SlideShare a Scribd company logo
1 | P a g e
Page1
Power Distribution System loss reduction & Investment analysis: Some Cases
Case 1 : A 11 KV feeder of X Private Ltd. company has unbalance loads on R, Y, B phases as 120 A, 200 A, 180
A respectively. The line conductor resistance is 4 ohm. Calculate
a) Losses in unbalanced load condition of feeder.
b) Losses in balanced condition of feeder, if load is balanced.
c) Savings, if load is balanced.
Sol: a) Losses in unbalanced load condition= (120)2 x 4+ (200)2 x 4 + (180)2x4
= 4x (32400+40000+14400) =347.2 KW
b) On balancing each phase carries load current= (120+200+180) / 3=166.67 A
Losses in bal. condition= (166.67) 2 x 4 + (166.67)2 x 4 + (166.67)2 x 4
333.3 KW
Savings = (a)- (b) Watts= 347.2 KW - 333.3KW =13.9 KW
Case 2 : As a result of Unequal loads on the individual phases, negative and zero sequence components of
current causes overheating of Transformers, cables, Conductors, Motors. Losses in system also increase.
As per IS: 325-1996 (clause 4.2) NPS of 1.5 % voltage is the limit. Calculate NPS, if line voltages measured are 395
V, 415 V, and 435 V.
(Hint: NPS= (71/V av. ) x (Vhigh-1/4xVmiddle-3/4 V low)
Sol: % NPS= [71 / (395+415+435)/ 3 ] X [ (435)-1/4 x ( 415)- 3/4 x (395)]
=0.172 X 35
= 5.985 %
Case 3 : X distribution ltd. is supplying three phase power to an industrial consumer. Sanctioned load is
4577.00 KVA; Contract demand is 4577 KVA with the condition imposed by utility that consumer will maintain
the power factor of his Installation as 0.95 lag. The average power factor of consumer billed during month of
September 2017 was 0.82 due to improper maintenance of installation by consumer as a result, KVA demand
from utility grid increased to 4800 KVA.
Demand charges are INR 200 per KVA, Calculate:
a) Total KVA Charges
b) Capacity of Capacitor banks to be installed
c) Total Cost of Supply & Installation of capacitor banks, if cost Supply & Installation is INR 1000 per KVAR.
d) Simple payback period.
Sol: a) Total KVA charge=4800 x 200=Rs. 960000
b) Capacity of capacitor banks= KVA2 x Sin (phi2)-KVA1 x Sin (phi1)
=4800 x 0.572-4577 x 0.311=2745.6 KVAR - 1423.447 KVAR= 1322.153 KVAR
2 | P a g e
Page2
(c)Total Cost of supply and installation of CB=1322.153 X 1000= Rs.1322153
(d)SPBP= (Total Cost of supply and installation of CB) / saving per month
= (1322153)/ (4800 x 200-4577 x 200) = 1322153 /44600=29.64 months
= 2.47 years
Case 4: What is the NPV of a Project, (life 3 years) which requires an investment of Rs.60, 000 & it investment
yields savings of Rs. 20,000 in first year, Rs. 30,000 in second year and Rs. 40,000 in the third year. Discount rate
is 10%.
Sol:
NPV= -CF0 / (1+d) 0+ NF1/ (1+d)1+NF2/ (1+d)2+NF3/ (1+d)3
=-60,000/ (1.1)0 +20,000/ (1.1)1+30,000/ (1.1)2+40,000/ (1.1)3
=-60,000+ 18181.818 + 24793.388 + 30052.592
= (+) Rs. 13027.798, Acceptable

More Related Content

What's hot

Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system AnalysisAbha Tripathi
 
Cascaded Open-End Winding Transformer based DVR
Cascaded Open-End Winding Transformer based DVRCascaded Open-End Winding Transformer based DVR
Cascaded Open-End Winding Transformer based DVRAsoka Technologies
 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01vikram anand
 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generationSerajul Haque
 
17 mse013 performance of power plant
17 mse013 performance of power plant17 mse013 performance of power plant
17 mse013 performance of power plantpaneliya sagar
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit iiAbha Tripathi
 
Newton Raphson
Newton RaphsonNewton Raphson
Newton RaphsonAisu
 
Per unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comPer unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comboromama
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsAbha Tripathi
 

What's hot (20)

Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Cascaded Open-End Winding Transformer based DVR
Cascaded Open-End Winding Transformer based DVRCascaded Open-End Winding Transformer based DVR
Cascaded Open-End Winding Transformer based DVR
 
Economic Dispatch
Economic DispatchEconomic Dispatch
Economic Dispatch
 
Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01Economicloaddispatch 111213025406-phpapp01
Economicloaddispatch 111213025406-phpapp01
 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generation
 
ECNG 6503 #4
ECNG 6503 #4ECNG 6503 #4
ECNG 6503 #4
 
Unit v
Unit vUnit v
Unit v
 
17 mse013 performance of power plant
17 mse013 performance of power plant17 mse013 performance of power plant
17 mse013 performance of power plant
 
Per unit
Per unitPer unit
Per unit
 
Solutions -unit4
Solutions  -unit4Solutions  -unit4
Solutions -unit4
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Newton Raphson
Newton RaphsonNewton Raphson
Newton Raphson
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Per unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comPer unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.com
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 

Similar to Ds loss

How Power Factor corection works.pdf
How Power Factor corection works.pdfHow Power Factor corection works.pdf
How Power Factor corection works.pdfChristinaBoyd12
 
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...IRJET Journal
 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionAbdur rehman
 
Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings RCREEE
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.pptVidya Sagar
 
Chapter two Part two.pptx
Chapter two Part two.pptxChapter two Part two.pptx
Chapter two Part two.pptxAbdalleAidrous
 
Energy & safety audit of rice mill for husk based power plant for finance, ...
Energy & safety audit of rice mill for husk based power plant   for finance, ...Energy & safety audit of rice mill for husk based power plant   for finance, ...
Energy & safety audit of rice mill for husk based power plant for finance, ...Radha Krishna Sahoo
 
Power Factor : Basics and Benefits of Improvement
Power Factor : Basics and  Benefits of ImprovementPower Factor : Basics and  Benefits of Improvement
Power Factor : Basics and Benefits of ImprovementBijadhar Pandey
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET Journal
 
Schuler Electronics Instructor CH07 amplifiers part 2.ppt
Schuler Electronics Instructor CH07 amplifiers part 2.pptSchuler Electronics Instructor CH07 amplifiers part 2.ppt
Schuler Electronics Instructor CH07 amplifiers part 2.pptSreejaSujith2
 
A novel four wire inverter system using SVPWM technique for ups applications
A novel four wire inverter system using SVPWM technique for ups applicationsA novel four wire inverter system using SVPWM technique for ups applications
A novel four wire inverter system using SVPWM technique for ups applicationsIRJET Journal
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdfChadWood16
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdfAhmadHamouda3
 
Cigre test system description justifications and simulation results v3
Cigre test system   description justifications and simulation results v3Cigre test system   description justifications and simulation results v3
Cigre test system description justifications and simulation results v3sebden
 

Similar to Ds loss (20)

How Power Factor corection works.pdf
How Power Factor corection works.pdfHow Power Factor corection works.pdf
How Power Factor corection works.pdf
 
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings Day 3: Power Supply Quality in Buildings
Day 3: Power Supply Quality in Buildings
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
 
Chapter two Part two.pptx
Chapter two Part two.pptxChapter two Part two.pptx
Chapter two Part two.pptx
 
Energy & safety audit of rice mill for husk based power plant for finance, ...
Energy & safety audit of rice mill for husk based power plant   for finance, ...Energy & safety audit of rice mill for husk based power plant   for finance, ...
Energy & safety audit of rice mill for husk based power plant for finance, ...
 
Power Factor : Basics and Benefits of Improvement
Power Factor : Basics and  Benefits of ImprovementPower Factor : Basics and  Benefits of Improvement
Power Factor : Basics and Benefits of Improvement
 
2011 ced capacitors
2011 ced capacitors2011 ced capacitors
2011 ced capacitors
 
capacitors
capacitorscapacitors
capacitors
 
Unit 2
Unit 2Unit 2
Unit 2
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
 
Lecture 11&12
Lecture 11&12Lecture 11&12
Lecture 11&12
 
Schuler Electronics Instructor CH07 amplifiers part 2.ppt
Schuler Electronics Instructor CH07 amplifiers part 2.pptSchuler Electronics Instructor CH07 amplifiers part 2.ppt
Schuler Electronics Instructor CH07 amplifiers part 2.ppt
 
APFC AMTL 30.01.2015
APFC  AMTL  30.01.2015APFC  AMTL  30.01.2015
APFC AMTL 30.01.2015
 
A novel four wire inverter system using SVPWM technique for ups applications
A novel four wire inverter system using SVPWM technique for ups applicationsA novel four wire inverter system using SVPWM technique for ups applications
A novel four wire inverter system using SVPWM technique for ups applications
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
 
Cigre test system description justifications and simulation results v3
Cigre test system   description justifications and simulation results v3Cigre test system   description justifications and simulation results v3
Cigre test system description justifications and simulation results v3
 

More from Atar Singh

IEEEx SmartGrid01
IEEEx SmartGrid01IEEEx SmartGrid01
IEEEx SmartGrid01Atar Singh
 
IMFx ESRx Certificate _ edX
IMFx ESRx Certificate _ edXIMFx ESRx Certificate _ edX
IMFx ESRx Certificate _ edXAtar Singh
 
DelftX NGIx Certificate _ edX
DelftX NGIx Certificate _ edXDelftX NGIx Certificate _ edX
DelftX NGIx Certificate _ edXAtar Singh
 
DelftX ET3034x Certificate _ edX
DelftX ET3034x Certificate _ edXDelftX ET3034x Certificate _ edX
DelftX ET3034x Certificate _ edXAtar Singh
 
IIMBx ST250x Certificate _ edX
IIMBx ST250x Certificate _ edXIIMBx ST250x Certificate _ edX
IIMBx ST250x Certificate _ edXAtar Singh
 
Certificate.pdf responsible innov
Certificate.pdf responsible innovCertificate.pdf responsible innov
Certificate.pdf responsible innovAtar Singh
 

More from Atar Singh (8)

IEEEx SmartGrid01
IEEEx SmartGrid01IEEEx SmartGrid01
IEEEx SmartGrid01
 
IMFx ESRx Certificate _ edX
IMFx ESRx Certificate _ edXIMFx ESRx Certificate _ edX
IMFx ESRx Certificate _ edX
 
DelftX NGIx Certificate _ edX
DelftX NGIx Certificate _ edXDelftX NGIx Certificate _ edX
DelftX NGIx Certificate _ edX
 
DelftX ET3034x Certificate _ edX
DelftX ET3034x Certificate _ edXDelftX ET3034x Certificate _ edX
DelftX ET3034x Certificate _ edX
 
u lab
u labu lab
u lab
 
unlocking
unlockingunlocking
unlocking
 
IIMBx ST250x Certificate _ edX
IIMBx ST250x Certificate _ edXIIMBx ST250x Certificate _ edX
IIMBx ST250x Certificate _ edX
 
Certificate.pdf responsible innov
Certificate.pdf responsible innovCertificate.pdf responsible innov
Certificate.pdf responsible innov
 

Recently uploaded

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxViniHema
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdfPratik Pawar
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptssuser9bd3ba
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 

Recently uploaded (20)

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

Ds loss

  • 1. 1 | P a g e Page1 Power Distribution System loss reduction & Investment analysis: Some Cases Case 1 : A 11 KV feeder of X Private Ltd. company has unbalance loads on R, Y, B phases as 120 A, 200 A, 180 A respectively. The line conductor resistance is 4 ohm. Calculate a) Losses in unbalanced load condition of feeder. b) Losses in balanced condition of feeder, if load is balanced. c) Savings, if load is balanced. Sol: a) Losses in unbalanced load condition= (120)2 x 4+ (200)2 x 4 + (180)2x4 = 4x (32400+40000+14400) =347.2 KW b) On balancing each phase carries load current= (120+200+180) / 3=166.67 A Losses in bal. condition= (166.67) 2 x 4 + (166.67)2 x 4 + (166.67)2 x 4 333.3 KW Savings = (a)- (b) Watts= 347.2 KW - 333.3KW =13.9 KW Case 2 : As a result of Unequal loads on the individual phases, negative and zero sequence components of current causes overheating of Transformers, cables, Conductors, Motors. Losses in system also increase. As per IS: 325-1996 (clause 4.2) NPS of 1.5 % voltage is the limit. Calculate NPS, if line voltages measured are 395 V, 415 V, and 435 V. (Hint: NPS= (71/V av. ) x (Vhigh-1/4xVmiddle-3/4 V low) Sol: % NPS= [71 / (395+415+435)/ 3 ] X [ (435)-1/4 x ( 415)- 3/4 x (395)] =0.172 X 35 = 5.985 % Case 3 : X distribution ltd. is supplying three phase power to an industrial consumer. Sanctioned load is 4577.00 KVA; Contract demand is 4577 KVA with the condition imposed by utility that consumer will maintain the power factor of his Installation as 0.95 lag. The average power factor of consumer billed during month of September 2017 was 0.82 due to improper maintenance of installation by consumer as a result, KVA demand from utility grid increased to 4800 KVA. Demand charges are INR 200 per KVA, Calculate: a) Total KVA Charges b) Capacity of Capacitor banks to be installed c) Total Cost of Supply & Installation of capacitor banks, if cost Supply & Installation is INR 1000 per KVAR. d) Simple payback period. Sol: a) Total KVA charge=4800 x 200=Rs. 960000 b) Capacity of capacitor banks= KVA2 x Sin (phi2)-KVA1 x Sin (phi1) =4800 x 0.572-4577 x 0.311=2745.6 KVAR - 1423.447 KVAR= 1322.153 KVAR
  • 2. 2 | P a g e Page2 (c)Total Cost of supply and installation of CB=1322.153 X 1000= Rs.1322153 (d)SPBP= (Total Cost of supply and installation of CB) / saving per month = (1322153)/ (4800 x 200-4577 x 200) = 1322153 /44600=29.64 months = 2.47 years Case 4: What is the NPV of a Project, (life 3 years) which requires an investment of Rs.60, 000 & it investment yields savings of Rs. 20,000 in first year, Rs. 30,000 in second year and Rs. 40,000 in the third year. Discount rate is 10%. Sol: NPV= -CF0 / (1+d) 0+ NF1/ (1+d)1+NF2/ (1+d)2+NF3/ (1+d)3 =-60,000/ (1.1)0 +20,000/ (1.1)1+30,000/ (1.1)2+40,000/ (1.1)3 =-60,000+ 18181.818 + 24793.388 + 30052.592 = (+) Rs. 13027.798, Acceptable