SlideShare a Scribd company logo
1 of 29
EXCAVATION FOR
FOUNDATION
METHODS & TEMPORARY EARTH
RETAINING STRUCTURE
SHIVANANDA ROY
B.TECH, M.TECH, AMIE
EXCAVATION FOR FOUNDATIONS AND
BASEMENT FLOORS
• Generally excavation means to loosen and take out materials leaving space above or below ground.
Sometimes in civil engineering term earthwork is used which include backfilling with new or original
materials to voids, spreading and levelling over an area.
• A basement is part of a building that is either partially or completely below ground level.
• Basements can be constructed using brick or concrete block, poured concrete, pre-cast concrete, or
even timber.
• Basements generally become more expensive as the depth increases. However, in prime locations,
the cost of land may justify multi-story basements or even below ground parking garages.
• Excavation in most situations nowadays is done by mechanical means. However, the exact method to
be adopted still depends upon a number of factors:
• 1. Nature of subsoil – affect type of machine used and the necessity of soil protection.
• 2. Size of excavation – affect type of machine used and method to excavate.
• 3. Scale of work – large volume of excavation may involve complicated phasing arrangement and work
planning
• 4. Ground water condition – affect degree of protection (watertight sheet piling or dewatering may required.)
• 5. Surrounding condition – impose certain restrictions and precautions (eg. diversion of a government drain, or
underpinning work to the nearby building foundation)
METHODS
• Full Open Cut Method
• Bracing Excavation Method
• Anchored Excavation Methods
• Island Excavation Methods
• Zoned Excavation Methods
• Top Down Excavation Methods
FULL OPEN CUT METHOD
• It divided into two major types: Sloped full open cut
and Cantilever full open cut.
• The former is assumed to be economical since the
side of excavation would be sloped and does not
need any support to held foundation wall.
• However, if the slope is considerably gentle or the
excavation is largely deep, it will costly.
• The latter needs retaining wall to support
foundation wall soil and prevent collapse of
foundation The economical method may be
distinguished based on analysis, design, and
evaluation results.
BRACING EXCAVATION METHOD
• Bracing excavation as shown in figure is the placement of horizontal struts in front of retaining wall
to held excavation wall material pressure. Bracing system consist of wale, strut, center posts, end
braces, and corner braces.
• Earth pressure transfer to horizontal struts through wale, and the purpose of corner and end braces
is to reduce wale span without increasing strut number. Center posts prevent the failure of struts
due to their own weight.
ANCHORED EXCAVATION METHODS
• In this technique, anchors are installed to counter act against earth pressure.
• Bonded portion of the anchor provides anchoring force that works against earth pressure whereas
unbonded part of the anchored transfer pressure to the anchor head. Anchor head transfer loads to
the retaining wall.
• The anchoring force is greatly based on the soil strength. The higher the soil strength the greater the
anchoring forces. This technique is not suitable for clay and granular soil with high ground water
table.
• Lastly, it require short time to complete excavation with great efficiency and suitable for large areas
and shallow depth.
ISLAND EXCAVATION METHODS
• In this method, the center of excavation area is dug and excavated material placed close to the
retaining wall to create a slope. After that, the major part of the structure would be constructed at
the center of the excavation. Then, the sloped soil will be excavated and struts will be placed
between retaining wall and the main structure.
• Finally, the struts will be removed and remaining parts of the structure will be constructed.
Sometimes, it might be required to use anchored or braced technique to removed slopes soil
material, specifically when the excavation is too deep.
ZONED EXCAVATION METHODS…
• Diaphragm walls are used as a retaining wall in the zoned excavation method. Deformation of the
longer span wall would greater than short span wall as explained first figure.
• So, the deflections of longer span walls are declined by dividing excavation area into small area
to decrease wall deformation and settlement as shown in second figure.
…ZONED EXCAVATION METHODS
• The excavation will begin in area B while area A would be left to support the wall of area B. then
struts in area B would be installed and excavation starts in area A. This process will continue in
stages till the whole excavation is completed.
• It can be clearly observed that the load on diaphragm wall would be considerably large and
hence deflection would great if the area had not been divided into smaller area.
TOP DOWN EXCAVATION METHODS…
• In this method, construction begins from the top to
the bottom of excavation and superstructure
construction starts after the construction of the first
slab is completed.
• So, slabs are constructed after each stage of
excavation is finished. The slabs play the same role
as struts in holding earth pressure.
…TOP DOWN EXCAVATION METHODS
• Construction process order include retaining wall construction, pile construction under column of
superstructure, placing columns on piles, and installing formwork for the first slab at the top then
other slabs of the would be constructed after each excavation.
• This technique would need short construction time, but the cost is higher compare to other methods.
Another advantage is that, construction area safer since slabs are stronger than struts.
TEMPORARY EARTH RETAINING STRUCTURES
• Deep excavation, unlike a shallow one, often requires to protect the sides of cut
using suitable support. Besides, the problem of ground water cannot be
avoided. There are methods to overcome this, such as:
Dumpling method Braced wall
Diaphragm walling Soil Nail Wall
Using cofferdams Soldier Pile and Lagging Walls
Sheet Steel Piling Sheet Pile Walls
Ground anchor
Reinforced Concrete Wall
Construction
DUMPLING METHOD
• This is used where there are buildings or street in the proximity.
The method is to construct a series of retaining wall in trench,
section by section, around the site perimeter ,leaving a centre called
"dumpling“
• When the perimeter walls are in place, excavation may start at the
centre of the dumpling, until exposing a section of the wall. Then
the wall may be side supported by struts, shoring or soil anchor etc.,
again section by section in short length, until the excavation is all
completed.
• This method does not require much heavy mechanical equipment
and thus cost of work is relatively lower. It can excavate up to a
maximum depth of about 3m.
• Sometimes in very poor soil or in waterlogged ground, interlocking
steel sheet pile may be driven to confine the area to be excavated
.After that excavation can be done in section and properly supported
similar to that mentioned above.
SHEET PILE WALLS …
• Sheet piles can be driven into soil by stricking or static vibrating and
have them interlocked or connected with one another.
• There are several shapes of sheet pile section viz- U-section, Z-section
and the line section.
• If the interlocking is well done, sheet piles can be quit efficient in water
sealing. If not, leaking may occur at the joints.
• In clayey soils, having low permeability, sheet piles do not necessarily
require perfect connection to prevent leaking.
• In sandy soils, with high permeability, any breach in sheet piles may
well cause leaking. If leak occur, sand in back of the retaining walls will
possibly flow out, which may cause settlement in turn.
… SHEET PILE WALLS …
• The construction method for sheet piles can be described as follows:
1. Drive sheet piles into soil by stricking or static vibrating.
2. Proceed to the first stage of excavation
3. Place wales in proper places and install horizontals struts.
4. Proceed to next stage of excavation.
5. Repeat 3 & 4 till the designed depth.
6. Complete excavation and begin to build the foundation of the building.
7. Build the inner walls of the basement. Dismantle the struts level and build the floor slabs
accordingly.
8. Complete the basement.
9. Dismantle the sheet piles.
… SHEET PILE WALLS
• The merits of steel pile method are:
• It is highly watertight
• It is reusable
• Has higher stiffness than soldier piles.
• The drawbacks of steel pile method are:
• Lower stiffness than column piles or diaphragm walls.
• Susceptible to settlement during stricking or dismantling in a sandy ground.
• Not easy to strike piles into hard soils.
• A lot of noise is caused during striking.
• Leaks cannot be completely avoided and sealing and grouting are probably necessary if leak
occurs.
DIAPHRAGM WALLING…
• This method need to construct a R.C. retaining wall along the area of work. Because the wall
is designed to reach very great depth, mechanical excavating method is employed. Typical
sequence of work includes:
• a) Construct a guide wall
• b) Excavation for the diaphragm wall
• c) Excavation support using bentonite
slurry
• d) Inert reinforcement and concreting
…DIAPHRAGM WALLING…
• Construct a guide wall – guide wall is two parallel
concrete beams running as a guide to the clamshell
which is used for the excavation of the diaphragm wall.
• Excavation for the diaphragm wall – In normal soil
conditions excavation is done using a clamshell or grab
suspended by cables to a crane. The grab can easily
chisel boulder in soil due to its weight.
• Excavation support – Excavation for the diaphragm
wall produces a vertical strip in soil which can collapse
easily. Bentonite slurry is used to protect the sides of
soi1.
• Reinforcement – Reinforcement is inserted in form of a
steel cage, but may require to lap and extend to the
required length.
…DIAPHRAGM WALLING
• Concreting – As Concrete being poured down, bentonite will be displaced due to its density is lower
than concrete. Bentonite is then collected and reuse. Usually compaction for concrete is not required
for the weight of the bentonite will drive most of the air voids in concrete.
• Joining design for the diaphragm wall –
• Diaphragm walling cannot be constructed continually for a very long section due to tremendous soil
pressure. The wall is usually constructed in alternative section.
• Two stop end tubes will be placed at the ends of the excavated trench before concreting. The tubes are
withdrawn at the same time of concreting so that a semi-circular end section is formed.
• Wall sections of this type are built alternatively leaving an intermediate section in between .The interior
sections are built similarly but without the end tube .
• At the end a continual diaphragm wall is constructed with the sections tightly joined by the semi-circular
groove.
USING COFFERDAMS
• A cofferdam may be defined as a temporary box structure constructed in earth or water to
exclude soil or water from a construction area, such as for foundation or basement works.
• Use of cofferdam suitable for excavation of larger scale can be of :
a) Sheet pile cofferdam – Also known as single skin cofferdam. Interlocking type steel sheet
pile is used and can use for excavation up to 15m. Sheet pile in this case acts as a cantilever member to
support the soil therefore adequate depth of pile or suitable toe treatment may be required. In
addition, cofferdams are need to be braced and strutted or anchored using tie rods or ground
anchors.
USING COFFERDAMS
• b) Double skin cofferdam – This works similarly like the sheet pile to form a diaphragm. However,
the diaphragm is double-skinned using two parallel rows of sheet pile with a filling material
placed in the void between. This creates somewhat a gravity retaining structure and increase the
ability to counteract the soil behind. However, more working space is required.
BRACED WALL
• This soil retaining arrangement is suitable for deep
and less wide soil excavations. Initially, horizontal
members are installed against the soil support. These
horizontal members are called as waler. From one waler
to the other, intermediate struts are installed across the
excavation.
• The excavation is performed step by step.
• This retaining system is suitable for soils with cohesion
and low or no water table level.
• The method is often limited to small dimension shafts
and trenches with and without penetration below base.
SOIL NAIL WALL …
• Soil nail wall construction is a technique used to
bring soil stability in areas where landslides
might be a problem.
• Soil nail can prevent landslides by inserting
steel reinforcement bars into the soil and
anchoring them to the soil strata.
• It is called Soil Nail because it’s like having a nail
being hammered into the soil, where the nails
are the steel bars.
SOIL NAIL WALL INSTALLATION PROCESS
• Soil nail wall provides a resisting force against slope
failures. Its construction process is faster than other
similar methods.
• The construction procedure starts, drilling into the
soil, where the nail, steel bar, is going to be placed.
• Then, it must be grouted into the soil to create a
structure similar to a gravity wall. After placing the
nail, a shot-crete layer is usually placed as a
facing material, to protect the exposed nail, and
then other architectural options are placed over the
shot-crete, creating an aesthetic finish to the project.
• Drainage is a critical aspect of soil nail wall
construction. Face drainage is virtually always used
with permanent walls, and very commonly used
with temporary walls. Face drainage usually consists
of synthetic drainage elements placed between the
shot-crete and the retained soil.
• The grouted soil nail hole typically has a minimum
diameter of 4 inches. Centralizers are placed around
the soil nail to maintain an even thickness of grout
around the bar. For permanent applications, nails
may be epoxy-coated or provided with a protective
sheath for corrosion protection.
SOIL NAIL WALL INSTALLATION PROCESS
• For a soil nail wall the general construction procedure involves:
1. Excavate for the first nail (soil must be sufficiently self standing)
2. Install the 1st nail.
3. Construct 1st phase shotcrete on soil face (optional if shotcrete is constructed) with wire mesh
or other reinforcement if required.
4. Install soil nail head plate (with or without other attachments)
5. Construct 2nd phase shotcrete (depending on staging specifications).
6. Excavate to next soil nail level, and install next soil nail, shotcrete etc.
7. Repeat steps 3 through 6 until the final excavation level is reached.
8. Construct additional permanent facing if required.
GROUND ANCHOR
• Ground anchor is basically a pre-stressing tendon embedded and anchored into soil or rock to provide
resistance to structural movements by a “tying back" principle.
• Common applications are :
1. General slope stabilization
2. Tying back/stabilizing a retaining structure
3. Tying back/stabilizing for diaphragm walls, but for a temporary nature
during excavation
4. Tying back the entire building from up possible uplifting
• Ground anchor can be classified into:
1. Rock anchor – for anchorage in rock
2. Injection anchor – suitable for most cohesive and non-cohesive soils
GROUND ANCHOR
• Method to form a ground anchor
1. A hole is predrilled on soil or rock in position carefully calculated. A dense high
strength grout is injected over a required length to develop sufficient
resistance to hold the bar when it is stressed.
2. For injection anchor, a hole should be bored usually with an expanded end
to increase anchorage ability. The pre-stressing bar is placed into the bore hole
and pressure grouted over the anchorage length.
3. Gravel placement ground anchor can also be used in clay soils for lighter
loading. In this method irregular gravel is injected into the borehole over the
anchorage length to form an end plug. The gravel p1ug is then force into soil
using percussion method through casing, forming an enlarged end. A stressing
bar is inserted into the casing and pressure grouted over the anchorage length
as the casing is removed.
4. It should be noted that certain protection measure against corrosion or rusting
is required for the stressing bar.
THIS IS THE LAST PAGE
Thank You
RISE & BELIEVE…

More Related Content

What's hot

What's hot (20)

Chapter 1 foundation
Chapter  1 foundationChapter  1 foundation
Chapter 1 foundation
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Site clearance & preparetion
Site clearance & preparetionSite clearance & preparetion
Site clearance & preparetion
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Foundation types
Foundation typesFoundation types
Foundation types
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Modes of failure of retaining walls
Modes of failure of retaining wallsModes of failure of retaining walls
Modes of failure of retaining walls
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building Construction
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
 
Foundation & Footings
Foundation & FootingsFoundation & Footings
Foundation & Footings
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Shear walls
Shear wallsShear walls
Shear walls
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
DPC, Back Filling and Plinth Protection.pptx
DPC, Back Filling and Plinth Protection.pptxDPC, Back Filling and Plinth Protection.pptx
DPC, Back Filling and Plinth Protection.pptx
 

Similar to EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures

Similar to EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures (20)

Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
soil retention in construction -Group 7 powerpoint
    soil retention in construction -Group 7 powerpoint    soil retention in construction -Group 7 powerpoint
soil retention in construction -Group 7 powerpoint
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
Micropile
MicropileMicropile
Micropile
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
pile wall
pile wallpile wall
pile wall
 
Unit 3
Unit 3Unit 3
Unit 3
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
UNderpinning.pptx.pdf
UNderpinning.pptx.pdfUNderpinning.pptx.pdf
UNderpinning.pptx.pdf
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 

More from Shivananda Roy

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSShivananda Roy
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONShivananda Roy
 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESShivananda Roy
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & ExcavationShivananda Roy
 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction EquipmentsShivananda Roy
 

More from Shivananda Roy (7)

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUES
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & Excavation
 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction Equipments
 
Green concrete
Green concreteGreen concrete
Green concrete
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 

Recently uploaded

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 

Recently uploaded (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 

EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures

  • 1. EXCAVATION FOR FOUNDATION METHODS & TEMPORARY EARTH RETAINING STRUCTURE SHIVANANDA ROY B.TECH, M.TECH, AMIE
  • 2. EXCAVATION FOR FOUNDATIONS AND BASEMENT FLOORS • Generally excavation means to loosen and take out materials leaving space above or below ground. Sometimes in civil engineering term earthwork is used which include backfilling with new or original materials to voids, spreading and levelling over an area. • A basement is part of a building that is either partially or completely below ground level. • Basements can be constructed using brick or concrete block, poured concrete, pre-cast concrete, or even timber. • Basements generally become more expensive as the depth increases. However, in prime locations, the cost of land may justify multi-story basements or even below ground parking garages.
  • 3. • Excavation in most situations nowadays is done by mechanical means. However, the exact method to be adopted still depends upon a number of factors: • 1. Nature of subsoil – affect type of machine used and the necessity of soil protection. • 2. Size of excavation – affect type of machine used and method to excavate. • 3. Scale of work – large volume of excavation may involve complicated phasing arrangement and work planning • 4. Ground water condition – affect degree of protection (watertight sheet piling or dewatering may required.) • 5. Surrounding condition – impose certain restrictions and precautions (eg. diversion of a government drain, or underpinning work to the nearby building foundation)
  • 4. METHODS • Full Open Cut Method • Bracing Excavation Method • Anchored Excavation Methods • Island Excavation Methods • Zoned Excavation Methods • Top Down Excavation Methods
  • 5. FULL OPEN CUT METHOD • It divided into two major types: Sloped full open cut and Cantilever full open cut. • The former is assumed to be economical since the side of excavation would be sloped and does not need any support to held foundation wall. • However, if the slope is considerably gentle or the excavation is largely deep, it will costly. • The latter needs retaining wall to support foundation wall soil and prevent collapse of foundation The economical method may be distinguished based on analysis, design, and evaluation results.
  • 6. BRACING EXCAVATION METHOD • Bracing excavation as shown in figure is the placement of horizontal struts in front of retaining wall to held excavation wall material pressure. Bracing system consist of wale, strut, center posts, end braces, and corner braces. • Earth pressure transfer to horizontal struts through wale, and the purpose of corner and end braces is to reduce wale span without increasing strut number. Center posts prevent the failure of struts due to their own weight.
  • 7. ANCHORED EXCAVATION METHODS • In this technique, anchors are installed to counter act against earth pressure. • Bonded portion of the anchor provides anchoring force that works against earth pressure whereas unbonded part of the anchored transfer pressure to the anchor head. Anchor head transfer loads to the retaining wall. • The anchoring force is greatly based on the soil strength. The higher the soil strength the greater the anchoring forces. This technique is not suitable for clay and granular soil with high ground water table. • Lastly, it require short time to complete excavation with great efficiency and suitable for large areas and shallow depth.
  • 8. ISLAND EXCAVATION METHODS • In this method, the center of excavation area is dug and excavated material placed close to the retaining wall to create a slope. After that, the major part of the structure would be constructed at the center of the excavation. Then, the sloped soil will be excavated and struts will be placed between retaining wall and the main structure. • Finally, the struts will be removed and remaining parts of the structure will be constructed. Sometimes, it might be required to use anchored or braced technique to removed slopes soil material, specifically when the excavation is too deep.
  • 9. ZONED EXCAVATION METHODS… • Diaphragm walls are used as a retaining wall in the zoned excavation method. Deformation of the longer span wall would greater than short span wall as explained first figure. • So, the deflections of longer span walls are declined by dividing excavation area into small area to decrease wall deformation and settlement as shown in second figure.
  • 10. …ZONED EXCAVATION METHODS • The excavation will begin in area B while area A would be left to support the wall of area B. then struts in area B would be installed and excavation starts in area A. This process will continue in stages till the whole excavation is completed. • It can be clearly observed that the load on diaphragm wall would be considerably large and hence deflection would great if the area had not been divided into smaller area.
  • 11. TOP DOWN EXCAVATION METHODS… • In this method, construction begins from the top to the bottom of excavation and superstructure construction starts after the construction of the first slab is completed. • So, slabs are constructed after each stage of excavation is finished. The slabs play the same role as struts in holding earth pressure.
  • 12. …TOP DOWN EXCAVATION METHODS • Construction process order include retaining wall construction, pile construction under column of superstructure, placing columns on piles, and installing formwork for the first slab at the top then other slabs of the would be constructed after each excavation. • This technique would need short construction time, but the cost is higher compare to other methods. Another advantage is that, construction area safer since slabs are stronger than struts.
  • 13. TEMPORARY EARTH RETAINING STRUCTURES • Deep excavation, unlike a shallow one, often requires to protect the sides of cut using suitable support. Besides, the problem of ground water cannot be avoided. There are methods to overcome this, such as: Dumpling method Braced wall Diaphragm walling Soil Nail Wall Using cofferdams Soldier Pile and Lagging Walls Sheet Steel Piling Sheet Pile Walls Ground anchor Reinforced Concrete Wall Construction
  • 14. DUMPLING METHOD • This is used where there are buildings or street in the proximity. The method is to construct a series of retaining wall in trench, section by section, around the site perimeter ,leaving a centre called "dumpling“ • When the perimeter walls are in place, excavation may start at the centre of the dumpling, until exposing a section of the wall. Then the wall may be side supported by struts, shoring or soil anchor etc., again section by section in short length, until the excavation is all completed. • This method does not require much heavy mechanical equipment and thus cost of work is relatively lower. It can excavate up to a maximum depth of about 3m. • Sometimes in very poor soil or in waterlogged ground, interlocking steel sheet pile may be driven to confine the area to be excavated .After that excavation can be done in section and properly supported similar to that mentioned above.
  • 15. SHEET PILE WALLS … • Sheet piles can be driven into soil by stricking or static vibrating and have them interlocked or connected with one another. • There are several shapes of sheet pile section viz- U-section, Z-section and the line section. • If the interlocking is well done, sheet piles can be quit efficient in water sealing. If not, leaking may occur at the joints. • In clayey soils, having low permeability, sheet piles do not necessarily require perfect connection to prevent leaking. • In sandy soils, with high permeability, any breach in sheet piles may well cause leaking. If leak occur, sand in back of the retaining walls will possibly flow out, which may cause settlement in turn.
  • 16. … SHEET PILE WALLS … • The construction method for sheet piles can be described as follows: 1. Drive sheet piles into soil by stricking or static vibrating. 2. Proceed to the first stage of excavation 3. Place wales in proper places and install horizontals struts. 4. Proceed to next stage of excavation. 5. Repeat 3 & 4 till the designed depth. 6. Complete excavation and begin to build the foundation of the building. 7. Build the inner walls of the basement. Dismantle the struts level and build the floor slabs accordingly. 8. Complete the basement. 9. Dismantle the sheet piles.
  • 17. … SHEET PILE WALLS • The merits of steel pile method are: • It is highly watertight • It is reusable • Has higher stiffness than soldier piles. • The drawbacks of steel pile method are: • Lower stiffness than column piles or diaphragm walls. • Susceptible to settlement during stricking or dismantling in a sandy ground. • Not easy to strike piles into hard soils. • A lot of noise is caused during striking. • Leaks cannot be completely avoided and sealing and grouting are probably necessary if leak occurs.
  • 18. DIAPHRAGM WALLING… • This method need to construct a R.C. retaining wall along the area of work. Because the wall is designed to reach very great depth, mechanical excavating method is employed. Typical sequence of work includes: • a) Construct a guide wall • b) Excavation for the diaphragm wall • c) Excavation support using bentonite slurry • d) Inert reinforcement and concreting
  • 19. …DIAPHRAGM WALLING… • Construct a guide wall – guide wall is two parallel concrete beams running as a guide to the clamshell which is used for the excavation of the diaphragm wall. • Excavation for the diaphragm wall – In normal soil conditions excavation is done using a clamshell or grab suspended by cables to a crane. The grab can easily chisel boulder in soil due to its weight. • Excavation support – Excavation for the diaphragm wall produces a vertical strip in soil which can collapse easily. Bentonite slurry is used to protect the sides of soi1. • Reinforcement – Reinforcement is inserted in form of a steel cage, but may require to lap and extend to the required length.
  • 20. …DIAPHRAGM WALLING • Concreting – As Concrete being poured down, bentonite will be displaced due to its density is lower than concrete. Bentonite is then collected and reuse. Usually compaction for concrete is not required for the weight of the bentonite will drive most of the air voids in concrete. • Joining design for the diaphragm wall – • Diaphragm walling cannot be constructed continually for a very long section due to tremendous soil pressure. The wall is usually constructed in alternative section. • Two stop end tubes will be placed at the ends of the excavated trench before concreting. The tubes are withdrawn at the same time of concreting so that a semi-circular end section is formed. • Wall sections of this type are built alternatively leaving an intermediate section in between .The interior sections are built similarly but without the end tube . • At the end a continual diaphragm wall is constructed with the sections tightly joined by the semi-circular groove.
  • 21. USING COFFERDAMS • A cofferdam may be defined as a temporary box structure constructed in earth or water to exclude soil or water from a construction area, such as for foundation or basement works. • Use of cofferdam suitable for excavation of larger scale can be of : a) Sheet pile cofferdam – Also known as single skin cofferdam. Interlocking type steel sheet pile is used and can use for excavation up to 15m. Sheet pile in this case acts as a cantilever member to support the soil therefore adequate depth of pile or suitable toe treatment may be required. In addition, cofferdams are need to be braced and strutted or anchored using tie rods or ground anchors.
  • 22. USING COFFERDAMS • b) Double skin cofferdam – This works similarly like the sheet pile to form a diaphragm. However, the diaphragm is double-skinned using two parallel rows of sheet pile with a filling material placed in the void between. This creates somewhat a gravity retaining structure and increase the ability to counteract the soil behind. However, more working space is required.
  • 23. BRACED WALL • This soil retaining arrangement is suitable for deep and less wide soil excavations. Initially, horizontal members are installed against the soil support. These horizontal members are called as waler. From one waler to the other, intermediate struts are installed across the excavation. • The excavation is performed step by step. • This retaining system is suitable for soils with cohesion and low or no water table level. • The method is often limited to small dimension shafts and trenches with and without penetration below base.
  • 24. SOIL NAIL WALL … • Soil nail wall construction is a technique used to bring soil stability in areas where landslides might be a problem. • Soil nail can prevent landslides by inserting steel reinforcement bars into the soil and anchoring them to the soil strata. • It is called Soil Nail because it’s like having a nail being hammered into the soil, where the nails are the steel bars.
  • 25. SOIL NAIL WALL INSTALLATION PROCESS • Soil nail wall provides a resisting force against slope failures. Its construction process is faster than other similar methods. • The construction procedure starts, drilling into the soil, where the nail, steel bar, is going to be placed. • Then, it must be grouted into the soil to create a structure similar to a gravity wall. After placing the nail, a shot-crete layer is usually placed as a facing material, to protect the exposed nail, and then other architectural options are placed over the shot-crete, creating an aesthetic finish to the project. • Drainage is a critical aspect of soil nail wall construction. Face drainage is virtually always used with permanent walls, and very commonly used with temporary walls. Face drainage usually consists of synthetic drainage elements placed between the shot-crete and the retained soil. • The grouted soil nail hole typically has a minimum diameter of 4 inches. Centralizers are placed around the soil nail to maintain an even thickness of grout around the bar. For permanent applications, nails may be epoxy-coated or provided with a protective sheath for corrosion protection.
  • 26. SOIL NAIL WALL INSTALLATION PROCESS • For a soil nail wall the general construction procedure involves: 1. Excavate for the first nail (soil must be sufficiently self standing) 2. Install the 1st nail. 3. Construct 1st phase shotcrete on soil face (optional if shotcrete is constructed) with wire mesh or other reinforcement if required. 4. Install soil nail head plate (with or without other attachments) 5. Construct 2nd phase shotcrete (depending on staging specifications). 6. Excavate to next soil nail level, and install next soil nail, shotcrete etc. 7. Repeat steps 3 through 6 until the final excavation level is reached. 8. Construct additional permanent facing if required.
  • 27. GROUND ANCHOR • Ground anchor is basically a pre-stressing tendon embedded and anchored into soil or rock to provide resistance to structural movements by a “tying back" principle. • Common applications are : 1. General slope stabilization 2. Tying back/stabilizing a retaining structure 3. Tying back/stabilizing for diaphragm walls, but for a temporary nature during excavation 4. Tying back the entire building from up possible uplifting • Ground anchor can be classified into: 1. Rock anchor – for anchorage in rock 2. Injection anchor – suitable for most cohesive and non-cohesive soils
  • 28. GROUND ANCHOR • Method to form a ground anchor 1. A hole is predrilled on soil or rock in position carefully calculated. A dense high strength grout is injected over a required length to develop sufficient resistance to hold the bar when it is stressed. 2. For injection anchor, a hole should be bored usually with an expanded end to increase anchorage ability. The pre-stressing bar is placed into the bore hole and pressure grouted over the anchorage length. 3. Gravel placement ground anchor can also be used in clay soils for lighter loading. In this method irregular gravel is injected into the borehole over the anchorage length to form an end plug. The gravel p1ug is then force into soil using percussion method through casing, forming an enlarged end. A stressing bar is inserted into the casing and pressure grouted over the anchorage length as the casing is removed. 4. It should be noted that certain protection measure against corrosion or rusting is required for the stressing bar.
  • 29. THIS IS THE LAST PAGE Thank You RISE & BELIEVE…