As part of the ongoing commitment to keep Council apprised of the progress of the O-Train
Confederation Line project, this memo outlines the milestones achieved in Q1 and provides an
overview of the planned work for Q2 2017. In addition, it provides information that addresses
the most common questions received by staff from Members of Council.
Completed:
• Tunnel excavation (last section west of Rideau station) completed;
• Ramp excavation at west portal completed;
• Parliament Station East Tunnel Vent Shaft (TVS) excavation completed and shaft
waterproofed;
• Parliament East entrance exterior excavation completed;
• Tremblay Station building steel and roofing completed and permanent station power
energized;
• Completion of all civil and structural work at Blair, Cyrville and St. Laurent Stations;
• Nine vehicles have been fully assembled and are in various stages of testing;
• Climatic chamber testing of Light Rail Vehicle 3 (LRV3) has been completed;
• 6,978 metres of Overhead Catenary System wire has been installed along the guideway;
• 142 Overhead Catenary System poles (of 323) have been installed along the guideway;
• Seven Traction Power Sub Stations (TPSS) have been installed;
• 6.5 km of track has been installed at Belfast Yard and 11 km of track has been installed
along the guideway; and,
• Fire resistance testing of the vehicle under-frame and roof.
New/Ongoing:
• Tunney’s Pasture Station foundation and servicing work nearing completion;
• Guideway/track work continues between Tunney’s Pasture Station and the west portal;
• Bayview Station: The elevated guideway structure is nearing completion and concrete
work for ancillary building is ongoing;
• Pimisi Station: Erection of steel work is ongoing;
• Excavation of east portal ramp continues and wall construction continues at both the
east and west portals;
To / Destinataire Mayor and Members of Council File/N° de fichier:
From / Expéditeur Director,
O-Train Construction
Transportation Services Department
Subject / Objet O-Train Confederation Line Quarterly
Update (Q1 – 2017)
Date: May 11, 2017
2
• Work continues at Lyon Station vent and HVAC shafts;
• Lyon Station concrete lining nearing completion;
• Lyon Station east entrance construction continues within Place de Ville;
• Lyon Station west entrance is ongoing;
• Work continues on the west entrance of Parliament Station at Sun Life and the east
entrance at 155 Queen Street;
• Tunnel final lining continues between Parliament and Rideau Stations;
• Parliament and Rideau Stations concrete lining nearing completion;
• Rideau Station west entrance excavation ongoing;
• Concrete lining nearing completion at Rideau Station HVAC shaft;
• uOttawa Station mechanical and electrical work continues;
• Traction Power Sub Station 4 (TPSS4) delivery and installation near Mann Avenue;
• Reconstruction of the Mann Avenue Bridge is nearing completion;
• Canopy Steel work continues at Hurdman and commenced at Lees, uOttawa, Pimisi,
and Bayview;
• Overhead Catenary System (OCS) installation and electrification work continues
between Blair and Hurdman Stations;
• Architectural finishing, building systems and vertical circulation installations continue at
Blair, Cyrville, St-Laurent and Tremblay Stations;
• High speed vehicle testing from Blair to Cyrville;
• Testing continues on the various components of the vehicle and systems; and,
• Assembly of LR vehicles continues at Belfast Yard with an additional four vehicles in an
advanced state of assembly.
Budget
March 31, 2017
Project Description Authority Actual Expenditures
Contractual
Obligations/
Contingency Draws
Unspent/
Uncommitted
Balance
Confederation Line 2,130,000,000 1,387,270,689 720,413,702 22,315,609
Confederation Line
Contingency
100,000,000 32,041,003 57,233,401 10,725,596
LRT 417 Widening 226,000,000 222,598,738 267,184 3,134,078
To date, of the $100M contingency fund, the Contingency Management Committee (CMC) has
reserved $89M for contract variations and possible future changes, primarily related to property
requirements and transit priorities. This leaves a balance of $11M to cover other unforeseen
costs.
Revenue Service Availability/Revenue Service Start Date:
There have been a number of questions brought forward with respect to whether or not
construction timelines for the O-Train Confederation Line will be delayed due to the
infrastructure failure (‘the sinkhole”) event last June, and the term ‘Revenue Service’ is being
3
used to describe the completion of construction as well as the start of passenger service on the
train. The two are not the same, but they are related.
Revenue Service Availability is a contractual date identified in the Project Agreement between
the City and Rideau Transit Group (RTG), identifying the date the City officially takes ownership
of the newly constructed O-Train Confederation Line system. The Project Agreement has
established the ownership transfer date to be May 24, 2018 (just over a year from now).
Construction for the O-Train Confederation Line is ongoing at multiple locations. On any given
day, some parts of the project are ahead of schedule, some are on time and some are behind.
Following the sinkhole on Rideau Street, RTG developed a modified schedule that adjusted the
construction program, and provided additional resources and strategies to mitigate the impact
of the sinkhole on the overall schedule. RTG, based on the redefined workplan, has told the
City that they will meet the May 24, 2018 date for Revenue Service Availability (the transfer of
ownership) as outlined in the contract. This schedule will be continuously monitored, and the
City will be advised of any deviations or concerns about the contractual date. Should RTG
provide any indication or notification to the City that the transfer of ownership date will not be
met, staff will inform Council. If RTG does not meet this date, the structure of the Project
Agreement serves to impose significant financial consequences on RTG, most notably the
deferred payment of the Revenue Service Availability Payment of approximately $202M and
reduction of the fixed 30-year maintenance period and corresponding loss of the associated
Monthly Service Payments, as outlined in the Project Agreement.
The Revenue Service Availability Date, which is the transfer of ownership, is separate and
distinct from the actual beginning of revenue service for passengers. The City does not expect
to receive the trains one day and fill them with passengers the next. The transition from the
current public transit network (which is mainly bus, augmented by the O-Train Trillium Line) to
the multi-modal transit system, which will be the busiest Light Rail Transit (LRT) in North
America on day one of service, requires meticulous planning and extensive verification of
preparedness. These complex plans are being developed and will be in place in advance of the
launch of the O-Train Confederation Line, including the Ready for Rail campaign that was
launched at the April 19 Transit Commission meeting. The objective of the Ready for Rail
campaign is to implement a comprehensive communication, marketing, information and
education campaign, by building on the key findings of the 2018 Multi-Modal Customer Journey
project. The campaign will create awareness and equip customers with the information they
need to seamlessly transition to their new journey and create excitement for the launch of the
O-Train Confederation Line.
Staff is aware of the importance of establishing the date for passenger revenue service as soon
as possible. At the same time, staff want the public to be able to count on the date and to know
what to expect in the first few weeks of passenger service as they transition with us from
primarily bus-only service to reliable and efficient bus and rail service. Staff anticipates being
able to advise Council by the end of 2017 on the status of the anticipated first day of revenue
service.
Comprehensive component and system testing is integrated into the contract for the
Confederation Line. This testing, overseen by the City and verified by an independent certifier,
has already begun and will be on-going until the transfer of ownership. Before revenue service
4
for passengers begins, there will need to be specific, comprehensive testing of all operational
systems safety protocols and connection points to the feeder bus system. Rigorous testing and
safety inspections of all operational elements and the customer experience will be part of the
commissioning process. Passenger service will only begin when all systems testing and
commissioning protocols have been completed to the City`s satisfaction, industry requirements
and safety regimes.
The comprehensive testing and commissioning process includes the following elements:
• Vehicle static and dynamic testing;
• Traction Power Supply and Distribution;
• Trackwork, including switch heaters;
• Communication systems including: SCADA (Control Systems; CCTV cameras; public
address and passenger information; emergency, information and fire telephones;
intrusion control; and guideway intrusion detection;
• Train Control systems including signals, track switches and computer based train control;
• Tunnel ventilations systems;
• Radio systems;
• Transit Operations Control Centre;
• Light Rail Stations including elevators, escalators and fire alarms; and,
• Fare collection systems.
Additionally, the City and RTG are tracking the progress towards Revenue Service Availability
using a robust decision making plan called the Rail Activation Management Program (RAMP).
This comprehensive program was developed using best industry practice with input from rail
experts and details the key elements and deliverables that have to be achieved in order to
commence operations. In addition, a comprehensive decision making matrix was developed in
cooperation with RTG that outlines the key elements and conditions that must be met in
addition to the Project Agreement requirements in order to move into revenue service. RAMP
and the matrix was recently reviewed and endorsed by the Auditor General as part of the 2016
Audit of Light Rail Transit Planning and Change Management.
Worker Safety at Rideau Transit Group Construction Sites and Other Safety-related
Issues:
The Rideau Transit Group (RTG) is aware that protecting worker and public safety is a top
priority for the City of Ottawa, as it is for them. For the O-Train Confederation Line construction
and related works, RTG and OLRT-Constructors (OLRT-C) are required to meet provincial
labour laws and to ensure the safety and security of all their employees. In accordance with the
Occupational Health and Safety Act, conditions at all sites are monitored on an going basis by
OLRT-C or their subcontractor’s site supervisors and safety teams. Employees are encouraged
to bring any concerns they may have to the Joint Health and Safety Committee, comprised of
representatives from OLRT-C’s management and workers.
RTG has advised that, to date, over 5 million hours of labour have been invested in the project,
which has had an accident rate slightly over 0.3, approximately two-thirds less than the industry
average of 1.0 for heavy civil construction in Ontario. RTG and OLRT-C have confirmed that
5
they work collaboratively with the Ministry of Labour (MOL) to continually improve safety at their
construction sites and further reduce or eliminate the risk of injury.
The City of Ottawa does not formerly receive and is not a direct party to any order issued by the
MOL. The City does expect and receives high-level updates on all safety-related issues. RTG
has advised that, with respect to MOL inspections and subsequent orders, all of the
approximately 150 recent MOL orders, ranging from site housekeeping to washroom facilities to
improved lighting, have been addressed by RTG. Final resolution of these orders will be
completed upon verification by the MOL.
With respect to the recent crane incident and the gas leak, the City has been advised that these
are being actively addressed. The MOL attended the site of the crane incident at the east
portal on April 26, and RTG was ordered to stop work at this location until the structural integrity
of the retaining walls could be confirmed. This was accomplished on April 28. RTG’s
constructor and their subcontractor are undertaking a thorough review of the incident and the
equipment involved. The gas main break on Queen Street on May 2 is currently under
investigation by the Technical Standards & Safety Authority (TSSA) and the MOL. The MOL
has met with the constructor, released the site, and is now continuing their investigation with
subcontractors.
The City is also ensuring that the Chief Executive Officer of RTG, the General Manager of the
City’s Transportation Services Department and the Director of O-Train Construction are meeting
monthly with the Ottawa and District Labour Council to address any ongoing or emerging safety
concerns.
In addition, beginning the week of April 18, RTG’s constructor OLRT-C has been conducting a
series of exercises with Paramedics and Fire Services in the area of the east and west portals,
designed to ensure coordinated and effective emergency response in the tunnel. These
exercises will help ensure emergency responders are familiar with and oriented to the various
sites in the tunnel and its access points. These exercises are part of a transition from a tunnel
excavation to a construction operation and ultimately a passenger service, whereby emergency
rescues will become the responsibility of Ottawa’s emergency services personnel.
Confederation Line Tours During the Final Year of Construction:
As we enter the final year of construction on the O-Train Confederation Line, critical work
elements must be scheduled on specific timelines. Because tours of the O-train Confederation
Line for interested parties requires halting construction in order to ensure a safe environment
for visitors, tours will be restricted to only those required to fulfill obligations to the federal and
provincial funding partners in order to maintain the current production schedule. The recently
announced Ready for Rail campaign will provide other opportunities for Council to showcase
the system. Staff will continue to support Councillors’ requests for information and pictures to be
shared with constituents. Staff will provide Council with notice with respect to when tours might
be arranged again, closer to the date of ownership transfer.
2017 Readiness:
6
The Project Agreement for the Confederation Line project includes clauses regarding 2017
readiness. The intent of these requirements was to ensure city streets between the east and
west portals were restored to pre-construction configuration before the 2017 Canada Day
celebrations.
These Project Agreement requirements were re-examined following the June 2016 sinkhole.
RTG, in cooperation with the City, has implemented more crews, more equipment and more
work shifts in order to remain on schedule. However, some surface work will continue beyond
July 2017.
Work on Queen Street streetscaping has resumed between Bank and O’Connor Streets, and
will continue through the summer. This work, to improve pedestrian, cycling and vehicle
infrastructure, requires some street closures and detours.
The section of Queen Street between Bank Street and O’Connor Street is closed to motorists
and cyclists until mid-June to allow for sidewalk and roadway improvements that will help the
Queen Street corridor better integrate with the O-Train Confederation Line Light Rail Transit
Project.
Local traffic is still being maintained through this period to allow access to parking garages, and
pedestrian access is maintained on the north side of Queen Street.
Signed detours are in place for motorists and cyclists during the closure.
RTG will cease construction activities on Rideau Street on Canada Day that could affect public
mobility and enjoyment of the festivities. Enhanced hoarding and street cleaning on both
Rideau Street and Queen Street will provide for a welcoming environment during Canada Day
celebrations.
KONTINUUM at Lyon Station:
The City and RTG are on track to hand over Lyon Station to the Ottawa 2017 Bureau for
Kontinuum. The Ottawa 2017 Bureau is responsible for the installation of the show once the
station is handed over to them. In the coming weeks, the Bureau will be providing the details on
their event and the opening date.
Communications
As has been noted, the O-Train Confederation Line construction project is a multi-year
project, with numerous construction sites across the city, resulting in both localized and
citywide impacts. As part of the Project Agreement, the City is the lead for the management
and sharing of public information.
The City has divided communications efforts into two streams:
• Stakeholder Relations: focuses on local residents, businesses and other stakeholders
directly affected by the construction; and,
• Citywide Communications: ensures that communications on the overall project, as well
as traffic and mobility impacts, are shared with the public in a timely and consistent
7
manner. This information is integrated with traffic and mobility impacts resulting from
other construction projects as well as planned and unplanned events.
The Stakeholder Relations group continues to meet with Councillors, stakeholders and
community representatives affected by the O-Train Confederation Line project to provide
information about upcoming work, mitigate risk and coordinate activities, as required. Examples
of these outreach efforts include:
• Weekly construction project updates sent to subscriber list and posted on
Ottawa.ca/confederationline;
• Regular, monthly meetings and presentations to key stakeholders, including the
Canadian Broadcasting Corporation (CBC), uOttawa, VIA Rail and Public Services
Procurement Canada (PSPC);
• Sharing information through meetings and communication documents with property
owners regarding tunnel excavation under Queen Street, Rideau Street and Waller
Street alignments;
• Regular design and construction meetings with all integrated station partners;
• Sharing information through meetings and communication documents with local
residents and businesses regarding Belfast Yard and connector work;
• Sharing information through presentations, meetings and communication documents
with local residents and businesses regarding the construction at Blair, Cyrville, St-
Laurent, Tremblay, Hurdman, Lees, uOttawa, Rideau, Parliament, Lyon, Pimisi, Bayview
and Tunney’s Pasture Stations;
• Sharing information through regular monthly Councillor led community meetings, weekly
updates and communications documents with Scott Street residents;
• Information booths at various City events including Councillor Open Houses and senior
tea luncheons hosted by various members of Council; and,
• Project presentations to multiple internal and external organizations and departments
(including industry associations, community associations, business groups, international
delegations and business improvement areas).
With respect to citywide communications, the City has increased communications efforts
around all construction-related projects to provide timely, accurate and reliable information to
help the public plan how to move around the city. The public is also kept informed and
engaged on construction milestones. Examples of citywide communications efforts include:
• Regular Public Service Announcements related to the O-Train Confederation Line
projects;
• Weekly updates to the O-Train Confederation Line project website;
• Daily Traffic Updates are shared with local traffic reporters;
• Real-time commuter delays are shared with the public via Twitter at
@Ottawacity,@Ottawa_Traffic and @OCTranspo;
• Quarterly traffic and construction briefings providing four-month outlooks;
• The Ottawa Nav mobile app is available for motorists, cyclists and pedestrians to
plan routes in real-time;
• Construction and variable message signs are installed near construction sites alerting
commuters to current or planned works;
• Information about construction and traffic impacts are posted on Ottawa.ca and
8
weekly updates on the Confederation Line are included on Ottawa.ca/confederationline;
• Notifications are issued prior to the start of any construction project;
• Unplanned traffic impacts are shared with the public via Twitter and on the landing
page of Ottawa.ca; and,
• Milestones and interesting facts about the project are highlighted via the City's social
media channels.
Look Ahead
The following activities are planned for Q2 2017:
• Trackwork begins in west running tunnel moving eastward;
• Lyon Station west entrance architectural finishes begin;
• Tunnel vent shafts at Lyon Station substantially completed;
• Parliament Station architectural work begins;
• West Portal construction substantial completion;
• Brake and propulsion tests on the vehicles being completed;
• Thales train control equipment mimic screen live at the Maintenance and Storage Facility
(MSF); and,
• System Integration Testing begins.
Should you have any questions, please do not hesitate to contact me at extension 16623.
Original signed by
Steve Cripps
cc: Senior Leadership Team
Transportation Services Departmental Leadership Team
Director, Public Information and Media Relations

More Related Content

What's hot

I-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework DocumentI-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework DocumentFairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Silver Line Update July 2016
Silver Line Update July 2016Silver Line Update July 2016
Silver Line Update July 2016Fairfax County
 
Gauteng Freeways
Gauteng FreewaysGauteng Freeways
Gauteng Freewaysguest85be6a
 
Railway sidings 017
Railway sidings 017Railway sidings 017
Railway sidings 017Mohd Bakhsh
 
20131002 presentation
20131002 presentation20131002 presentation
20131002 presentationRafat Ali
 
Spring 2017-service-change-external-memo -final-feb-27-en
Spring 2017-service-change-external-memo -final-feb-27-enSpring 2017-service-change-external-memo -final-feb-27-en
Spring 2017-service-change-external-memo -final-feb-27-enDevyn Barrie
 
Operation Bridgeguard 2007
Operation Bridgeguard 2007Operation Bridgeguard 2007
Operation Bridgeguard 2007Bradley Yates
 
TTC Procurement Authorization for ATC-CBTC
TTC Procurement Authorization for ATC-CBTCTTC Procurement Authorization for ATC-CBTC
TTC Procurement Authorization for ATC-CBTCGerman Camargo
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Airport Monitoring Report 2011-12
Airport Monitoring Report 2011-12Airport Monitoring Report 2011-12
Airport Monitoring Report 2011-12Rafat Ali
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...Sok-Tharath CHREUNG
 
Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012Sok-Tharath CHREUNG
 
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014SCVTA
 
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014COTA BUS
 
Item 8.5 2014 lua update
Item 8.5   2014 lua updateItem 8.5   2014 lua update
Item 8.5 2014 lua updateepdevelopment
 

What's hot (20)

Presentation_EUFARM_Final_SC
Presentation_EUFARM_Final_SCPresentation_EUFARM_Final_SC
Presentation_EUFARM_Final_SC
 
I-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework DocumentI-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework Document
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
TeamTX Austin 2015 Presentations
TeamTX Austin 2015 PresentationsTeamTX Austin 2015 Presentations
TeamTX Austin 2015 Presentations
 
FAMPO Update on I-95 Corridor Study Phase I
FAMPO Update on I-95 Corridor Study Phase IFAMPO Update on I-95 Corridor Study Phase I
FAMPO Update on I-95 Corridor Study Phase I
 
Silver Line Update July 2016
Silver Line Update July 2016Silver Line Update July 2016
Silver Line Update July 2016
 
Gauteng Freeways
Gauteng FreewaysGauteng Freeways
Gauteng Freeways
 
Railway sidings 017
Railway sidings 017Railway sidings 017
Railway sidings 017
 
20131002 presentation
20131002 presentation20131002 presentation
20131002 presentation
 
Spring 2017-service-change-external-memo -final-feb-27-en
Spring 2017-service-change-external-memo -final-feb-27-enSpring 2017-service-change-external-memo -final-feb-27-en
Spring 2017-service-change-external-memo -final-feb-27-en
 
Operation Bridgeguard 2007
Operation Bridgeguard 2007Operation Bridgeguard 2007
Operation Bridgeguard 2007
 
TTC Procurement Authorization for ATC-CBTC
TTC Procurement Authorization for ATC-CBTCTTC Procurement Authorization for ATC-CBTC
TTC Procurement Authorization for ATC-CBTC
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Airport Monitoring Report 2011-12
Airport Monitoring Report 2011-12Airport Monitoring Report 2011-12
Airport Monitoring Report 2011-12
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
Presentation for Railways Rehabilitation Project in Cambodia for Technical Wo...
 
Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012Presentation of Railway Department, Cambodia, 2012
Presentation of Railway Department, Cambodia, 2012
 
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014
VTA Light Rail Efficiency Project Mountain View newsletter Spring 2014
 
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
CMAX Cleveland Avenue BRT Public Meeting - October 14, 2014
 
Item 8.5 2014 lua update
Item 8.5   2014 lua updateItem 8.5   2014 lua update
Item 8.5 2014 lua update
 

Similar to Confederation line quarterly memo to council q1 2017

Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House SlidesCrosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment WorksCrosstown TO
 
May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfSteve Desroches
 
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Jonathan Granda
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Cts tradeshow remarks
Cts tradeshow remarksCts tradeshow remarks
Cts tradeshow remarksCrosstown TO
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Ibrahim Al-Hudhaif
 

Similar to Confederation line quarterly memo to council q1 2017 (20)

SmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network PlanningSmartTrack Presentation- Toronto Transit Network Planning
SmartTrack Presentation- Toronto Transit Network Planning
 
Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031Developing Toronto’s Transit Network Plan to 2031
Developing Toronto’s Transit Network Plan to 2031
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
Scarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 PresentationScarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 Presentation
 
SmartTrack Presentation - June, 2015
SmartTrack Presentation - June, 2015SmartTrack Presentation - June, 2015
SmartTrack Presentation - June, 2015
 
15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation
 
2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG2016-06-06 Scarborough Subway Extension SAG
2016-06-06 Scarborough Subway Extension SAG
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 
May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdf
 
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Toronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting PresentationToronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting Presentation
 
15 03-24 rlpa sag1 presentation
15 03-24 rlpa sag1 presentation15 03-24 rlpa sag1 presentation
15 03-24 rlpa sag1 presentation
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Cts tradeshow remarks
Cts tradeshow remarksCts tradeshow remarks
Cts tradeshow remarks
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
 

More from Devyn Barrie

Memo to council step 1 rules for food and drink establishments
Memo to council   step 1 rules for food and drink establishmentsMemo to council   step 1 rules for food and drink establishments
Memo to council step 1 rules for food and drink establishmentsDevyn Barrie
 
Rideau Station indoor air quality assessment report
Rideau Station indoor air quality assessment reportRideau Station indoor air quality assessment report
Rideau Station indoor air quality assessment reportDevyn Barrie
 
2018 CUSA by-election writ
2018 CUSA by-election writ 2018 CUSA by-election writ
2018 CUSA by-election writ Devyn Barrie
 
Notice of applicaton[30031]
Notice of applicaton[30031]Notice of applicaton[30031]
Notice of applicaton[30031]Devyn Barrie
 
Background the ottawa hospital site review[11168]
Background the ottawa hospital site review[11168]Background the ottawa hospital site review[11168]
Background the ottawa hospital site review[11168]Devyn Barrie
 
Councilor's letter to OMB
Councilor's letter to OMBCouncilor's letter to OMB
Councilor's letter to OMBDevyn Barrie
 
The ottawa hospital site review
The ottawa hospital site reviewThe ottawa hospital site review
The ottawa hospital site reviewDevyn Barrie
 
Ottawa fall construction season 2016
Ottawa fall construction season 2016Ottawa fall construction season 2016
Ottawa fall construction season 2016Devyn Barrie
 
160812. statement of claim
160812. statement of claim160812. statement of claim
160812. statement of claimDevyn Barrie
 
Dw advisory-update-no-3-1600-aug-11-2016
Dw advisory-update-no-3-1600-aug-11-2016Dw advisory-update-no-3-1600-aug-11-2016
Dw advisory-update-no-3-1600-aug-11-2016Devyn Barrie
 
Arnprior water advisory extension news release
Arnprior water advisory extension news releaseArnprior water advisory extension news release
Arnprior water advisory extension news releaseDevyn Barrie
 
Memo to council June 13 2016
Memo to council June 13 2016Memo to council June 13 2016
Memo to council June 13 2016Devyn Barrie
 
City of Ottawa crime trends 2014-15
City of Ottawa crime trends 2014-15City of Ottawa crime trends 2014-15
City of Ottawa crime trends 2014-15Devyn Barrie
 
2015 crime states for Ward 6 Stittsville
2015 crime states for Ward 6 Stittsville2015 crime states for Ward 6 Stittsville
2015 crime states for Ward 6 StittsvilleDevyn Barrie
 
Report on fraud and waste hotline - June 20 2016
Report on fraud and waste hotline - June 20 2016Report on fraud and waste hotline - June 20 2016
Report on fraud and waste hotline - June 20 2016Devyn Barrie
 

More from Devyn Barrie (16)

Memo to council step 1 rules for food and drink establishments
Memo to council   step 1 rules for food and drink establishmentsMemo to council   step 1 rules for food and drink establishments
Memo to council step 1 rules for food and drink establishments
 
Rideau Station indoor air quality assessment report
Rideau Station indoor air quality assessment reportRideau Station indoor air quality assessment report
Rideau Station indoor air quality assessment report
 
2018 CUSA by-election writ
2018 CUSA by-election writ 2018 CUSA by-election writ
2018 CUSA by-election writ
 
Notice of applicaton[30031]
Notice of applicaton[30031]Notice of applicaton[30031]
Notice of applicaton[30031]
 
7628 flewellyn
7628 flewellyn7628 flewellyn
7628 flewellyn
 
Background the ottawa hospital site review[11168]
Background the ottawa hospital site review[11168]Background the ottawa hospital site review[11168]
Background the ottawa hospital site review[11168]
 
Councilor's letter to OMB
Councilor's letter to OMBCouncilor's letter to OMB
Councilor's letter to OMB
 
The ottawa hospital site review
The ottawa hospital site reviewThe ottawa hospital site review
The ottawa hospital site review
 
Ottawa fall construction season 2016
Ottawa fall construction season 2016Ottawa fall construction season 2016
Ottawa fall construction season 2016
 
160812. statement of claim
160812. statement of claim160812. statement of claim
160812. statement of claim
 
Dw advisory-update-no-3-1600-aug-11-2016
Dw advisory-update-no-3-1600-aug-11-2016Dw advisory-update-no-3-1600-aug-11-2016
Dw advisory-update-no-3-1600-aug-11-2016
 
Arnprior water advisory extension news release
Arnprior water advisory extension news releaseArnprior water advisory extension news release
Arnprior water advisory extension news release
 
Memo to council June 13 2016
Memo to council June 13 2016Memo to council June 13 2016
Memo to council June 13 2016
 
City of Ottawa crime trends 2014-15
City of Ottawa crime trends 2014-15City of Ottawa crime trends 2014-15
City of Ottawa crime trends 2014-15
 
2015 crime states for Ward 6 Stittsville
2015 crime states for Ward 6 Stittsville2015 crime states for Ward 6 Stittsville
2015 crime states for Ward 6 Stittsville
 
Report on fraud and waste hotline - June 20 2016
Report on fraud and waste hotline - June 20 2016Report on fraud and waste hotline - June 20 2016
Report on fraud and waste hotline - June 20 2016
 

Recently uploaded

Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirt
Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-ShirtNika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirt
Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirtniherranjansingha
 
Minnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T ShirtMinnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T Shirtniherranjansingha
 
19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Abdul-Hakim Shabazz
 
Meta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololMeta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololbhavenpr
 
2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politicsConradSmit5
 
24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Encore portal Project PPt on live portal
Encore portal Project PPt on live portalEncore portal Project PPt on live portal
Encore portal Project PPt on live portalEshantRawat2
 
23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jEmbed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jbhavenpr
 
israeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfisraeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfssuser5750e1
 
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[bhavenpr
 
20052024_First India Newspaper Jaipur.pdf
20052024_First India Newspaper Jaipur.pdf20052024_First India Newspaper Jaipur.pdf
20052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Dominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryDominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryRDE GROUP CORP
 
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosR$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosMaurílio Júnior
 
21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...Faga1939
 
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:bhavenpr
 
May 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfMay 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfmanisha194592
 

Recently uploaded (20)

Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirt
Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-ShirtNika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirt
Nika Muhl Visa Approval Shirt, Nika Muhl Visa Approval T-Shirt
 
Minnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T ShirtMinnesota Timberwolves Bring Ya Ass T Shirt
Minnesota Timberwolves Bring Ya Ass T Shirt
 
19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf19052024_First India Newspaper Jaipur.pdf
19052024_First India Newspaper Jaipur.pdf
 
Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!Have A Complimentary Cheat Sheet, On Us!!!
Have A Complimentary Cheat Sheet, On Us!!!
 
Meta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejololMeta_AI_ads_investigation.pdfldoljjwejolejolol
Meta_AI_ads_investigation.pdfldoljjwejolejolol
 
2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics2024 - Love and Madness - a book about love, madness, heartbreak and politics
2024 - Love and Madness - a book about love, madness, heartbreak and politics
 
24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf24052024_First India Newspaper Jaipur.pdf
24052024_First India Newspaper Jaipur.pdf
 
Encore portal Project PPt on live portal
Encore portal Project PPt on live portalEncore portal Project PPt on live portal
Encore portal Project PPt on live portal
 
23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf23052024_First India Newspaper Jaipur.pdf
23052024_First India Newspaper Jaipur.pdf
 
25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf25052024_First India Newspaper Jaipur.pdf
25052024_First India Newspaper Jaipur.pdf
 
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;jEmbed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
Embed-4-1-1.pdf vm ;sdkp[kdp[kpdkpodp;p;j
 
israeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdfisraeil_bnetaniahou_panel_report_eng.pdf
israeil_bnetaniahou_panel_report_eng.pdf
 
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
Embed-4-3 (1).pdf cvxx'f['df[p'lf][l][fl][fl][][l[
 
20052024_First India Newspaper Jaipur.pdf
20052024_First India Newspaper Jaipur.pdf20052024_First India Newspaper Jaipur.pdf
20052024_First India Newspaper Jaipur.pdf
 
Dominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive SummaryDominican American Coalition PAC Executive Summary
Dominican American Coalition PAC Executive Summary
 
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatóriosR$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
R$ 78 milhões: Estado aprova 593 propostas para acordos diretos de precatórios
 
21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf21052024_First India Newspaper Jaipur.pdf
21052024_First India Newspaper Jaipur.pdf
 
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
PEACE BETWEEN ISRAEL AND PALESTINE REQUIRES EXTREMISTS OUT OF POWER AND RESTR...
 
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:Embed-3-1-1.pdf  The ECI direction on April 2, 2024 can be read here:
Embed-3-1-1.pdf The ECI direction on April 2, 2024 can be read here:
 
May 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdfMay 2024 - Crypto Market Report_FINAL.pdf
May 2024 - Crypto Market Report_FINAL.pdf
 

Confederation line quarterly memo to council q1 2017

  • 1. M E M O / N O T E D E S E R V I C E As part of the ongoing commitment to keep Council apprised of the progress of the O-Train Confederation Line project, this memo outlines the milestones achieved in Q1 and provides an overview of the planned work for Q2 2017. In addition, it provides information that addresses the most common questions received by staff from Members of Council. Completed: • Tunnel excavation (last section west of Rideau station) completed; • Ramp excavation at west portal completed; • Parliament Station East Tunnel Vent Shaft (TVS) excavation completed and shaft waterproofed; • Parliament East entrance exterior excavation completed; • Tremblay Station building steel and roofing completed and permanent station power energized; • Completion of all civil and structural work at Blair, Cyrville and St. Laurent Stations; • Nine vehicles have been fully assembled and are in various stages of testing; • Climatic chamber testing of Light Rail Vehicle 3 (LRV3) has been completed; • 6,978 metres of Overhead Catenary System wire has been installed along the guideway; • 142 Overhead Catenary System poles (of 323) have been installed along the guideway; • Seven Traction Power Sub Stations (TPSS) have been installed; • 6.5 km of track has been installed at Belfast Yard and 11 km of track has been installed along the guideway; and, • Fire resistance testing of the vehicle under-frame and roof. New/Ongoing: • Tunney’s Pasture Station foundation and servicing work nearing completion; • Guideway/track work continues between Tunney’s Pasture Station and the west portal; • Bayview Station: The elevated guideway structure is nearing completion and concrete work for ancillary building is ongoing; • Pimisi Station: Erection of steel work is ongoing; • Excavation of east portal ramp continues and wall construction continues at both the east and west portals; To / Destinataire Mayor and Members of Council File/N° de fichier: From / Expéditeur Director, O-Train Construction Transportation Services Department Subject / Objet O-Train Confederation Line Quarterly Update (Q1 – 2017) Date: May 11, 2017
  • 2. 2 • Work continues at Lyon Station vent and HVAC shafts; • Lyon Station concrete lining nearing completion; • Lyon Station east entrance construction continues within Place de Ville; • Lyon Station west entrance is ongoing; • Work continues on the west entrance of Parliament Station at Sun Life and the east entrance at 155 Queen Street; • Tunnel final lining continues between Parliament and Rideau Stations; • Parliament and Rideau Stations concrete lining nearing completion; • Rideau Station west entrance excavation ongoing; • Concrete lining nearing completion at Rideau Station HVAC shaft; • uOttawa Station mechanical and electrical work continues; • Traction Power Sub Station 4 (TPSS4) delivery and installation near Mann Avenue; • Reconstruction of the Mann Avenue Bridge is nearing completion; • Canopy Steel work continues at Hurdman and commenced at Lees, uOttawa, Pimisi, and Bayview; • Overhead Catenary System (OCS) installation and electrification work continues between Blair and Hurdman Stations; • Architectural finishing, building systems and vertical circulation installations continue at Blair, Cyrville, St-Laurent and Tremblay Stations; • High speed vehicle testing from Blair to Cyrville; • Testing continues on the various components of the vehicle and systems; and, • Assembly of LR vehicles continues at Belfast Yard with an additional four vehicles in an advanced state of assembly. Budget March 31, 2017 Project Description Authority Actual Expenditures Contractual Obligations/ Contingency Draws Unspent/ Uncommitted Balance Confederation Line 2,130,000,000 1,387,270,689 720,413,702 22,315,609 Confederation Line Contingency 100,000,000 32,041,003 57,233,401 10,725,596 LRT 417 Widening 226,000,000 222,598,738 267,184 3,134,078 To date, of the $100M contingency fund, the Contingency Management Committee (CMC) has reserved $89M for contract variations and possible future changes, primarily related to property requirements and transit priorities. This leaves a balance of $11M to cover other unforeseen costs. Revenue Service Availability/Revenue Service Start Date: There have been a number of questions brought forward with respect to whether or not construction timelines for the O-Train Confederation Line will be delayed due to the infrastructure failure (‘the sinkhole”) event last June, and the term ‘Revenue Service’ is being
  • 3. 3 used to describe the completion of construction as well as the start of passenger service on the train. The two are not the same, but they are related. Revenue Service Availability is a contractual date identified in the Project Agreement between the City and Rideau Transit Group (RTG), identifying the date the City officially takes ownership of the newly constructed O-Train Confederation Line system. The Project Agreement has established the ownership transfer date to be May 24, 2018 (just over a year from now). Construction for the O-Train Confederation Line is ongoing at multiple locations. On any given day, some parts of the project are ahead of schedule, some are on time and some are behind. Following the sinkhole on Rideau Street, RTG developed a modified schedule that adjusted the construction program, and provided additional resources and strategies to mitigate the impact of the sinkhole on the overall schedule. RTG, based on the redefined workplan, has told the City that they will meet the May 24, 2018 date for Revenue Service Availability (the transfer of ownership) as outlined in the contract. This schedule will be continuously monitored, and the City will be advised of any deviations or concerns about the contractual date. Should RTG provide any indication or notification to the City that the transfer of ownership date will not be met, staff will inform Council. If RTG does not meet this date, the structure of the Project Agreement serves to impose significant financial consequences on RTG, most notably the deferred payment of the Revenue Service Availability Payment of approximately $202M and reduction of the fixed 30-year maintenance period and corresponding loss of the associated Monthly Service Payments, as outlined in the Project Agreement. The Revenue Service Availability Date, which is the transfer of ownership, is separate and distinct from the actual beginning of revenue service for passengers. The City does not expect to receive the trains one day and fill them with passengers the next. The transition from the current public transit network (which is mainly bus, augmented by the O-Train Trillium Line) to the multi-modal transit system, which will be the busiest Light Rail Transit (LRT) in North America on day one of service, requires meticulous planning and extensive verification of preparedness. These complex plans are being developed and will be in place in advance of the launch of the O-Train Confederation Line, including the Ready for Rail campaign that was launched at the April 19 Transit Commission meeting. The objective of the Ready for Rail campaign is to implement a comprehensive communication, marketing, information and education campaign, by building on the key findings of the 2018 Multi-Modal Customer Journey project. The campaign will create awareness and equip customers with the information they need to seamlessly transition to their new journey and create excitement for the launch of the O-Train Confederation Line. Staff is aware of the importance of establishing the date for passenger revenue service as soon as possible. At the same time, staff want the public to be able to count on the date and to know what to expect in the first few weeks of passenger service as they transition with us from primarily bus-only service to reliable and efficient bus and rail service. Staff anticipates being able to advise Council by the end of 2017 on the status of the anticipated first day of revenue service. Comprehensive component and system testing is integrated into the contract for the Confederation Line. This testing, overseen by the City and verified by an independent certifier, has already begun and will be on-going until the transfer of ownership. Before revenue service
  • 4. 4 for passengers begins, there will need to be specific, comprehensive testing of all operational systems safety protocols and connection points to the feeder bus system. Rigorous testing and safety inspections of all operational elements and the customer experience will be part of the commissioning process. Passenger service will only begin when all systems testing and commissioning protocols have been completed to the City`s satisfaction, industry requirements and safety regimes. The comprehensive testing and commissioning process includes the following elements: • Vehicle static and dynamic testing; • Traction Power Supply and Distribution; • Trackwork, including switch heaters; • Communication systems including: SCADA (Control Systems; CCTV cameras; public address and passenger information; emergency, information and fire telephones; intrusion control; and guideway intrusion detection; • Train Control systems including signals, track switches and computer based train control; • Tunnel ventilations systems; • Radio systems; • Transit Operations Control Centre; • Light Rail Stations including elevators, escalators and fire alarms; and, • Fare collection systems. Additionally, the City and RTG are tracking the progress towards Revenue Service Availability using a robust decision making plan called the Rail Activation Management Program (RAMP). This comprehensive program was developed using best industry practice with input from rail experts and details the key elements and deliverables that have to be achieved in order to commence operations. In addition, a comprehensive decision making matrix was developed in cooperation with RTG that outlines the key elements and conditions that must be met in addition to the Project Agreement requirements in order to move into revenue service. RAMP and the matrix was recently reviewed and endorsed by the Auditor General as part of the 2016 Audit of Light Rail Transit Planning and Change Management. Worker Safety at Rideau Transit Group Construction Sites and Other Safety-related Issues: The Rideau Transit Group (RTG) is aware that protecting worker and public safety is a top priority for the City of Ottawa, as it is for them. For the O-Train Confederation Line construction and related works, RTG and OLRT-Constructors (OLRT-C) are required to meet provincial labour laws and to ensure the safety and security of all their employees. In accordance with the Occupational Health and Safety Act, conditions at all sites are monitored on an going basis by OLRT-C or their subcontractor’s site supervisors and safety teams. Employees are encouraged to bring any concerns they may have to the Joint Health and Safety Committee, comprised of representatives from OLRT-C’s management and workers. RTG has advised that, to date, over 5 million hours of labour have been invested in the project, which has had an accident rate slightly over 0.3, approximately two-thirds less than the industry average of 1.0 for heavy civil construction in Ontario. RTG and OLRT-C have confirmed that
  • 5. 5 they work collaboratively with the Ministry of Labour (MOL) to continually improve safety at their construction sites and further reduce or eliminate the risk of injury. The City of Ottawa does not formerly receive and is not a direct party to any order issued by the MOL. The City does expect and receives high-level updates on all safety-related issues. RTG has advised that, with respect to MOL inspections and subsequent orders, all of the approximately 150 recent MOL orders, ranging from site housekeeping to washroom facilities to improved lighting, have been addressed by RTG. Final resolution of these orders will be completed upon verification by the MOL. With respect to the recent crane incident and the gas leak, the City has been advised that these are being actively addressed. The MOL attended the site of the crane incident at the east portal on April 26, and RTG was ordered to stop work at this location until the structural integrity of the retaining walls could be confirmed. This was accomplished on April 28. RTG’s constructor and their subcontractor are undertaking a thorough review of the incident and the equipment involved. The gas main break on Queen Street on May 2 is currently under investigation by the Technical Standards & Safety Authority (TSSA) and the MOL. The MOL has met with the constructor, released the site, and is now continuing their investigation with subcontractors. The City is also ensuring that the Chief Executive Officer of RTG, the General Manager of the City’s Transportation Services Department and the Director of O-Train Construction are meeting monthly with the Ottawa and District Labour Council to address any ongoing or emerging safety concerns. In addition, beginning the week of April 18, RTG’s constructor OLRT-C has been conducting a series of exercises with Paramedics and Fire Services in the area of the east and west portals, designed to ensure coordinated and effective emergency response in the tunnel. These exercises will help ensure emergency responders are familiar with and oriented to the various sites in the tunnel and its access points. These exercises are part of a transition from a tunnel excavation to a construction operation and ultimately a passenger service, whereby emergency rescues will become the responsibility of Ottawa’s emergency services personnel. Confederation Line Tours During the Final Year of Construction: As we enter the final year of construction on the O-Train Confederation Line, critical work elements must be scheduled on specific timelines. Because tours of the O-train Confederation Line for interested parties requires halting construction in order to ensure a safe environment for visitors, tours will be restricted to only those required to fulfill obligations to the federal and provincial funding partners in order to maintain the current production schedule. The recently announced Ready for Rail campaign will provide other opportunities for Council to showcase the system. Staff will continue to support Councillors’ requests for information and pictures to be shared with constituents. Staff will provide Council with notice with respect to when tours might be arranged again, closer to the date of ownership transfer. 2017 Readiness:
  • 6. 6 The Project Agreement for the Confederation Line project includes clauses regarding 2017 readiness. The intent of these requirements was to ensure city streets between the east and west portals were restored to pre-construction configuration before the 2017 Canada Day celebrations. These Project Agreement requirements were re-examined following the June 2016 sinkhole. RTG, in cooperation with the City, has implemented more crews, more equipment and more work shifts in order to remain on schedule. However, some surface work will continue beyond July 2017. Work on Queen Street streetscaping has resumed between Bank and O’Connor Streets, and will continue through the summer. This work, to improve pedestrian, cycling and vehicle infrastructure, requires some street closures and detours. The section of Queen Street between Bank Street and O’Connor Street is closed to motorists and cyclists until mid-June to allow for sidewalk and roadway improvements that will help the Queen Street corridor better integrate with the O-Train Confederation Line Light Rail Transit Project. Local traffic is still being maintained through this period to allow access to parking garages, and pedestrian access is maintained on the north side of Queen Street. Signed detours are in place for motorists and cyclists during the closure. RTG will cease construction activities on Rideau Street on Canada Day that could affect public mobility and enjoyment of the festivities. Enhanced hoarding and street cleaning on both Rideau Street and Queen Street will provide for a welcoming environment during Canada Day celebrations. KONTINUUM at Lyon Station: The City and RTG are on track to hand over Lyon Station to the Ottawa 2017 Bureau for Kontinuum. The Ottawa 2017 Bureau is responsible for the installation of the show once the station is handed over to them. In the coming weeks, the Bureau will be providing the details on their event and the opening date. Communications As has been noted, the O-Train Confederation Line construction project is a multi-year project, with numerous construction sites across the city, resulting in both localized and citywide impacts. As part of the Project Agreement, the City is the lead for the management and sharing of public information. The City has divided communications efforts into two streams: • Stakeholder Relations: focuses on local residents, businesses and other stakeholders directly affected by the construction; and, • Citywide Communications: ensures that communications on the overall project, as well as traffic and mobility impacts, are shared with the public in a timely and consistent
  • 7. 7 manner. This information is integrated with traffic and mobility impacts resulting from other construction projects as well as planned and unplanned events. The Stakeholder Relations group continues to meet with Councillors, stakeholders and community representatives affected by the O-Train Confederation Line project to provide information about upcoming work, mitigate risk and coordinate activities, as required. Examples of these outreach efforts include: • Weekly construction project updates sent to subscriber list and posted on Ottawa.ca/confederationline; • Regular, monthly meetings and presentations to key stakeholders, including the Canadian Broadcasting Corporation (CBC), uOttawa, VIA Rail and Public Services Procurement Canada (PSPC); • Sharing information through meetings and communication documents with property owners regarding tunnel excavation under Queen Street, Rideau Street and Waller Street alignments; • Regular design and construction meetings with all integrated station partners; • Sharing information through meetings and communication documents with local residents and businesses regarding Belfast Yard and connector work; • Sharing information through presentations, meetings and communication documents with local residents and businesses regarding the construction at Blair, Cyrville, St- Laurent, Tremblay, Hurdman, Lees, uOttawa, Rideau, Parliament, Lyon, Pimisi, Bayview and Tunney’s Pasture Stations; • Sharing information through regular monthly Councillor led community meetings, weekly updates and communications documents with Scott Street residents; • Information booths at various City events including Councillor Open Houses and senior tea luncheons hosted by various members of Council; and, • Project presentations to multiple internal and external organizations and departments (including industry associations, community associations, business groups, international delegations and business improvement areas). With respect to citywide communications, the City has increased communications efforts around all construction-related projects to provide timely, accurate and reliable information to help the public plan how to move around the city. The public is also kept informed and engaged on construction milestones. Examples of citywide communications efforts include: • Regular Public Service Announcements related to the O-Train Confederation Line projects; • Weekly updates to the O-Train Confederation Line project website; • Daily Traffic Updates are shared with local traffic reporters; • Real-time commuter delays are shared with the public via Twitter at @Ottawacity,@Ottawa_Traffic and @OCTranspo; • Quarterly traffic and construction briefings providing four-month outlooks; • The Ottawa Nav mobile app is available for motorists, cyclists and pedestrians to plan routes in real-time; • Construction and variable message signs are installed near construction sites alerting commuters to current or planned works; • Information about construction and traffic impacts are posted on Ottawa.ca and
  • 8. 8 weekly updates on the Confederation Line are included on Ottawa.ca/confederationline; • Notifications are issued prior to the start of any construction project; • Unplanned traffic impacts are shared with the public via Twitter and on the landing page of Ottawa.ca; and, • Milestones and interesting facts about the project are highlighted via the City's social media channels. Look Ahead The following activities are planned for Q2 2017: • Trackwork begins in west running tunnel moving eastward; • Lyon Station west entrance architectural finishes begin; • Tunnel vent shafts at Lyon Station substantially completed; • Parliament Station architectural work begins; • West Portal construction substantial completion; • Brake and propulsion tests on the vehicles being completed; • Thales train control equipment mimic screen live at the Maintenance and Storage Facility (MSF); and, • System Integration Testing begins. Should you have any questions, please do not hesitate to contact me at extension 16623. Original signed by Steve Cripps cc: Senior Leadership Team Transportation Services Departmental Leadership Team Director, Public Information and Media Relations