Task was assigned to provide most economical and sustaniable design idea for given design specifications.Two solutions must be proposed and recomend best possible solution.
The document provides details of a cost estimation project for constructing a house in Bahria Town, Islamabad. It includes an introduction, objectives, background on the plot of land and house design. It then outlines the work breakdown structure and provides details on excavation, brickwork, concrete, steel reinforcement, doors/windows, flooring and other construction items. Summary sheets show the total estimated construction cost, overhead costs, contingencies, taxes, profit and overall project cost of 61.7 million Pakistani rupees. The document demonstrates the group's thorough cost estimation process over 14 weeks to maximize profits for all involved in the construction project.
Multi story building construction anshulAnshul Shakya
Multi-storey buildings aim to increase the floor area of the building without increasing the area of the land the building is built on, hence saving land and, in most cases, money (depending on material used and land prices in the area). The building with the most storeys is the Jaypee green garden isles is 2B+G+38.
This site visit report summarizes observations from a visit to a construction site building 96 semi-detached houses. Key points include:
- Safety procedures were emphasized including wearing proper attire and helmets. Various signs indicated potential dangers.
- Construction equipment observed included excavators, road rollers, lorries, backhoe loaders used to move materials and compact soil.
- Materials seen included reinforcement bars, steel roof trusses, formwork and concrete mix.
- The process of constructing pad footings involved excavating, pouring a lean concrete layer, adding formwork and reinforcement bars, and pouring concrete.
Nursyafiqah Ismail completed her 10-week industrial training with Pembinaan Thin Chai Sdn. Bhd, a construction company established in 1970. She gained experience in design analysis, preparing method statements and bills of quantities, conducting site inspections, and ordering materials. Some of her responsibilities included designing fencing for a bridge project, drafting repair methods for concrete beams, and inspecting construction progress at sites in Gua Musang and Port Klang. Through hands-on learning and documentation tasks, she enhanced her skills in areas like structural analysis and software like AutoCAD.
PPT on industrial summer training in civil engineer ramit raj
Initial works in construction of residential building conducted by civil engineer like what is site plan ,site clearance , field test of material,layout, grid line etc.
The document provides details about the Capital Gate building project in Abu Dhabi. It describes the building as having a record lean of 18 degrees and being 160 meters tall. Unconventional construction methods were used, including pre-cambering and post-tensioning of the core and custom steel diagrids. The building achieved several awards and set new benchmarks in civil engineering.
1) The document outlines the structural design of a 5-floor male student residence building located in Alkhoudh, Oman with a total area of 3500 sqm and total cost of 1,131,925 Omani Riyals.
2) It describes the methodology used, including the limit state method and software like STAAD.Pro, and outlines the structural elements of the building like beams, columns, walls, slabs, and foundations.
3) The document provides details on the loading assumptions, material specifications, and cost breakdown by floor. Challenges and lessons learned are also summarized.
The document provides details of a cost estimation project for constructing a house in Bahria Town, Islamabad. It includes an introduction, objectives, background on the plot of land and house design. It then outlines the work breakdown structure and provides details on excavation, brickwork, concrete, steel reinforcement, doors/windows, flooring and other construction items. Summary sheets show the total estimated construction cost, overhead costs, contingencies, taxes, profit and overall project cost of 61.7 million Pakistani rupees. The document demonstrates the group's thorough cost estimation process over 14 weeks to maximize profits for all involved in the construction project.
Multi story building construction anshulAnshul Shakya
Multi-storey buildings aim to increase the floor area of the building without increasing the area of the land the building is built on, hence saving land and, in most cases, money (depending on material used and land prices in the area). The building with the most storeys is the Jaypee green garden isles is 2B+G+38.
This site visit report summarizes observations from a visit to a construction site building 96 semi-detached houses. Key points include:
- Safety procedures were emphasized including wearing proper attire and helmets. Various signs indicated potential dangers.
- Construction equipment observed included excavators, road rollers, lorries, backhoe loaders used to move materials and compact soil.
- Materials seen included reinforcement bars, steel roof trusses, formwork and concrete mix.
- The process of constructing pad footings involved excavating, pouring a lean concrete layer, adding formwork and reinforcement bars, and pouring concrete.
Nursyafiqah Ismail completed her 10-week industrial training with Pembinaan Thin Chai Sdn. Bhd, a construction company established in 1970. She gained experience in design analysis, preparing method statements and bills of quantities, conducting site inspections, and ordering materials. Some of her responsibilities included designing fencing for a bridge project, drafting repair methods for concrete beams, and inspecting construction progress at sites in Gua Musang and Port Klang. Through hands-on learning and documentation tasks, she enhanced her skills in areas like structural analysis and software like AutoCAD.
PPT on industrial summer training in civil engineer ramit raj
Initial works in construction of residential building conducted by civil engineer like what is site plan ,site clearance , field test of material,layout, grid line etc.
The document provides details about the Capital Gate building project in Abu Dhabi. It describes the building as having a record lean of 18 degrees and being 160 meters tall. Unconventional construction methods were used, including pre-cambering and post-tensioning of the core and custom steel diagrids. The building achieved several awards and set new benchmarks in civil engineering.
1) The document outlines the structural design of a 5-floor male student residence building located in Alkhoudh, Oman with a total area of 3500 sqm and total cost of 1,131,925 Omani Riyals.
2) It describes the methodology used, including the limit state method and software like STAAD.Pro, and outlines the structural elements of the building like beams, columns, walls, slabs, and foundations.
3) The document provides details on the loading assumptions, material specifications, and cost breakdown by floor. Challenges and lessons learned are also summarized.
Multi story building construction training report anshulAnshul Shakya
A Multi-storey is a building that has multiple floors above ground in the building.
Multi-storey buildings aim to increase the floor area of the building without increasing the area of the land the building is built on, hence saving land and, in most cases, money (depending on material used and land prices in the area). The building with the most stories is the Burj Khalifa, with 162.
The word building is both a noun and a verb: the structure itself and the act of making it. As a noun, a building is 'a structure that has a roof and walls and stands more or less permanently in one place "there was a three-storey building on the corner"; "it was an imposing edifice". In the broadest interpretation a fence or wall is a building However, the word structure is used more broadly than building including natural and man-made formations and does not necessarily have walls. Structure is more likely to be used for a fence. Sturgis' Dictionary included that "[building] differs from Architecture in excluding all idea of artistic treatment; and it differs from Construction in the idea of excluding scientific or highly skilful treatment.As a verb, building is the act of construction.
Structural height in technical usage is the height to the highest architectural detail on building from street-level. Depending on how they are classified, spires and masts may or may not be included in this height. Spires and masts used as antennas are not generally included. The definition of a low-rise vs. a high-rise building is a matter of debate, but generally three storeys or less is considered low-rise.
1) The document summarizes a site visit by students to an active construction project located in Puchong, Malaysia.
2) Upon arrival, students received a briefing about the project which included details about its large size and budget. Safety precautions for the site were also explained.
3) Students then toured the site in small groups, observing construction equipment, materials, and techniques used by workers. This helped students understand practical applications compared to theoretical knowledge.
4) Key aspects of the site included its use of pile foundations due to soil conditions, as well as reinforced concrete construction using grades 30-40 concrete.
This technical site visit summary is as follows:
1. The site visit was to an Andes construction site located in Puchong to understand the construction process.
2. The project involved pile foundations, including bored piles over 3 meters deep, as well as construction of basement slab, beams, and ground floor structures.
3. Different areas of the building used reinforced concrete of varying grades, with foundations at Grade 35 and columns at Grade 45.
The document is a site visit report for a construction project comprising 96 residential units. It includes an introduction, objectives of the site visit, summaries of the site layout and house types, and observations of construction materials and methods used - including scaffolding, formwork, pad footings, and reinforced concrete. Photos supplement the technical descriptions and the conclusion reflects on the learning experience gained from directly observing construction practices.
This document provides information and assignment briefs for a technical site visit to an Andes Construction site for three modules: Measurement 1, Construction Technology 1, and Building Materials. Students are required to submit a report by July 3rd that includes the objectives of the site visit, an introduction to the site, technical observations made on site, and how the visit helped achieve the learning outcomes. Specifically, the report must identify the foundation type and its advantages/disadvantages, explain the construction process and sequence of work observed, and identify the reinforced concrete grades used for different building elements and their advantages/disadvantages. The assignment will be assessed based on the objective, content, photos, learning outcomes, and conclusion, for a total of
This document provides details of the design and analysis of a 4-storey steel structure residential building. It includes the modeling processes, floor plans, steel and concrete frame designs, connection designs, schedules and structural details. The modeling processes include grid system definition, material definition, frame modeling, slab/stair modeling, load case definition, load combination, and analysis and design. Floor plans, member sizes, reinforcement details, footing details and connection details are shown. Schedules for beams, columns, hollow sections, decking and footings are provided.
Construction of residential building summer training pptSumit Singh
Sumit Singh completed a summer training project on the construction of a residential building complex called Assotech Blith Group Housing in Gurgaon, Haryana, India. The project involved constructing 7 towers ranging from G+18 to G+25 floors over an area of 12 acres. Singh learned about the various stages of construction including land acquisition, excavation, formwork, reinforcement placement, casting, and finishing. He was trained in activities like shuttering, bar placing, staircase construction, brickwork, and safety requirements. The training helped improve his confidence and choice to study civil engineering.
This document provides a case study of the Tower Center International building in Bucharest, Romania. It summarizes key details of the building including its dimensions, number of stories, foundation type, and structural system. The main structure used partially encased steel columns, steel beams and bracings, with composite slabs. The structural system included cruciform cross section columns made of hot rolled steel profiles in moment resisting frame and composite beam bays.
This document summarizes a student's report on a site visit to a construction project. The student observed various construction techniques, including different types of formwork used for beams, columns, and slabs. Scaffolding types like independent scaffolding were also discussed. The project involved constructing two residential towers with amenities on a podium structure over basement parking levels. The student learned about construction processes, safety practices, and building materials and was able to see theory applied in practice during the site visit.
This document provides details on the design and construction of flat slab structures. It discusses the benefits of flat slabs such as flexibility in layout, reduced building height and faster construction. Key considerations for design include wall and column placement, structural layout optimization, deflection checks, crack control and punching shear. Analysis involves dividing the slab into strips and determining moment and shear distributions. Reinforcement is arranged in two directions and detailing includes reinforcement lapping and service penetrations.
Study of Folded Plates for understanding their use, types, technology along with suitable case studies. This is a specific type of Methodology adopted for construction over long spans column free spaces. How structurally Folded plates surpases the need of column grids and conventional methods of construction with the proper design and technology is the motive of this study.
This document provides an analysis and design of the structural elements for a multi-storey residential building, including slabs, columns, shear walls, and foundations. It discusses the objectives, general approach, types of buildings and concrete mixtures used. The structural elements are then analyzed and designed according to the given specifications and loadings, with reinforcement details provided for slabs, columns, shear walls, and pile caps.
This document discusses formwork used for concrete structures. It begins with defining formwork as a temporary supporting structure used to form concrete into required shapes and sizes. Formwork is then classified based on the system used, materials, and application. Specific formwork types are described, including conventional timber formwork, proprietary modular systems, aluminum formwork, slip forming, and tunnel forming. Components, uses, and construction processes are outlined for walls, columns, beams, and other concrete elements. Considerations for precast versus cast-in-place formwork are also covered.
This document summarizes a seminar presentation on box pushing technology. Box pushing technology involves prefabricating concrete box segments and pushing them underground using hydraulic jacks to form tunnels, culverts, and other underground structures with minimal excavation. The presentation covers the objectives of box pushing, key components of the process, construction steps, advantages over conventional excavation methods, safety measures, environmental benefits, and future trends in the technology. Box pushing allows for faster, less disruptive, and more cost-effective construction of underground infrastructure compared to traditional excavation methods.
The industrial training presentation outlines the objectives and process of a construction project. The objectives are to gain experience, generic skills, networks, and self-awareness. The construction process involves soil testing, excavation, laying foundations, erecting columns, beams and slabs over 31 steps. Office work includes producing drawings like site plans, elevations, and structural, plumbing and electrical layouts to guide construction. The presenter concluded they gained construction knowledge and confidence through the training experience.
This document discusses the design and analysis of flat slab structures. It begins with an introduction to flat slabs and their uses of column heads and drop panels. The benefits of flat slabs are then outlined, including flexibility in layout, reduced building height, and ease of M&E installation. Design considerations are presented such as structural stiffness, deflection limits, and shear reinforcement. The document analyzes flat slab design methodology including finite element analysis, simplified methods, and equivalent frame analysis. Moment distribution, punching shear, deflection, and detailing of reinforcement mesh are also summarized.
The London Aquatics Center is an indoor facility with two 50-metre (164-foot) swimming pools and a 25-metre (82-foot) diving pool in Queen Elizabeth Olympic Park in Stafford, London.
The Aldar Headquarters building in Abu Dhabi is the first spherical building in the Middle East. It has a diameter of 120.9 meters and stands 121 meters tall. The building's unique design includes a diagrid structural system that eliminates the need for internal columns. It also has a glass facade composed of triangular glass pieces that fit together to curve with the building's spherical shape. The building was constructed using sustainable materials and methods, such as a vacuum waste collection system and prefabricated elements, and achieved LEED Silver certification.
The Turning Torso is a 190-meter residential skyscraper located in Malmo, Sweden that was designed by architect Santiago Calatrava. Some key details:
- It has a twisting form composed of nine concrete cubes that twist 90 degrees from the base to the top.
- The central concrete core provides structural support, containing elevators and staircases. An exterior steel exoskeleton transfers wind loads and allows the concrete floors to cantilever.
- Construction began in 2001 and was completed in 2005, using a unique climbing form system to pour the concrete floors which rotated 1.6 degrees with each level.
- The skyscraper contains residential units and office space and utilizes sustainable design principles
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....ManoharManu993491
This document describes the analysis and design of a residential building with four stories using flat slab construction in STAAD Pro software. It includes modeling the building with drop panels and column heads, applying dead, live and roof loads, performing analysis to obtain deflections, bending moments and pressures, and designing the concrete columns and slab according to IS 456 code. The results show maximum bending moments in beams of 210 kN-m, and designs meet code requirements for shear, bending and deflections.
The Ronan Point apartment tower collapse in 1968 was caused by a partial collapse initiated by a small gas explosion. The collapse propagated due to a lack of structural redundancy in the building's design. Four people were killed and 17 injured. Investigations found flaws in both the design and construction of the building.
The Skyline Plaza construction collapse in 1973 killed 14 workers and injured 34 others. A punching shear failure occurred around columns on the 23rd floor due to improper removal of supporting forms before the concrete had reached full strength.
The Walkie Talkie building in London focused sunlight onto nearby surfaces, with reports of temperatures reaching 91°C. This was due to a fatal flaw in the building's design which did not
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
This document provides an overview of an industrial training presentation on a redevelopment project by NBCC Limited in New Delhi, India. It summarizes the project details including the construction being divided into 5 packages, methodology used such as site clearance, excavation, laying of concrete, and quality control testing. The presentation also includes photos from the construction site and details of structural elements like columns, beams, and lifts.
Multi story building construction training report anshulAnshul Shakya
A Multi-storey is a building that has multiple floors above ground in the building.
Multi-storey buildings aim to increase the floor area of the building without increasing the area of the land the building is built on, hence saving land and, in most cases, money (depending on material used and land prices in the area). The building with the most stories is the Burj Khalifa, with 162.
The word building is both a noun and a verb: the structure itself and the act of making it. As a noun, a building is 'a structure that has a roof and walls and stands more or less permanently in one place "there was a three-storey building on the corner"; "it was an imposing edifice". In the broadest interpretation a fence or wall is a building However, the word structure is used more broadly than building including natural and man-made formations and does not necessarily have walls. Structure is more likely to be used for a fence. Sturgis' Dictionary included that "[building] differs from Architecture in excluding all idea of artistic treatment; and it differs from Construction in the idea of excluding scientific or highly skilful treatment.As a verb, building is the act of construction.
Structural height in technical usage is the height to the highest architectural detail on building from street-level. Depending on how they are classified, spires and masts may or may not be included in this height. Spires and masts used as antennas are not generally included. The definition of a low-rise vs. a high-rise building is a matter of debate, but generally three storeys or less is considered low-rise.
1) The document summarizes a site visit by students to an active construction project located in Puchong, Malaysia.
2) Upon arrival, students received a briefing about the project which included details about its large size and budget. Safety precautions for the site were also explained.
3) Students then toured the site in small groups, observing construction equipment, materials, and techniques used by workers. This helped students understand practical applications compared to theoretical knowledge.
4) Key aspects of the site included its use of pile foundations due to soil conditions, as well as reinforced concrete construction using grades 30-40 concrete.
This technical site visit summary is as follows:
1. The site visit was to an Andes construction site located in Puchong to understand the construction process.
2. The project involved pile foundations, including bored piles over 3 meters deep, as well as construction of basement slab, beams, and ground floor structures.
3. Different areas of the building used reinforced concrete of varying grades, with foundations at Grade 35 and columns at Grade 45.
The document is a site visit report for a construction project comprising 96 residential units. It includes an introduction, objectives of the site visit, summaries of the site layout and house types, and observations of construction materials and methods used - including scaffolding, formwork, pad footings, and reinforced concrete. Photos supplement the technical descriptions and the conclusion reflects on the learning experience gained from directly observing construction practices.
This document provides information and assignment briefs for a technical site visit to an Andes Construction site for three modules: Measurement 1, Construction Technology 1, and Building Materials. Students are required to submit a report by July 3rd that includes the objectives of the site visit, an introduction to the site, technical observations made on site, and how the visit helped achieve the learning outcomes. Specifically, the report must identify the foundation type and its advantages/disadvantages, explain the construction process and sequence of work observed, and identify the reinforced concrete grades used for different building elements and their advantages/disadvantages. The assignment will be assessed based on the objective, content, photos, learning outcomes, and conclusion, for a total of
This document provides details of the design and analysis of a 4-storey steel structure residential building. It includes the modeling processes, floor plans, steel and concrete frame designs, connection designs, schedules and structural details. The modeling processes include grid system definition, material definition, frame modeling, slab/stair modeling, load case definition, load combination, and analysis and design. Floor plans, member sizes, reinforcement details, footing details and connection details are shown. Schedules for beams, columns, hollow sections, decking and footings are provided.
Construction of residential building summer training pptSumit Singh
Sumit Singh completed a summer training project on the construction of a residential building complex called Assotech Blith Group Housing in Gurgaon, Haryana, India. The project involved constructing 7 towers ranging from G+18 to G+25 floors over an area of 12 acres. Singh learned about the various stages of construction including land acquisition, excavation, formwork, reinforcement placement, casting, and finishing. He was trained in activities like shuttering, bar placing, staircase construction, brickwork, and safety requirements. The training helped improve his confidence and choice to study civil engineering.
This document provides a case study of the Tower Center International building in Bucharest, Romania. It summarizes key details of the building including its dimensions, number of stories, foundation type, and structural system. The main structure used partially encased steel columns, steel beams and bracings, with composite slabs. The structural system included cruciform cross section columns made of hot rolled steel profiles in moment resisting frame and composite beam bays.
This document summarizes a student's report on a site visit to a construction project. The student observed various construction techniques, including different types of formwork used for beams, columns, and slabs. Scaffolding types like independent scaffolding were also discussed. The project involved constructing two residential towers with amenities on a podium structure over basement parking levels. The student learned about construction processes, safety practices, and building materials and was able to see theory applied in practice during the site visit.
This document provides details on the design and construction of flat slab structures. It discusses the benefits of flat slabs such as flexibility in layout, reduced building height and faster construction. Key considerations for design include wall and column placement, structural layout optimization, deflection checks, crack control and punching shear. Analysis involves dividing the slab into strips and determining moment and shear distributions. Reinforcement is arranged in two directions and detailing includes reinforcement lapping and service penetrations.
Study of Folded Plates for understanding their use, types, technology along with suitable case studies. This is a specific type of Methodology adopted for construction over long spans column free spaces. How structurally Folded plates surpases the need of column grids and conventional methods of construction with the proper design and technology is the motive of this study.
This document provides an analysis and design of the structural elements for a multi-storey residential building, including slabs, columns, shear walls, and foundations. It discusses the objectives, general approach, types of buildings and concrete mixtures used. The structural elements are then analyzed and designed according to the given specifications and loadings, with reinforcement details provided for slabs, columns, shear walls, and pile caps.
This document discusses formwork used for concrete structures. It begins with defining formwork as a temporary supporting structure used to form concrete into required shapes and sizes. Formwork is then classified based on the system used, materials, and application. Specific formwork types are described, including conventional timber formwork, proprietary modular systems, aluminum formwork, slip forming, and tunnel forming. Components, uses, and construction processes are outlined for walls, columns, beams, and other concrete elements. Considerations for precast versus cast-in-place formwork are also covered.
This document summarizes a seminar presentation on box pushing technology. Box pushing technology involves prefabricating concrete box segments and pushing them underground using hydraulic jacks to form tunnels, culverts, and other underground structures with minimal excavation. The presentation covers the objectives of box pushing, key components of the process, construction steps, advantages over conventional excavation methods, safety measures, environmental benefits, and future trends in the technology. Box pushing allows for faster, less disruptive, and more cost-effective construction of underground infrastructure compared to traditional excavation methods.
The industrial training presentation outlines the objectives and process of a construction project. The objectives are to gain experience, generic skills, networks, and self-awareness. The construction process involves soil testing, excavation, laying foundations, erecting columns, beams and slabs over 31 steps. Office work includes producing drawings like site plans, elevations, and structural, plumbing and electrical layouts to guide construction. The presenter concluded they gained construction knowledge and confidence through the training experience.
This document discusses the design and analysis of flat slab structures. It begins with an introduction to flat slabs and their uses of column heads and drop panels. The benefits of flat slabs are then outlined, including flexibility in layout, reduced building height, and ease of M&E installation. Design considerations are presented such as structural stiffness, deflection limits, and shear reinforcement. The document analyzes flat slab design methodology including finite element analysis, simplified methods, and equivalent frame analysis. Moment distribution, punching shear, deflection, and detailing of reinforcement mesh are also summarized.
The London Aquatics Center is an indoor facility with two 50-metre (164-foot) swimming pools and a 25-metre (82-foot) diving pool in Queen Elizabeth Olympic Park in Stafford, London.
The Aldar Headquarters building in Abu Dhabi is the first spherical building in the Middle East. It has a diameter of 120.9 meters and stands 121 meters tall. The building's unique design includes a diagrid structural system that eliminates the need for internal columns. It also has a glass facade composed of triangular glass pieces that fit together to curve with the building's spherical shape. The building was constructed using sustainable materials and methods, such as a vacuum waste collection system and prefabricated elements, and achieved LEED Silver certification.
The Turning Torso is a 190-meter residential skyscraper located in Malmo, Sweden that was designed by architect Santiago Calatrava. Some key details:
- It has a twisting form composed of nine concrete cubes that twist 90 degrees from the base to the top.
- The central concrete core provides structural support, containing elevators and staircases. An exterior steel exoskeleton transfers wind loads and allows the concrete floors to cantilever.
- Construction began in 2001 and was completed in 2005, using a unique climbing form system to pour the concrete floors which rotated 1.6 degrees with each level.
- The skyscraper contains residential units and office space and utilizes sustainable design principles
Analysis and Design of G+3 building with flat slab using STAAD PRO V8i M F-1....ManoharManu993491
This document describes the analysis and design of a residential building with four stories using flat slab construction in STAAD Pro software. It includes modeling the building with drop panels and column heads, applying dead, live and roof loads, performing analysis to obtain deflections, bending moments and pressures, and designing the concrete columns and slab according to IS 456 code. The results show maximum bending moments in beams of 210 kN-m, and designs meet code requirements for shear, bending and deflections.
The Ronan Point apartment tower collapse in 1968 was caused by a partial collapse initiated by a small gas explosion. The collapse propagated due to a lack of structural redundancy in the building's design. Four people were killed and 17 injured. Investigations found flaws in both the design and construction of the building.
The Skyline Plaza construction collapse in 1973 killed 14 workers and injured 34 others. A punching shear failure occurred around columns on the 23rd floor due to improper removal of supporting forms before the concrete had reached full strength.
The Walkie Talkie building in London focused sunlight onto nearby surfaces, with reports of temperatures reaching 91°C. This was due to a fatal flaw in the building's design which did not
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
This document provides an overview of an industrial training presentation on a redevelopment project by NBCC Limited in New Delhi, India. It summarizes the project details including the construction being divided into 5 packages, methodology used such as site clearance, excavation, laying of concrete, and quality control testing. The presentation also includes photos from the construction site and details of structural elements like columns, beams, and lifts.
This document provides details about the construction of a residential building with 7 flats in Nagpur, India. It describes the foundation layout including spread footings and reinforcement. Preparations for the slab pour are outlined, including leveling, formwork, reinforcement, and calculating the concrete volume. Activities after casting like curing and starter columns are also summarized. The conclusion reflects on how the training helped provide practical experience in areas like planning, execution, and concrete volume calculations.
This document contains the final term project submitted by Zarnosh Khattaq for their Building Construction course. It discusses various topics related to building construction including formwork requirements, types of formwork for floors, beams, walls and columns with photos. It also describes the importance of building bye-laws and requirements for amenities buildings, commercial buildings, industrial buildings, public buildings, residential buildings, and apartment buildings as per bye-laws.
Oldcastle Precast Spokane - Urban Modular Construction - The Grand HotelBlake Johnson
The document discusses a modular construction project by Oldcastle Precast to build the Davenport Grand Hotel using over 4,500 precast concrete pieces. Key elements were cast in place, like footings, shear walls, and topping slabs, while modular precast construction was used for columns, beams, flooring, wall panels, stair towers, and more. This accelerated method allowed the hotel to be completed in just 2 years, providing large open spaces, high efficiency, and reduced costs for the owner.
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN) Hamza Waheed
Hamza Waheed conducted a study of construction practices in Multan, Pakistan. He visited 5 construction sites, documenting materials, machinery, and processes used. Brick, cement, aggregate, and steel were commonly used materials. Construction involved laying foundations, formwork, concrete mixing and pouring, masonry, and finishing. English bond was most often used, and ratios of 1:2:4 for RCC and 1:4 or 1:6 for mortar were prevalent. The study provided insight into current construction methods in Multan.
The document summarizes the analysis and design of a multi-story institutional building with hollow core slabs. It discusses using Staad.Pro software to analyze and design the building's hollow core slabs, beams, columns, footings, and stairs. The production process of hollow core slabs is also outlined, including bed preparation, stressing strands, casting, curing, transport, and erection. Key activities to be performed include calculating loads, designing hollow core slabs, connecting slab panels, designing beams and columns, and designing footings.
This document provides details on planning, analysis, and design of a four-story commercial building with a reinforced concrete frame structure. It includes the building specifications, objectives, methodology, structural designs, material details, software used, and conclusions. The commercial building has a total plinth area of 5070 square feet and is estimated to cost approximately Rs. 2.85 crores. STADD PRO software is used to analyze the multi-story frame and design the structural elements according to code specifications.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELgerogepatton
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMHODECEDSIET
Time Division Multiplexing (TDM) is a method of transmitting multiple signals over a single communication channel by dividing the signal into many segments, each having a very short duration of time. These time slots are then allocated to different data streams, allowing multiple signals to share the same transmission medium efficiently. TDM is widely used in telecommunications and data communication systems.
### How TDM Works
1. **Time Slots Allocation**: The core principle of TDM is to assign distinct time slots to each signal. During each time slot, the respective signal is transmitted, and then the process repeats cyclically. For example, if there are four signals to be transmitted, the TDM cycle will divide time into four slots, each assigned to one signal.
2. **Synchronization**: Synchronization is crucial in TDM systems to ensure that the signals are correctly aligned with their respective time slots. Both the transmitter and receiver must be synchronized to avoid any overlap or loss of data. This synchronization is typically maintained by a clock signal that ensures time slots are accurately aligned.
3. **Frame Structure**: TDM data is organized into frames, where each frame consists of a set of time slots. Each frame is repeated at regular intervals, ensuring continuous transmission of data streams. The frame structure helps in managing the data streams and maintaining the synchronization between the transmitter and receiver.
4. **Multiplexer and Demultiplexer**: At the transmitting end, a multiplexer combines multiple input signals into a single composite signal by assigning each signal to a specific time slot. At the receiving end, a demultiplexer separates the composite signal back into individual signals based on their respective time slots.
### Types of TDM
1. **Synchronous TDM**: In synchronous TDM, time slots are pre-assigned to each signal, regardless of whether the signal has data to transmit or not. This can lead to inefficiencies if some time slots remain empty due to the absence of data.
2. **Asynchronous TDM (or Statistical TDM)**: Asynchronous TDM addresses the inefficiencies of synchronous TDM by allocating time slots dynamically based on the presence of data. Time slots are assigned only when there is data to transmit, which optimizes the use of the communication channel.
### Applications of TDM
- **Telecommunications**: TDM is extensively used in telecommunication systems, such as in T1 and E1 lines, where multiple telephone calls are transmitted over a single line by assigning each call to a specific time slot.
- **Digital Audio and Video Broadcasting**: TDM is used in broadcasting systems to transmit multiple audio or video streams over a single channel, ensuring efficient use of bandwidth.
- **Computer Networks**: TDM is used in network protocols and systems to manage the transmission of data from multiple sources over a single network medium.
### Advantages of TDM
- **Efficient Use of Bandwidth**: TDM all
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
2. Group Members
■ Amjad Ali
■ Junaid Ijaz
■ Fazal Hussain
■ Zubair
■ Rana Ahsan
■ Sohaib Arshad
3. Contents
■ Objective
■ Problem Statement
■ Proposed Designs
■ Design of Steel Structure
■ Design of Concrete Structure
■ Bill of Quantities
■ Scheduling
■ Letter to Client
4. Objective
To propose two solutions for the design of the structure.
To analyze both solution and to adopt one solution that is
more feasible.
To make rough estimate of time for the completion of
construction works.
To determine the construction cost of project.
5. Problem Statement
■ Design of covered market with following
Specifications.
The roofed area is to be 650 x 260 feet with a clear roof height of
30’.
Entrance 10.0 ft wide are required between 23 ft long sections of
wall.
The roof is required to overhang the perimeter enclosure by
32.75 ft on all sides.
Supporting columns are to have a minimum spacing of 45 ft
internally and externally
The ground floor will be raised above general ground level by 4
inches.
6. Imposed Loading
■ Roof generally: 13 psf
■ Ground floor: 105 psf
Site Conditions
■ The site is flat.
■ The wind load on the structure can be taken as 35 psf.
■ Ground Conditions:
■ 0 ft to 16.5 ft – very soft clay and silt (Allowable soil pressure = 1 ksf)
■ Below 16.5 ft - strong limestone and hard sandstone (Allowable
pressure = 80 ksf)
7. Proposed Designs
We proposed two solutions for the design of the structure:
■ Design using steel frame with concrete foundation.
■ Design using reinforced concrete.
8. Design of light weight Steel
Structure
■ First proposed structural designs on which we decided to work was
steel design.
■ It was like a hipped roof to which a steel frame was supporting.
■ We provides 15 degree slope on each side.
■ The highest point of the slab was the middle section and gradually
decreasing towards the edges in all directions.
9. TopView
■ We drawn the whole covered area of the building inAutoCAD
software.
13. Design Of Concrete Structure
■ Second proposed solution was to design it using reinforced
concrete and following the ACI code.
■ We divided our slab into small huts of sizes 49.56 x 49.85.
■ Each hut was further divided into smaller panels of sizes 15.52’x
16.44
■ By using cross beams to reduce the required depth of the slab.
14. ■ There are total 48panels and 65 columns (13 along 650’& 5
along 260’) supporting these panels.
15. Design Approach
■ The shape of the building was drawn in AutoCAD ,we divided it
into panels of 49.6’x 49.58’.
■ Each panel was of hut like shape.
■ We calculated the total load that is applied on the structure.
For example, wind load of 35 psf and imposed loading of 13 psf.
■ Slab, was divided into panels in the first step. Slab type was
coming out to be one-way.
16.
17. ■ Load from slab was transferred on to the beam
including the dead load of the slab.
■ There are three types of beams.
■ Then load transferred from beams to columns, now
this load was including the dead loads of slab
a) High Wind Load
When we tried to proceed to model and design these members of frame, we calculated loads, the wind load for this frame structure was so challenging. In case of steel, the dead load is very low as compare to concrete so to cater upward wind load in case of a light weight steel frame, we had to take very seriously the joints and the concrete foundation too. Otherwise wind would lift off the whole frame and structure would collapse.
b) Limited Software knowledge
When we decided to model the frame on ETABS software because we had some basic know how about analyzing some structure on software, but for modeling it was our first try, but we faced a problem of having a little knowledge about the design of steel structures and software as well. we tried to get some knowledge about the method from internet, how to model a frame on the software, but we realized that the time was too short to learn software and steel design code to model such challenging frame.