SlideShare a Scribd company logo
EOQ – P MODEL
Submitted by
Saurav Kumar
• The economic order-quantity model considers the
tradeoff between ordering cost and storage cost in
choosing the quantity to use in replenishing item
inventories.

Economic Order Quantity
Model
• In p model, inventory situations(records)is reviewed at fixed intervals
of time when the required replenishment orders are placed.
• We have a predetermined time (P) between orders (sales rep comes
by every 10 days) or the average time between orders from EOQ =
Q/r year
• Used for bulk materials and services like refineries, petrol pumps
,etc.

• Also called as fixed time Model because the review of purchase is
done after some fixed time say 5 or 10 days

P model
• Stocks at petrol pump is say 120 kl and consumption per
week is 100 kl, thus safety stock is 20kl
• Demand is always variable and in 95% cases it may not
exceed 120 kl, thus it is called 95% service level stocks

Cntd…
• There is some lead time (L) to get the supply and thus the
variation in demand during lead time is “σL”
• Due to this variation, the stocks level will also vary and
the stock level variation is denoted by “z”
Therefore:
Safety Stocks = z x σL

Symbols and
explanations
•

Cntd…
Daily demand at a petrol pump os 10 KL and variation in
daily demand is 3 KL. Review period is 30 days and lead
time is 14 days. Opening Inventory is 150 KL and variation
in stock level is 0.21 . Find q?

Example 1
• In a chemical company , average demand for product is
10 KL per day and standard variation is 2 Kl per day. The
inventory levels was 20 kl. The review time is 60 days
and lead time is 15 days. Find q so as to maintain 95%
service level stock ( z at 95% is 1.645)

Example-2
Given data :
T=60,L=15,
σT+L= 2
d=10 and I = 20
we have
q= (r x (T+L)) + (z x σT+L) – I
q= 10x(60+15)+(1.645x2)-20 = 733 KL

Solution
• Consider an item for which
Annual demand= 1000 units
Standard deviation of demand per week = 10 units
Cost per unit = Rs 5
Ordering cost per order = Rs 150
Inventory carrying cost= 30 percent
Average lead time = 4 weeks
Maximum delay in lead time = 3 weeks
Probability of delay = 0.30
Service level= 95%

Example 3
solution
• Hema garment Manufacturing Company uses basic cloth,
„two by two‟ , in most of its products. It buys its annual
requirement of 16000 metres of cloth in economic lots of
4000 metres each. The lead time for procurement is
generally taken as 6 weeks . Hema maintains a safety
sticks of 1000 metres. If Hema were to change over to a
fixed order cycle system, maintaining the safety stocks

Example 4
solution

More Related Content

What's hot

Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentationDelwin Arikatt
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planningRajeev Sharan
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
Sugandha Vidge
 
Supply chain managements
Supply chain managementsSupply chain managements
Supply chain managementsSarwat Shabbir
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
Rajendran Ananda Krishnan
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
Suryakumar Thangarasu
 
Inventory models
Inventory modelsInventory models
Inventory models
MOHD BILAL NAIM SHAIKH
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
Aqib ali
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
Biswajit Ghosh
 
Master scheduling
Master schedulingMaster scheduling
Master schedulingmehrdad66
 
Quality Function Deployment
Quality Function DeploymentQuality Function Deployment
Quality Function Deployment
mmarleanne
 
Quality Function Deployment PPT Slide Template
Quality Function Deployment PPT Slide TemplateQuality Function Deployment PPT Slide Template
Quality Function Deployment PPT Slide Template
PresentationLoad
 
Mass production
Mass productionMass production
Mass production
Pathmanathan Pathmaraj
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
MRPeasy
 
House of quality matrix
House of quality matrixHouse of quality matrix
House of quality matrix
Rohit K.
 
Aggregate Planning Report
Aggregate Planning ReportAggregate Planning Report
Aggregate Planning Report
Dianne Rivera
 
Jit & Lean Operations
Jit & Lean OperationsJit & Lean Operations
Jit & Lean Operations
kahogan62
 
Competitive supply chain strategies lsm
Competitive supply chain strategies  lsmCompetitive supply chain strategies  lsm
Competitive supply chain strategies lsm
Madhuri Muniyal
 
Quality Control
Quality ControlQuality Control
Quality Control
vishakeb
 

What's hot (20)

Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
 
Supply chain managements
Supply chain managementsSupply chain managements
Supply chain managements
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
 
Inventory models
Inventory modelsInventory models
Inventory models
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 
Master scheduling
Master schedulingMaster scheduling
Master scheduling
 
Quality Function Deployment
Quality Function DeploymentQuality Function Deployment
Quality Function Deployment
 
Quality Function Deployment PPT Slide Template
Quality Function Deployment PPT Slide TemplateQuality Function Deployment PPT Slide Template
Quality Function Deployment PPT Slide Template
 
Mass production
Mass productionMass production
Mass production
 
Supply chain management ppt
Supply chain management pptSupply chain management ppt
Supply chain management ppt
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
House of quality matrix
House of quality matrixHouse of quality matrix
House of quality matrix
 
Aggregate Planning Report
Aggregate Planning ReportAggregate Planning Report
Aggregate Planning Report
 
Jit & Lean Operations
Jit & Lean OperationsJit & Lean Operations
Jit & Lean Operations
 
Competitive supply chain strategies lsm
Competitive supply chain strategies  lsmCompetitive supply chain strategies  lsm
Competitive supply chain strategies lsm
 
Quality Control
Quality ControlQuality Control
Quality Control
 

Similar to Eoq(p) model

Unit III - Inventory Problems
Unit III - Inventory ProblemsUnit III - Inventory Problems
Unit III - Inventory Problems
SSN College of Engineering, Kalavakkam
 
Reorder point
Reorder pointReorder point
Reorder point
Don Paul
 
Inventory model (operation research)
Inventory model (operation research)Inventory model (operation research)
Inventory model (operation research)
Amrita Gharti
 
Inventory management
Inventory managementInventory management
Inventory management
Kaizer Dave
 
NUS DOS3701 Week 3 PPT Supply Chain Management
NUS DOS3701 Week 3 PPT Supply Chain ManagementNUS DOS3701 Week 3 PPT Supply Chain Management
NUS DOS3701 Week 3 PPT Supply Chain Management
yxiinyu
 
Inventory management
Inventory managementInventory management
Inventory management
Jubayer Alam Shoikat
 
Inventory Management
Inventory ManagementInventory Management
Inventory ManagementVishal Joshi
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-ppt
shahidch44
 
eMba ii pmom_unit-3.1 inventory management a
eMba ii pmom_unit-3.1 inventory management aeMba ii pmom_unit-3.1 inventory management a
eMba ii pmom_unit-3.1 inventory management a
Rai University
 
Inventory notes
Inventory notesInventory notes
Inventory notes
Chinnannan Periasamy
 
what is Inventory and its classification
what is Inventory and its classificationwhat is Inventory and its classification
what is Inventory and its classificationPriyanka Singh
 
Inventory management
Inventory managementInventory management
Inventory management
Nilesh Ahuja
 
chap014.ppt
chap014.pptchap014.ppt
chap014.ppt
AgungTriPamungkas1
 
24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3Harshawardhan Thakare
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory management
sakshi0503sakshi
 
Inventry..
Inventry..Inventry..
Inventry..
VIBHASH SINGH
 
Inventory Man2
Inventory Man2Inventory Man2
Inventory Man2ajithsrc
 

Similar to Eoq(p) model (20)

Unit III - Inventory Problems
Unit III - Inventory ProblemsUnit III - Inventory Problems
Unit III - Inventory Problems
 
Reorder point
Reorder pointReorder point
Reorder point
 
Unit 3-inventory control
Unit 3-inventory controlUnit 3-inventory control
Unit 3-inventory control
 
Inventory model (operation research)
Inventory model (operation research)Inventory model (operation research)
Inventory model (operation research)
 
Inventory management
Inventory managementInventory management
Inventory management
 
NUS DOS3701 Week 3 PPT Supply Chain Management
NUS DOS3701 Week 3 PPT Supply Chain ManagementNUS DOS3701 Week 3 PPT Supply Chain Management
NUS DOS3701 Week 3 PPT Supply Chain Management
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-ppt
 
eMba ii pmom_unit-3.1 inventory management a
eMba ii pmom_unit-3.1 inventory management aeMba ii pmom_unit-3.1 inventory management a
eMba ii pmom_unit-3.1 inventory management a
 
Inventory notes
Inventory notesInventory notes
Inventory notes
 
what is Inventory and its classification
what is Inventory and its classificationwhat is Inventory and its classification
what is Inventory and its classification
 
Inventory management
Inventory managementInventory management
Inventory management
 
chap014.ppt
chap014.pptchap014.ppt
chap014.ppt
 
24867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-324867879 inventory-management-control-lecture-3
24867879 inventory-management-control-lecture-3
 
Inventory control
Inventory controlInventory control
Inventory control
 
Inventory Management Inventory management
Inventory Management Inventory managementInventory Management Inventory management
Inventory Management Inventory management
 
Inventry..
Inventry..Inventry..
Inventry..
 
Inventory Man2
Inventory Man2Inventory Man2
Inventory Man2
 
Ops5
Ops5Ops5
Ops5
 

Recently uploaded

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 

Recently uploaded (20)

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 

Eoq(p) model

  • 1. EOQ – P MODEL Submitted by Saurav Kumar
  • 2. • The economic order-quantity model considers the tradeoff between ordering cost and storage cost in choosing the quantity to use in replenishing item inventories. Economic Order Quantity Model
  • 3. • In p model, inventory situations(records)is reviewed at fixed intervals of time when the required replenishment orders are placed. • We have a predetermined time (P) between orders (sales rep comes by every 10 days) or the average time between orders from EOQ = Q/r year • Used for bulk materials and services like refineries, petrol pumps ,etc. • Also called as fixed time Model because the review of purchase is done after some fixed time say 5 or 10 days P model
  • 4. • Stocks at petrol pump is say 120 kl and consumption per week is 100 kl, thus safety stock is 20kl • Demand is always variable and in 95% cases it may not exceed 120 kl, thus it is called 95% service level stocks Cntd…
  • 5. • There is some lead time (L) to get the supply and thus the variation in demand during lead time is “σL” • Due to this variation, the stocks level will also vary and the stock level variation is denoted by “z” Therefore: Safety Stocks = z x σL Symbols and explanations
  • 7. Daily demand at a petrol pump os 10 KL and variation in daily demand is 3 KL. Review period is 30 days and lead time is 14 days. Opening Inventory is 150 KL and variation in stock level is 0.21 . Find q? Example 1
  • 8.
  • 9. • In a chemical company , average demand for product is 10 KL per day and standard variation is 2 Kl per day. The inventory levels was 20 kl. The review time is 60 days and lead time is 15 days. Find q so as to maintain 95% service level stock ( z at 95% is 1.645) Example-2
  • 10. Given data : T=60,L=15, σT+L= 2 d=10 and I = 20 we have q= (r x (T+L)) + (z x σT+L) – I q= 10x(60+15)+(1.645x2)-20 = 733 KL Solution
  • 11. • Consider an item for which Annual demand= 1000 units Standard deviation of demand per week = 10 units Cost per unit = Rs 5 Ordering cost per order = Rs 150 Inventory carrying cost= 30 percent Average lead time = 4 weeks Maximum delay in lead time = 3 weeks Probability of delay = 0.30 Service level= 95% Example 3
  • 13. • Hema garment Manufacturing Company uses basic cloth, „two by two‟ , in most of its products. It buys its annual requirement of 16000 metres of cloth in economic lots of 4000 metres each. The lead time for procurement is generally taken as 6 weeks . Hema maintains a safety sticks of 1000 metres. If Hema were to change over to a fixed order cycle system, maintaining the safety stocks Example 4