SlideShare a Scribd company logo
Dry coke to wet-Actions
Changes during dry to wet coke
screen jam due to high moisture
Nut coke outer surface covered with fines
Burden head end and tail end lead with nut coke
Coke Bunker levels difficult to maintain
Fines increases result in reduction in wind acceptance
Underutilisation of nutcoke to take care of acceptance impact on low level of coke result in fines due to high fall.
Centre coke surface coke proportion change
Process upsets /control on process
Process Control
Temperature control
•Thermal Control scheme
Gas control
•Burden distribution
Chemical control
•Burdening
Thermal Control
Purpose of;
Ensure temperature of
hot metal is as required
by steel plant, while
maintaining a fluid slag
Controlled by;
Coke rate
Measured
with;
Hot metal temperature
maintaining a fluid slag
Tuyere injectants Top temperature
Heat losses
Chemical Control
Purpose of; chemical
control
• Ensuring the correct HM
composition for steel plant,
and slag granulate for
customer
Controlled by;
• Burden chemistry
Measured with;
• Hot metal analysis
• Slag analysis
• Top gas analysis
Steam and PCI: T Flame and Hydrogen
• The furnace content sees only:
– Gas, consisting of CO ( CO2), H2 ( H2O), N2
– Heat
– The furnace doesn’t know where hydrogen comes from. Moisture? Coal?
• Hydrogen
– Normal operation for all coke
• HBT 1010, moisture 40 gr/NM3, no oxygen enrichment, O2/tHM 245 NM3,
– blast volume = 1200 NM3/t, 48 kg steam per ton: 5,5 kg H2/tHM of which ~2
kg comes from ambient moisture
kg comes from ambient moisture
– Coal contains 4-5% hydrogen, 3,5 kg hydrogen comes from ~80-90 kg
PCI/tHM
– At PCI of 80-90 kg/tHM, steam injection can be 0
• Step by step, reduce first to moisture in HB to total 30 gr/NM3
• Learn to use PCI for “safety”
– Availability PCI
– Works only if T Flame is > 2050 C
• Heat: control T Flame 2050-2250(?) C
– Too high: burden descent can become erratic
– Too low: PCI “doesn’t work”
Out of Control Sheet
Be aware of
furnace ‘out of
control’ when;
Burden descent is
poor
Keep furnace
under control by;
Reducing blast
rate
Furnace cooling
down
Water ingress
into furnace
Long stops
Casting
Using ‘safe’
burden (low
basicity, high coke
rate)
Defining ‘Out of Control’
• Furnace not reacting to standard measures in
the usual time span
• Frequent slips
• Cooling trend that cannot be reversed with
Operating outside • Cooling trend that cannot be reversed with
corrective actions
• High blast pressure
• Cause can not be found
• Have investigated and eliminated possible
causes
• Unexplained casting irregularities
Operating outside
normal procedures,
that is:
Protecting the Furnace
Add extra fuel by way of a coke blank, increase coke rate by 3% and increase fuel injection
Reduce the blast rate, but keep fuel injection on the furnace
Cast the furnace
Expert systems are not designed to operate during chills, should not be relied upon at such times.
These actions are done to Protect the furnace for the time that is required to find the problem.
Investigate the situation, now that the furnace process has been protected
Call Management to inform them of the situation
Reduce basicity by 10%
Raise the cohesive zone with a coke blank
• Charge a 15 t coke blank
• Short interruption of production
• Situation fully back to normal after six hours
• No burden calculation required – original is still applicable
• Automatically reduces basicity
Gas Flow Control
• Giving enough contact between
the ore and the gas for sufficient
indirect reduction to occur
Purpose
of;
Controlled • Burden distribution
Controlled
by;
• Above burden probes
• stack temperatures
• pressure taps
• Top temperature
• Top gas analyses
Measured
with;
Effect of a tuyere without fuel injection
Asymmetric cohesive zone
Cohesive zone with one tuyere off
Pressure Drop and Coke Rate
Peep-sight Observations (2)
4. Oval tuyere
surround
• Tipped tuyere
• If lance
position can
not be seen,
impingement is
possible
5. Partially
blocked tuyere
• May be
blocked with
slag, char or
unreduced
material
6. Fully blocked
tuyere
• Injection is no
longer possible
Peep-sight Observations (1)
1. Normal tuyere
flame
• Lance in
correct
position
• Bright flame
2. Dull appearance
of tuyere flame
• Possibly water
leakage in the
furnace
3. Lance position
incorrect
• This can lead
to wearing of
the tuyere,
causing tuyere
leakage
Peep-sight Observations (3)
7. Slag entering the
tuyere
• Shows a high
liquid level, usually
when blast
pressure is being
reduced
8. Solid material in
front of the tuyere
• This can be scabs,
or a concentration
of fines coming
down in front of
the tuyere
Summary of Gas Flow Control
Monitor stability of
burden descent
Stockrods
Stack Pressure Taps
Monitor stability of
central coke chimney and
central gas flow
CO/CO2
Above burden probe
central gas flow Above burden probe
In burden probe
Monitor wall gas flow Skinflow TC’s
Heat flux (esp upper
belly, lower stack)
Wall temperatures
Above burden probe
In burden probe
Gas Flow Control
Blast Furnace Parameters
for Gas Flow Control
Burden
• Size
• Weights
• Coke moisture gauges
Above Burden Probe
Profile Meter
Top Gas
• Analysis
• Temperature (uptakes or
dust catcher)
• Pressure
Infra-red camera
Stock Rod
Skin flow thermocouple
Profile Meter
In–burden Probe
(fixed or retractable)
Hot Blast
• Flow Rate
• Temperature
• Tuyere input (H20, O2, Fuel…)
Skin flow thermocouple
• Intermediate Pressure Taps
• In–wall Thermocouple
• Heat Loss Measurements
• Stave body temperatures
Effect of thick ore layer in Furnaces
• Ore flows more towards the
centre
• It overflows the coke
• When this ore starts to melt, it
will have poor permeability
Permeability of coke and ore layers
High resistance to gas flow
• Ore burden particles are smaller and have less voidage.
• Gas flows 4 times easier through coke than through ore.
Low resistance to gas flow
What to do in case of poor burden descent?
• Too high blast pressure: decrease
blast
• Poor hearth drainage: cast, open
2nd taphole, open with bigger
drill diameter
• Too hot furnace (means high
position of cohesive zone): cool
Burden weight
Upward force by
position of cohesive zone): cool
down with additional moisture
injection
• Too many fines in burden:
eliminate sources of fines e.g.
poor quality burden materials
Upward force by
blast
Upward force by
liquid
Summary Sheet
• Poor burden descent is indicator of disturbed blast furnace process
• In sequence of severity:
– Slow burden movement and slight slips
– Hanging and slipping
– Kicks
• Will lead to fuel shortage in furnace
• Corrective actions:
– Decrease blast volume
– Compensate with extra fuel
Feed tank failure, what to do?
• Low injection levels (< 25 t/hr)
– Switch off oxygen when not injecting PCI
– Cycle time of filling feed tank is 15-20 minutes
– Feed tank can deliver 22 ton per cycle (1 hour or more)
– For limited time, go to PCI on/off cycle. Take oxygen also on/off.
feed tank cycle available for injection
hour 0 1 2 3 4 5
feed tank 1
feed tank 2
feed tank 1
feed tank 2 not available
Causes of Poor Burden Descent
• High blast pressure caused by
• Retained liquids in hearth
• Hot furnace: cohesive zone high in furnace
• Too many fines
Effects of Slips on Furnace Process
• Cold material in hearth
• Energy escapes from furnace not
being used in the process: high
top temperature, high CO/CO2,
high wall temperatures
• Cooling trend
• What to do:
• What to do:
– Make up energy loss with
additional fuel
– Recover burden level
– Recover normal layer
structure, if needed, by
operating for a complete
furnace fill on lower blast
volume (4-6 hours)
T Flame effects
• 5 ton coal/hr reduces T Flame ~ 65 C
• 1% oxygen increases Tflame ~ 54 C
• - 10 g/NM3 moisture = -2,5 ton steam/hr
increases T Flame with ~53 C
Burden Slips
• Voidage collapses
• Burden level low
• Severe disruption of layer
structure
• Gas flow impeded, gas jets along
furnace wall
Racing/Fast Filling / High Charging Rate
High charging rate is
consequence of
High oxygen input into
furnace
Wind
Too low fuel rate
Coke charged
Effects:
Low top
temperature
Reaction: slow down
production rate by
increasing fuel
injection
Oxygen
enrichment
Water!
(Leakage)
Fuel injection
level
Too much
fuel used in
process
Low CO/CO2
(High
solution loss)
Cooling trend
How to manage Low Bin Levels
Potential Consequences
for the furnace?
•Material falls further
•More fines are produced
How can Control Room
Operator find out if bin What are steps to take?
•More fines are produced
•Either these will be screened
out, giving a yield loss
•Or, they will be charged to the
furnace
•Blast pressure can increase
with more fines
•Wind rate has to be reduced
•So production is reduced
Operator find out if bin
levels are too low?
•Reported by
personnel/automatic system
•Known interruptions in supply
•Cameras and/or level indicators
What are steps to take?
•Stagger the restart of the bins
to avoid high-fines material
being charged from two bins
simultaneously
•Try to keep all bins at >80% full
Bin Contamination
•Fuel shortage/excess
•Basicity changes
•Contaminated central coke chimney
•High wall flows
Potential consequences for the furnace
•Reported to him when it occurs, or is noticed
How can Control Room Operator find out about contamination?
•Reported to him when it occurs, or is noticed
•Furnace top cameras
•Increase/change in return fines
•Chemistry changes in hot metal or slag
•Filling times
•Moisture levels
•isolate the bunker
•Assess the impact on the furnace of the material already charged
•Charge as a different specified material
•Or Charge a much smaller quantity to empty the bunker
•Or empty out
Steps to Take
Practical Examples
Bin
Contamination
What are the potential
consequences for the
furnace?
Bin Levels too
low
What are the
potential
consequences for
furnace?
How can the Control
Room Operator find
out of bins are
contaminated?
What are the steps to
take when bins are
known to be
contaminated? Why?
consequences for
the furnace?
How can the Control
Room Operator find
out if the bin levels
are too low?
What are the steps
to take when bin
levels are too low?
Why?
Coke break-up, nut coke covered with more fines
As weak coke breaks up voids fill with smaller pieces and the gas flow and
liquid metal and slag flow becomes more difficult.
Fines Descending through Furnace
Descend
1
2
Fines charged
near wall
Descend
straight down,
do not melt or
reduce
(impermeable
to gases)
Solids seen
through
peephole
Blast pressure
may increase,
furnace can
hang
2
3
Blast Pressure & the Process
Below the
equipment-set
The maximum blast
pressure for the Above the
Reducing the blast
pressure before the
When Top pressure
is kept constant;
equipment-set
blast pressure limit,
the blast pressure
fluctuates up to a
defined limit for
the process.
pressure for the
process is the point
at which the
furnace can
operate without
the risk of hanging
and slipping.
Above the
maximum blast
pressure for the
process the furnace
may start to hang
or slip.
pressure before the
maximum is
reached can
stabilise the
process before
hanging or slipping
occurs.
Required Properties of Material
• Moisture content controlled – may be measured and corrected for by
gauges
• Strength at ambient temperature – to prevent breaking up before charging
• Strength at high temperature – to prevent breaking up in the furnace
• Chemistry – to make sure there is enough of what is required, and not too
much of anything else
much of anything else
• Size distribution – limit the amount of fines
• Average size – should be within required range
Thermal Control
• CO Utilisation
• Heat Load to the Walls
• Top Gas Temperature
• Hot Metal Temperature and Silicon Content
• Charging Rate-Racing furnace
• Loss of Hot Blast Temperature
• Loss of Stockline
Racing furnace-example
• Number of charges (0-2) - Average number of charges per
hour over the last 2 hours
• Number of charges(0-8) - Average number of charges per
hour over the last 8 hours
• If Number of charges/hour C(0-2) = Number of
For example
• If Number of charges/hour C(0-2) = Number of
charges/hour(0-8) + 2
• We say furnace racing, making more melt, thermal sink
• Consequences- reduce the blast volume by 1800 Nm3/hr
For example
Racing Furnace, Direct Reduction (DR) and Wu
Racing Furnace, Direct Reduction (DR) and Wu
FeO + CO = Fe + CO2
Fe₂O₃ + CO = 2FeO + CO₂
110⁰C
1300⁰C
4/7/2021 38
FeO + CO = Fe + CO2
C + CO₂ = 2CO (>900oC: Solution loss)
Why fce cool during racing condition?
Racing furnace happens due to more DR which
consumes heat and consumes Carbon which does not
burn at the tuyeres
So Furnace cools. Due to poor reduction.
Wu is the residual heat in the lower zone = heat of
combustion – heat of solution loss + heat of blast
temp – heat to split steam and PCI
1500⁰C
2150⁰C
DR
Guidelines for operators-How to keep thermal stability in racing furnace
• For racing furnace, consider the 4 hour charging rate, as well as the 8 hour, because there are
times when this will give earlier warning, especially when the charging rate rapidly
accelerates.
• Racing furnace actions if the 4 hour charging rate is at least 9% above expected or the 8 hour
is at least 5% above expected.
• If the charging rate is increasing, (4 hour or 8 hour), or we are building up blast volume from
a reduced blast period, do not set coal variation to negative.
a reduced blast period, do not set coal variation to negative.
• Be very wary of setting the coal variation below -5 for more than a few hours. Increase
steam first. i.e. only if charging rate slow and furnace hot.
• Do not go below -5 if charging rate slow but thermally OK.
• Do not go below -5 if furnace hot but charging rate OK.
• When the top gas analysis is under maintenance, Wu ends up well out of range and
misleading. If Wu does not look right, cross check the top gas analysis with the power station
on the expert system trend.
• Note that the time for a PCI rate change to affect metal quality is 7 to 11 hours, whereas
steam is 3 to 5 hours.
Delays and effect times
PCI: 3 kg/thm = 10 deg C = 0.07% Si. 7 to 11 hours
Steam: -4g/Nm3 = 8 deg C. 3 to 5 hours
PCI to Wu: 3 kg/thm = 50 MJ/thm. 4 to 6 hours.
0
2
4
6
8
10
12
0 1 2 3 4 5 6 7 8 9 10 11 12
Hours
Effect time PCI change to hotmetal temp
PCI change (kg/thm)
Change in metal temp (deg C)
50
60
70
80
90
100
5
6
7
8
9
10
Change
in
Wu
MJ/thm
Change
in
PCI
ratekg/thm
Effect time PCI change to Wu
PCI change (kg/thm)
Change in Wu (MJ/thm)
Wu to HMT: 50 MJ/thm = 10 deg C. 3 hours
0
10
20
30
40
0
1
2
3
4
0 1 2 3 4 5 6 7 8 9 10 11 12
Change
in
Wu
MJ/thm
Change
in
PCI
ratekg/thm
Hours
-5
-3
-1
1
3
5
7
0 1 2 3 4 5 6 7 8 9 10 11 12
Hours
Effect time steam change to hotmetal temp
Steam change (kg/thm)
Change in metal temp (deg C)
Note that the furnace is not an incinerator.
Increasing PCI rate does not immediately generate more heat
as the furnace will just burn coal instead of coke.
The furnace will eventually warm up because the burden
in the stack will descend more slowly so will be exposed
to more reducing gas.
It will then be better reduced and need less direct reduction.
What is oxy/thm factor?
• Volume of oxygen assumed to make 1 thm
• 6300 BV at 3% enrichment: oxygen in blast is
6300 * (21+3)/100 = 1512 Nm3/min
• If oxy/thm is 245 Nm3/thm then furnace is assumed to produce
1512/245 = 6.17 thm/minute = 370 thm/hour
1512/245 = 6.17 thm/minute = 370 thm/hour
• Aim PCI of 130 kg/thm. So coal flow setpoint calculated is
370 * 130 = 48140 kg/h
• If the furnace is racing so that it is only using 235 Nm3/thm:
• Actual production rate = 1512/235 * 60 = 386 thm/hour
• Actual coal rate = 48140/386 = 125 kg/thm (5 kg/thm short)
– Plus the effect of less coke to burn and higher direct reduction
8h expected and actual charging rate on RTR1
• 8 hourly charging rate is the actual measured charges per 8 hours
• Expected charging rate is what the 8 hour charging rate would be if the furnace
was charging as expected. The expected make is calculated from the average blast
volume and oxygen enrichment over the past 8 hours and the oxy/thm factor. This
is divided by the current fe yield per charge to calculate the expected charging
rate.
• Actual v expected is the percentage difference between the actual charging rate
• Actual v expected is the percentage difference between the actual charging rate
and what it should have been.
• If the furnace is charging at least 5% faster than it should be, averaged over 8
hours, then this indicates a racing furnace. The colour of this row changes to red.
• If the charging rate is more than 2% above where it should be then the colour
changes to orange, as this is likely to lead to a cooling furnace if it persists.
• Note that when burdening for a change in PCI rate the expected rate will be more
accurate on the expert system as it allows for the change in coke volume in the
stack which occurs before the change in PCI rate.

More Related Content

What's hot

111658903 kiln-burning-systems
111658903 kiln-burning-systems111658903 kiln-burning-systems
111658903 kiln-burning-systemsIngrid McKenzie
 
blast-furnace-and-basic-oxygen-process
 blast-furnace-and-basic-oxygen-process blast-furnace-and-basic-oxygen-process
blast-furnace-and-basic-oxygen-processAchmad Shofi
 
Snow ball formation pradeep kumar
Snow ball formation  pradeep kumarSnow ball formation  pradeep kumar
Snow ball formation pradeep kumarpradeepdeepi
 
Coke oven life prolongation a multidisciplinary approach
Coke oven life prolongation   a multidisciplinary approachCoke oven life prolongation   a multidisciplinary approach
Coke oven life prolongation a multidisciplinary approach
Jorge Madias
 
Sintering plant
Sintering plantSintering plant
Sintering plant
Aidin Sadeghianpour
 
Sponge iron making process
Sponge iron making processSponge iron making process
Sponge iron making process
Albertus Septyantoko
 
Sponge Iron Industry
Sponge Iron IndustrySponge Iron Industry
Sponge Iron Industry
susmitadasgupta
 
Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilnspradeepdeepi
 
Sulfur formation
Sulfur formationSulfur formation
Sulfur formation
mkpq pasha
 
Sintering Technology
Sintering   Technology  Sintering   Technology
Sintering Technology
Sajan Agrawal
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation
Muzzamil Eatoo
 
Burning and cooling
Burning and coolingBurning and cooling
Burning and coolingirrraju1976
 
Sintering plant at a glance
Sintering plant at a glanceSintering plant at a glance
Sintering plant at a glance
Sajan Agrawal
 
Jindal Steel Training
Jindal Steel TrainingJindal Steel Training
Jindal Steel Training
Himanshu Yadav
 
PYRO-JET BURNER Prism Johnson Cement.ppt
PYRO-JET BURNER Prism Johnson Cement.pptPYRO-JET BURNER Prism Johnson Cement.ppt
PYRO-JET BURNER Prism Johnson Cement.ppt
RamakantTiwari26
 
Formulas kiln
Formulas kilnFormulas kiln
Formulas kiln
Inderjeet Singh Sidhu
 
Blast furnace
Blast furnaceBlast furnace
Blast furnace
MD Raza
 

What's hot (20)

111658903 kiln-burning-systems
111658903 kiln-burning-systems111658903 kiln-burning-systems
111658903 kiln-burning-systems
 
blast-furnace-and-basic-oxygen-process
 blast-furnace-and-basic-oxygen-process blast-furnace-and-basic-oxygen-process
blast-furnace-and-basic-oxygen-process
 
Coke oven
Coke ovenCoke oven
Coke oven
 
Snow ball formation pradeep kumar
Snow ball formation  pradeep kumarSnow ball formation  pradeep kumar
Snow ball formation pradeep kumar
 
Coke oven life prolongation a multidisciplinary approach
Coke oven life prolongation   a multidisciplinary approachCoke oven life prolongation   a multidisciplinary approach
Coke oven life prolongation a multidisciplinary approach
 
Sintering plant
Sintering plantSintering plant
Sintering plant
 
Sponge iron making process
Sponge iron making processSponge iron making process
Sponge iron making process
 
Sponge Iron Industry
Sponge Iron IndustrySponge Iron Industry
Sponge Iron Industry
 
Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilns
 
sponge iron TCE NMD
sponge iron TCE NMDsponge iron TCE NMD
sponge iron TCE NMD
 
Sulfur formation
Sulfur formationSulfur formation
Sulfur formation
 
Sintering Technology
Sintering   Technology  Sintering   Technology
Sintering Technology
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation
 
Burning and cooling
Burning and coolingBurning and cooling
Burning and cooling
 
sail bokaro
sail bokarosail bokaro
sail bokaro
 
Sintering plant at a glance
Sintering plant at a glanceSintering plant at a glance
Sintering plant at a glance
 
Jindal Steel Training
Jindal Steel TrainingJindal Steel Training
Jindal Steel Training
 
PYRO-JET BURNER Prism Johnson Cement.ppt
PYRO-JET BURNER Prism Johnson Cement.pptPYRO-JET BURNER Prism Johnson Cement.ppt
PYRO-JET BURNER Prism Johnson Cement.ppt
 
Formulas kiln
Formulas kilnFormulas kiln
Formulas kiln
 
Blast furnace
Blast furnaceBlast furnace
Blast furnace
 

Similar to Blast furnace process-Dry and wet coke in blast furnace

Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
Gerard B. Hawkins
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
SubratSahu57
 
FIRED HEATERS.ppt
FIRED HEATERS.pptFIRED HEATERS.ppt
FIRED HEATERS.ppt
LokeshRavichandran1
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
ZookOne
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
HRHabib7
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
SupratimRoy16
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
rajam575648
 
Avoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operationAvoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operation
Gerard B. Hawkins
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
Gerard B. Hawkins
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
DeepakSingh1807
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
VEERABHADRA SWAMY
 
different type of boiler & combustion in boilers
different type of boiler & combustion in boilersdifferent type of boiler & combustion in boilers
different type of boiler & combustion in boilers
Showhanur Rahman
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
Susovan Sensharma
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
Gerard B. Hawkins
 
Slide share porous load autoclave wet loads
Slide share porous load autoclave wet loadsSlide share porous load autoclave wet loads
Slide share porous load autoclave wet loads
Chris Maughan
 
Superheat in Porous Load Autoclaves
Superheat in Porous Load AutoclavesSuperheat in Porous Load Autoclaves
Superheat in Porous Load Autoclaves
Chris Maughan
 
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdfEthylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
MeysamAmini4
 
O&amp;m of boiler
O&amp;m of boilerO&amp;m of boiler
O&amp;m of boiler
Kshirod Bose
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
Gerard B. Hawkins
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
HirajanSandragesan
 

Similar to Blast furnace process-Dry and wet coke in blast furnace (20)

Reduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming CatalystReduction and Start-Up of Steam Reforming Catalyst
Reduction and Start-Up of Steam Reforming Catalyst
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 
FIRED HEATERS.ppt
FIRED HEATERS.pptFIRED HEATERS.ppt
FIRED HEATERS.ppt
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 
Avoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operationAvoid syn gas catalyst mal operation
Avoid syn gas catalyst mal operation
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
different type of boiler & combustion in boilers
different type of boiler & combustion in boilersdifferent type of boiler & combustion in boilers
different type of boiler & combustion in boilers
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
The Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam ReformingThe Benefits and Disadvantages of Potash in Steam Reforming
The Benefits and Disadvantages of Potash in Steam Reforming
 
Slide share porous load autoclave wet loads
Slide share porous load autoclave wet loadsSlide share porous load autoclave wet loads
Slide share porous load autoclave wet loads
 
Superheat in Porous Load Autoclaves
Superheat in Porous Load AutoclavesSuperheat in Porous Load Autoclaves
Superheat in Porous Load Autoclaves
 
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdfEthylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
Ethylene Unit Cracked Gas Compressor Case Studies on Fouling.pdf
 
O&amp;m of boiler
O&amp;m of boilerO&amp;m of boiler
O&amp;m of boiler
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
 

Recently uploaded

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Blast furnace process-Dry and wet coke in blast furnace

  • 1. Dry coke to wet-Actions
  • 2. Changes during dry to wet coke screen jam due to high moisture Nut coke outer surface covered with fines Burden head end and tail end lead with nut coke Coke Bunker levels difficult to maintain Fines increases result in reduction in wind acceptance Underutilisation of nutcoke to take care of acceptance impact on low level of coke result in fines due to high fall. Centre coke surface coke proportion change Process upsets /control on process
  • 3. Process Control Temperature control •Thermal Control scheme Gas control •Burden distribution Chemical control •Burdening
  • 4. Thermal Control Purpose of; Ensure temperature of hot metal is as required by steel plant, while maintaining a fluid slag Controlled by; Coke rate Measured with; Hot metal temperature maintaining a fluid slag Tuyere injectants Top temperature Heat losses
  • 5. Chemical Control Purpose of; chemical control • Ensuring the correct HM composition for steel plant, and slag granulate for customer Controlled by; • Burden chemistry Measured with; • Hot metal analysis • Slag analysis • Top gas analysis
  • 6. Steam and PCI: T Flame and Hydrogen • The furnace content sees only: – Gas, consisting of CO ( CO2), H2 ( H2O), N2 – Heat – The furnace doesn’t know where hydrogen comes from. Moisture? Coal? • Hydrogen – Normal operation for all coke • HBT 1010, moisture 40 gr/NM3, no oxygen enrichment, O2/tHM 245 NM3, – blast volume = 1200 NM3/t, 48 kg steam per ton: 5,5 kg H2/tHM of which ~2 kg comes from ambient moisture kg comes from ambient moisture – Coal contains 4-5% hydrogen, 3,5 kg hydrogen comes from ~80-90 kg PCI/tHM – At PCI of 80-90 kg/tHM, steam injection can be 0 • Step by step, reduce first to moisture in HB to total 30 gr/NM3 • Learn to use PCI for “safety” – Availability PCI – Works only if T Flame is > 2050 C • Heat: control T Flame 2050-2250(?) C – Too high: burden descent can become erratic – Too low: PCI “doesn’t work”
  • 7. Out of Control Sheet Be aware of furnace ‘out of control’ when; Burden descent is poor Keep furnace under control by; Reducing blast rate Furnace cooling down Water ingress into furnace Long stops Casting Using ‘safe’ burden (low basicity, high coke rate)
  • 8. Defining ‘Out of Control’ • Furnace not reacting to standard measures in the usual time span • Frequent slips • Cooling trend that cannot be reversed with Operating outside • Cooling trend that cannot be reversed with corrective actions • High blast pressure • Cause can not be found • Have investigated and eliminated possible causes • Unexplained casting irregularities Operating outside normal procedures, that is:
  • 9. Protecting the Furnace Add extra fuel by way of a coke blank, increase coke rate by 3% and increase fuel injection Reduce the blast rate, but keep fuel injection on the furnace Cast the furnace Expert systems are not designed to operate during chills, should not be relied upon at such times. These actions are done to Protect the furnace for the time that is required to find the problem. Investigate the situation, now that the furnace process has been protected Call Management to inform them of the situation Reduce basicity by 10%
  • 10. Raise the cohesive zone with a coke blank • Charge a 15 t coke blank • Short interruption of production • Situation fully back to normal after six hours • No burden calculation required – original is still applicable • Automatically reduces basicity
  • 11. Gas Flow Control • Giving enough contact between the ore and the gas for sufficient indirect reduction to occur Purpose of; Controlled • Burden distribution Controlled by; • Above burden probes • stack temperatures • pressure taps • Top temperature • Top gas analyses Measured with;
  • 12. Effect of a tuyere without fuel injection Asymmetric cohesive zone Cohesive zone with one tuyere off
  • 13. Pressure Drop and Coke Rate
  • 14. Peep-sight Observations (2) 4. Oval tuyere surround • Tipped tuyere • If lance position can not be seen, impingement is possible 5. Partially blocked tuyere • May be blocked with slag, char or unreduced material 6. Fully blocked tuyere • Injection is no longer possible
  • 15. Peep-sight Observations (1) 1. Normal tuyere flame • Lance in correct position • Bright flame 2. Dull appearance of tuyere flame • Possibly water leakage in the furnace 3. Lance position incorrect • This can lead to wearing of the tuyere, causing tuyere leakage
  • 16. Peep-sight Observations (3) 7. Slag entering the tuyere • Shows a high liquid level, usually when blast pressure is being reduced 8. Solid material in front of the tuyere • This can be scabs, or a concentration of fines coming down in front of the tuyere
  • 17. Summary of Gas Flow Control Monitor stability of burden descent Stockrods Stack Pressure Taps Monitor stability of central coke chimney and central gas flow CO/CO2 Above burden probe central gas flow Above burden probe In burden probe Monitor wall gas flow Skinflow TC’s Heat flux (esp upper belly, lower stack) Wall temperatures Above burden probe In burden probe
  • 18. Gas Flow Control Blast Furnace Parameters for Gas Flow Control Burden • Size • Weights • Coke moisture gauges Above Burden Probe Profile Meter Top Gas • Analysis • Temperature (uptakes or dust catcher) • Pressure Infra-red camera Stock Rod Skin flow thermocouple Profile Meter In–burden Probe (fixed or retractable) Hot Blast • Flow Rate • Temperature • Tuyere input (H20, O2, Fuel…) Skin flow thermocouple • Intermediate Pressure Taps • In–wall Thermocouple • Heat Loss Measurements • Stave body temperatures
  • 19. Effect of thick ore layer in Furnaces • Ore flows more towards the centre • It overflows the coke • When this ore starts to melt, it will have poor permeability
  • 20. Permeability of coke and ore layers High resistance to gas flow • Ore burden particles are smaller and have less voidage. • Gas flows 4 times easier through coke than through ore. Low resistance to gas flow
  • 21. What to do in case of poor burden descent? • Too high blast pressure: decrease blast • Poor hearth drainage: cast, open 2nd taphole, open with bigger drill diameter • Too hot furnace (means high position of cohesive zone): cool Burden weight Upward force by position of cohesive zone): cool down with additional moisture injection • Too many fines in burden: eliminate sources of fines e.g. poor quality burden materials Upward force by blast Upward force by liquid
  • 22. Summary Sheet • Poor burden descent is indicator of disturbed blast furnace process • In sequence of severity: – Slow burden movement and slight slips – Hanging and slipping – Kicks • Will lead to fuel shortage in furnace • Corrective actions: – Decrease blast volume – Compensate with extra fuel
  • 23. Feed tank failure, what to do? • Low injection levels (< 25 t/hr) – Switch off oxygen when not injecting PCI – Cycle time of filling feed tank is 15-20 minutes – Feed tank can deliver 22 ton per cycle (1 hour or more) – For limited time, go to PCI on/off cycle. Take oxygen also on/off. feed tank cycle available for injection hour 0 1 2 3 4 5 feed tank 1 feed tank 2 feed tank 1 feed tank 2 not available
  • 24. Causes of Poor Burden Descent • High blast pressure caused by • Retained liquids in hearth • Hot furnace: cohesive zone high in furnace • Too many fines
  • 25. Effects of Slips on Furnace Process • Cold material in hearth • Energy escapes from furnace not being used in the process: high top temperature, high CO/CO2, high wall temperatures • Cooling trend • What to do: • What to do: – Make up energy loss with additional fuel – Recover burden level – Recover normal layer structure, if needed, by operating for a complete furnace fill on lower blast volume (4-6 hours)
  • 26. T Flame effects • 5 ton coal/hr reduces T Flame ~ 65 C • 1% oxygen increases Tflame ~ 54 C • - 10 g/NM3 moisture = -2,5 ton steam/hr increases T Flame with ~53 C
  • 27. Burden Slips • Voidage collapses • Burden level low • Severe disruption of layer structure • Gas flow impeded, gas jets along furnace wall
  • 28. Racing/Fast Filling / High Charging Rate High charging rate is consequence of High oxygen input into furnace Wind Too low fuel rate Coke charged Effects: Low top temperature Reaction: slow down production rate by increasing fuel injection Oxygen enrichment Water! (Leakage) Fuel injection level Too much fuel used in process Low CO/CO2 (High solution loss) Cooling trend
  • 29. How to manage Low Bin Levels Potential Consequences for the furnace? •Material falls further •More fines are produced How can Control Room Operator find out if bin What are steps to take? •More fines are produced •Either these will be screened out, giving a yield loss •Or, they will be charged to the furnace •Blast pressure can increase with more fines •Wind rate has to be reduced •So production is reduced Operator find out if bin levels are too low? •Reported by personnel/automatic system •Known interruptions in supply •Cameras and/or level indicators What are steps to take? •Stagger the restart of the bins to avoid high-fines material being charged from two bins simultaneously •Try to keep all bins at >80% full
  • 30. Bin Contamination •Fuel shortage/excess •Basicity changes •Contaminated central coke chimney •High wall flows Potential consequences for the furnace •Reported to him when it occurs, or is noticed How can Control Room Operator find out about contamination? •Reported to him when it occurs, or is noticed •Furnace top cameras •Increase/change in return fines •Chemistry changes in hot metal or slag •Filling times •Moisture levels •isolate the bunker •Assess the impact on the furnace of the material already charged •Charge as a different specified material •Or Charge a much smaller quantity to empty the bunker •Or empty out Steps to Take
  • 31. Practical Examples Bin Contamination What are the potential consequences for the furnace? Bin Levels too low What are the potential consequences for furnace? How can the Control Room Operator find out of bins are contaminated? What are the steps to take when bins are known to be contaminated? Why? consequences for the furnace? How can the Control Room Operator find out if the bin levels are too low? What are the steps to take when bin levels are too low? Why?
  • 32. Coke break-up, nut coke covered with more fines As weak coke breaks up voids fill with smaller pieces and the gas flow and liquid metal and slag flow becomes more difficult.
  • 33. Fines Descending through Furnace Descend 1 2 Fines charged near wall Descend straight down, do not melt or reduce (impermeable to gases) Solids seen through peephole Blast pressure may increase, furnace can hang 2 3
  • 34. Blast Pressure & the Process Below the equipment-set The maximum blast pressure for the Above the Reducing the blast pressure before the When Top pressure is kept constant; equipment-set blast pressure limit, the blast pressure fluctuates up to a defined limit for the process. pressure for the process is the point at which the furnace can operate without the risk of hanging and slipping. Above the maximum blast pressure for the process the furnace may start to hang or slip. pressure before the maximum is reached can stabilise the process before hanging or slipping occurs.
  • 35. Required Properties of Material • Moisture content controlled – may be measured and corrected for by gauges • Strength at ambient temperature – to prevent breaking up before charging • Strength at high temperature – to prevent breaking up in the furnace • Chemistry – to make sure there is enough of what is required, and not too much of anything else much of anything else • Size distribution – limit the amount of fines • Average size – should be within required range
  • 36. Thermal Control • CO Utilisation • Heat Load to the Walls • Top Gas Temperature • Hot Metal Temperature and Silicon Content • Charging Rate-Racing furnace • Loss of Hot Blast Temperature • Loss of Stockline
  • 37. Racing furnace-example • Number of charges (0-2) - Average number of charges per hour over the last 2 hours • Number of charges(0-8) - Average number of charges per hour over the last 8 hours • If Number of charges/hour C(0-2) = Number of For example • If Number of charges/hour C(0-2) = Number of charges/hour(0-8) + 2 • We say furnace racing, making more melt, thermal sink • Consequences- reduce the blast volume by 1800 Nm3/hr For example
  • 38. Racing Furnace, Direct Reduction (DR) and Wu Racing Furnace, Direct Reduction (DR) and Wu FeO + CO = Fe + CO2 Fe₂O₃ + CO = 2FeO + CO₂ 110⁰C 1300⁰C 4/7/2021 38 FeO + CO = Fe + CO2 C + CO₂ = 2CO (>900oC: Solution loss) Why fce cool during racing condition? Racing furnace happens due to more DR which consumes heat and consumes Carbon which does not burn at the tuyeres So Furnace cools. Due to poor reduction. Wu is the residual heat in the lower zone = heat of combustion – heat of solution loss + heat of blast temp – heat to split steam and PCI 1500⁰C 2150⁰C DR
  • 39. Guidelines for operators-How to keep thermal stability in racing furnace • For racing furnace, consider the 4 hour charging rate, as well as the 8 hour, because there are times when this will give earlier warning, especially when the charging rate rapidly accelerates. • Racing furnace actions if the 4 hour charging rate is at least 9% above expected or the 8 hour is at least 5% above expected. • If the charging rate is increasing, (4 hour or 8 hour), or we are building up blast volume from a reduced blast period, do not set coal variation to negative. a reduced blast period, do not set coal variation to negative. • Be very wary of setting the coal variation below -5 for more than a few hours. Increase steam first. i.e. only if charging rate slow and furnace hot. • Do not go below -5 if charging rate slow but thermally OK. • Do not go below -5 if furnace hot but charging rate OK. • When the top gas analysis is under maintenance, Wu ends up well out of range and misleading. If Wu does not look right, cross check the top gas analysis with the power station on the expert system trend. • Note that the time for a PCI rate change to affect metal quality is 7 to 11 hours, whereas steam is 3 to 5 hours.
  • 40. Delays and effect times PCI: 3 kg/thm = 10 deg C = 0.07% Si. 7 to 11 hours Steam: -4g/Nm3 = 8 deg C. 3 to 5 hours PCI to Wu: 3 kg/thm = 50 MJ/thm. 4 to 6 hours. 0 2 4 6 8 10 12 0 1 2 3 4 5 6 7 8 9 10 11 12 Hours Effect time PCI change to hotmetal temp PCI change (kg/thm) Change in metal temp (deg C) 50 60 70 80 90 100 5 6 7 8 9 10 Change in Wu MJ/thm Change in PCI ratekg/thm Effect time PCI change to Wu PCI change (kg/thm) Change in Wu (MJ/thm) Wu to HMT: 50 MJ/thm = 10 deg C. 3 hours 0 10 20 30 40 0 1 2 3 4 0 1 2 3 4 5 6 7 8 9 10 11 12 Change in Wu MJ/thm Change in PCI ratekg/thm Hours -5 -3 -1 1 3 5 7 0 1 2 3 4 5 6 7 8 9 10 11 12 Hours Effect time steam change to hotmetal temp Steam change (kg/thm) Change in metal temp (deg C) Note that the furnace is not an incinerator. Increasing PCI rate does not immediately generate more heat as the furnace will just burn coal instead of coke. The furnace will eventually warm up because the burden in the stack will descend more slowly so will be exposed to more reducing gas. It will then be better reduced and need less direct reduction.
  • 41. What is oxy/thm factor? • Volume of oxygen assumed to make 1 thm • 6300 BV at 3% enrichment: oxygen in blast is 6300 * (21+3)/100 = 1512 Nm3/min • If oxy/thm is 245 Nm3/thm then furnace is assumed to produce 1512/245 = 6.17 thm/minute = 370 thm/hour 1512/245 = 6.17 thm/minute = 370 thm/hour • Aim PCI of 130 kg/thm. So coal flow setpoint calculated is 370 * 130 = 48140 kg/h • If the furnace is racing so that it is only using 235 Nm3/thm: • Actual production rate = 1512/235 * 60 = 386 thm/hour • Actual coal rate = 48140/386 = 125 kg/thm (5 kg/thm short) – Plus the effect of less coke to burn and higher direct reduction
  • 42. 8h expected and actual charging rate on RTR1 • 8 hourly charging rate is the actual measured charges per 8 hours • Expected charging rate is what the 8 hour charging rate would be if the furnace was charging as expected. The expected make is calculated from the average blast volume and oxygen enrichment over the past 8 hours and the oxy/thm factor. This is divided by the current fe yield per charge to calculate the expected charging rate. • Actual v expected is the percentage difference between the actual charging rate • Actual v expected is the percentage difference between the actual charging rate and what it should have been. • If the furnace is charging at least 5% faster than it should be, averaged over 8 hours, then this indicates a racing furnace. The colour of this row changes to red. • If the charging rate is more than 2% above where it should be then the colour changes to orange, as this is likely to lead to a cooling furnace if it persists. • Note that when burdening for a change in PCI rate the expected rate will be more accurate on the expert system as it allows for the change in coke volume in the stack which occurs before the change in PCI rate.