Advanced Supply Chain Planning
Lab: Expert Plan
by
GROUP N
Sayuri Mancilla - 833874
Rosario Meneses - 837412
Federico Edoardo Pantanella - 837908
Fabio Parisi - 838093
Danilo Torretta - 837978
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result
GOAL:
TOTAL COST MINIMIZATION
Production
costs
Penalty
costs
Plan
cost
Operative levers:
• Delay deliveries
• Produce in advance at most 3 orders
• Customer order ranking
• Standard time, overtime or extra shift
• Alternative routings (internal or external
suppliers)
General strategy In-depth analysis
Problem setting
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result

• The available levers can be divided in three operational areas: Heuristic, Demand ordering and Demand
anticipation.
• Even though these areas are mutually interrelated, we decided to follow a reference decisional
sequence.
1. Heuristic: deciding how many resources to activate,
which capacity level to deploy and the maximum
delivery delay.
2. Demand ordering: setting the right priorities to
efficiently allocate demand orders in the available
production capacity for each time bucket.
3. Demand anticipation: deciding 3 orders to produce
in advance in order to further improve the cost
performance.
General strategy
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result


Cost per hour
(€/h)
Laser Cutting Cutting Bending Assembly Final
Assembly
Preferred
Resource
50 – 60 - 70 50 – 60 – 70 50 – 60 – 70 50 – 60 – 70 50 – 60 – 120
Internal
Alternative
/ 50 – 60 – 70 50 – 60 – 70 50 – 60 – 70 60 – 75 – 120
Contractor
(open order)
/ / / 100 100
Contractor
(extra)
/ / / 300 300
While making decisions in terms of heuristic management (how many resources to activate
and which capacity level to deploy), we decided to focus on just two activities - assembly and
final assembly – as production costs for laser cutting, cutting and bending are not
not differential.
Heuristic: Production costs Table
Option 1: No extra suppliers
Delay cost = 200*7 = 1400 €
Cost of Bianchi’s capacity =
10*1*100 = 1000 €
Total cost = 2400 €
Option 2: Activating extra
suppliers
Cost of Verdi’s capacity = Total
cost = 10*1*300 = 3000 €
Heuristic: How many resources to activate
Lower
cost
We chose not to activate extra suppliers, as relying just on suppliers with long term contracts is always cheaper than
activating extra suppliers.
AN EXAMPLE
• Capacity Level = 2
• We have to perform final assembly (LT=1
hour) on a 10-unit order (the average
order size is 9.8), but Bianchi has reached
full capacity
• With no extra suppliers, the worst case
scenario is that we are forced to delay the
order and use Bianchi’s capacity (the most
expensive) in the following week; the cost
of delay is 200 € per day (max delay cost)
• If we activated extra suppliers, we would
use Verdi’s capacity
Even the worst case scenario with no extra suppliers is
cheaper than activating extra suppliers
Final Heuristic
63 days of
allowed delay
ensures that each
and every
demand order is
satisfied
Option 1: Level 2
Cost of Bianchi’s capacity = Total
cost = 10*1*100 = 1000 €
Option 2: Level 3
Cost of the internal alternative’s
capacity = Total cost =
2*1*75+8*1*120 = 1110 €
Heuristic: Which capacity level to deploy
Lower
cost
We chose not to activate Level 3, considering that most of scenarios where Saturday overtime is deployed (Level 3)
are actually more expensive than scenarios where production takes place 5 days a week, 10 hours a day (Level 2).
AN EXAMPLE
• We activated only suppliers with long term
contracts
• We have to perform final assembly (LT=1 hour) on a
10-unit order
• With no Saturday overtime, Bianchi is the only
resource with enough available capacity
• By activating Level 3, we have available capacity on
the internal alternative: we can produce 2 units in
the last two hours on Friday and the remaining 8 on
Saturday
Activating Level 3 may be convenient when Saturday overtime is used instead of delaying orders,
but this specific situation did not occur frequently in the simulations we ran;
therefore, not activating Level 3 leads to a general cost reduction
Capacity Level
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result



Penalty
cost
A-Z
from lowest to
highest delay cost
per day
Z-A
from highest to
lowest delay cost
per day
Delivery
date
A-Z
from nearest to
farthest delivery
date
Z-A
from farthest to
nearest delivery
date
Order
quantity
A-Z
from smallest to
biggest order size
Z-A
from biggest to
smallest order size
Our ranking
Penalty Z-A
Date A-Z
Quantity A-Z
1
3
2
Demand ordering: Available criteria and ranking
Delay
Penalty
(€/Day)
No. of
orders
No. of
delayed
orders
200 12 0
150 4 0
140 1 0
130 3 0
120 4 0
100 302 23
80 11 2
50 1 1
40 1 0
20 1 1
We selected delay penalty cost as the first criterion in our customer order
ranking. In this way, we were able to reduce the probability that an order
with a high penalty cost were delivered in delay.
The table aside shows the number
of orders for each “delay penalty”
category.
As the last column underlines, in
our solution only low-penalty cost
orders have been delivered in
delay (those with a penalty of
100€/day or below).
Demand ordering: Penalty cost
In choosing between Date A-Z and Date Z-A, we tried to figure out how this decision affected delay costs.
Therefore, we analysed how orders are differently allocated according to these two criteria.
Demand ordering: Delivery date (1/3)
By allocating orders with nearest delivery date first (Date A-
Z), we had several delayed orders with a reduction in the
average number of delay weeks per order. On the contrary,
by allocating orders with farthest delivery date first (Date Z-
A), we had fewer delayed orders but an increase in the
average number of delay weeks. In the two scenarios, these
effects tend to neutralize each other, causing nearly the
same delay costs.
After running a few simulations, we saw that, by choosing
Date A-Z, we could achieve a slight decrease of delay costs.
In an “infinite capacity” simulation, 2 orders are in overflow on TB 2. Hence, these orders
exceeding capacity have to be relocated on the following time buckets, causing a delay.
AN EXAMPLE
• Only 1 resource
• Capacity = 30 units in every time
bucket
• Orders to be processed have the
same quantity (10 units)
• Delivery dates
• 1 order on Time Bucket (TB) 1
• 5 orders on TB 2
• 3 orders on TB 3
• 2 orders on TB 4
• 1 order on TB 5
Demand ordering: Delivery date (2/3)
Date Z-A Date A-Z
Number of delayed orders = 2
Average delay weeks per order = 2.5
Number of delayed orders = 5
Average delay weeks per order = 1
Demand ordering: Delivery date (3/3)
At this stage of allocating demand orders, weekly delay cost and delivery date are the same for each
order we consider, as these two criteria come first in our customer order ranking.
Demand ordering: Order quantity (1/2)
Therefore, in choosing between Quantity A-Z and Quantity
Z-A, we tried to minimize the number of delayed orders as
we knew that it would lead for sure to a decrease in delay
costs (as said, at this stage weekly delay cost is a fixed
parameter).
We decided to allocate orders with fewest quantity first
(Quantity A-Z), as this option allows a smarter distribution
over the time buckets, characterized by a lower number of
delayed orders.
AN EXAMPLE
• Only 1 resource
• Capacity = 50 units in
every time bucket
• Orders to be processed
• 1 order : 20 units
• 4 orders: 10 units
• 2 orders: 5 units
• Delay cost = 700 €/week
for every order
• Delivery date on Time
bucket 1
Number of delayed orders = 1
Total delay cost = 700 €
Number of delayed orders = 3
Total delay cost = 2100 €
Quantity A-Z Quantity Z-A
Demand ordering: Order quantity (2/2)
Demand Sequence
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result




Plan cost
minimization
Production
costs
Moving orders from
expensive resources (e.g.
external contractors) to
more efficient ones (e.g.
preferred resource)
Delay costs
Producing on time (or
reducing delay time) orders
in delay
Demand anticipation: Strategy
Low
potential
gains
Better
option
How to reduce
delay costs?
1. Anticipate orders with the highest total delay cost (= daily penalty * days of delay)
2. Anticipate orders to release production capacity and deliver other critical orders on
time or at least with reduced delay
3. A mix of the two! Our strategy!
Demand anticipation: In detail
• First we analysed the “infinite capacity” scenario, which showed that the most critical time bucket is
week 25 (20/06): 290 items to deliver.
In our “finite capacity” solution, this situation resulted in a huge number of delayed orders from week
26 to week 30.
• Second, we isolated the orders with the highest total delay cost: order 204 (delay cost = 1750€) was
produced in week 30 (5 weeks in delay), whereas orders 210, 217 and 219 (delay cost = 1400€ each) in
week 27.
Order Delivery
Date
Planned
Date
Delay
(days)
Delay
Penalty
(€/day)
Total Delay
Cost (€)
OV20160204 20/06/2016 25/07/2016 35 50 1750
OV20160210 20/06/2016 04/07/2016 14 100 1400
0V20160217 20/06/2016 04/07/2016 14 100 1400
0V20160219 20/06/2016 04/07/2016 14 100 1400
Demand anticipation: Final decision
• If we had anticipated order 204, we would have set some production capacity free in week 30, but,
evidently, this capacity could not have been used to produce any other order on time, since no delayed
orders were scheduled in week 31, 32 and 33.
• After running some simulations, we verified that, even though order 204 had the highest total delay
cost, by anticipating orders 210, 217 and 219 we could release capacity in week 27 and produce on time
(or with lower delay) some delayed orders that were previously allocated in week 28, 29 and 30.
Orders we decided
to anticipate
OV20160210
OV20160217
0V20160219
BEFORE . . .
Thanks to the anticipation, the number of delayed orders decreased by
13. This is attributable to two reasons:
• the 3 orders we anticipated are no longer in delay;
• other 10 delayed orders have been delivered on time thanks to the
released capacity that was previously used to produce the 3 orders
anticipated.
Accordingly, delay penalty
cost decreased by 35%.
Since load cost remained
approximately steady, the
plan cost is lower.
. . . AFTER
Demand anticipation: Result
Executive summary
Problem setting
General strategy
Heuristic
Demand ordering
Demand anticipation
Final result





Plan cost =
363.556,67 €
Final result
GROUP N
Sayuri Mancilla - 833874
Rosario Meneses - 837412
Federico Edoardo Pantanella - 837908
Fabio Parisi - 838093
Danilo Torretta - 837978
THANK YOU
FOR YOUR
ATTENTION

More Related Content

What's hot

EOQ Ken Homa
EOQ   Ken HomaEOQ   Ken Homa
EOQ Ken Homa
Nilam Kabra
 
Inventory management1
Inventory management1Inventory management1
Inventory management1
Raja Mohan Murugiah
 
Eoq(p) model
Eoq(p) modelEoq(p) model
Eoq(p) model
Saurav Srivastava
 
Ch14. inventory management
Ch14. inventory managementCh14. inventory management
Ch14. inventory management
Raja Mohan Murugiah
 
Material ledger by guntupalli hari krishna
Material ledger by guntupalli hari krishnaMaterial ledger by guntupalli hari krishna
Material ledger by guntupalli hari krishna
Hari Krishna
 
Basic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot SizeBasic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot Size
Phillip Leonard Petate
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory management
hakimizaki
 
The eoq model
The eoq modelThe eoq model
The eoq model
Hasnain Baber
 
3...economic order quantity
3...economic order quantity3...economic order quantity
3...economic order quantity
DEVIKA ANTHARJANAM
 
Multi item inventory - joint ordering
Multi item inventory - joint orderingMulti item inventory - joint ordering
Multi item inventory - joint ordering
Anand Ellur
 
Single period inventory ordering
Single period inventory orderingSingle period inventory ordering
Single period inventory ordering
Fatih Mutlu
 
Inventory management
Inventory managementInventory management
Inventory management
AngelaMaurya
 
Economic order quantity (eoq) model
Economic order quantity (eoq) modelEconomic order quantity (eoq) model
Economic order quantity (eoq) model
leizel altamia
 
AGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINANAGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINAN
John Quillinan
 
Model eoq
Model eoqModel eoq
Model eoq
Rutuja Chudnaik
 
ITFT-- EOQ
ITFT-- EOQITFT-- EOQ
ITFT-- EOQ
Ravi Kaushal
 
Economic Order Quality Eoq
Economic Order Quality  EoqEconomic Order Quality  Eoq
Economic Order Quality Eoq
sikander kushwaha
 
Ckm3 material price analysis
Ckm3 material price analysisCkm3 material price analysis
Ckm3 material price analysis
Libelula5002
 
Product costing
Product costingProduct costing
Product costing
Khalid Aziz
 
Case study material ledger implementation lessons learned
Case study  material ledger implementation lessons learnedCase study  material ledger implementation lessons learned
Case study material ledger implementation lessons learned
Johannes Le Roux
 

What's hot (20)

EOQ Ken Homa
EOQ   Ken HomaEOQ   Ken Homa
EOQ Ken Homa
 
Inventory management1
Inventory management1Inventory management1
Inventory management1
 
Eoq(p) model
Eoq(p) modelEoq(p) model
Eoq(p) model
 
Ch14. inventory management
Ch14. inventory managementCh14. inventory management
Ch14. inventory management
 
Material ledger by guntupalli hari krishna
Material ledger by guntupalli hari krishnaMaterial ledger by guntupalli hari krishna
Material ledger by guntupalli hari krishna
 
Basic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot SizeBasic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot Size
 
C9 inventory management
C9 inventory managementC9 inventory management
C9 inventory management
 
The eoq model
The eoq modelThe eoq model
The eoq model
 
3...economic order quantity
3...economic order quantity3...economic order quantity
3...economic order quantity
 
Multi item inventory - joint ordering
Multi item inventory - joint orderingMulti item inventory - joint ordering
Multi item inventory - joint ordering
 
Single period inventory ordering
Single period inventory orderingSingle period inventory ordering
Single period inventory ordering
 
Inventory management
Inventory managementInventory management
Inventory management
 
Economic order quantity (eoq) model
Economic order quantity (eoq) modelEconomic order quantity (eoq) model
Economic order quantity (eoq) model
 
AGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINANAGIFORS1995-EPIM-QUILLINAN
AGIFORS1995-EPIM-QUILLINAN
 
Model eoq
Model eoqModel eoq
Model eoq
 
ITFT-- EOQ
ITFT-- EOQITFT-- EOQ
ITFT-- EOQ
 
Economic Order Quality Eoq
Economic Order Quality  EoqEconomic Order Quality  Eoq
Economic Order Quality Eoq
 
Ckm3 material price analysis
Ckm3 material price analysisCkm3 material price analysis
Ckm3 material price analysis
 
Product costing
Product costingProduct costing
Product costing
 
Case study material ledger implementation lessons learned
Case study  material ledger implementation lessons learnedCase study  material ledger implementation lessons learned
Case study material ledger implementation lessons learned
 

Viewers also liked

Order Fulfillment Process: How to Improve It
Order Fulfillment Process: How to Improve ItOrder Fulfillment Process: How to Improve It
Order Fulfillment Process: How to Improve It
Handshake
 
Final report of organisation study 222 (1)
Final report of organisation study 222 (1)Final report of organisation study 222 (1)
Final report of organisation study 222 (1)
KomalJhingade
 
Order processing
Order processingOrder processing
Order processing
Navin Raj Saroj
 
Organizational study report (MBA)
Organizational study report (MBA)Organizational study report (MBA)
Organizational study report (MBA)
Cochin University
 
Ch 9 organizational structure and design
Ch 9 organizational structure and designCh 9 organizational structure and design
Ch 9 organizational structure and design
Nardin A
 
organization structure
organization structureorganization structure
organization structure
Mukesh Gupta
 
Organizational structure ppt
Organizational structure pptOrganizational structure ppt
Organizational structure ppt
vibhugorintla
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational Structure
ahmad bassiouny
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational Structure
Mary Ann Adiong
 

Viewers also liked (9)

Order Fulfillment Process: How to Improve It
Order Fulfillment Process: How to Improve ItOrder Fulfillment Process: How to Improve It
Order Fulfillment Process: How to Improve It
 
Final report of organisation study 222 (1)
Final report of organisation study 222 (1)Final report of organisation study 222 (1)
Final report of organisation study 222 (1)
 
Order processing
Order processingOrder processing
Order processing
 
Organizational study report (MBA)
Organizational study report (MBA)Organizational study report (MBA)
Organizational study report (MBA)
 
Ch 9 organizational structure and design
Ch 9 organizational structure and designCh 9 organizational structure and design
Ch 9 organizational structure and design
 
organization structure
organization structureorganization structure
organization structure
 
Organizational structure ppt
Organizational structure pptOrganizational structure ppt
Organizational structure ppt
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational Structure
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational Structure
 

Similar to Advanced Supply Chain Planning Lab: Expert Plan by Quin

Unit 3-inventory control
Unit 3-inventory controlUnit 3-inventory control
Unit 3-inventory control
CHAKRADHAR BANDAPALLI
 
Presentaci ã³n 1 eoq
Presentaci ã³n 1 eoqPresentaci ã³n 1 eoq
Presentaci ã³n 1 eoq
Javi Dela
 
Kanban pull.pptx
Kanban pull.pptxKanban pull.pptx
Kanban pull.pptx
Rodrigo Costa, MSc, HCMP
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
Kinshook Chaturvedi
 
inventory-management
inventory-managementinventory-management
inventory-management
rajesh.pal45
 
Ch14 Inventory Management
Ch14  Inventory ManagementCh14  Inventory Management
Ch14 Inventory Management
ajithsrc
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentation
Sanaullah Shimul
 
W3D1-Accounting-for-Materials-pt2 (1).pdf
W3D1-Accounting-for-Materials-pt2 (1).pdfW3D1-Accounting-for-Materials-pt2 (1).pdf
W3D1-Accounting-for-Materials-pt2 (1).pdf
Aral20101
 
W3D1-Accounting-for-Materials-pt2 (1).pptx
W3D1-Accounting-for-Materials-pt2 (1).pptxW3D1-Accounting-for-Materials-pt2 (1).pptx
W3D1-Accounting-for-Materials-pt2 (1).pptx
Aral20101
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory management
sakshi0503sakshi
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-ppt
shahidch44
 
Inventory
InventoryInventory
Inventory
knksmart
 
INVENTORY MODELS
INVENTORY MODELSINVENTORY MODELS
INVENTORY MODELS
Navya Jayakumar
 
Ops5
Ops5Ops5
Ops5
Geethaka
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layouts
Akash Bakshi
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
Vishal Joshi
 
Cycle inventory
Cycle inventoryCycle inventory
Cycle inventory
Shagun Agarwal
 
sunil chopra 1
sunil chopra 1sunil chopra 1
sunil chopra 1
NurulIslamRupok
 
Inventory management
Inventory managementInventory management
Inventory management
Jubayer Alam Shoikat
 
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptxCE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
ID Bilişim ve Ticaret Ltd. Şti.
 

Similar to Advanced Supply Chain Planning Lab: Expert Plan by Quin (20)

Unit 3-inventory control
Unit 3-inventory controlUnit 3-inventory control
Unit 3-inventory control
 
Presentaci ã³n 1 eoq
Presentaci ã³n 1 eoqPresentaci ã³n 1 eoq
Presentaci ã³n 1 eoq
 
Kanban pull.pptx
Kanban pull.pptxKanban pull.pptx
Kanban pull.pptx
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
 
inventory-management
inventory-managementinventory-management
inventory-management
 
Ch14 Inventory Management
Ch14  Inventory ManagementCh14  Inventory Management
Ch14 Inventory Management
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentation
 
W3D1-Accounting-for-Materials-pt2 (1).pdf
W3D1-Accounting-for-Materials-pt2 (1).pdfW3D1-Accounting-for-Materials-pt2 (1).pdf
W3D1-Accounting-for-Materials-pt2 (1).pdf
 
W3D1-Accounting-for-Materials-pt2 (1).pptx
W3D1-Accounting-for-Materials-pt2 (1).pptxW3D1-Accounting-for-Materials-pt2 (1).pptx
W3D1-Accounting-for-Materials-pt2 (1).pptx
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory management
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-ppt
 
Inventory
InventoryInventory
Inventory
 
INVENTORY MODELS
INVENTORY MODELSINVENTORY MODELS
INVENTORY MODELS
 
Ops5
Ops5Ops5
Ops5
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layouts
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
 
Cycle inventory
Cycle inventoryCycle inventory
Cycle inventory
 
sunil chopra 1
sunil chopra 1sunil chopra 1
sunil chopra 1
 
Inventory management
Inventory managementInventory management
Inventory management
 
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptxCE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
 

Recently uploaded

Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 

Recently uploaded (20)

Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 

Advanced Supply Chain Planning Lab: Expert Plan by Quin

  • 1. Advanced Supply Chain Planning Lab: Expert Plan by GROUP N Sayuri Mancilla - 833874 Rosario Meneses - 837412 Federico Edoardo Pantanella - 837908 Fabio Parisi - 838093 Danilo Torretta - 837978
  • 2. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result
  • 3. GOAL: TOTAL COST MINIMIZATION Production costs Penalty costs Plan cost Operative levers: • Delay deliveries • Produce in advance at most 3 orders • Customer order ranking • Standard time, overtime or extra shift • Alternative routings (internal or external suppliers) General strategy In-depth analysis Problem setting
  • 4. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result 
  • 5. • The available levers can be divided in three operational areas: Heuristic, Demand ordering and Demand anticipation. • Even though these areas are mutually interrelated, we decided to follow a reference decisional sequence. 1. Heuristic: deciding how many resources to activate, which capacity level to deploy and the maximum delivery delay. 2. Demand ordering: setting the right priorities to efficiently allocate demand orders in the available production capacity for each time bucket. 3. Demand anticipation: deciding 3 orders to produce in advance in order to further improve the cost performance. General strategy
  • 6. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result  
  • 7. Cost per hour (€/h) Laser Cutting Cutting Bending Assembly Final Assembly Preferred Resource 50 – 60 - 70 50 – 60 – 70 50 – 60 – 70 50 – 60 – 70 50 – 60 – 120 Internal Alternative / 50 – 60 – 70 50 – 60 – 70 50 – 60 – 70 60 – 75 – 120 Contractor (open order) / / / 100 100 Contractor (extra) / / / 300 300 While making decisions in terms of heuristic management (how many resources to activate and which capacity level to deploy), we decided to focus on just two activities - assembly and final assembly – as production costs for laser cutting, cutting and bending are not not differential. Heuristic: Production costs Table
  • 8. Option 1: No extra suppliers Delay cost = 200*7 = 1400 € Cost of Bianchi’s capacity = 10*1*100 = 1000 € Total cost = 2400 € Option 2: Activating extra suppliers Cost of Verdi’s capacity = Total cost = 10*1*300 = 3000 € Heuristic: How many resources to activate Lower cost We chose not to activate extra suppliers, as relying just on suppliers with long term contracts is always cheaper than activating extra suppliers. AN EXAMPLE • Capacity Level = 2 • We have to perform final assembly (LT=1 hour) on a 10-unit order (the average order size is 9.8), but Bianchi has reached full capacity • With no extra suppliers, the worst case scenario is that we are forced to delay the order and use Bianchi’s capacity (the most expensive) in the following week; the cost of delay is 200 € per day (max delay cost) • If we activated extra suppliers, we would use Verdi’s capacity Even the worst case scenario with no extra suppliers is cheaper than activating extra suppliers
  • 10. 63 days of allowed delay ensures that each and every demand order is satisfied
  • 11.
  • 12.
  • 13. Option 1: Level 2 Cost of Bianchi’s capacity = Total cost = 10*1*100 = 1000 € Option 2: Level 3 Cost of the internal alternative’s capacity = Total cost = 2*1*75+8*1*120 = 1110 € Heuristic: Which capacity level to deploy Lower cost We chose not to activate Level 3, considering that most of scenarios where Saturday overtime is deployed (Level 3) are actually more expensive than scenarios where production takes place 5 days a week, 10 hours a day (Level 2). AN EXAMPLE • We activated only suppliers with long term contracts • We have to perform final assembly (LT=1 hour) on a 10-unit order • With no Saturday overtime, Bianchi is the only resource with enough available capacity • By activating Level 3, we have available capacity on the internal alternative: we can produce 2 units in the last two hours on Friday and the remaining 8 on Saturday Activating Level 3 may be convenient when Saturday overtime is used instead of delaying orders, but this specific situation did not occur frequently in the simulations we ran; therefore, not activating Level 3 leads to a general cost reduction
  • 15. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result   
  • 16. Penalty cost A-Z from lowest to highest delay cost per day Z-A from highest to lowest delay cost per day Delivery date A-Z from nearest to farthest delivery date Z-A from farthest to nearest delivery date Order quantity A-Z from smallest to biggest order size Z-A from biggest to smallest order size Our ranking Penalty Z-A Date A-Z Quantity A-Z 1 3 2 Demand ordering: Available criteria and ranking
  • 17. Delay Penalty (€/Day) No. of orders No. of delayed orders 200 12 0 150 4 0 140 1 0 130 3 0 120 4 0 100 302 23 80 11 2 50 1 1 40 1 0 20 1 1 We selected delay penalty cost as the first criterion in our customer order ranking. In this way, we were able to reduce the probability that an order with a high penalty cost were delivered in delay. The table aside shows the number of orders for each “delay penalty” category. As the last column underlines, in our solution only low-penalty cost orders have been delivered in delay (those with a penalty of 100€/day or below). Demand ordering: Penalty cost
  • 18. In choosing between Date A-Z and Date Z-A, we tried to figure out how this decision affected delay costs. Therefore, we analysed how orders are differently allocated according to these two criteria. Demand ordering: Delivery date (1/3) By allocating orders with nearest delivery date first (Date A- Z), we had several delayed orders with a reduction in the average number of delay weeks per order. On the contrary, by allocating orders with farthest delivery date first (Date Z- A), we had fewer delayed orders but an increase in the average number of delay weeks. In the two scenarios, these effects tend to neutralize each other, causing nearly the same delay costs. After running a few simulations, we saw that, by choosing Date A-Z, we could achieve a slight decrease of delay costs.
  • 19. In an “infinite capacity” simulation, 2 orders are in overflow on TB 2. Hence, these orders exceeding capacity have to be relocated on the following time buckets, causing a delay. AN EXAMPLE • Only 1 resource • Capacity = 30 units in every time bucket • Orders to be processed have the same quantity (10 units) • Delivery dates • 1 order on Time Bucket (TB) 1 • 5 orders on TB 2 • 3 orders on TB 3 • 2 orders on TB 4 • 1 order on TB 5 Demand ordering: Delivery date (2/3)
  • 20. Date Z-A Date A-Z Number of delayed orders = 2 Average delay weeks per order = 2.5 Number of delayed orders = 5 Average delay weeks per order = 1 Demand ordering: Delivery date (3/3)
  • 21. At this stage of allocating demand orders, weekly delay cost and delivery date are the same for each order we consider, as these two criteria come first in our customer order ranking. Demand ordering: Order quantity (1/2) Therefore, in choosing between Quantity A-Z and Quantity Z-A, we tried to minimize the number of delayed orders as we knew that it would lead for sure to a decrease in delay costs (as said, at this stage weekly delay cost is a fixed parameter). We decided to allocate orders with fewest quantity first (Quantity A-Z), as this option allows a smarter distribution over the time buckets, characterized by a lower number of delayed orders.
  • 22. AN EXAMPLE • Only 1 resource • Capacity = 50 units in every time bucket • Orders to be processed • 1 order : 20 units • 4 orders: 10 units • 2 orders: 5 units • Delay cost = 700 €/week for every order • Delivery date on Time bucket 1 Number of delayed orders = 1 Total delay cost = 700 € Number of delayed orders = 3 Total delay cost = 2100 € Quantity A-Z Quantity Z-A Demand ordering: Order quantity (2/2)
  • 24.
  • 25. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result    
  • 26. Plan cost minimization Production costs Moving orders from expensive resources (e.g. external contractors) to more efficient ones (e.g. preferred resource) Delay costs Producing on time (or reducing delay time) orders in delay Demand anticipation: Strategy Low potential gains Better option How to reduce delay costs? 1. Anticipate orders with the highest total delay cost (= daily penalty * days of delay) 2. Anticipate orders to release production capacity and deliver other critical orders on time or at least with reduced delay 3. A mix of the two! Our strategy!
  • 27. Demand anticipation: In detail • First we analysed the “infinite capacity” scenario, which showed that the most critical time bucket is week 25 (20/06): 290 items to deliver. In our “finite capacity” solution, this situation resulted in a huge number of delayed orders from week 26 to week 30. • Second, we isolated the orders with the highest total delay cost: order 204 (delay cost = 1750€) was produced in week 30 (5 weeks in delay), whereas orders 210, 217 and 219 (delay cost = 1400€ each) in week 27. Order Delivery Date Planned Date Delay (days) Delay Penalty (€/day) Total Delay Cost (€) OV20160204 20/06/2016 25/07/2016 35 50 1750 OV20160210 20/06/2016 04/07/2016 14 100 1400 0V20160217 20/06/2016 04/07/2016 14 100 1400 0V20160219 20/06/2016 04/07/2016 14 100 1400
  • 28. Demand anticipation: Final decision • If we had anticipated order 204, we would have set some production capacity free in week 30, but, evidently, this capacity could not have been used to produce any other order on time, since no delayed orders were scheduled in week 31, 32 and 33. • After running some simulations, we verified that, even though order 204 had the highest total delay cost, by anticipating orders 210, 217 and 219 we could release capacity in week 27 and produce on time (or with lower delay) some delayed orders that were previously allocated in week 28, 29 and 30. Orders we decided to anticipate OV20160210 OV20160217 0V20160219
  • 29. BEFORE . . . Thanks to the anticipation, the number of delayed orders decreased by 13. This is attributable to two reasons: • the 3 orders we anticipated are no longer in delay; • other 10 delayed orders have been delivered on time thanks to the released capacity that was previously used to produce the 3 orders anticipated. Accordingly, delay penalty cost decreased by 35%. Since load cost remained approximately steady, the plan cost is lower. . . . AFTER Demand anticipation: Result
  • 30.
  • 31.
  • 32.
  • 33. Executive summary Problem setting General strategy Heuristic Demand ordering Demand anticipation Final result     
  • 34. Plan cost = 363.556,67 € Final result
  • 35. GROUP N Sayuri Mancilla - 833874 Rosario Meneses - 837412 Federico Edoardo Pantanella - 837908 Fabio Parisi - 838093 Danilo Torretta - 837978 THANK YOU FOR YOUR ATTENTION