Kapasitor bank functions primarily to improve power factor, especially for large AC current applications in industry. It also provides reactive power to maximize utilization of complex power (kVA), reduces voltage drop, prevents transformer overload, controls temperature rise in cables, improves efficiency by lowering total KVA usage, minimizes electrical network losses, and prevents penalties from electricity suppliers due to reactive power. Examples show how to calculate the required capacitor size in kVAR and Farads to improve the power factor of motors and alternators from given values using simple formulas and tables. Key formulas used in power factor improvement and these calculations are also outlined.
Jenis-jenis Papan Suis Utama ( Main Switch Board) Akilan36
Papan Suis Utama merupakan satu rangkuman perkakas elektrik yang digunakan untuk pensuisan, perlindungan dan pengukuran untuk keseluruhan beban agihan dipasang pada punca masuk bekalan utama. Saiz PSU adalah bergantung kepada sejumlah pemasangan alat pengukuran, alat perlindungan dan jenis beban di bawah kawalannya.
LOW VOLTAGE OVERHEAD SYSTEM INSTALLATION&MAINTENANCEAkilan36
Dokumen tersebut membahas tentang pemasangan dan pemeliharaan sistem talian atas voltan rendah. Terdiri dari tiga bagian utama yaitu pengenalan komponen sistem talian atas, pemasangan kabel bertebat di udara, dan peraturan yang terkait seperti Akta Bekalan Elektrik.
Jenis-jenis Papan Suis Utama ( Main Switch Board) Akilan36
Papan Suis Utama merupakan satu rangkuman perkakas elektrik yang digunakan untuk pensuisan, perlindungan dan pengukuran untuk keseluruhan beban agihan dipasang pada punca masuk bekalan utama. Saiz PSU adalah bergantung kepada sejumlah pemasangan alat pengukuran, alat perlindungan dan jenis beban di bawah kawalannya.
LOW VOLTAGE OVERHEAD SYSTEM INSTALLATION&MAINTENANCEAkilan36
Dokumen tersebut membahas tentang pemasangan dan pemeliharaan sistem talian atas voltan rendah. Terdiri dari tiga bagian utama yaitu pengenalan komponen sistem talian atas, pemasangan kabel bertebat di udara, dan peraturan yang terkait seperti Akta Bekalan Elektrik.
Dokumen ini menjelaskan prosedur pengujian rintangan penebatan untuk memastikan tiada kebocoran arus antara fasa, fasa ke neutral dan bumi menggunakan penguji penebatan 500V dan 1000V. Ujian dilakukan untuk litar lampu, soket, unit pengguna, pepasangan tiga fasa dan alat radas untuk memastikan bacaan melebihi 1MΩ untuk semua sambungan dan 0.5MΩ untuk peralatan. Bacaan rendah menunj
Komponen utama dalam litar kawalan motor termasuk sesentuh magnetik, geganti beban lampau, dan geganti masa. Sesentuh magnetik menyambung dan memutuskan litar dengan bantuan alat pandu, manakala geganti beban lampau memutuskan litar jika terdapat beban lampau. Geganti masa pula melewatkan masa kendalian sesentuh.
Dokumen tersebut memberikan panduan mengenai ujian keterusan pemasangan listrik untuk memastikan keselamatan. Ujian tersebut meliputi pemeriksaan visual, ujian keterusan kabel dan litar, serta ujian keterusan pengalir perlindungan menggunakan ohm meter dan loceng penguji sesuai prosedur yang ditetapkan.
Dokumen tersebut memberikan panduan mengenai pemeliharaan dan penyenggaraan peralatan elektrik secara berkala untuk memastikan operasi yang selamat dan lancar. Ia menjelaskan proses penyenggaraan untuk komponen seperti transformer, kabel bawah tanah, papan suis utama, alat perlindungan, dan sistem pembumian serta menekankan pentingnya menyimpan rekod dan melakukan pengujian berkala.
The document provides instructions for testing electrical circuits without power (dead testing) and insulation testing. It describes checking visual connections, continuity testing between phases, and insulation testing between live conductors and earth. Connection tightness, cable colors, sizes and labeling are checked visually. Continuity tests are done between lamp circuits, sockets, and earth connections. Insulation testing measures resistance between live conductors and earth/metalwork to check for faults. Readings below 1MΩ indicate failure.
LOW VOLTAGE GENERATOR INSTALLATION AND MAINTENANCE Akilan36
Janakuasa tunggu sedia adalah merupakan sistem bekalan elektrik yang tidak digunakan dalam keadaan bekalan elektrik adalah normal.
Digunakan apabila bekalan kuasa elektrik yang biasa diterima terputus atau mengalami gangguan.
Sistem penjanaan kecil atau sederhana kebanyakkan bahan bakar yang mudah diperolehi ialah diesel.
Janakuasa dihidupkan melalui satu panel kawalan AMF board (Automatic Main Failure) yang mana telah dirancang dari segi sistem litar kawalan.
Bagi mengendali dan mengawal janakuasa tunggu sedia, pihak pengurusan perlu melantik seorang yang memegang satu perakuan kekompetenan Penjaga Jentera kategori A4 dan A4-1
Dokumen ini membahas tentang pengalir dan penebat talian volt tinggi 33kV. Ia menjelaskan jenis pengalir seperti tembaga dan silmalek serta ukuran pengalir yang digunakan. Dokumen ini juga menjelaskan tentang penebat pin, penebat tutup dan pin, serta pemasangan komponen-komponen talian seperti set gantungan, set tegangan, dawai bumi dan lain-lain.
Dokumen tersebut memberikan prosedur penyelenggaraan Air Circuit Breaker (ACB) yang meliputi tes mekanikal dan elektrikal ACB, pembersihan kontak utama dan busur, pelumasan bagian bergerak, dan pengecekan komponen penting lainnya untuk memastikan ACB beroperasi dengan baik.
LOW VOLTAGE TRANSFORMER INSTALLATION AND MAINTENANCEAkilan36
Pengenalan alatubah ialah satu perkakasan elektrik yang boleh mengubah voltan dari voltan tinggi ke voltan rendah atau dari voltan rendah ke voltan tinggi.
Alatubah yang biasa digunakan untuk sistem pembahagian ialah alatubah yang mengubah voltan dari voltan tinggi ke voltan rendah bagi disalurkan kepada pengguna.
Voltan yang dikeluarkan oleh alatubah pembahagian ialah 415V sistem tiga fasa, Biasanya alatubah yang digunakan bagi system pembahagian mempunyai kumpulan vektor Dyll iaitu DELTA - STAR.
Di antara jenama-jenama alatubah pembahagian yang biasa digunapakai oleh Tenaga Nasional.
Papan Suis Utama merupakan perkakas elektrik penting yang digunakan untuk mensuis, melindungi dan mengukur bekalan elektrik ke seluruh bangunan. Ia hadir dalam pelbagai saiz dan jenis bergantung kepada beban elektrik yang disokongnya. Papan Suis Utama perlu dipasang mengikut standard keselamatan untuk melindungi pengguna dan harta benda.
Dokumen tersebut membahas berbagai jenis ujian yang dilakukan untuk memastikan keselamatan sistem pendawaian listrik, termasuk ujian keterusan, kekutuban, penebatan, gegelung Murray, Varley, dan pulse echo. Ujian-ujian tersebut digunakan untuk mendeteksi kecacatan seperti litar pintas, kerosakan bumi, dan kesalahan sambungan kabel.
Dokumen tersebut membahas mengenai jenis-jenis beban listrik dan kuasa serta pengaruh faktor kuasa rendah. Faktor kuasa rendah menyebabkan arus meningkat dan kerugian daya, sementara faktor kuasa tinggi mengurangi arus dan kerugian daya. Kapasitor bank dapat meningkatkan faktor kuasa dengan menyediakan daya reaktif.
Dokumen tersebut membahas tentang pemula mara-songsang (forward-reverse starter) untuk motor listrik 3 fasa. Ia menjelaskan litar kawalan dan utama pemula tersebut, komponen-komponennya seperti kontaktor, overload relay, tombol hidup-mati, dan fungsi masing-masing komponen. Dokumen ini juga mendemonstrasikan bagaimana motor dapat dihidupkan dan diubah arah putarannya menjadi maju atau mundur dengan menekan tombol maju at
This document provides an overview of capacitors and capacitor fundamentals, ratings, applications, and protection. It discusses basic power calculations related to reactive power and power factor. It covers capacitor construction and ratings based on IEEE standards. Application considerations are presented for different installation configurations such as pole-top, pad-mounted, and substation installations. Protection methods like fuseless, internally fused, and externally fused capacitors are described. Group and individual fusing approaches are compared.
Dokumen ini menjelaskan prosedur pengujian rintangan penebatan untuk memastikan tiada kebocoran arus antara fasa, fasa ke neutral dan bumi menggunakan penguji penebatan 500V dan 1000V. Ujian dilakukan untuk litar lampu, soket, unit pengguna, pepasangan tiga fasa dan alat radas untuk memastikan bacaan melebihi 1MΩ untuk semua sambungan dan 0.5MΩ untuk peralatan. Bacaan rendah menunj
Komponen utama dalam litar kawalan motor termasuk sesentuh magnetik, geganti beban lampau, dan geganti masa. Sesentuh magnetik menyambung dan memutuskan litar dengan bantuan alat pandu, manakala geganti beban lampau memutuskan litar jika terdapat beban lampau. Geganti masa pula melewatkan masa kendalian sesentuh.
Dokumen tersebut memberikan panduan mengenai ujian keterusan pemasangan listrik untuk memastikan keselamatan. Ujian tersebut meliputi pemeriksaan visual, ujian keterusan kabel dan litar, serta ujian keterusan pengalir perlindungan menggunakan ohm meter dan loceng penguji sesuai prosedur yang ditetapkan.
Dokumen tersebut memberikan panduan mengenai pemeliharaan dan penyenggaraan peralatan elektrik secara berkala untuk memastikan operasi yang selamat dan lancar. Ia menjelaskan proses penyenggaraan untuk komponen seperti transformer, kabel bawah tanah, papan suis utama, alat perlindungan, dan sistem pembumian serta menekankan pentingnya menyimpan rekod dan melakukan pengujian berkala.
The document provides instructions for testing electrical circuits without power (dead testing) and insulation testing. It describes checking visual connections, continuity testing between phases, and insulation testing between live conductors and earth. Connection tightness, cable colors, sizes and labeling are checked visually. Continuity tests are done between lamp circuits, sockets, and earth connections. Insulation testing measures resistance between live conductors and earth/metalwork to check for faults. Readings below 1MΩ indicate failure.
LOW VOLTAGE GENERATOR INSTALLATION AND MAINTENANCE Akilan36
Janakuasa tunggu sedia adalah merupakan sistem bekalan elektrik yang tidak digunakan dalam keadaan bekalan elektrik adalah normal.
Digunakan apabila bekalan kuasa elektrik yang biasa diterima terputus atau mengalami gangguan.
Sistem penjanaan kecil atau sederhana kebanyakkan bahan bakar yang mudah diperolehi ialah diesel.
Janakuasa dihidupkan melalui satu panel kawalan AMF board (Automatic Main Failure) yang mana telah dirancang dari segi sistem litar kawalan.
Bagi mengendali dan mengawal janakuasa tunggu sedia, pihak pengurusan perlu melantik seorang yang memegang satu perakuan kekompetenan Penjaga Jentera kategori A4 dan A4-1
Dokumen ini membahas tentang pengalir dan penebat talian volt tinggi 33kV. Ia menjelaskan jenis pengalir seperti tembaga dan silmalek serta ukuran pengalir yang digunakan. Dokumen ini juga menjelaskan tentang penebat pin, penebat tutup dan pin, serta pemasangan komponen-komponen talian seperti set gantungan, set tegangan, dawai bumi dan lain-lain.
Dokumen tersebut memberikan prosedur penyelenggaraan Air Circuit Breaker (ACB) yang meliputi tes mekanikal dan elektrikal ACB, pembersihan kontak utama dan busur, pelumasan bagian bergerak, dan pengecekan komponen penting lainnya untuk memastikan ACB beroperasi dengan baik.
LOW VOLTAGE TRANSFORMER INSTALLATION AND MAINTENANCEAkilan36
Pengenalan alatubah ialah satu perkakasan elektrik yang boleh mengubah voltan dari voltan tinggi ke voltan rendah atau dari voltan rendah ke voltan tinggi.
Alatubah yang biasa digunakan untuk sistem pembahagian ialah alatubah yang mengubah voltan dari voltan tinggi ke voltan rendah bagi disalurkan kepada pengguna.
Voltan yang dikeluarkan oleh alatubah pembahagian ialah 415V sistem tiga fasa, Biasanya alatubah yang digunakan bagi system pembahagian mempunyai kumpulan vektor Dyll iaitu DELTA - STAR.
Di antara jenama-jenama alatubah pembahagian yang biasa digunapakai oleh Tenaga Nasional.
Papan Suis Utama merupakan perkakas elektrik penting yang digunakan untuk mensuis, melindungi dan mengukur bekalan elektrik ke seluruh bangunan. Ia hadir dalam pelbagai saiz dan jenis bergantung kepada beban elektrik yang disokongnya. Papan Suis Utama perlu dipasang mengikut standard keselamatan untuk melindungi pengguna dan harta benda.
Dokumen tersebut membahas berbagai jenis ujian yang dilakukan untuk memastikan keselamatan sistem pendawaian listrik, termasuk ujian keterusan, kekutuban, penebatan, gegelung Murray, Varley, dan pulse echo. Ujian-ujian tersebut digunakan untuk mendeteksi kecacatan seperti litar pintas, kerosakan bumi, dan kesalahan sambungan kabel.
Dokumen tersebut membahas mengenai jenis-jenis beban listrik dan kuasa serta pengaruh faktor kuasa rendah. Faktor kuasa rendah menyebabkan arus meningkat dan kerugian daya, sementara faktor kuasa tinggi mengurangi arus dan kerugian daya. Kapasitor bank dapat meningkatkan faktor kuasa dengan menyediakan daya reaktif.
Dokumen tersebut membahas tentang pemula mara-songsang (forward-reverse starter) untuk motor listrik 3 fasa. Ia menjelaskan litar kawalan dan utama pemula tersebut, komponen-komponennya seperti kontaktor, overload relay, tombol hidup-mati, dan fungsi masing-masing komponen. Dokumen ini juga mendemonstrasikan bagaimana motor dapat dihidupkan dan diubah arah putarannya menjadi maju atau mundur dengan menekan tombol maju at
This document provides an overview of capacitors and capacitor fundamentals, ratings, applications, and protection. It discusses basic power calculations related to reactive power and power factor. It covers capacitor construction and ratings based on IEEE standards. Application considerations are presented for different installation configurations such as pole-top, pad-mounted, and substation installations. Protection methods like fuseless, internally fused, and externally fused capacitors are described. Group and individual fusing approaches are compared.
This document provides an overview of capacitors and capacitor fundamentals, ratings, applications, and protection. It discusses basic power calculations involving reactive power (VARs) and power factor. It describes capacitor types, configurations, installation methods, and IEEE standards for ratings and testing. The key points are that capacitors provide reactive power (VARs) to improve power factor; applications include pole-top, pad-mounted, and substation installations; configurations are delta or wye; and ratings are defined by standards.
This document discusses power factor and power factor improvement. It defines key terms like active power, reactive power, and apparent power. It explains that loads like motors and transformers are inherently inductive and have low power factors. The advantages of improving power factor are discussed, such as reducing line losses and increasing transmission capacity. Common methods for improving power factor like installing capacitors are described. Examples are provided to illustrate power factor calculations and capacitor sizing. The natural power factors of various equipment types are also listed.
The document discusses transformer ratings, efficiency, and power factor. It explains that transformers are rated in kVA rather than kW because manufacturers do not know the load power factor in advance. Maximum efficiency occurs when iron losses equal copper losses. Transformer efficiency is calculated based on output power in watts rather than volt-amperes. Low power factor reduces efficiency by decreasing the output power relative to losses. Correcting power factor can help increase efficiency when a transformer is overloaded.
This document discusses power supply quality in buildings. It covers topics like generation and distribution of electricity, phases of electricity, power factor, power quality issues like harmonics, and electrical load management strategies. Case studies are provided on using capacitors and load scheduling to reduce peak demand and lower electricity costs. Transformers are described as devices that transform voltages efficiently with losses that vary based on loading.
This document discusses power factor improvement through the use of capacitors. It begins with definitions of key terms like active power, reactive power, and apparent power. It then discusses how inductive loads cause low power factors and the disadvantages of low power factors, such as increased current and line losses. The document presents methods for calculating the capacitance needed to improve the power factor of an inductive load. It also provides examples of typical power factors for various equipment and industries. Overall, the document provides an overview of power factors and how capacitors can be used to improve power factors.
The document discusses electrical power supply systems and power factor correction. It provides details on components of an electric power supply system including power stations, transmission lines, and distribution. It defines power factor and discusses types of electrical loads and their typical power factors. The document also describes various methods for power factor improvement including capacitors, synchronous motors, and phase advancers. It discusses the effects of low power factor and benefits of power factor correction such as reduced losses, current, transformer rating, and cost savings.
The document discusses electrical power supply systems and power factor correction. It provides details on components of an electric power supply system including power stations, transmission lines, and distribution. It defines power factor and different types of electrical power. The document also discusses causes of low power factor, various power factor improvement equipment like static capacitors, synchronous condensers and phase advancers. It provides advantages and disadvantages of these equipment. Finally, it discusses effects of improving power factor such as reduction in transformer rating, KVAR demand, line current, line losses, cable size and switchgear rating.
This document outlines classroom rules for a class, including that students must listen when the teacher talks, certain items are not allowed like phones or sleeping, and provides contact information for the teacher. It also lists topics to be covered in the class, including three-phase synchronous machines, their operating principles, construction features and applications. Finally, it discusses assessment requirements, including that all practical assignments must be completed and details around exams and resits.
Capacitors can be installed at industrial facilities to improve power factor by supplying reactive power (kVAR) near electrical loads like motors. This reduces costs by lowering a facility's kVA demand, improving voltage, increasing system capacity, and reducing line losses. The document provides examples of how to calculate kVAR needs and estimated savings from power factor correction. It also discusses best practices for capacitor installation locations and applications for different load types.
Power Factor Correction Methods
Fixed Capcitors
Synchronous Condensors
Phase Advancers
Switch Capacitors
Static Var Compensator(SVC)
Static Synchronous Compensator(STATCOM)
Modulated power filter capacitor compensator
Economics of power factor improvement
Economical comparison of increasing the power supply
Power upgrading of transmission line by combining ac dc transmissionShailesh Senta
Long extra high voltage (EHV) ac lines cannot be loaded to their Thermal limits in order
to keep sufficient margin against transient instability. With The scheme proposed in this
project, it is possible to load these lines very close to their thermal limits. The conductors
are allowed to carry usual ac along with dc superimposed on it.
The added dc power flow does not cause any transient instability. This Paper gives the
feasibility of converting a double circuit ac line into composite ac– dc power transmission
line to get the advantages of parallel ac–dc transmission to improve stability and damping
out oscillations. Simulation and experimental studies are carried out for the coordinated
control as well as independent control of ac and dc power transmissions. No alterations of
conductors, insulator strings, and towers of the original line are needed. Substantial gain in
the load ability of the line is obtained. Master current controller senses ac current and
regulates the dc current orders for converters online such that conductor current never
exceeds its thermal limit.
Power upgrading of transmission line by combining ac dc transmissionShailesh Senta
Long extra high voltage (EHV) ac lines cannot be loaded to their Thermal limits in order
to keep sufficient margin against transient instability. With The scheme proposed in this
project, it is possible to load these lines very close to their thermal limits. The conductors
are allowed to carry usual ac along with dc superimposed on it.
The added dc power flow does not cause any transient instability. This Paper gives the
feasibility of converting a double circuit ac line into composite ac– dc power transmission
line to get the advantages of parallel ac–dc transmission to improve stability and damping
out oscillations. Simulation and experimental studies are carried out for the coordinated
control as well as independent control of ac and dc power transmissions. No alterations of
conductors, insulator strings, and towers of the original line are needed. Substantial gain in
the load ability of the line is obtained. Master current controller senses ac current and
regulates the dc current orders for converters online such that conductor current never
exceeds its thermal limit.
A 100-kW PV array is connected to a 25-kV grid via a DC-DC boost converter and a three-phase three-level Voltage Source Converter (VSC). Maximum Power Point Tracking (MPPT) is implemented in the boost converter by means of a Simulink® model using the 'Incremental Conductance + Integral Regulator' technique.
Another example (see PVArrayGridAverageModel model) uses average models for the DC_DC and VSC converters. In this average model the MPPT controller is based on the 'Perturb and Observe' technique.
This document discusses power factor, causes of low power factor, disadvantages of low power factor, and methods for improving power factor. It begins by defining power factor as the ratio of active power to apparent power. Inductive loads like transformers and motors cause low power factors by introducing reactive power. Low power factor results in larger equipment sizes, greater losses, and reduced system capacity. Methods for improving power factor include installing capacitors to offset reactive power and replacing standard motors with high efficiency models. The document concludes with a case study where installing capacitors at a factory's main board improved the average power factor from 0.75 to 0.95.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
Walmart Business+ and Spark Good for Nonprofits.pdfTechSoup
"Learn about all the ways Walmart supports nonprofit organizations.
You will hear from Liz Willett, the Head of Nonprofits, and hear about what Walmart is doing to help nonprofits, including Walmart Business and Spark Good. Walmart Business+ is a new offer for nonprofits that offers discounts and also streamlines nonprofits order and expense tracking, saving time and money.
The webinar may also give some examples on how nonprofits can best leverage Walmart Business+.
The event will cover the following::
Walmart Business + (https://business.walmart.com/plus) is a new shopping experience for nonprofits, schools, and local business customers that connects an exclusive online shopping experience to stores. Benefits include free delivery and shipping, a 'Spend Analytics” feature, special discounts, deals and tax-exempt shopping.
Special TechSoup offer for a free 180 days membership, and up to $150 in discounts on eligible orders.
Spark Good (walmart.com/sparkgood) is a charitable platform that enables nonprofits to receive donations directly from customers and associates.
Answers about how you can do more with Walmart!"
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumMJDuyan
(𝐓𝐋𝐄 𝟏𝟎𝟎) (𝐋𝐞𝐬𝐬𝐨𝐧 𝟏)-𝐏𝐫𝐞𝐥𝐢𝐦𝐬
𝐃𝐢𝐬𝐜𝐮𝐬𝐬 𝐭𝐡𝐞 𝐄𝐏𝐏 𝐂𝐮𝐫𝐫𝐢𝐜𝐮𝐥𝐮𝐦 𝐢𝐧 𝐭𝐡𝐞 𝐏𝐡𝐢𝐥𝐢𝐩𝐩𝐢𝐧𝐞𝐬:
- Understand the goals and objectives of the Edukasyong Pantahanan at Pangkabuhayan (EPP) curriculum, recognizing its importance in fostering practical life skills and values among students. Students will also be able to identify the key components and subjects covered, such as agriculture, home economics, industrial arts, and information and communication technology.
𝐄𝐱𝐩𝐥𝐚𝐢𝐧 𝐭𝐡𝐞 𝐍𝐚𝐭𝐮𝐫𝐞 𝐚𝐧𝐝 𝐒𝐜𝐨𝐩𝐞 𝐨𝐟 𝐚𝐧 𝐄𝐧𝐭𝐫𝐞𝐩𝐫𝐞𝐧𝐞𝐮𝐫:
-Define entrepreneurship, distinguishing it from general business activities by emphasizing its focus on innovation, risk-taking, and value creation. Students will describe the characteristics and traits of successful entrepreneurs, including their roles and responsibilities, and discuss the broader economic and social impacts of entrepreneurial activities on both local and global scales.
How to Setup Warehouse & Location in Odoo 17 InventoryCeline George
In this slide, we'll explore how to set up warehouses and locations in Odoo 17 Inventory. This will help us manage our stock effectively, track inventory levels, and streamline warehouse operations.
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPRAHUL
This Dissertation explores the particular circumstances of Mirzapur, a region located in the
core of India. Mirzapur, with its varied terrains and abundant biodiversity, offers an optimal
environment for investigating the changes in vegetation cover dynamics. Our study utilizes
advanced technologies such as GIS (Geographic Information Systems) and Remote sensing to
analyze the transformations that have taken place over the course of a decade.
The complex relationship between human activities and the environment has been the focus
of extensive research and worry. As the global community grapples with swift urbanization,
population expansion, and economic progress, the effects on natural ecosystems are becoming
more evident. A crucial element of this impact is the alteration of vegetation cover, which plays a
significant role in maintaining the ecological equilibrium of our planet.Land serves as the foundation for all human activities and provides the necessary materials for
these activities. As the most crucial natural resource, its utilization by humans results in different
'Land uses,' which are determined by both human activities and the physical characteristics of the
land.
The utilization of land is impacted by human needs and environmental factors. In countries
like India, rapid population growth and the emphasis on extensive resource exploitation can lead
to significant land degradation, adversely affecting the region's land cover.
Therefore, human intervention has significantly influenced land use patterns over many
centuries, evolving its structure over time and space. In the present era, these changes have
accelerated due to factors such as agriculture and urbanization. Information regarding land use and
cover is essential for various planning and management tasks related to the Earth's surface,
providing crucial environmental data for scientific, resource management, policy purposes, and
diverse human activities.
Accurate understanding of land use and cover is imperative for the development planning
of any area. Consequently, a wide range of professionals, including earth system scientists, land
and water managers, and urban planners, are interested in obtaining data on land use and cover
changes, conversion trends, and other related patterns. The spatial dimensions of land use and
cover support policymakers and scientists in making well-informed decisions, as alterations in
these patterns indicate shifts in economic and social conditions. Monitoring such changes with the
help of Advanced technologies like Remote Sensing and Geographic Information Systems is
crucial for coordinated efforts across different administrative levels. Advanced technologies like
Remote Sensing and Geographic Information Systems
9
Changes in vegetation cover refer to variations in the distribution, composition, and overall
structure of plant communities across different temporal and spatial scales. These changes can
occur natural.
This presentation was provided by Racquel Jemison, Ph.D., Christina MacLaughlin, Ph.D., and Paulomi Majumder. Ph.D., all of the American Chemical Society, for the second session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session Two: 'Expanding Pathways to Publishing Careers,' was held June 13, 2024.
2. FUNGSI UTAMA KAPASITOR BANK
•Memperbaiki faktor kuasa elektrik
khususnya pada pemasangan arus AC
dengan nilai kuasa besar seperti
penggunaan di industri.
3. FUNGSI KAPASITOR BANK SELAIN DARI
MEMPERBAIKI POWER FACTOR (PF);
• Membekalkan kuasa reaktif dengan tujuan untuk memaksimakan penggunaan kuasa
komplek (kva).
• Mengurangi terjadinya Voltage drop atau voltan menurun.
• Mencegah overload atau beban lebih pada transformer kerana kapasitor bank boleh
berfungsi juga sebagai kuasa tambahan.
• Mencegah kenaikan suhu kabel (temperature).
• Mengawal Efisiensi /kuasa dengan menurunkan KVA secara total kerana penggunaan
KVA lebih efisien dengan nilai Kw yang digunakan.
• Meminimakan kerugian pada jaringan elektrik.
• Mencegah denda daripada Pembekal Tenaga Seperti Tenaga Nasional
Berhad(Semenanjung Malaysia), Sabah Elektricity Sdn. Bhd.(SESB),Sarawak Energy
Berhad(SEB) kerana adanya kuasa reaktif.
4. EXAMPLE: 1
A 3 PHASE, 5 KW INDUCTION MOTOR HAS A P.F (POWER
FACTOR) OF 0.75 LAGGING. WHAT SIZE OF CAPACITOR IN
KVAR IS REQUIRED TO IMPROVE THE P.F (POWER
FACTOR) TO 0.90?
Solution #1 (By Simple Table Method)
• Motor Input = 5kW
• From Table, Multiplier to improve PF from 0.75 to 0.90 is .398
• Required Capacitor kVAR to improve P.F from 0.75 to 0.90
• Required Capacitor kVAR = kW x Table 1 Multiplier of 0.75 and 0.90 = 5kW x .398
= 1.99 kVAR
• And Rating of Capacitors connected in each Phase, 1.99/3 = 0.663 kVAR
5. EXAMPLE: 1
A 3 PHASE, 5 KW INDUCTION MOTOR HAS A P.F (POWER
FACTOR) OF 0.75 LAGGING. WHAT SIZE OF CAPACITOR IN
KVAR IS REQUIRED TO IMPROVE THE P.F (POWER
FACTOR) TO 0.90?
Solution # 2 (Classical Calculation Method)
• Motor input = P = 5 kW
• Original P.F = Cosθ1 = 0.75
• Final P.F = Cosθ2 = 0.90
• θ1 = Cos-1 = (0.75) = 41°.41; Tan θ1 = Tan (41°.41) = 0.8819
• θ2 = Cos-1 = (0.90) = 25°.84; Tan θ2 = Tan (25°.50) = 0.4843
• Required Capacitor kVAR to improve P.F from 0.75 to 0.90
• Required Capacitor kVAR = P (Tan θ1 – Tan θ2) = 5kW (0.8819 – 0.4843) = 1.99 kVAR
• And Rating of Capacitors connected in each Phase, 1.99/3 = 0.663 kVAR
6. EXAMPLE 2:
AN ALTERNATOR IS SUPPLYING A LOAD OF 650 KW AT A P.F (POWER FACT OR) OF
0.65. WHAT SIZE OF CAPACITOR IN KVAR IS REQUIRED TO RAISE THE P.F (POWER
FACTOR) TO UNITY (1)? AND HOW MANY MORE KW CAN THE ALTERNATOR
SUPPLY FOR THE SAME KVA LOADING WHEN P.F IMPROVED.
Solution #1 (By Simple Table Method)
• Supplying kW = 650 kW
• From Table 1, Multiplier to improve PF from 0.65 to unity (1) is 1.169
• Required Capacitor kVAR to improve P.F from 0.65 to unity (1)
• Required Capacitor kVAR = kW x Table 1 Multiplier of 65 and 100 = 650kW x 1.169 = 759.85
kVAR
• We know that P.F = Cosθ = kW/kVA . . .or
• kVA = kW / Cosθ = 650/0.65 = 1000 kVA
• When Power Factor is raised to unity (1)
• No of kW = kVA x Cosθ = 1000 x 1 = 1000kW
• Hence increased Power supplied by Alternator, 1000kW – 650kW = 350kW
7. EXAMPLE 2:
AN ALTERNATOR IS SUPPLYING A LOAD OF 650 KW AT A P.F (POWER FACT OR) OF
0.65. WHAT SIZE OF CAPACITOR IN KVAR IS REQUIRED TO RAISE THE P.F (POWER
FACTOR) TO UNITY (1)? AND HOW MANY MORE KW CAN THE ALTERNATOR
SUPPLY FOR THE SAME KVA LOADING WHEN P.F IMPROVED.
Solution # 2 (Classical Calculation Method)
• Supplying kW = 650 kW
• Original P.F = Cosθ1 = 0.65
• Final P.F = Cosθ2 = 1
• θ1 = Cos-1 = (0.65) = 49°.45; Tan θ1 = Tan (41°.24) = 1.169
• θ2 = Cos-1 = (1) = 0°; Tan θ2 = Tan (0°) = 0
• Required Capacitor kVAR to improve P.F from 0.75 to 0.90
• Required Capacitor kVAR = P (Tan θ1 – Tan θ2) = 650kW (1.169– 0)
= 759.85 kVAR
8. HOW TO CALCULATE THE
REQUIRED CAPACITOR BANK
VALUE IN BOTH KVAR AND
FARADS?
(HOW TO CONVERT FARADS
INTO KVAR AND VICE VERSA)
9. EXAMPLE: 3
A single phase 400V, 50hz, motor takes a supply current of 50A at a
P.F (power factor) of 0.6. The motor power factor has to be improved
to 0.9 by connecting a capacitor in parallel with it. Calculate the
required capacity of capacitor in both kvar and farads.
Solution #1 (by simple table method)
• Motor input = p = v x i x cosθ = 400V x 50A x 0.6 = 12kw
• From table, multiplier to improve pf from 0.60 to 0.90 is 0.849
• Required capacitor kvar to improve P.F from 0.60 to 0.90
• Required capacitor kvar = kw x table multiplier of 0.60 and 0.90 = 12kw
x 0.849 = 10.188 kvar
10. EXAMPLE: 3
A SINGLE PHASE 400V, 50HZ, MOTOR TAKES A SUPPLY CURRENT OF 50A
AT A P.F (POWER FACTOR) OF 0.6. THE MOTOR POWER FACTOR HAS TO
BE IMPROVED TO 0.9 BY CONNECTING A CAPACITOR IN PARALLEL WITH
IT. CALCULATE THE REQUIRED CAPACITY OF CAPACITOR IN BOTH KVAR
AND FARADS.
Solution # 2 (Classical Calculation Method)
• Motor Input = P = V x I x Cosθ = 400V x 50A x 0.6 = 12kW
• Actual P.F = Cosθ1 = 0.6
• Required P.F = Cosθ2 = 0.90
• θ1 = Cos-1 = (0.60) = 53°.13; Tan θ1 = Tan (53°.13) = 1.3333
• θ2 = Cos-1 = (0.90) = 25°.84; Tan θ2 = Tan (25°.50) = 0.4843
• Required Capacitor kVAR to improve P.F from 0.60 to 0.90
= P (Tan θ1 – Tan θ2) = 5kW (1.3333– 0.4843) =10.188 kVAR
11. EXAMPLE: 3
A SINGLE PHASE 400V, 50HZ, MOTOR TAKES A SUPPLY CURRENT OF 50A
AT A P.F (POWER FACTOR) OF 0.6. THE MOTOR POWER FACTOR HAS TO
BE IMPROVED TO 0.9 BY CONNECTING A CAPACITOR IN PARALLEL WITH
IT. CALCULATE THE REQUIRED CAPACITY OF CAPACITOR IN BOTH KVAR
AND FARADS.
Solution #1 (Using a Simple Formula)
We have already calculated the required Capacity of Capacitor in kVAR,
we can easily convert it into Farads by using this simple formula
• Required Capacity of Capacitor in Farads/Microfarads = C = kVAR / (2
f V2) in microfarad
• Putting the Values in the above formula = (10.188kVAR) / (2 x π x 50 x
4002)
= 2.0268 x 10-4 = 202.7 x 10-6 = 202.7μF
12. Example: 3
A single phase 400V, 50hz, motor takes A supply current of
50A at A P.F (power factor) of 0.6. The motor power factor
has to be improved to 0.9 by connecting A capacitor in
parallel with it. Calculate the required capacity of
capacitor in both kvar and farads.
Solution # 2 (Simple Calculation Method)
• kVAR = 10.188 … (i)
• We know that; IC = V/ XC , Whereas XC = 1 / 2 π F C
• IC = V / (1 / 2 π F C) = V 2 F C = (400) x 2π x (50) x C = 125663.7 x C
And,
• kVAR = (V x IC) / 1000 … [kVAR =( V x I)/ 1000 ] = 400 x 125663.7 x C
• IC = 50265.48 x C … (ii)
13. EXAMPLE: 3
A SINGLE PHASE 400V, 50HZ, MOTOR TAKES A SUPPLY CURRENT OF 50A
AT A P.F (POWER FACTOR) OF 0.6. THE MOTOR POWER FACTOR HAS TO
BE IMPROVED TO 0.9 BY CONNECTING A CAPACITOR IN PARALLEL WITH
IT. CALCULATE THE REQUIRED CAPACITY OF CAPACITOR IN BOTH KVAR
AND FARADS.
• Solution # 2 (Simple Calculation Method)
Equating Equation (i) & (ii), we get,
• 50265.48 x C = 10.188C = 10.188 / 50265.48 = 2.0268 x 10-4 = 202.7 x 10-6 = 202.7μF
14. EXAMPLE 4
WHAT VALUE OF CAPACITANCE MUST BE CONNECTED IN PARALLEL WITH
A LOAD DRAWING 1KW AT 70% LAGGING POWER FACTOR FROM A 208V,
60HZ SOURCE IN ORDER TO RAISE THE OVERALL POWER FACTOR TO
91%.
• Solution:
• You can use either Table method or Simple Calculation method to find the required value of Capacitance in Farads or
to improve Power factor from 0.71 to 0.97. So I used table method in this case.
• P = 1000W
• Actual Power factor = Cosθ1 = 0.71
• Desired Power factor = Cosθ2 = 0.97
• From Table, Multiplier to improve PF from 0.71 to 0.97 is 0.783
• Required Capacitor kVAR to improve P.F from 0.71 to 0.97
• Required Capacitor kVAR = kW x Table Multiplier of 0.71 and 0.97
• = 1kW x 0.783
• =783 VAR (required Capacitance Value in kVAR)
15. EXAMPLE 4
WHAT VALUE OF CAPACITANCE MUST BE CONNECTED IN PARALLEL WITH
A LOAD DRAWING 1KW AT 70% LAGGING POWER FACTOR FROM A 208V,
60HZ SOURCE IN ORDER TO RAISE THE OVERALL POWER FACTOR TO
91%.
Solution:
• Current in the Capacitor = IC = QC / V = 783 / 208 = 3.76A
• And
• XC = V / IC = 208 / 3.76 = 55.25Ω
• C = 1/ (2 π f XC) = 1 (2 π x 60 x 55.25) = 48 μF (required Capacitance Value in Farads)
16. IMPORTANT FORMULAS WHICH IS USED FOR
POWER FACTOR IMPROVEMENT CALCULATION AS
WELL AS USED IN THE ABOVE CALCULATION
Power in Watts
• kW = kVA x Cosθ
• kW = HP x 0.746 or (HP x 0.746) / Efficiency … (HP = Motor Power)
• kW = √ ( kVA2– kVAR2)
• kW = P = VI Cosθ … (Single Phase)
• kW = P =√3x V x I Cosθ … (Three Phase)
17. IMPORTANT FORMULAS WHICH IS USED FOR
POWER FACTOR IMPROVEMENT CALCULATION AS
WELL AS USED IN THE ABOVE CALCULATION
Apparent Power in VA
• kVA= √(kW2+ kVAR2)
• kVA = kW/ Cosθ
Reactive Power in VA
• kVAR= √(kVA2– kW2)
• kVAR = C x (2 π f V2)
18. IMPORTANT FORMULAS WHICH IS USED FOR
POWER FACTOR IMPROVEMENT CALCULATION AS
WELL AS USED IN THE ABOVE CALCULATION
Power factor (from 0.1 to 1)
• Power Factor = Cosθ = P / V I … (Single Phase)
• Power Factor = Cosθ = P / (√3x V x I) … (Three Phase)
• Power Factor = Cosθ = kW / kVA … (Both Single Phase & Three Phase)
• Power Factor = Cosθ = R/Z … (Resistance / Impedance)
XC = 1/ (2 π f C) … (XC = Capacitive reactance)
• IC = V/ XC … (I = V / R)
Required Capacity of Capacitor in Farads/Microfarads
• C = kVAR / (2 π f V2) in microfarad
Required Capacity of Capacitor in kVAR
• kVAR = C x (2 π f V2)