The feasibility study found that a 10MW biomass power plant fueled by wood waste from local timber operations in Ndola, Zambia is feasible. A plant using steam turbine technology could be sustained from available waste and have a capacity of 7MW. Additional biomass sources could increase capacity to 10MW. Challenges include finalizing land acquisition, securing a firm feedstock supply, and obtaining a tariff that makes the plant economically viable. Next steps are to complete the land deal, environmental review, engage potential heat and electricity customers, and arrange project financing.