SlideShare a Scribd company logo
1 of 40
2/29/2024 1
COLLEGE OF ENGINEERING TECHNOLOGY
DEPARTEMENT OF CIVIL ENGINEERING
Contract, Specification and Quantity Survey
(CENG 5121 )
QUANTITY SURVEYING
prepared byEDEN H.(MSC.)
2/29/2024 2
Quantity surveying is a term or processes used in the construction
industry to take measurements of civil works, prepare specifications,
and estimate the cost of works either for each trade of work or for the
whole project.
The following tasks are covered in quantity surveying:
1. Preparation of Specification and wbs
2.Taking measurements of civil works (Taking off quantities and
preparing BOQ)
2/29/2024 3
3. Preparation of approximate (preliminary) cost estimate at the
very early stage of the project
4. Preparation of detail cost estimate at different stages (taking as
built measurements/existing dimensions and conditions and
preparing payment certificates or approval of payment certificates
prepared by taking measurements)
5. Valuation of property
2/29/2024 4
PURPOSE OF QUANTITY SURVEYING
The purpose of quantity surveying hence the preparation of Bill of
quantities is:
I. Assist the client to have an accurate estimate of the volume of
work as well as the required budget.
II. To assist in the accurate preparation of tenders, by providing
uniform measurement of quantities.
III. To give an accurate checklist of work accomplished
IV. To assist in the certification of payments
V. To give insight into the required variation work amounts
2/29/2024 5
MEASUREMENT OF CIVIL WORKS
• Measurement of civil works includes the billing of each trade
of work either from drawings or the building itself for
defining the extent of works under each trade.
• The standard book, which is used in Ethiopia, is standard
technical specification & method of measurement for
construction of buildings by BaTCoDA, March 1991.
2/29/2024 6
MEASUREMENT OF CIVIL WORKS
Specification Worksheet (BOQ form)
It is the format which is used in a bill of quantity to list
(include) a short description of the specification along with its
measuring unit, quantity and unit prices to determine the total
cost for each trade of item.
2/29/2024 7
3.3 MEASUREMENT OF CIVIL
WORKS
THE PROCESS OF QUANTITY SURVEYING
There are four clearly defined steps in preparation of Bill of
Quantities:
1. Taking off
2. Squaring
3. Abstracting
4. Writing the final Bill of Quantity
2/29/2024 8
MEASUREMENT OF CIVIL WORKS
TAKING OFF
• This is the process of preparing /defining a detailed list of all
labor and materials necessary for the work and entering the items
on properly dimensioned paper.
• The standard form used for entering the dimensions taken or
scaled from drawings to determine the accurate quantity in each
trade of work, except reinforcement steel, is called Take Off
Sheet or Dimension Paper.
• The dimension paper used for taking off is usually double –
ruled as shown (A4 size).
2/29/2024 9
MEASUREMENT OF CIVIL WORKS
TAKING OFF
2/29/2024 10
Measurement of civil works
TAKING OFF
2/29/2024 11
3.3.1TAKING OFF
2/29/2024 12
3.3. MEASUREMENT OF CIVIL WORKS
2/29/2024 13
I. Taking Off
A separate sheet (Bar Schedule) is used to prepare
reinforcement
• quantities as shown below.
2/29/2024 14
I. TAKING OFF
2/29/2024 15
The Process of Quantity Surveying
II. Squaring
 The dimensions entered in Column 2 are squared or cubed as the
case may be, multiplied by the timizing factor, and the result
entered in Column 3. This task is called squaring.
 All squared dimensions should be carefully checked by another
person before abstracting, and if correct the item should be ticked
with red. Use two decimal places.
III. Abstracting
 The squared dimensions are transferred to abstract sheets and all
similar dimensions are collected in the same category to obtain the
total quantity of each item.
2/29/2024 16
MEASUREMENT OF CIVIL WORKS
The Process of Quantity Surveying
Writing the final bill
 After the abstract sheets have been completed and checked, the
final bill of quantity is written.
 The dimensions are copied from the abstracts, and as each item
is transferred it should be ticked by a vertical line from the
abstract sheets.
 The description of each item in the final BOQ should be short,
precise and descriptive as per the specification.
2/29/2024 17
MEASUREMENT OF CIVIL WORKS
2/29/2024 18
Measurement of Civil Works
BASIC PRINCIPLES OF TAKING OFF
 The following tasks are part of the Taking Off
 Describing the item,
 Bracketing (relating the description to the quantity),
 Timsing,
 Dotting on (adding to the timising factor),
 The Ampersand (ditto),
 Waste calculations,
 Deduction of items,
 Correction of dimensions (nullifying).
2/29/2024 19
Measurement of Civil Works
TYPES OF TAKING OFF
 Mensuration (act of measuring)– the calculation of geometric
quantities such as length, area, and volume, from dimensions and
angles that are already known.
 Girth (perimeter) computation– linear measurement. There are
various methods of taking off quantities for computation of girth.
 In- to- in and out- to-out method – some wall lengths are taken out
to out and others in to in (offsets are added to out to out lengths) and
same are deducted from in-to-in lengths; used for any type of
measurement irrespective of condition of symmetry.
 Centre line method– suitable only when the cross sections of all
walls are symmetrical. In this method Centre line length is found and
same is used for taking off quantities (therefore only width and
depth vary).
2/29/2024 20
Measurement of Civil Works
I. Taking Off
Types of taking off
Crossing method –lengths and breadths of walls as shown in plan
are taken for working out various items and this method is useful
only if the offsets of footings are symmetrical.
A. Out – to - Out and In – to – In Method
• Long Wall (Out – to - Out ) = Inner Length + 2 Times
Thickness of the Wall
• Short Wall (In – to – In ) = Inner Length - 2 Times
Thickness of the Wall
B. Center Line Method
• All dimensions are taken center to center
2/29/2024 21
Measurement of Civil Works
C. Crossing Method
 Long Wall (Out – to - Out ) = Inner Length + 2 Times
Thickness of the Wall
 Short Wall (In – to – In ) = Inner Length
2/29/2024 22
EXAMPLE
2/29/2024 23
Measurement of Different Works
I. Substructure
Any structure below the ground floor slab level including the
basement, retaining walls, ground slab, grade beam, and
foundation is called a substructure. substructure work
categorized as follows:
1. Excavation and earthworks
2. Concrete works
3. Masonry works
24
2/29/2024
1. Excavation and Earthworks
A) Site clearance:
• Removal of materials (including trees, bushes and the top 20 to
30 cm soil), any other obstruction from the site.
• A working space of 1m is required on each side.
• Clearing site vegetation is measured in m2 and embraces bushes,
scrub, undergrowth trees .
• Removal of trees is measured as enumerated item.
25
2/29/2024
B) Excavation (bulk excavation)
• Excavation to get reduced levels of every structural element
below the ground level is called bulk excavation.
• Working space for bulk excavation is 25 cm (not used for shallow
masonry)
• Depth of excavation less than 30 cm measured per m2 ,depth > 30
cm per m3
26
2/29/2024
C) Deep Excavation
• It is the actual excavation for the foundation and is measured in
m3.
D) Fill / Embankment
• Shall be measured in m3 of net volume to be filled. Fill is
required because the reduced level of every structural element
above the structure has to be covered.
27
2/29/2024
The subdivisions under fill are
Back fill: - filling by using the excavated soil but by removing
coarse particles.
Borrow fill: - filling by using fill material from another place
when there is shortage of fill or when better quality material is
required.
E) Disposal - cleaning the building area including cart away.
measured with m3
28
2/29/2024
2. Concrete Works
A) Concrete
Grades of Concrete
C5 - lean concrete, measured with m2
C15- for totally supported structural elements
C20- used for slabs; mix proportion is 1:2:4
C25- Commonly used structural Concrete; mix proportion is 1:2:3
C30-Used for chemical stores and nuclear plants
29
2/29/2024
B) Formwork – measured in m2
• Period of removal (minimum):
1. Vertical formwork to columns, walls and beams: 1-2 days
depending on the types of cement we used
2. Soffits formwork to slab: 21 days
3. props to cantilever slabs: 14 days
4. Soffits(under side) formwork to beams: 21 days
5. Props to cantilever beams: 14 days
30
2/29/2024
C) Reinforcement
The reinforcement bars are tied by ø6 mm or ø8 mm mild steel
wire and measured in kg.
3. Masonry Works
stone for below ground work shall be chiseled from natural stone.
• Stone wall is measured by volume, whereas stone pavement is
measured by area, by specifying thickness.
31
2/29/2024
II. Superstructure
1. Concrete works
a. Concrete - as discussed in substructure part
b. Formwork: Specify the type of material used and where
to use (zigba or steel) – m2
c. Reinforcement: Weight per unit length for Ф6 is 0.222
kg/m; for any other diameter d2, with weight per unit
length w2
32
w2 = (d2*2/162) * 0.222
2/29/2024
2. Masonry works
a) Stone masonry:-Measured by volume
b) Hollow and solid concrete blocks, measured by area
specifying the thickness.
 The standard thicknesses of HCBs are 10cm, 15cm, and
20cm.
c) Bricks masonry: measured by area specifying the thickness.
 Bricks are fire resistant, watertight and can also resist
compressive action of up to 50 MPa.
 The thicknesses of brick masonry are 25 cm (for double
layer) and 12 cm (for single layer)
33
2/29/2024
3. Measurement of Roof Structure
• The Unit of measurement for roof structure naturally falls between
enumerated items (trusses) and linear meters, (rafters and
purlins).
Measurement of Pitched Roof Coverings
• The area of roof coverings is unaffected by the inclusion of hipped
ends and valleys as long as the roof pitch remains constant
34
2/29/2024
35
2/29/2024
Rainwater gutters and down pipes
• Rainwater goods completes the work associated with roof
coverings.
• Gutters and down pipes are measured in linear meters over all
fittings. The description should include reference to the type
of pipe or gutter, its nominal size, and the type, method
and spacing of fixings.
36
2/29/2024
• Fittings, such as running outlets, stopped ends, offsets and
connecting shoes, are enumerated and measured extra over
the pipe or gutter on which they occur.
37
2/29/2024
Measurement of Finishing's
• The term Finishing includes operations associated with
the completion of the floors, walls and ceilings of a
building. These are screeding, plastering, wall and floor
tiling, wallpapering and painting.
• The order of measurement of finishing on each floor will
normally be:
» Ceiling
» Walls
» Floors
38
2/29/2024
General rules of measurement
• Work to attached beams is included with ceiling finishes,
whilst work to attached columns is included with wall
finishes.
• Finishes to isolated beams and columns must be given
separately as should work in staircase.
• The principal unit of measurement for wall, floor and
ceiling finishes is m2. Where the width does not exceed
300 mm the unit of measurement is linear.
39
2/29/2024
6. Sanitary appliances such as sinks, wash basins, baths
and water closets.
7. Discharge pipes - waste, soil and vent pipes.
8. Any other work connected with the plumbing
installation.
Pipe work: Pipes are measured in linear meters over
all fittings and branches, stating the type, nominal
size and the method of jointing and fixing.
 Fittings are enumerated and measured as extra-over
the pipe work on which they occur.
40
2/29/2024

More Related Content

Similar to 3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh

Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)hlksd
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxNSHYAMANANDASINGH
 
specification estimation and valuation of a building
specification estimation and valuation of a buildingspecification estimation and valuation of a building
specification estimation and valuation of a buildingswethasekhar5
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringAabid Ansar
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptTauheedKhan45
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfIctsol
 
CSMT 442 Cost and Estimating II
CSMT 442 Cost and Estimating II                              CSMT 442 Cost and Estimating II
CSMT 442 Cost and Estimating II MargenePurnell14
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdfSoniaGandhi26
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptSOUMITRAMUDI
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxcricketreview
 

Similar to 3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh (20)

Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
specification estimation and valuation of a building
specification estimation and valuation of a buildingspecification estimation and valuation of a building
specification estimation and valuation of a building
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Ecm442 lecture 1 latest
Ecm442 lecture 1 latestEcm442 lecture 1 latest
Ecm442 lecture 1 latest
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
CSMT 442 Cost and Estimating II
CSMT 442 Cost and Estimating II                              CSMT 442 Cost and Estimating II
CSMT 442 Cost and Estimating II
 
Construction Estimating.pdf
Construction Estimating.pdfConstruction Estimating.pdf
Construction Estimating.pdf
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
188.pptx
188.pptx188.pptx
188.pptx
 
Ecv
EcvEcv
Ecv
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
construction management
construction managementconstruction management
construction management
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

3. QUANTITY SURVEYING.pptxgajanjsjsjjsjh

  • 2. COLLEGE OF ENGINEERING TECHNOLOGY DEPARTEMENT OF CIVIL ENGINEERING Contract, Specification and Quantity Survey (CENG 5121 ) QUANTITY SURVEYING prepared byEDEN H.(MSC.) 2/29/2024 2
  • 3. Quantity surveying is a term or processes used in the construction industry to take measurements of civil works, prepare specifications, and estimate the cost of works either for each trade of work or for the whole project. The following tasks are covered in quantity surveying: 1. Preparation of Specification and wbs 2.Taking measurements of civil works (Taking off quantities and preparing BOQ) 2/29/2024 3
  • 4. 3. Preparation of approximate (preliminary) cost estimate at the very early stage of the project 4. Preparation of detail cost estimate at different stages (taking as built measurements/existing dimensions and conditions and preparing payment certificates or approval of payment certificates prepared by taking measurements) 5. Valuation of property 2/29/2024 4
  • 5. PURPOSE OF QUANTITY SURVEYING The purpose of quantity surveying hence the preparation of Bill of quantities is: I. Assist the client to have an accurate estimate of the volume of work as well as the required budget. II. To assist in the accurate preparation of tenders, by providing uniform measurement of quantities. III. To give an accurate checklist of work accomplished IV. To assist in the certification of payments V. To give insight into the required variation work amounts 2/29/2024 5
  • 6. MEASUREMENT OF CIVIL WORKS • Measurement of civil works includes the billing of each trade of work either from drawings or the building itself for defining the extent of works under each trade. • The standard book, which is used in Ethiopia, is standard technical specification & method of measurement for construction of buildings by BaTCoDA, March 1991. 2/29/2024 6
  • 7. MEASUREMENT OF CIVIL WORKS Specification Worksheet (BOQ form) It is the format which is used in a bill of quantity to list (include) a short description of the specification along with its measuring unit, quantity and unit prices to determine the total cost for each trade of item. 2/29/2024 7
  • 8. 3.3 MEASUREMENT OF CIVIL WORKS THE PROCESS OF QUANTITY SURVEYING There are four clearly defined steps in preparation of Bill of Quantities: 1. Taking off 2. Squaring 3. Abstracting 4. Writing the final Bill of Quantity 2/29/2024 8
  • 9. MEASUREMENT OF CIVIL WORKS TAKING OFF • This is the process of preparing /defining a detailed list of all labor and materials necessary for the work and entering the items on properly dimensioned paper. • The standard form used for entering the dimensions taken or scaled from drawings to determine the accurate quantity in each trade of work, except reinforcement steel, is called Take Off Sheet or Dimension Paper. • The dimension paper used for taking off is usually double – ruled as shown (A4 size). 2/29/2024 9
  • 10. MEASUREMENT OF CIVIL WORKS TAKING OFF 2/29/2024 10
  • 11. Measurement of civil works TAKING OFF 2/29/2024 11
  • 13. 3.3. MEASUREMENT OF CIVIL WORKS 2/29/2024 13
  • 14. I. Taking Off A separate sheet (Bar Schedule) is used to prepare reinforcement • quantities as shown below. 2/29/2024 14
  • 16. The Process of Quantity Surveying II. Squaring  The dimensions entered in Column 2 are squared or cubed as the case may be, multiplied by the timizing factor, and the result entered in Column 3. This task is called squaring.  All squared dimensions should be carefully checked by another person before abstracting, and if correct the item should be ticked with red. Use two decimal places. III. Abstracting  The squared dimensions are transferred to abstract sheets and all similar dimensions are collected in the same category to obtain the total quantity of each item. 2/29/2024 16
  • 17. MEASUREMENT OF CIVIL WORKS The Process of Quantity Surveying Writing the final bill  After the abstract sheets have been completed and checked, the final bill of quantity is written.  The dimensions are copied from the abstracts, and as each item is transferred it should be ticked by a vertical line from the abstract sheets.  The description of each item in the final BOQ should be short, precise and descriptive as per the specification. 2/29/2024 17
  • 18. MEASUREMENT OF CIVIL WORKS 2/29/2024 18
  • 19. Measurement of Civil Works BASIC PRINCIPLES OF TAKING OFF  The following tasks are part of the Taking Off  Describing the item,  Bracketing (relating the description to the quantity),  Timsing,  Dotting on (adding to the timising factor),  The Ampersand (ditto),  Waste calculations,  Deduction of items,  Correction of dimensions (nullifying). 2/29/2024 19
  • 20. Measurement of Civil Works TYPES OF TAKING OFF  Mensuration (act of measuring)– the calculation of geometric quantities such as length, area, and volume, from dimensions and angles that are already known.  Girth (perimeter) computation– linear measurement. There are various methods of taking off quantities for computation of girth.  In- to- in and out- to-out method – some wall lengths are taken out to out and others in to in (offsets are added to out to out lengths) and same are deducted from in-to-in lengths; used for any type of measurement irrespective of condition of symmetry.  Centre line method– suitable only when the cross sections of all walls are symmetrical. In this method Centre line length is found and same is used for taking off quantities (therefore only width and depth vary). 2/29/2024 20
  • 21. Measurement of Civil Works I. Taking Off Types of taking off Crossing method –lengths and breadths of walls as shown in plan are taken for working out various items and this method is useful only if the offsets of footings are symmetrical. A. Out – to - Out and In – to – In Method • Long Wall (Out – to - Out ) = Inner Length + 2 Times Thickness of the Wall • Short Wall (In – to – In ) = Inner Length - 2 Times Thickness of the Wall B. Center Line Method • All dimensions are taken center to center 2/29/2024 21
  • 22. Measurement of Civil Works C. Crossing Method  Long Wall (Out – to - Out ) = Inner Length + 2 Times Thickness of the Wall  Short Wall (In – to – In ) = Inner Length 2/29/2024 22
  • 24. Measurement of Different Works I. Substructure Any structure below the ground floor slab level including the basement, retaining walls, ground slab, grade beam, and foundation is called a substructure. substructure work categorized as follows: 1. Excavation and earthworks 2. Concrete works 3. Masonry works 24 2/29/2024
  • 25. 1. Excavation and Earthworks A) Site clearance: • Removal of materials (including trees, bushes and the top 20 to 30 cm soil), any other obstruction from the site. • A working space of 1m is required on each side. • Clearing site vegetation is measured in m2 and embraces bushes, scrub, undergrowth trees . • Removal of trees is measured as enumerated item. 25 2/29/2024
  • 26. B) Excavation (bulk excavation) • Excavation to get reduced levels of every structural element below the ground level is called bulk excavation. • Working space for bulk excavation is 25 cm (not used for shallow masonry) • Depth of excavation less than 30 cm measured per m2 ,depth > 30 cm per m3 26 2/29/2024
  • 27. C) Deep Excavation • It is the actual excavation for the foundation and is measured in m3. D) Fill / Embankment • Shall be measured in m3 of net volume to be filled. Fill is required because the reduced level of every structural element above the structure has to be covered. 27 2/29/2024
  • 28. The subdivisions under fill are Back fill: - filling by using the excavated soil but by removing coarse particles. Borrow fill: - filling by using fill material from another place when there is shortage of fill or when better quality material is required. E) Disposal - cleaning the building area including cart away. measured with m3 28 2/29/2024
  • 29. 2. Concrete Works A) Concrete Grades of Concrete C5 - lean concrete, measured with m2 C15- for totally supported structural elements C20- used for slabs; mix proportion is 1:2:4 C25- Commonly used structural Concrete; mix proportion is 1:2:3 C30-Used for chemical stores and nuclear plants 29 2/29/2024
  • 30. B) Formwork – measured in m2 • Period of removal (minimum): 1. Vertical formwork to columns, walls and beams: 1-2 days depending on the types of cement we used 2. Soffits formwork to slab: 21 days 3. props to cantilever slabs: 14 days 4. Soffits(under side) formwork to beams: 21 days 5. Props to cantilever beams: 14 days 30 2/29/2024
  • 31. C) Reinforcement The reinforcement bars are tied by ø6 mm or ø8 mm mild steel wire and measured in kg. 3. Masonry Works stone for below ground work shall be chiseled from natural stone. • Stone wall is measured by volume, whereas stone pavement is measured by area, by specifying thickness. 31 2/29/2024
  • 32. II. Superstructure 1. Concrete works a. Concrete - as discussed in substructure part b. Formwork: Specify the type of material used and where to use (zigba or steel) – m2 c. Reinforcement: Weight per unit length for Ф6 is 0.222 kg/m; for any other diameter d2, with weight per unit length w2 32 w2 = (d2*2/162) * 0.222 2/29/2024
  • 33. 2. Masonry works a) Stone masonry:-Measured by volume b) Hollow and solid concrete blocks, measured by area specifying the thickness.  The standard thicknesses of HCBs are 10cm, 15cm, and 20cm. c) Bricks masonry: measured by area specifying the thickness.  Bricks are fire resistant, watertight and can also resist compressive action of up to 50 MPa.  The thicknesses of brick masonry are 25 cm (for double layer) and 12 cm (for single layer) 33 2/29/2024
  • 34. 3. Measurement of Roof Structure • The Unit of measurement for roof structure naturally falls between enumerated items (trusses) and linear meters, (rafters and purlins). Measurement of Pitched Roof Coverings • The area of roof coverings is unaffected by the inclusion of hipped ends and valleys as long as the roof pitch remains constant 34 2/29/2024
  • 36. Rainwater gutters and down pipes • Rainwater goods completes the work associated with roof coverings. • Gutters and down pipes are measured in linear meters over all fittings. The description should include reference to the type of pipe or gutter, its nominal size, and the type, method and spacing of fixings. 36 2/29/2024
  • 37. • Fittings, such as running outlets, stopped ends, offsets and connecting shoes, are enumerated and measured extra over the pipe or gutter on which they occur. 37 2/29/2024
  • 38. Measurement of Finishing's • The term Finishing includes operations associated with the completion of the floors, walls and ceilings of a building. These are screeding, plastering, wall and floor tiling, wallpapering and painting. • The order of measurement of finishing on each floor will normally be: » Ceiling » Walls » Floors 38 2/29/2024
  • 39. General rules of measurement • Work to attached beams is included with ceiling finishes, whilst work to attached columns is included with wall finishes. • Finishes to isolated beams and columns must be given separately as should work in staircase. • The principal unit of measurement for wall, floor and ceiling finishes is m2. Where the width does not exceed 300 mm the unit of measurement is linear. 39 2/29/2024
  • 40. 6. Sanitary appliances such as sinks, wash basins, baths and water closets. 7. Discharge pipes - waste, soil and vent pipes. 8. Any other work connected with the plumbing installation. Pipe work: Pipes are measured in linear meters over all fittings and branches, stating the type, nominal size and the method of jointing and fixing.  Fittings are enumerated and measured as extra-over the pipe work on which they occur. 40 2/29/2024