SlideShare a Scribd company logo
Copyright @ 2011. All rights reserved
NEC3 Contracts – Managing Risk
and Change
Project Controls Expo – 18th Nov 2014
Emirates Stadium, London
Copyright @ 2011. All rights reserved
About the Speaker
• Director of BuiltIntelligence
• BI provide training, consultancy,
resources to the construction
industry
• Presented at various national
conferences
• Number of industry published
articles on NEC3 and programme
management
Risk at tender stage
Risk at tender stage takes various forms - Contractor
needs to ascertain risk their risks by reading the
contract that they are signing up to:
• Contract makes it clear what risks are the
Employers under the contract
• Clause 80.1 Employers risks
• clause 60.1 – 19 items that would be
compensation events
• Additional Employer’s risks identified in contract
data part 1
• Z clause amendments could alter risk profile
• 2ndry options that have/have not been included
• Contract data includes a place to identify risks to
be included in the Risk Register, but these do not
(and should not) allocate who’s risk they are
NEC Risk Register is not same as traditional
“risk registers”
• often see “risk registers” included within a
tender document or signed contract
• these (attempt) to allocate “risk”, often
contrary to what the contract says.
• e.g. state weather is Contractor risk, yet they
leave in 60.1(13), or say ground conditions are
Contractor risk and yet leave in 60.1(12)
• the contract should identify whose risks are
whose either by the wording of the contract
or by the content of the Works Information
• NEC3 Risk Register is different from
other traditional risk registers you may
have used
• Not produced until post contract award
• Traditional risk registers included within
the contract attempt to allocate risk –
which potentially creates ambiguities
Early Warnings
8
16.1
Contractor and Project Manager have a duty to
notify each other as soon as they become aware of
a matter which could
–increase the total of the Prices
–delay Completion,
–delay meeting a Key Date or
–impair the performance of the works in use
16.2
potential instruction to attend risk reduction meeting
9
Intent of Risk Reduction meeting is for all those who
attend to :
• consider if the risk(s) is really likely to happen
• if the risk(s) can be avoided altogether or at least
minimised
• come up with solutions to the problem without
worrying/focusing upon about associated liability
• deciding actions as to who/when will move the matter(s)
forward
• Project Manager responsibility to update and re-issue
the Risk Register in terms of items closed out, and who’s
required to take what action
This should be considered a collaborative operational
tool, not a commercial tool
Risk Register is a defined term:
• Risk Register is a register of the risks
which are listed in the contract data, and
• risks which the Project Manager or
Contractor has notified as an early warning
matter.
• It should include a description of the risk
and a description of the action to be taken
to avoid or reduce the risk.
Example of a Risk Register
Programme
Clause 31 – The programme
31.2 - Items to be shown on the programme include:
• starting date/ access dates/ Completion Date/ Key Dates
(sectional completion)
• planned Completion
ECC Section 3 – Time
Start Float
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14w
4w
3w
3w
3w
3w
3w
4w
5w float
Start Float
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14w
4w
3w
3w
3w
3w
3w
4w
CE’s
Acceleration
Start Float
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14w
4w
3w
3w
3w
3w
3w
4w
ANYTHING
Start Float
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14w
4w
3w
3w
3w
3w
3w
4w
Start Float
Activity A 0w
Activity B -1w
Activity C -1w
Activity D -1w
Activity E -1w
Activity F 5w
Activity G 4w
Activity H 4w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14
5w
3w
4w
3w
3w
3w
4w
1w
Accepted Programme
Start Float
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
planned Completion 0w
Completion Date 0w
0 2 4 6 8 10 12 14w
4w
3w
3w
3w
3w
3w
4w
Start Float
Activity A 1w
Activity B 1w
Activity C 1w
Activity D 1w
Activity E 1w
Activity F 5w
Activity G 6w
Activity H 6w
planned Completion 1w
Completion Date 0w
0 2 4 6 8 10 12 14w
3w
3w
2w
3w
3w
4w
3w
1w
Accepted Programme
Clause 31 – The programme
31.2 - Items to be shown on the programme include:
• starting date/access dates/Completion Date/Key Dates
• planned Completion
• order and timing of operations to Provide the Works
• float
• time risk allowances
• health and safety requirements
• Plant & Materials from Employer
• acceptances
• information from Others
• statements of how the Contractor plans to do the work
identifying principal equipment and resources
Reasons for not accepting a programme
Under clause 31.3 there are only four reasons not to accept a
programme:
• The Contractor’s plans which it shows are not practicable
• It does not show the information which this contract requires
• It does not represent the Contractor’s plans realistically or
• It does not comply with the Works Information
Project Manager has up to two weeks in which to accept or not
accept the programme.
If the Project Manager fails to respond it is a CE under 60.1(6), or if
does not accept for reason stated in contract is a CE under 60.1(9)
Acceptance of a programme by the Project Manager is not a
pre-condition to the Contractor proceeding with the work
24
Revised programme (32)
• Shows
– the actual progress achieved on each operation
and its effect upon the timing of the remaining
work
– implemented compensation events
– how the Contractor plans to deal with any delays
– other changes the Contractor proposes to make
• How frequent?
– on instruction by Project Manager
– when Contractor chooses
– interval stated in Contract Data (32.2)
Initial Programme Sanction
• 50.3 - 25% of PWDD retained if
no 1st accepted programme in
place
Subsequent Programme Sanctions
• 64.1 – Project Manager can make
their own assessment of all
compensation events
Sanctions of non-acceptance
Programme under the ECC is the
“beating heart of the contract”
Compensation Events
Compensation Events
• matters that occur that are not the Contractor’s risk under the
contract (and needn't have priced for)
• for it to be a compensation event it has to comply to a reason
within the contract i.e. clause 60.1
• assessment should always consider both time and cost but may
be neither
• Contractor should include risk for cost and time within their
assessment for risk which has a significant chance of occurring
and is their risk under the contract (63.6)
• 63.1 emphasises that it should be forecast defined cost when
assessing a CE from the point at which the Project Manager
requested/should have requested a quotation – i.e. not simply
actual cost if you have done the work before quote agreed.
30
Clause 60.1 The following are compensation events
(1) the Project Manager gives an instruction changing the Works
Information (except value engineering/accepting a defect)
(2) the Employer does not allow access to and use of part of the
Site by the later of its access date and the date shown on the
Accepted Programme.
(3) the Employer does not provide something which he is to
provide by the date for providing it shown on the Accepted
Programme.
(6) the Project Manager does not reply to a communication
(9) the Project Manager withholds acceptance for a reason not
stated in the contract
(12) unforeseen physical conditions
(13) weather – 1 in 10 year event…
(19) an event stops the Contractor from completing the works…
.
PM Assessment/Reply
(accept/not accept )
Notification of CE – by PM or C 8 Week time bar - for
certain CE’s (61.3)
PM Decision <1 Week
Instruct quote(61.1) Should EW have
been given? (61.5)
C issues quote <3 Week
<2 Week
Deemed acceptance after two
weeks from Contractor
advising no decision received
Deemed acceptance after two
weeks from Contractor
advising no decision received
PM assessment (if required)
Implementation
FINALITY
Unless include PM assumptions
which have been affected Time/cost freeze
Deemed acceptance after two
weeks from Contractor
advising no decision received
<3 Week
PM to state if any
assumptions to be used(61.6)
Can issue proposed
instructions(61.2) or alternative
quotes (62.1)
Quotation
Notification
Assessment
Implementation
CE
PMI
EW could/might affect time, cost, quality
has/will affect time, cost, quality
Contractor
obeys and
proceeds
(27.3)
if a CE
61.1
61.2
62.1
Sources of help/information:
LinkedIn Group:
eLearning Modules
Copyright @ 2011. All rights reserved
Any Questions??

More Related Content

What's hot

NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
Browne Jacobson LLP
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
Association for Project Management
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Project Controls Expo
 
CFW Supply Chain Development
CFW Supply Chain DevelopmentCFW Supply Chain Development
CFW Supply Chain Development
Rae Davies
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
Rae Davies
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
MANNU KUMAR
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
Association for Project Management
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
Association for Project Management
 
types of contracts
 types of contracts types of contracts
types of contracts
KEVINMISTRY8
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
Bhalindra Bath - projects & M&A law
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
Cordell Parvin
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Project Controls Expo
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
Association for Project Management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012Ola Odejayi
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
Gerald R. (Jerry) Genge
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 

What's hot (20)

NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
 
CFW Supply Chain Development
CFW Supply Chain DevelopmentCFW Supply Chain Development
CFW Supply Chain Development
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
types of contracts
 types of contracts types of contracts
types of contracts
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 

Similar to Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Change" By Glenn Hide

NEC3 programme
NEC3 programmeNEC3 programme
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
My own
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
Pankaj K Sinha
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
ManaliChitranshi
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1
Farha Sharmin
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11
cmcgoverntobin
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
Bodenbr
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
Bodenbr
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 

Similar to Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Change" By Glenn Hide (20)

NEC3 programme
NEC3 programmeNEC3 programme
NEC3 programme
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
Project Controls Expo Thursday 10th Nov 2011 - "The Key Role of the NEC Progr...
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
Project Finance Session 02
Project Finance   Session 02Project Finance   Session 02
Project Finance Session 02
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
Project Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
faizulhassanfaiz1670
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
eCommerce Institute
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Access Innovations, Inc.
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 

Recently uploaded (16)

Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 

Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Change" By Glenn Hide

  • 1. Copyright @ 2011. All rights reserved NEC3 Contracts – Managing Risk and Change Project Controls Expo – 18th Nov 2014 Emirates Stadium, London
  • 2. Copyright @ 2011. All rights reserved About the Speaker • Director of BuiltIntelligence • BI provide training, consultancy, resources to the construction industry • Presented at various national conferences • Number of industry published articles on NEC3 and programme management
  • 4. Risk at tender stage takes various forms - Contractor needs to ascertain risk their risks by reading the contract that they are signing up to: • Contract makes it clear what risks are the Employers under the contract • Clause 80.1 Employers risks • clause 60.1 – 19 items that would be compensation events • Additional Employer’s risks identified in contract data part 1 • Z clause amendments could alter risk profile • 2ndry options that have/have not been included • Contract data includes a place to identify risks to be included in the Risk Register, but these do not (and should not) allocate who’s risk they are
  • 5. NEC Risk Register is not same as traditional “risk registers” • often see “risk registers” included within a tender document or signed contract • these (attempt) to allocate “risk”, often contrary to what the contract says. • e.g. state weather is Contractor risk, yet they leave in 60.1(13), or say ground conditions are Contractor risk and yet leave in 60.1(12) • the contract should identify whose risks are whose either by the wording of the contract or by the content of the Works Information
  • 6. • NEC3 Risk Register is different from other traditional risk registers you may have used • Not produced until post contract award • Traditional risk registers included within the contract attempt to allocate risk – which potentially creates ambiguities
  • 8. 8 16.1 Contractor and Project Manager have a duty to notify each other as soon as they become aware of a matter which could –increase the total of the Prices –delay Completion, –delay meeting a Key Date or –impair the performance of the works in use 16.2 potential instruction to attend risk reduction meeting
  • 9. 9 Intent of Risk Reduction meeting is for all those who attend to : • consider if the risk(s) is really likely to happen • if the risk(s) can be avoided altogether or at least minimised • come up with solutions to the problem without worrying/focusing upon about associated liability • deciding actions as to who/when will move the matter(s) forward • Project Manager responsibility to update and re-issue the Risk Register in terms of items closed out, and who’s required to take what action This should be considered a collaborative operational tool, not a commercial tool
  • 10. Risk Register is a defined term: • Risk Register is a register of the risks which are listed in the contract data, and • risks which the Project Manager or Contractor has notified as an early warning matter. • It should include a description of the risk and a description of the action to be taken to avoid or reduce the risk.
  • 11. Example of a Risk Register
  • 12.
  • 14. Clause 31 – The programme 31.2 - Items to be shown on the programme include: • starting date/ access dates/ Completion Date/ Key Dates (sectional completion) • planned Completion ECC Section 3 – Time
  • 15. Start Float Activity A 0w Activity B 0w Activity C 0w Activity D 0w Activity E 0w Activity F 5w Activity G 5w Activity H 5w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14w 4w 3w 3w 3w 3w 3w 4w 5w float
  • 16. Start Float Activity A 0w Activity B 0w Activity C 0w Activity D 0w Activity E 0w Activity F 5w Activity G 5w Activity H 5w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14w 4w 3w 3w 3w 3w 3w 4w CE’s Acceleration
  • 17. Start Float Activity A 0w Activity B 0w Activity C 0w Activity D 0w Activity E 0w Activity F 5w Activity G 5w Activity H 5w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14w 4w 3w 3w 3w 3w 3w 4w ANYTHING
  • 18. Start Float Activity A 0w Activity B 0w Activity C 0w Activity D 0w Activity E 0w Activity F 5w Activity G 5w Activity H 5w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14w 4w 3w 3w 3w 3w 3w 4w
  • 19. Start Float Activity A 0w Activity B -1w Activity C -1w Activity D -1w Activity E -1w Activity F 5w Activity G 4w Activity H 4w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14 5w 3w 4w 3w 3w 3w 4w 1w Accepted Programme
  • 20. Start Float Activity A 0w Activity B 0w Activity C 0w Activity D 0w Activity E 0w Activity F 5w Activity G 5w Activity H 5w planned Completion 0w Completion Date 0w 0 2 4 6 8 10 12 14w 4w 3w 3w 3w 3w 3w 4w
  • 21. Start Float Activity A 1w Activity B 1w Activity C 1w Activity D 1w Activity E 1w Activity F 5w Activity G 6w Activity H 6w planned Completion 1w Completion Date 0w 0 2 4 6 8 10 12 14w 3w 3w 2w 3w 3w 4w 3w 1w Accepted Programme
  • 22. Clause 31 – The programme 31.2 - Items to be shown on the programme include: • starting date/access dates/Completion Date/Key Dates • planned Completion • order and timing of operations to Provide the Works • float • time risk allowances • health and safety requirements • Plant & Materials from Employer • acceptances • information from Others • statements of how the Contractor plans to do the work identifying principal equipment and resources
  • 23. Reasons for not accepting a programme Under clause 31.3 there are only four reasons not to accept a programme: • The Contractor’s plans which it shows are not practicable • It does not show the information which this contract requires • It does not represent the Contractor’s plans realistically or • It does not comply with the Works Information Project Manager has up to two weeks in which to accept or not accept the programme. If the Project Manager fails to respond it is a CE under 60.1(6), or if does not accept for reason stated in contract is a CE under 60.1(9) Acceptance of a programme by the Project Manager is not a pre-condition to the Contractor proceeding with the work
  • 24. 24 Revised programme (32) • Shows – the actual progress achieved on each operation and its effect upon the timing of the remaining work – implemented compensation events – how the Contractor plans to deal with any delays – other changes the Contractor proposes to make • How frequent? – on instruction by Project Manager – when Contractor chooses – interval stated in Contract Data (32.2)
  • 25.
  • 26. Initial Programme Sanction • 50.3 - 25% of PWDD retained if no 1st accepted programme in place Subsequent Programme Sanctions • 64.1 – Project Manager can make their own assessment of all compensation events Sanctions of non-acceptance
  • 27. Programme under the ECC is the “beating heart of the contract”
  • 29. Compensation Events • matters that occur that are not the Contractor’s risk under the contract (and needn't have priced for) • for it to be a compensation event it has to comply to a reason within the contract i.e. clause 60.1 • assessment should always consider both time and cost but may be neither • Contractor should include risk for cost and time within their assessment for risk which has a significant chance of occurring and is their risk under the contract (63.6) • 63.1 emphasises that it should be forecast defined cost when assessing a CE from the point at which the Project Manager requested/should have requested a quotation – i.e. not simply actual cost if you have done the work before quote agreed.
  • 30. 30 Clause 60.1 The following are compensation events (1) the Project Manager gives an instruction changing the Works Information (except value engineering/accepting a defect) (2) the Employer does not allow access to and use of part of the Site by the later of its access date and the date shown on the Accepted Programme. (3) the Employer does not provide something which he is to provide by the date for providing it shown on the Accepted Programme. (6) the Project Manager does not reply to a communication (9) the Project Manager withholds acceptance for a reason not stated in the contract (12) unforeseen physical conditions (13) weather – 1 in 10 year event… (19) an event stops the Contractor from completing the works…
  • 31. . PM Assessment/Reply (accept/not accept ) Notification of CE – by PM or C 8 Week time bar - for certain CE’s (61.3) PM Decision <1 Week Instruct quote(61.1) Should EW have been given? (61.5) C issues quote <3 Week <2 Week Deemed acceptance after two weeks from Contractor advising no decision received Deemed acceptance after two weeks from Contractor advising no decision received PM assessment (if required) Implementation FINALITY Unless include PM assumptions which have been affected Time/cost freeze Deemed acceptance after two weeks from Contractor advising no decision received <3 Week PM to state if any assumptions to be used(61.6) Can issue proposed instructions(61.2) or alternative quotes (62.1)
  • 32. Quotation Notification Assessment Implementation CE PMI EW could/might affect time, cost, quality has/will affect time, cost, quality Contractor obeys and proceeds (27.3) if a CE 61.1 61.2 62.1
  • 33.
  • 36.
  • 38. Copyright @ 2011. All rights reserved Any Questions??