SlideShare a Scribd company logo
1 of 52
SITE INTRODUCTION 
THE SITE THAT WE RESEARCH ON IS LOCATED AT THE CITY CENTRE OF BANTING .THE SITE IS CONNECTED WITH THE 
KLANG BANTING HIGHWAY THAT PASS THROUGH MAJOR INTERSECTION OF JALAN BANTING-SEMENYIH . 
THE ROADS SURROUNDING THE SITE 
1. NORTH-JALAN BUNGA PEKAM 
2. SOUTH-JALAN SUASA 
3. EAST-JALAN BUNGA PEKAN 9 
4. WEST-JALAN GANGSA 
1. STATE 
2. DISTRICT 
3. CITY 
4. NO.LOT 
5. AREA 
6. TYPE OF BUILDING 
7. COMPANY 
-SELANGOR DARUL EHSAN 
-KUALA LANGAT 
-BANTING 
-PT 791, SEKSYEN 3 
-21632 METER SQUARE 
-SHOPLOTS 
-EHSAN ISTIMEWA SDN.BHD. 
DISTANCE BETWEEN THE SITE AND OTHER MAJOR DEVELOP CITY 
• 30KM AWAY FROM KLIA (KULA LUMPUR INTERNATIONAL 
AIRPORT) 
• 25KM AWAY FROM PUTRAJAYA 
• 35KM AWAY FROM SHAH ALAM 
• 60KM AWAY FROM KUALA LUMPUR 
Building Construction Project 1 
1 
Building Construction Project 1 
By yap chein wee
Index page 
Introduction to site 
topic 1 : site plan and site safety 
Topic 2 : Earthwork 
topic 3 : foundation 
topic 4 : beams and column 
topic 5 : floor system 
topic 6 : wall system 
topic 7 : staircase 
topic 8 : door and window 
topic 9 : roof system 
Building Construction Project 1 
2 
Building Construction Project 1
1.0 Site plan 
Building Construction Project 1 
3 
By chua jiu xin
Site safety 
1.0 site plan 
1.1 Introduction to site safety 
Construction sites contain many risks that faced by both 
of the construction workers and the general public. A 
construction site is legally required to follow the 
regulations and guidelines set by the department of 
occupational safety and Health and other government 
agencies to ensure the safety of the workers and public. 
These guidelines apply to all work areas with building 
operations activities in Malaysia according to the 
Occupational Safety and Health Act 1994 (Act 514), the 
1.2 SIGNAGE 
Factories and Machinery Act 1967 (Act 199) and all 
other relevant regulations. 
The guideline dictates that every owner, developer, 
main contractor and such contractor must take steps to 
develop and promote safety and health programs to ensure 
the safety and health of both his employees and the 
general public. Safety signs are commonly found around 
construction sites containing information, often symbols 
relevant to site safety. Figure 1 shows symbols that 
explain without the use of much words of what the workers 
and public should and should not do around the 
construction site. The use of simple universal symbols is 
effective because in some cases the construction workers 
or the public might be illiterate or might not be 
f1a.mi3l ihaora rwditihng the language used on signs. 
Hoarding is a prerequisite for a construction site 
because it is legally required to protect the general 
public from the risks associated with construction sites. 
Hoarding is temporary fencing which is laid out around 
the site, defining its borders. Aside from safety, 
hoarding is also used for security purposes, preventing 
trespassing and theft in the construction site. The 
construction site uses metal hoarding. Metal hoarding 
usually uses corrugated metal sheets as temporary 
fencing material. Figure 2 marks the borders of the 
construction site where boarding is used. 
Building Construction 
Project 1 
By Chua jiu 
4 
xin
2.0 Earthwork Introduction 
Definition 
Excavation and piling of earth in connection with an engineering operation. 
It involves movingpart of the earth to another location to create a 
desired shape. 
Machinery used: 
Much of the excavation is done with operated machines to ease work, 
cost and also saves time. These equipment includes:- 
Equipments Function 
Wheel Loader Scoop up lose materials from the ground from one point to another without pushing the materials 
across the ground 
Back Hoes Dig up hard materials and trenches 
Scrapers Machine to move earth over short distance (smoothen) 
Excavators Digging, demolition, forestry work, grading, landscaping, heavy lifting and brush cutting 
Motor Grader Finish grade the rought grading created by heavy vehivles (Created flat surface) 
Rollers Use to compact the soil after grading 
Building Construction Project 1 
5 
By tsang hao ren
Earthwork Machinery 
Fork Lifter lifting bags of 
Cement 
Crane being used to lift materials Concrete mixer mixing cement 
Using normal Truck to 
Send scaffold 
Backhoe excavating land for 
foundation Using backhoe loader to 
Transport steel bar 
Building Construction Project 1 
6 
By tsang hao ren
Earthwork Excavation 
Types of Excavation 
There are different types of excavation and it is classified by the type of materials 
Type of Excavation Description 
Topsoil excavation Removal of the exposed layer of the earth’s surface, including vegetation. Contains more 
moisture than that underneath. 
Earth excavation removal of the layer of soil immediately under the topsoil and on top of rock. Used to 
construct embankments and foundations 
Rock excavation removal of a formation that cannot be excavated without drilling and blasting. Any boulder 
larger than 1⁄2 yd3 generally is classified as rock. 
Muck excavation removal of material that contains an excessive amount of water and undesirable soil. 
Removal of water can be accomplished by spreading muck over a large area and letting it 
dry, by changing soil characteristics, or by stabilizing muck with some other material, 
thereby reducing the water content. 
Unclassified excavation removal of any combination of topsoil, earth, rock, and muck. earthmoving must be done 
without regard to the materials encountered. Much excavation is performed on an 
unclassified basis because of the difficulty of distinguishing, legally or practically, between 
earth, muck, and rock. 
Building Construction Project 1 
7 
By tsang hao ren
Earthwork Soil Testing 
Introduction 
The investigation of the geology and previous uses of any site, 
together with the determination of its engineering, environmental 
and contamination characteristics is fundamental to both safe and 
economic development. 
Soil Investigation Techniques that are employed for the project 
are as followed : 
1. Boreholes 2. In-situ testing 
1. Boreholes 
Rotary Boring is 
boring hole using 
drilling fluid (water 
or mud) pumped 
down a rod fitted 
at the bottom some 
sort of cutting bit. 
2. In-situ Testing 
In-situ testing techniques, Standard Penetration Testing, 
Permeability Testing and Borehole Vane Testing are carried out in 
the boreholes in order to provide information for geotechnical 
design. Disturbed and undisturbed samples are retrieved from the 
boreholes for inspection and logging by engineers and subsequent 
testing in our laboratories. 
Standard Penetration test (SPT) 
Hammer weight = 65kg 
- Drop height = 760mm 
- Total penetration is 450mm and the 
number of blows for the last 300mm is 
the SPT’ N’ value. 
Care 
- depth of test vs casing L 
*site supervision 
Laboratory Test 
Triaxial test 
common method to measure the mechanical properties of many 
deformable solids, especially soil (e.g. sand, clay) and rock, and 
other granular materials or powders. 
Unconfined compression 
The objective of the unconfined compression test is to 
determine the UU (unconsolidated, undrained) strength of a 
cohesive soil in an inexpensive manner. 
Building Construction Project 1 
8 
By tsang hao ren
Earthwork Cut and Fill 
Cut and fill 
the process of constructing railway, road or 
canal whereby the amount of material from cuts 
roughly 
matches the amount of fill needed to make 
nearby embankments, so minimizing the amount of 
construction labor. 
Various sections of a roadway design will require 
bringing in earth. Other sections will require earth to 
be removed. 
THE MASS DIAGRAM 
The mass diagram is one method of analyzing 
earthmoving operations. This diagram can tell the 
engineer where to 
use certain types of equipment, the quantities of 
materials needed and the average haul distances etc. 
The mass diagram has many limitations that preclude its use in all 
earthmoving operations. At best, it is merely a 
guide indicating the general manner in which the operations should be 
controlled. 
Building Construction Project 1 
9 
By tsang hao ren
3.0 Foundation 
DEEP foundation 
Deep foundations extend down through unsuitable or unstable soil to transfer building loads to a 
more appropriate bearing stratum. The two principal types of deep foundations are pile 
foundations and caisson foundations. 
This is usually at depths more than 3 meters below the finished ground level.. If unsuitable soils 
are found at the surface, Deep foundations can be used to transfer the loading to a deeper, more 
competent strata at depth. 
Piles caissons 
Caissons are a form of deep 
foundation which are constructed 
above ground level.. A DRILLED, 
CYLINDRICAL FOUNDATION SHAFT 
USED TO TRANSFER LOAD 
THROUGH SOFT STRATA TO FIRM 
STRATA. tHE SHAFT CAN BE 
FILLED WITH EITHER REINFORCED 
OR UNREINFORCED CONCRETE 
A SLENDER TIMBER, CONCRETE OR 
STEEL STRUCTURAL ELEMENT, 
DRIVEN, JETTED, OR OTHERWISE 
EMBEDDED ON END IN THE 
GROUND FOR THE PURPOSE OF 
SUPPORTING A LOAD. 
Building Construction Project 1 
10 
By Yap kar juen
Foundation 
Pile cap foundation on site 
Pile Cap foundations allows any type of structure to be supported 
by layers of soil. When the upper layers of the ground are too soft, 
Pile Cap Foundation is used to provide proper support to the weight 
of the building. These piles will penetrate these 'soft' layers into the 
stronger layers beneath.. 
At our site, deep foundation is applied. The building loads are 
transferred to a better bearing stratum of rock or dense sands and 
gravels below superstructure. 
COLUMN 
PILE CAP 
PILE 
Example of a 4-pile cap 
Photo of a 4-pile cap taken on 
site 
4-pile cap plan drawing 
Building Construction Project 1 
11 
By Yap kar juen
Foundation 
Pile cap structure 
Column load 
Piles are usually driven in 
clusters of two or more 
The reinforced concrete pile 
cap joins the heads of a 
cluster of piles so that the 
load can be distributed from 
a column or grade beam 
equally among the piles. 
Piles are driven into earth 
by pile driver, precast 
concrete piles can be round, 
square, or polygonal cross 
sections or even an open 
core. Precast piles are always 
often prestressed. 
Friction piles is used in our site. It 
depends on the frictional resistance 
of a surrounding earth mass for 
support. The stiffness increases 
when the the depth increases 
A pile foundation is a system of end-bearing 
or friction piles, pile caps and 
also tie beams for transferring the 
building loads to a more suitable bearing 
stratum 
Building Construction Project 1 
12 
By Yap kar juen
Bars evenly distributed on the 
bottom and top surfaces. No lacer 
bars. 
Bottom bars concentrated over the 
piles, top bars under the column. 
Two lacer bars. 
Layout view Layout view 
Foundation 
concrete slab and bars in pile cap 
superstructure 
Reinforced concrete slab with one layer of damp 
proof membrane to engr’s detail.. 
R.C SLAB 
A cONCRETE SLAB IS PLACED AT OR NEAR GRADE 
LEVEL TO SERVE AS A COMBINED FLOOR AND 
FOUNDATION SYSTEM. The sUITABILITY OF the SLAB 
has to depend on the geographic location, topography, 
superstructure design and soil characteristic of site. 
Building Construction Project 1 
13 
By Yap kar juen
1) THE VIBROFLOT IS 
USED TO PENETRATE THE 
LOOSE SOILS TO CREATE 
BORE HOLE 
2) A cONCRETE PLUG IS 
THEN FORMED AT THE 
BASE OF THE BORE HOLE 
TO SEAL CONTAMINANT 
PATHWAYS 
3) THE CONCRETE IS THEN 
REPEATEDLY PENETRATED BY 
THE VIBROFLOT TO COMPACT 
INTO THE SURROUNDING SOILS 
Image above shows a AND FORM AN ENLARGED TOE 
pilling machine 
drop hammer friction piles 
The drop hammer friction piles are at this site. is the most commonly used method of insertion of 
displacement piles. A pile, which is long with a cross section of circle, square or octagon and is usually made 
out of either cement, wood or steel. It is forced vertically to pass through the soil using a pile driver. 
The piles are grouped together and connected by a pile cap if the load is expected to be too large for the 
foundation to take. 
Foundation 
piling 
Building Construction Project 1 
14 
By Yap kar juen
Column footings 
Footings are an important part of foundation construction. The footing is the 
bottom part of the foundation. A footing is typically concrete and typically 
reinforced with steel. The usage of footings is to support the foundation and also 
prevent settling. Footings are very important in areas, which have troublesome soils. 
Placement of footings is very important so that it can provide the proper support 
for the foundation and ultimately the whole structure. 
Vertical reinforcement 
Lateral reinforcement 
steel dowels anchor column to footing 
Critical section for two-way 
shear 
Reinforced concrete column 
Two-way reinforcement uniformly 
spaced 
Foundation 
Building Construction Project 1 
15 
By Yap kar juen
4.0 Beam and ColumnsIntroduction 
Beams 
A beam is a horizontal structural 
element that is capable of 
withstanding load primarily by 
resisting bending. The bending force 
induced into the material of the 
beam as a result of the external 
loads, own weight, span and external 
reactions to these loads is called 
a bending moment. 
Beams and Columns 
Columns 
a Vertical structural element that 
transmits, through compression, the 
weight of the structure above to 
other structural elements below. 
Structural System 
Our site uses a structural system for its building. 
By using in-situ concrete to create the structural 
System of the building. 
Formwork 
temporary or permanent molds into 
which concretes are poured. In the 
context of concrete construction, 
the falsework supports the 
shuttering moulds. 
Building Construction Project 1 
16 
By tsang hao ren
Beam and Columns Structural System 
After completing the footings of the structure, the next step is to create the structural 
system of the building using beams and columns, 
To create the columns,and the 
beam they must firstidentify 
its position according to the 
construction drawings and also 
their foundations 
Building Construction Project 1 
17 
By tsang hao ren
Beam and Columns Structural System 
1. Post Foundation work 
2. Creating Formwork in preparation 
For cement 
3. Poring Cement into formwork 
5. Balance the soil and creating Reinforced 4. Let Concrete dry and remove formwork 
concrete columns 
6. Create beam connected to column to 
support the 2nd floor 
Building Construction Project 1 
18 
By tsang hao ren
Beam and Columns Formwork 
Column Formwork 
Beam Formwork 
A 3-sided box propped in the desired 
measurements. The beam form side have 
to retain the wet concrete and able to 
withstand initial hydrostatic presseure 
of the wet concrete 
This consists of a vertical mold 
of the desired shape and 
measurements. There will be 
bracing, stakes and sole plate 
to help straighten the 
formwork. 
A good formwork should satisfy the following 
requirements: 
1. It should be strong enough to withstand all types 
of dead and live loads. 
2. It should be rigidly constructed and efficiently 
propped and braced both horizontally and 
vertically, so as to retain its shape. 
3. The joints in the formwork should be tight 
against leakage of cement grout. 
4. Construction of formwork should permit removal 
of various parts in desired sequences without 
damage to the concrete. 
5. The material of the formwork should be cheap, 
easily available and should be suitable for reuse. 
6. The formwork should be set accurately to the 
desired line and levels should have plane surface. 
7. It should be as light as possible. 
8. The material of the formwork should not warp or 
get distorted when exposed to the elements. 
9. t should rest on firm base. 
Building Construction Project 1 
19 
By tsang hao ren
5.0 Floor system introduction 
A floor is a horizontal plane in a building that supports both living loads (people, 
furniture/anything moveable) and dead loads (weight of the floor construction itself). 
It acts as the lower enclosing surface of a room. 
It transfers the load horizontally to the beam, column or load bearing wall... 
floor system may composed of:- 
• series of linear beams and joist overlaid with a plane of sheathing 
• Homogeneous slab of reinforced concrete 
Functional requirement of The floor: 
1.Strength and Stability - able to withstand heavy weight of live and dead 
loads, impact to the floor, without breaking/damaged. 
2.Fire resistance - high fire insulation and not combustible. 
3.Damp resistance - Moisture will take the floor damp, cool and uncomfortable 
and may cause decay to the floor finish (I.e timber & carpet) 
4.Sound insulation - thickness of floor affects amount of sound transmitted 
to the lower/upper ground. 
5.Thermal insulation - thickness/material of floor affects the thermal 
insulation. 
Type of floors 
Mud floor 
Brick floor 
Tile floor 
Flagstone floor 
Concrete floor 
Building Construction Project 1 
20 
By cheah teck wei
Floor system in site 
Ground floor: 
Reinforced concrete slab with one layer of damp-proof 
membrane 
Function: 
• Prevent green grows inside building by concrete. 
• Prevent damp from penetrating into the building by the use of 
damp-proof membrane. 
Reason: 
• Cheap and ease of construction 
• Flexibility in finishing available 
• High strength and durable 
Non-suspended cast in-situ concrete 
Section showing component of floor 
Floor slab- 
• Concrete bed with reinforcement inside. 
Screed – 
• to provide smooth surface where floor finish can be applied 
Dpm (damp proof membrane) – 
• prevent moisture from entering the building. 
Blinding – 
• 25-30mm thick weak mortar. 
• to produce a even surface for reinforcement and dpm. 
hardcore – 
• form a dry working surface 
• hard, durable, chemically inert 
• 100-150mm thick 
Building Construction Project 1 
21 
By cheah teck wei
Measure and set 
the area for 
the floor to be 
constructed 
Construct a 
formwork at the 
measured place 
for the floor and 
use sticks to 
secure the 
formwork 
Spacer block and 
brc wire mesh is 
put inside the 
formwork to 
provide 
reinforcement when 
concrete is 
poured. 
By cheah teck 
Mix the cement 
and water to 
create concrete. 
Pour the concrete 
mixture into the 
formwork with brc 
wire mesh. 
Polish and smoothen 
the concrete then 
cover with plastic 
to prevent dust or 
excess water 
affecting the 
drying process thus 
affecting its 
appearance after 
done. 
Remove the 
formwork when 
concrete is dried 
out. 
Apply tiles on the 
concrete to 
produce a 
different finishes 
for the floor.. 
Floor system construction 
Ground floor construction process 
Building Construction 
Project 1 
22 
wei
Floor system in site 
Intermediate floor: 
Reinforced concrete slab 
By cheah teck 
Function: 
• Support their own weight, ceilings and 
superimposed loads. 
• providing lateral restraint to heights 
of external and internal walls. 
• Provides insulation to fire & sound 
• Divides one space to two 
• Act as ceiling to the lower floor 
• Space between floors and ceiling will 
accommodate the building services 
features such as electrical, 
telephone wirings etc. 
Mild steel main 
reinforcement 
bars 
Mild steel 
distribution 
bars 
Two-way slab & beam 
• Const5ructed with four column with 
supporting beams connecting each of them 
forming a square or nearly square bays. 
• Reinforcement is cast in two direction to 
the supporting beam and column. 
• Effective to medium to heavy load. 
• High resistance to lateral force. 
Most efficient when spanning square or nearly 
square bays. 
Tensile 
reinforcemen 
t 
Building Construction 
Project 1 
23 
wei
Floor system construction 
Intermediate floor construction 
Timber formwork is set 
up on the area for the 
upper floor. 
Rebars are placed 
equally on the formwork 
to provide reinforcement 
to the slab structure, 
increasing its tensile 
strength.. 
By cheah teck 
Concrete mixture is then 
poured onto the whole 
structure evenly then 
allowed to dry out. 
The structure is then 
done available for 
floor finishes to be 
carried out. 
Timber formworks. 
process 
Building Construction 
Project 1 
24 
wei
6.0 WALL introduction 
introduction 
By cheah teck 
A wall is the vertical planes that defines the 
volume of mass and space in a building with 
the combination of overhead plane and base 
plane. 
Walls are placed in 
Interior (wall/partitions) 
• Subdivides the space in the building 
• Can be structural or non-bearing 
• Provide required degree of acoustical separation 
• Accommodation of necessary electrical and mechanical 
services 
Exterior wall 
• Able to withstand horizontal wind loading 
• Can serve as shear walls and transfer lateral wind and 
seismic forces to the ground foundation if rigid 
enough 
• Act as protective shield against weather. 
• Insulation toward air, sound, damp, moisture and 
heat. 
• Able to support the weight of building or non bearing 
Type of walls: 
• Concrete wall 
• Masonry wall 
• Dry wall 
• Glass wall 
• Curtain wall 
a wall can be a: 
a Load bearing 
wall-a wall that 
bears some of the 
buildings weight 
and its own 
weight. 
a Non-load bearing 
wall-bears only 
its own weight. 
Building Construction 
Project 1 
25 
wei
Wall in site 
Masonry Walls 
Characteristics 
• Durable, good sound insulation, fire insulation 
and thermal insulation. 
• Offers great flexibility in form and 
appearance 
• Can be either load bearing or non-load 
bearing 
• Easy and cheap construction 
• Made by solid cement sand brick (standard 
modular 3.5x2.5x7.5) 
By cheah teck 
7.5 
3.5 
2.5 
Standard dimension 
of brick 
Type of brick bonds Type of brick joints 
Building Construction 
Project 1 
26 
wei
Wall details 
Fire rated party 
wall 
ENGLISH BOND 
• Named 9-inches brick among 
the field. 
• Used on walls that separates 
each shop unit as it 
provides better fire 
insulation with its extra 
thickness. 
• Considered as the strongest 
bond among others 
• Non-load bearing wall 
• Solid wall 
English Bond brickwork 
has alternate courses 
of headers and 
stretchers in which the 
headers are centered 
on stretchers and the 
joints between 
stretchers line up 
vertically in all 
2134 
courses. 230mm thick fire rated 
party wall with 230mm 
high clay brick above 
roof with 19mm thick 
cement plaster on both 
side. 
Building Construction 
Project 1 
By cheah teck 
27 
wei
Wall details 
High brick wall 
RUNNING/stretcher BOND 
• Used on walls that is located 
in a shop unit. 
• Not as thick as English bond 
thus providing lesser fire 
insulation (thinnest type of 
bond) 
• acting mainly as space 
divider. 
• Non-load bearing wall 
• Solid wall. 
• Simplest and cheapest bond 
among other bonds. 
• Brick on upper level is 
placed at the joint of two 
bottom bricks. 
2134 
115mm thick high 
brick wall with 19mm 
thick cement plaster on 
both side. 
Building Construction 
Project 1 
By cheah teck 
28 
wei
Wall construction 
By cheah teck 
1. Lay out the brick on a dry 
run to ensure the location of 
wall is placed correctly. 
2. Take out the bricks and 
apply a -inch thick mortar 
bed on it. 
3. Line up the brick and push 
it into the mortar leaving 
creating a 3/8-inch joint 
between each bricks. 
4. Check the bricks with a 
level and scrape off the 
excess mortar that squeezes 
off from the joints. 
5. The brickwork is started from 
each end toward the middle. 
The last brick of a level is 
called the closure brick. 
Trim the brick if it cant 
fit into the space. 
6. Apply mortar on both ends of 
the brick and slowly push to 
fit into the space. 
7. Ensure the reinforced steel 
bars from the concrete column 
are fitted in between the 
brick levels to increase the 
tensile strength of the wall. 
8. While the wall is complete, 
scrape off all the excess 
mortar from the joints. 
Masonry wall construction process 
Building Construction 
Project 1 
29 
wei
Wall example 
Concrete wall 
By chua jiu xin 
Concrete wall is a wall built by pouring concrete 
mixtures into a model/formwork with reinforcement 
bars then let dried forming a strong structure. 
Three types of concrete wall 
construction 
1. cast in-situ reinforced concrete 
(reinforced concrete) frame with rc infill 
panel walls 
2. cast in-situ shear wall 
3. pre-cast concrete walls 
Type of formworks 
1. Timber formwork 
2. Aluminium system 
formwork 
3. Modular steel 
formwork 
characteristic 
• Most built as load bearing wall due to 
its structural strength. 
• Various texture and appearance can be 
achieved by the use of formwork, 
admixtures and additives. 
• Cheap and ease of construction. 
Different texture of concrete 
wall 
Timber 
formwork 
Aluminium 
system 
formwork 
Modular steel 
formwork 
Building Construction 
Project 1 
30
7.0 STAIRCASE 
introduction 
A Introduction 
By chua jiu xin 
Staircase is a flight or series of flights of steps and a 
supporting structure connecting spaces between one level 
to another. It changes the overall circulation of a 
building. 
A There are many types of staircase constructed in 
different way using different type of material. 
Type of staircases 
Staircase 
material: 
• Concrete staircase 
• Timber staircase 
• Glass staircase 
• Steel staircase 
Building Construction 
Project 1 
31
STAIRCASE in site 
Half turning 
staircase 
Turns 180-degrees through 
two right-angles at 
intervening landings. 
Straight staircase 
A Straight staircase that 
extends from one level to 
another without turns or 
winder. 
Dimensions 
Riser = 160mm 
Tread = 255 + 
25mm 
Nosing = 915mm 
high ms 
handrail 
Total step = 20 
Dimensions 
By cheah teck 
Riser = 175.8mm 
Tread = 255 + 
25mm 
Nosing = 915mm 
high ms 
handrail 
Total step = 26 
5487 
8839 
4115 
Building Construction 
Project 1 
32 
wei
STAIRCASE construction 
A timber formwork 
is set up on the 
proposed area 
for the 
staircase. 
Every pieces for 
each step is 
placed properly 
to ensure 
accurate 
positioning and 
measurement.. 
Rebars were 
placed in the 
timber formwork to 
provide 
reinforcement for 
the structure 
(resist tensile 
force and shear) 
By cheah teck 
Concrete is 
poured into the 
formwork and thus 
removed after 
dried. . 
In situ cast concrete staircase 
construction process 
Building Construction 
Project 1 
33 
wei
STAIRCASE example 2 
Timber staircase 
By chua jiu xin 
A timber staircase is a staircase constructed using 
timbers. 
A Basically they share the same function but based on 
their materiality, they have different texture, 
sensory, durability, maintenance methodology and 
etc. 
A Hardwood is frequently used in constructing a timber 
staircase 
A Every 3-6 months should be maintenance once to 
ensure the timber is in good condition as timber is 
affected by the 
Humidity, ambience of air, insect and etc. 
Sr 
. 
No 
. 
Type of arrangement of staircase 
Wooden Staircase RCC Staircase 
1 Wooden staircase is 
relatively weaker. 
RCC staircase is relatively 
stronger. 
2 Construction time is 
relatively less. 
Cement setting takes at least 
21 days. Hence construction 
time is more. 
3 Timber has a life. It 
becomes weak after about 
70 to 80 years 
RCC hardens with age. The 
process of hardening 
continues forever increasing 
its strength. 
4 The appearance and the 
colour of the timber can 
be attractive. 
RCC staircase can be made 
attractive by cladding and 
other decorations. 
5 Timber staircases are 
light in weight 
These are heavier in 
weight. 
6 Timber is costlier than 
RCC. 
RCC is cheaper than timber. 
7 These are fire hazardous These cannot catch fire. 
Compare the advantages and disadvantages of the Wooden 
Staircase over the RCC staircase. 
8 These are sound and heat 
insulators. 
Comparatively lesser 
insulators. 
Building Construction 
Project 1 
34
DOORS 
Doors function as an entrance to a space and acts as a barrier that swings, slides 
or folds. Doors could be made of an assembly of timber, metal, or composite 
materials. Doors play a very important role in influencing the circulation system. 
Components of a door 
head 
stop 
jamb 
architrave 
sill 
Single door 
leaf 
wall 
architrave 
Door 
panel 
Main frame 
Sub frame 
nail 
Section of door frame 
8.0 doors 
Building Construction 
Project 1 
35 
By lim ming 
chek
DOOR operation 
Single leaf swinging door 
- Only one door leaf used. 
- Door leaf is hinged to the door frame. 
- Operational space required. 
DOOR details 
A. Jambs can be 
attached to the 
floor with 
powder-driven 
fasteners. 
Solid core 
door 
b. Reinforcement 
of jamb at hinge 
attachments 
c. Loose sheet 
metal tees are 
inserted into 
the frame and 
built into 
mortar joints to 
anchor jambs 
onto masonry 
walls 
The door also uses a double rabbet frame. 
Building Construction 
Project 1 
36 
By lim ming 
chek
DOORS PROCESS 
By lim ming 
Sub frame is installed prior to the main frame. This is done so that the main 
frame is less likely to shrink as it does not come in contact with the masonry wall. 
The door frame is also not stained by paint or cement mortar. Floor finishes are 
also easier to be installed as it does not need to suit the door frame profile. 
Step 1 - The location of the door is 
measured and marked according to the 
dimensions stated at the approved construction 
drawing. A few layers of brick are then 
laid by its side. 
Step 2  Frame of the door is then slotted 
into the measured space. The jamb of the 
door is nailed into the masonry wall for 
support purposes and bricks are continued to 
be laid. 
Building Construction 
Project 1 
37 
chek
Step 3  A pre-cast concrete lintel with same 
width and length of the door is bound with 
mortar and placed on top of the door head. 
The lintel is constructed to prevent the door 
frame from excessive vertical force and 
affect its ease of operation. 
Step 4  For timber door frame, the wall is 
plastered and the main frame is installed. 
For aluminium door frame however, the space 
between the masonry wall is filled with mortar 
before the wall is plastered. 
By lim ming 
Cement 
mortar 
Aluminium 
frame 
Building Construction 
Project 1 
38 
chek
Step 5  Shims are placed on the hinge side 
of the door and form a continuous gap in 
between. The hinge is then nailed into the 
side door jamb. 
Step 6  To ensure that the cracks and flaws 
in joining is hidden particularly for timber 
door frame as the wood will season and shrink 
after some time thus exposing cracks, the 
architrave is installed. 
Advantages of Using Aluminium Frame 
- Low maintenance frame. 
- High resistance to corrosion. 
- Strong and economical. 
- Environmentally sustainable material. 
- Easy to install due to its flexibility. 
Building Construction 
Project 1 
By lim ming 
39 
chek
Aluminium door frames. Double rabbet door 
frames slotted into 
measured space. 
By lim ming 
Wall completed with 
lintel seen for support. 
Building Construction 
Project 1 
40 
chek
By lim ming 
Roller shutters which consist of many 
horizontal slats hinged together are 
also used as the main as well as the 
back entrance. It is attached to a 
beam to support it. The door is 
raised to open and lowered to close 
it. 
Building Construction 
Project 1 
41 
chek
WINDOWS 
INSTALLATION OF WINDOW 
Step 1: Check the 
rough opening 
Measure the width of 
the rough opening at 
the top, middle, and 
bottom and the height 
at both sides and in the 
middle. 
Step 2: Protect against 
water infiltrationCut a 
strip of self-adhering 
waterproof membrane. 
Center the membrane under 
the rough opening and 
adhere it to the existing 
builder's felt 
STEP 3: check the 
perpendicularity 
By liau wen bin 
Step 4: drill a hole through 
between frame and wall 
the existing hole from 
the frame 
STEP 5: place a fischer 
through the hole 
Step 6: Install Window STEP 7: Finish the wall 
with sealant or mortar 
Building Construction 
Project 1 
42
windows 
By liau wen bin 
Window is an opening in a wall or other structures that is operable in opening and 
closing mechanism. It is the connection between interior and exterior space by 
allowing the passage of natural light, solar heat, air movement and also 
provide a view. Windows are undoubtedly important in achieving quality of life 
and comfort in buildings. 
TYPES OF WINDOWS 
An awning window is hinged at the top and 
opens outward.The glass protects the opening 
like an awning, enabling ventilation even 
dying rainy weather. It can be placed high 
on the wall to let in both light and air. 
Generally, awning windows are opened with a 
hand crank. Screens are on the inside of 
the window, where they are more protected 
from the elements. 
awning windows in side elevation (PART) 
When open, the sash is 
able to direct 
ventilation. The 
sashes may be stacked 
vertically with sashes 
closing on each other 
or on meeting sites. 
Hinged at the top and 
open outwardly because 
the sash closes by 
pressing against the 
frame. They generally 
have lower air leakage 
rates than sliding 
windows. 
Sash 
Hinge SLIDE 
Hinge TRACK 
JAMB 
RETAINER CLIP 
Hinge arm 
Building Construction 
Project 1 
43
WINDOWS 
OTHER TYPES OF WINDOWS 
Fixed 
windows 
Fixed windows consist of a 
frame and stationary sash. 
When used in conjunction with 
operable window units, the 
thickness of the fixed sash 
should approximate the cross-sectional 
dimension of the 
operating sashes, 
Jalousie windows have 
horizontal glass or wood 
louvers that pivot 
simultaneously in a common 
frame. 
Jalousies are used 
primarily in mild climates 
to control ventilation and 
to cut off visibility from 
the outside 
By liau wen bin 
Completion of construction 
showing multiple awning 
windows 
Jalousie windows 
Building Construction 
Project 1 
44
9.0 Roofing system 
Definition of roof 
By chew ung 
A roof is part of a building envelope that covering on the uppermost part of a 
building or shelter which include exterior surface and its supporting 
structures. It must be able carry its own weight, additional attached 
equipment and accumulated rain. Furthermore, it must be able to resist wind 
pressure 
Basic function of roof 
 Able to resist the passage of moisture to the inside of 
building. 
 Able to withstand atmospheric pollution, frost and 
other harmful condition 
 To prevent the spread of fire over the roof and 
from one building to another. 
 Thermal insulation is required to reduce heat losses 
and prevent excessive solar heat gains in hot 
weather. 
 Sound insulation is rarely an important consideration 
in roof design. 
TYPE OF ROOF 
There are different kind of roof (refer diagram2). The shape of roofs differs 
greatly from region to region and it affects the overall appearance of a 
home. The main factor which influence the shape of roofs are the climate and 
the materials available and the outer covering, appearance and aesthetics, 
maintenance and costing 
Components of roof 
Building Construction 
Project 1 
45 
heng
Introduction of Flat Roof 
By chew ung 
A flat roof is a roof which is almost level in contrast to the many types of sloped 
roofs. The slope of a roof is properly known as its pitch and flat roofs have up 
to approximately 10.Flat roofs are an ancient form mostly used in arid climates 
and allow the roof space to be used as a living space or a living roof. 
Introduction of Butterfly Roof 
A roof shape which has two surfaces that rise from the centre to the eaves 
with a valley in the centre, resembles the wings of a butterfly. 
TYPE: 
The shop lots use two kinds of roof which are Reinforced concrete flat roof and 
butterfly roof at the top of those shop lots 
Elevation 
Reinforce 
concrete 
Flat roof 
Roof plan 
flat roof Butterfly roof 
flat 
roof 
Butterfly 
Roof 
Building Construction 
Project 1 
46 
heng
TYPE OF FLAT ROOF 
By chew ung 
Most of the materials that used in the flat roof provide insufficient 
resistance to the transfer of heat to meet the requirement of the building 
regulations. Therefore an insulating layer is needed. The position of the 
insulation will define the type of flat roof. 
Warm Roof 
• Sandwich Roof 
• Inverted Roof 
Cold roof 
(ventilated 
roof) 
Membranes of flat roof 
1.BUR ( built up membrane ) 
2.Modified bitumen membrane 
3.Single-Ply Membranes 
1 
Type of flat roof 
of shop lots in 
2 
3 
Metal panel ( Galvanized steel panels ) 
Steel is defined as any alloy of iron with content of 2 percent and below. Steel 
is strong in both compression and tension. Galvanized steel is kind of steel that is 
coated in zinc which can prevent rust. The process is achieved through hot dip 
galvanizingCorrugated roofing panels span between beams or purlins running across 
the slope. The roofing panels can be aluminium, corrugated structural glass, 
fibreglass or in the case of the shop lots in Banting, galvanized steel. 
Corrugated Glass 
Panels 
Aluminium PanelsFibreglas 
s panels 
Galvanized 
steel 
Type of 
roof that 
used to 
roofing 
the shop 
lots in 
Banting 
banting 
Building Construction 
Project 1 
47 
heng
Roof details 
elevation 
sectio 
n 
Roof plan 
By chew ung 
The insulation is below the deck of 
the roof in Banting can be 
considered as a cold roof. The roof 
is covered by blue Galvanized steel 
panels. 
Corrugate 
d Roofing 
Performed 
closure 
strip to 
seal the 
openings of 
corrugation 
against 
wind-driven 
rain 
Flashing 
sheet 
Steel 
cee 
purlin 
Roof 
beam 
insulati 
on 
Components of 
flat roof 
Panel 
Building Construction 
Project 1 
48 
heng
Construction of Concrete Reinforced 
Flat roof 
1. Temporary propping or 
scaffolding is required 
and set up to support the 
framework 
By yap chein 
2. The joist of the roof is connected to the 
wall by metal wall plates, is slope to create 
a fall, which supported below by the 
concrete roof beam 
3. The Metal panels is added to cover the 
roofing 
Steel Bar 
Concealed, 
floating 
clips 
attach the 
G.S panels 
to the 
framework 
Panels 
overla 
p each 
other 
to 
concea 
l the 
roof 
clips 
4. Steel bar to join the metal 
wall plates to fix the shape of 
the roof 
Roof 
panels 
are 
seamed 
togeth 
er with 
a 
mechan 
ical 
seamer 
Roofing method 
Fall 
creating by 
sloping the 
joist 
Galvanize 
d steel 
panels 
1 2 
3 
Building Construction 
Project 1 
49 
wee
Butterfly Roof 
By yap chein 
Butterfly Roof basic structure 
A butterfly roof consists of two roofs 
joined at their low points to form a 
valley, which sometimes serves as a 
reservoir. The angle of the two roofs is 
determined by the architect or designer, 
but it typically creates slight but 
visually discernible slopes that give the 
building a more modern and less angular 
appearance than that of a traditional 
roof. 
Butterfly roof versions 
Several unique styles of roofs have 
emerged based on the atypical pitches of 
butterfly roofs. A shed roof has a single 
slope and typically includes the slope at 
different levels on top of the building. A 
saddle roof is shaped like a Western style 
saddle used to ride a horse, with a convex 
curve on one side of the axis and a 
concave curve on the other. Gabled 
butterfly roofs generally have a 
triangular sloping roof attached to a flat 
roof with windows placed near the top of 
the walls beneath it. Zigzag roofs look 
like the edge of a saw blade, with many 
acutely angled peaks in a row. Architects 
sometimes mix and match roofs of different 
pitches on a single structure. 
Details of butterfly 
roof 
Valley 
gutter 
Two roofs joined 
at their low points 
to form a valley 
Building Construction 
Project 1 
50 
wee
Reference 
EARTHWORK 
1)Fundamentals of building construction by edward allen josepg iano 
2)Construction methods and planning j.r. illingworth 
3)Building construction illustrated by francis d.k.ching 
Foundation 
1)http://constructionduniya.blogspot.com/2012/02/pile-foundations.html 
2)BUILDING CONSTRUCTION ILLUSTRATED BY FRANCIS D.K. CHIING 
3)http://tgbuilders.co.uk/our-services/foundation/ 
SUPERSTRUCTURE 
-BEAM AND COLUMN 
1) Building conctruction illustrated by francis d.k. ching 
-Floor 
1)https://www.dlsweb.rmit.edu.au/toolbox/buildright/content/bcgbc4010a/10_flo 
or_systems/topic_index.htm 
2)Building construction illustrated by francis d.k. ching 
-Wall 
1)http://www.wbdg.org/design/env_wall_masonry.php 
2)http://www.understandconstruction.com/walls.html 
3)Building construction illustrated by francis d.k. ching 
-Staircase 
1) Building construction illustrated by francis d.k. ching 
Building Construction 
Project 1 
51
Reference 
-door and windows 
1)http://free-ed.net/free-ed/ 
Resources/Trades/carpentry/Building01/?iNum=1102 
2)Fundamentals of building construction by edward allen joseph iano 
-roof 
1)http://www.the-flat-roof.co.uk/Sect3_6.pdf 
2)http://www.buildingregs4plans.co.uk/guidance_flat_roof_types.php 
3) 
http://learn.hackney.ac.uk/pluginfile.php/14157/mod_resource/content/0/The 
ory/FirstYearTheory11.pdf 
Building Construction Project 1

More Related Content

What's hot

Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction reportClara Lee
 
Final slides
Final slidesFinal slides
Final slideshongbinng
 
Bcon revised
Bcon revisedBcon revised
Bcon revisedKen Wong
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1KohSungJie
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Dexter Ng
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II ReportBolin Loong
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1Cryslyn Tan
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1Alexis Wei
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...aarenneoone
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Darshiini Vig
 
BUILDING CONSTRUCTION
BUILDING CONSTRUCTION BUILDING CONSTRUCTION
BUILDING CONSTRUCTION Eric Lo
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group reportXingYue0907
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing ConstructionLek Yuen
 

What's hot (15)

Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction report
 
Final slides
Final slidesFinal slides
Final slides
 
Bcon revised
Bcon revisedBcon revised
Bcon revised
 
Be con
Be con Be con
Be con
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
Bcon draft
Bcon draftBcon draft
Bcon draft
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1
 
BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1BUILDING CONSTRUCTION 1
BUILDING CONSTRUCTION 1
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
BUILDING CONSTRUCTION
BUILDING CONSTRUCTION BUILDING CONSTRUCTION
BUILDING CONSTRUCTION
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group report
 
Project 01 - Experiencing Construction
Project 01 - Experiencing ConstructionProject 01 - Experiencing Construction
Project 01 - Experiencing Construction
 

Viewers also liked

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Planning Structures
Planning StructuresPlanning Structures
Planning StructuresVIVA_EAST
 
Design brief & specification
Design brief & specificationDesign brief & specification
Design brief & specificationhaobinliu
 
Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Anthony Chew
 
B sc (hons)(arch) tau arc61301 project mac 2016 (2)
B sc (hons)(arch)  tau arc61301 project mac 2016 (2)B sc (hons)(arch)  tau arc61301 project mac 2016 (2)
B sc (hons)(arch) tau arc61301 project mac 2016 (2)Anthony Chew
 
Arc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalArc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalAnthony Chew
 
Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Anthony Chew
 
The idea journal 3
The idea journal 3The idea journal 3
The idea journal 3Anthony Chew
 
Cts performance day
Cts performance dayCts performance day
Cts performance dayAnthony Chew
 
The idea journal 2
The idea journal 2The idea journal 2
The idea journal 2Anthony Chew
 
Arc1126 project 2b retreat house at fraser s hill
Arc1126 project 2b retreat house at fraser s hillArc1126 project 2b retreat house at fraser s hill
Arc1126 project 2b retreat house at fraser s hillAnthony Chew
 
Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015Anthony Chew
 
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)Anthony Chew
 
Asian architecture
Asian architectureAsian architecture
Asian architectureAnthony Chew
 

Viewers also liked (20)

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Planning Structures
Planning StructuresPlanning Structures
Planning Structures
 
Design brief & specification
Design brief & specificationDesign brief & specification
Design brief & specification
 
Ch 7 design of rcc footing
Ch 7 design of rcc footingCh 7 design of rcc footing
Ch 7 design of rcc footing
 
Ici p1 0413
Ici p1 0413Ici p1 0413
Ici p1 0413
 
Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014Building con 1 (arc 1523) project 1 brief aug 2014
Building con 1 (arc 1523) project 1 brief aug 2014
 
B sc (hons)(arch) tau arc61301 project mac 2016 (2)
B sc (hons)(arch)  tau arc61301 project mac 2016 (2)B sc (hons)(arch)  tau arc61301 project mac 2016 (2)
B sc (hons)(arch) tau arc61301 project mac 2016 (2)
 
Arc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief finalArc60103 (arc1313) 1 april 2014 project brief final
Arc60103 (arc1313) 1 april 2014 project brief final
 
Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015Project 1 sketchbook and journal jan2015
Project 1 sketchbook and journal jan2015
 
Project 1 brief
Project 1 briefProject 1 brief
Project 1 brief
 
Idj 02
Idj 02Idj 02
Idj 02
 
The idea journal 3
The idea journal 3The idea journal 3
The idea journal 3
 
Project 1
Project 1Project 1
Project 1
 
Cts performance day
Cts performance dayCts performance day
Cts performance day
 
The idea journal 2
The idea journal 2The idea journal 2
The idea journal 2
 
Arc1126 project 2b retreat house at fraser s hill
Arc1126 project 2b retreat house at fraser s hillArc1126 project 2b retreat house at fraser s hill
Arc1126 project 2b retreat house at fraser s hill
 
Project2 brief
Project2 briefProject2 brief
Project2 brief
 
Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015Project 1 brief b.services aug 2015
Project 1 brief b.services aug 2015
 
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)B sc (hons)(arch)  asian architecture arc60403 outline aug 2015 (2)
B sc (hons)(arch) asian architecture arc60403 outline aug 2015 (2)
 
Asian architecture
Asian architectureAsian architecture
Asian architecture
 

Similar to Banting Site Introduction

Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing ConstructionSNLim125
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
BCON I PROJECT 1
BCON I PROJECT 1BCON I PROJECT 1
BCON I PROJECT 1dtan97
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Civil Engineering Technology (Fawzan Fahry)
Civil Engineering Technology  (Fawzan Fahry)Civil Engineering Technology  (Fawzan Fahry)
Civil Engineering Technology (Fawzan Fahry)FAwzan Mohamad
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionYung Kai
 
Building Construction Details
Building Construction DetailsBuilding Construction Details
Building Construction Detailscocongkening
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstructionvietcgxd
 
Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Sumit Modi
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports ssuser061280
 
B.con slide
B.con slideB.con slide
B.con slideTeh Yang
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES Saleh Ahmed
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report I'mMiss Lily
 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONIRJET Journal
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101SHAZEBALIKHAN1
 

Similar to Banting Site Introduction (20)

Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing Construction
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
BCON I PROJECT 1
BCON I PROJECT 1BCON I PROJECT 1
BCON I PROJECT 1
 
Construction site
Construction siteConstruction site
Construction site
 
Civil Engineering Technology (Fawzan Fahry)
Civil Engineering Technology  (Fawzan Fahry)Civil Engineering Technology  (Fawzan Fahry)
Civil Engineering Technology (Fawzan Fahry)
 
Building Economics
Building EconomicsBuilding Economics
Building Economics
 
Final slides
Final slidesFinal slides
Final slides
 
Building Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience ConstructionBuilding Contruction 1 Project 1: Experience Construction
Building Contruction 1 Project 1: Experience Construction
 
Building Construction Details
Building Construction DetailsBuilding Construction Details
Building Construction Details
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892Report 150720083151-lva1-app6892
Report 150720083151-lva1-app6892
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports
 
BCON PJT 1
BCON PJT 1BCON PJT 1
BCON PJT 1
 
B.con slide
B.con slideB.con slide
B.con slide
 
B.con slide
B.con slideB.con slide
B.con slide
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATIONSOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
SOIL EXPLORATION AND GEOTECHNICAL DESIGN OF A FOUNDATION
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
 

More from dicky177

Presentation5
Presentation5Presentation5
Presentation5dicky177
 
Presentation6
Presentation6Presentation6
Presentation6dicky177
 
Presentation4
Presentation4Presentation4
Presentation4dicky177
 
Presentation7
Presentation7Presentation7
Presentation7dicky177
 
Presentation3
Presentation3Presentation3
Presentation3dicky177
 
Presentation2
Presentation2Presentation2
Presentation2dicky177
 
Presentation1
Presentation1Presentation1
Presentation1dicky177
 
Presentation3
Presentation3Presentation3
Presentation3dicky177
 
Presentation2
Presentation2Presentation2
Presentation2dicky177
 
Living room perspective
Living room perspectiveLiving room perspective
Living room perspectivedicky177
 
Bedroom perspective
Bedroom perspectiveBedroom perspective
Bedroom perspectivedicky177
 
Bedroom perspective
Bedroom perspectiveBedroom perspective
Bedroom perspectivedicky177
 
Living room perspective
Living room perspectiveLiving room perspective
Living room perspectivedicky177
 
Progress 1
Progress 1Progress 1
Progress 1dicky177
 
Progress 2
Progress 2Progress 2
Progress 2dicky177
 
Progress 1
Progress 1Progress 1
Progress 1dicky177
 

More from dicky177 (20)

Presentation5
Presentation5Presentation5
Presentation5
 
Presentation6
Presentation6Presentation6
Presentation6
 
Presentation4
Presentation4Presentation4
Presentation4
 
Presentation7
Presentation7Presentation7
Presentation7
 
Presentation3
Presentation3Presentation3
Presentation3
 
Presentation2
Presentation2Presentation2
Presentation2
 
Presentation1
Presentation1Presentation1
Presentation1
 
Presentation3
Presentation3Presentation3
Presentation3
 
Presentation2
Presentation2Presentation2
Presentation2
 
1111
11111111
1111
 
Living room perspective
Living room perspectiveLiving room perspective
Living room perspective
 
Bedroom perspective
Bedroom perspectiveBedroom perspective
Bedroom perspective
 
Bedroom perspective
Bedroom perspectiveBedroom perspective
Bedroom perspective
 
Living room perspective
Living room perspectiveLiving room perspective
Living room perspective
 
Progress 1
Progress 1Progress 1
Progress 1
 
Progress 2
Progress 2Progress 2
Progress 2
 
Progress 1
Progress 1Progress 1
Progress 1
 
Sem2.5.
Sem2.5.Sem2.5.
Sem2.5.
 
Sem2.5
Sem2.5Sem2.5
Sem2.5
 
Sketches
SketchesSketches
Sketches
 

Recently uploaded

Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Parkjosebenzaquen
 
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call GirlsPragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Call Girls in Islamabad | 03274100048 | Call Girl Service
Call Girls in Islamabad | 03274100048 | Call Girl ServiceCall Girls in Islamabad | 03274100048 | Call Girl Service
Call Girls in Islamabad | 03274100048 | Call Girl ServiceAyesha Khan
 
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | DelhiMalviyaNagarCallGirl
 
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiMalviyaNagarCallGirl
 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMroute66connected
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akolasrsj9000
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiMalviyaNagarCallGirl
 
Call Girl Service in Karachi +923081633338 Karachi Call Girls
Call Girl Service in Karachi +923081633338 Karachi Call GirlsCall Girl Service in Karachi +923081633338 Karachi Call Girls
Call Girl Service in Karachi +923081633338 Karachi Call GirlsAyesha Khan
 
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl service
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl serviceDelhi Room Call Girls : ☎ 8527673949, Low rate Call girl service
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl serviceashishs7044
 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...akbard9823
 
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiMalviyaNagarCallGirl
 
Strip Zagor Extra 322 - Dva ortaka.pdf
Strip   Zagor Extra 322 - Dva ortaka.pdfStrip   Zagor Extra 322 - Dva ortaka.pdf
Strip Zagor Extra 322 - Dva ortaka.pdfStripovizijacom
 
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call GirlsKishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Karachi Escorts | +923070433345 | Escort Service in Karachi
Karachi Escorts | +923070433345 | Escort Service in KarachiKarachi Escorts | +923070433345 | Escort Service in Karachi
Karachi Escorts | +923070433345 | Escort Service in KarachiAyesha Khan
 
FULL ENJOY - 9953040155 Call Girls in Shahdara | Delhi
FULL ENJOY - 9953040155 Call Girls in Shahdara | DelhiFULL ENJOY - 9953040155 Call Girls in Shahdara | Delhi
FULL ENJOY - 9953040155 Call Girls in Shahdara | DelhiMalviyaNagarCallGirl
 
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...akbard9823
 
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?kexey39068
 

Recently uploaded (20)

Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Park
 
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call GirlsPragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
 
Call Girls in Islamabad | 03274100048 | Call Girl Service
Call Girls in Islamabad | 03274100048 | Call Girl ServiceCall Girls in Islamabad | 03274100048 | Call Girl Service
Call Girls in Islamabad | 03274100048 | Call Girl Service
 
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in New Ashok Nagar | Delhi
 
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
 
Roadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NMRoadrunner Lodge, Motel/Residence, Tucumcari NM
Roadrunner Lodge, Motel/Residence, Tucumcari NM
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
 
Dxb Call Girls # +971529501107 # Call Girls In Dxb Dubai || (UAE)
Dxb Call Girls # +971529501107 # Call Girls In Dxb Dubai || (UAE)Dxb Call Girls # +971529501107 # Call Girls In Dxb Dubai || (UAE)
Dxb Call Girls # +971529501107 # Call Girls In Dxb Dubai || (UAE)
 
Call Girl Service in Karachi +923081633338 Karachi Call Girls
Call Girl Service in Karachi +923081633338 Karachi Call GirlsCall Girl Service in Karachi +923081633338 Karachi Call Girls
Call Girl Service in Karachi +923081633338 Karachi Call Girls
 
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl service
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl serviceDelhi Room Call Girls : ☎ 8527673949, Low rate Call girl service
Delhi Room Call Girls : ☎ 8527673949, Low rate Call girl service
 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
 
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
 
Strip Zagor Extra 322 - Dva ortaka.pdf
Strip   Zagor Extra 322 - Dva ortaka.pdfStrip   Zagor Extra 322 - Dva ortaka.pdf
Strip Zagor Extra 322 - Dva ortaka.pdf
 
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call GirlsKishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
 
Karachi Escorts | +923070433345 | Escort Service in Karachi
Karachi Escorts | +923070433345 | Escort Service in KarachiKarachi Escorts | +923070433345 | Escort Service in Karachi
Karachi Escorts | +923070433345 | Escort Service in Karachi
 
FULL ENJOY - 9953040155 Call Girls in Shahdara | Delhi
FULL ENJOY - 9953040155 Call Girls in Shahdara | DelhiFULL ENJOY - 9953040155 Call Girls in Shahdara | Delhi
FULL ENJOY - 9953040155 Call Girls in Shahdara | Delhi
 
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...Patrakarpuram ) Cheap Call Girls In Lucknow  (Adult Only) 🧈 8923113531 𓀓 Esco...
Patrakarpuram ) Cheap Call Girls In Lucknow (Adult Only) 🧈 8923113531 𓀓 Esco...
 
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?
How Can You Get Dubai Call Girls +971564860409 Call Girls Dubai?
 

Banting Site Introduction

  • 1. SITE INTRODUCTION THE SITE THAT WE RESEARCH ON IS LOCATED AT THE CITY CENTRE OF BANTING .THE SITE IS CONNECTED WITH THE KLANG BANTING HIGHWAY THAT PASS THROUGH MAJOR INTERSECTION OF JALAN BANTING-SEMENYIH . THE ROADS SURROUNDING THE SITE 1. NORTH-JALAN BUNGA PEKAM 2. SOUTH-JALAN SUASA 3. EAST-JALAN BUNGA PEKAN 9 4. WEST-JALAN GANGSA 1. STATE 2. DISTRICT 3. CITY 4. NO.LOT 5. AREA 6. TYPE OF BUILDING 7. COMPANY -SELANGOR DARUL EHSAN -KUALA LANGAT -BANTING -PT 791, SEKSYEN 3 -21632 METER SQUARE -SHOPLOTS -EHSAN ISTIMEWA SDN.BHD. DISTANCE BETWEEN THE SITE AND OTHER MAJOR DEVELOP CITY • 30KM AWAY FROM KLIA (KULA LUMPUR INTERNATIONAL AIRPORT) • 25KM AWAY FROM PUTRAJAYA • 35KM AWAY FROM SHAH ALAM • 60KM AWAY FROM KUALA LUMPUR Building Construction Project 1 1 Building Construction Project 1 By yap chein wee
  • 2. Index page Introduction to site topic 1 : site plan and site safety Topic 2 : Earthwork topic 3 : foundation topic 4 : beams and column topic 5 : floor system topic 6 : wall system topic 7 : staircase topic 8 : door and window topic 9 : roof system Building Construction Project 1 2 Building Construction Project 1
  • 3. 1.0 Site plan Building Construction Project 1 3 By chua jiu xin
  • 4. Site safety 1.0 site plan 1.1 Introduction to site safety Construction sites contain many risks that faced by both of the construction workers and the general public. A construction site is legally required to follow the regulations and guidelines set by the department of occupational safety and Health and other government agencies to ensure the safety of the workers and public. These guidelines apply to all work areas with building operations activities in Malaysia according to the Occupational Safety and Health Act 1994 (Act 514), the 1.2 SIGNAGE Factories and Machinery Act 1967 (Act 199) and all other relevant regulations. The guideline dictates that every owner, developer, main contractor and such contractor must take steps to develop and promote safety and health programs to ensure the safety and health of both his employees and the general public. Safety signs are commonly found around construction sites containing information, often symbols relevant to site safety. Figure 1 shows symbols that explain without the use of much words of what the workers and public should and should not do around the construction site. The use of simple universal symbols is effective because in some cases the construction workers or the public might be illiterate or might not be f1a.mi3l ihaora rwditihng the language used on signs. Hoarding is a prerequisite for a construction site because it is legally required to protect the general public from the risks associated with construction sites. Hoarding is temporary fencing which is laid out around the site, defining its borders. Aside from safety, hoarding is also used for security purposes, preventing trespassing and theft in the construction site. The construction site uses metal hoarding. Metal hoarding usually uses corrugated metal sheets as temporary fencing material. Figure 2 marks the borders of the construction site where boarding is used. Building Construction Project 1 By Chua jiu 4 xin
  • 5. 2.0 Earthwork Introduction Definition Excavation and piling of earth in connection with an engineering operation. It involves movingpart of the earth to another location to create a desired shape. Machinery used: Much of the excavation is done with operated machines to ease work, cost and also saves time. These equipment includes:- Equipments Function Wheel Loader Scoop up lose materials from the ground from one point to another without pushing the materials across the ground Back Hoes Dig up hard materials and trenches Scrapers Machine to move earth over short distance (smoothen) Excavators Digging, demolition, forestry work, grading, landscaping, heavy lifting and brush cutting Motor Grader Finish grade the rought grading created by heavy vehivles (Created flat surface) Rollers Use to compact the soil after grading Building Construction Project 1 5 By tsang hao ren
  • 6. Earthwork Machinery Fork Lifter lifting bags of Cement Crane being used to lift materials Concrete mixer mixing cement Using normal Truck to Send scaffold Backhoe excavating land for foundation Using backhoe loader to Transport steel bar Building Construction Project 1 6 By tsang hao ren
  • 7. Earthwork Excavation Types of Excavation There are different types of excavation and it is classified by the type of materials Type of Excavation Description Topsoil excavation Removal of the exposed layer of the earth’s surface, including vegetation. Contains more moisture than that underneath. Earth excavation removal of the layer of soil immediately under the topsoil and on top of rock. Used to construct embankments and foundations Rock excavation removal of a formation that cannot be excavated without drilling and blasting. Any boulder larger than 1⁄2 yd3 generally is classified as rock. Muck excavation removal of material that contains an excessive amount of water and undesirable soil. Removal of water can be accomplished by spreading muck over a large area and letting it dry, by changing soil characteristics, or by stabilizing muck with some other material, thereby reducing the water content. Unclassified excavation removal of any combination of topsoil, earth, rock, and muck. earthmoving must be done without regard to the materials encountered. Much excavation is performed on an unclassified basis because of the difficulty of distinguishing, legally or practically, between earth, muck, and rock. Building Construction Project 1 7 By tsang hao ren
  • 8. Earthwork Soil Testing Introduction The investigation of the geology and previous uses of any site, together with the determination of its engineering, environmental and contamination characteristics is fundamental to both safe and economic development. Soil Investigation Techniques that are employed for the project are as followed : 1. Boreholes 2. In-situ testing 1. Boreholes Rotary Boring is boring hole using drilling fluid (water or mud) pumped down a rod fitted at the bottom some sort of cutting bit. 2. In-situ Testing In-situ testing techniques, Standard Penetration Testing, Permeability Testing and Borehole Vane Testing are carried out in the boreholes in order to provide information for geotechnical design. Disturbed and undisturbed samples are retrieved from the boreholes for inspection and logging by engineers and subsequent testing in our laboratories. Standard Penetration test (SPT) Hammer weight = 65kg - Drop height = 760mm - Total penetration is 450mm and the number of blows for the last 300mm is the SPT’ N’ value. Care - depth of test vs casing L *site supervision Laboratory Test Triaxial test common method to measure the mechanical properties of many deformable solids, especially soil (e.g. sand, clay) and rock, and other granular materials or powders. Unconfined compression The objective of the unconfined compression test is to determine the UU (unconsolidated, undrained) strength of a cohesive soil in an inexpensive manner. Building Construction Project 1 8 By tsang hao ren
  • 9. Earthwork Cut and Fill Cut and fill the process of constructing railway, road or canal whereby the amount of material from cuts roughly matches the amount of fill needed to make nearby embankments, so minimizing the amount of construction labor. Various sections of a roadway design will require bringing in earth. Other sections will require earth to be removed. THE MASS DIAGRAM The mass diagram is one method of analyzing earthmoving operations. This diagram can tell the engineer where to use certain types of equipment, the quantities of materials needed and the average haul distances etc. The mass diagram has many limitations that preclude its use in all earthmoving operations. At best, it is merely a guide indicating the general manner in which the operations should be controlled. Building Construction Project 1 9 By tsang hao ren
  • 10. 3.0 Foundation DEEP foundation Deep foundations extend down through unsuitable or unstable soil to transfer building loads to a more appropriate bearing stratum. The two principal types of deep foundations are pile foundations and caisson foundations. This is usually at depths more than 3 meters below the finished ground level.. If unsuitable soils are found at the surface, Deep foundations can be used to transfer the loading to a deeper, more competent strata at depth. Piles caissons Caissons are a form of deep foundation which are constructed above ground level.. A DRILLED, CYLINDRICAL FOUNDATION SHAFT USED TO TRANSFER LOAD THROUGH SOFT STRATA TO FIRM STRATA. tHE SHAFT CAN BE FILLED WITH EITHER REINFORCED OR UNREINFORCED CONCRETE A SLENDER TIMBER, CONCRETE OR STEEL STRUCTURAL ELEMENT, DRIVEN, JETTED, OR OTHERWISE EMBEDDED ON END IN THE GROUND FOR THE PURPOSE OF SUPPORTING A LOAD. Building Construction Project 1 10 By Yap kar juen
  • 11. Foundation Pile cap foundation on site Pile Cap foundations allows any type of structure to be supported by layers of soil. When the upper layers of the ground are too soft, Pile Cap Foundation is used to provide proper support to the weight of the building. These piles will penetrate these 'soft' layers into the stronger layers beneath.. At our site, deep foundation is applied. The building loads are transferred to a better bearing stratum of rock or dense sands and gravels below superstructure. COLUMN PILE CAP PILE Example of a 4-pile cap Photo of a 4-pile cap taken on site 4-pile cap plan drawing Building Construction Project 1 11 By Yap kar juen
  • 12. Foundation Pile cap structure Column load Piles are usually driven in clusters of two or more The reinforced concrete pile cap joins the heads of a cluster of piles so that the load can be distributed from a column or grade beam equally among the piles. Piles are driven into earth by pile driver, precast concrete piles can be round, square, or polygonal cross sections or even an open core. Precast piles are always often prestressed. Friction piles is used in our site. It depends on the frictional resistance of a surrounding earth mass for support. The stiffness increases when the the depth increases A pile foundation is a system of end-bearing or friction piles, pile caps and also tie beams for transferring the building loads to a more suitable bearing stratum Building Construction Project 1 12 By Yap kar juen
  • 13. Bars evenly distributed on the bottom and top surfaces. No lacer bars. Bottom bars concentrated over the piles, top bars under the column. Two lacer bars. Layout view Layout view Foundation concrete slab and bars in pile cap superstructure Reinforced concrete slab with one layer of damp proof membrane to engr’s detail.. R.C SLAB A cONCRETE SLAB IS PLACED AT OR NEAR GRADE LEVEL TO SERVE AS A COMBINED FLOOR AND FOUNDATION SYSTEM. The sUITABILITY OF the SLAB has to depend on the geographic location, topography, superstructure design and soil characteristic of site. Building Construction Project 1 13 By Yap kar juen
  • 14. 1) THE VIBROFLOT IS USED TO PENETRATE THE LOOSE SOILS TO CREATE BORE HOLE 2) A cONCRETE PLUG IS THEN FORMED AT THE BASE OF THE BORE HOLE TO SEAL CONTAMINANT PATHWAYS 3) THE CONCRETE IS THEN REPEATEDLY PENETRATED BY THE VIBROFLOT TO COMPACT INTO THE SURROUNDING SOILS Image above shows a AND FORM AN ENLARGED TOE pilling machine drop hammer friction piles The drop hammer friction piles are at this site. is the most commonly used method of insertion of displacement piles. A pile, which is long with a cross section of circle, square or octagon and is usually made out of either cement, wood or steel. It is forced vertically to pass through the soil using a pile driver. The piles are grouped together and connected by a pile cap if the load is expected to be too large for the foundation to take. Foundation piling Building Construction Project 1 14 By Yap kar juen
  • 15. Column footings Footings are an important part of foundation construction. The footing is the bottom part of the foundation. A footing is typically concrete and typically reinforced with steel. The usage of footings is to support the foundation and also prevent settling. Footings are very important in areas, which have troublesome soils. Placement of footings is very important so that it can provide the proper support for the foundation and ultimately the whole structure. Vertical reinforcement Lateral reinforcement steel dowels anchor column to footing Critical section for two-way shear Reinforced concrete column Two-way reinforcement uniformly spaced Foundation Building Construction Project 1 15 By Yap kar juen
  • 16. 4.0 Beam and ColumnsIntroduction Beams A beam is a horizontal structural element that is capable of withstanding load primarily by resisting bending. The bending force induced into the material of the beam as a result of the external loads, own weight, span and external reactions to these loads is called a bending moment. Beams and Columns Columns a Vertical structural element that transmits, through compression, the weight of the structure above to other structural elements below. Structural System Our site uses a structural system for its building. By using in-situ concrete to create the structural System of the building. Formwork temporary or permanent molds into which concretes are poured. In the context of concrete construction, the falsework supports the shuttering moulds. Building Construction Project 1 16 By tsang hao ren
  • 17. Beam and Columns Structural System After completing the footings of the structure, the next step is to create the structural system of the building using beams and columns, To create the columns,and the beam they must firstidentify its position according to the construction drawings and also their foundations Building Construction Project 1 17 By tsang hao ren
  • 18. Beam and Columns Structural System 1. Post Foundation work 2. Creating Formwork in preparation For cement 3. Poring Cement into formwork 5. Balance the soil and creating Reinforced 4. Let Concrete dry and remove formwork concrete columns 6. Create beam connected to column to support the 2nd floor Building Construction Project 1 18 By tsang hao ren
  • 19. Beam and Columns Formwork Column Formwork Beam Formwork A 3-sided box propped in the desired measurements. The beam form side have to retain the wet concrete and able to withstand initial hydrostatic presseure of the wet concrete This consists of a vertical mold of the desired shape and measurements. There will be bracing, stakes and sole plate to help straighten the formwork. A good formwork should satisfy the following requirements: 1. It should be strong enough to withstand all types of dead and live loads. 2. It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape. 3. The joints in the formwork should be tight against leakage of cement grout. 4. Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete. 5. The material of the formwork should be cheap, easily available and should be suitable for reuse. 6. The formwork should be set accurately to the desired line and levels should have plane surface. 7. It should be as light as possible. 8. The material of the formwork should not warp or get distorted when exposed to the elements. 9. t should rest on firm base. Building Construction Project 1 19 By tsang hao ren
  • 20. 5.0 Floor system introduction A floor is a horizontal plane in a building that supports both living loads (people, furniture/anything moveable) and dead loads (weight of the floor construction itself). It acts as the lower enclosing surface of a room. It transfers the load horizontally to the beam, column or load bearing wall... floor system may composed of:- • series of linear beams and joist overlaid with a plane of sheathing • Homogeneous slab of reinforced concrete Functional requirement of The floor: 1.Strength and Stability - able to withstand heavy weight of live and dead loads, impact to the floor, without breaking/damaged. 2.Fire resistance - high fire insulation and not combustible. 3.Damp resistance - Moisture will take the floor damp, cool and uncomfortable and may cause decay to the floor finish (I.e timber & carpet) 4.Sound insulation - thickness of floor affects amount of sound transmitted to the lower/upper ground. 5.Thermal insulation - thickness/material of floor affects the thermal insulation. Type of floors Mud floor Brick floor Tile floor Flagstone floor Concrete floor Building Construction Project 1 20 By cheah teck wei
  • 21. Floor system in site Ground floor: Reinforced concrete slab with one layer of damp-proof membrane Function: • Prevent green grows inside building by concrete. • Prevent damp from penetrating into the building by the use of damp-proof membrane. Reason: • Cheap and ease of construction • Flexibility in finishing available • High strength and durable Non-suspended cast in-situ concrete Section showing component of floor Floor slab- • Concrete bed with reinforcement inside. Screed – • to provide smooth surface where floor finish can be applied Dpm (damp proof membrane) – • prevent moisture from entering the building. Blinding – • 25-30mm thick weak mortar. • to produce a even surface for reinforcement and dpm. hardcore – • form a dry working surface • hard, durable, chemically inert • 100-150mm thick Building Construction Project 1 21 By cheah teck wei
  • 22. Measure and set the area for the floor to be constructed Construct a formwork at the measured place for the floor and use sticks to secure the formwork Spacer block and brc wire mesh is put inside the formwork to provide reinforcement when concrete is poured. By cheah teck Mix the cement and water to create concrete. Pour the concrete mixture into the formwork with brc wire mesh. Polish and smoothen the concrete then cover with plastic to prevent dust or excess water affecting the drying process thus affecting its appearance after done. Remove the formwork when concrete is dried out. Apply tiles on the concrete to produce a different finishes for the floor.. Floor system construction Ground floor construction process Building Construction Project 1 22 wei
  • 23. Floor system in site Intermediate floor: Reinforced concrete slab By cheah teck Function: • Support their own weight, ceilings and superimposed loads. • providing lateral restraint to heights of external and internal walls. • Provides insulation to fire & sound • Divides one space to two • Act as ceiling to the lower floor • Space between floors and ceiling will accommodate the building services features such as electrical, telephone wirings etc. Mild steel main reinforcement bars Mild steel distribution bars Two-way slab & beam • Const5ructed with four column with supporting beams connecting each of them forming a square or nearly square bays. • Reinforcement is cast in two direction to the supporting beam and column. • Effective to medium to heavy load. • High resistance to lateral force. Most efficient when spanning square or nearly square bays. Tensile reinforcemen t Building Construction Project 1 23 wei
  • 24. Floor system construction Intermediate floor construction Timber formwork is set up on the area for the upper floor. Rebars are placed equally on the formwork to provide reinforcement to the slab structure, increasing its tensile strength.. By cheah teck Concrete mixture is then poured onto the whole structure evenly then allowed to dry out. The structure is then done available for floor finishes to be carried out. Timber formworks. process Building Construction Project 1 24 wei
  • 25. 6.0 WALL introduction introduction By cheah teck A wall is the vertical planes that defines the volume of mass and space in a building with the combination of overhead plane and base plane. Walls are placed in Interior (wall/partitions) • Subdivides the space in the building • Can be structural or non-bearing • Provide required degree of acoustical separation • Accommodation of necessary electrical and mechanical services Exterior wall • Able to withstand horizontal wind loading • Can serve as shear walls and transfer lateral wind and seismic forces to the ground foundation if rigid enough • Act as protective shield against weather. • Insulation toward air, sound, damp, moisture and heat. • Able to support the weight of building or non bearing Type of walls: • Concrete wall • Masonry wall • Dry wall • Glass wall • Curtain wall a wall can be a: a Load bearing wall-a wall that bears some of the buildings weight and its own weight. a Non-load bearing wall-bears only its own weight. Building Construction Project 1 25 wei
  • 26. Wall in site Masonry Walls Characteristics • Durable, good sound insulation, fire insulation and thermal insulation. • Offers great flexibility in form and appearance • Can be either load bearing or non-load bearing • Easy and cheap construction • Made by solid cement sand brick (standard modular 3.5x2.5x7.5) By cheah teck 7.5 3.5 2.5 Standard dimension of brick Type of brick bonds Type of brick joints Building Construction Project 1 26 wei
  • 27. Wall details Fire rated party wall ENGLISH BOND • Named 9-inches brick among the field. • Used on walls that separates each shop unit as it provides better fire insulation with its extra thickness. • Considered as the strongest bond among others • Non-load bearing wall • Solid wall English Bond brickwork has alternate courses of headers and stretchers in which the headers are centered on stretchers and the joints between stretchers line up vertically in all 2134 courses. 230mm thick fire rated party wall with 230mm high clay brick above roof with 19mm thick cement plaster on both side. Building Construction Project 1 By cheah teck 27 wei
  • 28. Wall details High brick wall RUNNING/stretcher BOND • Used on walls that is located in a shop unit. • Not as thick as English bond thus providing lesser fire insulation (thinnest type of bond) • acting mainly as space divider. • Non-load bearing wall • Solid wall. • Simplest and cheapest bond among other bonds. • Brick on upper level is placed at the joint of two bottom bricks. 2134 115mm thick high brick wall with 19mm thick cement plaster on both side. Building Construction Project 1 By cheah teck 28 wei
  • 29. Wall construction By cheah teck 1. Lay out the brick on a dry run to ensure the location of wall is placed correctly. 2. Take out the bricks and apply a -inch thick mortar bed on it. 3. Line up the brick and push it into the mortar leaving creating a 3/8-inch joint between each bricks. 4. Check the bricks with a level and scrape off the excess mortar that squeezes off from the joints. 5. The brickwork is started from each end toward the middle. The last brick of a level is called the closure brick. Trim the brick if it cant fit into the space. 6. Apply mortar on both ends of the brick and slowly push to fit into the space. 7. Ensure the reinforced steel bars from the concrete column are fitted in between the brick levels to increase the tensile strength of the wall. 8. While the wall is complete, scrape off all the excess mortar from the joints. Masonry wall construction process Building Construction Project 1 29 wei
  • 30. Wall example Concrete wall By chua jiu xin Concrete wall is a wall built by pouring concrete mixtures into a model/formwork with reinforcement bars then let dried forming a strong structure. Three types of concrete wall construction 1. cast in-situ reinforced concrete (reinforced concrete) frame with rc infill panel walls 2. cast in-situ shear wall 3. pre-cast concrete walls Type of formworks 1. Timber formwork 2. Aluminium system formwork 3. Modular steel formwork characteristic • Most built as load bearing wall due to its structural strength. • Various texture and appearance can be achieved by the use of formwork, admixtures and additives. • Cheap and ease of construction. Different texture of concrete wall Timber formwork Aluminium system formwork Modular steel formwork Building Construction Project 1 30
  • 31. 7.0 STAIRCASE introduction A Introduction By chua jiu xin Staircase is a flight or series of flights of steps and a supporting structure connecting spaces between one level to another. It changes the overall circulation of a building. A There are many types of staircase constructed in different way using different type of material. Type of staircases Staircase material: • Concrete staircase • Timber staircase • Glass staircase • Steel staircase Building Construction Project 1 31
  • 32. STAIRCASE in site Half turning staircase Turns 180-degrees through two right-angles at intervening landings. Straight staircase A Straight staircase that extends from one level to another without turns or winder. Dimensions Riser = 160mm Tread = 255 + 25mm Nosing = 915mm high ms handrail Total step = 20 Dimensions By cheah teck Riser = 175.8mm Tread = 255 + 25mm Nosing = 915mm high ms handrail Total step = 26 5487 8839 4115 Building Construction Project 1 32 wei
  • 33. STAIRCASE construction A timber formwork is set up on the proposed area for the staircase. Every pieces for each step is placed properly to ensure accurate positioning and measurement.. Rebars were placed in the timber formwork to provide reinforcement for the structure (resist tensile force and shear) By cheah teck Concrete is poured into the formwork and thus removed after dried. . In situ cast concrete staircase construction process Building Construction Project 1 33 wei
  • 34. STAIRCASE example 2 Timber staircase By chua jiu xin A timber staircase is a staircase constructed using timbers. A Basically they share the same function but based on their materiality, they have different texture, sensory, durability, maintenance methodology and etc. A Hardwood is frequently used in constructing a timber staircase A Every 3-6 months should be maintenance once to ensure the timber is in good condition as timber is affected by the Humidity, ambience of air, insect and etc. Sr . No . Type of arrangement of staircase Wooden Staircase RCC Staircase 1 Wooden staircase is relatively weaker. RCC staircase is relatively stronger. 2 Construction time is relatively less. Cement setting takes at least 21 days. Hence construction time is more. 3 Timber has a life. It becomes weak after about 70 to 80 years RCC hardens with age. The process of hardening continues forever increasing its strength. 4 The appearance and the colour of the timber can be attractive. RCC staircase can be made attractive by cladding and other decorations. 5 Timber staircases are light in weight These are heavier in weight. 6 Timber is costlier than RCC. RCC is cheaper than timber. 7 These are fire hazardous These cannot catch fire. Compare the advantages and disadvantages of the Wooden Staircase over the RCC staircase. 8 These are sound and heat insulators. Comparatively lesser insulators. Building Construction Project 1 34
  • 35. DOORS Doors function as an entrance to a space and acts as a barrier that swings, slides or folds. Doors could be made of an assembly of timber, metal, or composite materials. Doors play a very important role in influencing the circulation system. Components of a door head stop jamb architrave sill Single door leaf wall architrave Door panel Main frame Sub frame nail Section of door frame 8.0 doors Building Construction Project 1 35 By lim ming chek
  • 36. DOOR operation Single leaf swinging door - Only one door leaf used. - Door leaf is hinged to the door frame. - Operational space required. DOOR details A. Jambs can be attached to the floor with powder-driven fasteners. Solid core door b. Reinforcement of jamb at hinge attachments c. Loose sheet metal tees are inserted into the frame and built into mortar joints to anchor jambs onto masonry walls The door also uses a double rabbet frame. Building Construction Project 1 36 By lim ming chek
  • 37. DOORS PROCESS By lim ming Sub frame is installed prior to the main frame. This is done so that the main frame is less likely to shrink as it does not come in contact with the masonry wall. The door frame is also not stained by paint or cement mortar. Floor finishes are also easier to be installed as it does not need to suit the door frame profile. Step 1 - The location of the door is measured and marked according to the dimensions stated at the approved construction drawing. A few layers of brick are then laid by its side. Step 2  Frame of the door is then slotted into the measured space. The jamb of the door is nailed into the masonry wall for support purposes and bricks are continued to be laid. Building Construction Project 1 37 chek
  • 38. Step 3  A pre-cast concrete lintel with same width and length of the door is bound with mortar and placed on top of the door head. The lintel is constructed to prevent the door frame from excessive vertical force and affect its ease of operation. Step 4  For timber door frame, the wall is plastered and the main frame is installed. For aluminium door frame however, the space between the masonry wall is filled with mortar before the wall is plastered. By lim ming Cement mortar Aluminium frame Building Construction Project 1 38 chek
  • 39. Step 5  Shims are placed on the hinge side of the door and form a continuous gap in between. The hinge is then nailed into the side door jamb. Step 6  To ensure that the cracks and flaws in joining is hidden particularly for timber door frame as the wood will season and shrink after some time thus exposing cracks, the architrave is installed. Advantages of Using Aluminium Frame - Low maintenance frame. - High resistance to corrosion. - Strong and economical. - Environmentally sustainable material. - Easy to install due to its flexibility. Building Construction Project 1 By lim ming 39 chek
  • 40. Aluminium door frames. Double rabbet door frames slotted into measured space. By lim ming Wall completed with lintel seen for support. Building Construction Project 1 40 chek
  • 41. By lim ming Roller shutters which consist of many horizontal slats hinged together are also used as the main as well as the back entrance. It is attached to a beam to support it. The door is raised to open and lowered to close it. Building Construction Project 1 41 chek
  • 42. WINDOWS INSTALLATION OF WINDOW Step 1: Check the rough opening Measure the width of the rough opening at the top, middle, and bottom and the height at both sides and in the middle. Step 2: Protect against water infiltrationCut a strip of self-adhering waterproof membrane. Center the membrane under the rough opening and adhere it to the existing builder's felt STEP 3: check the perpendicularity By liau wen bin Step 4: drill a hole through between frame and wall the existing hole from the frame STEP 5: place a fischer through the hole Step 6: Install Window STEP 7: Finish the wall with sealant or mortar Building Construction Project 1 42
  • 43. windows By liau wen bin Window is an opening in a wall or other structures that is operable in opening and closing mechanism. It is the connection between interior and exterior space by allowing the passage of natural light, solar heat, air movement and also provide a view. Windows are undoubtedly important in achieving quality of life and comfort in buildings. TYPES OF WINDOWS An awning window is hinged at the top and opens outward.The glass protects the opening like an awning, enabling ventilation even dying rainy weather. It can be placed high on the wall to let in both light and air. Generally, awning windows are opened with a hand crank. Screens are on the inside of the window, where they are more protected from the elements. awning windows in side elevation (PART) When open, the sash is able to direct ventilation. The sashes may be stacked vertically with sashes closing on each other or on meeting sites. Hinged at the top and open outwardly because the sash closes by pressing against the frame. They generally have lower air leakage rates than sliding windows. Sash Hinge SLIDE Hinge TRACK JAMB RETAINER CLIP Hinge arm Building Construction Project 1 43
  • 44. WINDOWS OTHER TYPES OF WINDOWS Fixed windows Fixed windows consist of a frame and stationary sash. When used in conjunction with operable window units, the thickness of the fixed sash should approximate the cross-sectional dimension of the operating sashes, Jalousie windows have horizontal glass or wood louvers that pivot simultaneously in a common frame. Jalousies are used primarily in mild climates to control ventilation and to cut off visibility from the outside By liau wen bin Completion of construction showing multiple awning windows Jalousie windows Building Construction Project 1 44
  • 45. 9.0 Roofing system Definition of roof By chew ung A roof is part of a building envelope that covering on the uppermost part of a building or shelter which include exterior surface and its supporting structures. It must be able carry its own weight, additional attached equipment and accumulated rain. Furthermore, it must be able to resist wind pressure Basic function of roof  Able to resist the passage of moisture to the inside of building.  Able to withstand atmospheric pollution, frost and other harmful condition  To prevent the spread of fire over the roof and from one building to another.  Thermal insulation is required to reduce heat losses and prevent excessive solar heat gains in hot weather.  Sound insulation is rarely an important consideration in roof design. TYPE OF ROOF There are different kind of roof (refer diagram2). The shape of roofs differs greatly from region to region and it affects the overall appearance of a home. The main factor which influence the shape of roofs are the climate and the materials available and the outer covering, appearance and aesthetics, maintenance and costing Components of roof Building Construction Project 1 45 heng
  • 46. Introduction of Flat Roof By chew ung A flat roof is a roof which is almost level in contrast to the many types of sloped roofs. The slope of a roof is properly known as its pitch and flat roofs have up to approximately 10.Flat roofs are an ancient form mostly used in arid climates and allow the roof space to be used as a living space or a living roof. Introduction of Butterfly Roof A roof shape which has two surfaces that rise from the centre to the eaves with a valley in the centre, resembles the wings of a butterfly. TYPE: The shop lots use two kinds of roof which are Reinforced concrete flat roof and butterfly roof at the top of those shop lots Elevation Reinforce concrete Flat roof Roof plan flat roof Butterfly roof flat roof Butterfly Roof Building Construction Project 1 46 heng
  • 47. TYPE OF FLAT ROOF By chew ung Most of the materials that used in the flat roof provide insufficient resistance to the transfer of heat to meet the requirement of the building regulations. Therefore an insulating layer is needed. The position of the insulation will define the type of flat roof. Warm Roof • Sandwich Roof • Inverted Roof Cold roof (ventilated roof) Membranes of flat roof 1.BUR ( built up membrane ) 2.Modified bitumen membrane 3.Single-Ply Membranes 1 Type of flat roof of shop lots in 2 3 Metal panel ( Galvanized steel panels ) Steel is defined as any alloy of iron with content of 2 percent and below. Steel is strong in both compression and tension. Galvanized steel is kind of steel that is coated in zinc which can prevent rust. The process is achieved through hot dip galvanizingCorrugated roofing panels span between beams or purlins running across the slope. The roofing panels can be aluminium, corrugated structural glass, fibreglass or in the case of the shop lots in Banting, galvanized steel. Corrugated Glass Panels Aluminium PanelsFibreglas s panels Galvanized steel Type of roof that used to roofing the shop lots in Banting banting Building Construction Project 1 47 heng
  • 48. Roof details elevation sectio n Roof plan By chew ung The insulation is below the deck of the roof in Banting can be considered as a cold roof. The roof is covered by blue Galvanized steel panels. Corrugate d Roofing Performed closure strip to seal the openings of corrugation against wind-driven rain Flashing sheet Steel cee purlin Roof beam insulati on Components of flat roof Panel Building Construction Project 1 48 heng
  • 49. Construction of Concrete Reinforced Flat roof 1. Temporary propping or scaffolding is required and set up to support the framework By yap chein 2. The joist of the roof is connected to the wall by metal wall plates, is slope to create a fall, which supported below by the concrete roof beam 3. The Metal panels is added to cover the roofing Steel Bar Concealed, floating clips attach the G.S panels to the framework Panels overla p each other to concea l the roof clips 4. Steel bar to join the metal wall plates to fix the shape of the roof Roof panels are seamed togeth er with a mechan ical seamer Roofing method Fall creating by sloping the joist Galvanize d steel panels 1 2 3 Building Construction Project 1 49 wee
  • 50. Butterfly Roof By yap chein Butterfly Roof basic structure A butterfly roof consists of two roofs joined at their low points to form a valley, which sometimes serves as a reservoir. The angle of the two roofs is determined by the architect or designer, but it typically creates slight but visually discernible slopes that give the building a more modern and less angular appearance than that of a traditional roof. Butterfly roof versions Several unique styles of roofs have emerged based on the atypical pitches of butterfly roofs. A shed roof has a single slope and typically includes the slope at different levels on top of the building. A saddle roof is shaped like a Western style saddle used to ride a horse, with a convex curve on one side of the axis and a concave curve on the other. Gabled butterfly roofs generally have a triangular sloping roof attached to a flat roof with windows placed near the top of the walls beneath it. Zigzag roofs look like the edge of a saw blade, with many acutely angled peaks in a row. Architects sometimes mix and match roofs of different pitches on a single structure. Details of butterfly roof Valley gutter Two roofs joined at their low points to form a valley Building Construction Project 1 50 wee
  • 51. Reference EARTHWORK 1)Fundamentals of building construction by edward allen josepg iano 2)Construction methods and planning j.r. illingworth 3)Building construction illustrated by francis d.k.ching Foundation 1)http://constructionduniya.blogspot.com/2012/02/pile-foundations.html 2)BUILDING CONSTRUCTION ILLUSTRATED BY FRANCIS D.K. CHIING 3)http://tgbuilders.co.uk/our-services/foundation/ SUPERSTRUCTURE -BEAM AND COLUMN 1) Building conctruction illustrated by francis d.k. ching -Floor 1)https://www.dlsweb.rmit.edu.au/toolbox/buildright/content/bcgbc4010a/10_flo or_systems/topic_index.htm 2)Building construction illustrated by francis d.k. ching -Wall 1)http://www.wbdg.org/design/env_wall_masonry.php 2)http://www.understandconstruction.com/walls.html 3)Building construction illustrated by francis d.k. ching -Staircase 1) Building construction illustrated by francis d.k. ching Building Construction Project 1 51
  • 52. Reference -door and windows 1)http://free-ed.net/free-ed/ Resources/Trades/carpentry/Building01/?iNum=1102 2)Fundamentals of building construction by edward allen joseph iano -roof 1)http://www.the-flat-roof.co.uk/Sect3_6.pdf 2)http://www.buildingregs4plans.co.uk/guidance_flat_roof_types.php 3) http://learn.hackney.ac.uk/pluginfile.php/14157/mod_resource/content/0/The ory/FirstYearTheory11.pdf Building Construction Project 1