BOQ
• BOQ is a document is a document used in tendering in the construction industry
in which materials, parts, and labor (and their costs) are itemized.
• It’s important parameters are length (rate/km), area (Sqm), volume (Cu.m), weight
(Kg/m) & numbers (Nos.)
• BOQ are done to
a. Save the cost and time of several contractors measuring the same design in order
to calculate their bids for competition.
b. Provide a consistent basis for competitive bids so that the contractor who is the
most efficient and least expensive in providing the items of work is likely to be
commissioned for the job.
c. Provide an open basis for the contract; the client provides an extensive and clear
statement of the work he/she requires and the contractor states the price at
which he/she is prepared to undertake the job.
d. Provide a very strong basis for financial administration of the contract.
SL.NO. CLAUSE
NO.
PARTICULARS UNIT
1. 201 Site Clearance & Dismantling
• Clearing & Grubbing of road land
• Tree cutting
• Dismantling of existing structures may be bitumen, concrete or steel structures
Hectares
Nos.
Cu.m
2. 301
305
Earthwork
• Earthwork in excavation necessary for the construction of roadway in all types of soil,
ordinary & soft soils, ordinary/soft rock or hard rock .
• Construction of embankment
• Construction of Subgrade
• Construction of earthen shoulders with suitable material obtained from roadway,
drainage excavation etc. satisfying the requirements of minimum soaked CBR value
• Granular layer on shoulder
• Filling behind structure, RE wall or Median/island
• Scarifying the existing bituminous surface
Cu.m
Cu.m
Cu.m
Cu.m
Cu.m
Cu.m
Sqm
3.
401
406
Granular base course & Sub base
• Grading for close-graded or coarse-graded sub-base material (Grade -1,2,3)
• Wet Mix Macadam (WMM)
Cu.m
Cu.m
According to MORTH specifications for road & bridge works,
the following items are included as follows:
SL.NO. CLAUSE
NO.
PARTICULARS UNIT
4. 502
512
504
507
601
602
Bituminous course & Rigid pavement
• Providing and applying primer coat with bitumen emulsion on prepared surface of
granular Base including clearing of road surface and spraying primer at the rate of 0.6
to 0.9 kg/Sqm using mechanical means complete.
• Bituminous Concrete (BC)
• Pavement Quality Concrete (PQC)
• Bituminous Macadam
• Dense bituminous Macadam
• Dry Lean Concrete (DLC)
• Plain Cement concrete pavement
Cu.m
Cu.m
Cu.m
Cu.m
Cu.m
Cu.m
5. 801
803
Traffic Signs
Road Markings
Nos.
Paints
6.
7.
1701
1601
Drainage
Excavation for foundation for drains
PCC – Plain Cement Concrete
RCC – Reinforced Cement Concrete
HYSD – High Yield Steel Bars
Protective Works
RE wall
PCC wall
Gabion wall
RCC wall
RR Masonry wall
Cu.m
Cu.m
Cu.m
MT
Sqm
Cu.m
Cu.m
Cu.m
Cu.m
QUALITY CONTROL PLAN
• Quality Control (QC) = The contractors system in place during the construction to
manage, control and document his activities in order to comply with contract
requirements
• Quality Assurance (QA) = The Governments system in place to monitor the Quality
Control efforts of the contractor
• QC + QA = HIGH QUALITY FINISHED ROAD
• 3 phases of contractor quality control :
PREPARATORY PHASE
•Review Plans and Specs
•Verify submittal approval
•Check preliminary work
•Examine materials
•Discuss construction methods
•Review Safety
•Coordinate surveying and
staking work
START-UP PHASE
• Establish quality required
• Resolve conflicts
• Ensure testing is
performed
• Establish detailed testing
schedule based on
production schedule
• Review safety
PRODUCTION PHASE
• Ensure contract compliance
• Conduct intermittent or continuous
inspections to identify & correct
deficiencies.
• Inspect completed phases before
scheduled government acceptance
• Ensure testing reports are submitted
• Ensure rework is completed
TYPICALFLOWCHARTFORQUALITYIN
ROADWORKS

More Related Content

What's hot

Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
Minh Bui Si
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
AshwiniChaudhari13
 
Rules and regulation of transmission and distribution of natural gas and its ...
Rules and regulation of transmission and distribution of natural gas and its ...Rules and regulation of transmission and distribution of natural gas and its ...
Rules and regulation of transmission and distribution of natural gas and its ...
Md. Shahadot Hossain
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement Factory
Sven Maedler
 
Cv SF van Zyl - December 2015
Cv SF van Zyl - December 2015Cv SF van Zyl - December 2015
Cv SF van Zyl - December 2015
Frans Van Zyl
 
AUSTROPLAN_References_Cement 2014
AUSTROPLAN_References_Cement 2014AUSTROPLAN_References_Cement 2014
AUSTROPLAN_References_Cement 2014
Cheryl Schultze
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
Manoranjan Roy
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Muhammad Umar
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
imaduddin91
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
Mohd Nizam Mohd Zan
 
Cost leadership & differentiation
Cost leadership & differentiationCost leadership & differentiation
Cost leadership & differentiation
Asep Maulana Akbar
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
SHAZEBALIKHAN1
 
Internship_report
Internship_reportInternship_report
Internship_report
Devarsh Kumar
 
High way
High wayHigh way
High way
Mani Das
 
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
IRJET Journal
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
FeteneBefekadu
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
76s201901
76s20190176s201901
76s201901
IJRAT
 
Two-Lift Paving - Design Viewpoints
Two-Lift Paving - Design ViewpointsTwo-Lift Paving - Design Viewpoints
Two-Lift Paving - Design Viewpoints
Center for Transportation Research - UT Austin
 
gr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnlgr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnl
Dennis McElroy
 

What's hot (20)

Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
 
Rules and regulation of transmission and distribution of natural gas and its ...
Rules and regulation of transmission and distribution of natural gas and its ...Rules and regulation of transmission and distribution of natural gas and its ...
Rules and regulation of transmission and distribution of natural gas and its ...
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement Factory
 
Cv SF van Zyl - December 2015
Cv SF van Zyl - December 2015Cv SF van Zyl - December 2015
Cv SF van Zyl - December 2015
 
AUSTROPLAN_References_Cement 2014
AUSTROPLAN_References_Cement 2014AUSTROPLAN_References_Cement 2014
AUSTROPLAN_References_Cement 2014
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
 
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
Selection of Roof Casting Formwork Systems for the Bird Island Project: Case ...
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Cost leadership & differentiation
Cost leadership & differentiationCost leadership & differentiation
Cost leadership & differentiation
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Internship_report
Internship_reportInternship_report
Internship_report
 
High way
High wayHigh way
High way
 
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
IRJET- Improvement of Engineering Properties of Soil using Pond ASH and Alcco...
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
76s201901
76s20190176s201901
76s201901
 
Two-Lift Paving - Design Viewpoints
Two-Lift Paving - Design ViewpointsTwo-Lift Paving - Design Viewpoints
Two-Lift Paving - Design Viewpoints
 
gr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnlgr_2016_cir-lam-card_fnl
gr_2016_cir-lam-card_fnl
 

Viewers also liked

Boq sample
Boq sampleBoq sample
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
Harish Mahavar
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
Welekemah Bindah
 
Boq of furniture (be & i project)
Boq of furniture (be & i project)Boq of furniture (be & i project)
Boq of furniture (be & i project)
Anupam Paul
 
Comparison of Brick Wall and Concrete Wall
Comparison of Brick Wall and Concrete WallComparison of Brick Wall and Concrete Wall
Comparison of Brick Wall and Concrete Wall
constructor
 
Construction phases
Construction phasesConstruction phases
Construction phases
Meesum Zaidi
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )
Lee Pei Gie
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
R.R.G.S Bandara
 
bamboo species good for construction in india nd as a material
bamboo species good for construction in india nd as a materialbamboo species good for construction in india nd as a material
bamboo species good for construction in india nd as a material
Deepanker Ras
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
SUJAYKUMAR R SANGLIKAR
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
Natalie Reid
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
Bt Lee
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
Awanish Shukla
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
hlksd
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
Building construction
Building constructionBuilding construction
Building construction
Llyod cassidy
 
NATIONAL INSITUTE OF DESIGN
NATIONAL INSITUTE OF DESIGN NATIONAL INSITUTE OF DESIGN
NATIONAL INSITUTE OF DESIGN
Ar Naveen Naveen
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
Mereia Kali
 

Viewers also liked (19)

Boq sample
Boq sampleBoq sample
Boq sample
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
Boq of furniture (be & i project)
Boq of furniture (be & i project)Boq of furniture (be & i project)
Boq of furniture (be & i project)
 
Comparison of Brick Wall and Concrete Wall
Comparison of Brick Wall and Concrete WallComparison of Brick Wall and Concrete Wall
Comparison of Brick Wall and Concrete Wall
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
bamboo species good for construction in india nd as a material
bamboo species good for construction in india nd as a materialbamboo species good for construction in india nd as a material
bamboo species good for construction in india nd as a material
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Building construction
Building constructionBuilding construction
Building construction
 
NATIONAL INSITUTE OF DESIGN
NATIONAL INSITUTE OF DESIGN NATIONAL INSITUTE OF DESIGN
NATIONAL INSITUTE OF DESIGN
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 

Similar to construction management

internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering institute
SrikanthReddy345872
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
AKASHGARG131
 
Contract presentation
Contract presentation  Contract presentation
Contract presentation
amity university
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
DanielWisman1
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
RAKESHPANDEY754083
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
Akshay kumar
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
Dr K M SONI
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
Sachin Kulkarni
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
Sandeep Reddy
 
Road work construction proxy(1)
Road work   construction proxy(1)Road work   construction proxy(1)
Road work construction proxy(1)
FeteneBefekadu
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
Beipazilaikibby
 
M.Salah cv1
M.Salah cv1M.Salah cv1
M.Salah cv1
mohamed salah
 
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
TemeTeme1
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
Ictsol
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
Darshan Parakhiya
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
Dharmendra Kumar
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
MekonnenAyal
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
'Sayed Asadullah
 

Similar to construction management (20)

internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering institute
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Contract presentation
Contract presentation  Contract presentation
Contract presentation
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 
Road work construction proxy(1)
Road work   construction proxy(1)Road work   construction proxy(1)
Road work construction proxy(1)
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
M.Salah cv1
M.Salah cv1M.Salah cv1
M.Salah cv1
 
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
READY MIX CONCRETE
READY MIX CONCRETEREADY MIX CONCRETE
READY MIX CONCRETE
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 

Recently uploaded

The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
dsnow9802
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
TulsiDhidhi1
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
Dr. Christine Ngari ,Ph.D (HRM)
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
spandane
 
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Alexey Krivitsky
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Dr. Nazrul Islam
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
8p28uk6g
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
GanpatiKumarChoudhar
 
All the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/BozenAll the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/Bozen
Alberto Brandolini
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
stuwilson.co.uk
 
Team Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL ExplainedTeam Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL Explained
iampriyanshujaiswal
 

Recently uploaded (14)

The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
 
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
 
All the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/BozenAll the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/Bozen
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
 
Team Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL ExplainedTeam Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL Explained
 

construction management

  • 1. BOQ • BOQ is a document is a document used in tendering in the construction industry in which materials, parts, and labor (and their costs) are itemized. • It’s important parameters are length (rate/km), area (Sqm), volume (Cu.m), weight (Kg/m) & numbers (Nos.) • BOQ are done to a. Save the cost and time of several contractors measuring the same design in order to calculate their bids for competition. b. Provide a consistent basis for competitive bids so that the contractor who is the most efficient and least expensive in providing the items of work is likely to be commissioned for the job. c. Provide an open basis for the contract; the client provides an extensive and clear statement of the work he/she requires and the contractor states the price at which he/she is prepared to undertake the job. d. Provide a very strong basis for financial administration of the contract.
  • 2. SL.NO. CLAUSE NO. PARTICULARS UNIT 1. 201 Site Clearance & Dismantling • Clearing & Grubbing of road land • Tree cutting • Dismantling of existing structures may be bitumen, concrete or steel structures Hectares Nos. Cu.m 2. 301 305 Earthwork • Earthwork in excavation necessary for the construction of roadway in all types of soil, ordinary & soft soils, ordinary/soft rock or hard rock . • Construction of embankment • Construction of Subgrade • Construction of earthen shoulders with suitable material obtained from roadway, drainage excavation etc. satisfying the requirements of minimum soaked CBR value • Granular layer on shoulder • Filling behind structure, RE wall or Median/island • Scarifying the existing bituminous surface Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Sqm 3. 401 406 Granular base course & Sub base • Grading for close-graded or coarse-graded sub-base material (Grade -1,2,3) • Wet Mix Macadam (WMM) Cu.m Cu.m According to MORTH specifications for road & bridge works, the following items are included as follows:
  • 3. SL.NO. CLAUSE NO. PARTICULARS UNIT 4. 502 512 504 507 601 602 Bituminous course & Rigid pavement • Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.6 to 0.9 kg/Sqm using mechanical means complete. • Bituminous Concrete (BC) • Pavement Quality Concrete (PQC) • Bituminous Macadam • Dense bituminous Macadam • Dry Lean Concrete (DLC) • Plain Cement concrete pavement Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m 5. 801 803 Traffic Signs Road Markings Nos. Paints 6. 7. 1701 1601 Drainage Excavation for foundation for drains PCC – Plain Cement Concrete RCC – Reinforced Cement Concrete HYSD – High Yield Steel Bars Protective Works RE wall PCC wall Gabion wall RCC wall RR Masonry wall Cu.m Cu.m Cu.m MT Sqm Cu.m Cu.m Cu.m Cu.m
  • 4. QUALITY CONTROL PLAN • Quality Control (QC) = The contractors system in place during the construction to manage, control and document his activities in order to comply with contract requirements • Quality Assurance (QA) = The Governments system in place to monitor the Quality Control efforts of the contractor • QC + QA = HIGH QUALITY FINISHED ROAD • 3 phases of contractor quality control : PREPARATORY PHASE •Review Plans and Specs •Verify submittal approval •Check preliminary work •Examine materials •Discuss construction methods •Review Safety •Coordinate surveying and staking work START-UP PHASE • Establish quality required • Resolve conflicts • Ensure testing is performed • Establish detailed testing schedule based on production schedule • Review safety PRODUCTION PHASE • Ensure contract compliance • Conduct intermittent or continuous inspections to identify & correct deficiencies. • Inspect completed phases before scheduled government acceptance • Ensure testing reports are submitted • Ensure rework is completed