SlideShare a Scribd company logo
Mansoura University                                                       Construction Project Management
Faculty of Engineering                                                                       3rd Year Civil
Structural Eng. Dept.                                                                           2006-2007
                                              Exercise 5
                                  Due date: Wednesday, Nov 16th 2006

1. The construction of a housing project involves the activities given in the following table. The
   contract is for the construction of twelve houses in 60 days. The man-hours for each activity
   and the crew size/house are also given. Prepare an LOB schedule for the contract. Assume a
   minimum buffer time of one day and six 8-hour days per week. What is the overall project
   duration and when will the first team of roof leave the site.

                    Description           Predecessors      Man-hours Team Size / Section
         Activity
            10      Substructure                 -              100                  4
            20      Superstructure              10              200                  8
            30      Roof                        20               60                  4
            40      Carpenter                   30               90                  6
            50      Plumber                     30               45                  3
            60      Electrician                 30               40                  3
            70      Plaster                 40, 50, 60          120                  8
            80      Final fix                   70              350                  24

2. The following network diagram represents the activities involved in a single house. Each
   activity shows the man-hours needed and the number of crew members. Assume 8 working
   hours per day and one day buffer time between activities.

    If you are to construct these tasks for 5 houses in 24 days, calculate the number of crews that
    need to be involved in each activity. Draw the schedule and define the day numbers in which
    each crew enters and leaves the site.

                                        Sanit. Main           Footing 2
                                       48 Mhrs              64 Mhrs
                                       3 Men                2 Man



                  Excavation             Footing 1             Wall 1               Wall 2
                 48 Mhrs               64 Mhrs              72 Mhrs              72 Mhrs
                 3 Men                 2 Man                3 Men                3 Men


3. The construction plan for a house is as follows, with activities durations in days:

                                                                 D (2)

            A (5)              B (5)            C (7)            E (3)            F (5)




Construction Management                                 1                                 Dr. Emad Elbeltagi
Mansoura University                                                Construction Project Management
Faculty of Engineering                                                                3rd Year Civil
Structural Eng. Dept.                                                                    2006-2007
 a) Calculate a weekly target rate to be used for scheduling a project of 30 repetitive houses, if
    all crews are working five 8-hour days per week and the project has to be delivered in 85
    days.

 b) Given a desired target rate of four units per week, what is the number of crews to be
    employed in activity B.

 c) Using the same number of crews obtained in (b), activity B has to be speed-up to a target
    rate of 5 units per week. Calculate how much time a crew needs to cut from the duration of
    each unit. Work continuity and crew synchronization has to be maintained.




Construction Management                         2                               Dr. Emad Elbeltagi

More Related Content

What's hot

Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
K.MAHESH KUMAR
 
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Sunil Kumar Meena
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABS
IRJET Journal
 
Hostel
HostelHostel
Hostel
Arpit Singh
 
REPORT BY SHUBHAM TRIPATHI
REPORT BY SHUBHAM TRIPATHIREPORT BY SHUBHAM TRIPATHI
REPORT BY SHUBHAM TRIPATHI
Shubham Tripathi
 
Seismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codesSeismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codes
eSAT Journals
 
Cantilever bridge lecture by amanat sir ce 316
Cantilever bridge lecture by amanat sir ce 316Cantilever bridge lecture by amanat sir ce 316
Cantilever bridge lecture by amanat sir ce 316
nazifa tabassum
 
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Sunil Kumar Meena
 
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET-  	  Seismic Analysis of G+6 Frame Building using ETABSIRJET-  	  Seismic Analysis of G+6 Frame Building using ETABS
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET Journal
 
residential buliding by stadd pro
residential buliding by stadd proresidential buliding by stadd pro
residential buliding by stadd pro
ila vamsi krishna
 
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
Suman Sau
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471
ktx500
 
C.V.
C.V.C.V.
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
Fresher Thinking
 
Milutin K.Zizic_PORFOLIO
Milutin K.Zizic_PORFOLIOMilutin K.Zizic_PORFOLIO
Milutin K.Zizic_PORFOLIO
MILUTIN K. ZIZIC
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Pro
gsharda123
 
Planning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential BuildingPlanning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential Building
Mohamed Peer Thavood
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ila vamsi krishna
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
Ali Meer
 
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET Journal
 

What's hot (20)

Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABS
 
Hostel
HostelHostel
Hostel
 
REPORT BY SHUBHAM TRIPATHI
REPORT BY SHUBHAM TRIPATHIREPORT BY SHUBHAM TRIPATHI
REPORT BY SHUBHAM TRIPATHI
 
Seismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codesSeismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codes
 
Cantilever bridge lecture by amanat sir ce 316
Cantilever bridge lecture by amanat sir ce 316Cantilever bridge lecture by amanat sir ce 316
Cantilever bridge lecture by amanat sir ce 316
 
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...Structural anaysis and design of g + 5 storey building using bentley stadd pr...
Structural anaysis and design of g + 5 storey building using bentley stadd pr...
 
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET-  	  Seismic Analysis of G+6 Frame Building using ETABSIRJET-  	  Seismic Analysis of G+6 Frame Building using ETABS
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
 
residential buliding by stadd pro
residential buliding by stadd proresidential buliding by stadd pro
residential buliding by stadd pro
 
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
PLANNING AND DESIGN OF G+3 RESIDENTIAL HOUSING COMPLEX (Share By Suman Sau)
 
Group 2 , ce471
Group 2  ,  ce471Group 2  ,  ce471
Group 2 , ce471
 
C.V.
C.V.C.V.
C.V.
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Milutin K.Zizic_PORFOLIO
Milutin K.Zizic_PORFOLIOMilutin K.Zizic_PORFOLIO
Milutin K.Zizic_PORFOLIO
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Pro
 
Planning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential BuildingPlanning Analysis Designing and Estimation of Residential Building
Planning Analysis Designing and Estimation of Residential Building
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
IRJET- Collapse Analysis of Irregular Flat Slab Structure at different Seismi...
 

Viewers also liked

Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
Tu Nguyen, PMP®,PMI-RMP®
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
Tu Nguyen, PMP®,PMI-RMP®
 
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 8
Cm exercise 8Cm exercise 8
P introduction
P introductionP introduction
Cm exercise 1
Cm exercise 1Cm exercise 1
P planning
P planningP planning
Bid document for Solar Plant at J&K
Bid document for Solar Plant at J&KBid document for Solar Plant at J&K
Bid document for Solar Plant at J&K
Headway Solar
 

Viewers also liked (9)

Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 2
 
Cm exercise 8
Cm exercise 8Cm exercise 8
Cm exercise 8
 
P introduction
P introductionP introduction
P introduction
 
Cm exercise 1
Cm exercise 1Cm exercise 1
Cm exercise 1
 
P planning
P planningP planning
P planning
 
Bid document for Solar Plant at J&K
Bid document for Solar Plant at J&KBid document for Solar Plant at J&K
Bid document for Solar Plant at J&K
 

Similar to Cm exercise 5

Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - Report
Sarchia Khursheed
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
guestac67362
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
guestd436758
 
IRJET- Analysis of Diagrid Structure
IRJET-  	  Analysis of Diagrid StructureIRJET-  	  Analysis of Diagrid Structure
IRJET- Analysis of Diagrid Structure
IRJET Journal
 
report2
report2report2
report2
Udayan Mitra
 
01ADNAN Mtech
01ADNAN Mtech01ADNAN Mtech
01ADNAN Mtech
adnan ahmed
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using Etabs
IRJET Journal
 
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
IRJET Journal
 
D18 cl124 report_8sem
D18 cl124 report_8semD18 cl124 report_8sem
D18 cl124 report_8sem
CHARUSSAT UNIVERSITY
 
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
IRJET Journal
 
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
IRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Mary Montoya
 
Use of OpenSees for the development of physics based tsunami fragility functions
Use of OpenSees for the development of physics based tsunami fragility functionsUse of OpenSees for the development of physics based tsunami fragility functions
Use of OpenSees for the development of physics based tsunami fragility functions
openseesdays
 
MIVAN TECHNOLOGY
MIVAN TECHNOLOGY MIVAN TECHNOLOGY
MIVAN TECHNOLOGY
ijiert bestjournal
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC Structures
IRJET Journal
 
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWAREREPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
RakeshDas161
 
Analysis of super structure building with plan and elevation irregularities u...
Analysis of super structure building with plan and elevation irregularities u...Analysis of super structure building with plan and elevation irregularities u...
Analysis of super structure building with plan and elevation irregularities u...
IRJET Journal
 
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
IRJET Journal
 
188.pptx
188.pptx188.pptx
188.pptx
19188BikashSah
 

Similar to Cm exercise 5 (20)

Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - Report
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
IRJET- Analysis of Diagrid Structure
IRJET-  	  Analysis of Diagrid StructureIRJET-  	  Analysis of Diagrid Structure
IRJET- Analysis of Diagrid Structure
 
report2
report2report2
report2
 
01ADNAN Mtech
01ADNAN Mtech01ADNAN Mtech
01ADNAN Mtech
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using Etabs
 
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
COMPARATIVE STUDY OF SEISMIC ANALYSIS OF REGULAR AND IRREGULAR STRUCTURE WITH...
 
D18 cl124 report_8sem
D18 cl124 report_8semD18 cl124 report_8sem
D18 cl124 report_8sem
 
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
BEHAVIOR OF MULTI STORIED BUILDING WITH VARYING HEIGHT, SEISMIC ZONE AND SOIL...
 
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
Evaluating Seismic Efficiency with Combination of Bracings in Steel Building ...
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
Use of OpenSees for the development of physics based tsunami fragility functions
Use of OpenSees for the development of physics based tsunami fragility functionsUse of OpenSees for the development of physics based tsunami fragility functions
Use of OpenSees for the development of physics based tsunami fragility functions
 
MIVAN TECHNOLOGY
MIVAN TECHNOLOGY MIVAN TECHNOLOGY
MIVAN TECHNOLOGY
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC Structures
 
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWAREREPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
 
Analysis of super structure building with plan and elevation irregularities u...
Analysis of super structure building with plan and elevation irregularities u...Analysis of super structure building with plan and elevation irregularities u...
Analysis of super structure building with plan and elevation irregularities u...
 
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
Cost Effectiveness of Reinforced Concrete and Post Tensioning Beam in Multi-S...
 
188.pptx
188.pptx188.pptx
188.pptx
 

More from Tu Nguyen, PMP®,PMI-RMP®

4.contracting
4.contracting4.contracting
3.estimating
3.estimating3.estimating
2.tendering
2.tendering2.tendering
1.introduction
1.introduction1.introduction
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Node
NodeNode
Contract
ContractContract
Cash flow
Cash flowCash flow
Bar chart
Bar chartBar chart
Arrow computation
Arrow computationArrow computation
Arrow computation
Tu Nguyen, PMP®,PMI-RMP®
 
Arrow
ArrowArrow
Administration
AdministrationAdministration
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
Tu Nguyen, PMP®,PMI-RMP®
 

More from Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 

Cm exercise 5

  • 1. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 Exercise 5 Due date: Wednesday, Nov 16th 2006 1. The construction of a housing project involves the activities given in the following table. The contract is for the construction of twelve houses in 60 days. The man-hours for each activity and the crew size/house are also given. Prepare an LOB schedule for the contract. Assume a minimum buffer time of one day and six 8-hour days per week. What is the overall project duration and when will the first team of roof leave the site. Description Predecessors Man-hours Team Size / Section Activity 10 Substructure - 100 4 20 Superstructure 10 200 8 30 Roof 20 60 4 40 Carpenter 30 90 6 50 Plumber 30 45 3 60 Electrician 30 40 3 70 Plaster 40, 50, 60 120 8 80 Final fix 70 350 24 2. The following network diagram represents the activities involved in a single house. Each activity shows the man-hours needed and the number of crew members. Assume 8 working hours per day and one day buffer time between activities. If you are to construct these tasks for 5 houses in 24 days, calculate the number of crews that need to be involved in each activity. Draw the schedule and define the day numbers in which each crew enters and leaves the site. Sanit. Main Footing 2 48 Mhrs 64 Mhrs 3 Men 2 Man Excavation Footing 1 Wall 1 Wall 2 48 Mhrs 64 Mhrs 72 Mhrs 72 Mhrs 3 Men 2 Man 3 Men 3 Men 3. The construction plan for a house is as follows, with activities durations in days: D (2) A (5) B (5) C (7) E (3) F (5) Construction Management 1 Dr. Emad Elbeltagi
  • 2. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 a) Calculate a weekly target rate to be used for scheduling a project of 30 repetitive houses, if all crews are working five 8-hour days per week and the project has to be delivered in 85 days. b) Given a desired target rate of four units per week, what is the number of crews to be employed in activity B. c) Using the same number of crews obtained in (b), activity B has to be speed-up to a target rate of 5 units per week. Calculate how much time a crew needs to cut from the duration of each unit. Work continuity and crew synchronization has to be maintained. Construction Management 2 Dr. Emad Elbeltagi