SlideShare a Scribd company logo
1 of 41
DIAGNOSTICS FOR
TIME MANAGEMENT
TO C R A S H O R N OT TO C R A S H ?
TA K E T H E G U E S S W O R K O U T O F Y O U R D E A D L I N E .
PROJECT TIME MANAGEMENT
KNOWLEDGE AREA
• AGENDA:
– COST TIME TRADE OFFS OF CRASHING
– PROBABILITY OF COMPLETING A PROJECT BASED ON PERT ANALYSYS
• PMBOK GUIDE 6TH EDITION
• DEVELOP SCHEDULE: TOOLS AND TECHNIQUES –
– SCHEDULE COMPRESSION – CRASHING (6.5.2.6)
– DATA ANALYSIS – SIMULATION MODELS (6.5.2.4)
• PLANNING PROCESS GROUP
WHO WE ARE
• ROBERT DAVIES – LEAD ELECTRONICS ENGINEER, PRIDE MOBILITY PRODUCTS
• MS ENGINEERING OPERATIONS AND STRATEGY 2018’
• OVER A DECADE OF EXPERIENCE IN ELECTRICAL/ELECTRONIC SYSTEMS DESIGN
• 4 US PATENTS (PENDING) & 1 EU PATENT (PENDING)
• APRIL DAVIES – PROJECT COORDINATOR, TMG HEALTH / COGNIZANT
• MS PROJECT MANAGEMENT (HEALTHCARE ADMINISTRATION) 2018
• MA COMMUNICATION ARTS – MARYWOOD UNIVERSITY
• DECADE OF EXPERIECNE IN EXECUTIVE LEVEL SUPPORT AND SPECIAL PROJECTS
• CAPM JUNE 2017
PROJECT
CRASHING
PROJECT CRASHING
• The PMBOK defines project crashing as a technique used to
shorten the schedule duration for the least cost by adding
resources.
• Crashing is one method of schedule compression used to
accelerate the schedule duration to meet constraints, key
dates and other schedule objectives without reducing the
project scope.
COST TIME TRADE OFFS OF
CRASHING
• When managing a project it’s not uncommon for a project
manager to be faced with these scenarios.
–A project is falling behind schedule.
And/or
–The scheduled completion date of a project is moved
forward.
–In either scenario, we need to determine how to speed up
the activities that occur within the project’s pipeline.
DETERMINING ACTIVITIES TO CRASH
• The concern lies in the question of:
– Which activities should be shortened?
– How many activities should be shortened?
• The project manager needs to review the critical activities and
determine which would have the least impact to the cost.
• Costs need to be compared, but how?
• Assumptions:
– Manager is working to ensure that the cost of the crash is permissible.
– The shortened activity time will allow us to meet the due date.
– Total cost of crashing is as small as possible.
PROJECT COSTS
• Project direct costs to the project that consist of labor, materials,
equipment and contractor expenses.
• Direct cost are assigned to each of the project activities.
• Under a normal assumption, the direct costs represent normal delivery
of project activities.
• Changes to the normal delivery of of these activities would constitute an
increase to the project’s direct costs.
• The sum of all project costs is equivalent to the sum of all activities and
the total direct cost of the project.
• Not all costs are the same for every activity, therefore it could be
difficult to determine which activity to shorten.
COST TIME TRADE OFF
Crash Point
Cost
Activity 1
Activity 2
Crash Point
Normal
HOW TO CRASH A PROJECT
1) Compute the crash cost per time period.
2) Find the critical path of the project’s network.
3) Find the activities on the critical path that can be
crashed and have the smallest crash cost.
4) Update activity times to determine if the desired due
dates can be reached.
THE DILEMMA
T H E D E L I M M A
Julie Anne’s boss tells her
that she must complete her
project at an earlier than
anticipated due date. He is
willing to pay any price to
have the project come in
sooner then planned. Julie
Anne needs to determine
which activities to crash, by
how much, and how to meet
his 13 week deadline which
was shortened from 15
weeks. She would like to
speed up her project by 2
weeks at the least minimal
STEP 1
Compute the crash cost per time period.
Crash Cost per Period =
Crash Cost – Normal Cost
Normal Time – Crash Time
CALCULATING CRASH COST
Crash Cost =
Crash Cost – Normal Cost
Normal Time – Crash Time
Activity Normal Time Crash Time Normal Cost Crash Cost Cost per
time period
A 2 1 22,000 22,750 750
B 3 1 30,000 34,000 2,000
C 2 1 26,000 27,000 1,000
D 4 3 48,000 49,000 1,000
E 4 2 56,000 58,000 1,000
F 3 2 30,000 30,500 500
G 5 2 80,000 84,500 1,500
H 2 1 16,000 19,000 3,000
CRITICAL PATH
POP QUIZ
STEP 2
Find the Critical Path
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
STEP 2
Find the Critical Path
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
STEP 3
• Find the critical path activities with smallest crash cost.
Activity Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
Cost per
time
period
Critical
Path
A 2 1 22,000 22,750 750 Yes
B 3 1 30,000 34,000 2,000 No
C 2 1 26,000 27,000 1,000 Yes
D 4 3 48,000 49,000 1,000 No
E 4 2 56,000 58,000 1,000 Yes
F 3 2 30,000 30,500 500 No
G 5 2 80,000 84,500 1,500 Yes
H 2 1 16,000 19,000 3,000 Yes
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
1
H
2
Activity
Duration
14 weeks
Total: $750
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
1
H
2
Activity
Duration
13 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
Total: $2,750
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
Total: $1,500
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
2
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
12 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
SUCCESSFUL CRASH REMINDERS
• Ensure that the cost to crash is as small as possible.
• Update your project with new activity times and budget with
new cost considerations. Crashing only works for critical path
activities.
• Crashing can increase risk. Reevaluate risk as needed.
• Ensure your resources are available to complete the crash.
• Receive the proper prior authorization to make the change (CR)
• Remember to be considerate of money. Consider the approach
of take only what is needed.
• Remember Responsible Crashing: Always Weigh Impact to
Quality
– 4 Hour House – What is the cost of quality.
– https://www.youtube.com/watch?v=oDB1O5cadQw
PERT ANALYSIS
WHAT IS PERT?
• The program (or project) evaluation and review
technique, commonly abbreviated PERT, is a
statistical tool, used in project management…
PERT
HISTORY?
• Initially PERT stood for
Program Evaluation
Research Task
• Started by the US NAVY
1950’s – as part of a
(CPM) analysis Critical
Path Method.
• Design to simplify and
plan complex projects i.e.
building of a nuclear
submarines.
WHAT DOES PERT DO?
• PERT - in its simplest form is a tool for estimating
the probability of completing a task (program or
project) in a given time constraint.
• “What is the confidence level of completing phase
2 by Oct 15th ?” said the VP
EXAMPLE OF PERT
PERT STEP 1.
• Identify Critical Path Tasks
• The longest possible continuous pathway taken from the
initial event to the terminal event. It determines the total
calendar time required for the project; and, therefore, any
time delays along the critical path will delay the reaching
of the terminal event by at least the same amount.
PERT STEP 2.
• Optimistic : The
minimum possible
time required to
accomplish a task,
assuming
everything
proceeds better
than is normally
expected.
PERT STEP 3.
• Likely : The best
estimate of the time
required to
accomplish a task,
assuming everything
proceeds as normal.
PERT STEP 4.
• Pessimistic : The
maximum possible
time required to
accomplish a task,
assuming
everything goes
wrong (but
excluding major
catastrophes).
PERT STEP 5.
• Calculate Expected Duration using given inputs
PERT STEP 6.
• Calculate Standard Deviation / Variance
PERT STEP 6.2.0
• Calculate Standard Deviation / Variance
PERT STEP 7.
• Given a due date we can calculate the
probability of meeting a particular due date
PERT STEP 8.
• Now we look up
Z in the Normal
Distribution
Table
PERT STEP 9.
• That’s it! Report the probability of completion in
percentage i.e. 0.99 equates to 99% probability.
QUESTIONS AND
CONCLUSION

More Related Content

What's hot

Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms Babasab Patil
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path AnalysisDavid Zaki
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 

What's hot (20)

Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
 
Critical path method
Critical path methodCritical path method
Critical path method
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 

Similar to Project Management Diagnostics for Time Management

Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chaintanishkagupta907
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 

Similar to Project Management Diagnostics for Time Management (20)

Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 

Recently uploaded

Microphone- characteristics,carbon microphone, dynamic microphone.pptx
Microphone- characteristics,carbon microphone, dynamic microphone.pptxMicrophone- characteristics,carbon microphone, dynamic microphone.pptx
Microphone- characteristics,carbon microphone, dynamic microphone.pptxpriyankatabhane
 
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCR
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCRCall Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCR
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCRlizamodels9
 
Speech, hearing, noise, intelligibility.pptx
Speech, hearing, noise, intelligibility.pptxSpeech, hearing, noise, intelligibility.pptx
Speech, hearing, noise, intelligibility.pptxpriyankatabhane
 
Analytical Profile of Coleus Forskohlii | Forskolin .pptx
Analytical Profile of Coleus Forskohlii | Forskolin .pptxAnalytical Profile of Coleus Forskohlii | Forskolin .pptx
Analytical Profile of Coleus Forskohlii | Forskolin .pptxSwapnil Therkar
 
Welcome to GFDL for Take Your Child To Work Day
Welcome to GFDL for Take Your Child To Work DayWelcome to GFDL for Take Your Child To Work Day
Welcome to GFDL for Take Your Child To Work DayZachary Labe
 
Evidences of Evolution General Biology 2
Evidences of Evolution General Biology 2Evidences of Evolution General Biology 2
Evidences of Evolution General Biology 2John Carlo Rollon
 
insect anatomy and insect body wall and their physiology
insect anatomy and insect body wall and their  physiologyinsect anatomy and insect body wall and their  physiology
insect anatomy and insect body wall and their physiologyDrAnita Sharma
 
TOTAL CHOLESTEROL (lipid profile test).pptx
TOTAL CHOLESTEROL (lipid profile test).pptxTOTAL CHOLESTEROL (lipid profile test).pptx
TOTAL CHOLESTEROL (lipid profile test).pptxdharshini369nike
 
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptx
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptxTHE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptx
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptxNandakishor Bhaurao Deshmukh
 
Is RISC-V ready for HPC workload? Maybe?
Is RISC-V ready for HPC workload? Maybe?Is RISC-V ready for HPC workload? Maybe?
Is RISC-V ready for HPC workload? Maybe?Patrick Diehl
 
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |aasikanpl
 
Neurodevelopmental disorders according to the dsm 5 tr
Neurodevelopmental disorders according to the dsm 5 trNeurodevelopmental disorders according to the dsm 5 tr
Neurodevelopmental disorders according to the dsm 5 trssuser06f238
 
Cytokinin, mechanism and its application.pptx
Cytokinin, mechanism and its application.pptxCytokinin, mechanism and its application.pptx
Cytokinin, mechanism and its application.pptxVarshiniMK
 
Twin's paradox experiment is a meassurement of the extra dimensions.pptx
Twin's paradox experiment is a meassurement of the extra dimensions.pptxTwin's paradox experiment is a meassurement of the extra dimensions.pptx
Twin's paradox experiment is a meassurement of the extra dimensions.pptxEran Akiva Sinbar
 
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tanta
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tantaDashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tanta
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tantaPraksha3
 
Manassas R - Parkside Middle School 🌎🏫
Manassas R - Parkside Middle School 🌎🏫Manassas R - Parkside Middle School 🌎🏫
Manassas R - Parkside Middle School 🌎🏫qfactory1
 
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptx
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptxLIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptx
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptxmalonesandreagweneth
 

Recently uploaded (20)

Microphone- characteristics,carbon microphone, dynamic microphone.pptx
Microphone- characteristics,carbon microphone, dynamic microphone.pptxMicrophone- characteristics,carbon microphone, dynamic microphone.pptx
Microphone- characteristics,carbon microphone, dynamic microphone.pptx
 
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCR
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCRCall Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCR
Call Girls In Nihal Vihar Delhi ❤️8860477959 Looking Escorts In 24/7 Delhi NCR
 
Speech, hearing, noise, intelligibility.pptx
Speech, hearing, noise, intelligibility.pptxSpeech, hearing, noise, intelligibility.pptx
Speech, hearing, noise, intelligibility.pptx
 
Hot Sexy call girls in Moti Nagar,🔝 9953056974 🔝 escort Service
Hot Sexy call girls in  Moti Nagar,🔝 9953056974 🔝 escort ServiceHot Sexy call girls in  Moti Nagar,🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Moti Nagar,🔝 9953056974 🔝 escort Service
 
Analytical Profile of Coleus Forskohlii | Forskolin .pptx
Analytical Profile of Coleus Forskohlii | Forskolin .pptxAnalytical Profile of Coleus Forskohlii | Forskolin .pptx
Analytical Profile of Coleus Forskohlii | Forskolin .pptx
 
Welcome to GFDL for Take Your Child To Work Day
Welcome to GFDL for Take Your Child To Work DayWelcome to GFDL for Take Your Child To Work Day
Welcome to GFDL for Take Your Child To Work Day
 
Engler and Prantl system of classification in plant taxonomy
Engler and Prantl system of classification in plant taxonomyEngler and Prantl system of classification in plant taxonomy
Engler and Prantl system of classification in plant taxonomy
 
Evidences of Evolution General Biology 2
Evidences of Evolution General Biology 2Evidences of Evolution General Biology 2
Evidences of Evolution General Biology 2
 
insect anatomy and insect body wall and their physiology
insect anatomy and insect body wall and their  physiologyinsect anatomy and insect body wall and their  physiology
insect anatomy and insect body wall and their physiology
 
TOTAL CHOLESTEROL (lipid profile test).pptx
TOTAL CHOLESTEROL (lipid profile test).pptxTOTAL CHOLESTEROL (lipid profile test).pptx
TOTAL CHOLESTEROL (lipid profile test).pptx
 
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptx
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptxTHE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptx
THE ROLE OF PHARMACOGNOSY IN TRADITIONAL AND MODERN SYSTEM OF MEDICINE.pptx
 
Is RISC-V ready for HPC workload? Maybe?
Is RISC-V ready for HPC workload? Maybe?Is RISC-V ready for HPC workload? Maybe?
Is RISC-V ready for HPC workload? Maybe?
 
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |
Call Us ≽ 9953322196 ≼ Call Girls In Mukherjee Nagar(Delhi) |
 
Neurodevelopmental disorders according to the dsm 5 tr
Neurodevelopmental disorders according to the dsm 5 trNeurodevelopmental disorders according to the dsm 5 tr
Neurodevelopmental disorders according to the dsm 5 tr
 
Cytokinin, mechanism and its application.pptx
Cytokinin, mechanism and its application.pptxCytokinin, mechanism and its application.pptx
Cytokinin, mechanism and its application.pptx
 
Volatile Oils Pharmacognosy And Phytochemistry -I
Volatile Oils Pharmacognosy And Phytochemistry -IVolatile Oils Pharmacognosy And Phytochemistry -I
Volatile Oils Pharmacognosy And Phytochemistry -I
 
Twin's paradox experiment is a meassurement of the extra dimensions.pptx
Twin's paradox experiment is a meassurement of the extra dimensions.pptxTwin's paradox experiment is a meassurement of the extra dimensions.pptx
Twin's paradox experiment is a meassurement of the extra dimensions.pptx
 
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tanta
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tantaDashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tanta
Dashanga agada a formulation of Agada tantra dealt in 3 Rd year bams agada tanta
 
Manassas R - Parkside Middle School 🌎🏫
Manassas R - Parkside Middle School 🌎🏫Manassas R - Parkside Middle School 🌎🏫
Manassas R - Parkside Middle School 🌎🏫
 
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptx
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptxLIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptx
LIGHT-PHENOMENA-BY-CABUALDIONALDOPANOGANCADIENTE-CONDEZA (1).pptx
 

Project Management Diagnostics for Time Management

  • 1. DIAGNOSTICS FOR TIME MANAGEMENT TO C R A S H O R N OT TO C R A S H ? TA K E T H E G U E S S W O R K O U T O F Y O U R D E A D L I N E .
  • 2. PROJECT TIME MANAGEMENT KNOWLEDGE AREA • AGENDA: – COST TIME TRADE OFFS OF CRASHING – PROBABILITY OF COMPLETING A PROJECT BASED ON PERT ANALYSYS • PMBOK GUIDE 6TH EDITION • DEVELOP SCHEDULE: TOOLS AND TECHNIQUES – – SCHEDULE COMPRESSION – CRASHING (6.5.2.6) – DATA ANALYSIS – SIMULATION MODELS (6.5.2.4) • PLANNING PROCESS GROUP
  • 3. WHO WE ARE • ROBERT DAVIES – LEAD ELECTRONICS ENGINEER, PRIDE MOBILITY PRODUCTS • MS ENGINEERING OPERATIONS AND STRATEGY 2018’ • OVER A DECADE OF EXPERIENCE IN ELECTRICAL/ELECTRONIC SYSTEMS DESIGN • 4 US PATENTS (PENDING) & 1 EU PATENT (PENDING) • APRIL DAVIES – PROJECT COORDINATOR, TMG HEALTH / COGNIZANT • MS PROJECT MANAGEMENT (HEALTHCARE ADMINISTRATION) 2018 • MA COMMUNICATION ARTS – MARYWOOD UNIVERSITY • DECADE OF EXPERIECNE IN EXECUTIVE LEVEL SUPPORT AND SPECIAL PROJECTS • CAPM JUNE 2017
  • 5. PROJECT CRASHING • The PMBOK defines project crashing as a technique used to shorten the schedule duration for the least cost by adding resources. • Crashing is one method of schedule compression used to accelerate the schedule duration to meet constraints, key dates and other schedule objectives without reducing the project scope.
  • 6. COST TIME TRADE OFFS OF CRASHING • When managing a project it’s not uncommon for a project manager to be faced with these scenarios. –A project is falling behind schedule. And/or –The scheduled completion date of a project is moved forward. –In either scenario, we need to determine how to speed up the activities that occur within the project’s pipeline.
  • 7. DETERMINING ACTIVITIES TO CRASH • The concern lies in the question of: – Which activities should be shortened? – How many activities should be shortened? • The project manager needs to review the critical activities and determine which would have the least impact to the cost. • Costs need to be compared, but how? • Assumptions: – Manager is working to ensure that the cost of the crash is permissible. – The shortened activity time will allow us to meet the due date. – Total cost of crashing is as small as possible.
  • 8. PROJECT COSTS • Project direct costs to the project that consist of labor, materials, equipment and contractor expenses. • Direct cost are assigned to each of the project activities. • Under a normal assumption, the direct costs represent normal delivery of project activities. • Changes to the normal delivery of of these activities would constitute an increase to the project’s direct costs. • The sum of all project costs is equivalent to the sum of all activities and the total direct cost of the project. • Not all costs are the same for every activity, therefore it could be difficult to determine which activity to shorten.
  • 9. COST TIME TRADE OFF Crash Point Cost Activity 1 Activity 2 Crash Point Normal
  • 10. HOW TO CRASH A PROJECT 1) Compute the crash cost per time period. 2) Find the critical path of the project’s network. 3) Find the activities on the critical path that can be crashed and have the smallest crash cost. 4) Update activity times to determine if the desired due dates can be reached.
  • 12. T H E D E L I M M A Julie Anne’s boss tells her that she must complete her project at an earlier than anticipated due date. He is willing to pay any price to have the project come in sooner then planned. Julie Anne needs to determine which activities to crash, by how much, and how to meet his 13 week deadline which was shortened from 15 weeks. She would like to speed up her project by 2 weeks at the least minimal
  • 13. STEP 1 Compute the crash cost per time period. Crash Cost per Period = Crash Cost – Normal Cost Normal Time – Crash Time
  • 14. CALCULATING CRASH COST Crash Cost = Crash Cost – Normal Cost Normal Time – Crash Time Activity Normal Time Crash Time Normal Cost Crash Cost Cost per time period A 2 1 22,000 22,750 750 B 3 1 30,000 34,000 2,000 C 2 1 26,000 27,000 1,000 D 4 3 48,000 49,000 1,000 E 4 2 56,000 58,000 1,000 F 3 2 30,000 30,500 500 G 5 2 80,000 84,500 1,500 H 2 1 16,000 19,000 3,000
  • 16. STEP 2 Find the Critical Path S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration
  • 17. STEP 2 Find the Critical Path S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration
  • 18. STEP 3 • Find the critical path activities with smallest crash cost. Activity Normal Time Crash Time Normal Cost Crash Cost Cost per time period Critical Path A 2 1 22,000 22,750 750 Yes B 3 1 30,000 34,000 2,000 No C 2 1 26,000 27,000 1,000 Yes D 4 3 48,000 49,000 1,000 No E 4 2 56,000 58,000 1,000 Yes F 3 2 30,000 30,500 500 No G 5 2 80,000 84,500 1,500 Yes H 2 1 16,000 19,000 3,000 Yes
  • 19. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 20. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 21. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 1 H 2 Activity Duration 14 weeks Total: $750 Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 22. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 1 H 2 Activity Duration 13 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000 Total: $2,750
  • 23. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000 Total: $1,500
  • 24. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 2 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 12 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 25. SUCCESSFUL CRASH REMINDERS • Ensure that the cost to crash is as small as possible. • Update your project with new activity times and budget with new cost considerations. Crashing only works for critical path activities. • Crashing can increase risk. Reevaluate risk as needed. • Ensure your resources are available to complete the crash. • Receive the proper prior authorization to make the change (CR) • Remember to be considerate of money. Consider the approach of take only what is needed. • Remember Responsible Crashing: Always Weigh Impact to Quality – 4 Hour House – What is the cost of quality. – https://www.youtube.com/watch?v=oDB1O5cadQw
  • 27. WHAT IS PERT? • The program (or project) evaluation and review technique, commonly abbreviated PERT, is a statistical tool, used in project management…
  • 28. PERT HISTORY? • Initially PERT stood for Program Evaluation Research Task • Started by the US NAVY 1950’s – as part of a (CPM) analysis Critical Path Method. • Design to simplify and plan complex projects i.e. building of a nuclear submarines.
  • 29. WHAT DOES PERT DO? • PERT - in its simplest form is a tool for estimating the probability of completing a task (program or project) in a given time constraint. • “What is the confidence level of completing phase 2 by Oct 15th ?” said the VP
  • 31. PERT STEP 1. • Identify Critical Path Tasks • The longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
  • 32. PERT STEP 2. • Optimistic : The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
  • 33. PERT STEP 3. • Likely : The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
  • 34. PERT STEP 4. • Pessimistic : The maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
  • 35. PERT STEP 5. • Calculate Expected Duration using given inputs
  • 36. PERT STEP 6. • Calculate Standard Deviation / Variance
  • 37. PERT STEP 6.2.0 • Calculate Standard Deviation / Variance
  • 38. PERT STEP 7. • Given a due date we can calculate the probability of meeting a particular due date
  • 39. PERT STEP 8. • Now we look up Z in the Normal Distribution Table
  • 40. PERT STEP 9. • That’s it! Report the probability of completion in percentage i.e. 0.99 equates to 99% probability.

Editor's Notes

  1. Northeast Branch: September 2017 Meeting When: September 28, 2017 Where: Marzoni's Brick Oven & Brewing - 26 Montage Mountain Rd, Moosic, PA 18507 Speaker:  Robert & April Davies Topic: Diagnostic Techniques for Project Time Management Brief Description: To crash or not to crash? Take the guesswork out of your deadline.     Find out how to calculate the probability of hitting target dates at September's PMI Keystone Chapter’s Meeting. Robert and April Davies will be presenting on diagnostic techniques for project time management. In their presentation, they will review PERT analysis, probability of completion, and cost time trade-offs.  Talent Triangle Category(s): Technical Project Management (1 PDU)
  2. References: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679 In this presentation will be touching on to diagnostic techniques for project time management. We will review probability of completion using PERT, and cost time trade-offs.
  3. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  4. The shortest possible time that a project activity can be completed which is called crash time. Crash time must be realistic. The cost to crash is called the crash cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  5. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  6. We are making the assumptions are that the cost time relationship is linear. Normal cost assumes the must efficient methods to complete the activity. Crash Time represents the least amount of time needed to complete an activity - which is the greatest time reduction possible under realistic conditions Slope assumes the cost per unit of time. Less steep slopes means that it costs less to shorten the duration of that activity. All accelerations must occur within normal and crash times. It’s also normal to assume that crash cost will be higher than normal. In some cases we find that adding more resources will help shorten the time it takes to complete an activity but at a higher cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  7. Compute the crash cost per time period. EX: Grocery Store: Pound of bananas. We need to consider the cost of each banana, not the complete bunch. We will look at calculating the cost of the activity per time segment. Find the critical path of the project’s network. Using the same approach as defined in the PMBOK. We will look at the critical path to determine which activities can have an impact on our schedule Find the activities on the critical path that have the smallest crash cost. Determine which activities are the best candidates for crashing. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  8. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  9. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  10. Julie Anne needs to crash at the least minimal cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  11. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  12. Find the critical path of the activities S – A – C – E – G – H Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  13. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  14. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  15. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  16. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  17. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  18. Option would be to use MS Project to determine the activities. 0 slack activities D not originally on critical path but changed. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  19. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  20. Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  21. Compute the crash cost per time period. EX: Grocery Store: Pound of bananas. We need to consider the cost of each banana, not the complete bunch. We will look at calculating the cost of the activity per time segment. Find the critical path of the project’s network. Using the same approach as defined in the PMBOK. We will look at the critical path to determine which activities can have an impact on our schedule Find the activities on the critical path that have the smallest crash cost. Determine which activities are the best candidates for crashing. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  22. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  23. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  24. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  25. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  26. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  27. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  28. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  29. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  30. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  31. I hope you enjoyed our presentation on cost time trade offs and the probability of completion.