SlideShare a Scribd company logo
Mansoura University                                                     Construction Project Management
Faculty of Engineering                                                                     3rd Year Civil
Structural Eng. Dept.                                                                         2006-2007
                                               Exercise 4
                                    Due date: Wednesday, Nov 2nd 2005

1. The free float is defined as:
    a. The amount of time an activity can be delayed without affecting the following activity.
    b. The amount of time an activity can be delayed without affecting total project duration.

2. Total float equals:
    a. Late finish minus early finish                   c. Late start minus early start
    b. Late finish minus (early start + duration)       d. All of the above

3. State True (T) or False (F):

     a.   The critical activities can be determined easily when using the bar chart.
     b.   The network must have definite points of beginning and end.
     c.   The network must be continuous from start to end.
     d.   There’s no dummy activities in the arrow networks,
     e.   A forward pass is used to determine late start and late finish times.
     f.   The time for completing a project is equal to the sum of the individual activity times.

4. For the Following project data, answer the following questions:

                     Activity                 Duration (days)   Predecessor
                                A             2                          --
                                B             6                          A
                                C             3                          A
                                D             1                          B
                                E             6                          B
                                F             3                         C, D
                                G             2                         E, F

          a)   Draw an AOA network and perform forward and backward pass calculations?
          b)   Draw an AON network and perform forward and backward pass calculations?
          c)   Draw a time-scaled diagram of the project?
          d)   Tabulate activities ES, EF, LS, LF, TF, and FF.
          e)   What is the effect of delaying activity D by 3 days?

5. For the following AOA network, determine the following:

          a. Calculate ES, LF, & TF for all activities. Identify critical ones.
          b. Draw an early Bar Chart for the project.
          c. What is the effect of delaying activity “H” by two days on the total project duration?




Construction Management                             1                                Dr. Emad Elbeltagi
Mansoura University                                                                     Construction Project Management
Faculty of Engineering                                                                                     3rd Year Civil
Structural Eng. Dept.                                                                                         2006-2007

                                          3    D (8)         9
                              A (4)                                    H (4)


                    1           B (6)           E (10)       11      I (8)     15       K (5)    17
                                          5
                          C (2)                       F (16)
                                                                               J (10)
                                          7   G (6)          13



6. Perform PDM calculations for the project below and determine activity times. Durations are
shown on the activities

                                                                                         I
                                                                                        (2)

                                         B              D                G
                                        (4)            (1)              (1)

                         A                                                               J             L
                        (1)                                                             (7)           (2)

                                         C              E                H
                                        (1)            (2)              (1)

                                                        F                                K
                                                       (2)                              (4)



7. A gas station is proposed to be built on an already developed site. It will consist essentially of
a sales outlet and an office block. The sales outlet comprises of cash office and gas pumps. The
manager’s office building, which also houses public washrooms and an air compressor, is called
the office block. Adjacent to pumps will be a concrete pit that will house the gas tanks.

The entire area, excluding the office and pumps site, is covered with a concrete slab, and there is
a low perimeter wall in the rear. The utility company has undertaken to install an electric meter
on the site and connect it to the mains. Gasoline pumps must be obtained from the
manufacturers, and after being installed, they are to be connected to the gasoline tanks and the
power supply. Before use the local authority to ensure safety and compliance with regulations
must inspect them. Gasoline tanks are housed in concrete pits and covered by concrete slabs.
Before they are covered, however, the tanks and the associated pipe work have to be inspected
by the local authority. The sales outlet base is excavated first, the pipe work and tanks second,
the office block third, and the trench for underground services last. After the excavation for the
tanks and pipe work is completed, work can proceed on the construction of the perimeter wall
and air points.

Compressed air for inflated tires will be supplied by an electrically driven compressor, which
must be inspected by a competent person before the compressor is put into use. The air lines to

Construction Management                                          2                                    Dr. Emad Elbeltagi
Mansoura University                                                   Construction Project Management
Faculty of Engineering                                                                   3rd Year Civil
Structural Eng. Dept.                                                                       2006-2007
the “free air” points are installed with the general underground services, and the points
themselves are mounted on the perimeter wall. The air pints can be hooked up after the concrete
slab has been poured. Mobilization to start work comprises, among other preparations, the
moving of a trailer to the site to store tools, furnishings, and any weather prone parts and to serve
as the site office. Similarly, when work at the site is completed, the trailer will be removed, and
all scaffolding and construction equipment taken away. This is known as “demobilization and
clean up of site.”

You are required to determine the project duration, critical path(s), and tabulate activity times
(ES, EF, LS, LF, TF, and FF).

                         No            Activity Description            Duration
                          A   Excavate for sales outlet                     1
                          B   Construct sales outlet base                   1
                          C   Construct cash office                         2
                          D   Obtain pumps                                 16
                          E   Install pumps                                 2
                          F   Connect pumps                                 1
                          G   Inspector approves pumps installation         2
                          H   Paint & furnish office & washrooms            2
                          I   Connect office & toilet lighting              1
                          J   Excavate for office block                     1
                          K   Construct office block                        1
                          L   Build office & washrooms + services          15
                         M    Install electric meter                       14
                          N   Connect main cable to meter                   1
                          O   Install area lighting                         4
                          P   Mobilize site                                 1
                          Q   Set out and level site                        1
                          R   Excavate & lay underground services           1
                          S   Excavate for pipes and tanks                  1
                          T   Construct concrete pit                        2
                          U   Obtain pipes and tanks                        2
                          V   Install pipes and tanks                       3
                         W    Obtain compressor                            10
                          X   Install compressor                            1
                          Y   Connect power to compressor                   1
                          Z   Inspection of compressor                      2
                         AA   Backfill and cover tanks                      1
                         BB   Pour concrete slab                            2
                         CC   Construct perimeter wall + air points         2
                         DD   Connect air points                            1
                         EE   Demobilize and clean site                     1
                         FF   Inspection of pipes and tanks                 2



Construction Management                            3                               Dr. Emad Elbeltagi
Mansoura University                                                       Construction Project Management
 Faculty of Engineering                                                                       3rd Year Civil
 Structural Eng. Dept.                                                                           2006-2007
 8. For the following list of activities, draw a time-scaled diagram and mark the critical path.
 Determine activities ES, EF, LS, LF, FF, and TF.


                          Activity             Duration (days)    Predecessor
                                     A         4                          --
                                     B         10                         A
                                     C         2                          A
                                     D         6                          C
                                     E         15                       B, D
                                     F         4                        B, D
                                     G         3                          F
                                     H         2                        B, D
                                     I         1                       E, G, H
                                     J         3                          I
                                     K         2                          E
                                     L         1                          J
                                     M         2                        K, L


 9. For the following PDM, perform the forward pass and backward pass calculations. Determine
    the project duration and critical path. Tabulate the ES, EF, LS, LF, TF, and FF information for
    each activity.

                                                            E
                                                                            FF7
                                                            7




A         SS3, FF4
                      B        SS2
                                          D                                     F      SS8
                                                                                                       G
10                    8                   12                     FF5            9                      12


                                                                                             SS8

                                                                                                               J
                                                            C                                                  0
                                               SF5
                                                            8



                                         FS6
                                                                             H        FF3
                                                                                                   I
                                                                             10                    8




     Construction Management                            4                               Dr. Emad Elbeltagi

More Related Content

What's hot

Consolidated Drained (CD) Triaxial Test.pdf
Consolidated Drained (CD) Triaxial Test.pdfConsolidated Drained (CD) Triaxial Test.pdf
Consolidated Drained (CD) Triaxial Test.pdf
A K
 
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Muhammad Irfan
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidation
Malika khalil
 
Lecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soilLecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soil
husseinhadi2
 
Normal Consistency of Hydraulic Cement | Jameel Academy
Normal Consistency of Hydraulic Cement | Jameel AcademyNormal Consistency of Hydraulic Cement | Jameel Academy
Normal Consistency of Hydraulic Cement | Jameel Academy
Jameel Academy
 
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
Muhammad Irfan
 
Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
kmasz kamal
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
SantistebanCampos
 
Geotechnical Engineering-I [Lec #21: Consolidation Problems]
Geotechnical Engineering-I [Lec #21: Consolidation Problems]Geotechnical Engineering-I [Lec #21: Consolidation Problems]
Geotechnical Engineering-I [Lec #21: Consolidation Problems]
Muhammad Irfan
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
Dr. Mahmoud Al-Naimi
 
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
Muhammad Irfan
 
Homework 1 (solution )
Homework 1 (solution )Homework 1 (solution )
Homework 1 (solution )
Dr.Abdulmannan Orabi
 
Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head Method
Jameel Academy
 
ultimate bearing capacity of shallow foundations: special cases
ultimate bearing capacity of shallow foundations: special casesultimate bearing capacity of shallow foundations: special cases
ultimate bearing capacity of shallow foundations: special cases
Mehmet Akin
 
Class 4 Soil Compaction ( Geotechnical Engineering )
Class 4    Soil Compaction ( Geotechnical Engineering )Class 4    Soil Compaction ( Geotechnical Engineering )
Class 4 Soil Compaction ( Geotechnical Engineering )
Hossam Shafiq I
 
Pert analysis
Pert analysisPert analysis
Pert analysis
Hashamuddin Yaakob
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]
Muhammad Irfan
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Muhammad Irfan
 
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Muhammad Irfan
 
Mass haul diagram
Mass haul diagramMass haul diagram
Mass haul diagram
Professional Engineer
 

What's hot (20)

Consolidated Drained (CD) Triaxial Test.pdf
Consolidated Drained (CD) Triaxial Test.pdfConsolidated Drained (CD) Triaxial Test.pdf
Consolidated Drained (CD) Triaxial Test.pdf
 
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]Geotechnical Engineering-II [Lec #13: Elastic Settlements]
Geotechnical Engineering-II [Lec #13: Elastic Settlements]
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidation
 
Lecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soilLecture 1. bearing capacity of soil
Lecture 1. bearing capacity of soil
 
Normal Consistency of Hydraulic Cement | Jameel Academy
Normal Consistency of Hydraulic Cement | Jameel AcademyNormal Consistency of Hydraulic Cement | Jameel Academy
Normal Consistency of Hydraulic Cement | Jameel Academy
 
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
Geotechnical Engineering-I [Lec #20: Consolidation Settlement Computation]
 
Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
Geotechnical Engineering-I [Lec #21: Consolidation Problems]
Geotechnical Engineering-I [Lec #21: Consolidation Problems]Geotechnical Engineering-I [Lec #21: Consolidation Problems]
Geotechnical Engineering-I [Lec #21: Consolidation Problems]
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
Geotechnical Engineering-I [Lec #14: Lab Compaction of Soil]
 
Homework 1 (solution )
Homework 1 (solution )Homework 1 (solution )
Homework 1 (solution )
 
Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head Method
 
ultimate bearing capacity of shallow foundations: special cases
ultimate bearing capacity of shallow foundations: special casesultimate bearing capacity of shallow foundations: special cases
ultimate bearing capacity of shallow foundations: special cases
 
Class 4 Soil Compaction ( Geotechnical Engineering )
Class 4    Soil Compaction ( Geotechnical Engineering )Class 4    Soil Compaction ( Geotechnical Engineering )
Class 4 Soil Compaction ( Geotechnical Engineering )
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]Geotechnical Engineering-I [Lec #17: Consolidation]
Geotechnical Engineering-I [Lec #17: Consolidation]
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
 
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
Geotechnical Engineering-II [Lec #20: WT effect on Bearing Capcity)
 
Mass haul diagram
Mass haul diagramMass haul diagram
Mass haul diagram
 

Viewers also liked

Cm exercise 1
Cm exercise 1Cm exercise 1
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
Tu Nguyen, PMP®,PMI-RMP®
 
P introduction
P introductionP introduction
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 8
Cm exercise 8Cm exercise 8
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
Tu Nguyen, PMP®,PMI-RMP®
 
Cm exercise 6
Cm exercise 6Cm exercise 6
Cm exercise 3
Cm exercise 3Cm exercise 3
Cm exercise 5
Cm exercise 5Cm exercise 5
P contracts
P contractsP contracts
Strategic cost management
Strategic cost managementStrategic cost management
Strategic cost management
Vaibhav Banjan
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 

Viewers also liked (13)

Cm exercise 1
Cm exercise 1Cm exercise 1
Cm exercise 1
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
P introduction
P introductionP introduction
P introduction
 
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 2
 
Cm exercise 8
Cm exercise 8Cm exercise 8
Cm exercise 8
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Cm exercise 6
Cm exercise 6Cm exercise 6
Cm exercise 6
 
Cm exercise 3
Cm exercise 3Cm exercise 3
Cm exercise 3
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Cm exercise 5
Cm exercise 5Cm exercise 5
Cm exercise 5
 
P contracts
P contractsP contracts
P contracts
 
Strategic cost management
Strategic cost managementStrategic cost management
Strategic cost management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 

Similar to Cm exercise 4

606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
UpulHettiarachchi5
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
Tadele Asmare
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
Vinay Prajapati
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
guestd436758
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
guestac67362
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Ch4 scheduling
Ch4 schedulingCh4 scheduling
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
chandraswami
 
Robust Information Exchanges For BIM
Robust Information Exchanges For BIMRobust Information Exchanges For BIM
Robust Information Exchanges For BIM
Manu Venugopal
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
Ganesh Kandalkar
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project scheduling
Tadele Asmare
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
Abdullahi Oladimeji Hassan
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
Raja Manyam
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
Subhra Mishra
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using Etabs
IRJET Journal
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
ahsanrabbani
 
Syallabus Discussion Python.pptx
Syallabus Discussion Python.pptxSyallabus Discussion Python.pptx
Syallabus Discussion Python.pptx
SachinHarkal1
 

Similar to Cm exercise 4 (20)

606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Ch4 scheduling
Ch4 schedulingCh4 scheduling
Ch4 scheduling
 
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
 
Robust Information Exchanges For BIM
Robust Information Exchanges For BIMRobust Information Exchanges For BIM
Robust Information Exchanges For BIM
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project scheduling
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using Etabs
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
 
Syallabus Discussion Python.pptx
Syallabus Discussion Python.pptxSyallabus Discussion Python.pptx
Syallabus Discussion Python.pptx
 

More from Tu Nguyen, PMP®,PMI-RMP®

4.contracting
4.contracting4.contracting
3.estimating
3.estimating3.estimating
2.tendering
2.tendering2.tendering
1.introduction
1.introduction1.introduction
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Node
NodeNode
Contract
ContractContract
Cash flow
Cash flowCash flow
Bar chart
Bar chartBar chart
Arrow computation
Arrow computationArrow computation
Arrow computation
Tu Nguyen, PMP®,PMI-RMP®
 
Arrow
ArrowArrow
Administration
AdministrationAdministration
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
Tu Nguyen, PMP®,PMI-RMP®
 

More from Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 

Cm exercise 4

  • 1. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 Exercise 4 Due date: Wednesday, Nov 2nd 2005 1. The free float is defined as: a. The amount of time an activity can be delayed without affecting the following activity. b. The amount of time an activity can be delayed without affecting total project duration. 2. Total float equals: a. Late finish minus early finish c. Late start minus early start b. Late finish minus (early start + duration) d. All of the above 3. State True (T) or False (F): a. The critical activities can be determined easily when using the bar chart. b. The network must have definite points of beginning and end. c. The network must be continuous from start to end. d. There’s no dummy activities in the arrow networks, e. A forward pass is used to determine late start and late finish times. f. The time for completing a project is equal to the sum of the individual activity times. 4. For the Following project data, answer the following questions: Activity Duration (days) Predecessor A 2 -- B 6 A C 3 A D 1 B E 6 B F 3 C, D G 2 E, F a) Draw an AOA network and perform forward and backward pass calculations? b) Draw an AON network and perform forward and backward pass calculations? c) Draw a time-scaled diagram of the project? d) Tabulate activities ES, EF, LS, LF, TF, and FF. e) What is the effect of delaying activity D by 3 days? 5. For the following AOA network, determine the following: a. Calculate ES, LF, & TF for all activities. Identify critical ones. b. Draw an early Bar Chart for the project. c. What is the effect of delaying activity “H” by two days on the total project duration? Construction Management 1 Dr. Emad Elbeltagi
  • 2. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 3 D (8) 9 A (4) H (4) 1 B (6) E (10) 11 I (8) 15 K (5) 17 5 C (2) F (16) J (10) 7 G (6) 13 6. Perform PDM calculations for the project below and determine activity times. Durations are shown on the activities I (2) B D G (4) (1) (1) A J L (1) (7) (2) C E H (1) (2) (1) F K (2) (4) 7. A gas station is proposed to be built on an already developed site. It will consist essentially of a sales outlet and an office block. The sales outlet comprises of cash office and gas pumps. The manager’s office building, which also houses public washrooms and an air compressor, is called the office block. Adjacent to pumps will be a concrete pit that will house the gas tanks. The entire area, excluding the office and pumps site, is covered with a concrete slab, and there is a low perimeter wall in the rear. The utility company has undertaken to install an electric meter on the site and connect it to the mains. Gasoline pumps must be obtained from the manufacturers, and after being installed, they are to be connected to the gasoline tanks and the power supply. Before use the local authority to ensure safety and compliance with regulations must inspect them. Gasoline tanks are housed in concrete pits and covered by concrete slabs. Before they are covered, however, the tanks and the associated pipe work have to be inspected by the local authority. The sales outlet base is excavated first, the pipe work and tanks second, the office block third, and the trench for underground services last. After the excavation for the tanks and pipe work is completed, work can proceed on the construction of the perimeter wall and air points. Compressed air for inflated tires will be supplied by an electrically driven compressor, which must be inspected by a competent person before the compressor is put into use. The air lines to Construction Management 2 Dr. Emad Elbeltagi
  • 3. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 the “free air” points are installed with the general underground services, and the points themselves are mounted on the perimeter wall. The air pints can be hooked up after the concrete slab has been poured. Mobilization to start work comprises, among other preparations, the moving of a trailer to the site to store tools, furnishings, and any weather prone parts and to serve as the site office. Similarly, when work at the site is completed, the trailer will be removed, and all scaffolding and construction equipment taken away. This is known as “demobilization and clean up of site.” You are required to determine the project duration, critical path(s), and tabulate activity times (ES, EF, LS, LF, TF, and FF). No Activity Description Duration A Excavate for sales outlet 1 B Construct sales outlet base 1 C Construct cash office 2 D Obtain pumps 16 E Install pumps 2 F Connect pumps 1 G Inspector approves pumps installation 2 H Paint & furnish office & washrooms 2 I Connect office & toilet lighting 1 J Excavate for office block 1 K Construct office block 1 L Build office & washrooms + services 15 M Install electric meter 14 N Connect main cable to meter 1 O Install area lighting 4 P Mobilize site 1 Q Set out and level site 1 R Excavate & lay underground services 1 S Excavate for pipes and tanks 1 T Construct concrete pit 2 U Obtain pipes and tanks 2 V Install pipes and tanks 3 W Obtain compressor 10 X Install compressor 1 Y Connect power to compressor 1 Z Inspection of compressor 2 AA Backfill and cover tanks 1 BB Pour concrete slab 2 CC Construct perimeter wall + air points 2 DD Connect air points 1 EE Demobilize and clean site 1 FF Inspection of pipes and tanks 2 Construction Management 3 Dr. Emad Elbeltagi
  • 4. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 8. For the following list of activities, draw a time-scaled diagram and mark the critical path. Determine activities ES, EF, LS, LF, FF, and TF. Activity Duration (days) Predecessor A 4 -- B 10 A C 2 A D 6 C E 15 B, D F 4 B, D G 3 F H 2 B, D I 1 E, G, H J 3 I K 2 E L 1 J M 2 K, L 9. For the following PDM, perform the forward pass and backward pass calculations. Determine the project duration and critical path. Tabulate the ES, EF, LS, LF, TF, and FF information for each activity. E FF7 7 A SS3, FF4 B SS2 D F SS8 G 10 8 12 FF5 9 12 SS8 J C 0 SF5 8 FS6 H FF3 I 10 8 Construction Management 4 Dr. Emad Elbeltagi