EOQ – P MODEL
Submitted by
Saurav Kumar
• The economic order-quantity model considers the
tradeoff between ordering cost and storage cost in
choosing the quantity to use in replenishing item
inventories.

Economic Order Quantity
Model
• In p model, inventory situations(records)is reviewed at fixed intervals
of time when the required replenishment orders are placed.
• We have a predetermined time (P) between orders (sales rep comes
by every 10 days) or the average time between orders from EOQ =
Q/r year
• Used for bulk materials and services like refineries, petrol pumps
,etc.

• Also called as fixed time Model because the review of purchase is
done after some fixed time say 5 or 10 days

P model
• Stocks at petrol pump is say 120 kl and consumption per
week is 100 kl, thus safety stock is 20kl
• Demand is always variable and in 95% cases it may not
exceed 120 kl, thus it is called 95% service level stocks

Cntd…
• There is some lead time (L) to get the supply and thus the
variation in demand during lead time is “σL”
• Due to this variation, the stocks level will also vary and
the stock level variation is denoted by “z”
Therefore:
Safety Stocks = z x σL

Symbols and
explanations
•

Cntd…
Daily demand at a petrol pump os 10 KL and variation in
daily demand is 3 KL. Review period is 30 days and lead
time is 14 days. Opening Inventory is 150 KL and variation
in stock level is 0.21 . Find q?

Example 1
• In a chemical company , average demand for product is
10 KL per day and standard variation is 2 Kl per day. The
inventory levels was 20 kl. The review time is 60 days
and lead time is 15 days. Find q so as to maintain 95%
service level stock ( z at 95% is 1.645)

Example-2
Given data :
T=60,L=15,
σT+L= 2
d=10 and I = 20
we have
q= (r x (T+L)) + (z x σT+L) – I
q= 10x(60+15)+(1.645x2)-20 = 733 KL

Solution
• Consider an item for which
Annual demand= 1000 units
Standard deviation of demand per week = 10 units
Cost per unit = Rs 5
Ordering cost per order = Rs 150
Inventory carrying cost= 30 percent
Average lead time = 4 weeks
Maximum delay in lead time = 3 weeks
Probability of delay = 0.30
Service level= 95%

Example 3
solution
• Hema garment Manufacturing Company uses basic cloth,
„two by two‟ , in most of its products. It buys its annual
requirement of 16000 metres of cloth in economic lots of
4000 metres each. The lead time for procurement is
generally taken as 6 weeks . Hema maintains a safety
sticks of 1000 metres. If Hema were to change over to a
fixed order cycle system, maintaining the safety stocks

Example 4
solution

Eoq(p) model

  • 1.
    EOQ – PMODEL Submitted by Saurav Kumar
  • 2.
    • The economicorder-quantity model considers the tradeoff between ordering cost and storage cost in choosing the quantity to use in replenishing item inventories. Economic Order Quantity Model
  • 3.
    • In pmodel, inventory situations(records)is reviewed at fixed intervals of time when the required replenishment orders are placed. • We have a predetermined time (P) between orders (sales rep comes by every 10 days) or the average time between orders from EOQ = Q/r year • Used for bulk materials and services like refineries, petrol pumps ,etc. • Also called as fixed time Model because the review of purchase is done after some fixed time say 5 or 10 days P model
  • 4.
    • Stocks atpetrol pump is say 120 kl and consumption per week is 100 kl, thus safety stock is 20kl • Demand is always variable and in 95% cases it may not exceed 120 kl, thus it is called 95% service level stocks Cntd…
  • 5.
    • There issome lead time (L) to get the supply and thus the variation in demand during lead time is “σL” • Due to this variation, the stocks level will also vary and the stock level variation is denoted by “z” Therefore: Safety Stocks = z x σL Symbols and explanations
  • 6.
  • 7.
    Daily demand ata petrol pump os 10 KL and variation in daily demand is 3 KL. Review period is 30 days and lead time is 14 days. Opening Inventory is 150 KL and variation in stock level is 0.21 . Find q? Example 1
  • 9.
    • In achemical company , average demand for product is 10 KL per day and standard variation is 2 Kl per day. The inventory levels was 20 kl. The review time is 60 days and lead time is 15 days. Find q so as to maintain 95% service level stock ( z at 95% is 1.645) Example-2
  • 10.
    Given data : T=60,L=15, σT+L=2 d=10 and I = 20 we have q= (r x (T+L)) + (z x σT+L) – I q= 10x(60+15)+(1.645x2)-20 = 733 KL Solution
  • 11.
    • Consider anitem for which Annual demand= 1000 units Standard deviation of demand per week = 10 units Cost per unit = Rs 5 Ordering cost per order = Rs 150 Inventory carrying cost= 30 percent Average lead time = 4 weeks Maximum delay in lead time = 3 weeks Probability of delay = 0.30 Service level= 95% Example 3
  • 12.
  • 13.
    • Hema garmentManufacturing Company uses basic cloth, „two by two‟ , in most of its products. It buys its annual requirement of 16000 metres of cloth in economic lots of 4000 metres each. The lead time for procurement is generally taken as 6 weeks . Hema maintains a safety sticks of 1000 metres. If Hema were to change over to a fixed order cycle system, maintaining the safety stocks Example 4
  • 14.