This document contains three questions related to construction project scheduling: 1. The first question provides a table of activities, durations, and crew sizes needed to build 12 houses over 60 days. It asks to create a line of balance schedule and determine when the first roofing team will leave the site. 2. The second question provides a network diagram of activities needed to build a single house. It asks to determine the number of crews needed for each activity to build 5 houses over 24 days and create a schedule showing crew entry and exit dates. 3. The third question provides durations for activities to build a house. It asks to calculate a weekly target rate to complete 30 houses in 85 days, determine the number of