SlideShare a Scribd company logo
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
ROI Case Study 2
Paper Mill Grows RCM Program
with Savings Developed from IR
Window Program
By Martin Robinson, CMRP Level III Thermographer President, IRISS Inc.
18-1034-0002 Rev. A
Overview:
A paper mill in Georgia had run a very successful infrared inspection program for a number of years via
a local contract thermographers working with the mill’s in-house electricians. Although the program
had a good track record, senior management was concerned about the potential impact that NFPA 70E
requirements, and how best to comply with them. The plant commissioned IRISS, Inc. to complete a cost
benefit analysis and present its recommendations.
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Analysis of Inspection Program
The annual infrared surveys focused on the power distribution equipment as detailed in Table 1.
Twelve of the twenty-seven pieces of 13.8kV primary switchgear were not included during the inspection
due to switched interlocks (which automatically de-energize the equipment upon opening). In addition,
the thermographer was unable to inspect eight HV (high voltage) transformer cable compartments
under load due to the energized work restrictions implemented by the plant safety manager. The review
showed that 11% of the plant’s critical assets were never inspected during the annual survey.
A time study was completed detailing the man-hours and the costs involved in completing the annual IR
inspection based on NFPA and OSHA safety mandates.
Cost Analysis of Traditional Inspection
The client had been using a contract thermography company for more than seven years, and it was
very happy with the service. The scanning crew consisted of two in-house electricians and one contact
thermographer. The hourly wrench time (time spent on productive labor) rate for the electricians were
calculated at $68 per hour, and the contract thermographer’s rate was $150 per hour ($1,200 per day).
Traditionally, the whole inspection required 29 days to complete. This translated into 787 billable hours
(as seen in table 2).
Table 1
Application Total Qty Qty Insp
13.8 kV Primary Switch 27 15
Secondary Switchgear 48 48
Transformers (13.8kV) 22 14
MCC’s 50 50
Miscellaneous Switchgear 26 26
Generators 6 6
Total Assemblies 179 159
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Table 2
Man
Hours
Total Assemblies 159
Inspection Compartments 233
PPE Suit-Up Time 88.0
Time Taken to Remove Covers 0.4 Hrs 186.4
Time Taken for IR Inspection 0.2 Hrs 46.6
Time Taken to Replace Covers 0.4 Hrs 186.4
Electrician Waiting Time 93.2
Thermographer Waiting Time 186.4
Total Billable Man Hours 787.0
The entire inspection team dressed in 40 Cal/cm2 PPE (personal protective equipment) in accordance
with NFPA 70E and OSHA mandates for energized work. They spent on average 30 minutes to suit-up
and dress-down - twice a day. This was a total of 88 hours related to PPE over a 29-day inspection cycle.
The thermographer spent 186.4 hours waiting for panel covers to be opened/closed to provide him with
access. Similarly, the electricians spent 93.2 hours (46.6 hours x two men) waiting for the thermographer
to complete his work once the panels were removed.
After analyzing the time studies, facility management was surprised to learn that a staggering 367.6
hours (46.7%) of the total project time for the traditional open-panel surveys was non-productive (PPE
suit-up, thermographer wait-time, electrician wait-time, etc.). A task breakdown is shown in Table 2.
Table 2 details the man-hour costs for the infrared survey using a contract thermographer – without
infrared windows or viewports. The following assumptions are made:
•	 Total man-hours per inspection of “inspectable” equipment: 787 hours (29 days)
•	 Staff electrician internal charge-out rate $68 per hour
•	 Contract thermographer charge-out rate $150 per hour
•	 PPE suit-up twice daily, per man (30 minutes per man, per suit-up)
•	 48 minutes per compartment panel for safe removal, refitting, (per man for a two-man team)
•	 12 minutes per panel for infrared scan
•	 233 individual panels to inspect (Table 2)
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Infrared Windows
In search for an alternative approach that was both safer and standard-compliant, the corporate
reliability engineer investigated how infrared inspection windows (commonly referred to as IR
windows, viewports or sight glasses) might be utilized. It was determined that:
•	 Use of IR windows would provide non-intrusive access to electrical applications. Surveys 	
	 could be conducted during periods of peak load without elevating risk to either plant 	
	 assets or processes.
•	 Use of IR windows or “sightglasses” would eliminate the need for a supporting cast of 	
	 electricians to remove and reinstall panel covers. These critical personnel would then be 	
	 available to perform other tasks which were often being outsourced.
•	 Use of IR windows and closed-panel inspection would eliminate high-risk tasks during 	
	 inspections, thereby increasing safety for thermographers.
•	 Use of infrared windows for routine inspections of healthy equipment did not require the 	
	 elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating 	
	 conditions, enclosed energized equipment that has been properly installed and maintained 	
	 is not likely to pose an arc flash hazard.” In NFPA terms, an IR window maintains electrical 	
	 equipment in an “enclosed” state and it maintains energized components and circuit parts 	
	 in a “guarded” condition. Therefore, the hazard/risk category would be equivalent to 	
	 reading a panel meter, using a visual inspection pane for lockout/tag-out confirmations, or 	
	 walking past enclosed, energized equipment.
•	 Use of infrared windows would improve inspection efficiency. It would allow increases in 	
	 inspection frequency for those mission critical or suspect applications.
Table 3	
Total Cost of Traditional Inspection
Removal and Replacement of Panels	 373		 $25,316
Infrared Inspection 			 47		 $6,990
Electrician waiting Time			 94		 $6,329
Contract Thermographer Wait Time	 186		 $27,960
PPE Suit-up Time 			 87		 $8,324
Total 	 						 $74,919
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Investment
The facility’s 179 applications with 263 inspection compartments required 312 infrared inspection windows
(Table 4) in various sizes:
•	 143 units, two-inch diameter (VPFR-50)
•	 107 units, three-inch diameter (VPFR-75)
•	 62 units, four-inch diameter (VPFR-100)
The 312 windows represented an investment of $51,405.00. IRISS also provided a cost-benefit analysis
comparing in-house installation versus out-sourced.
Out-sourced installation (Table 5) was based on the following assumptions:
•	 A two-man installation team can comfortably install 40 inspection windows in one shift
•	 312 infrared inspection windows would require eight shifts to install completely (shutdowns 		
	permitting)
•	 The cost of the contract installation team was calculated as follows: eight days at $625 per 		
	 man, per day (total cost $1,300 per day) for a total of $10,400.00
•	 Installer would charge a flat $30 fee per window – in addition to the daily rate (312 windows x 	
	 $30 = $9,360)
•	 Total installation charge: $19,760
In-house costs (Table 6) were calculated using the following assumptions:
•	 A two-man team can comfortably install 40 inspection windows per shift
•	 312 infrared inspection windows would require eight shifts, or 128 man-hours, to install.
•	 The complete project could be managed around shutdowns.
•	 In-house team costs were calculated as follows: 128 man-hours at $68 per man/ per day for a 	
	 total cost of $8,893
•	 No additional charge incurred per window
•	 Client would retain IRISS for a day of on-site installation training at $995
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
With the savings, the client decided to use in-house manpower for the installation. The Jumpstart
Installation training was scheduled for the first day of the shutdown so the in-house electrical staff could
be properly trained.
Total savings to the customer by adopting an in-house installation program were $9,872.00 – almost a
14% savings over out-sourced.
Table 5
IR Window Supply & Contracted Installation Team
Infrared Windows 						$ 51,405
Install Costs for 312 IR Windows					 $ 19,760
Total								$ 71,165
Table 4
Application						 Quantity
13.8 kV Primary Switch						 27
Secondary Switchgear						 48
Transformers (13.8 kV)						 22
MCC's								 50
Miscellaneous Switchgear					 26
Generators							 6
Total Assemblies 						 179
Inspection Compartments					 263
IR Windows							 312
Table 6
IR Window Supply & Internal Installation Team
Infrared Windows 						$ 51,405
Install Costs for 312 IR Windows					 $ 8,893
Installers Training Course						$ 995
Total								$ 61,293
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
The Installation
The installation of the inspection panes was conducted during a seven-day shutdown, using two install
teams. The majority of the windows were installed while equipment was de-energized, in what NFPA
terms an “electrically safe work condition.” However, some involved energized gear using the traditional
safety measures such as use of PPE, energized work permits, etc. The work occurred during normal
business hours since this allowed more flexibility.
The plan called for two teams working a twelve-hour shift. Installers were quickly and safely working at
a rate of approximately six windows per hour. As they progressed down the learning curve, the teams
became more proficient, achieving an installation rate of 7 to 8 windows per hour (versus the budgeted
5).
Cost Analysis with Windows
With the infrared windows installed, there was no requirement to remove panels or wear increased levels
of PPE. In addition, inspections were now performed on the 11% of locations that had previously been
considered “uninspectable.” Finally, the entire task became a one-man job.
The windows also increased efficiency and economy-of-motion. Total man-hours to complete an
inspection dropped to just 53. As a result, the new survey dropped from almost $75,000 to just under
$8,000 (as detailed in Table 7). Because of the efficiencies achieved, the mill saves $68,964 per inspection,
a 92% savings.
Because of the efficiencies which they gain through the use of infrared windows, the paper mill saves
$68,964 per inspection cycle, representing a 92% savings compared to the costs of traditional inspections.
Table 7	
Total Cost of Inspection Using IR Windows
Inspection Time					53		$7,950
PPE Suit-up Time	 			 0		 $ 0.00
Total 								$7,950
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
ROI
Table 8 combines the data from the previous tables to illustrate the paper mill’s ROI (return on investment)
that the mill realized from its infrared window program. The table details the total investment using
three scenarios: 1) traditional open-panel inspections with a contract thermographer and two staff
electricians; 2) the same contractor using infrared windows; and 3) an in-house thermographer using
infrared inspection windows. It then compares the ROI that the mill was able to achieve using windows
and either a contract or in-house thermographer.
Switching to infrared windows is shown to pay dividends in just one inspection cycle. Over $5,600 in
savings can be put back into the budget by the end of the first cycle. After just five inspection cycles, the
mill shows a savings of over $273,542.
Plant management was encouraged by these projections, so they decided to invest in an infrared camera
and training for two of its engineers (one electrical and one mechanical). Two engineers were enrolled
in a Level I thermography course at $1,250 per man. An additional $1,500 per man was budgeted for
travel and expenses. The new camera totaled $8,000. The total investment to start up the new internal
inspection team was $13,500.
The cost of in-house inspection (47 hours x $68) amounted to $3,196 per inspection, yielding a savings
of $3,794 per inspection (or 54%) compared to a contractor.
ROI of the new program using internal resources was achieved within the second inspection cycle; by the
fifth cycle, the ROI was over $280,000. Because inspections can now be completed with greater ease and
without increased risk to plant personnel and processes, the mill increased the frequency to quarterly,
reflecting best-practice recommendations that originally were not considered feasible.
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Table8
Contractor
Traditional
Contractor
Windows
ROI
Contractor
Windowsvs.
Contractor
Traditional	
In-House
Windows
ROIIn-House
Windowsvs.
Contractor
Traditional	
ROIIn-House
Windowsvs.
Contractor
Windows
312Windows:One-Timeinvestment		None		$51,405				$51,405			
WindowInstallation:One-TimeInvestment	None		$9,898				$9,898			
IRTraining&Camera:One-TimeInvestment	None		None				$13,500			
LaborCosts:PerInspectionCycle			$74,919		$7,950		$66,969	$3,196		$71,723		$4,754
Investment:InspectionCycle1			$74,919		$69,253	$5,666		$77,999	$(3,080)		$(8,746)
Investment:InspectionCycle2			$149,838	$77,203	$72,635	$81,195		$68,643		$(3,992)
Investment:InspectionCycle3			$224,757	$85,153		$139,604	$84,391		$140,366	$762
Investment:InspectionCycle4			$299,676	$93,103		$206,573	$87,587	$212,089	$5,516
Investment:InspectionCycle5			$374,595	$101,053	$273,542	$90,783	$283,812	$10,270
5yr.Investment:QUARTERLYInspectionCycle	$1,498,380	$220,303	$1,278,077	$138,723	$1,359,657	$81,580
CaseStudy
PaperMill-Georgia
iriss.com
US : +1 (941) 907 9128
EMEA : +44 (0) 1245 399 713
APAC : +61 (0) 3 9872 3000
Conclusion
The new inspection process using infrared windows brought significant ROI to the plant in just one
quarter, while reducing the risk of catastrophic failure among the plant’s critical power distribution
systems.
Management succeeded in:
•	 Increasing safety
•	 Facilitating inspections of previously “uninspectable” equipment (11% of critical assets were not 	
	 inspected in the old program)
•	 Increasing the frequency of inspection - while saving money
•	 Safeguarding profitability by eliminating high-risk behavior that posed a risk to plant assets 		
	 and production
The purchase of the IR camera and training for the maintenance engineers quickly paid dividends. It
allowed the plant to improve the maintenance program while operating in full compliance with the
requirements of NFPA and OSHA.
An infrared window program provides a cost-effective and safer alternative to traditional open-panel
inspections. To learn more, visit www.iriss.com where you will find more case studies and white papers.
To learn more about infrared windows, Electrical Preventive
Maintenance, NFPA standards or electrical thermography
please visit www.iriss.com.
“10 Things You Need to Know About Infrared Windows”,
valued at $49.99, contains more information on the benefits
of IR windows. To get your free digital copy, Visit Us.
“10 Things You Need to Know About Infrared Windows”
Use of IRISS family Electrical Maintenance Safety Devices (EMSDs) such as infrared windows, ultrasound
ports, voltage detection ports and online monitoring, allow energized electrical maintenance tasks to
safely and efficiently be completed while switchgear enclosure remains closed.

More Related Content

What's hot

Greenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final OutlineGreenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final Outline
guest098cf2fe
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation Projects
Yokogawa1
 
Optimised control using Proportional-Integral-Derivative controller tuned usi...
Optimised control using Proportional-Integral-Derivative controller tuned usi...Optimised control using Proportional-Integral-Derivative controller tuned usi...
Optimised control using Proportional-Integral-Derivative controller tuned usi...
IJECEIAES
 
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
Sandia National Laboratories: Energy & Climate: Renewables
 
Automation of Eddy Current Processes for NDT
Automation of Eddy Current Processes for NDTAutomation of Eddy Current Processes for NDT
Automation of Eddy Current Processes for NDT
Zetec Inc.
 
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
IRJET Journal
 
Understanding Transmitter Seals Webinar
Understanding Transmitter Seals WebinarUnderstanding Transmitter Seals Webinar
Understanding Transmitter Seals Webinar
Yokogawa1
 
Aplication of on line data analytics to a continuous process polybetene unit
Aplication of on line data analytics to a continuous process polybetene unitAplication of on line data analytics to a continuous process polybetene unit
Aplication of on line data analytics to a continuous process polybetene unit
Emerson Exchange
 
Vibration Analysis
Vibration AnalysisVibration Analysis
Vibration Analysis
Sarafian Salleh
 
Solution: Long Seam Weld Inspection
Solution: Long Seam Weld InspectionSolution: Long Seam Weld Inspection
Solution: Long Seam Weld Inspection
Zetec Inc.
 
Identifying and Overcoming Noise in Data Acquisition
Identifying and Overcoming Noise in Data AcquisitionIdentifying and Overcoming Noise in Data Acquisition
Identifying and Overcoming Noise in Data Acquisition
Yokogawa1
 
AlLERT Life Cycle Sustainment.
AlLERT Life Cycle Sustainment.AlLERT Life Cycle Sustainment.
AlLERT Life Cycle Sustainment.
Mike Kellner
 
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest PresentationWestern Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
flukecontests
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
Emerson Exchange
 
Changing world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS ConsultingChanging world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS Consulting
NSW Environment and Planning
 

What's hot (19)

Pre commissioning
Pre commissioningPre commissioning
Pre commissioning
 
Greenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final OutlineGreenbelt Six Sigma Final Outline
Greenbelt Six Sigma Final Outline
 
vinayak_Resume_18112014
vinayak_Resume_18112014vinayak_Resume_18112014
vinayak_Resume_18112014
 
Key Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation ProjectsKey Considerations for Scoping Reinstrumentation Projects
Key Considerations for Scoping Reinstrumentation Projects
 
Optimised control using Proportional-Integral-Derivative controller tuned usi...
Optimised control using Proportional-Integral-Derivative controller tuned usi...Optimised control using Proportional-Integral-Derivative controller tuned usi...
Optimised control using Proportional-Integral-Derivative controller tuned usi...
 
Volume iii revised
Volume iii revisedVolume iii revised
Volume iii revised
 
374504b
374504b374504b
374504b
 
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
Optimizing Quality Assurance Inspections to Improve the Probability of Damage...
 
Automation of Eddy Current Processes for NDT
Automation of Eddy Current Processes for NDTAutomation of Eddy Current Processes for NDT
Automation of Eddy Current Processes for NDT
 
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
 
Understanding Transmitter Seals Webinar
Understanding Transmitter Seals WebinarUnderstanding Transmitter Seals Webinar
Understanding Transmitter Seals Webinar
 
Aplication of on line data analytics to a continuous process polybetene unit
Aplication of on line data analytics to a continuous process polybetene unitAplication of on line data analytics to a continuous process polybetene unit
Aplication of on line data analytics to a continuous process polybetene unit
 
Vibration Analysis
Vibration AnalysisVibration Analysis
Vibration Analysis
 
Solution: Long Seam Weld Inspection
Solution: Long Seam Weld InspectionSolution: Long Seam Weld Inspection
Solution: Long Seam Weld Inspection
 
Identifying and Overcoming Noise in Data Acquisition
Identifying and Overcoming Noise in Data AcquisitionIdentifying and Overcoming Noise in Data Acquisition
Identifying and Overcoming Noise in Data Acquisition
 
AlLERT Life Cycle Sustainment.
AlLERT Life Cycle Sustainment.AlLERT Life Cycle Sustainment.
AlLERT Life Cycle Sustainment.
 
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest PresentationWestern Iowa Tech Community College Fluke Connect Student Contest Presentation
Western Iowa Tech Community College Fluke Connect Student Contest Presentation
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
 
Changing world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS ConsultingChanging world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS Consulting
 

Viewers also liked

Assistive technology
Assistive technologyAssistive technology
Assistive technologylemonsb
 
Font
FontFont
Font
sigateam
 
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
Frédéric Houbert
 
Stem certification presentation
Stem certification presentationStem certification presentation
Stem certification presentation
Angela Ergle
 
HEAT PUMP BY ER SOHEL R SHEIKH
HEAT PUMP BY ER SOHEL R SHEIKHHEAT PUMP BY ER SOHEL R SHEIKH
HEAT PUMP BY ER SOHEL R SHEIKH
Er Sohel R Sheikh
 
AEROGEL
AEROGEL AEROGEL
Sludgehandlinganddisposal
SludgehandlinganddisposalSludgehandlinganddisposal
Sludgehandlinganddisposal
Er Sohel R Sheikh
 
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
Shutterstock
 
Chemical reaction engineering introduction by Er sohel R sheikh
Chemical reaction engineering introduction by Er sohel R sheikhChemical reaction engineering introduction by Er sohel R sheikh
Chemical reaction engineering introduction by Er sohel R sheikh
Er Sohel R Sheikh
 

Viewers also liked (16)

What is kpi report
What is kpi reportWhat is kpi report
What is kpi report
 
Website kpi
Website kpiWebsite kpi
Website kpi
 
CS003
CS003CS003
CS003
 
Assistive technology
Assistive technologyAssistive technology
Assistive technology
 
Font
FontFont
Font
 
What is kpi mean
What is kpi meanWhat is kpi mean
What is kpi mean
 
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
Le Black's Law Dictionary, monument de la lexicographie juridique - ATA 2010
 
Ssas kpi
Ssas kpiSsas kpi
Ssas kpi
 
Sample kpi
Sample kpiSample kpi
Sample kpi
 
Stem certification presentation
Stem certification presentationStem certification presentation
Stem certification presentation
 
HEAT PUMP BY ER SOHEL R SHEIKH
HEAT PUMP BY ER SOHEL R SHEIKHHEAT PUMP BY ER SOHEL R SHEIKH
HEAT PUMP BY ER SOHEL R SHEIKH
 
AEROGEL
AEROGEL AEROGEL
AEROGEL
 
Sludgehandlinganddisposal
SludgehandlinganddisposalSludgehandlinganddisposal
Sludgehandlinganddisposal
 
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
The Explorers Guide to Travel Photography & Destination Video (Whitepaper)
 
Chemical reaction engineering introduction by Er sohel R sheikh
Chemical reaction engineering introduction by Er sohel R sheikhChemical reaction engineering introduction by Er sohel R sheikh
Chemical reaction engineering introduction by Er sohel R sheikh
 
CS001
CS001CS001
CS001
 

Similar to CS002

Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVueEffective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
ABJ Drones
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
Ganesh TN
 
Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub
IRJET Journal
 
Solving the maintain vs. modernization equation
Solving the maintain vs. modernization equationSolving the maintain vs. modernization equation
Solving the maintain vs. modernization equation
Schneider Electric
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
Nidec Corporation
 
Power Performance Optimization using LiDAR technology : India Pilot Project R...
Power Performance Optimization using LiDAR technology : India Pilot Project R...Power Performance Optimization using LiDAR technology : India Pilot Project R...
Power Performance Optimization using LiDAR technology : India Pilot Project R...
Karim Fahssis 卡卡
 
Thermal Techniques Brochure
Thermal Techniques BrochureThermal Techniques Brochure
Thermal Techniques Brochure
Thermal Techniques
 
University of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
University of Kentucky Solar Car Team Fluke Connect Student Contest PresentationUniversity of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
University of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
flukecontests
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
IRJET Journal
 
F.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdfF.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdf
BalaBalaji45
 
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
Power System Operation
 
Condition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence TechniqueCondition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence Technique
ijsrd.com
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
Living Online
 
Fluke contest entry
Fluke contest entryFluke contest entry
Fluke contest entry
Chad Plante
 
Schneider plc
Schneider plcSchneider plc
Schneider plc
Ghadak Mohammad
 
S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016
CETN
 
A-ConMonIntro.ppt
A-ConMonIntro.pptA-ConMonIntro.ppt
A-ConMonIntro.ppt
veeruyadav9
 
NIGERIA GRID CODE
NIGERIA GRID CODE NIGERIA GRID CODE
NIGERIA GRID CODE
Power System Operation
 
The 5th Aslla Symposium
The 5th Aslla SymposiumThe 5th Aslla Symposium
The 5th Aslla Symposium
Wesley De Neve
 
CONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONCONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONIgnesias Tsotetsi
 

Similar to CS002 (20)

Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVueEffective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
Effective Drone Solar Farm Inspection with Thermal Imaging - ABJ SolarVue
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub Actual Time Online Thermal Mapping Of significant Components In Data Hub
Actual Time Online Thermal Mapping Of significant Components In Data Hub
 
Solving the maintain vs. modernization equation
Solving the maintain vs. modernization equationSolving the maintain vs. modernization equation
Solving the maintain vs. modernization equation
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
 
Power Performance Optimization using LiDAR technology : India Pilot Project R...
Power Performance Optimization using LiDAR technology : India Pilot Project R...Power Performance Optimization using LiDAR technology : India Pilot Project R...
Power Performance Optimization using LiDAR technology : India Pilot Project R...
 
Thermal Techniques Brochure
Thermal Techniques BrochureThermal Techniques Brochure
Thermal Techniques Brochure
 
University of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
University of Kentucky Solar Car Team Fluke Connect Student Contest PresentationUniversity of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
University of Kentucky Solar Car Team Fluke Connect Student Contest Presentation
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
F.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdfF.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdf
 
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
 
Condition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence TechniqueCondition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence Technique
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
 
Fluke contest entry
Fluke contest entryFluke contest entry
Fluke contest entry
 
Schneider plc
Schneider plcSchneider plc
Schneider plc
 
S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016S4 oman wind energy the technology 2016
S4 oman wind energy the technology 2016
 
A-ConMonIntro.ppt
A-ConMonIntro.pptA-ConMonIntro.ppt
A-ConMonIntro.ppt
 
NIGERIA GRID CODE
NIGERIA GRID CODE NIGERIA GRID CODE
NIGERIA GRID CODE
 
The 5th Aslla Symposium
The 5th Aslla SymposiumThe 5th Aslla Symposium
The 5th Aslla Symposium
 
CONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONCONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATION
 

More from Steve Willetts

Thermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical MaintenanceThermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical Maintenance
Steve Willetts
 

More from Steve Willetts (6)

Moog Case Study
Moog Case StudyMoog Case Study
Moog Case Study
 
Iris Presentation
Iris PresentationIris Presentation
Iris Presentation
 
Thermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical MaintenanceThermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical Maintenance
 
casestudy3indd
casestudy3inddcasestudy3indd
casestudy3indd
 
casestudy2indd
casestudy2inddcasestudy2indd
casestudy2indd
 
casestudy1indd
casestudy1inddcasestudy1indd
casestudy1indd
 

CS002

  • 1. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 ROI Case Study 2 Paper Mill Grows RCM Program with Savings Developed from IR Window Program By Martin Robinson, CMRP Level III Thermographer President, IRISS Inc. 18-1034-0002 Rev. A Overview: A paper mill in Georgia had run a very successful infrared inspection program for a number of years via a local contract thermographers working with the mill’s in-house electricians. Although the program had a good track record, senior management was concerned about the potential impact that NFPA 70E requirements, and how best to comply with them. The plant commissioned IRISS, Inc. to complete a cost benefit analysis and present its recommendations.
  • 2. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Analysis of Inspection Program The annual infrared surveys focused on the power distribution equipment as detailed in Table 1. Twelve of the twenty-seven pieces of 13.8kV primary switchgear were not included during the inspection due to switched interlocks (which automatically de-energize the equipment upon opening). In addition, the thermographer was unable to inspect eight HV (high voltage) transformer cable compartments under load due to the energized work restrictions implemented by the plant safety manager. The review showed that 11% of the plant’s critical assets were never inspected during the annual survey. A time study was completed detailing the man-hours and the costs involved in completing the annual IR inspection based on NFPA and OSHA safety mandates. Cost Analysis of Traditional Inspection The client had been using a contract thermography company for more than seven years, and it was very happy with the service. The scanning crew consisted of two in-house electricians and one contact thermographer. The hourly wrench time (time spent on productive labor) rate for the electricians were calculated at $68 per hour, and the contract thermographer’s rate was $150 per hour ($1,200 per day). Traditionally, the whole inspection required 29 days to complete. This translated into 787 billable hours (as seen in table 2). Table 1 Application Total Qty Qty Insp 13.8 kV Primary Switch 27 15 Secondary Switchgear 48 48 Transformers (13.8kV) 22 14 MCC’s 50 50 Miscellaneous Switchgear 26 26 Generators 6 6 Total Assemblies 179 159
  • 3. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Table 2 Man Hours Total Assemblies 159 Inspection Compartments 233 PPE Suit-Up Time 88.0 Time Taken to Remove Covers 0.4 Hrs 186.4 Time Taken for IR Inspection 0.2 Hrs 46.6 Time Taken to Replace Covers 0.4 Hrs 186.4 Electrician Waiting Time 93.2 Thermographer Waiting Time 186.4 Total Billable Man Hours 787.0 The entire inspection team dressed in 40 Cal/cm2 PPE (personal protective equipment) in accordance with NFPA 70E and OSHA mandates for energized work. They spent on average 30 minutes to suit-up and dress-down - twice a day. This was a total of 88 hours related to PPE over a 29-day inspection cycle. The thermographer spent 186.4 hours waiting for panel covers to be opened/closed to provide him with access. Similarly, the electricians spent 93.2 hours (46.6 hours x two men) waiting for the thermographer to complete his work once the panels were removed. After analyzing the time studies, facility management was surprised to learn that a staggering 367.6 hours (46.7%) of the total project time for the traditional open-panel surveys was non-productive (PPE suit-up, thermographer wait-time, electrician wait-time, etc.). A task breakdown is shown in Table 2. Table 2 details the man-hour costs for the infrared survey using a contract thermographer – without infrared windows or viewports. The following assumptions are made: • Total man-hours per inspection of “inspectable” equipment: 787 hours (29 days) • Staff electrician internal charge-out rate $68 per hour • Contract thermographer charge-out rate $150 per hour • PPE suit-up twice daily, per man (30 minutes per man, per suit-up) • 48 minutes per compartment panel for safe removal, refitting, (per man for a two-man team) • 12 minutes per panel for infrared scan • 233 individual panels to inspect (Table 2)
  • 4. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Infrared Windows In search for an alternative approach that was both safer and standard-compliant, the corporate reliability engineer investigated how infrared inspection windows (commonly referred to as IR windows, viewports or sight glasses) might be utilized. It was determined that: • Use of IR windows would provide non-intrusive access to electrical applications. Surveys could be conducted during periods of peak load without elevating risk to either plant assets or processes. • Use of IR windows or “sightglasses” would eliminate the need for a supporting cast of electricians to remove and reinstall panel covers. These critical personnel would then be available to perform other tasks which were often being outsourced. • Use of IR windows and closed-panel inspection would eliminate high-risk tasks during inspections, thereby increasing safety for thermographers. • Use of infrared windows for routine inspections of healthy equipment did not require the elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating conditions, enclosed energized equipment that has been properly installed and maintained is not likely to pose an arc flash hazard.” In NFPA terms, an IR window maintains electrical equipment in an “enclosed” state and it maintains energized components and circuit parts in a “guarded” condition. Therefore, the hazard/risk category would be equivalent to reading a panel meter, using a visual inspection pane for lockout/tag-out confirmations, or walking past enclosed, energized equipment. • Use of infrared windows would improve inspection efficiency. It would allow increases in inspection frequency for those mission critical or suspect applications. Table 3 Total Cost of Traditional Inspection Removal and Replacement of Panels 373 $25,316 Infrared Inspection 47 $6,990 Electrician waiting Time 94 $6,329 Contract Thermographer Wait Time 186 $27,960 PPE Suit-up Time 87 $8,324 Total $74,919
  • 5. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Investment The facility’s 179 applications with 263 inspection compartments required 312 infrared inspection windows (Table 4) in various sizes: • 143 units, two-inch diameter (VPFR-50) • 107 units, three-inch diameter (VPFR-75) • 62 units, four-inch diameter (VPFR-100) The 312 windows represented an investment of $51,405.00. IRISS also provided a cost-benefit analysis comparing in-house installation versus out-sourced. Out-sourced installation (Table 5) was based on the following assumptions: • A two-man installation team can comfortably install 40 inspection windows in one shift • 312 infrared inspection windows would require eight shifts to install completely (shutdowns permitting) • The cost of the contract installation team was calculated as follows: eight days at $625 per man, per day (total cost $1,300 per day) for a total of $10,400.00 • Installer would charge a flat $30 fee per window – in addition to the daily rate (312 windows x $30 = $9,360) • Total installation charge: $19,760 In-house costs (Table 6) were calculated using the following assumptions: • A two-man team can comfortably install 40 inspection windows per shift • 312 infrared inspection windows would require eight shifts, or 128 man-hours, to install. • The complete project could be managed around shutdowns. • In-house team costs were calculated as follows: 128 man-hours at $68 per man/ per day for a total cost of $8,893 • No additional charge incurred per window • Client would retain IRISS for a day of on-site installation training at $995
  • 6. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 With the savings, the client decided to use in-house manpower for the installation. The Jumpstart Installation training was scheduled for the first day of the shutdown so the in-house electrical staff could be properly trained. Total savings to the customer by adopting an in-house installation program were $9,872.00 – almost a 14% savings over out-sourced. Table 5 IR Window Supply & Contracted Installation Team Infrared Windows $ 51,405 Install Costs for 312 IR Windows $ 19,760 Total $ 71,165 Table 4 Application Quantity 13.8 kV Primary Switch 27 Secondary Switchgear 48 Transformers (13.8 kV) 22 MCC's 50 Miscellaneous Switchgear 26 Generators 6 Total Assemblies 179 Inspection Compartments 263 IR Windows 312 Table 6 IR Window Supply & Internal Installation Team Infrared Windows $ 51,405 Install Costs for 312 IR Windows $ 8,893 Installers Training Course $ 995 Total $ 61,293
  • 7. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 The Installation The installation of the inspection panes was conducted during a seven-day shutdown, using two install teams. The majority of the windows were installed while equipment was de-energized, in what NFPA terms an “electrically safe work condition.” However, some involved energized gear using the traditional safety measures such as use of PPE, energized work permits, etc. The work occurred during normal business hours since this allowed more flexibility. The plan called for two teams working a twelve-hour shift. Installers were quickly and safely working at a rate of approximately six windows per hour. As they progressed down the learning curve, the teams became more proficient, achieving an installation rate of 7 to 8 windows per hour (versus the budgeted 5). Cost Analysis with Windows With the infrared windows installed, there was no requirement to remove panels or wear increased levels of PPE. In addition, inspections were now performed on the 11% of locations that had previously been considered “uninspectable.” Finally, the entire task became a one-man job. The windows also increased efficiency and economy-of-motion. Total man-hours to complete an inspection dropped to just 53. As a result, the new survey dropped from almost $75,000 to just under $8,000 (as detailed in Table 7). Because of the efficiencies achieved, the mill saves $68,964 per inspection, a 92% savings. Because of the efficiencies which they gain through the use of infrared windows, the paper mill saves $68,964 per inspection cycle, representing a 92% savings compared to the costs of traditional inspections. Table 7 Total Cost of Inspection Using IR Windows Inspection Time 53 $7,950 PPE Suit-up Time 0 $ 0.00 Total $7,950
  • 8. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 ROI Table 8 combines the data from the previous tables to illustrate the paper mill’s ROI (return on investment) that the mill realized from its infrared window program. The table details the total investment using three scenarios: 1) traditional open-panel inspections with a contract thermographer and two staff electricians; 2) the same contractor using infrared windows; and 3) an in-house thermographer using infrared inspection windows. It then compares the ROI that the mill was able to achieve using windows and either a contract or in-house thermographer. Switching to infrared windows is shown to pay dividends in just one inspection cycle. Over $5,600 in savings can be put back into the budget by the end of the first cycle. After just five inspection cycles, the mill shows a savings of over $273,542. Plant management was encouraged by these projections, so they decided to invest in an infrared camera and training for two of its engineers (one electrical and one mechanical). Two engineers were enrolled in a Level I thermography course at $1,250 per man. An additional $1,500 per man was budgeted for travel and expenses. The new camera totaled $8,000. The total investment to start up the new internal inspection team was $13,500. The cost of in-house inspection (47 hours x $68) amounted to $3,196 per inspection, yielding a savings of $3,794 per inspection (or 54%) compared to a contractor. ROI of the new program using internal resources was achieved within the second inspection cycle; by the fifth cycle, the ROI was over $280,000. Because inspections can now be completed with greater ease and without increased risk to plant personnel and processes, the mill increased the frequency to quarterly, reflecting best-practice recommendations that originally were not considered feasible.
  • 9. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Table8 Contractor Traditional Contractor Windows ROI Contractor Windowsvs. Contractor Traditional In-House Windows ROIIn-House Windowsvs. Contractor Traditional ROIIn-House Windowsvs. Contractor Windows 312Windows:One-Timeinvestment None $51,405 $51,405 WindowInstallation:One-TimeInvestment None $9,898 $9,898 IRTraining&Camera:One-TimeInvestment None None $13,500 LaborCosts:PerInspectionCycle $74,919 $7,950 $66,969 $3,196 $71,723 $4,754 Investment:InspectionCycle1 $74,919 $69,253 $5,666 $77,999 $(3,080) $(8,746) Investment:InspectionCycle2 $149,838 $77,203 $72,635 $81,195 $68,643 $(3,992) Investment:InspectionCycle3 $224,757 $85,153 $139,604 $84,391 $140,366 $762 Investment:InspectionCycle4 $299,676 $93,103 $206,573 $87,587 $212,089 $5,516 Investment:InspectionCycle5 $374,595 $101,053 $273,542 $90,783 $283,812 $10,270 5yr.Investment:QUARTERLYInspectionCycle $1,498,380 $220,303 $1,278,077 $138,723 $1,359,657 $81,580
  • 10. CaseStudy PaperMill-Georgia iriss.com US : +1 (941) 907 9128 EMEA : +44 (0) 1245 399 713 APAC : +61 (0) 3 9872 3000 Conclusion The new inspection process using infrared windows brought significant ROI to the plant in just one quarter, while reducing the risk of catastrophic failure among the plant’s critical power distribution systems. Management succeeded in: • Increasing safety • Facilitating inspections of previously “uninspectable” equipment (11% of critical assets were not inspected in the old program) • Increasing the frequency of inspection - while saving money • Safeguarding profitability by eliminating high-risk behavior that posed a risk to plant assets and production The purchase of the IR camera and training for the maintenance engineers quickly paid dividends. It allowed the plant to improve the maintenance program while operating in full compliance with the requirements of NFPA and OSHA. An infrared window program provides a cost-effective and safer alternative to traditional open-panel inspections. To learn more, visit www.iriss.com where you will find more case studies and white papers. To learn more about infrared windows, Electrical Preventive Maintenance, NFPA standards or electrical thermography please visit www.iriss.com. “10 Things You Need to Know About Infrared Windows”, valued at $49.99, contains more information on the benefits of IR windows. To get your free digital copy, Visit Us. “10 Things You Need to Know About Infrared Windows” Use of IRISS family Electrical Maintenance Safety Devices (EMSDs) such as infrared windows, ultrasound ports, voltage detection ports and online monitoring, allow energized electrical maintenance tasks to safely and efficiently be completed while switchgear enclosure remains closed.