SlideShare a Scribd company logo
1 of 7
Download to read offline
CaseStudy
PowerGeneration
Power Generation ROI
A Powerful Case for
Infrared Windows
By Martin Robinson, CMRP Level III Thermographer CEO, IRISS, Inc.
18-1034-0003 Rev. A
Overview:
A regional Power Generation Facility had been tasked by their insurance carrier to perform regular
preventive maintenance on the switchgear within their facility. Unfortunately, regular downtime was
not a practical option for them as the processes required to do the live inspections were hazardous and
required more manpower and resources than they had to provide. In addition, they too were feeling the
pressure of the requirements of NFPA 70E and were starting to re-think their strategy since inspections of
energized equipment was becoming more restrictive, more time consuming and more costly.
CaseStudy
PowerGeneration
The insurance carrier had done the necessary research and determined that the facility should
consider Infrared windows as an alternative method of conducting safer, standards-compliant
inspections and it was determined that a reduction in hazard liability and maintenance costs could
be attained through:
•	 Use of Infrared Windows for routine inspections of healthy equipment did not require the 	
	 elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating 	
	 conditions, enclosed energized equipment that has been properly installed and maintained 	
	 is not likely to pose an arc flash hazard.”
•	 Maintaining an “enclosed” state for the switchgear, MCC, Transformer, etc., and maintains 	
	 energized components and circuit parts in a “guarded” condition, in NFPA terms.  	 	
	 Therefore, the hazard/risk category would be equal to that of reading a panel meter, 	
	 using a visual inspection pane for lockout/tagout confirmations, or walking past enclosed, 	
	 energized equipment and could even be conducted during peak hours for best diagnostic 	
	data.
• 	 Use of IR windows would eliminate the need for a supporting cast of electricians to remove 	
	 and reinstall panel covers.
• 	 Allowing critical personnel to then be available to perform other tasks which were often 	
	 being outsourced.
•	 Providing the ability to perform more frequent inspections feasible for critical or suspect 	
	 applications to ensure plant uptime and appease the insurance carrier of the reduced 	
	 insurance liabilities.
The focus was to facilitate inspection of the primary switchgear in their electrical distribution system
and several smaller operations within the plant. An impending shutdown increased the sense of
urgency since all Phase I installation could be fitted during that period.
Table 1
Application				 Total Qty.	 Qty. lnsp
Primary Switch		 		 15	 0
Secondary Switchgear			 23 		 19
Transformers 				 15		 0
MCC's					 24		 24
Miscellaneous Switchgear		 8			 8
Generators				 10		 10
Total Assemblies				 95		 61
Investment
A pre-site inspection by IRISS was performed to ascertain the optimal position and quantity of windows
which would give thermographers thorough visibility of desired targets. Previously, none of the primary
CaseStudy
PowerGeneration
switchgear or transformers had been included in the sites inspections due to the inherent safety hazards
associated with their being safely inspected while energized. The review showed that some of the plant’s
critical assets were never inspected during the annual survey. The primary goal of Phase I was to bring
this equipment into the standard inspection routes. A time study was completed detailing the man-
hours and the costs involved in completing Phase I of the IR window installation allowing the inspections
to be completed in line with NFPA and OSHA safety mandates.
Typical Cost Analysis of Standard Inspection
The client had been using a contract thermography company for some time and the survey crew
consisted of two in-house electricians and one contact thermographer.
The hourly wrench time (time spent on productive labor) rate for the electrician was calculated at $62,
and the contract thermographer’s rate was $150 per hour ($1,200 a day). Typically, the equipment being
considered for Phase I window retrofitting would require 19 days to complete. This translated into 497.7
billable hours (as shown in Table 2).
The entire inspection team dressed in 40 Cal/cm2 PPE (personal protective equipment) in accordance
with NFPA 70E and OSHA mandates for energized work. They spent on average 30 minutes to suit-up
and dress-down - twice a day. This was a total of 88 hours related to PPE over a 19-day cycle.
The thermographer spent 186.4 hours waiting for panel covers to be opened/closed to provide him with
access. Similarly, the electricians spent 58.8 hours (29.4 hours x two men) waiting for the thermographer
to complete his work once the panels were removed.
After analyzing the time studies, facility management was surprised to learn that a staggering 468.3
hours (94%) of the total project time for the traditional open-panel surveys was non-productive (PPE
suit-up, thermographer wait-time, electrician wait-time, etc.)  The task breakdown is reflected within
Table 2.
Table 2 	
							 Man-Hours
Total Assemblies				 95
Inspection Compartments		 147
PPE Suit-up Time			 0.5 Hrs.			 57.0
Time Taken to Remove Covers		 0.4 Hrs.			 117.6
Time Taken for IR Inspection 		 0.2 Hrs.			 29.4
Time Taken to Replace Covers		 0.4 Hrs 		 117.6
Electrician Waiting Time						58.8
Thermographer Waiting Time 					117.6
Total Billable Man-Hours 						497.7
Unproductive Man-Hours					468.3
CaseStudy
PowerGeneration
Table 3 details the man-hour costs for the infrared survey using a contract thermographer without
infrared windows or viewports. The following assumptions are made:
• 	 Total man-hours per inspection of “inspectable” equipment: 497.7 hours (19 days)
• 	 Staff electrician internal charge-out rate $62 per hour
•	 Contract thermographer charge-out rate $150 per hour
• 	 PPE suit-up twice daily, per man (30 minutes per man, per suit-up)
• 	 48 minutes per compartment panel for safe removal, refitting (per man for a two-man team)
• 	 12 minutes per panel for infrared scan.
• 	 147 individual panels to inspect (Table2)
Table 3
Total Cost of Traditional Inspection:
Removal and Replacement of Panels		 235.2		 $ 4,582
Infrared Inspection 				 29.4		 $ 4,410
Electrician Wait-Time 				 58.8		 $ 3,646
Contract Thermographer Wait-Time		 117.6 		 $ 17,640
PPE Suit-up Time				 57		 $ 5,206
Total 		 	 					 $ 45,484
Infrared Windows
In search for an alternative approach that was both safer and standards-compliant, the corporate
reliability engineer investigated how infrared inspection windows (commonly referred to as IR windows,
viewports or sight glasses) might be utilized. It was determined that:
• 	 Use of IR windows would provide non-intrusive access to electrical applications. Surveys could 	
	 be conducted during periods of peak-load without elevating risk to either plant assets or 		
	processes.
• 	 Use of IR windows would eliminate the need for a supporting cast of electricians to remove 		
	 and reinstall panel covers. These critical personnel would then be available to perform other 	
	 tasks which were often being outsourced.
• 	 Use of IR windows and closed-panel inspection would eliminate high-risk tasks during 		
	 inspections – increasing safety for thermographers.
• 	 Use of infrared windows for routine inspections of healthy equipment did not require the 		
	 elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating 		
	 conditions, enclosed energized equipment that has been properly installed and maintained is 	
	 not likely to pose an arc flash hazard.”
•	 In NFPA terms, an IR window maintains electrical equipment in an “enclosed” state and 	 	
	 it maintains energized components and circuit parts in a “guarded” condition.  Therefore, the 	
	 hazard/risk category would be equivalent to reading a panel meter, using a visual inspection
CaseStudy
PowerGeneration
	 pane for lockout/tag-out confirmation, or walking past enclosed, energized equipment.
•	 Use of infrared windows would improve inspection efficiency. It would allow increases in 	 	
	 inspection frequency for those mission critical or suspect applications.
Investment
The 203 installed IRISS infrared windows represented an investment of $48,841.00. IRISS, Inc. also
provided a cost benefit analysis comparing in-house installation versus outsourced (Table 4). The facility’s
95 applications with 147 inspection compartments required 203 infrared inspection windows (Table 5).
Table 4
IR Window Supply & Contracted Installation Team
Infrared Windows						$36,255
Install Costs for 203 IR Windows					 $12,586
Total 								$48,841
Table 5
Application						 Quantity
Primary Switch 							 15
Secondary Switchgear 						 23
Transformers 							 15
MCC’s 								 24
Miscellaneous Switchgear 					 8
Generators 							 10
Total Assemblies 						 95
Inspection Compartments 					 147
IR Windows							 203
The Installation
The installation of the inspection panes was conducted during a shutdown, using two install teams.
The majority of the windows were installed while equipment was de-energized, in what NFPA terms
an “electrically safe work condition.”  However, some installations involved energized gear and needed
to employ the traditional safety measures such as use of PPE, energized work permits, etc. The work
occurred during normal business hours since this allowed more flexibility.
CaseStudy
PowerGeneration
Cost Analysis with Windows
With the infrared windows installed, there was no requirement to remove panels or wear increased levels
of PPE. In addition, inspections were now performed on their applications that had previously been
considered “un-inspectable.”  Finally, the entire task became a one-man job.
The windows also increased efficiency and economy-of-motion.   Total man-hours to complete an
inspection dropped to just 33. As a result, the new survey dropped from almost $45,484 to just under
$4,950 (as detailed in Table 6).
Table 6
Total Cost of Inspection 	 Using IR	 Windows
Inspection Time 				 33 		 $4,950
PPE Suit-up Time 			 0 			 $0.00
Total 								$4,950
Because of the efficiencies achieved, the facility saves $40,534 per inspection – that’s a savings greater
than 90%.
ROI
Table 7 combines the data from the previous tables to illustrate the ROI (return on investment) that
the facility realized from Phase I of its infrared window program. The table details the total investment
using 2 scenarios: 1) Traditional open-panel inspections with a contract thermographer and two staff
electricians; 2) the same contractor using infrared windows.
Switching to infrared windows is shown to pay dividends in just two inspection cycles. Over $33,227 in
savings can be put back into the budget by the end of the second cycle.
After just five inspection cycles, the facility shows a savings of over $153,829.  
Because inspections can now be completed with greater ease and without increased risk to plant,
personnel and processes, the facility increased the frequency of inspections to quarterly, reflecting best-
practice recommendations that originally were not considered feasible.
CaseStudy
PowerGeneration
Conclusion
The new inspection process using infrared windows brought significant ROI to the plant in just two
inspection cycles, while reducing the risk of catastrophic failure among the plant’s critical power
distribution systems.
Management succeeded in:
•	 Increasing safety
•	 Facilitating inspections of previously “un-inspectable” equipment
•	 Increasing the frequency of inspection – while saving money
•	 Safeguarding profitability by eliminating high-risk behavior that posed a risk to plant assets 		
	 and production
In the future the facility is planning to purchase its own IR camera and training for the maintenance
engineers, which will quickly pay dividends and allow the plant to improve the maintenance program
while operating in full compliance with the requirements of NFPA and OSHA.
An infrared window program provides a cost-effective and safer alternative to traditional open-panel
inspections.  To learn more, visit www.iriss.com where you will find the FREE ROI calculator, case studies
and white papers.
To learn more about infrared windows, Electrical Preventive
Maintenance, NFPA standards or electrical thermography
please visit www.iriss.com.
“10 Things You Need to Know About Infrared Windows”
contains more information on the benefits of IR windows. To
get your free digital copy, Click Here.
Interested in IRISS IR Window Solutions? Click Here
“10 Things You Need to Know About Infrared Windows”

More Related Content

What's hot

CONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONCONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONIgnesias Tsotetsi
 
Damage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsDamage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsMarcep Inc.
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisAnas Momen
 
Trp reliability presentation 2
Trp reliability presentation 2 Trp reliability presentation 2
Trp reliability presentation 2 trpservices1
 
Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control managerMary Claire Simoneaux
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyDesign World
 
An Introduction to Condition Based Maintenance (CBM)
An Introduction to  Condition Based Maintenance (CBM)An Introduction to  Condition Based Maintenance (CBM)
An Introduction to Condition Based Maintenance (CBM)abasathab
 
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...Cairn India Limited
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements360factors
 
Octavis Vibration Monitor Brochure
Octavis Vibration Monitor BrochureOctavis Vibration Monitor Brochure
Octavis Vibration Monitor Brochureifm electronic gmbh
 
Pa pdf-output-specs-section-c9-biomedical-engineering-final-no
Pa pdf-output-specs-section-c9-biomedical-engineering-final-noPa pdf-output-specs-section-c9-biomedical-engineering-final-no
Pa pdf-output-specs-section-c9-biomedical-engineering-final-noRyan Tansa T Wardhana
 
Case study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionCase study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionJohn Kingsley
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurementsEmerson Exchange
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editorseldhoev
 

What's hot (20)

CONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATIONCONDITION BASED MONITORING PRESENTATION
CONDITION BASED MONITORING PRESENTATION
 
Damage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsDamage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipments
 
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects AnalysisPoster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
Poster_EGY_TE_Anas Momen_Hilal-Failure Modes and Effects Analysis
 
Trp reliability presentation 2
Trp reliability presentation 2 Trp reliability presentation 2
Trp reliability presentation 2
 
Change your board operator to a process control manager
Change your board operator to a process control managerChange your board operator to a process control manager
Change your board operator to a process control manager
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
 
An Introduction to Condition Based Maintenance (CBM)
An Introduction to  Condition Based Maintenance (CBM)An Introduction to  Condition Based Maintenance (CBM)
An Introduction to Condition Based Maintenance (CBM)
 
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...Critical Review of  PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
Critical Review of PSM In Petroleum Industry | Mr. Hirak Dutta, Executive Di...
 
TRP
TRPTRP
TRP
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
 
Octavis Vibration Monitor Brochure
Octavis Vibration Monitor BrochureOctavis Vibration Monitor Brochure
Octavis Vibration Monitor Brochure
 
Pa pdf-output-specs-section-c9-biomedical-engineering-final-no
Pa pdf-output-specs-section-c9-biomedical-engineering-final-noPa pdf-output-specs-section-c9-biomedical-engineering-final-no
Pa pdf-output-specs-section-c9-biomedical-engineering-final-no
 
Why SIL3 (ENG)
Why SIL3 (ENG)Why SIL3 (ENG)
Why SIL3 (ENG)
 
Case study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during executionCase study of dcs upgrade how to reduce stress during execution
Case study of dcs upgrade how to reduce stress during execution
 
Control using wireless measurements
Control using wireless measurementsControl using wireless measurements
Control using wireless measurements
 
CI_SCS_Intro
CI_SCS_IntroCI_SCS_Intro
CI_SCS_Intro
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editors
 
HIPPS
HIPPSHIPPS
HIPPS
 
Pre commissioning
Pre commissioningPre commissioning
Pre commissioning
 

Similar to CS003

AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304Niels Inderbiethen
 
Wuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionWuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionJoel Gil
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansLiving Online
 
F.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdfF.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdfBalaBalaji45
 
Productivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching ProcessProductivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching Processidescitation
 
Energy Auditing.pptx
Energy Auditing.pptxEnergy Auditing.pptx
Energy Auditing.pptxMoaz27
 
Infrared inspection power point
Infrared inspection power pointInfrared inspection power point
Infrared inspection power pointCharles Russell
 
Condition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence TechniqueCondition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence Techniqueijsrd.com
 
Planned Preventive Ambulance Medical Equipment Maintenance
Planned Preventive Ambulance Medical Equipment MaintenancePlanned Preventive Ambulance Medical Equipment Maintenance
Planned Preventive Ambulance Medical Equipment MaintenanceAshendu Pandey
 
Introduction to infrared condition monitoring with Viking Mining Services.
Introduction to infrared condition monitoring with Viking Mining Services.Introduction to infrared condition monitoring with Viking Mining Services.
Introduction to infrared condition monitoring with Viking Mining Services.VikingServices
 
Electrical Safety Audit for Risk Management.pptx
Electrical Safety Audit for Risk Management.pptxElectrical Safety Audit for Risk Management.pptx
Electrical Safety Audit for Risk Management.pptxURS Certification
 
Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR KUNDLAJAYALAKSHMI
 
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING Power System Operation
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overviewNidec Corporation
 
Energy auditing
Energy auditingEnergy auditing
Energy auditingJari Abbas
 
Electrical FM Compiled.pdf
Electrical  FM Compiled.pdfElectrical  FM Compiled.pdf
Electrical FM Compiled.pdfSyed Atif Naseem
 

Similar to CS003 (20)

AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304AS_TD_en_SAFE-Audit-Tools_1304
AS_TD_en_SAFE-Audit-Tools_1304
 
Wuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionWuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular Construction
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
 
F.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdfF.O.Enemuoh (1).pdf
F.O.Enemuoh (1).pdf
 
Productivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching ProcessProductivity Studies of Ultra High Density (UHD) Stitching Process
Productivity Studies of Ultra High Density (UHD) Stitching Process
 
Energy Auditing.pptx
Energy Auditing.pptxEnergy Auditing.pptx
Energy Auditing.pptx
 
Inspection and testing
Inspection and testingInspection and testing
Inspection and testing
 
Infrared inspection power point
Infrared inspection power pointInfrared inspection power point
Infrared inspection power point
 
Condition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence TechniqueCondition Monitoring of DC Motor using Artificial Intelligence Technique
Condition Monitoring of DC Motor using Artificial Intelligence Technique
 
Planned Preventive Ambulance Medical Equipment Maintenance
Planned Preventive Ambulance Medical Equipment MaintenancePlanned Preventive Ambulance Medical Equipment Maintenance
Planned Preventive Ambulance Medical Equipment Maintenance
 
Introduction to infrared condition monitoring with Viking Mining Services.
Introduction to infrared condition monitoring with Viking Mining Services.Introduction to infrared condition monitoring with Viking Mining Services.
Introduction to infrared condition monitoring with Viking Mining Services.
 
Electrical Safety Audit for Risk Management.pptx
Electrical Safety Audit for Risk Management.pptxElectrical Safety Audit for Risk Management.pptx
Electrical Safety Audit for Risk Management.pptx
 
Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR Qualification of analytical instrument of FTIR
Qualification of analytical instrument of FTIR
 
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
SURVEY ON HYDRO GENERATOR INSTRUMENTATION AND MONITORING
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
 
maintenance_lec-3-4.pptx
maintenance_lec-3-4.pptxmaintenance_lec-3-4.pptx
maintenance_lec-3-4.pptx
 
EESS 2018 Day 1 - Tim Webster
EESS 2018 Day 1 - Tim WebsterEESS 2018 Day 1 - Tim Webster
EESS 2018 Day 1 - Tim Webster
 
Energy auditing
Energy auditingEnergy auditing
Energy auditing
 
Instrumentation ppt original.pptx
Instrumentation ppt original.pptxInstrumentation ppt original.pptx
Instrumentation ppt original.pptx
 
Electrical FM Compiled.pdf
Electrical  FM Compiled.pdfElectrical  FM Compiled.pdf
Electrical FM Compiled.pdf
 

More from Steve Willetts

More from Steve Willetts (6)

Moog Case Study
Moog Case StudyMoog Case Study
Moog Case Study
 
Iris Presentation
Iris PresentationIris Presentation
Iris Presentation
 
Thermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical MaintenanceThermal Imaging for Electrical Maintenance
Thermal Imaging for Electrical Maintenance
 
casestudy3indd
casestudy3inddcasestudy3indd
casestudy3indd
 
casestudy2indd
casestudy2inddcasestudy2indd
casestudy2indd
 
casestudy1indd
casestudy1inddcasestudy1indd
casestudy1indd
 

CS003

  • 1. CaseStudy PowerGeneration Power Generation ROI A Powerful Case for Infrared Windows By Martin Robinson, CMRP Level III Thermographer CEO, IRISS, Inc. 18-1034-0003 Rev. A Overview: A regional Power Generation Facility had been tasked by their insurance carrier to perform regular preventive maintenance on the switchgear within their facility. Unfortunately, regular downtime was not a practical option for them as the processes required to do the live inspections were hazardous and required more manpower and resources than they had to provide. In addition, they too were feeling the pressure of the requirements of NFPA 70E and were starting to re-think their strategy since inspections of energized equipment was becoming more restrictive, more time consuming and more costly.
  • 2. CaseStudy PowerGeneration The insurance carrier had done the necessary research and determined that the facility should consider Infrared windows as an alternative method of conducting safer, standards-compliant inspections and it was determined that a reduction in hazard liability and maintenance costs could be attained through: • Use of Infrared Windows for routine inspections of healthy equipment did not require the elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating conditions, enclosed energized equipment that has been properly installed and maintained is not likely to pose an arc flash hazard.” • Maintaining an “enclosed” state for the switchgear, MCC, Transformer, etc., and maintains energized components and circuit parts in a “guarded” condition, in NFPA terms. Therefore, the hazard/risk category would be equal to that of reading a panel meter, using a visual inspection pane for lockout/tagout confirmations, or walking past enclosed, energized equipment and could even be conducted during peak hours for best diagnostic data. • Use of IR windows would eliminate the need for a supporting cast of electricians to remove and reinstall panel covers. • Allowing critical personnel to then be available to perform other tasks which were often being outsourced. • Providing the ability to perform more frequent inspections feasible for critical or suspect applications to ensure plant uptime and appease the insurance carrier of the reduced insurance liabilities. The focus was to facilitate inspection of the primary switchgear in their electrical distribution system and several smaller operations within the plant. An impending shutdown increased the sense of urgency since all Phase I installation could be fitted during that period. Table 1 Application Total Qty. Qty. lnsp Primary Switch 15 0 Secondary Switchgear 23 19 Transformers 15 0 MCC's 24 24 Miscellaneous Switchgear 8 8 Generators 10 10 Total Assemblies 95 61 Investment A pre-site inspection by IRISS was performed to ascertain the optimal position and quantity of windows which would give thermographers thorough visibility of desired targets. Previously, none of the primary
  • 3. CaseStudy PowerGeneration switchgear or transformers had been included in the sites inspections due to the inherent safety hazards associated with their being safely inspected while energized. The review showed that some of the plant’s critical assets were never inspected during the annual survey. The primary goal of Phase I was to bring this equipment into the standard inspection routes. A time study was completed detailing the man- hours and the costs involved in completing Phase I of the IR window installation allowing the inspections to be completed in line with NFPA and OSHA safety mandates. Typical Cost Analysis of Standard Inspection The client had been using a contract thermography company for some time and the survey crew consisted of two in-house electricians and one contact thermographer. The hourly wrench time (time spent on productive labor) rate for the electrician was calculated at $62, and the contract thermographer’s rate was $150 per hour ($1,200 a day). Typically, the equipment being considered for Phase I window retrofitting would require 19 days to complete. This translated into 497.7 billable hours (as shown in Table 2). The entire inspection team dressed in 40 Cal/cm2 PPE (personal protective equipment) in accordance with NFPA 70E and OSHA mandates for energized work. They spent on average 30 minutes to suit-up and dress-down - twice a day. This was a total of 88 hours related to PPE over a 19-day cycle. The thermographer spent 186.4 hours waiting for panel covers to be opened/closed to provide him with access. Similarly, the electricians spent 58.8 hours (29.4 hours x two men) waiting for the thermographer to complete his work once the panels were removed. After analyzing the time studies, facility management was surprised to learn that a staggering 468.3 hours (94%) of the total project time for the traditional open-panel surveys was non-productive (PPE suit-up, thermographer wait-time, electrician wait-time, etc.) The task breakdown is reflected within Table 2. Table 2 Man-Hours Total Assemblies 95 Inspection Compartments 147 PPE Suit-up Time 0.5 Hrs. 57.0 Time Taken to Remove Covers 0.4 Hrs. 117.6 Time Taken for IR Inspection 0.2 Hrs. 29.4 Time Taken to Replace Covers 0.4 Hrs 117.6 Electrician Waiting Time 58.8 Thermographer Waiting Time 117.6 Total Billable Man-Hours 497.7 Unproductive Man-Hours 468.3
  • 4. CaseStudy PowerGeneration Table 3 details the man-hour costs for the infrared survey using a contract thermographer without infrared windows or viewports. The following assumptions are made: • Total man-hours per inspection of “inspectable” equipment: 497.7 hours (19 days) • Staff electrician internal charge-out rate $62 per hour • Contract thermographer charge-out rate $150 per hour • PPE suit-up twice daily, per man (30 minutes per man, per suit-up) • 48 minutes per compartment panel for safe removal, refitting (per man for a two-man team) • 12 minutes per panel for infrared scan. • 147 individual panels to inspect (Table2) Table 3 Total Cost of Traditional Inspection: Removal and Replacement of Panels 235.2 $ 4,582 Infrared Inspection 29.4 $ 4,410 Electrician Wait-Time 58.8 $ 3,646 Contract Thermographer Wait-Time 117.6 $ 17,640 PPE Suit-up Time 57 $ 5,206 Total $ 45,484 Infrared Windows In search for an alternative approach that was both safer and standards-compliant, the corporate reliability engineer investigated how infrared inspection windows (commonly referred to as IR windows, viewports or sight glasses) might be utilized. It was determined that: • Use of IR windows would provide non-intrusive access to electrical applications. Surveys could be conducted during periods of peak-load without elevating risk to either plant assets or processes. • Use of IR windows would eliminate the need for a supporting cast of electricians to remove and reinstall panel covers. These critical personnel would then be available to perform other tasks which were often being outsourced. • Use of IR windows and closed-panel inspection would eliminate high-risk tasks during inspections – increasing safety for thermographers. • Use of infrared windows for routine inspections of healthy equipment did not require the elevated levels of PPE required in 70E, since as stated in 70E 100: “Under normal operating conditions, enclosed energized equipment that has been properly installed and maintained is not likely to pose an arc flash hazard.” • In NFPA terms, an IR window maintains electrical equipment in an “enclosed” state and it maintains energized components and circuit parts in a “guarded” condition. Therefore, the hazard/risk category would be equivalent to reading a panel meter, using a visual inspection
  • 5. CaseStudy PowerGeneration pane for lockout/tag-out confirmation, or walking past enclosed, energized equipment. • Use of infrared windows would improve inspection efficiency. It would allow increases in inspection frequency for those mission critical or suspect applications. Investment The 203 installed IRISS infrared windows represented an investment of $48,841.00. IRISS, Inc. also provided a cost benefit analysis comparing in-house installation versus outsourced (Table 4). The facility’s 95 applications with 147 inspection compartments required 203 infrared inspection windows (Table 5). Table 4 IR Window Supply & Contracted Installation Team Infrared Windows $36,255 Install Costs for 203 IR Windows $12,586 Total $48,841 Table 5 Application Quantity Primary Switch 15 Secondary Switchgear 23 Transformers 15 MCC’s 24 Miscellaneous Switchgear 8 Generators 10 Total Assemblies 95 Inspection Compartments 147 IR Windows 203 The Installation The installation of the inspection panes was conducted during a shutdown, using two install teams. The majority of the windows were installed while equipment was de-energized, in what NFPA terms an “electrically safe work condition.” However, some installations involved energized gear and needed to employ the traditional safety measures such as use of PPE, energized work permits, etc. The work occurred during normal business hours since this allowed more flexibility.
  • 6. CaseStudy PowerGeneration Cost Analysis with Windows With the infrared windows installed, there was no requirement to remove panels or wear increased levels of PPE. In addition, inspections were now performed on their applications that had previously been considered “un-inspectable.” Finally, the entire task became a one-man job. The windows also increased efficiency and economy-of-motion. Total man-hours to complete an inspection dropped to just 33. As a result, the new survey dropped from almost $45,484 to just under $4,950 (as detailed in Table 6). Table 6 Total Cost of Inspection Using IR Windows Inspection Time 33 $4,950 PPE Suit-up Time 0 $0.00 Total $4,950 Because of the efficiencies achieved, the facility saves $40,534 per inspection – that’s a savings greater than 90%. ROI Table 7 combines the data from the previous tables to illustrate the ROI (return on investment) that the facility realized from Phase I of its infrared window program. The table details the total investment using 2 scenarios: 1) Traditional open-panel inspections with a contract thermographer and two staff electricians; 2) the same contractor using infrared windows. Switching to infrared windows is shown to pay dividends in just two inspection cycles. Over $33,227 in savings can be put back into the budget by the end of the second cycle. After just five inspection cycles, the facility shows a savings of over $153,829. Because inspections can now be completed with greater ease and without increased risk to plant, personnel and processes, the facility increased the frequency of inspections to quarterly, reflecting best- practice recommendations that originally were not considered feasible.
  • 7. CaseStudy PowerGeneration Conclusion The new inspection process using infrared windows brought significant ROI to the plant in just two inspection cycles, while reducing the risk of catastrophic failure among the plant’s critical power distribution systems. Management succeeded in: • Increasing safety • Facilitating inspections of previously “un-inspectable” equipment • Increasing the frequency of inspection – while saving money • Safeguarding profitability by eliminating high-risk behavior that posed a risk to plant assets and production In the future the facility is planning to purchase its own IR camera and training for the maintenance engineers, which will quickly pay dividends and allow the plant to improve the maintenance program while operating in full compliance with the requirements of NFPA and OSHA. An infrared window program provides a cost-effective and safer alternative to traditional open-panel inspections. To learn more, visit www.iriss.com where you will find the FREE ROI calculator, case studies and white papers. To learn more about infrared windows, Electrical Preventive Maintenance, NFPA standards or electrical thermography please visit www.iriss.com. “10 Things You Need to Know About Infrared Windows” contains more information on the benefits of IR windows. To get your free digital copy, Click Here. Interested in IRISS IR Window Solutions? Click Here “10 Things You Need to Know About Infrared Windows”