The Key Role of the NEC Programme
and who really owns the float?
Presentation:
• Objectives of the NEC form
• Programme requirements under NEC
• Ownership of float
• Acceptance of programmes
Issues with other forms of contract and
management of programme:
• Retrospective analysis of time delay and
entitlement – subjective to say the least!
• No firm requirement on how to manage
programme during contract
• Often comparing current programme to
original baseline programme (which has no
resemblance as to how works now being
done).
Quote from a lawyer:
Programme under the NEC3 is
the “beating heart of the contract”
NEC Contract
Clause 31 – The programme
Clause 31 – The programme
31.2 - Items to be shown on the programme include:
• starting date/Completion Date/Key Dates
• planned Completion
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
CE’sAcceleration
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
ANYTHING!!
Clause 31 – The programme
31.2 - Items to be shown on the programme include:
• starting date/Completion Date/Key Dates
• planned Completion
• order and timing of operations to Provide the Works
• float
• time risk allowances
• health and safety requirements
• Plant & Materials from Employer
• acceptances
• information from Others
• statements of how the Contractor plans to do the work
Reasons for not accepting a programme
Under clause 31.3 there are only four reasons
not to accept a programme:
• The Contractor’s plans which it shows are not practicable
• It does not show the information which this contract requires
• It does not represent the Contractor’s plans realistically or
• It does not comply with the Works Information
If the Project Manager withholds acceptance for a reason not
stated in contract it is a compensation event
Acceptance of a programme by the Project Manager is not a
condition precedent to the Contractor proceeding with the work
25% of Price for Work Done to
Date deducted until first programme
submitted showing the information
the contract requires
Clause 31 – The Programme
Clause 32 - Revising the programme
32.1 - Contractor shows on each revised programme:
• actual progress achieved on each operation activity
and affect upon remaining work
• effects of implemented compensation events
• how Contractor plans to deal with any delays and to
correct notified Defects
• any other changes that Contractor proposes to make
32.2 – Contractor submits a revised programme:
• Within the period for reply after Project Manager
has instructed
• When the Contractor chooses to
• At no longer interval than stated in the contract
Types of Float
• Total float
• Time risk allowance
• Terminal float
Who Owns Total Float?
• Activity ‘A’ can move along its float & will move
activity ‘B’. When the end of the float is reached it
becomes critical
• Is available to accommodate
•the time effects of a compensation event
•lack of progress by the Contractor
TOTAL FLOAT
Who Owns Total Float?
Activity ‘A’
Activity ‘B’
Activity ‘C’
TOTAL FLOAT
Activity ‘D’
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
Ownership of Total Float
4w
4w
4w
3w
3w
3w
3w float
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
CE
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
CE
1w float
Accepted programme
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12 13
4w
4w
4w
3w
3w
3w
CE
1w delay
(Delay
Damages)
2w
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12 13
4w
4w
4w
3w
3w
3w
CE
2w
1w float
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
1w float
Accepted programme
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
CE
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12 13
4w
4w
4w
3w
3w CE
3w
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12 13
4w
4w
4w
3w
3w CE
1w float
No delay
damages
3w
Forecast
cost 1 week
delay in CE
Total Float
•Float shared – whoever gets there
first!
•Programme needs updated regularly
(daily/weekly) to demonstrate true
effect.
Who Owns Time Risk Allowance?
• Aim is to show that elements of risk have been
applied to each operation. Are owned by the
Contractor ( to cover his risks)
• This gives some comfort to the Employer that
particularly critical path is achievable
• Part of normal tender process i.e.
200m pipe @ 15.5m/gang/day = 12.9 so say 15 days
• Is NOT available to anyone other than the Contractor
– i.e. can not be used to mitigate affect of a CE
Time Risk Allowance
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
Ownership of Time Risk Allowance
4w
4w
4w
3w
3w
3w
3w float
Time Risk Allowance =3 days
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
CE – 3 day delay access to A
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
3w 2d
4w
4w
3w
3w
3w
?
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
3 days
Start TRA
Activity A 3d
Activity B 2d
Activity C 1d
Activity D 0d
Activity E 1d
Activity F 3d
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
4w
4w
4w
3w
3w
3w
Time Risk Allowance
• Time risk allowance is Contractor owned
• This can not be used up by the PM and
CE’s – although they may try!!!
• Programme has to be realistic/achievable
so disproportionately long elements of TRA
are unlikely to be accepted by PM.
Terminal Float
•Difference between planned
Completion and Completion Date
•Owned by the Contractor
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 4 8 12
Ownership of Terminal Float
4w
4w
4w
3w
3w
3w
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 3 4 8 12
4w
4w
4w
3w
3w
3w
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 3 4 8 12
3w
4w
4w
3w
3w
3w
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 3 4 8 12
3w
4w
4w
3w
3w
3w
1w
terminal
float
Accepted programme
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 3 4 8 12
3w
4w
4w
3w
3w
3w
CE – 1 WEEK
Start
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
planned Completion
Completion Date
WEEK NUMBERS 0 3 4 8 12
3w
4w
4w
3w
3w
3w
1 week
Terminal Float
• Completion Date moves out the amount
that planned Completion moves out due
to the effects of a Compensation Event
• Can then only be brought back by
acceleration.
Clause 31 – The programme
31.2 - Items to be shown on the programme include:
• starting date/Completion Date/Key Dates
• planned Completion
• order and timing of operations to Provide the Works
• float
• time risk allowances
Under clause 31.3 there are only four reasons
not to accept a programme:
• The Contractor’s plans which it shows are not practicable
• It does not show the information which this contract requires
• It does not represent the Contractor’s plans realistically or
• It does not comply with the Works Information
If programme not accepted:
• Neither party clear on the Completion Date and
contractor entitlement
• Employer will in the absence of a newly
accepted programme assess change (CE’s) on
the last accepted programme
• Important to both parties programme regularly
accepted.
• Otherwise enjoy the traditional end of project
bun-fight to sort out the final account…
Contractor:
• Make sure your programme fully complies with
clause 31.2 (and 32.1)
• Show difference between planned Completion/
Completion Date
• Comprehensive programme narrative with each
submission
• Programme review meeting during acceptance
period with PM
• If no response to programme – call a meeting
and try to bring it to a head
Employer:
• Review programme well within two week
response period and give early comment
• Aim for a one week response where
possible
• Give clear specific reasons why it is not
accepted - only four reasons under the
contract
• Accept with comments – comments being
minor issues that can be put right on the
next programme issue
Summary
• Role of programme within NEC contract is significantly
heightened – and hence the role of the planner
• Contract actually helps the planning function as it is enforcing
the normal day to day processes that the planner and the
business should be wanting to initiate
• Everyone on the project needs to be using the programme – not
just the planner
• TRANSPARENCY – do what ever it takes to present and
produce information that makes things clear and unambiguous
• Work in real time – each programme is a “line in the sand” as to
what has happened and what is projected at a single point in
time
• Keep on top of EW + CE’s and associated time affects
• Consider training to reinforce understanding of the contract
Thanks for listening, and remember…
…any questions from the audience???
For more details: www.gmhplanning.co.uk

More Related Content

What's hot

EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)
Anthony Davies
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
chetlapally balakrishna
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
Abdelhay Ghanem
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
Shahrukh Vahora
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
Shivam Sood
 
Project management-plan template
Project management-plan templateProject management-plan template
Project management-plan template
Vivek Srivastava
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
The Vertex Companies, LLC
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
Nilesh Dhotre
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
Glen Alleman
 
PM-Project Closing-UiTM Project
PM-Project Closing-UiTM ProjectPM-Project Closing-UiTM Project
PM-Project Closing-UiTM Project
TrainingandCoaching Trainer
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Ammar Hasan Beck
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
Khyati Tewari
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
Browne Jacobson LLP
 

What's hot (19)

EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
 
Project management-plan template
Project management-plan templateProject management-plan template
Project management-plan template
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
PM-Project Closing-UiTM Project
PM-Project Closing-UiTM ProjectPM-Project Closing-UiTM Project
PM-Project Closing-UiTM Project
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 

Similar to Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Programme and who really owns the float?" By Glenn Hide

Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Project Controls Expo
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
Association for Project Management
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
Association for Project Management
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
Aditi Garg
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
April Davies, MA, CAPM
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
Waqar Ahmed
 
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
Erasmus+ UK National Agency
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
abdelazizfarag1
 
ch13.ppt
ch13.pptch13.ppt
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
Jatindra Malik
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
Timothy Cochran
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
Nada Sallam
 

Similar to Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Programme and who really owns the float?" By Glenn Hide (20)

Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
Key Action 2 Start up seminar VET, Adult Education & Youth (2014 Call) 29.1.15
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
ch13.ppt
ch13.pptch13.ppt
ch13.ppt
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
Project Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Using-Presentation-Software-to-the-Fullf.pptx
Using-Presentation-Software-to-the-Fullf.pptxUsing-Presentation-Software-to-the-Fullf.pptx
Using-Presentation-Software-to-the-Fullf.pptx
kainatfatyma9
 
XP 2024 presentation: A New Look to Leadership
XP 2024 presentation: A New Look to LeadershipXP 2024 presentation: A New Look to Leadership
XP 2024 presentation: A New Look to Leadership
samililja
 
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
gpww3sf4
 
Carrer goals.pptx and their importance in real life
Carrer goals.pptx  and their importance in real lifeCarrer goals.pptx  and their importance in real life
Carrer goals.pptx and their importance in real life
artemacademy2
 
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
OECD Directorate for Financial and Enterprise Affairs
 
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
OECD Directorate for Financial and Enterprise Affairs
 
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussion
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussionPro-competitive Industrial Policy – LANE – June 2024 OECD discussion
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussion
OECD Directorate for Financial and Enterprise Affairs
 
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
Suzanne Lagerweij
 
The remarkable life of Sir Mokshagundam Visvesvaraya.pptx
The remarkable life of Sir Mokshagundam Visvesvaraya.pptxThe remarkable life of Sir Mokshagundam Visvesvaraya.pptx
The remarkable life of Sir Mokshagundam Visvesvaraya.pptx
JiteshKumarChoudhary2
 
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussion
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussionPro-competitive Industrial Policy – OECD – June 2024 OECD discussion
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussion
OECD Directorate for Financial and Enterprise Affairs
 
Gregory Harris - Cycle 2 - Civics Presentation
Gregory Harris - Cycle 2 - Civics PresentationGregory Harris - Cycle 2 - Civics Presentation
Gregory Harris - Cycle 2 - Civics Presentation
gharris9
 
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdfWhy Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
Ben Linders
 
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussionArtificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
OECD Directorate for Financial and Enterprise Affairs
 
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
OECD Directorate for Financial and Enterprise Affairs
 
ASONAM2023_presection_slide_track-recommendation.pdf
ASONAM2023_presection_slide_track-recommendation.pdfASONAM2023_presection_slide_track-recommendation.pdf
ASONAM2023_presection_slide_track-recommendation.pdf
ToshihiroIto4
 
Disaster Management project for holidays homework and other uses
Disaster Management project for holidays homework and other usesDisaster Management project for holidays homework and other uses
Disaster Management project for holidays homework and other uses
RIDHIMAGARG21
 
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdfBRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
Robin Haunschild
 
2024-05-30_meetup_devops_aix-marseille.pdf
2024-05-30_meetup_devops_aix-marseille.pdf2024-05-30_meetup_devops_aix-marseille.pdf
2024-05-30_meetup_devops_aix-marseille.pdf
Frederic Leger
 
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussionArtificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
OECD Directorate for Financial and Enterprise Affairs
 

Recently uploaded (20)

The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
The Intersection between Competition and Data Privacy – CAPEL – June 2024 OEC...
 
Using-Presentation-Software-to-the-Fullf.pptx
Using-Presentation-Software-to-the-Fullf.pptxUsing-Presentation-Software-to-the-Fullf.pptx
Using-Presentation-Software-to-the-Fullf.pptx
 
XP 2024 presentation: A New Look to Leadership
XP 2024 presentation: A New Look to LeadershipXP 2024 presentation: A New Look to Leadership
XP 2024 presentation: A New Look to Leadership
 
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
原版制作贝德福特大学毕业证(bedfordhire毕业证)硕士文凭原版一模一样
 
Carrer goals.pptx and their importance in real life
Carrer goals.pptx  and their importance in real lifeCarrer goals.pptx  and their importance in real life
Carrer goals.pptx and their importance in real life
 
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
Artificial Intelligence, Data and Competition – SCHREPEL – June 2024 OECD dis...
 
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
The Intersection between Competition and Data Privacy – OECD – June 2024 OECD...
 
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussion
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussionPro-competitive Industrial Policy – LANE – June 2024 OECD discussion
Pro-competitive Industrial Policy – LANE – June 2024 OECD discussion
 
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...
 
The remarkable life of Sir Mokshagundam Visvesvaraya.pptx
The remarkable life of Sir Mokshagundam Visvesvaraya.pptxThe remarkable life of Sir Mokshagundam Visvesvaraya.pptx
The remarkable life of Sir Mokshagundam Visvesvaraya.pptx
 
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussion
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussionPro-competitive Industrial Policy – OECD – June 2024 OECD discussion
Pro-competitive Industrial Policy – OECD – June 2024 OECD discussion
 
Gregory Harris - Cycle 2 - Civics Presentation
Gregory Harris - Cycle 2 - Civics PresentationGregory Harris - Cycle 2 - Civics Presentation
Gregory Harris - Cycle 2 - Civics Presentation
 
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdfWhy Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
Why Psychological Safety Matters for Software Teams - ACE 2024 - Ben Linders.pdf
 
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussionArtificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – LIM – June 2024 OECD discussion
 
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
Competition and Regulation in Professions and Occupations – OECD – June 2024 ...
 
ASONAM2023_presection_slide_track-recommendation.pdf
ASONAM2023_presection_slide_track-recommendation.pdfASONAM2023_presection_slide_track-recommendation.pdf
ASONAM2023_presection_slide_track-recommendation.pdf
 
Disaster Management project for holidays homework and other uses
Disaster Management project for holidays homework and other usesDisaster Management project for holidays homework and other uses
Disaster Management project for holidays homework and other uses
 
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdfBRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
BRIC_2024_2024-06-06-11:30-haunschild_archival_version.pdf
 
2024-05-30_meetup_devops_aix-marseille.pdf
2024-05-30_meetup_devops_aix-marseille.pdf2024-05-30_meetup_devops_aix-marseille.pdf
2024-05-30_meetup_devops_aix-marseille.pdf
 
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussionArtificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
Artificial Intelligence, Data and Competition – OECD – June 2024 OECD discussion
 

Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Programme and who really owns the float?" By Glenn Hide

  • 1. The Key Role of the NEC Programme and who really owns the float? Presentation: • Objectives of the NEC form • Programme requirements under NEC • Ownership of float • Acceptance of programmes Issues with other forms of contract and management of programme: • Retrospective analysis of time delay and entitlement – subjective to say the least! • No firm requirement on how to manage programme during contract • Often comparing current programme to original baseline programme (which has no resemblance as to how works now being done).
  • 2. Quote from a lawyer: Programme under the NEC3 is the “beating heart of the contract” NEC Contract Clause 31 – The programme Clause 31 – The programme 31.2 - Items to be shown on the programme include: • starting date/Completion Date/Key Dates • planned Completion
  • 3. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w CE’sAcceleration Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w ANYTHING!! Clause 31 – The programme 31.2 - Items to be shown on the programme include: • starting date/Completion Date/Key Dates • planned Completion • order and timing of operations to Provide the Works • float • time risk allowances • health and safety requirements • Plant & Materials from Employer • acceptances • information from Others • statements of how the Contractor plans to do the work
  • 4. Reasons for not accepting a programme Under clause 31.3 there are only four reasons not to accept a programme: • The Contractor’s plans which it shows are not practicable • It does not show the information which this contract requires • It does not represent the Contractor’s plans realistically or • It does not comply with the Works Information If the Project Manager withholds acceptance for a reason not stated in contract it is a compensation event Acceptance of a programme by the Project Manager is not a condition precedent to the Contractor proceeding with the work 25% of Price for Work Done to Date deducted until first programme submitted showing the information the contract requires Clause 31 – The Programme Clause 32 - Revising the programme 32.1 - Contractor shows on each revised programme: • actual progress achieved on each operation activity and affect upon remaining work • effects of implemented compensation events • how Contractor plans to deal with any delays and to correct notified Defects • any other changes that Contractor proposes to make 32.2 – Contractor submits a revised programme: • Within the period for reply after Project Manager has instructed • When the Contractor chooses to • At no longer interval than stated in the contract
  • 5. Types of Float • Total float • Time risk allowance • Terminal float Who Owns Total Float? • Activity ‘A’ can move along its float & will move activity ‘B’. When the end of the float is reached it becomes critical • Is available to accommodate •the time effects of a compensation event •lack of progress by the Contractor TOTAL FLOAT Who Owns Total Float? Activity ‘A’ Activity ‘B’ Activity ‘C’ TOTAL FLOAT Activity ‘D’
  • 6. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 Ownership of Total Float 4w 4w 4w 3w 3w 3w 3w float Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w CE Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w CE 1w float Accepted programme
  • 7. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 13 4w 4w 4w 3w 3w 3w CE 1w delay (Delay Damages) 2w Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 13 4w 4w 4w 3w 3w 3w CE 2w 1w float Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w 1w float Accepted programme
  • 8. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w CE Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 13 4w 4w 4w 3w 3w CE 3w Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 13 4w 4w 4w 3w 3w CE 1w float No delay damages 3w Forecast cost 1 week delay in CE
  • 9. Total Float •Float shared – whoever gets there first! •Programme needs updated regularly (daily/weekly) to demonstrate true effect. Who Owns Time Risk Allowance? • Aim is to show that elements of risk have been applied to each operation. Are owned by the Contractor ( to cover his risks) • This gives some comfort to the Employer that particularly critical path is achievable • Part of normal tender process i.e. 200m pipe @ 15.5m/gang/day = 12.9 so say 15 days • Is NOT available to anyone other than the Contractor – i.e. can not be used to mitigate affect of a CE Time Risk Allowance
  • 10. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 Ownership of Time Risk Allowance 4w 4w 4w 3w 3w 3w 3w float Time Risk Allowance =3 days Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w CE – 3 day delay access to A Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 3w 2d 4w 4w 3w 3w 3w ?
  • 11. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w 3 days Start TRA Activity A 3d Activity B 2d Activity C 1d Activity D 0d Activity E 1d Activity F 3d planned Completion Completion Date WEEK NUMBERS 0 4 8 12 4w 4w 4w 3w 3w 3w Time Risk Allowance • Time risk allowance is Contractor owned • This can not be used up by the PM and CE’s – although they may try!!! • Programme has to be realistic/achievable so disproportionately long elements of TRA are unlikely to be accepted by PM.
  • 12. Terminal Float •Difference between planned Completion and Completion Date •Owned by the Contractor Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 4 8 12 Ownership of Terminal Float 4w 4w 4w 3w 3w 3w Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 3 4 8 12 4w 4w 4w 3w 3w 3w
  • 13. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 3 4 8 12 3w 4w 4w 3w 3w 3w Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 3 4 8 12 3w 4w 4w 3w 3w 3w 1w terminal float Accepted programme Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 3 4 8 12 3w 4w 4w 3w 3w 3w CE – 1 WEEK
  • 14. Start Activity A Activity B Activity C Activity D Activity E Activity F planned Completion Completion Date WEEK NUMBERS 0 3 4 8 12 3w 4w 4w 3w 3w 3w 1 week Terminal Float • Completion Date moves out the amount that planned Completion moves out due to the effects of a Compensation Event • Can then only be brought back by acceleration.
  • 15. Clause 31 – The programme 31.2 - Items to be shown on the programme include: • starting date/Completion Date/Key Dates • planned Completion • order and timing of operations to Provide the Works • float • time risk allowances Under clause 31.3 there are only four reasons not to accept a programme: • The Contractor’s plans which it shows are not practicable • It does not show the information which this contract requires • It does not represent the Contractor’s plans realistically or • It does not comply with the Works Information If programme not accepted: • Neither party clear on the Completion Date and contractor entitlement • Employer will in the absence of a newly accepted programme assess change (CE’s) on the last accepted programme • Important to both parties programme regularly accepted. • Otherwise enjoy the traditional end of project bun-fight to sort out the final account…
  • 16. Contractor: • Make sure your programme fully complies with clause 31.2 (and 32.1) • Show difference between planned Completion/ Completion Date • Comprehensive programme narrative with each submission • Programme review meeting during acceptance period with PM • If no response to programme – call a meeting and try to bring it to a head Employer: • Review programme well within two week response period and give early comment • Aim for a one week response where possible • Give clear specific reasons why it is not accepted - only four reasons under the contract • Accept with comments – comments being minor issues that can be put right on the next programme issue Summary • Role of programme within NEC contract is significantly heightened – and hence the role of the planner • Contract actually helps the planning function as it is enforcing the normal day to day processes that the planner and the business should be wanting to initiate • Everyone on the project needs to be using the programme – not just the planner • TRANSPARENCY – do what ever it takes to present and produce information that makes things clear and unambiguous • Work in real time – each programme is a “line in the sand” as to what has happened and what is projected at a single point in time • Keep on top of EW + CE’s and associated time affects • Consider training to reinforce understanding of the contract
  • 17. Thanks for listening, and remember… …any questions from the audience??? For more details: www.gmhplanning.co.uk