SlideShare a Scribd company logo
DESIGN OF
MARKET
Group Members
■ Amjad Ali
■ Junaid Ijaz
■ Fazal Hussain
■ Zubair
■ Rana Ahsan
■ Sohaib Arshad
Contents
■ Objective
■ Problem Statement
■ Proposed Designs
■ Design of Steel Structure
■ Design of Concrete Structure
■ Bill of Quantities
■ Scheduling
■ Letter to Client
Objective
To propose two solutions for the design of the structure.
To analyze both solution and to adopt one solution that is
more feasible.
To make rough estimate of time for the completion of
construction works.
To determine the construction cost of project.
Problem Statement
■ Design of covered market with following
Specifications.
The roofed area is to be 650 x 260 feet with a clear roof height of
30’.
Entrance 10.0 ft wide are required between 23 ft long sections of
wall.
The roof is required to overhang the perimeter enclosure by
32.75 ft on all sides.
Supporting columns are to have a minimum spacing of 45 ft
internally and externally
The ground floor will be raised above general ground level by 4
inches.
Imposed Loading
■ Roof generally: 13 psf
■ Ground floor: 105 psf
Site Conditions
■ The site is flat.
■ The wind load on the structure can be taken as 35 psf.
■ Ground Conditions:
■ 0 ft to 16.5 ft – very soft clay and silt (Allowable soil pressure = 1 ksf)
■ Below 16.5 ft - strong limestone and hard sandstone (Allowable
pressure = 80 ksf)
Proposed Designs
We proposed two solutions for the design of the structure:
■ Design using steel frame with concrete foundation.
■ Design using reinforced concrete.
Design of light weight Steel
Structure
■ First proposed structural designs on which we decided to work was
steel design.
■ It was like a hipped roof to which a steel frame was supporting.
■ We provides 15 degree slope on each side.
■ The highest point of the slab was the middle section and gradually
decreasing towards the edges in all directions.
TopView
■ We drawn the whole covered area of the building inAutoCAD
software.
SectionViews
Limitations
This idea was rejected because of some limitations.
■ HighWind Load
■ Limited Software knowledge
Design using
reinforced
concrete.
Design of
Steel
Structure
up
Down
Design Of Concrete Structure
■ Second proposed solution was to design it using reinforced
concrete and following the ACI code.
■ We divided our slab into small huts of sizes 49.56 x 49.85.
■ Each hut was further divided into smaller panels of sizes 15.52’x
16.44
■ By using cross beams to reduce the required depth of the slab.
■ There are total 48panels and 65 columns (13 along 650’& 5
along 260’) supporting these panels.
Design Approach
■ The shape of the building was drawn in AutoCAD ,we divided it
into panels of 49.6’x 49.58’.
■ Each panel was of hut like shape.
■ We calculated the total load that is applied on the structure.
For example, wind load of 35 psf and imposed loading of 13 psf.
■ Slab, was divided into panels in the first step. Slab type was
coming out to be one-way.
■ Load from slab was transferred on to the beam
including the dead load of the slab.
■ There are three types of beams.
■ Then load transferred from beams to columns, now
this load was including the dead loads of slab
DESIGN OF
STRUCTURE
DESIGN
OF SLAB
DESIGN
OF
BEAMS
DESIGN
OF
COLUMN
S
DESIGN
OF
FOOTIN
G
Bill of Quantities (BOQ)
Bill of Quantities(BOQ)
SCHEDULING
SCHEDULING
SCHEDULING
References
■ Design of Concrete Structure by Nelson
■ PRC Lectures
■ ACI CODE
■ MRS
THANK
YOU!!

More Related Content

What's hot

Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
Anshul Shakya
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
Pui San
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
Site report 1
Site report 1Site report 1
Site report 1
Jenny Huoy Miin
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
Momo Poyi
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
Toe Myint Naing
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
Sumit Singh
 
Case study steel composite structure
Case study  steel composite structureCase study  steel composite structure
Case study steel composite structure
Shahin MB
 
Site report
Site reportSite report
Site report
Tee Joanne
 

What's hot (9)

Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Case study steel composite structure
Case study  steel composite structureCase study  steel composite structure
Case study steel composite structure
 
Site report
Site reportSite report
Site report
 

Similar to Design of Market

Flat slab design
Flat slab designFlat slab design
Flat slab design
Moussa Rili
 
Folded plates
Folded platesFolded plates
Folded plates
Rohan Narvekar
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.
CADmantra Technologies
 
TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION. TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION.
ARKALGUD NARASIMHA PRAKASH
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
SatyaNarayana135764
 
flat Slab
flat Slabflat Slab
flat Slab
Vikas Mehta
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid Architects
Dhanveersinh Chavda
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
Neha Rampuria
 
Turning torso
Turning torsoTurning torso
Turning torso
Miral Hadakia
 
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
ManoharManu993491
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
Vigneshwarsankar2
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
Building construction mini project
Building construction mini projectBuilding construction mini project
Building construction mini project
ZarnoshKtk
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Blake Johnson
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
BirukYared3
 
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN) CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
Hamza Waheed
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
MohdAbdulMujeeb5
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
RajeshKumar25548
 

Similar to Design of Market (20)

Flat slab design
Flat slab designFlat slab design
Flat slab design
 
Folded plates
Folded platesFolded plates
Folded plates
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.
 
TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION. TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION.
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
 
flat Slab
flat Slabflat Slab
flat Slab
 
London Aquatics Center – Zaha Hadid Architects
 London Aquatics Center – Zaha Hadid Architects London Aquatics Center – Zaha Hadid Architects
London Aquatics Center – Zaha Hadid Architects
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Turning torso
Turning torsoTurning torso
Turning torso
 
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Building construction mini project
Building construction mini projectBuilding construction mini project
Building construction mini project
 
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelOldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
Oldcastle Precast Spokane - Urban Modular Construction - The Grand Hotel
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN) CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
 

Recently uploaded

Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 

Recently uploaded (20)

Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 

Design of Market

  • 2. Group Members ■ Amjad Ali ■ Junaid Ijaz ■ Fazal Hussain ■ Zubair ■ Rana Ahsan ■ Sohaib Arshad
  • 3. Contents ■ Objective ■ Problem Statement ■ Proposed Designs ■ Design of Steel Structure ■ Design of Concrete Structure ■ Bill of Quantities ■ Scheduling ■ Letter to Client
  • 4. Objective To propose two solutions for the design of the structure. To analyze both solution and to adopt one solution that is more feasible. To make rough estimate of time for the completion of construction works. To determine the construction cost of project.
  • 5. Problem Statement ■ Design of covered market with following Specifications. The roofed area is to be 650 x 260 feet with a clear roof height of 30’. Entrance 10.0 ft wide are required between 23 ft long sections of wall. The roof is required to overhang the perimeter enclosure by 32.75 ft on all sides. Supporting columns are to have a minimum spacing of 45 ft internally and externally The ground floor will be raised above general ground level by 4 inches.
  • 6. Imposed Loading ■ Roof generally: 13 psf ■ Ground floor: 105 psf Site Conditions ■ The site is flat. ■ The wind load on the structure can be taken as 35 psf. ■ Ground Conditions: ■ 0 ft to 16.5 ft – very soft clay and silt (Allowable soil pressure = 1 ksf) ■ Below 16.5 ft - strong limestone and hard sandstone (Allowable pressure = 80 ksf)
  • 7. Proposed Designs We proposed two solutions for the design of the structure: ■ Design using steel frame with concrete foundation. ■ Design using reinforced concrete.
  • 8. Design of light weight Steel Structure ■ First proposed structural designs on which we decided to work was steel design. ■ It was like a hipped roof to which a steel frame was supporting. ■ We provides 15 degree slope on each side. ■ The highest point of the slab was the middle section and gradually decreasing towards the edges in all directions.
  • 9. TopView ■ We drawn the whole covered area of the building inAutoCAD software.
  • 11. Limitations This idea was rejected because of some limitations. ■ HighWind Load ■ Limited Software knowledge
  • 13. Design Of Concrete Structure ■ Second proposed solution was to design it using reinforced concrete and following the ACI code. ■ We divided our slab into small huts of sizes 49.56 x 49.85. ■ Each hut was further divided into smaller panels of sizes 15.52’x 16.44 ■ By using cross beams to reduce the required depth of the slab.
  • 14. ■ There are total 48panels and 65 columns (13 along 650’& 5 along 260’) supporting these panels.
  • 15. Design Approach ■ The shape of the building was drawn in AutoCAD ,we divided it into panels of 49.6’x 49.58’. ■ Each panel was of hut like shape. ■ We calculated the total load that is applied on the structure. For example, wind load of 35 psf and imposed loading of 13 psf. ■ Slab, was divided into panels in the first step. Slab type was coming out to be one-way.
  • 16.
  • 17. ■ Load from slab was transferred on to the beam including the dead load of the slab. ■ There are three types of beams. ■ Then load transferred from beams to columns, now this load was including the dead loads of slab
  • 20.
  • 21.
  • 23.
  • 24.
  • 26.
  • 27.
  • 29.
  • 30.
  • 33.
  • 37.
  • 38. References ■ Design of Concrete Structure by Nelson ■ PRC Lectures ■ ACI CODE ■ MRS

Editor's Notes

  1. a) High Wind Load When we tried to proceed to model and design these members of frame, we calculated loads, the wind load for this frame structure was so challenging. In case of steel, the dead load is very low as compare to concrete so to cater upward wind load in case of a light weight steel frame, we had to take very seriously the joints and the concrete foundation too. Otherwise wind would lift off the whole frame and structure would collapse. b) Limited Software knowledge When we decided to model the frame on ETABS software because we had some basic know how about analyzing some structure on software, but for modeling it was our first try, but we faced a problem of having a little knowledge about the design of steel structures and software as well. we tried to get some knowledge about the method from internet, how to model a frame on the software, but we realized that the time was too short to learn software and steel design code to model such challenging frame.