SlideShare a Scribd company logo
1 of 33
Download to read offline
Slide 1
6th Comprehensive Protection Training Program
at Pearl Continental L AHORE in 2012
A TYPICAL POWER SYSTEM
NETWORK
Slide 2
SIEMENS
LECTURE ON
OVER CURRENT & EARTH FAULT RELAY
SETTING CALCULATIONS
AT
PEARL CONTINENTAL HOTEL
LAHORE
ON 04-09-2012
BY
SIEMENS PAKISTAN ENGINEERING COMPANY
LTD
Slide 3
RELAY SETTING CALCULATIONS
A guide for the calculations of the Relay
Settings for:
Over current and Earth fault Relays
a) Definite Time Relays
b) Inverse Time Relays
For Power Transformers & 11kv feeders
Slide 4
RELAY SETTING CALCULATIONS
1. Enlist the technical data required in network study and
calculations of relay settings.
2. Ask from clientconsultant to provide essential technical data
relating to the existing network and equipment needed in the subject
matter.
3. Study carefully the protection schemes designed for the
project.
4. Enlist the protection relays with their functions to be used.
5. Chalk out which type of documents are agreed to submit to
consultant/client.
6. Arrange the content/index sheet of the relays, need to settings'
calculations.
7. Submission of proposed relay settings to the consultantclient for
approval.
8. Arrange a meeting to clarify technical and disputed points
regarding to the submitted document for the approval.
9. Finalize the relays setting calculations with duly signed from
clientconsultantcontractor.
10.Upload the parameters in the relays according to the calculations
at site for pre-commissioning and testing.
Slide 5
RELAY SETTING CALCULATIONS
Please note that
- Minimum generation is considered for
relay setting calculations. (pick up,trip)
&
- Circuit Breaking capacity is calculated
for maximum generation possible.
Slide 6
PAKISTAN
G
G
1 2
3
4
POWER HOUSE STATION A
132 kV
STATION B
132 kV
Boundary of Protection Zones are decided by Location of CT’s
X Circuit Breaker
1 Generator Protection Zone
2 Generator Transformer Unit Protection Zone
3 Bus Bar Protection Zone
4 Transmission Line Protection Zone
PROTECTION IN SMALL ZONES
USING OVERLAPPING PRINCIPLE
Slide 7
Slide 8
Definite Time Over current Characteristic
Slide 9
Inverse time Over current Characteristic
Slide 10
Slide 11
Normal Inverse time characteristic of relay 7SJ60
Slide 12
SETTING DEFINITE TIME OVERCURRENT
RELAYS
Over current Relays has a wide range of applications. It can be
applied where there is an abrupt change of current due to faulty
condition.
These relays are used for protection of Motors, Transformers,
Generators and Transmission Lines etc. In distribution networks
these are the main protection whereas in HV and EHV systems,
these are used as back up protection. Although there is no hard
and fast rule for use of definite time or inverse time relays and
one can decide by looking into the site requirements.
NTDC and the utilities in Pakistan
however have standard practice to use
Inverse time relays for back up of Motors,
Transformers and Generators. For HV and
EHV lines, definite time over current relays
are used for back up purpose.
Slide 13
SETTING DEFINITE TIME OVERCURRENT
RELAYS
Definite time over current relays have
adjustable over current elements. When an
element picks up, it energizes a built in time
element which initiates a tripping signal after
elapse of set time. In definite time over
current Relays, we have to set,
The over current element for its pick up
value, the high set element for its pick up
value along with the time delays required.
The instantaneous element pick up
value for the current is to be selected
whereas time setting is instantaneous.
Slide 14
7SJ602 SETTING POSSIBILITIES
OVERCURRENT RELAY 7SJ602
PHASE FAULTS EARTH FAULTS
STAGE I> DEFINITE TIME DEFINITE TIME
OR OR
IDMTL IDMTL
STAGE I>> DEFINITE TIME DEFINITE TIME
OR OR
INSTANTANEOUS INSTANTANEOUS
STAGE I>>> INSTANTANEOUS - - - - - - - - - - - -
Slide 15
OVERCURRENT RELAY SETTINGS
Slide 16
OVERCURRENT RELAY SETTINGS
The relay at the far end B is set with shortest
operating time. The Relay on upstream which
is at end A has to be time graded against
relay at end B with a minimum time difference
of 200-300mSec for numerical relays and of
400-500mSec for electro-mechanical relays.
The relay at end B is required to be set with
the minimum operating time IDMTL mode and
to be set for TMS of 0.1or 0.05 Time Dial
whichever setting is available. The relay at
end A has to be set accordingly.
Slide 17
SETTING OF OVER CURRENT RELAYS
Slide 18
OVERCURRENT RELAY SETTINGS
In the previous diagram, the relay at far end (D) is
set with shortest operating time. Relays on the
upstream are to be time graded against the next
down stream relay in steps of 0.2 Secs.
Definite time characteristic is selected where
Source Impedance is quite larger compared to the
line impedance. This means small current
variation between near and far end faults.
The inverse mode is selected where fault current
is much less at the far end of the line than at the
local end.
(Selection also depends on the utility preference looking into their
operational requirements.)
Slide 19
7SJ602 SETTING CALCULATIONS FOR
AUTOTRANSFORMER 3x200 MVA 500KV
3 × 200 MVA Auto-transformer HV Winding Circuit
Time Over Current Relay Type: 7SJ6021-5EB20-1FA0
CT Ratio : N = 3250/1
Rated power: S = 600MVA
Rated voltage: (at minimum tap) U = 472.5KV
Required Settings:
Plug Setting
Characteristic to be selected
Time Multiplier Setting (TMS)
High Set Element Settings, I >>
Instantaneous Element Setting, I >>>
Plug Setting:
Autotransformer HV winding rated current IN = S ÷ ( 3 × U ) IN = 733A
Allowed overloading = 5%
Relay's resetting ratio = Drop off ÷ Pick up R = 0.95
Relay's setting current = (IN + IN ) ÷ R Is = 810A
Corresponding secondary current = Is ÷ N = 0.25A
Slide 20
7SJ602 SETTING CALCULATIONS FOR
AUTOTRANSFORMER 3x200 MVA 500KV
Characteristic to be selected:
Normal Inverse Characteristic is selected according to the NTDC System practice.
Usually for inductive loads, inverse time characteristics are selected.
For line feeders, definite time characteristics are suggested.
Time Multiplier Setting:
Fault current at HV Connection of autotransformer IF =11548A
Multiples of Fault Current (PSM) = IF ÷ Is =14.25
As per IEC Normal Inverse characteristic =0.14÷{(14.25)0.02-1}
Operating time at TMS = 1 A =2.565 sec.
For selectivity as backup, tripping time chosen B =1.200 sec.
Required time multiplier setting, = B ÷ A TMS = 0.47
High Set Element setting = to be blocked
Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In
Settings recommended:
Over current plug setting =0.25 I/In
TMS setting =0.47
Characteristic = Normal Inverse
Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In
High Set Element Settings, I >> IE >> = Blocked
Slide 21
7SJ602 SETTING CALCULATIONS FOR
AUTOTRANSFORMER 3x200 MVA 500KV
3 × 200 MVA Auto-transformer HV Winding Circuit
Earth Fault Time Over Current Relay Type: 7SJ6021-5EB20-1FA0
CT Ratio : N = 3250/1
Rated power: S = 600MVA
Rated voltage: (at minimum tap) U = 472.5KV
Required Settings:
Plug Setting
Characteristic to be selected
Time Multiplier Setting (TMS)
High Set Element Settings, IE >>
Instantaneous Element Setting, IE >>>
Plug Setting:
Autotransformer HV winding rated current IN = S ÷ 3 × U ) IN = 733A
Minimum fault current considered as percentage of rated current = 5%
(for purpose of pick up of relay)
Relay's resetting ratio = Drop off ÷ Pick up R = 0.95
Relay's setting current = ( )×(IN ÷ R) =.05x733 ÷.95=38.57 or Is = 39A
Corresponding secondary current = Is ÷ N = 0.01A
Slide 22
7SJ602 SETTING CALCULATIONS FOR
AUTOTRANSFORMER 3x200 MVA 500KV
Characteristic to be selected:
Normal Inverse Characteristic is selected according to the NTDC System practice.
Usually for inductive loads, inverse time characteristics are selected and
For line feeders, definite time characteristics are suggested.
Time Multiplier Setting:
Fault current at HV Connection of autotransformer IF =1469A
Multiples of Fault Current (PSM) = IF ÷ Is =38.07
As per IEC Normal Inverse characteristic =0.14÷{(38.07)0.02-1}
Operating time at TMS = 1 A =1.854 sec.
For selectivity as backup, tripping time chosen B =1.100 sec.
Required time multiplier setting, = B ÷ A TMS = 0.59
High Set Element Setting = to be blocked
Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In
Settings recommended:
Over current plug setting =0.01 I/In
TMS setting =0.59
Characteristic = Normal Inverse
Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In
High Set Element Settings, I >> IE >> = Blocked
Slide 23
OVER CURRENT RELAY SETTINGS FOR 11KV
FEEDER
11 kV Outgoing Panel
CT Ratio = 400/5 = 80 Relay 7SJ602 O/C Settings
Calculations
Load Current = 360 A
Relay Nominal Current = 5A
___________________________________________________________________________
Settings Required
1) Characteristic to be chosen
2) Plug Setting
3) Time Multiplier Setting TMS
4) High Set elements settings I >> IE >>
5) Instantaneous element setting I >>>
___________________________________________________________________________
PHASE FAULT: Ip > (Pick Up)
1) Characteristic = Normal Inverse (IEC)
2) Plug Setting
Considering Full Load Current. = 360 A
Permissible over loading = 10 %
Relays Resetting ratio = Drop off/Pick up = 0.95
Relay setting current = 360x1.1 = 417 A
.95
Secondary Current = 417 = 5.2 A
80
Selected Pick Up Setting = 1.04
3) Time Multiplier Setting
Assuming fault current = 1350 A (an hypothetical value)
Multiple of Fault Current (PSM) = 1350 = 3.23
417
Slide 24
OVER CURRENT RELAY SETTINGS FOR 11KV
FEEDER (continues)
Operating time as per
IEC NI Characteristics = 0.14 = 0.14 = 5.24
(3.23 0.02
– 1) 0.0267
Time required for Relay Operation is = 300 mSec ( Normally site requirements should be
considered. )
Therefore: TMS = _0.3_ = 0.057
5.24
PHASE FAULT: Ip >> (High Set)
1) Characteristic = Definite Time _
2) Plug Setting
Considering 4.0 times the Pick up Current.
Secondary Current = 1668 = 20.85 A
80(ct ratio)
Selected Pick Up Setting = 20.85/ 5 =4.17
3) Time Setting
= 0.1 s (to be chosen by the engineer as per requirement)
PHASE FAULT: Ip>>> (Instantaneous)
1) Characteristic = Instantaneous
2) Plug Setting
Considering 5.0 times the Pick up Current.
Secondary Current = 417x5 = 26.05 A
80
Selected Pick Up Setting = 26.05/5 = 5.2
(or we can calculate from I pick up which will be 1.04 x 5 = 5.20)
(Please note that the fault current is to be calculated based on fault calculation study on HT side
and considering the secondary impedance of the Transformer installed )
Slide 25
EARTH FAULT SETTINGS FOR 11KV FEEDER
Relay 7SJ602 E/F Settings
Calculations
EARTH FAULT: Ie> (Pick Up)
CHARACTERISTIC SELECTED = NORMAL INVERSE (IEC)
Plug Setting
Considering NTDC practice to set the E/F element pick up at 20% of ct
sec. rated current. = 0.2 x 5 = 1 (effective value in amps = 80 Amps)
(Utilities normally select earth fault element pick up from 10% to 20%. At
lower pick up values, sensitivity increases and stability reduces. At
higher pick up, the sensitivity is reduced but stability is increased.
Normally time of operation is set equal to phase operation time.)
Time Multiplier Setting
Assuming single phase to ground fault current = 650 Amps
Multiple of Fault Current = 650 = 7.71
84.2
Operating time as per
IEC NI Characteristics = 0.14 = 0.14 = 3.365
(7.71 0.02
– 1) 0.0416
Slide 26
EARTH FAULT SETTINGS FOR 11KV FEEDER
Time required for Relay
Operation is = 0.3 Sec ( to be selected considering site
conditions)
Therefore: TMS = 0.3 = 0.089
3.365
EARTH FAULT: Ie>> (Instantaneous element setting)
1) Characteristic = Instantaneous
2) Plug Setting
Considering fault Current = 650A
= 650 = 8.125
80
Pick Up Setting for instantaneous element = 8.125/5=1.625
(It is to be noted that settings are selected keeping in view
the site conditions and past experience. No hard and fast
rules can be chalked out. These examples are to show the
procedure only. )
Slide 27
Thank you for your Attention
Slide 28
CONSTRUCTION OF ELECTRO-
MECHANICAL RELAYS
Slide 29
Protection Co ordination of inverse time relays &
Disc emulation
Disc emulation evokes a dropout process,
which begins after de energization. This
Process corresponds to the back turn of
a Ferraris Disc. In case several faults o-
ccur successively, it is ensured that due
to the inertia of the Ferraris Disc, the h-
istory is taken into consideration.
Consider the main over current relay of electro mechanical type and
the feeder relay of numerical type. There are chances that the
Main relay may operate unnecessarily on repeated feeder fault.
To avoid this Disc emulation feature is introduced.
The Disc emulation feature
Offers its advantages when the grading co ordination chart of
the time over current protection is combined with other devices
(elect. Mech or induction base) connected to the system.
Slide 30
SLAVE POINTER AND MEAN
VALUES
Slave pointer and Mean values is
basically a measuring technique to
measure the Maximum , Minimum and
average values of waveform. The
waveform can be of current or voltage.
Slide 31
THERMAL OVER LOAD PROTECTION
The thermal Over load protection prevents the protected object (
cables, motors and transformers etc) from damage caused by
thermal over loading. This protection operates independent on the
time over current and unbalanced load protection. It can work with
memory or without memory.
OVER LOAD PROTECTION WITHOUT MEMORY
If the overload protection without memory is selected, the tripping
time is calculated according to a formula. When the current in any
phase exceeds threshold value, timer picks up. Trip command is
given after the time has elapsed. This method is easy in handling.
t= 35x tL
(I/ IL )2 - 1
where
t is tripping time
I is over load current
IL parameterized threshold value
tL parameterized time multiplier
(tripping time with 6 times the
threshold value IL)
Slide 32
THERMAL OVER LOAD PROTECTION
OVER LOAD PROTECTION WITH MEMORY
The unit computes the temperature rise according to a
thermal single body model (thermal replica). This method
requires some knowledge of the protected object, its
ambient context and its cooling temperature etc.
This method is used when the object is to be operated at
the limit of its performance.
Slide 33
CONCEPT OF I/IN
IN is the rated current of the relay and also the secondary current
of the Current Transformer. They should match with each other so
that correct setting and pick up values could be selected.
Example: In the 7SJ602 relay, the phase current pick up I range
has been defined as 0.1 IN ------4.0 IN
If IN is 1 amp then it is easy to understand that the pick up range
will be from 0.1 amp to 4.0 amp
However if IN is 5 amp then the pick up range will be from 0.5 to 20
amps
To make it simpler we can write the above pick up range as
I/ IN from 0.1 to 4.0(10% to 400%)
This statement is independent of amps. We have to always look at
I/IN and set the relay from 0.1 to 4.0
Assume ct 100/1,relay rated current 1, the relay pick up set at 1
means relay will pick up at 100 Amps in primary
And if we assume ct of 100/5, relay rated current 5, the relay pick
up set at 1 means that relay will pick up at 100 Amps
(ct 100/5 relay 1 amp- relay pick up setting possible 2 to 80 Amp)
(100/5 means 20 relay can be set 20 x 0.1-4.0 i.e. 2-80 Amps)

More Related Content

Similar to 187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf

discharging-conditions-parameters-explanation-of-c.pdf
discharging-conditions-parameters-explanation-of-c.pdfdischarging-conditions-parameters-explanation-of-c.pdf
discharging-conditions-parameters-explanation-of-c.pdfRobin Yu
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewAUTHELECTRONIC
 
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
IRJET-  	  Speed Control of BLDC Motor using PID Tuned Fuzzy ControllerIRJET-  	  Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy ControllerIRJET Journal
 
Advanced motion controls s100a40
Advanced motion controls s100a40Advanced motion controls s100a40
Advanced motion controls s100a40Electromate
 
Advanced motion controls sx30a8
Advanced motion controls sx30a8Advanced motion controls sx30a8
Advanced motion controls sx30a8Electromate
 
Advanced motion controls s100a8
Advanced motion controls s100a8Advanced motion controls s100a8
Advanced motion controls s100a8Electromate
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionChandrabhan Sharma
 
Advanced motion controls s60a40ac
Advanced motion controls s60a40acAdvanced motion controls s60a40ac
Advanced motion controls s60a40acElectromate
 
Advanced motion controls s100a20
Advanced motion controls s100a20Advanced motion controls s100a20
Advanced motion controls s100a20Electromate
 
Wireless Sensor Network - An Outlook
Wireless Sensor Network - An OutlookWireless Sensor Network - An Outlook
Wireless Sensor Network - An OutlookIRJET Journal
 
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC Technology
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC TechnologyDesign and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC Technology
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC TechnologyIRJET Journal
 
Advanced motion controls s30a40
Advanced motion controls s30a40Advanced motion controls s30a40
Advanced motion controls s30a40Electromate
 
IRJET- Simulation of a Doubly Fed Induction Generator based Wind Energy C...
IRJET-  	  Simulation of a Doubly Fed Induction Generator based Wind Energy C...IRJET-  	  Simulation of a Doubly Fed Induction Generator based Wind Energy C...
IRJET- Simulation of a Doubly Fed Induction Generator based Wind Energy C...IRJET Journal
 
IRJET- Mollification Parameter Control by Dynamic Voltage Restorer (DVR)
IRJET-  	  Mollification Parameter Control by Dynamic Voltage Restorer (DVR)IRJET-  	  Mollification Parameter Control by Dynamic Voltage Restorer (DVR)
IRJET- Mollification Parameter Control by Dynamic Voltage Restorer (DVR)IRJET Journal
 
Transformerprotectionrelaycalculations.doc
Transformerprotectionrelaycalculations.docTransformerprotectionrelaycalculations.doc
Transformerprotectionrelaycalculations.docMdAbdullahAlMamun258178
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 
Design and Control of HESS based PEV
Design and Control of  HESS based PEVDesign and Control of  HESS based PEV
Design and Control of HESS based PEVMalyala Varun
 

Similar to 187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf (20)

discharging-conditions-parameters-explanation-of-c.pdf
discharging-conditions-parameters-explanation-of-c.pdfdischarging-conditions-parameters-explanation-of-c.pdf
discharging-conditions-parameters-explanation-of-c.pdf
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
 
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
IRJET-  	  Speed Control of BLDC Motor using PID Tuned Fuzzy ControllerIRJET-  	  Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
 
Advanced motion controls s100a40
Advanced motion controls s100a40Advanced motion controls s100a40
Advanced motion controls s100a40
 
Advanced motion controls sx30a8
Advanced motion controls sx30a8Advanced motion controls sx30a8
Advanced motion controls sx30a8
 
Advanced motion controls s100a8
Advanced motion controls s100a8Advanced motion controls s100a8
Advanced motion controls s100a8
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent Protection
 
Advanced motion controls s60a40ac
Advanced motion controls s60a40acAdvanced motion controls s60a40ac
Advanced motion controls s60a40ac
 
Advanced motion controls s100a20
Advanced motion controls s100a20Advanced motion controls s100a20
Advanced motion controls s100a20
 
Wireless Sensor Network - An Outlook
Wireless Sensor Network - An OutlookWireless Sensor Network - An Outlook
Wireless Sensor Network - An Outlook
 
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC Technology
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC TechnologyDesign and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC Technology
Design and Simulation Of 1.2V to 0.9V, 40ma LDO Using 90nm TSMC Technology
 
Advanced motion controls s30a40
Advanced motion controls s30a40Advanced motion controls s30a40
Advanced motion controls s30a40
 
IRJET- Simulation of a Doubly Fed Induction Generator based Wind Energy C...
IRJET-  	  Simulation of a Doubly Fed Induction Generator based Wind Energy C...IRJET-  	  Simulation of a Doubly Fed Induction Generator based Wind Energy C...
IRJET- Simulation of a Doubly Fed Induction Generator based Wind Energy C...
 
Ac closed loop
Ac closed loopAc closed loop
Ac closed loop
 
Ac motor closedloo[p
Ac motor closedloo[pAc motor closedloo[p
Ac motor closedloo[p
 
IRJET- Mollification Parameter Control by Dynamic Voltage Restorer (DVR)
IRJET-  	  Mollification Parameter Control by Dynamic Voltage Restorer (DVR)IRJET-  	  Mollification Parameter Control by Dynamic Voltage Restorer (DVR)
IRJET- Mollification Parameter Control by Dynamic Voltage Restorer (DVR)
 
Transformerprotectionrelaycalculations.doc
Transformerprotectionrelaycalculations.docTransformerprotectionrelaycalculations.doc
Transformerprotectionrelaycalculations.doc
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
Design and Control of HESS based PEV
Design and Control of  HESS based PEVDesign and Control of  HESS based PEV
Design and Control of HESS based PEV
 

More from ChadWood16

17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.pptChadWood16
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.pptChadWood16
 
Electrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfElectrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfChadWood16
 
OverCurrent(1).pdf
OverCurrent(1).pdfOverCurrent(1).pdf
OverCurrent(1).pdfChadWood16
 
Lecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfLecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfChadWood16
 
Line Protection.pdf
Line Protection.pdfLine Protection.pdf
Line Protection.pdfChadWood16
 
CH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfCH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfChadWood16
 
CH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfCH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfChadWood16
 

More from ChadWood16 (9)

17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.ppt
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
 
Electrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfElectrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdf
 
OverCurrent(1).pdf
OverCurrent(1).pdfOverCurrent(1).pdf
OverCurrent(1).pdf
 
Lecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfLecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdf
 
Line Protection.pdf
Line Protection.pdfLine Protection.pdf
Line Protection.pdf
 
CH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfCH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdf
 
CH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfCH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdf
 
CH2_.pdf
CH2_.pdfCH2_.pdf
CH2_.pdf
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf

  • 1. Slide 1 6th Comprehensive Protection Training Program at Pearl Continental L AHORE in 2012 A TYPICAL POWER SYSTEM NETWORK
  • 2. Slide 2 SIEMENS LECTURE ON OVER CURRENT & EARTH FAULT RELAY SETTING CALCULATIONS AT PEARL CONTINENTAL HOTEL LAHORE ON 04-09-2012 BY SIEMENS PAKISTAN ENGINEERING COMPANY LTD
  • 3. Slide 3 RELAY SETTING CALCULATIONS A guide for the calculations of the Relay Settings for: Over current and Earth fault Relays a) Definite Time Relays b) Inverse Time Relays For Power Transformers & 11kv feeders
  • 4. Slide 4 RELAY SETTING CALCULATIONS 1. Enlist the technical data required in network study and calculations of relay settings. 2. Ask from clientconsultant to provide essential technical data relating to the existing network and equipment needed in the subject matter. 3. Study carefully the protection schemes designed for the project. 4. Enlist the protection relays with their functions to be used. 5. Chalk out which type of documents are agreed to submit to consultant/client. 6. Arrange the content/index sheet of the relays, need to settings' calculations. 7. Submission of proposed relay settings to the consultantclient for approval. 8. Arrange a meeting to clarify technical and disputed points regarding to the submitted document for the approval. 9. Finalize the relays setting calculations with duly signed from clientconsultantcontractor. 10.Upload the parameters in the relays according to the calculations at site for pre-commissioning and testing.
  • 5. Slide 5 RELAY SETTING CALCULATIONS Please note that - Minimum generation is considered for relay setting calculations. (pick up,trip) & - Circuit Breaking capacity is calculated for maximum generation possible.
  • 6. Slide 6 PAKISTAN G G 1 2 3 4 POWER HOUSE STATION A 132 kV STATION B 132 kV Boundary of Protection Zones are decided by Location of CT’s X Circuit Breaker 1 Generator Protection Zone 2 Generator Transformer Unit Protection Zone 3 Bus Bar Protection Zone 4 Transmission Line Protection Zone PROTECTION IN SMALL ZONES USING OVERLAPPING PRINCIPLE
  • 8. Slide 8 Definite Time Over current Characteristic
  • 9. Slide 9 Inverse time Over current Characteristic
  • 11. Slide 11 Normal Inverse time characteristic of relay 7SJ60
  • 12. Slide 12 SETTING DEFINITE TIME OVERCURRENT RELAYS Over current Relays has a wide range of applications. It can be applied where there is an abrupt change of current due to faulty condition. These relays are used for protection of Motors, Transformers, Generators and Transmission Lines etc. In distribution networks these are the main protection whereas in HV and EHV systems, these are used as back up protection. Although there is no hard and fast rule for use of definite time or inverse time relays and one can decide by looking into the site requirements. NTDC and the utilities in Pakistan however have standard practice to use Inverse time relays for back up of Motors, Transformers and Generators. For HV and EHV lines, definite time over current relays are used for back up purpose.
  • 13. Slide 13 SETTING DEFINITE TIME OVERCURRENT RELAYS Definite time over current relays have adjustable over current elements. When an element picks up, it energizes a built in time element which initiates a tripping signal after elapse of set time. In definite time over current Relays, we have to set, The over current element for its pick up value, the high set element for its pick up value along with the time delays required. The instantaneous element pick up value for the current is to be selected whereas time setting is instantaneous.
  • 14. Slide 14 7SJ602 SETTING POSSIBILITIES OVERCURRENT RELAY 7SJ602 PHASE FAULTS EARTH FAULTS STAGE I> DEFINITE TIME DEFINITE TIME OR OR IDMTL IDMTL STAGE I>> DEFINITE TIME DEFINITE TIME OR OR INSTANTANEOUS INSTANTANEOUS STAGE I>>> INSTANTANEOUS - - - - - - - - - - - -
  • 16. Slide 16 OVERCURRENT RELAY SETTINGS The relay at the far end B is set with shortest operating time. The Relay on upstream which is at end A has to be time graded against relay at end B with a minimum time difference of 200-300mSec for numerical relays and of 400-500mSec for electro-mechanical relays. The relay at end B is required to be set with the minimum operating time IDMTL mode and to be set for TMS of 0.1or 0.05 Time Dial whichever setting is available. The relay at end A has to be set accordingly.
  • 17. Slide 17 SETTING OF OVER CURRENT RELAYS
  • 18. Slide 18 OVERCURRENT RELAY SETTINGS In the previous diagram, the relay at far end (D) is set with shortest operating time. Relays on the upstream are to be time graded against the next down stream relay in steps of 0.2 Secs. Definite time characteristic is selected where Source Impedance is quite larger compared to the line impedance. This means small current variation between near and far end faults. The inverse mode is selected where fault current is much less at the far end of the line than at the local end. (Selection also depends on the utility preference looking into their operational requirements.)
  • 19. Slide 19 7SJ602 SETTING CALCULATIONS FOR AUTOTRANSFORMER 3x200 MVA 500KV 3 × 200 MVA Auto-transformer HV Winding Circuit Time Over Current Relay Type: 7SJ6021-5EB20-1FA0 CT Ratio : N = 3250/1 Rated power: S = 600MVA Rated voltage: (at minimum tap) U = 472.5KV Required Settings: Plug Setting Characteristic to be selected Time Multiplier Setting (TMS) High Set Element Settings, I >> Instantaneous Element Setting, I >>> Plug Setting: Autotransformer HV winding rated current IN = S ÷ ( 3 × U ) IN = 733A Allowed overloading = 5% Relay's resetting ratio = Drop off ÷ Pick up R = 0.95 Relay's setting current = (IN + IN ) ÷ R Is = 810A Corresponding secondary current = Is ÷ N = 0.25A
  • 20. Slide 20 7SJ602 SETTING CALCULATIONS FOR AUTOTRANSFORMER 3x200 MVA 500KV Characteristic to be selected: Normal Inverse Characteristic is selected according to the NTDC System practice. Usually for inductive loads, inverse time characteristics are selected. For line feeders, definite time characteristics are suggested. Time Multiplier Setting: Fault current at HV Connection of autotransformer IF =11548A Multiples of Fault Current (PSM) = IF ÷ Is =14.25 As per IEC Normal Inverse characteristic =0.14÷{(14.25)0.02-1} Operating time at TMS = 1 A =2.565 sec. For selectivity as backup, tripping time chosen B =1.200 sec. Required time multiplier setting, = B ÷ A TMS = 0.47 High Set Element setting = to be blocked Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In Settings recommended: Over current plug setting =0.25 I/In TMS setting =0.47 Characteristic = Normal Inverse Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In High Set Element Settings, I >> IE >> = Blocked
  • 21. Slide 21 7SJ602 SETTING CALCULATIONS FOR AUTOTRANSFORMER 3x200 MVA 500KV 3 × 200 MVA Auto-transformer HV Winding Circuit Earth Fault Time Over Current Relay Type: 7SJ6021-5EB20-1FA0 CT Ratio : N = 3250/1 Rated power: S = 600MVA Rated voltage: (at minimum tap) U = 472.5KV Required Settings: Plug Setting Characteristic to be selected Time Multiplier Setting (TMS) High Set Element Settings, IE >> Instantaneous Element Setting, IE >>> Plug Setting: Autotransformer HV winding rated current IN = S ÷ 3 × U ) IN = 733A Minimum fault current considered as percentage of rated current = 5% (for purpose of pick up of relay) Relay's resetting ratio = Drop off ÷ Pick up R = 0.95 Relay's setting current = ( )×(IN ÷ R) =.05x733 ÷.95=38.57 or Is = 39A Corresponding secondary current = Is ÷ N = 0.01A
  • 22. Slide 22 7SJ602 SETTING CALCULATIONS FOR AUTOTRANSFORMER 3x200 MVA 500KV Characteristic to be selected: Normal Inverse Characteristic is selected according to the NTDC System practice. Usually for inductive loads, inverse time characteristics are selected and For line feeders, definite time characteristics are suggested. Time Multiplier Setting: Fault current at HV Connection of autotransformer IF =1469A Multiples of Fault Current (PSM) = IF ÷ Is =38.07 As per IEC Normal Inverse characteristic =0.14÷{(38.07)0.02-1} Operating time at TMS = 1 A =1.854 sec. For selectivity as backup, tripping time chosen B =1.100 sec. Required time multiplier setting, = B ÷ A TMS = 0.59 High Set Element Setting = to be blocked Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In Settings recommended: Over current plug setting =0.01 I/In TMS setting =0.59 Characteristic = Normal Inverse Instantaneous setting (Ipick up = 5 × IN ) =5.00 I/In High Set Element Settings, I >> IE >> = Blocked
  • 23. Slide 23 OVER CURRENT RELAY SETTINGS FOR 11KV FEEDER 11 kV Outgoing Panel CT Ratio = 400/5 = 80 Relay 7SJ602 O/C Settings Calculations Load Current = 360 A Relay Nominal Current = 5A ___________________________________________________________________________ Settings Required 1) Characteristic to be chosen 2) Plug Setting 3) Time Multiplier Setting TMS 4) High Set elements settings I >> IE >> 5) Instantaneous element setting I >>> ___________________________________________________________________________ PHASE FAULT: Ip > (Pick Up) 1) Characteristic = Normal Inverse (IEC) 2) Plug Setting Considering Full Load Current. = 360 A Permissible over loading = 10 % Relays Resetting ratio = Drop off/Pick up = 0.95 Relay setting current = 360x1.1 = 417 A .95 Secondary Current = 417 = 5.2 A 80 Selected Pick Up Setting = 1.04 3) Time Multiplier Setting Assuming fault current = 1350 A (an hypothetical value) Multiple of Fault Current (PSM) = 1350 = 3.23 417
  • 24. Slide 24 OVER CURRENT RELAY SETTINGS FOR 11KV FEEDER (continues) Operating time as per IEC NI Characteristics = 0.14 = 0.14 = 5.24 (3.23 0.02 – 1) 0.0267 Time required for Relay Operation is = 300 mSec ( Normally site requirements should be considered. ) Therefore: TMS = _0.3_ = 0.057 5.24 PHASE FAULT: Ip >> (High Set) 1) Characteristic = Definite Time _ 2) Plug Setting Considering 4.0 times the Pick up Current. Secondary Current = 1668 = 20.85 A 80(ct ratio) Selected Pick Up Setting = 20.85/ 5 =4.17 3) Time Setting = 0.1 s (to be chosen by the engineer as per requirement) PHASE FAULT: Ip>>> (Instantaneous) 1) Characteristic = Instantaneous 2) Plug Setting Considering 5.0 times the Pick up Current. Secondary Current = 417x5 = 26.05 A 80 Selected Pick Up Setting = 26.05/5 = 5.2 (or we can calculate from I pick up which will be 1.04 x 5 = 5.20) (Please note that the fault current is to be calculated based on fault calculation study on HT side and considering the secondary impedance of the Transformer installed )
  • 25. Slide 25 EARTH FAULT SETTINGS FOR 11KV FEEDER Relay 7SJ602 E/F Settings Calculations EARTH FAULT: Ie> (Pick Up) CHARACTERISTIC SELECTED = NORMAL INVERSE (IEC) Plug Setting Considering NTDC practice to set the E/F element pick up at 20% of ct sec. rated current. = 0.2 x 5 = 1 (effective value in amps = 80 Amps) (Utilities normally select earth fault element pick up from 10% to 20%. At lower pick up values, sensitivity increases and stability reduces. At higher pick up, the sensitivity is reduced but stability is increased. Normally time of operation is set equal to phase operation time.) Time Multiplier Setting Assuming single phase to ground fault current = 650 Amps Multiple of Fault Current = 650 = 7.71 84.2 Operating time as per IEC NI Characteristics = 0.14 = 0.14 = 3.365 (7.71 0.02 – 1) 0.0416
  • 26. Slide 26 EARTH FAULT SETTINGS FOR 11KV FEEDER Time required for Relay Operation is = 0.3 Sec ( to be selected considering site conditions) Therefore: TMS = 0.3 = 0.089 3.365 EARTH FAULT: Ie>> (Instantaneous element setting) 1) Characteristic = Instantaneous 2) Plug Setting Considering fault Current = 650A = 650 = 8.125 80 Pick Up Setting for instantaneous element = 8.125/5=1.625 (It is to be noted that settings are selected keeping in view the site conditions and past experience. No hard and fast rules can be chalked out. These examples are to show the procedure only. )
  • 27. Slide 27 Thank you for your Attention
  • 28. Slide 28 CONSTRUCTION OF ELECTRO- MECHANICAL RELAYS
  • 29. Slide 29 Protection Co ordination of inverse time relays & Disc emulation Disc emulation evokes a dropout process, which begins after de energization. This Process corresponds to the back turn of a Ferraris Disc. In case several faults o- ccur successively, it is ensured that due to the inertia of the Ferraris Disc, the h- istory is taken into consideration. Consider the main over current relay of electro mechanical type and the feeder relay of numerical type. There are chances that the Main relay may operate unnecessarily on repeated feeder fault. To avoid this Disc emulation feature is introduced. The Disc emulation feature Offers its advantages when the grading co ordination chart of the time over current protection is combined with other devices (elect. Mech or induction base) connected to the system.
  • 30. Slide 30 SLAVE POINTER AND MEAN VALUES Slave pointer and Mean values is basically a measuring technique to measure the Maximum , Minimum and average values of waveform. The waveform can be of current or voltage.
  • 31. Slide 31 THERMAL OVER LOAD PROTECTION The thermal Over load protection prevents the protected object ( cables, motors and transformers etc) from damage caused by thermal over loading. This protection operates independent on the time over current and unbalanced load protection. It can work with memory or without memory. OVER LOAD PROTECTION WITHOUT MEMORY If the overload protection without memory is selected, the tripping time is calculated according to a formula. When the current in any phase exceeds threshold value, timer picks up. Trip command is given after the time has elapsed. This method is easy in handling. t= 35x tL (I/ IL )2 - 1 where t is tripping time I is over load current IL parameterized threshold value tL parameterized time multiplier (tripping time with 6 times the threshold value IL)
  • 32. Slide 32 THERMAL OVER LOAD PROTECTION OVER LOAD PROTECTION WITH MEMORY The unit computes the temperature rise according to a thermal single body model (thermal replica). This method requires some knowledge of the protected object, its ambient context and its cooling temperature etc. This method is used when the object is to be operated at the limit of its performance.
  • 33. Slide 33 CONCEPT OF I/IN IN is the rated current of the relay and also the secondary current of the Current Transformer. They should match with each other so that correct setting and pick up values could be selected. Example: In the 7SJ602 relay, the phase current pick up I range has been defined as 0.1 IN ------4.0 IN If IN is 1 amp then it is easy to understand that the pick up range will be from 0.1 amp to 4.0 amp However if IN is 5 amp then the pick up range will be from 0.5 to 20 amps To make it simpler we can write the above pick up range as I/ IN from 0.1 to 4.0(10% to 400%) This statement is independent of amps. We have to always look at I/IN and set the relay from 0.1 to 4.0 Assume ct 100/1,relay rated current 1, the relay pick up set at 1 means relay will pick up at 100 Amps in primary And if we assume ct of 100/5, relay rated current 5, the relay pick up set at 1 means that relay will pick up at 100 Amps (ct 100/5 relay 1 amp- relay pick up setting possible 2 to 80 Amp) (100/5 means 20 relay can be set 20 x 0.1-4.0 i.e. 2-80 Amps)