SlideShare a Scribd company logo
A. N. PRAKASH CONSTRUCTION PROJECT
MANAGEMENT CONSULTANTS PVT. LTD.
ANP TALK SERIES
Saturday, June 20th, 2015
FORMWORK
for Concrete Structures
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 2
― Definition of Formwork
― Classification of formwork
― Scaffolds
― Failure of Formwork
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 3
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 4
DEFINITION OF
FORMWORK
Definition of formwork
“Formwork is a complete system of
temporary supporting structures and
mould to create structural elements of
required shape and size out of
concrete when poured into these
moulds”.
“Complete system of temporary
supporting structure which includes the
surface in contact built to contain the
fresh concrete so as to form it to the
required shape and dimensions and to
support it until it hardens sufficiently to
become self supporting”.
- IS 6461 Part 5 - 1972
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 5
Requirements of a formwork
• To carry following loads :
 Its own load (self load).
 Freshly placed concrete till it gains
enough strength to carry its own weight.
 Live load during concreting.
 Impact load when concrete is placed
from a height such as a skip or a boom
placer.
• Should be easily dismantled / struck with
minimum effort and shall without damage
concrete.
• Arrangement should facilitate easy placing
of concrete.
• Should be water tight to avoid leakage of
cement slurry / grout.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 6
Requirements of a formwork
• Should be re-usable.
• Easy for handling both by men and machine.
• Should be able to retain dimensions without
distortion.
• Minimum sawing and cutting etc.
• Must have safety arrangements for working
areas.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 7
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 8
CLASSIFICATION OF
FORMWORK
Classification of Formwork
Formwork
System adopted Material used Application
• Conventional
• Proprietary or patented
• Modular
• Custom made
• Wood / Timber/ Plywood
• Wooden planks
• Plastic
• Glass fibre reinforced plastic
• Metal
 Steel sheets
 Aluminium sheets
 MS Pipes
• Pre-casting
• In-situ Casting
• Form finish
(Architectural Finish)
• Architectural shapes
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 9
Classification of formwork
Formwork may be classified based on :
a. System adopted.
• Conventional
• Proprietary or patented
• Modular
• Custom made
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 10
Classification of formwork
Formwork may be classified based on :
b. Material used
• Wood / Timber /Plywood
• Wooden planks
• Plastic
• Glass fibre reinforced plastic
Contd…
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 11
…contd Classification of formwork
Metal
• Steel sheets
• Aluminium sheets
• MS Pipes
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 12
…contd Classification of formwork
c. Application
• Pre-casting
• In situ Casting
• Form finish (Architectural Finish)
• Architectural shapes
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 13
14
…contd Classification of formwork
Architectural
Shapes
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 14
Conventional system
• Built of Timbers or steel props, wooden
planks / plywood, wooden runners
etc.
• Produced at site.
• Custom made each time.
• Time consuming, particularly for large
structures.
• Preferred where the labour cost are
cheap and skills available are limited.
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 15
Conventional system
• Very flexible and can be used in combination with
modular/ patented system.
• Structural properties of the materials being used not known.
• Quality of finished product could suffer.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 16
Proprietary or Patented
• Mostly modular.
• Made of timber and plywood.
• Factory produced mostly.
• Custom made.
• Preferred for large structures.
• Can be handled easily by men and
machine.
• Designed specifically to carry the
load.
• Quality of the finished concrete high
in terms of line and length and
surface finish.
• Can be used repetitively gaining
high economy
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 17
Formwork
Flying Formwork
Tunnel Formwork
Aluminium Formwork
Slip Formwork
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 18
Disposable Column Forms
• A cost effective solution to problems for
forming round columns.
• Great versatility to the architectural
design.
• Provides the contractors an easy means of
achieving the desired quality standard.
• Strong yet light and easy to handle.
• One-use disposable design.
• Supplied to site ready prepared to length.
• Base and top are easily secured.
• No mould oil or release agent required.
• Stripped in seconds.
• Protects finished column from site
damage.
• Available in a wide range of sizes.
• Can be made available within short span
of time.
• Suitable for horizontal void cutting.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 19
Formwork liners
• Elastomeric form liner
• Rigid
• Fibre glass reinforced
• Foam polyurethane
• Expanded polystyrene
• Rubber
• Vacuum liners (treatment) very expensive
• Absorption liners (cotton cloth paper)
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 20
How are pre-cast formwork different from cast-in-
situ formwork.
• Pre-cast moulds are subject to much more
repetitions.
• Have to be sturdy and strong.
• Have to be designed to take external vibrations
on the mould.
• Dimensional accuracy is very important.
• Mould bottoms are normally stationary and the
sides removable.
• Must have sufficient chamfers and batter.
• Preferable to mount the moulds on rubber pads
for vibration.
• Absence of elaborate supporting system.
• Economy of scale
• Controlled quality.
• Slip form is similar to extrusion.
• Used to build high rise structures very quickly.
• Should be designed to normally carry ultimate
design but also erection loads.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 21
Components of Aluminium Formwork
RockerBeam Side Panel Deck Prop Length Deck Beam Bar External CornerProp head for Soffit
beam
Beam Soffit-panel Beam Soffit bulk head Deck Mid-beam
Internal Soffit
Corner
Internal Corners Kicker
Deck Panel Deck Prop Soffit Length
External Soffit
Corner
Wall Panel Stub Pin
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 22
Aluminium Formwork
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 23
Flying forms
• Flying forms are a system of formwork.
• They are called ‘flying forms’ since they
are literally flown from one place to
another.
• They are assembled on ground.
• They are placed in the location.
• Suitable for typical slabs of high rise
building.
• Suitable for large slabs.
• Slabs – Flat slabs / flat plates, high numbers
of repetition.
• High productivity.
• Suitable only when cranes are there.
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 24
Flying forms
Limitations
• Requires large open space for assembling.
• Crane required to remove and erect.
• Requires elaborate planning.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 25
Tunnel forms (slabs)
Limitations
• High capital cost.
• Requires very good spacing.
• Architectural limitations
• Crane dependent,
• Limited in terms of changes to
the structural configuration.
• Economy can be achieved only
when there is large repetition to
get ROI. (South city, Bangalore)
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 26
Tunnel forms (slabs)
• For use of repetition cellular structures.
• Can construct both horizontal and vertical
elements.
• Suitable for both high and low rise
buildings.
• High quality finishes.
• Dimensional accuracy.
• Savings upto 25% in Time and 15% in Cost.
• Work possible in all weather.
• An excellent structural solution.
• The formwork is available for purchase or
rent.
• Suppliers / contractors provide full design
and technical support.
• Supplier’s site training quickly brings them
up to speed.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 27
Typical Tunnel Formwork Cycle
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 28
Tunnel formwork in housing project
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 29
Slip forms
How does it work :
• The forms more either vertically or horizontally.
• Concrete is shaped in the design profile as the form moves
up.
• Forms use the set concrete for gripping and moving.
• The movement is normally slow to allow the concrete to set.
• The concrete would be strong enough to carry the weight of
the shutters.
• Designed to carry the concrete load as well as the wind
load.
Most suited for :
• Chimneys.
• Silos.
• Water towers.
• Telecommunications towers.
• Bridge piers.
• Pylons.
• Elevator shaft lines.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 30
Other forms
• Fibre forms
• Lost forms
• Pre-cast planks
• Sand wash
• ‘Roladeck’ forms for slabs
• Column mounted shoring system
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 31
System comparison for various features
Features Conventional system Proprietary / patented Modular formwork system
Flexibility It has high flexibility.
It has reasonably good
flexibility.
The system brings in
standardization and makes
entire formwork operation very
easy.
Reuse
Values
Limited reuse value.
Nailing renders
materials unusable
after a few uses.
The system has high
reuse value.
A large number of repetitions
(reuse) of modular formwork
are
Making
involved at
site
There is large making
of formwork involved
at site.
There is very little making
of formwork involved at
site.
Very less making at site, only
assembly of standard
components required
Expertise
required at
site
Considerable expert
carpentry effort is
required.
These can be assembled
and dismantled easily with
unskilled/semiskilled labour.
The work can be
accomplished
even by the less skilled worker.
Contd…
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 32
System comparison for various features
Features Conventional system Proprietary / patented Modular formwork system
Assembling at site
Considerable effort is
required for assembly at
site
Uses features and
accessories developed over
many to save time and
labour and gives higher
productivity.
Assembled very quickly at site.
Considerable reduction in the
erection time. The installation
process is also simple
Quality of
concrete surface
The quality of formwork
and productivity varies
depending on the skill of
labour.
Uniform quality
The quality of concrete
surface
obtained is extremely good
Productivity Low High Higher
Cost
Not economical for
large Projects
Very economical compared
to conventional formwork
for large projects.
Cost of formwork being
considerably on a lower side.
Planning
requirement
Planning is difficult. The
indiscriminate cutting of
timber is difficult to be
controlled.
Preplanning is easy and
effective and also
contributes to the efficiency
of work at site.
The standardization offers ease
in planning.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 33
PROCESS OF FORMWORK
CONSTRUCTION & STRUCTURING
Columns, Walls, Slabs
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 34
PROCESS OF FORMWORK
CONSTRUCTION
FORMWORK FOR VARIOUS STRUCTURAL MEMBERS
Construction of formwork:
This normally involves the following operations:
1. Propping and centering
2. Shuttering
3. Provision of camber
4. Cleaning and surface treatment
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 35
It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
After completing one side of formwork
reinforcement is provided at the place then the
second side formwork is provided.
FORMWORK FOR WALL
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 36
Wall Formworks and its components
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 37
FORMWORK FOR COLUMN
• It consists of the following
– Side & End Planks
– Yoke
– Nut & Bolts
• Two end & two side planks are
joined by the yokes and bolts.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 38
Erection sequence for a column
Prior to positioning column formwork check that steel for the column
has been inspected and cleared for casting.
• Position formwork for the column from predetermined grids.
• Plumb formwork both ways and securely support using adjustable
steel props.
• The propping angle should be 45° to the floor.
• Ensure the steel props are safely secured to the column formwork
and the floor, and that adjustment for pushing and pulling is
operational.
• Set out the positions of column clamps from a storey rod.
• Transfer the column clamp positions from the storey rod onto
column formwork.
• Use nails to support the arms of column clamps while wedging.
• Position and wedge the bottom, middle and top clamps sets.
• Check the formwork at the top for square.
• Position and wedge the remainder of the column clamps.
• Using a plumb bob suspended from a gauge block plumb the
column.
When all the column formwork is securely propped a final check must
be made for plumb and column alignment before and immediately
after the concrete has been poured and vibrated.
Column clamps are created to give extra
external support to the formwork from
avoiding circularing of the column
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 39
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 40
CIRCULAR AND OCTAGONAL COLUMNS
• Circular column formwork
• Fabricated steel, usually two piece, and
often with a hinge.
• Fibre cement pipes which are left in place
as permanent formwork.
• Timber sheathing tied with standard column
clamps. Corners need to have infill pieces.
Alternatively, metal strap can be used
without the need for corner infills.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 41
Column formwork bracing performs two functions:
• It must maintain the accuracy of the column form position and plumb so that it is
within tolerance.
• Withstand results of forces acting on either the column formwork or the bracing.
The forces may be wind or impact. These impact forces can occur from the
collision of concrete buckets or cranes hoisting materials
COLUMN BRACING FORMWORK
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 42
FORMWORK FOR BEAM
• Beam soffit must be thickened timber or strengthened plywood.
• Beam sides 18mm plywood or 25mm boards, with studs (cleats)
at 500 to 600mm centre.
• Deep beams (over 600mm) should have walkers and ties.
• Use angle fillets in the beam side to soffit joint where possible.
• Allowance must be made for height adjustment of the props or
falsework.
Erection sequence for constructing beam formwork includes
• Position of sole plates;
• Marking out and setting heights for falseworks;
• Assemble and position props, adjustable head jacks, falseworks,
bearers and Spreaders;
• Construct and erect side walls and beam soffit.
• Position of sole plates
43
FORMWORK FOR STAIRCASE
Points to consider when designing stair form work :
• Stair formwork must support the weight of concrete.
The weight of the throat of the stair and the steps will
have to be supported.
• Because of the slope of the stair, some of the force is
transmitted sideways. All formwork must be well tied
together to prevent sideway movement.
• Consider the finish of the stair treads and type of
nosing. Space may have to be left for purpose made
nosing.
44
SUSPENDED SLABS
Suspended floor slabs can be constructed using cast in‐
situ, precast units or a combination of both.
Whichever method is used, it is important to support the
proposed method of construction using a combination
of timber or steel bearers and adjustable shoring.
The spacing and type of support system required is
determined by the load imposed during the
construction process.
Manufacturers provide tables to assist in the selection
and spacing of adjustable shoring systems. The erection sequence for constructing
a suspended floor slab includes:
• Determining the bearer spacing;
• Erecting bearers and joists;
• Fixing the sheeting;
• Preparation for concrete.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 45
SOLE PLATE
The purpose of a sole plate is to transfer vertical load from
one vertical support member to the foundation
• The vertical support requires a base plate fitted to help
distribute the load to the sole plate, which is usually a
sleeper.
• If the sole plate is positioned on natural ground, it is
important the ground is graded and consolidated to a
level surface.
• The objective is to achieve maximum bearing beneath
sole plate. Once sole plates are positioned and firmly
bedded they should be checked for level.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 46
Screw Anchor Screw Anchor Bolt Hair Pin Anchor
Loop Anchor
A She-bolt
Pig Tail Anchor
Patented Tie
Systems
Formwork Accessories
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 47
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 48
SCAFFOLDS
Scaffolds
Classification of scaffolds
• Platform scaffolds
• Tower scaffolds
• Cantilever type
• Suspended type / cradle
Cantilever
scaffolds
Tower scaffolds
Platform scaffolds
suspended scaffolds
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 49
Contd…
Scaffolds
Classification of scaffolds
• Based on material – timber and metal
• Based on type of construction
• Out log scaffolds or single pole
• Double pole / independent scaffolds
Individual
Component
Type
Unit Frame
Type
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 50
Plan of formwork
arrangement using shoring
towers
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
51
Arrangement of shoring
towers in plan for slab and
beam formwork
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
52
Sectional view of formwork
arrangement using shoring
towers
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 53
Sectional view of shoring
towers for slab and beam
formwork
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 54
Beam formwork supported on
shoring tower
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 55
Scaffolds
Possible causes for collapse of scaffold
systems.
• Construction load exceeding the critical
load of the scaffold system.
• Horizontal instability
• Diagonal bracing not being used in the
scaffold.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 56
Scaffolds Safety
• Scaffold should be braced by means of
longitudinal and transverse bracing systems so as
to form a rigid and stable structure.
• Install additional ties to the scaffold to prevent
overturning and collapse.
• Guide rails and toe boards must be provided.
• All working platforms should be fully covered to
prevent materials falling.
• Safety nets and other screens should be
provided.
• Care should be taken to see that no uninsulated
wire exists within 3 m of the working platforms
gangways etc.
• Men should not be allowed on scaffolds during
storms and high winds.
• Grease, mud, paint etc should be removed from
the scaffolds.
• All projecting nails from the platforms or other
members should be removed.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 57
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 58
FAILURE OF
FORMWORK
Reasons for failure of Formwork
• Not designed for specific purpose.
• Improper stripping or shoring removal (cantilever).
• Not designed for horizontal thrust.
• Damaged elements .(span weld, broken u clamps
• Inadequate bracing.
• Vibration (passing traffic).
• Unstable soil under the props, Sole plates.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 59
Failure of Formwork
• The problem with formwork is that it is
‘temporary’
• The word temporary is associated with
lack of need for :
• Design
• Planning
• Care
• Strength
• Safety
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 60
Reasons for failure of Formwork
• Shoring not plumb.
• Rate of concreting.
• On site modifications due to site conditions.
• When formwork is not at fault.
• Ingress of water
• Removal of wedges by workers.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 61
Cantilever
Place concrete into the beams first and the
more towards the free end
Strike / de-shutter in the direction opposite
to that of concreting
De-shuttering
Concrete
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 62
Sequence of Beams and Slabs
Beam and Slab
• Start with beams.
• After beams start from beam more towards centre of
slab.
Precautions:
• Don’t store large quantities of concrete at one
place.
• Spread concrete immediately.
• Make sure that the scaffolding / staging is designed
to take horizontal movement of the pipe.
• Place from the centre and go towards the beams /
supports.
De-Shuttering
Beams
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 63
Sloping Slab Shuttering
Double Shuttering
• IS 1200 Part 5, Classification 5.1.D.ii.
• Top shutter not payable.
>300
Spacer
Bottom Shutter
Top Shutter
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 64
Method of Measurement – IS 1200
• Method of measurement of
building and Civil Engineering
works – Part V Formwork : IS 1200
(Part V) 1982.
• Code of practices for steel tubular
scaffolding – II IS 4014 (Part 2) 1967.
• Building and other construction
workers (BOCW) act (Regulation of
employment and conditions of
service) Act 1996.
Beam
Column
Depth of
beam
Beam
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 65
Specification writing for formwork
66
Points to be noted :
• The loads and the lateral pressure, the maximum permitted
deflection.
• Instructions on formwork detailing and fabrication and guidelines on
the required dimensions, the plumb, and the joints.
• Instructions on supervision of the formwork activities.
• Instruction on delivery, storage, protection and handling of the
formwork materials. Acceptance criteria of the formwork materials.
• Prior to commencement of the work, existing dimensions, elevations,
locations and conditions applicable to the work shall be field
verified.
• Instruction on the time allowed between erection of the forms and
placing of the concrete for the various trades to properly install their
work.
• Instruction on application of load on recently cast concrete.
• Specifications for lumber, sheathing material, and shoring.
Instruction on fabrication of form panels in conformity with the
approved submittals.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
Contd…
Specification writing for formwork
Points to be noted :
• Specifications for formwork accessories, such as form ties, hangers,
clamps, lugs, cones, washers, form liners or other devices.
• Specifications for triangular fillets if applicable.
• Instructions for cleaning and maintaining the form work materials.
• Instruction on inspections for cleanliness and accuracy of the
alignment prior to the placement of the concrete.
• Instruction on location, snugness and tightness of joints.
• Instruction on level of horizontal joints and plumb of vertical joints.
• Location size and construction of openings.
• Specification on expansion joint material, water stops, and other
embedded items to be built in to the forms and the instructions on
their placement and support against displacement.
• Filling of voids in sleeves, inserts and anchor slots.
Contd…
67A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
Specification writing for formwork
68
Points to be noted :
• Setting up of edge forms or bulkheads and intermediate screed
strips for the slabs to obtain required elevations and contours in the
finished slab surface.
• Supervision for checking deviations from desired elevation,
alignment, plumb and camber at the time of concreting.
• Guidelines for taking remedial measures in case at the time of
casting, weakness develops and the formwork shows settlement,
deflection or distortion.
• Specification on form coating material and instruction for their
application.
• Re-shoring, permissible loading on re-shores, timing of placement of
re-shores, instruction on tightening of re-shores.
• Guidelines for removal of forms, form ties and bracings to insure
complete safety to the structure.
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
Thank You
69
A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.

More Related Content

What's hot

Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
JYOTIRANJAN43
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
Karan Patel
 
Causes of deterioration of concrete structures
Causes of deterioration of concrete structuresCauses of deterioration of concrete structures
Causes of deterioration of concrete structures
Karthi Kavya
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
A Makwana
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
Karan Patel
 
Confined masonry
Confined masonryConfined masonry
Confined masonry
Dr. Nitin Naik
 
Pile load test
Pile load testPile load test
Pile load test
Naman Kantesaria
 
Placing of concrete
Placing of concretePlacing of concrete
Placing of concrete
Muhammad Hassaan Sajid
 
Caissons
Caissons Caissons
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and Classification
Sagar Radadiya
 
Bituminous penetration macadam base course
Bituminous penetration macadam base courseBituminous penetration macadam base course
Bituminous penetration macadam base course
Aglaia Connect
 
Aggregates
AggregatesAggregates
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Bhalchandra Tankkar
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
Shankar Ramasamy
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Structural steel
Structural steelStructural steel
Structural steel
vinod singh
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
9833356555
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
Avinash Kumar Gupta
 
Patten of collection systems of sanitation
Patten of collection systems of sanitationPatten of collection systems of sanitation
Patten of collection systems of sanitation
lobsang jampa
 
Planning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential BuildingPlanning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential Building
Mohamed Peer Thavood
 

What's hot (20)

Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Causes of deterioration of concrete structures
Causes of deterioration of concrete structuresCauses of deterioration of concrete structures
Causes of deterioration of concrete structures
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
 
Confined masonry
Confined masonryConfined masonry
Confined masonry
 
Pile load test
Pile load testPile load test
Pile load test
 
Placing of concrete
Placing of concretePlacing of concrete
Placing of concrete
 
Caissons
Caissons Caissons
Caissons
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and Classification
 
Bituminous penetration macadam base course
Bituminous penetration macadam base courseBituminous penetration macadam base course
Bituminous penetration macadam base course
 
Aggregates
AggregatesAggregates
Aggregates
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Structural steel
Structural steelStructural steel
Structural steel
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Patten of collection systems of sanitation
Patten of collection systems of sanitationPatten of collection systems of sanitation
Patten of collection systems of sanitation
 
Planning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential BuildingPlanning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential Building
 

Similar to TYPES OF FORMWORK AND THEIR APPLICATION.

HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
MohdAbdulMujeeb5
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
SAGAR RAUT
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
The Merits of Structural Steelwork
The Merits of Structural SteelworkThe Merits of Structural Steelwork
The Merits of Structural Steelwork
ESTRUCAD METÀL·LICS
 
Formwork
FormworkFormwork
Formwork
kajol panchal
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
Communications Branding
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
CivilTY09AdityaGaval
 
Formwork
FormworkFormwork
Formwork
Sneha Kaira
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
Prashant Borge
 
M.Tech PPT.pptx
M.Tech PPT.pptxM.Tech PPT.pptx
M.Tech PPT.pptx
ErAkshayNadiger
 
Site report
Site reportSite report
Site report
Tee Joanne
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
ErankajKumar
 
Formwork
FormworkFormwork
Formwork
snehakaira
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
dharmveersingh60
 
BridgProdPPTJan_2024_Reduced_Productline.pptx
BridgProdPPTJan_2024_Reduced_Productline.pptxBridgProdPPTJan_2024_Reduced_Productline.pptx
BridgProdPPTJan_2024_Reduced_Productline.pptx
The D.S. Brown Company
 
Company profile
Company profileCompany profile
Company profile
Dr Kari Thangaratnam
 

Similar to TYPES OF FORMWORK AND THEIR APPLICATION. (20)

HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
The Merits of Structural Steelwork
The Merits of Structural SteelworkThe Merits of Structural Steelwork
The Merits of Structural Steelwork
 
Formwork
FormworkFormwork
Formwork
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
 
Formwork
FormworkFormwork
Formwork
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
M.Tech PPT.pptx
M.Tech PPT.pptxM.Tech PPT.pptx
M.Tech PPT.pptx
 
Site report
Site reportSite report
Site report
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Formwork
FormworkFormwork
Formwork
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
 
BridgProdPPTJan_2024_Reduced_Productline.pptx
BridgProdPPTJan_2024_Reduced_Productline.pptxBridgProdPPTJan_2024_Reduced_Productline.pptx
BridgProdPPTJan_2024_Reduced_Productline.pptx
 
Company profile
Company profileCompany profile
Company profile
 

Recently uploaded

Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
MiscAnnoy1
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
shahdabdulbaset
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
Madan Karki
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 

Recently uploaded (20)

Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 

TYPES OF FORMWORK AND THEIR APPLICATION.

  • 1. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. ANP TALK SERIES Saturday, June 20th, 2015
  • 2. FORMWORK for Concrete Structures A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 2
  • 3. ― Definition of Formwork ― Classification of formwork ― Scaffolds ― Failure of Formwork A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 3
  • 4. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 4 DEFINITION OF FORMWORK
  • 5. Definition of formwork “Formwork is a complete system of temporary supporting structures and mould to create structural elements of required shape and size out of concrete when poured into these moulds”. “Complete system of temporary supporting structure which includes the surface in contact built to contain the fresh concrete so as to form it to the required shape and dimensions and to support it until it hardens sufficiently to become self supporting”. - IS 6461 Part 5 - 1972 A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 5
  • 6. Requirements of a formwork • To carry following loads :  Its own load (self load).  Freshly placed concrete till it gains enough strength to carry its own weight.  Live load during concreting.  Impact load when concrete is placed from a height such as a skip or a boom placer. • Should be easily dismantled / struck with minimum effort and shall without damage concrete. • Arrangement should facilitate easy placing of concrete. • Should be water tight to avoid leakage of cement slurry / grout. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 6
  • 7. Requirements of a formwork • Should be re-usable. • Easy for handling both by men and machine. • Should be able to retain dimensions without distortion. • Minimum sawing and cutting etc. • Must have safety arrangements for working areas. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 7
  • 8. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 8 CLASSIFICATION OF FORMWORK
  • 9. Classification of Formwork Formwork System adopted Material used Application • Conventional • Proprietary or patented • Modular • Custom made • Wood / Timber/ Plywood • Wooden planks • Plastic • Glass fibre reinforced plastic • Metal  Steel sheets  Aluminium sheets  MS Pipes • Pre-casting • In-situ Casting • Form finish (Architectural Finish) • Architectural shapes A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 9
  • 10. Classification of formwork Formwork may be classified based on : a. System adopted. • Conventional • Proprietary or patented • Modular • Custom made Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 10
  • 11. Classification of formwork Formwork may be classified based on : b. Material used • Wood / Timber /Plywood • Wooden planks • Plastic • Glass fibre reinforced plastic Contd… Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 11
  • 12. …contd Classification of formwork Metal • Steel sheets • Aluminium sheets • MS Pipes Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 12
  • 13. …contd Classification of formwork c. Application • Pre-casting • In situ Casting • Form finish (Architectural Finish) • Architectural shapes A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 13
  • 14. 14 …contd Classification of formwork Architectural Shapes A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 14
  • 15. Conventional system • Built of Timbers or steel props, wooden planks / plywood, wooden runners etc. • Produced at site. • Custom made each time. • Time consuming, particularly for large structures. • Preferred where the labour cost are cheap and skills available are limited. Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 15
  • 16. Conventional system • Very flexible and can be used in combination with modular/ patented system. • Structural properties of the materials being used not known. • Quality of finished product could suffer. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 16
  • 17. Proprietary or Patented • Mostly modular. • Made of timber and plywood. • Factory produced mostly. • Custom made. • Preferred for large structures. • Can be handled easily by men and machine. • Designed specifically to carry the load. • Quality of the finished concrete high in terms of line and length and surface finish. • Can be used repetitively gaining high economy A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 17
  • 18. Formwork Flying Formwork Tunnel Formwork Aluminium Formwork Slip Formwork A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 18
  • 19. Disposable Column Forms • A cost effective solution to problems for forming round columns. • Great versatility to the architectural design. • Provides the contractors an easy means of achieving the desired quality standard. • Strong yet light and easy to handle. • One-use disposable design. • Supplied to site ready prepared to length. • Base and top are easily secured. • No mould oil or release agent required. • Stripped in seconds. • Protects finished column from site damage. • Available in a wide range of sizes. • Can be made available within short span of time. • Suitable for horizontal void cutting. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 19
  • 20. Formwork liners • Elastomeric form liner • Rigid • Fibre glass reinforced • Foam polyurethane • Expanded polystyrene • Rubber • Vacuum liners (treatment) very expensive • Absorption liners (cotton cloth paper) A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 20
  • 21. How are pre-cast formwork different from cast-in- situ formwork. • Pre-cast moulds are subject to much more repetitions. • Have to be sturdy and strong. • Have to be designed to take external vibrations on the mould. • Dimensional accuracy is very important. • Mould bottoms are normally stationary and the sides removable. • Must have sufficient chamfers and batter. • Preferable to mount the moulds on rubber pads for vibration. • Absence of elaborate supporting system. • Economy of scale • Controlled quality. • Slip form is similar to extrusion. • Used to build high rise structures very quickly. • Should be designed to normally carry ultimate design but also erection loads. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 21
  • 22. Components of Aluminium Formwork RockerBeam Side Panel Deck Prop Length Deck Beam Bar External CornerProp head for Soffit beam Beam Soffit-panel Beam Soffit bulk head Deck Mid-beam Internal Soffit Corner Internal Corners Kicker Deck Panel Deck Prop Soffit Length External Soffit Corner Wall Panel Stub Pin A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 22
  • 23. Aluminium Formwork A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 23
  • 24. Flying forms • Flying forms are a system of formwork. • They are called ‘flying forms’ since they are literally flown from one place to another. • They are assembled on ground. • They are placed in the location. • Suitable for typical slabs of high rise building. • Suitable for large slabs. • Slabs – Flat slabs / flat plates, high numbers of repetition. • High productivity. • Suitable only when cranes are there. Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 24
  • 25. Flying forms Limitations • Requires large open space for assembling. • Crane required to remove and erect. • Requires elaborate planning. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 25
  • 26. Tunnel forms (slabs) Limitations • High capital cost. • Requires very good spacing. • Architectural limitations • Crane dependent, • Limited in terms of changes to the structural configuration. • Economy can be achieved only when there is large repetition to get ROI. (South city, Bangalore) A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 26
  • 27. Tunnel forms (slabs) • For use of repetition cellular structures. • Can construct both horizontal and vertical elements. • Suitable for both high and low rise buildings. • High quality finishes. • Dimensional accuracy. • Savings upto 25% in Time and 15% in Cost. • Work possible in all weather. • An excellent structural solution. • The formwork is available for purchase or rent. • Suppliers / contractors provide full design and technical support. • Supplier’s site training quickly brings them up to speed. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 27
  • 28. Typical Tunnel Formwork Cycle A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 28
  • 29. Tunnel formwork in housing project A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 29
  • 30. Slip forms How does it work : • The forms more either vertically or horizontally. • Concrete is shaped in the design profile as the form moves up. • Forms use the set concrete for gripping and moving. • The movement is normally slow to allow the concrete to set. • The concrete would be strong enough to carry the weight of the shutters. • Designed to carry the concrete load as well as the wind load. Most suited for : • Chimneys. • Silos. • Water towers. • Telecommunications towers. • Bridge piers. • Pylons. • Elevator shaft lines. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 30
  • 31. Other forms • Fibre forms • Lost forms • Pre-cast planks • Sand wash • ‘Roladeck’ forms for slabs • Column mounted shoring system A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 31
  • 32. System comparison for various features Features Conventional system Proprietary / patented Modular formwork system Flexibility It has high flexibility. It has reasonably good flexibility. The system brings in standardization and makes entire formwork operation very easy. Reuse Values Limited reuse value. Nailing renders materials unusable after a few uses. The system has high reuse value. A large number of repetitions (reuse) of modular formwork are Making involved at site There is large making of formwork involved at site. There is very little making of formwork involved at site. Very less making at site, only assembly of standard components required Expertise required at site Considerable expert carpentry effort is required. These can be assembled and dismantled easily with unskilled/semiskilled labour. The work can be accomplished even by the less skilled worker. Contd… A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 32
  • 33. System comparison for various features Features Conventional system Proprietary / patented Modular formwork system Assembling at site Considerable effort is required for assembly at site Uses features and accessories developed over many to save time and labour and gives higher productivity. Assembled very quickly at site. Considerable reduction in the erection time. The installation process is also simple Quality of concrete surface The quality of formwork and productivity varies depending on the skill of labour. Uniform quality The quality of concrete surface obtained is extremely good Productivity Low High Higher Cost Not economical for large Projects Very economical compared to conventional formwork for large projects. Cost of formwork being considerably on a lower side. Planning requirement Planning is difficult. The indiscriminate cutting of timber is difficult to be controlled. Preplanning is easy and effective and also contributes to the efficiency of work at site. The standardization offers ease in planning. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 33
  • 34. PROCESS OF FORMWORK CONSTRUCTION & STRUCTURING Columns, Walls, Slabs A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 34
  • 35. PROCESS OF FORMWORK CONSTRUCTION FORMWORK FOR VARIOUS STRUCTURAL MEMBERS Construction of formwork: This normally involves the following operations: 1. Propping and centering 2. Shuttering 3. Provision of camber 4. Cleaning and surface treatment A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 35
  • 36. It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided. FORMWORK FOR WALL A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 36
  • 37. Wall Formworks and its components A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 37
  • 38. FORMWORK FOR COLUMN • It consists of the following – Side & End Planks – Yoke – Nut & Bolts • Two end & two side planks are joined by the yokes and bolts. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 38
  • 39. Erection sequence for a column Prior to positioning column formwork check that steel for the column has been inspected and cleared for casting. • Position formwork for the column from predetermined grids. • Plumb formwork both ways and securely support using adjustable steel props. • The propping angle should be 45° to the floor. • Ensure the steel props are safely secured to the column formwork and the floor, and that adjustment for pushing and pulling is operational. • Set out the positions of column clamps from a storey rod. • Transfer the column clamp positions from the storey rod onto column formwork. • Use nails to support the arms of column clamps while wedging. • Position and wedge the bottom, middle and top clamps sets. • Check the formwork at the top for square. • Position and wedge the remainder of the column clamps. • Using a plumb bob suspended from a gauge block plumb the column. When all the column formwork is securely propped a final check must be made for plumb and column alignment before and immediately after the concrete has been poured and vibrated. Column clamps are created to give extra external support to the formwork from avoiding circularing of the column A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 39
  • 40. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 40
  • 41. CIRCULAR AND OCTAGONAL COLUMNS • Circular column formwork • Fabricated steel, usually two piece, and often with a hinge. • Fibre cement pipes which are left in place as permanent formwork. • Timber sheathing tied with standard column clamps. Corners need to have infill pieces. Alternatively, metal strap can be used without the need for corner infills. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 41
  • 42. Column formwork bracing performs two functions: • It must maintain the accuracy of the column form position and plumb so that it is within tolerance. • Withstand results of forces acting on either the column formwork or the bracing. The forces may be wind or impact. These impact forces can occur from the collision of concrete buckets or cranes hoisting materials COLUMN BRACING FORMWORK A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 42
  • 43. FORMWORK FOR BEAM • Beam soffit must be thickened timber or strengthened plywood. • Beam sides 18mm plywood or 25mm boards, with studs (cleats) at 500 to 600mm centre. • Deep beams (over 600mm) should have walkers and ties. • Use angle fillets in the beam side to soffit joint where possible. • Allowance must be made for height adjustment of the props or falsework. Erection sequence for constructing beam formwork includes • Position of sole plates; • Marking out and setting heights for falseworks; • Assemble and position props, adjustable head jacks, falseworks, bearers and Spreaders; • Construct and erect side walls and beam soffit. • Position of sole plates 43
  • 44. FORMWORK FOR STAIRCASE Points to consider when designing stair form work : • Stair formwork must support the weight of concrete. The weight of the throat of the stair and the steps will have to be supported. • Because of the slope of the stair, some of the force is transmitted sideways. All formwork must be well tied together to prevent sideway movement. • Consider the finish of the stair treads and type of nosing. Space may have to be left for purpose made nosing. 44
  • 45. SUSPENDED SLABS Suspended floor slabs can be constructed using cast in‐ situ, precast units or a combination of both. Whichever method is used, it is important to support the proposed method of construction using a combination of timber or steel bearers and adjustable shoring. The spacing and type of support system required is determined by the load imposed during the construction process. Manufacturers provide tables to assist in the selection and spacing of adjustable shoring systems. The erection sequence for constructing a suspended floor slab includes: • Determining the bearer spacing; • Erecting bearers and joists; • Fixing the sheeting; • Preparation for concrete. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 45
  • 46. SOLE PLATE The purpose of a sole plate is to transfer vertical load from one vertical support member to the foundation • The vertical support requires a base plate fitted to help distribute the load to the sole plate, which is usually a sleeper. • If the sole plate is positioned on natural ground, it is important the ground is graded and consolidated to a level surface. • The objective is to achieve maximum bearing beneath sole plate. Once sole plates are positioned and firmly bedded they should be checked for level. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 46
  • 47. Screw Anchor Screw Anchor Bolt Hair Pin Anchor Loop Anchor A She-bolt Pig Tail Anchor Patented Tie Systems Formwork Accessories A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 47
  • 48. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 48 SCAFFOLDS
  • 49. Scaffolds Classification of scaffolds • Platform scaffolds • Tower scaffolds • Cantilever type • Suspended type / cradle Cantilever scaffolds Tower scaffolds Platform scaffolds suspended scaffolds A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 49 Contd…
  • 50. Scaffolds Classification of scaffolds • Based on material – timber and metal • Based on type of construction • Out log scaffolds or single pole • Double pole / independent scaffolds Individual Component Type Unit Frame Type A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 50
  • 51. Plan of formwork arrangement using shoring towers A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 51
  • 52. Arrangement of shoring towers in plan for slab and beam formwork A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 52
  • 53. Sectional view of formwork arrangement using shoring towers A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 53
  • 54. Sectional view of shoring towers for slab and beam formwork A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 54
  • 55. Beam formwork supported on shoring tower A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 55
  • 56. Scaffolds Possible causes for collapse of scaffold systems. • Construction load exceeding the critical load of the scaffold system. • Horizontal instability • Diagonal bracing not being used in the scaffold. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 56
  • 57. Scaffolds Safety • Scaffold should be braced by means of longitudinal and transverse bracing systems so as to form a rigid and stable structure. • Install additional ties to the scaffold to prevent overturning and collapse. • Guide rails and toe boards must be provided. • All working platforms should be fully covered to prevent materials falling. • Safety nets and other screens should be provided. • Care should be taken to see that no uninsulated wire exists within 3 m of the working platforms gangways etc. • Men should not be allowed on scaffolds during storms and high winds. • Grease, mud, paint etc should be removed from the scaffolds. • All projecting nails from the platforms or other members should be removed. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 57
  • 58. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 58 FAILURE OF FORMWORK
  • 59. Reasons for failure of Formwork • Not designed for specific purpose. • Improper stripping or shoring removal (cantilever). • Not designed for horizontal thrust. • Damaged elements .(span weld, broken u clamps • Inadequate bracing. • Vibration (passing traffic). • Unstable soil under the props, Sole plates. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 59
  • 60. Failure of Formwork • The problem with formwork is that it is ‘temporary’ • The word temporary is associated with lack of need for : • Design • Planning • Care • Strength • Safety A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 60
  • 61. Reasons for failure of Formwork • Shoring not plumb. • Rate of concreting. • On site modifications due to site conditions. • When formwork is not at fault. • Ingress of water • Removal of wedges by workers. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 61
  • 62. Cantilever Place concrete into the beams first and the more towards the free end Strike / de-shutter in the direction opposite to that of concreting De-shuttering Concrete A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 62
  • 63. Sequence of Beams and Slabs Beam and Slab • Start with beams. • After beams start from beam more towards centre of slab. Precautions: • Don’t store large quantities of concrete at one place. • Spread concrete immediately. • Make sure that the scaffolding / staging is designed to take horizontal movement of the pipe. • Place from the centre and go towards the beams / supports. De-Shuttering Beams A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 63
  • 64. Sloping Slab Shuttering Double Shuttering • IS 1200 Part 5, Classification 5.1.D.ii. • Top shutter not payable. >300 Spacer Bottom Shutter Top Shutter A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 64
  • 65. Method of Measurement – IS 1200 • Method of measurement of building and Civil Engineering works – Part V Formwork : IS 1200 (Part V) 1982. • Code of practices for steel tubular scaffolding – II IS 4014 (Part 2) 1967. • Building and other construction workers (BOCW) act (Regulation of employment and conditions of service) Act 1996. Beam Column Depth of beam Beam A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. 65
  • 66. Specification writing for formwork 66 Points to be noted : • The loads and the lateral pressure, the maximum permitted deflection. • Instructions on formwork detailing and fabrication and guidelines on the required dimensions, the plumb, and the joints. • Instructions on supervision of the formwork activities. • Instruction on delivery, storage, protection and handling of the formwork materials. Acceptance criteria of the formwork materials. • Prior to commencement of the work, existing dimensions, elevations, locations and conditions applicable to the work shall be field verified. • Instruction on the time allowed between erection of the forms and placing of the concrete for the various trades to properly install their work. • Instruction on application of load on recently cast concrete. • Specifications for lumber, sheathing material, and shoring. Instruction on fabrication of form panels in conformity with the approved submittals. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD. Contd…
  • 67. Specification writing for formwork Points to be noted : • Specifications for formwork accessories, such as form ties, hangers, clamps, lugs, cones, washers, form liners or other devices. • Specifications for triangular fillets if applicable. • Instructions for cleaning and maintaining the form work materials. • Instruction on inspections for cleanliness and accuracy of the alignment prior to the placement of the concrete. • Instruction on location, snugness and tightness of joints. • Instruction on level of horizontal joints and plumb of vertical joints. • Location size and construction of openings. • Specification on expansion joint material, water stops, and other embedded items to be built in to the forms and the instructions on their placement and support against displacement. • Filling of voids in sleeves, inserts and anchor slots. Contd… 67A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
  • 68. Specification writing for formwork 68 Points to be noted : • Setting up of edge forms or bulkheads and intermediate screed strips for the slabs to obtain required elevations and contours in the finished slab surface. • Supervision for checking deviations from desired elevation, alignment, plumb and camber at the time of concreting. • Guidelines for taking remedial measures in case at the time of casting, weakness develops and the formwork shows settlement, deflection or distortion. • Specification on form coating material and instruction for their application. • Re-shoring, permissible loading on re-shores, timing of placement of re-shores, instruction on tightening of re-shores. • Guidelines for removal of forms, form ties and bracings to insure complete safety to the structure. A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.
  • 69. Thank You 69 A. N. PRAKASH CONSTRUCTION PROJECT MANAGEMENT CONSULTANTS PVT. LTD.