Business Analytics
Business Process and Analytics


KAIST
박준성 교수


 2012. 12. 13


                Copyright © 2012. Dr. June Sung Park. All rights reserved.
Big Data

What is the most important part
of the term big data?

             big

            data

            both

           neither




                                  2
Big Data

What is the most important part
of the term big data?

              big

             data

             both

            neither

    What organizations do with big data is what is most important. The
    analysis your organization does against big data combined with the
    actions that are taken to improve your business are what matters.
    Analytics only produces business value if it is incorporated into business
    processes, enabling business managers and users to act upon the
    findings to improve organizational performance.

                       Bill Franks, Taming the Big Data Tidal Wave, Wiley, 2012.
                                                                                   3
Enterprise Analytics Capability




          Using analytics in mainstream business activities is one of
          the effective habits of a successful organization.


                                                                        4
Case Study: Amcor



 Company
 Global packing company in Australia
 with 20+K employees and $7B revenue
 in 2008.


 Challenge
 CEO initiated “Vale Plus” approach
 requiring measurement of “pocket
 margin” of 1M products down to the
 invoice level.




                                       5
Case Study: Amcor

Project
 Phase I:
    • Built a data warehouse over a year
      consolidating data from 32 apps.
    • Biggest challenge was standardizing
      and cleansing data.
 Phase II:
    • Built analytics and visualization over
      a month using an easy-to-use tool.
    • Business people with knowledge of
      processes helped fit the BI app into
      Amcor’s processes.
    • Rolled out the BI app in 4 stages,
      conducting usability tests, and
      training users by their business
      managers.

                                               6
Case Study: Amcor



Result                                 Lessons Learned
 500 users adopted it for daily use      Link BI projects with strategic initiatives.
  in 3 months.                            Align BI output with corporate KPIs.
 Incentives introduced that are          Implement BI within business processes.
  based on pocket margins.                Have business people, not IT people,
 Corporate gross margin                  determine BI use cases, i.e., where and
  improved.                               how they would use the BI app in process
                                          execution.
                                          Take enough time to consolidate silo
                                          data into a single version of standardized
                                          and cleansed data.
                                          Pick a tool easy for rapid deployment and
                                          easy for users.
                                          Have business managers train users.




                                                                                         7
Pattern-Based Business Strategy




                               Technology                    Market




                                            Your
                                          Company
                       Supplier                                Competition




    Enterprises should listen to signals and understand when the signals
    are patterns that require adaptation.
    Listening requires enterprises to combine traditional data sources with
    new sources of data.
                  Gartner, Pattern-based strategy: compete in the new economy using
                  Gartner’s business pattern framework, Sept. 14, 2005.
                                                                                      8
Pattern-Based Business Strategy

                                    Collective




               Defined                                   Creative
                                                           Case Management
 Business Process                                          Social Media
 Database / Data Mart / Warehouse                          Enterprise Mobility
 Service-Oriented Architecture                             Big Data Analytics
 Process Orchestration                                     Complex Event Processing
                                                           Event-Driven Architecture
         Anticipated Exceptions                   Anticipated Exceptions


  Enterprises should focus their investments on a balanced diversity of
  business activities in the defined, creative, collective and exceptions
  categories that enable them to innovate and respond to change of patterns.


                                                                                       9
Case Study: Investments in Big Data Analytics


                     TXU Energy installed smart electric meters in customer homes and read the
                     meter every 15 minutes. Based on an analysis of the metering data, it applies
                     dynamic pricing to shape demand curve during peak hours. This eliminates the
                     need for adding power generating capacity, saving millions of dollars for the
                     company and saving customer expenditures as well.



                     T-Mobile USA has integrated data across multiple IT systems to combine
                     customer transaction and interactions data in order to better predict customer
                     defections. By leveraging social media data along with transaction data from
                     CRM and billing systems, T-Mobile USA has been able to “cut customer
                     defections in half in a single quarter”.



                      US Xpress collects about a thousand data elements ranging from fuel usage to
                     tire condition to truck engine operations to GPS information, and uses this data
                     for optimal fleet management and to drive productivity saving millions of dollars
                     in operating costs.




                                                                                                         10
Pace-Layered IT Strategy


                                                                                      Case Management
         Explorative Apps                                                             Social Media
                                                                                      Enterprise Mobility
                                                                                      Big Data Analytics
        Exploitative Apps                                                             Complex Event Processing
                                                                                      Event-Driven Architecture

Stable Digital Foundation                                                             Business Process
                                                                                      Database / Data Mart / Warehouse
                                                                                      Service-Oriented Architecture
                                                                                      Process Orchestration



      Applications move across layers as they mature, or as the business
      process shifts from experimental to well-established to industry standard.
      You, however, cannot innovate on an unstable foundation.
      Many apps for both disruptive and sustaining innovations should be
      based on processes and data in the stable foundation

              Gartner, Accelerating innovation by adopting a pace-layered application strategy, Jan. 9. 2012.
                                                                                                                         11
Evolution of Enterprise IT

    Matured enterprise architecture is today based on standardized
    and integrated processes and data, and service-oriented
                                                                   Mobile Cloud
    architecture of apps.                                           Computing
                                                                                                                                                      (2010-2015)
                                                                                                             Technical Debt Payoff
                                                                                                                 (2005-2010)
                                                                                     E-Business




                                                                                                                                                                                  Process-Orchestrated
                                                                                    (1995-2005)




                                                                                                                                                        Mobile + Social + Cloud



                                                                                                                                                                                     Cloud Services
                                                  Client/Server




                                                                                                                                                              + Big Data
                                                   Computing




                                                                                                                                 Process Management
                                                  (1990-1995)
                                IT Dark Age




                                                                                                              IT Modernization


                                                                                                                                      SOA-Based
                    Online       (1980-90)




                                                                                       Process Integration
                  Computing



                                                                  Standardization

                                                                                           EA-Based
                  (1970-80)
      Batch
    Computing                                                           IT
   (1950-1970)
                                           Reengineering
                                              Process




                                                                                                  Stable Digital Foundation

             J. W. Ross, P. Weill and D. C. Robertson, Enterprise Architecture as Strategy, HBS Press, 2006.
                                                                                                                                                                                                    12
Stable Digital Foundation

   Business process management (BPM) is an ideal technology for agile development
   of explorative, exploitative and core apps for an enterprise.
   SOA embodies the middle-out architecture where business processes can be
   reengineered in flight to quickly implement new business use cases reusing core
   business services.
   Business service repository and data federation layers virtualize and synchronize
   physical apps and data to provide an integrated and standardized foundation.

                      Composite Apps

        Business Process Composition
           Business Service Repository
      Metadata-Based Data Federation
                         Physical Apps
                Physical Data Sources

                      Gartner, EIM reference architecture: an essential building block for
                      enterprise information management, Sept. 14, 2005.
                                                                                             13
Enterprise Architecture


                          Business Architecture                                 BPM  ACM
Business-IT Alignment




                        Application Architecture                                SOA  EDA

                              Data Architecture                                 MDM  Big Data

                          Technical Architecture                                TRM  Virtualization




                         EA is a strategy planning process ensuring business-IT alignment across
                         the enterprise using the architectural approach.
                         Matured EA employs BPM, SOA and MDM disciplines to enable quick
                         alignment between business use cases and app delivery by reusing
                         common master data and core services.

                                                                                                   14
Enterprise Architecture




                   Strategy Plan                      Demand Plan

                             As Is                    To Be

                   BA

                   AA

        IT Asset   DA                                               Investment
         Mgmt                                                          Plan
                   TA

                                     Transformation


                              Project Portfolio Mgmt



                                                                                 15
Business Process Management


                                 BPMN 2.0
               Design
        Graphical modeling,
        process simulation,
        business rules                                   BPEL4WS, BPEL4P
                                         Implement
                                  Code generation

                                                                   Execute       BPMS
                                                          Automation, workflow and
                                                          integration
                                          Monitor
                                 Business activity monitoring,
                                 automated process discovery and
                                 dashboards
              Optimize
        Analyze and dynamically adjust
        business processes and rules


                                                                                        16
Business Process Modeling



                             Enterprise
                            Content Mgmt
                                           Data Analytics




          Data modeling is designing the intended use of data.
          Process and data modeling cannot be done separately.

                                                                 17
Business Process Reengineering



                                      Adaptive
                                  Case Management
                                                    Social Collaboration




       Process innovation is often enabled by redesigning the flow of
       information.


                                                                           18
Adaptive, Intelligent and Social BPM
  Analytics, social network and adaptive case management are integrated into BPM
  for performance monitoring and reporting, forecasting, scenario modeling,
  complex decisions, planning, real-time situation recognition, immediate next
  action recommendation, etc.
  Enterprises need business process and performance management maturity that
  enables cross-functional accountability and top-down/bottom-up information
  flows.




                                       Enterprise
                                      Content Mgmt
                                                                                     Data Analytics


                                     Adaptive
                                       Case                          Social
                                    Management                   Collaboration
                Forrester, Forrester wave: dynamic case management, Jan. 31, 2011.
                                                                                                      19
Adaptive, Intelligent and Social BPM
  Integration of analytics into operational processes—which contrasts with past
  approaches that separated analytical work from transactional work—
  empowers the workforce to make better and faster contextualized decisions
  in order to guide work toward optimal outcome, and its impact is immediately
  apparent to business people because it changes the way they do their jobs.




                  http://bps.opentext.com/resources/ot_bps_OT-Process360_ds.pdf
                                                                                  20
BPM Maturity Model
   Enterprises usually cannot skip maturity levels.
   Enterprises should develop a long-term roadmap to improve their
   maturity level, based on the current state assessment and the readiness
   check for the next immediate actions.
                                                                       SOA




                              EA
   BPR




                                                                                           iBPMS




                                   BSC



              Gartner, ITScore overview for business process management, Sept. 17, 2010.
                                                                                                   21
Advanced BPM Initiatives
  Tomorrow's business operations require
  integration of real-time intelligence.
  Process is the unifying construct for intelligent
  operations.
  Integration of BPM and automated analytics into
  SOA-based iBPM is an important business
  evolution underway.




                Gartner, Business process management key initiative overview, July 22, 2011.
                                                                                               22
iBPMS
 Talend provides open source solutions for data integration, data profiling, data
 cleansing, master data management, enterprise service bus, Hadoop connection,
 cloud enablement, and BPM.
 Using Talend solutions, you can load data from multiple sources into a master
 data hub as a SoR, apply the data quality tool to resolve data conflicts, and
 provide clean data services for automated decisions in business processes or for
 business workers whose workflow is orchestrated by BPM.




                                                                                    23
iBPMS
        iBPMS has 10 core
        components:
          Orchestration engine
          for processes and
          cases
          Model-driven
          composition
          Human-driven
          workflow
          Content-driven
          workflow
          Connectivity of
          process to resources
          Active analytics
          On-demand analytics
          Business rule
          management
          Process repository
          BPMS administration

                                 24
Service-Oriented Enterprise Architecture



              Portal

             Business
             Process

         Business Service

                               SaaS
            Component

             Metadata
              Service

       Data Mart / Warehouse


             Database


             Big Data



                                           25
SOA Implementation using BPM Suite




                                                                               BPEL Process
Process Redesign using BPMN   Process KPI Definition     Process Simulation   Implementation




   Service        BPM UI and Monitoring           Service                Integration Test
 Specification      Implementation               Realization              and Execution




                                                                                               26
Linking BPM to Analytics based on SOA: SAP Netweaver

                                            BPM-specific BI content in
                                            InfoCube (star schema)



                                                                              OLAP data




                                                            Query on InfoCube


                                                                         Result
                                                                         in WSDL

                                                  Dashboard rendering
                                                  data from BPM




                                                                                          27
Enterprise Information Management




                                    Information
                                    governance and
                                    metadata
                                    management is
                                    critical to any
                                    initiative that
                                    uses data to
                                    drive
                                    improvements to
                                    business
                                    outcome.




                                                      28
Enterprise Information Management




                                    29
Enterprise Information Management Initiative
   Through 2015, 85% of Fortune 500 organizations will be unable to exploit
   big data for competitive advantage.


   1    Explore fundamental technology trends, such as big data, mobile, social
        media, cloud computing, and how they reinforce each other to offer
        opportunities and risks.
   2    Plan based on business strategy and enterprise architecture.


   3    Model business requirements and detail specification for solution delivery.

   4    Choose technologies and vendor/service providers.

   5    Implement, test and release the solution iteratively, seeking user feedback.

   6    Operate the solution, measure performance, revise the solution and refine
        governance processes.


                Gartner, Information innovation: innovation key Initiative overview, Apr. 27, 2012.
                                                                                                      30
Analytics Framework
    Analytic apps can work with any kind of data, including transactions, events,
    unstructured contents, website data, social networks, and Internet of things
    (machines, sensors).
                                                                                                             Increase
    Analytics, however, should resolve management challenges first.                                      analytical skills
                                Embed analytics into the                    Establish corporate           of centralized
                             business process and workflow.                performance metrics.          analytic team as
                                                                                                           well as self-
                                                                                                         service analysts
                                                                                                         within business
     Attract                                                                                                   units.
corporate execs
 to participate.
                                                                                                           Ensure data
                                                                                                            quality and
Find use cases                                                                                             consistency.
  and justify
business cases.
                                                                                                              Build
                                                                                                           requirement
    Create                                                                                                 engineering
 organization                                                                                              competency.
   culture of
 valuing fact-          Consumerize                                 Balance between standardization and diversification,
based decisions.       through mobile                               custom-design and packaged apps, on-premise and
                           delivery.                                   cloud, SQL and NoSQL, storage and in-memory
                            Gartner, Analytics key Initiative overview, July 22, 2011.
                                                                                                                           31
Analytics Maturity Model
   Enterprises usually cannot skip maturity levels.
   Enterprises should develop a long-term roadmap to improve their
   maturity level, based on the current state assessment and the
   readiness check for the next immediate actions.




        Gartner, ITScore overview for business intelligence and performance management, Sept. 17, 2010.
                                                                                                          32
Analytics Roadmap Planning
  Enterprises should assess the current level of maturity using a analytics
  framework, find areas of weakness and opportunities for improvement,
  set up a long-term roadmap to raise the maturity level, follow the EA
  process to determine and execute short-term improvement initiatives,
  and put in a continuous improvement program.

                             Data Consistency and Quality



          Culture of                                          Analytic
     Fact-Based Decision                                    Competencies




        Requirement
                                                              Process
        Engineering
                                                             and Metrics
        Methodology


                           Exec Commitment and Governance
                                                                              33
Analytics Lifecycle



                      Acquire data                      Organize data

                                           ETL or
                                            ELT     Data platform
                             Data source              (DB, DW,
                                                      Hadoop)
                 Set requirements                           Select and build
                  and hypotheses                                models
                                                                                Analyze
         Take                   BPM                   Analytics                   data
        action
                                                                               for insight
                      Embed into
                                                           Extract rules
                       operation
                                            BRM




                                    Make decision


                                                                                             34
Analytics Methodology: IBM and Capgemini




                                           35
Analytics Methodology: IBM




                             36
Analytics Requirement Metamodel
   Big data needs big process. (Forrester Research)
   Big data without a process context and a compelling use case for a
   specific user class is like a Maserati without an engine.
   Big data with proven values will become structured.
Process Model                                    Use Case Model     UX Model
    Business         Process Actor                  Use Case            Persona
      Rule                                           Actor


    I/O Info           Process        Event      Communication
                       Activity                    Association


                                                    Use Case            User Task

 Information Model
                                     Service
     Data                                           Use Case            User Task
                                                    Scenario            Scenario
   Dictionary
                                     Analytics

                                                                   User Concept
    Glossary          Data Model                                       Map



                                                                                    37
Analytics Requirement Engineering for SOA

                                                                   Enterprise
          Business                                                Architecture
          Strategy
                             Conceptual
                            Process Model
  UX                                                                  Conceptual
 Model                                                                Data Model               Business
                Use Case                     Conceptual
                                                                                               Req’ts
                 Model                      Service Model



                              Executable
                            Process Model                                                      Software
                                                            Logical Data                       Req’ts
                                                              Schema
   UI           Use Case
 Design         Scenario


                                                                                   Analytics

                     Test                     Service
                     Case                   Specification


                                                                                                          38
Analytics Requirement Engineering for SOA




                                      Design
          Model

                                                               Portal
           UX




                                        UI
                                                              Business




                                                    Case
                                                    Test
                                                              Process
                                        Scenario
                                                              Business
                  Case
                  Use




                                                               Service

                                                                            SaaS
                                                             Component
Process




                            Process
 Model




                             Exec




                                                              Metadata
                                                               Service

                                                             Data Mart /
                                                   Service
                  Service




                                                             Warehouse
                  Model




                                                    Spec




                                                              Database
                                      Schema




                                                              Big Data
          Model




                                       Data
          Data




                                                                           Service-Oriented Architecture


                                                                                                           39
Analytics Requirement Engineering for SOA: IBM

                                                             Service               Service         Process
            Use Case Model       Process Model             Specification        Implementation   Orchestration




    Industry
Reference Model




  Data Model




                      IBM, Building service-oriented solutions with IBM industry models and
                      Rational software development platform, 2007.
                                                                                                                 40
Analytics Requirement Engineering for SOA: Capgemini




                                                       41
Case Study: PayPal

Company
Global e-commerce business allowing payments and money transfers to be
made through the Internet.
Role of Global Business Analytics Team
 Managing Down: Ensure connection between the analysis they do and the
  actions the company takes. Work closely together with business people
  for right questions and right interpretation of findings.
 Managing Up: Establish themselves as thought partners, not data
  providers, to the executive, and translate analytical insights into actionable
  recommendations.                                                                                    Veronika
                                                                                                      Belokhvostova, Head
Analytics Team Members                                                                                of Global Business
Business analysts with a mix of technical and business skills. Most having                            Analytics at PayPal
MBAs in addition to data analysis skills.
Project Examples
Analysis of customer behaviors and interactions for improving products and
marketing, analysis of the impact of website redesign, analysis of the effect
of promotional pricing, diagnosis of of revenue leakages, analysis of the
impact of risk management policies on customers, etc.


                   Renee Ferguson, Mining data at PayPal to guide business strategy (Interview with
                   Veronika Belokhvostova), MIT Sloan Management Review, Sept. 2012.
                                                                                                                            42
Process-Driven Big Data Analytics Initiative


 Big data analytics requires a data-
  savvy business strategy to achieve
  competitive advantage.
 Keep the process transparent; it is
  key to successful big data projects.
 Educate process owners about
  potential big data opportunities
  now readily available through start-
  small, cost-effective analytics tools
  and techniques.
 The value delivered from an
  investment in big data analytics
  must be visible and measureable.




                                               43
Process-Driven Big Data Analytics Initiative

 Use low-cost, open-source tools in
  early pilots to demonstrate the
  feasibility of big data projects.
 Explore the increasing number of
  public datasets now available through
  open APIs.
 Produce a resource plan that identifies
  big data skill gaps. Look for business-
  savvy analysts (especially data
  scientists) and analytics-savvy
  business leaders who can work
  together to find what business should
  do based on analytic results and then
  do it.
 Assess resource needs for information
  infrastructure and identify technical
  gaps when supporting big data
  solutions.

                                               44
Data Scientist


                                                                               Business Use Cases


                                                                                  Analytics Apps


                                                                            Analytics Common Services

                                                            RT-OLAP             Analytic Algorithms         Visualization
                                                          e.g. BigQuery          e.g. Greenplum             e.g. Pentaho

                                                         In-Memory Data            Data Models                  ETL
                                                           e.g. GridGain         e.g. NoSQL, RDB             e.g. Kettle


                                                                          Basic Data Transformation
                                                                   e.g. Map Reduce, Pig, Hive, Sqoop, Lucene


                                                                File System                             NoSQL DB
                                                                 e.g. HDFS                              e.g. Hbase

                                                                           (In-Memory) Stream Processing
                                                                                  e.g. Flume, Avro

                                                                                Distributed Agents




                 Thomas Davenport and D. Patil, Data scientist: the sexiest job of the
                 21st century, Harvard Business Review Oct. 2012.
                                                                                                                            45
Case Study: Sears


Company
American chain of department stores
Challenge
 Decided to generate greater value from
  the huge amounts of customer, product
  and promotion data collected from its
  stores.
 Took 8 weeks, due to highly fragmented
  databases and data warehouses, to
  generate personalized promotions, at
  which point many of them were no
  longer optimal.




                    Andrew McAfee and Erik Brynjolfsson, Big data: the management
                    revolution, Harvard Business Review, Oct. 2012.
                                                                                    46
Case Study: Sears



Solution
 Set up a Hadoop cluster in 2010,
  and used it to store incoming data
  from its stores and to hold data
  from existing data warehouses.
 Conducted analyses directly on the
  cluster, with the processing time
  reduced from 8 to 1 week, and still
  dropping.
 Got help from Cloudera initially,
  but over time internal IT and
  analysts became comfortable with
  the new tools and methods.




                                        47
Q&A

Business process based analytics

  • 1.
    Business Analytics Business Processand Analytics KAIST 박준성 교수 2012. 12. 13 Copyright © 2012. Dr. June Sung Park. All rights reserved.
  • 2.
    Big Data What isthe most important part of the term big data? big data both neither 2
  • 3.
    Big Data What isthe most important part of the term big data? big data both neither What organizations do with big data is what is most important. The analysis your organization does against big data combined with the actions that are taken to improve your business are what matters. Analytics only produces business value if it is incorporated into business processes, enabling business managers and users to act upon the findings to improve organizational performance. Bill Franks, Taming the Big Data Tidal Wave, Wiley, 2012. 3
  • 4.
    Enterprise Analytics Capability Using analytics in mainstream business activities is one of the effective habits of a successful organization. 4
  • 5.
    Case Study: Amcor Company Global packing company in Australia with 20+K employees and $7B revenue in 2008. Challenge CEO initiated “Vale Plus” approach requiring measurement of “pocket margin” of 1M products down to the invoice level. 5
  • 6.
    Case Study: Amcor Project Phase I: • Built a data warehouse over a year consolidating data from 32 apps. • Biggest challenge was standardizing and cleansing data.  Phase II: • Built analytics and visualization over a month using an easy-to-use tool. • Business people with knowledge of processes helped fit the BI app into Amcor’s processes. • Rolled out the BI app in 4 stages, conducting usability tests, and training users by their business managers. 6
  • 7.
    Case Study: Amcor Result Lessons Learned  500 users adopted it for daily use Link BI projects with strategic initiatives. in 3 months. Align BI output with corporate KPIs.  Incentives introduced that are Implement BI within business processes. based on pocket margins. Have business people, not IT people,  Corporate gross margin determine BI use cases, i.e., where and improved. how they would use the BI app in process execution. Take enough time to consolidate silo data into a single version of standardized and cleansed data. Pick a tool easy for rapid deployment and easy for users. Have business managers train users. 7
  • 8.
    Pattern-Based Business Strategy Technology Market Your Company Supplier Competition Enterprises should listen to signals and understand when the signals are patterns that require adaptation. Listening requires enterprises to combine traditional data sources with new sources of data. Gartner, Pattern-based strategy: compete in the new economy using Gartner’s business pattern framework, Sept. 14, 2005. 8
  • 9.
    Pattern-Based Business Strategy Collective Defined Creative Case Management Business Process Social Media Database / Data Mart / Warehouse Enterprise Mobility Service-Oriented Architecture Big Data Analytics Process Orchestration Complex Event Processing Event-Driven Architecture Anticipated Exceptions Anticipated Exceptions Enterprises should focus their investments on a balanced diversity of business activities in the defined, creative, collective and exceptions categories that enable them to innovate and respond to change of patterns. 9
  • 10.
    Case Study: Investmentsin Big Data Analytics TXU Energy installed smart electric meters in customer homes and read the meter every 15 minutes. Based on an analysis of the metering data, it applies dynamic pricing to shape demand curve during peak hours. This eliminates the need for adding power generating capacity, saving millions of dollars for the company and saving customer expenditures as well. T-Mobile USA has integrated data across multiple IT systems to combine customer transaction and interactions data in order to better predict customer defections. By leveraging social media data along with transaction data from CRM and billing systems, T-Mobile USA has been able to “cut customer defections in half in a single quarter”. US Xpress collects about a thousand data elements ranging from fuel usage to tire condition to truck engine operations to GPS information, and uses this data for optimal fleet management and to drive productivity saving millions of dollars in operating costs. 10
  • 11.
    Pace-Layered IT Strategy Case Management Explorative Apps Social Media Enterprise Mobility Big Data Analytics Exploitative Apps Complex Event Processing Event-Driven Architecture Stable Digital Foundation Business Process Database / Data Mart / Warehouse Service-Oriented Architecture Process Orchestration Applications move across layers as they mature, or as the business process shifts from experimental to well-established to industry standard. You, however, cannot innovate on an unstable foundation. Many apps for both disruptive and sustaining innovations should be based on processes and data in the stable foundation Gartner, Accelerating innovation by adopting a pace-layered application strategy, Jan. 9. 2012. 11
  • 12.
    Evolution of EnterpriseIT Matured enterprise architecture is today based on standardized and integrated processes and data, and service-oriented Mobile Cloud architecture of apps. Computing (2010-2015) Technical Debt Payoff (2005-2010) E-Business Process-Orchestrated (1995-2005) Mobile + Social + Cloud Cloud Services Client/Server + Big Data Computing Process Management (1990-1995) IT Dark Age IT Modernization SOA-Based Online (1980-90) Process Integration Computing Standardization EA-Based (1970-80) Batch Computing IT (1950-1970) Reengineering Process Stable Digital Foundation J. W. Ross, P. Weill and D. C. Robertson, Enterprise Architecture as Strategy, HBS Press, 2006. 12
  • 13.
    Stable Digital Foundation Business process management (BPM) is an ideal technology for agile development of explorative, exploitative and core apps for an enterprise. SOA embodies the middle-out architecture where business processes can be reengineered in flight to quickly implement new business use cases reusing core business services. Business service repository and data federation layers virtualize and synchronize physical apps and data to provide an integrated and standardized foundation. Composite Apps Business Process Composition Business Service Repository Metadata-Based Data Federation Physical Apps Physical Data Sources Gartner, EIM reference architecture: an essential building block for enterprise information management, Sept. 14, 2005. 13
  • 14.
    Enterprise Architecture Business Architecture BPM  ACM Business-IT Alignment Application Architecture SOA  EDA Data Architecture MDM  Big Data Technical Architecture TRM  Virtualization EA is a strategy planning process ensuring business-IT alignment across the enterprise using the architectural approach. Matured EA employs BPM, SOA and MDM disciplines to enable quick alignment between business use cases and app delivery by reusing common master data and core services. 14
  • 15.
    Enterprise Architecture Strategy Plan Demand Plan As Is To Be BA AA IT Asset DA Investment Mgmt Plan TA Transformation Project Portfolio Mgmt 15
  • 16.
    Business Process Management BPMN 2.0 Design Graphical modeling, process simulation, business rules BPEL4WS, BPEL4P Implement Code generation Execute BPMS Automation, workflow and integration Monitor Business activity monitoring, automated process discovery and dashboards Optimize Analyze and dynamically adjust business processes and rules 16
  • 17.
    Business Process Modeling Enterprise Content Mgmt Data Analytics Data modeling is designing the intended use of data. Process and data modeling cannot be done separately. 17
  • 18.
    Business Process Reengineering Adaptive Case Management Social Collaboration Process innovation is often enabled by redesigning the flow of information. 18
  • 19.
    Adaptive, Intelligent andSocial BPM Analytics, social network and adaptive case management are integrated into BPM for performance monitoring and reporting, forecasting, scenario modeling, complex decisions, planning, real-time situation recognition, immediate next action recommendation, etc. Enterprises need business process and performance management maturity that enables cross-functional accountability and top-down/bottom-up information flows. Enterprise Content Mgmt Data Analytics Adaptive Case Social Management Collaboration Forrester, Forrester wave: dynamic case management, Jan. 31, 2011. 19
  • 20.
    Adaptive, Intelligent andSocial BPM Integration of analytics into operational processes—which contrasts with past approaches that separated analytical work from transactional work— empowers the workforce to make better and faster contextualized decisions in order to guide work toward optimal outcome, and its impact is immediately apparent to business people because it changes the way they do their jobs. http://bps.opentext.com/resources/ot_bps_OT-Process360_ds.pdf 20
  • 21.
    BPM Maturity Model Enterprises usually cannot skip maturity levels. Enterprises should develop a long-term roadmap to improve their maturity level, based on the current state assessment and the readiness check for the next immediate actions. SOA EA BPR iBPMS BSC Gartner, ITScore overview for business process management, Sept. 17, 2010. 21
  • 22.
    Advanced BPM Initiatives Tomorrow's business operations require integration of real-time intelligence. Process is the unifying construct for intelligent operations. Integration of BPM and automated analytics into SOA-based iBPM is an important business evolution underway. Gartner, Business process management key initiative overview, July 22, 2011. 22
  • 23.
    iBPMS Talend providesopen source solutions for data integration, data profiling, data cleansing, master data management, enterprise service bus, Hadoop connection, cloud enablement, and BPM. Using Talend solutions, you can load data from multiple sources into a master data hub as a SoR, apply the data quality tool to resolve data conflicts, and provide clean data services for automated decisions in business processes or for business workers whose workflow is orchestrated by BPM. 23
  • 24.
    iBPMS iBPMS has 10 core components: Orchestration engine for processes and cases Model-driven composition Human-driven workflow Content-driven workflow Connectivity of process to resources Active analytics On-demand analytics Business rule management Process repository BPMS administration 24
  • 25.
    Service-Oriented Enterprise Architecture Portal Business Process Business Service SaaS Component Metadata Service Data Mart / Warehouse Database Big Data 25
  • 26.
    SOA Implementation usingBPM Suite BPEL Process Process Redesign using BPMN Process KPI Definition Process Simulation Implementation Service BPM UI and Monitoring Service Integration Test Specification Implementation Realization and Execution 26
  • 27.
    Linking BPM toAnalytics based on SOA: SAP Netweaver BPM-specific BI content in InfoCube (star schema) OLAP data Query on InfoCube Result in WSDL Dashboard rendering data from BPM 27
  • 28.
    Enterprise Information Management Information governance and metadata management is critical to any initiative that uses data to drive improvements to business outcome. 28
  • 29.
  • 30.
    Enterprise Information ManagementInitiative Through 2015, 85% of Fortune 500 organizations will be unable to exploit big data for competitive advantage. 1 Explore fundamental technology trends, such as big data, mobile, social media, cloud computing, and how they reinforce each other to offer opportunities and risks. 2 Plan based on business strategy and enterprise architecture. 3 Model business requirements and detail specification for solution delivery. 4 Choose technologies and vendor/service providers. 5 Implement, test and release the solution iteratively, seeking user feedback. 6 Operate the solution, measure performance, revise the solution and refine governance processes. Gartner, Information innovation: innovation key Initiative overview, Apr. 27, 2012. 30
  • 31.
    Analytics Framework Analytic apps can work with any kind of data, including transactions, events, unstructured contents, website data, social networks, and Internet of things (machines, sensors). Increase Analytics, however, should resolve management challenges first. analytical skills Embed analytics into the Establish corporate of centralized business process and workflow. performance metrics. analytic team as well as self- service analysts within business Attract units. corporate execs to participate. Ensure data quality and Find use cases consistency. and justify business cases. Build requirement Create engineering organization competency. culture of valuing fact- Consumerize Balance between standardization and diversification, based decisions. through mobile custom-design and packaged apps, on-premise and delivery. cloud, SQL and NoSQL, storage and in-memory Gartner, Analytics key Initiative overview, July 22, 2011. 31
  • 32.
    Analytics Maturity Model Enterprises usually cannot skip maturity levels. Enterprises should develop a long-term roadmap to improve their maturity level, based on the current state assessment and the readiness check for the next immediate actions. Gartner, ITScore overview for business intelligence and performance management, Sept. 17, 2010. 32
  • 33.
    Analytics Roadmap Planning Enterprises should assess the current level of maturity using a analytics framework, find areas of weakness and opportunities for improvement, set up a long-term roadmap to raise the maturity level, follow the EA process to determine and execute short-term improvement initiatives, and put in a continuous improvement program. Data Consistency and Quality Culture of Analytic Fact-Based Decision Competencies Requirement Process Engineering and Metrics Methodology Exec Commitment and Governance 33
  • 34.
    Analytics Lifecycle Acquire data Organize data ETL or ELT Data platform Data source (DB, DW, Hadoop) Set requirements Select and build and hypotheses models Analyze Take BPM Analytics data action for insight Embed into Extract rules operation BRM Make decision 34
  • 35.
  • 36.
  • 37.
    Analytics Requirement Metamodel Big data needs big process. (Forrester Research) Big data without a process context and a compelling use case for a specific user class is like a Maserati without an engine. Big data with proven values will become structured. Process Model Use Case Model UX Model Business Process Actor Use Case Persona Rule Actor I/O Info Process Event Communication Activity Association Use Case User Task Information Model Service Data Use Case User Task Scenario Scenario Dictionary Analytics User Concept Glossary Data Model Map 37
  • 38.
    Analytics Requirement Engineeringfor SOA Enterprise Business Architecture Strategy Conceptual Process Model UX Conceptual Model Data Model Business Use Case Conceptual Req’ts Model Service Model Executable Process Model Software Logical Data Req’ts Schema UI Use Case Design Scenario Analytics Test Service Case Specification 38
  • 39.
    Analytics Requirement Engineeringfor SOA Design Model Portal UX UI Business Case Test Process Scenario Business Case Use Service SaaS Component Process Process Model Exec Metadata Service Data Mart / Service Service Warehouse Model Spec Database Schema Big Data Model Data Data Service-Oriented Architecture 39
  • 40.
    Analytics Requirement Engineeringfor SOA: IBM Service Service Process Use Case Model Process Model Specification Implementation Orchestration Industry Reference Model Data Model IBM, Building service-oriented solutions with IBM industry models and Rational software development platform, 2007. 40
  • 41.
    Analytics Requirement Engineeringfor SOA: Capgemini 41
  • 42.
    Case Study: PayPal Company Globale-commerce business allowing payments and money transfers to be made through the Internet. Role of Global Business Analytics Team  Managing Down: Ensure connection between the analysis they do and the actions the company takes. Work closely together with business people for right questions and right interpretation of findings.  Managing Up: Establish themselves as thought partners, not data providers, to the executive, and translate analytical insights into actionable recommendations. Veronika Belokhvostova, Head Analytics Team Members of Global Business Business analysts with a mix of technical and business skills. Most having Analytics at PayPal MBAs in addition to data analysis skills. Project Examples Analysis of customer behaviors and interactions for improving products and marketing, analysis of the impact of website redesign, analysis of the effect of promotional pricing, diagnosis of of revenue leakages, analysis of the impact of risk management policies on customers, etc. Renee Ferguson, Mining data at PayPal to guide business strategy (Interview with Veronika Belokhvostova), MIT Sloan Management Review, Sept. 2012. 42
  • 43.
    Process-Driven Big DataAnalytics Initiative  Big data analytics requires a data- savvy business strategy to achieve competitive advantage.  Keep the process transparent; it is key to successful big data projects.  Educate process owners about potential big data opportunities now readily available through start- small, cost-effective analytics tools and techniques.  The value delivered from an investment in big data analytics must be visible and measureable. 43
  • 44.
    Process-Driven Big DataAnalytics Initiative  Use low-cost, open-source tools in early pilots to demonstrate the feasibility of big data projects.  Explore the increasing number of public datasets now available through open APIs.  Produce a resource plan that identifies big data skill gaps. Look for business- savvy analysts (especially data scientists) and analytics-savvy business leaders who can work together to find what business should do based on analytic results and then do it.  Assess resource needs for information infrastructure and identify technical gaps when supporting big data solutions. 44
  • 45.
    Data Scientist Business Use Cases Analytics Apps Analytics Common Services RT-OLAP Analytic Algorithms Visualization e.g. BigQuery e.g. Greenplum e.g. Pentaho In-Memory Data Data Models ETL e.g. GridGain e.g. NoSQL, RDB e.g. Kettle Basic Data Transformation e.g. Map Reduce, Pig, Hive, Sqoop, Lucene File System NoSQL DB e.g. HDFS e.g. Hbase (In-Memory) Stream Processing e.g. Flume, Avro Distributed Agents Thomas Davenport and D. Patil, Data scientist: the sexiest job of the 21st century, Harvard Business Review Oct. 2012. 45
  • 46.
    Case Study: Sears Company Americanchain of department stores Challenge  Decided to generate greater value from the huge amounts of customer, product and promotion data collected from its stores.  Took 8 weeks, due to highly fragmented databases and data warehouses, to generate personalized promotions, at which point many of them were no longer optimal. Andrew McAfee and Erik Brynjolfsson, Big data: the management revolution, Harvard Business Review, Oct. 2012. 46
  • 47.
    Case Study: Sears Solution Set up a Hadoop cluster in 2010, and used it to store incoming data from its stores and to hold data from existing data warehouses.  Conducted analyses directly on the cluster, with the processing time reduced from 8 to 1 week, and still dropping.  Got help from Cloudera initially, but over time internal IT and analysts became comfortable with the new tools and methods. 47
  • 48.