Line Update July 2016Fairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Fairfax County
 
Silver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportSilver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportFairfax County
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 

Similar to Dulles Corridor Metrorail Project: Board Transportation Committee Update- July 18, 2017 (20)

Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Western works final
Western works final Western works final
Western works final
 
Silver Line Update July 2016
Silver Line Update July 2016Silver Line Update July 2016
Silver Line Update July 2016
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Silver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportSilver Line Phase 1-Status Report
Silver Line Phase 1-Status Report
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Recently uploaded

Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfauroraaudrey4826
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaignanjanibaddipudi1
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Axel Bruns
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 

Recently uploaded (15)

Chandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdfChandrayaan 3 Successful Moon Landing Mission.pdf
Chandrayaan 3 Successful Moon Landing Mission.pdf
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election CampaignN Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
N Chandrababu Naidu Launches 'Praja Galam' As Part of TDP’s Election Campaign
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 

Dulles Corridor Metrorail Project: Board Transportation Committee Update- July 18, 2017

  • 1. Dulles Corridor Metrorail Project Board Transportation Committee Update July 18, 2017 Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation
  • 2. 2 Phase 1 • Old Meadow Road Realignment – in design, construction completion scheduled for the end of 2018 (contract award Oct. 2017) • Remaining VDOT punchlist ongoing • Phase 1 close out - $2.982B Phase 2 • Overall Phase 2 – 64% • Package A (Rail line, system, and stations)– 69% • Package B (Rail yard at Dulles) – 60% • Contractual Substantial Completion – August 2019 • WMATA to establish Revenue Operations Date
  • 3. 3 • Reston Town Center Station – Precast erection and structural steel • Herndon Station – Structural steel, precast detailing, and south pavilion construction • Innovation Station – Precast detailing, structural steel painting, electrical and plumbing, pedestrian bridge assembly for north and south pavilions • Dulles Airport Station – Precast and structural steel erection, station mechanical/electrical/plumbing rough in work, tunnel tie-in • Loudoun Gateway Station – Station precast erection • Ashburn Station - Station foundation, support walls, and start of precast erection Phase 2 – Station Construction
  • 4. 4 • Columns and Pier Caps – 100% • Deck Spans Poured – 86% • Trackway Spans • Precast girders have been erected and deck pours work ongoing Phase 2 – Aerial Guideway
  • 5. 5 • 100% Design Plans Submitted • Installation of stormwater, sanitary, duct bank structures, and retaining wall is ongoing • Final grading, utilities and yard layout continues • Structural steel, precast panels, and industrial equipment installation for Service and Inspection • Structural steel progressing on Maintenance Building • Foundation work for Transit Police and Train Wash Facility buildings is ongoing Phase 2 – Rail Yard at Dulles Airport
  • 6. 6 • Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.199B • Contingency Utilization • Total Contingency $551.5M • Total Contingency Utilized $173.2M • Remaining Contingency $378.3M Phase 2 – Cost Summary
  • 7. 7 • Total Project Estimate: $44.5M • Construction Progress – appx 29% complete Schedule • Construction Award: October 2016 • Construction (new garage): November 2016 – January 2019 • Construction (existing garage): February 2019 – March 2019 • Ready for Occupancy: April 2019 Herndon Metrorail Garage
  • 9. 9 • Total Project Estimate: $52 million • Construction Progress – appx 11% complete Schedule • Construction Award: March - April 2017 • Construction: April 2017 • Ready for Occupancy: April/May 2019 Innovation Metrorail Garage