SlideShare a Scribd company logo
FORMULATION OF DETAILED
   PROJECT REPORT –
   Chennai Metro Rail Project



                       Submitted By :
                        Ashish Kumar
                       Neeraj Kumar
                       Parag Chaubey
STAGES OF PLANNING

CONSTRUCTION STAGE
                                                                INVESTMENT DECISION
                                                           STATUTORY CLEARANCES
EVALUATION & APPRAISAL                                     ENVIRONMENTAL
                                                     TECHNO ECONOMIC
                                                COST ESTIMATE
FEASIBILITY REPORT/                         OTHER INPUTS
DETAILED PROJ REPORT                  CIVIL, MECH, ELECT & C&I INPUTS
                                 BASIC ENGG
                           SITE SPECIFIC STUDIES/INVESTIGATIONS
PROJECT              SITE SELECTION/PRE-FEASIBILITY STUDIES
FEASIBLITY       RECONNAISSANCE
Basic Components

• Tie-up of Basic Inputs
• Conduct Site Specific Studies/
  Investigations
• Basic Engg./System Finalization
• Technical Inputs
• Inputs other than Technical
• Clearances / Commitment
• Financing Plan
• Cost Estimates
Basic Inputs - Land

• Based on draft master plan 2026 (as per
  CMDA)
• Total land requirement (permanent) = approx
  49 Ha
• Project so designed so as to minimize private
  land acquisition
Total Land Requirement
                          Corridor 1             Corridor 2
 Ownership                         Mainten                 Mainten
               Stations     Running ance Stations Running ance
                                    Depot                   Depot Total

Vacant State
                1.14         0.53             3.47   0.10   20.98   26.22
Govt land
Other Govt
                4.34         1.68             3.88   0.38           10.28
Land
Private         2.17         0.00      4.10   2.37   3.94           12.58


TOTAL           7.65         2.21      4.10   9.72   4.42   20.98   49.08
Basic Inputs - Power

• Required for running of trains, station services
  and other O & M activities.
• Determined by peak hour demand of traction
  system and auxiliary applications.
Power Demand Assessment (MVA)
                                  Year
        Corridor
                           2014   2016   2026

               Traction    10.3   13.2   18.9
Corridor - 1   Auxiliary   31.4   32.1   39.7
                Total      41.7   45.3   58.6
               Traction    10.4   15.0   21.7
Corridor - 2   Auxiliary    7.2   8.6    10.1
                Total      17.6   23.6   31.8

         TOTAL             59.3   68.9   90.4
Sources of Power Supply
 Corridor       Grid Sub-    Location of RSS     Approx Length of Cables
             station (with      of Metro
              i/p voltage)      Authority


Corridor - 1 GMR Vasavi      Jail Complex      2km. 110 kV
             (230/110 kV)    (110/33 kV)       (Double Circuit Cables)
            Guindy Grid      Adiyar            2km. 110 kV
            Sub-station      (110/33 kV)       (Double Circuit Cables)
            (230/110 kV)
Corridor - 2 Koyambedu       Koyambedu         1km. 110 kV
             Grid Sub-       Depot             (Double Circuit Cables)
             station         (110/33 kV)
             (230/110 kV)
Site Specific Study
               Need for project

• Fourth largest city.
• Population = 80 lakhs.
• Population density = 6,482 /sq km.
• 110 lakh trips.
• Low per capita income (Rs 1,760 / month in
  2005).
• 65% population come under EWS.
Site Specific Study
               Need for project
• Study of 1992 shows Volume/capacity ratio on
  more than 1 in peak hours for 33.8 % of total
  road length.
• Congested roads.
• Poor geometrics of roads in older areas.
• Missing link has put pressure on radial
  network.
• Selection of Corridors based on previous
  studies.
Site Specific Study
                Traffic Forecast

• Based on land use planning and detailed
  surveys.
• Growth rate of traffic demand = 5.2 %.
• Growth in sub-urban rail system
     2006-07 = 23 %
     2007-08 = 12 %
Site Specific Study
                    Transport Demand
Year    Corridors      Daily     Length   Pass-km      Pass
                     Passenger    (km)               km/km
                                                      (lakh)
       Corr-1          318532     22.5     2632748     1.2
2011   Corr-2          254144     21.3     2137984     1.0
       Total           572676     43.8     4770732     1.1
       Corr-1          403169     22.5     3280363     1.5
2016   Corr-2          353297     21.3     2866624     1.3
       Total           756466     43.8     6146987     1.4
       Corr-1          542444     22.5     4575592     2.0
2016   Corr-2          521605     21.3     4323905     2.0
       Total          1064048     43.8     8899496     2.0
Site Specific Study
            Existing Infrastructure

• Rail Network
System Finalization
                    Track

• Standard Gauge (1435mm) for the following
   reasons :
a. Intensive usage
b.Long lasting
c. Minimum maintenance
d.Safety, reliability and comfort
e.Minimum noise and vibrations.
System Finalization
                 Traction System

• 750 V DC third rail for the following reasons :

a. Height of metro structures including train
   heights need to be restricted to 12 mtr.
b.25 kV AC traction system with overhead wires
   provides cluttered looks to system.
System Finalization
           Signaling & Train Control

• ‘Distance to go’ Automatic Train Protection
  and Automatic Train Supervision

To provide capacity optimization
Provide best services to public.
System Finalization
             Telecommunication

• Backbone for communication

Signaling
SCADA, AFC
Operational & Administrative requirements
Passenger Information System
Crisis Management during emergencies
System Finalization
              Automatic fare Collection
• To handle large number of passengers
 Efficient and Proper Ticket issue & fare collection
 Simple & easy to operate
 Easy accounting
 Less manpower requirement
 Amenable for quick fare changes
 Cheaper in long run
 Prevent leakage of revenue
 Less cost of recyclable tickets
System Finalization
                    Rolling Stock
• Same as used in DMRC for the following
  reasons:
 Proven Reliability
 Passenger Safety Feature
 Energy Efficiency
 Low Life Cycle Cost
 Light Weight
 High rate of acceleration and deceleration
Rail Network

• Line Map
• Schematic Map
Technical Inputs
• Civil Engineering




• Description of Alignment
    Corridor 1
         Breakup of Alignment length
  Total Elevated length = 8.785km
  Total Underground length = 14.300km
  Total Alignment length = 23.085km
    Corridor 2
      Break-up of alignment length
      Alignment length is 22.000 km from dead end to dead end
Technical Inputs
•   GEOTECHNICAL INVESTIGATION
      A total of 75 Boreholes were carried out along the corridors.
      Archeans rock, found in the peninsular region are generally composed of granite and
       Gneisses of Peninsular Gneissic Complex, composition of duke is mainly Doleritic
       whereas sedimentary formations are mainly of shale and sand stone with or without
       fossiliferous beds.


•   UTILITY DIVERSION
Following engineering items have been studied and described in this chapter:
      Existing utilities and planning for their diversion during construction, if necessary.
      Land acquisition necessary for the project both on permanent basis as well as
       temporary, including its break up between Government and private ownership.
Details of utility provided in the report are based on information provided by utility
   agencies and need to be physically verified before taking up construction work.
Technical Inputs
•   POWER SUPPLY SYSTEM
     Broad estimation of auxiliary and traction power demand is made based on
      the following assumptions:-
    I. Specific energy consumption of rolling stock – 70KWh/1000 GTKM
    II. Regeneration by rolling stock – 20%.
    III. Elevated/at –grade station load – initially 200KW, which will increase to 300 KW
         inclusive of Property Development loads in the year 2026.
    IV. Underground Station load – initially 2000 kW, which will increase to 2500 kW in the year
         2026.
    V. Depot auxiliary load – initially 2000KW, which will increase to 2500 KW in the year 2026.
•   SCADA SYSTEM
    I. The entire system of power supply (receiving, traction & auxiliary supply) shall be
       monitored and controlled from a centralized Operation Control Centre (OCC) through
       SCADA system. Modern SCADA system with intelligent remote terminal units (RTUs)
       shall be provided. Optical fibre provided for telecommunications will be used as
       communication carrier for SCADA system
Inputs Other Than Technical

•   Maintenance Depots:
      Two depots are proposed in phase-I. The Koyambedu Depot-cum-Workshop
       will be the main depot and located on corridor 2. the second depot is at
       Minambakkam on corridor 1 for stabling & inspection.

•   Train Operation Plan:
      Salient Features of the proposed trains operation plan are :
      Running of services for 19 hours of the day (5 AM to Midnight) with a
      station dwell time of 30 seconds,
      Make up time of 5 -10% with 8 -12% coasting.
      Scheduled speed for these corridors has been assumed as 34 Kmph.
Inputs Other Than Technical




Total 184 coaches (92 coaches for Corridor 1 & 92 coaches for Corridor 2) are
required in the year 2011.
Clearances and Commitments
•   Implementing a metro project in a congested metropolis is indeed a challenge.
•   In sheer size, magnitude and technical complexity there are no parallels to metro
•   projects. Further, these projects are to be carried out in difficult urban
    environment without dislocating city life, while at the same time preserving the
    environment.
•   The project involves integration of a number of complex technical systems – some
    of these technologies used in these systems are totally new to the country – each
    one of which is a major project by itself.
•   Interfacing various system contracts is a difficult and highly skilled exercise.
•   Side by side, timely and adequate funds have to be assured for implementation
    and lands, without encumbrances, have to be taken possession of in time.
•   Clearances from the local authorities have to be taken permission to cut trees,
    diversion of utilities, management of road traffic, etc., all of which will call for an
    efficient and competent project implementing agency.
•   Eg. Land Use Policy etc.
Approvals
 Government of Tamil Nadu have approved in
  principle the two initial corridors on 7-11-2007
 Government of India have approved the
  Chennai Metro Rail project on 28-1-2009.
Cost Estimates

•   Capital costs workout at March 2007 price level as described hereunder

    Corridor 1 Rs. 5,997 Crores
    Corridor 2 Rs. 5,106 Crores

    (Note: Under the ‘Fully Underground’ considered at one stage as per State
    Govt.’s request, the cost of Corridor I was Rs. 7408 crores and Corridor II was
    Rs. 7978 crores which was considered unviable.)
    Costs are excluding taxes and duties, but including general charges @ 5% on
          all items except land and 3% contingencies on all items.
Year Wise Investment
                                                  Figs in Rs. Cr
           FY        Without Taxes & Duties With Central Taxes Only
           2008-09             533                    570
           2009-10            2971                    3279
           2010-11            3080                    3484
           2011-12            2705                    3096
           2012-13            1544                    1767
           2013-14            1621                    1853
           2014-15             613                    701
           Total            13067                   14750
The staff is assumed to be provided @ 45 persons per kilometre. The escalation
factor used for staff costs is 6% per annum to provide for both escalation and
growth in salaries.
The cost of other expenses is based on the O & M unit cost expected for the
Delhi Metro Phase-1 project. The rate of electricity assumed in the Delhi Metro
study is about Rs. 2.30 per unit whereas at present in Chennai the applicable
rate is Rs. 3.00 per unit. The latter has been used for all calculations. The O&M
cost (excluding staff cost) has been obtained by providing an escalation of 5%
per annum.
Financing Plan
•   Funding Patter based on SPV model is selected as represented below:




•   This project which is termed as a social project is implemented and operated
    under a SPV owned by Government of Tamil Nadu (GOTN) and Government of
    India (GOI)
Revenues
•   The Revenue for Chennai metro mainly consists of fare box collection and other
    incomes from property development, advertisement, parking etc.
    Year      Corr 1&2 Trips Per Day (In lakhs)
    2013-14                  6.66
    2016-17                  7.75
    2026-27                 12.87

•   The growth rate for traffic is assumed at 5.2% per annum
•   The trip distribution has been worked out by considering average lead of 8.33 KM
    and with an assumption that maximum lead is 30 KM, The graphic presentation
    of the same is placed below.
Fare Structure
•   The metro fare obtained by multiplying the bus fare by 2 times has been rounded
    off to the nearest rupee.




• Other Sources of revenue:
 Development of Property
 Leasing of Parking Right at the station
 Advertisements on viaducts and many more……
References
• www.chennaimetrorail.gov.in
• www.cmdachennai.gov.in
• Japan International Co-operation Agency –
  www.jicago.jp
• International Association of Public Transport –
  www.uitp.org/regions/Asia-Pacific/activities.cfm
• www.uitp.org/Public-Transport/metro/index.cfm

More Related Content

What's hot

Unicorn Wireless Engineering Presentation
Unicorn Wireless Engineering PresentationUnicorn Wireless Engineering Presentation
Unicorn Wireless Engineering Presentation
drottmayer
 
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
Naoki Shibata
 
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
Wael ElDessouki
 
TTEng 422 s2021 module 5 Introduction to Traffic Flow Theory
TTEng 422  s2021 module 5 Introduction to Traffic Flow TheoryTTEng 422  s2021 module 5 Introduction to Traffic Flow Theory
TTEng 422 s2021 module 5 Introduction to Traffic Flow Theory
Wael ElDessouki
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing Performance
GSE Systems, Inc.
 
Henkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy ServicesHenkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy Services
Sammy Germany
 
Henkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy ServicesHenkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy Services
Sammy Germany
 
SESAR at World ATM Congress 2016 - SESAR Virtual Centres
SESAR at World ATM Congress 2016 - SESAR Virtual CentresSESAR at World ATM Congress 2016 - SESAR Virtual Centres
SESAR at World ATM Congress 2016 - SESAR Virtual Centres
SESAR Joint Undertaking
 
Podium engineering srl a Pépinières Ouvertes 2014
Podium engineering srl a Pépinières Ouvertes 2014Podium engineering srl a Pépinières Ouvertes 2014
Podium engineering srl a Pépinières Ouvertes 2014
Fabrizio Favre
 
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet ServiceDynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
Joseph Chow
 
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANTDEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
Akash M
 
Traffic studies volume study
Traffic studies volume studyTraffic studies volume study
Traffic studies volume study
Aglaia Connect
 
Engr.Amr Ayaad_CV
Engr.Amr Ayaad_CV Engr.Amr Ayaad_CV
Engr.Amr Ayaad_CV Amr Ayaad
 
Sondus Ahmed - CV - 2016
Sondus Ahmed - CV - 2016Sondus Ahmed - CV - 2016
Sondus Ahmed - CV - 2016Sondus Ahmed
 
Tteng 422 s2021 module 2b: Roundabout Capacity Analysis and Level of Service
Tteng 422  s2021 module 2b: Roundabout Capacity Analysis and Level of ServiceTteng 422  s2021 module 2b: Roundabout Capacity Analysis and Level of Service
Tteng 422 s2021 module 2b: Roundabout Capacity Analysis and Level of Service
Wael ElDessouki
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
Zawad khalil
 

What's hot (17)

Unicorn Wireless Engineering Presentation
Unicorn Wireless Engineering PresentationUnicorn Wireless Engineering Presentation
Unicorn Wireless Engineering Presentation
 
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
 
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
Traffic Operations and Management: Module1: Grade Separation & Weaving Segments
 
TTEng 422 s2021 module 5 Introduction to Traffic Flow Theory
TTEng 422  s2021 module 5 Introduction to Traffic Flow TheoryTTEng 422  s2021 module 5 Introduction to Traffic Flow Theory
TTEng 422 s2021 module 5 Introduction to Traffic Flow Theory
 
Virtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing PerformanceVirtual Commissioning and Real-Time Training for Increasing Performance
Virtual Commissioning and Real-Time Training for Increasing Performance
 
Henkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy ServicesHenkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy Services
 
Henkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy ServicesHenkels & McCoy Renewable Energy Services
Henkels & McCoy Renewable Energy Services
 
SESAR at World ATM Congress 2016 - SESAR Virtual Centres
SESAR at World ATM Congress 2016 - SESAR Virtual CentresSESAR at World ATM Congress 2016 - SESAR Virtual Centres
SESAR at World ATM Congress 2016 - SESAR Virtual Centres
 
Podium engineering srl a Pépinières Ouvertes 2014
Podium engineering srl a Pépinières Ouvertes 2014Podium engineering srl a Pépinières Ouvertes 2014
Podium engineering srl a Pépinières Ouvertes 2014
 
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet ServiceDynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
 
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANTDEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
 
Traffic studies volume study
Traffic studies volume studyTraffic studies volume study
Traffic studies volume study
 
Engr.Amr Ayaad_CV
Engr.Amr Ayaad_CV Engr.Amr Ayaad_CV
Engr.Amr Ayaad_CV
 
Sondus Ahmed - CV - 2016
Sondus Ahmed - CV - 2016Sondus Ahmed - CV - 2016
Sondus Ahmed - CV - 2016
 
Tteng 422 s2021 module 2b: Roundabout Capacity Analysis and Level of Service
Tteng 422  s2021 module 2b: Roundabout Capacity Analysis and Level of ServiceTteng 422  s2021 module 2b: Roundabout Capacity Analysis and Level of Service
Tteng 422 s2021 module 2b: Roundabout Capacity Analysis and Level of Service
 
NTE Seg3A-B-C
NTE Seg3A-B-CNTE Seg3A-B-C
NTE Seg3A-B-C
 
Traffic volume study
Traffic volume studyTraffic volume study
Traffic volume study
 

Similar to Formulation of detailed project report(final)

Robotics applied to power line
Robotics applied to power line Robotics applied to power line
Robotics applied to power line
RTE
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
Brett Payton
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metrosatish choudhari
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
Nishanth Patil
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
AfendiAriff
 
Srldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power MeetSrldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power Meet
PRIYANK JAIN
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
Pankaj Kumar Dwivedi
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
RAKESHPANDEY754083
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
Saksham Bhutani
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
Amit Kumar
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)Pablo Miguel Jurado
 
21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx
Naresh Prasad Keshari
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)Sindhuja Balaji
 
Railway electrification
Railway electrificationRailway electrification
Railway electrification
Suresh Sunny
 
railwayelectrification-151011045726-lva1-app6891.pdf
railwayelectrification-151011045726-lva1-app6891.pdfrailwayelectrification-151011045726-lva1-app6891.pdf
railwayelectrification-151011045726-lva1-app6891.pdf
VikashKumar547263
 
Industrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptxIndustrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptx
DivyanshKhelani1
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
seifelsaie2
 
Metro.pptx
Metro.pptxMetro.pptx
Metro.pptx
HindujaBairi
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Leonardo ENERGY
 

Similar to Formulation of detailed project report(final) (20)

Robotics applied to power line
Robotics applied to power line Robotics applied to power line
Robotics applied to power line
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
 
Srldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power MeetSrldc 28 May2013_congestionEnergy & Power Meet
Srldc 28 May2013_congestionEnergy & Power Meet
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
GTC
GTCGTC
GTC
 
21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
 
Railway electrification
Railway electrificationRailway electrification
Railway electrification
 
railwayelectrification-151011045726-lva1-app6891.pdf
railwayelectrification-151011045726-lva1-app6891.pdfrailwayelectrification-151011045726-lva1-app6891.pdf
railwayelectrification-151011045726-lva1-app6891.pdf
 
Industrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptxIndustrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptx
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
 
Metro.pptx
Metro.pptxMetro.pptx
Metro.pptx
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
 

More from Parag Chaubey

Fed ex
Fed exFed ex
Nepotism
NepotismNepotism
Nepotism
Parag Chaubey
 
Security analysis(parag chaubey)
Security analysis(parag chaubey)Security analysis(parag chaubey)
Security analysis(parag chaubey)Parag Chaubey
 
Toyota production system
Toyota production systemToyota production system
Toyota production systemParag Chaubey
 
Rubber industry globally
Rubber industry  globallyRubber industry  globally
Rubber industry globallyParag Chaubey
 

More from Parag Chaubey (7)

Fed ex
Fed exFed ex
Fed ex
 
Volvo village
Volvo villageVolvo village
Volvo village
 
Enron scandal
Enron scandalEnron scandal
Enron scandal
 
Nepotism
NepotismNepotism
Nepotism
 
Security analysis(parag chaubey)
Security analysis(parag chaubey)Security analysis(parag chaubey)
Security analysis(parag chaubey)
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Rubber industry globally
Rubber industry  globallyRubber industry  globally
Rubber industry globally
 

Recently uploaded

Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
bosssp10
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Lviv Startup Club
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.docBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
daothibichhang1
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 

Recently uploaded (20)

Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
Evgen Osmak: Methods of key project parameters estimation: from the shaman-in...
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.docBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 

Formulation of detailed project report(final)

  • 1. FORMULATION OF DETAILED PROJECT REPORT – Chennai Metro Rail Project Submitted By : Ashish Kumar Neeraj Kumar Parag Chaubey
  • 2. STAGES OF PLANNING CONSTRUCTION STAGE INVESTMENT DECISION STATUTORY CLEARANCES EVALUATION & APPRAISAL ENVIRONMENTAL TECHNO ECONOMIC COST ESTIMATE FEASIBILITY REPORT/ OTHER INPUTS DETAILED PROJ REPORT CIVIL, MECH, ELECT & C&I INPUTS BASIC ENGG SITE SPECIFIC STUDIES/INVESTIGATIONS PROJECT SITE SELECTION/PRE-FEASIBILITY STUDIES FEASIBLITY RECONNAISSANCE
  • 3. Basic Components • Tie-up of Basic Inputs • Conduct Site Specific Studies/ Investigations • Basic Engg./System Finalization • Technical Inputs • Inputs other than Technical • Clearances / Commitment • Financing Plan • Cost Estimates
  • 4. Basic Inputs - Land • Based on draft master plan 2026 (as per CMDA) • Total land requirement (permanent) = approx 49 Ha • Project so designed so as to minimize private land acquisition
  • 5. Total Land Requirement Corridor 1 Corridor 2 Ownership Mainten Mainten Stations Running ance Stations Running ance Depot Depot Total Vacant State 1.14 0.53 3.47 0.10 20.98 26.22 Govt land Other Govt 4.34 1.68 3.88 0.38 10.28 Land Private 2.17 0.00 4.10 2.37 3.94 12.58 TOTAL 7.65 2.21 4.10 9.72 4.42 20.98 49.08
  • 6. Basic Inputs - Power • Required for running of trains, station services and other O & M activities. • Determined by peak hour demand of traction system and auxiliary applications.
  • 7. Power Demand Assessment (MVA) Year Corridor 2014 2016 2026 Traction 10.3 13.2 18.9 Corridor - 1 Auxiliary 31.4 32.1 39.7 Total 41.7 45.3 58.6 Traction 10.4 15.0 21.7 Corridor - 2 Auxiliary 7.2 8.6 10.1 Total 17.6 23.6 31.8 TOTAL 59.3 68.9 90.4
  • 8. Sources of Power Supply Corridor Grid Sub- Location of RSS Approx Length of Cables station (with of Metro i/p voltage) Authority Corridor - 1 GMR Vasavi Jail Complex 2km. 110 kV (230/110 kV) (110/33 kV) (Double Circuit Cables) Guindy Grid Adiyar 2km. 110 kV Sub-station (110/33 kV) (Double Circuit Cables) (230/110 kV) Corridor - 2 Koyambedu Koyambedu 1km. 110 kV Grid Sub- Depot (Double Circuit Cables) station (110/33 kV) (230/110 kV)
  • 9. Site Specific Study Need for project • Fourth largest city. • Population = 80 lakhs. • Population density = 6,482 /sq km. • 110 lakh trips. • Low per capita income (Rs 1,760 / month in 2005). • 65% population come under EWS.
  • 10. Site Specific Study Need for project • Study of 1992 shows Volume/capacity ratio on more than 1 in peak hours for 33.8 % of total road length. • Congested roads. • Poor geometrics of roads in older areas. • Missing link has put pressure on radial network. • Selection of Corridors based on previous studies.
  • 11. Site Specific Study Traffic Forecast • Based on land use planning and detailed surveys. • Growth rate of traffic demand = 5.2 %. • Growth in sub-urban rail system 2006-07 = 23 % 2007-08 = 12 %
  • 12. Site Specific Study Transport Demand Year Corridors Daily Length Pass-km Pass Passenger (km) km/km (lakh) Corr-1 318532 22.5 2632748 1.2 2011 Corr-2 254144 21.3 2137984 1.0 Total 572676 43.8 4770732 1.1 Corr-1 403169 22.5 3280363 1.5 2016 Corr-2 353297 21.3 2866624 1.3 Total 756466 43.8 6146987 1.4 Corr-1 542444 22.5 4575592 2.0 2016 Corr-2 521605 21.3 4323905 2.0 Total 1064048 43.8 8899496 2.0
  • 13. Site Specific Study Existing Infrastructure • Rail Network
  • 14. System Finalization Track • Standard Gauge (1435mm) for the following reasons : a. Intensive usage b.Long lasting c. Minimum maintenance d.Safety, reliability and comfort e.Minimum noise and vibrations.
  • 15. System Finalization Traction System • 750 V DC third rail for the following reasons : a. Height of metro structures including train heights need to be restricted to 12 mtr. b.25 kV AC traction system with overhead wires provides cluttered looks to system.
  • 16. System Finalization Signaling & Train Control • ‘Distance to go’ Automatic Train Protection and Automatic Train Supervision To provide capacity optimization Provide best services to public.
  • 17. System Finalization Telecommunication • Backbone for communication Signaling SCADA, AFC Operational & Administrative requirements Passenger Information System Crisis Management during emergencies
  • 18. System Finalization Automatic fare Collection • To handle large number of passengers  Efficient and Proper Ticket issue & fare collection  Simple & easy to operate  Easy accounting  Less manpower requirement  Amenable for quick fare changes  Cheaper in long run  Prevent leakage of revenue  Less cost of recyclable tickets
  • 19. System Finalization Rolling Stock • Same as used in DMRC for the following reasons:  Proven Reliability  Passenger Safety Feature  Energy Efficiency  Low Life Cycle Cost  Light Weight  High rate of acceleration and deceleration
  • 20. Rail Network • Line Map • Schematic Map
  • 21. Technical Inputs • Civil Engineering • Description of Alignment  Corridor 1 Breakup of Alignment length Total Elevated length = 8.785km Total Underground length = 14.300km Total Alignment length = 23.085km  Corridor 2 Break-up of alignment length Alignment length is 22.000 km from dead end to dead end
  • 22. Technical Inputs • GEOTECHNICAL INVESTIGATION  A total of 75 Boreholes were carried out along the corridors.  Archeans rock, found in the peninsular region are generally composed of granite and Gneisses of Peninsular Gneissic Complex, composition of duke is mainly Doleritic whereas sedimentary formations are mainly of shale and sand stone with or without fossiliferous beds. • UTILITY DIVERSION Following engineering items have been studied and described in this chapter:  Existing utilities and planning for their diversion during construction, if necessary.  Land acquisition necessary for the project both on permanent basis as well as temporary, including its break up between Government and private ownership. Details of utility provided in the report are based on information provided by utility agencies and need to be physically verified before taking up construction work.
  • 23. Technical Inputs • POWER SUPPLY SYSTEM  Broad estimation of auxiliary and traction power demand is made based on the following assumptions:- I. Specific energy consumption of rolling stock – 70KWh/1000 GTKM II. Regeneration by rolling stock – 20%. III. Elevated/at –grade station load – initially 200KW, which will increase to 300 KW inclusive of Property Development loads in the year 2026. IV. Underground Station load – initially 2000 kW, which will increase to 2500 kW in the year 2026. V. Depot auxiliary load – initially 2000KW, which will increase to 2500 KW in the year 2026. • SCADA SYSTEM I. The entire system of power supply (receiving, traction & auxiliary supply) shall be monitored and controlled from a centralized Operation Control Centre (OCC) through SCADA system. Modern SCADA system with intelligent remote terminal units (RTUs) shall be provided. Optical fibre provided for telecommunications will be used as communication carrier for SCADA system
  • 24. Inputs Other Than Technical • Maintenance Depots:  Two depots are proposed in phase-I. The Koyambedu Depot-cum-Workshop will be the main depot and located on corridor 2. the second depot is at Minambakkam on corridor 1 for stabling & inspection. • Train Operation Plan:  Salient Features of the proposed trains operation plan are :  Running of services for 19 hours of the day (5 AM to Midnight) with a  station dwell time of 30 seconds,  Make up time of 5 -10% with 8 -12% coasting.  Scheduled speed for these corridors has been assumed as 34 Kmph.
  • 25. Inputs Other Than Technical Total 184 coaches (92 coaches for Corridor 1 & 92 coaches for Corridor 2) are required in the year 2011.
  • 26. Clearances and Commitments • Implementing a metro project in a congested metropolis is indeed a challenge. • In sheer size, magnitude and technical complexity there are no parallels to metro • projects. Further, these projects are to be carried out in difficult urban environment without dislocating city life, while at the same time preserving the environment. • The project involves integration of a number of complex technical systems – some of these technologies used in these systems are totally new to the country – each one of which is a major project by itself. • Interfacing various system contracts is a difficult and highly skilled exercise. • Side by side, timely and adequate funds have to be assured for implementation and lands, without encumbrances, have to be taken possession of in time. • Clearances from the local authorities have to be taken permission to cut trees, diversion of utilities, management of road traffic, etc., all of which will call for an efficient and competent project implementing agency. • Eg. Land Use Policy etc.
  • 27. Approvals  Government of Tamil Nadu have approved in principle the two initial corridors on 7-11-2007  Government of India have approved the Chennai Metro Rail project on 28-1-2009.
  • 28. Cost Estimates • Capital costs workout at March 2007 price level as described hereunder  Corridor 1 Rs. 5,997 Crores  Corridor 2 Rs. 5,106 Crores (Note: Under the ‘Fully Underground’ considered at one stage as per State Govt.’s request, the cost of Corridor I was Rs. 7408 crores and Corridor II was Rs. 7978 crores which was considered unviable.) Costs are excluding taxes and duties, but including general charges @ 5% on all items except land and 3% contingencies on all items.
  • 29. Year Wise Investment Figs in Rs. Cr FY Without Taxes & Duties With Central Taxes Only 2008-09 533 570 2009-10 2971 3279 2010-11 3080 3484 2011-12 2705 3096 2012-13 1544 1767 2013-14 1621 1853 2014-15 613 701 Total 13067 14750 The staff is assumed to be provided @ 45 persons per kilometre. The escalation factor used for staff costs is 6% per annum to provide for both escalation and growth in salaries. The cost of other expenses is based on the O & M unit cost expected for the Delhi Metro Phase-1 project. The rate of electricity assumed in the Delhi Metro study is about Rs. 2.30 per unit whereas at present in Chennai the applicable rate is Rs. 3.00 per unit. The latter has been used for all calculations. The O&M cost (excluding staff cost) has been obtained by providing an escalation of 5% per annum.
  • 30. Financing Plan • Funding Patter based on SPV model is selected as represented below: • This project which is termed as a social project is implemented and operated under a SPV owned by Government of Tamil Nadu (GOTN) and Government of India (GOI)
  • 31. Revenues • The Revenue for Chennai metro mainly consists of fare box collection and other incomes from property development, advertisement, parking etc. Year Corr 1&2 Trips Per Day (In lakhs) 2013-14 6.66 2016-17 7.75 2026-27 12.87 • The growth rate for traffic is assumed at 5.2% per annum • The trip distribution has been worked out by considering average lead of 8.33 KM and with an assumption that maximum lead is 30 KM, The graphic presentation of the same is placed below.
  • 32. Fare Structure • The metro fare obtained by multiplying the bus fare by 2 times has been rounded off to the nearest rupee. • Other Sources of revenue:  Development of Property  Leasing of Parking Right at the station  Advertisements on viaducts and many more……
  • 33. References • www.chennaimetrorail.gov.in • www.cmdachennai.gov.in • Japan International Co-operation Agency – www.jicago.jp • International Association of Public Transport – www.uitp.org/regions/Asia-Pacific/activities.cfm • www.uitp.org/Public-Transport/metro/index.cfm

Editor's Notes

  1. Most Important in Urban Development Project Capacity and design so as to assist urban requirement
  2. Most Important in Urban Development Project Capacity and design so as to assist urban requirement
  3. Most Important in Urban Development Project Capacity and design so as to assist urban requirement
  4. Engines