This document summarizes the scope of work for a project to design, supply materials for, erect, test and commission a 220kV transmission line on a turnkey basis. The scope includes overall project management, surveys, fabrication drawings, supplying towers, conductor and other materials, excavation, tower erection, stringing conductor and optical fiber ground wires, testing and commissioning. It describes the technical requirements for the transmission line, towers, conductor, earthwire, insulators and accessories. It also outlines the contractor qualification requirements, bidding process, bid evaluation process and procedures to ensure quality of work.
Design & Engineering is an integral part of the implementation of Solar Projects.
Engineering drawings & documents convey specifications, construction methodology, dimensions, tolerances etc capturing the scope of works and presenting a first-hand idea on the final by product that would be constructed.
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
Simulation of a fatigue crack problem in electronic devicesCADFEM Austria GmbH
Fatigue crack growth under active cycling conditions is simulated using the cohesive zone modeling concept within the framework of the Finite Element Method.
To this end, a cyclic cohesive zone model based on a damage evolution equation is extended onto the case of transient thermal loading conditions and is implemented into ANSYS. The thermal and mechanical interaction of the cohesive surfaces is taken into account for both open and closed crack states. By incorporating the temperature dependence of the cohesive zone model parameters, the model is also extended onto cases of nonisothermal fatigue.
To speed-up fatigue simulations, the cyclic cohesive zone model is equipped with the cycle jump technique based on direct iteration of the damage evolution equation.
The implemented thermomechanical cyclic cohesive zone model is applied to a problem of interfacial debonding between two layers of a power metallization stack subjected to the active thermal cycling.
Gensol Group has won the rights to subsidy by Solar Energy Corporation of India (SECI) for rooftop solar in the states of Gujarat, Maharashtra, Karnataka, Tamil Nadu.
The presentation explains the process to avail the subsidy and its salient features.
Design & Engineering is an integral part of the implementation of Solar Projects.
Engineering drawings & documents convey specifications, construction methodology, dimensions, tolerances etc capturing the scope of works and presenting a first-hand idea on the final by product that would be constructed.
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
Simulation of a fatigue crack problem in electronic devicesCADFEM Austria GmbH
Fatigue crack growth under active cycling conditions is simulated using the cohesive zone modeling concept within the framework of the Finite Element Method.
To this end, a cyclic cohesive zone model based on a damage evolution equation is extended onto the case of transient thermal loading conditions and is implemented into ANSYS. The thermal and mechanical interaction of the cohesive surfaces is taken into account for both open and closed crack states. By incorporating the temperature dependence of the cohesive zone model parameters, the model is also extended onto cases of nonisothermal fatigue.
To speed-up fatigue simulations, the cyclic cohesive zone model is equipped with the cycle jump technique based on direct iteration of the damage evolution equation.
The implemented thermomechanical cyclic cohesive zone model is applied to a problem of interfacial debonding between two layers of a power metallization stack subjected to the active thermal cycling.
Gensol Group has won the rights to subsidy by Solar Energy Corporation of India (SECI) for rooftop solar in the states of Gujarat, Maharashtra, Karnataka, Tamil Nadu.
The presentation explains the process to avail the subsidy and its salient features.
Gensol strives to add value from Project Conceptualisation to Commissioning to ensure timely, quality and cost effective completion. From drafting exhaustive EPC contracts to approving engineering drawings and quality control during construction, Gensol's experience of 1500 MW works to ensure Peace of Mind for the Project Developer.
What services should a solar project developer expect from solar park & how much each service can be valued.
The ppt clears concept on value add by solar park.
Cable stayed bridges of prestressed concrete.Franco Bontempi
Discusses prestressed concrete cable-stayed bridge
structures. Although most cable-stayed bridges
have been of steel construction, a few have been
made of prestressed concrete. This type of structure
is presented on a case-study basis with the
intent of encouraging designers to consider the
feasibility of using this type of structure which
in some instances might be a more appropriate choice.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
Its a detailed Presentation of Transmission Sector & Project Management of Transmission Lines.
The company selected for this was Kalpataru Power Transmission Ltd., Gandhinagar
it explaines how the indian power sector is, what is the tendering process, what is contract, bar-charts and cash flow management for the contract.
Project planning can be understood with help of a case Study, and Project Management from tendering to cash flow management can be understood by this presentation.
this is the Summer Internship Project of Mine and its Strictly unauthorised to use this presentation without author's permission.
Gensol strives to add value from Project Conceptualisation to Commissioning to ensure timely, quality and cost effective completion. From drafting exhaustive EPC contracts to approving engineering drawings and quality control during construction, Gensol's experience of 1500 MW works to ensure Peace of Mind for the Project Developer.
What services should a solar project developer expect from solar park & how much each service can be valued.
The ppt clears concept on value add by solar park.
Cable stayed bridges of prestressed concrete.Franco Bontempi
Discusses prestressed concrete cable-stayed bridge
structures. Although most cable-stayed bridges
have been of steel construction, a few have been
made of prestressed concrete. This type of structure
is presented on a case-study basis with the
intent of encouraging designers to consider the
feasibility of using this type of structure which
in some instances might be a more appropriate choice.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
Its a detailed Presentation of Transmission Sector & Project Management of Transmission Lines.
The company selected for this was Kalpataru Power Transmission Ltd., Gandhinagar
it explaines how the indian power sector is, what is the tendering process, what is contract, bar-charts and cash flow management for the contract.
Project planning can be understood with help of a case Study, and Project Management from tendering to cash flow management can be understood by this presentation.
this is the Summer Internship Project of Mine and its Strictly unauthorised to use this presentation without author's permission.
Complete details of EHV Transmission Line. Consolidated this presentation from those experts who had contributed separately on slider share and other web pages.Thanks for their valuable inputs.
Concept of energy transmission & distribution ZunAib Ali
Downlaod is NOW Allowed (08/06/2016)
for more help: email me at zunaib_91@yahoo.com
Purpose of Electrical Transmission System
Main Parts of Power System
One-Line Diagram of Generating Station
Main Parts of Generating Station
Components of a Transmission Line
Quality Control & Quality Assurance of MS pipelineIEI GSC
This presentation re. QC & QA of M S pipelines was made at Gujarat State Centre of the Institution of Engineers (India) at Ahmedabad by Er. Manoj Raghavan of SGS (India) Ltd.
We provide basic and detailed engineering services for gas and oil projects.
Our team is made up of professionals with wide experience in the design of solutions for pipework projects and installations for the processing, treatment, transport and distribution of natural gas.
We provide basic and detailed engineering services for gas and oil projects.
Our team is made up of professionals with wide experience in the design of solutions for pipework projects and installations for the processing, treatment, transport and distribution of natural gas.
We provide basic and detailed engineering services for gas and oil projects.
Our team is made up of professionals with wide experience in the design of solutions for pipework projects and installations for the processing, treatment, transport and distribution of natural gas.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
The Indian economy is classified into different sectors to simplify the analysis and understanding of economic activities. For Class 10, it's essential to grasp the sectors of the Indian economy, understand their characteristics, and recognize their importance. This guide will provide detailed notes on the Sectors of the Indian Economy Class 10, using specific long-tail keywords to enhance comprehension.
For more information, visit-www.vavaclasses.com
How to Create Map Views in the Odoo 17 ERPCeline George
The map views are useful for providing a geographical representation of data. They allow users to visualize and analyze the data in a more intuitive manner.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
What is the purpose of the Sabbath Law in the Torah. It is interesting to compare how the context of the law shifts from Exodus to Deuteronomy. Who gets to rest, and why?
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdfTechSoup
In this webinar you will learn how your organization can access TechSoup's wide variety of product discount and donation programs. From hardware to software, we'll give you a tour of the tools available to help your nonprofit with productivity, collaboration, financial management, donor tracking, security, and more.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
This is a presentation by Dada Robert in a Your Skill Boost masterclass organised by the Excellence Foundation for South Sudan (EFSS) on Saturday, the 25th and Sunday, the 26th of May 2024.
He discussed the concept of quality improvement, emphasizing its applicability to various aspects of life, including personal, project, and program improvements. He defined quality as doing the right thing at the right time in the right way to achieve the best possible results and discussed the concept of the "gap" between what we know and what we do, and how this gap represents the areas we need to improve. He explained the scientific approach to quality improvement, which involves systematic performance analysis, testing and learning, and implementing change ideas. He also highlighted the importance of client focus and a team approach to quality improvement.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
Ethnobotany and Ethnopharmacology:
Ethnobotany in herbal drug evaluation,
Impact of Ethnobotany in traditional medicine,
New development in herbals,
Bio-prospecting tools for drug discovery,
Role of Ethnopharmacology in drug evaluation,
Reverse Pharmacology.
The French Revolution, which began in 1789, was a period of radical social and political upheaval in France. It marked the decline of absolute monarchies, the rise of secular and democratic republics, and the eventual rise of Napoleon Bonaparte. This revolutionary period is crucial in understanding the transition from feudalism to modernity in Europe.
For more information, visit-www.vavaclasses.com
The French Revolution Class 9 Study Material pdf free download
61131730 transmission-line-case-study
1. Project Management
S.Rajagopalan
PGXPM VI Term-IV
1
PROJECT DESCRIPTION – Design, Supply of Materials, Erection including Civil Works, Testing
& Commissioning of 220 kV Transmission Line on Total Turnkey basis.
SCOPE OF WORK:
The salient features of the Scope include, but not limited to, the following:
a) Overall Project Management, Coordination.
b) Conducting of detailed survey, & Check Survey.
c) Preparation of fabrication drawings and shop drawings, fabrication and supply of towers
as per Standard Drawing and Bill of Materials.
d) Supply of Conductor, Ground Wire, Conductor accessories, earthing sets, Number
plates, Phase plates, Danger boards and all other materials required for completeness of
the line.
e) Excavation, casting of tower foundation, stub setting, erection of complete towers with
extensions and fixing of all accessories, hoisting of insulators, stringing of conductor and
ground wire, fixing of line hardware including all Civil and Structural works as per
specification.
f) All statutory clearance, wherever required shall be arranged by the owner. The Bidder
should clear any way leave problems, but the owner shall extend all help/co-operation
in this regard.
Techno Commercial Documents -
The Techno- Commercial Bid consists of following:
i) Techno - Commercial Sheets
ii) Data Requirement Sheets.
General
The transmission lines shall be designed and constructed meeting the requirements
mentioned in these regulations, requirements of applicable Indian Standards as well as
other rules & regulations as per latest amendments. The Contractor shall follow all the
prudent utility practices in the design and construction of the transmission lines. Also, the
design and construction of the transmission lines shall be such that they perform their
intended functions under the License.
Conductor
The conductor of appropriate size shall be selected considering power flow requirements
and other system considerations in consultation with neighboring transmission and
generation utilities. It shall be so selected so as to ensure satisfactory performance of
transmission lines from corona and interference aspects.
2. Project Management
S.Rajagopalan
PGXPM VI Term-IV
2
The conductors may be of type ACSR, AAAC or other and shall generally conform to
relevant IS or IEC standards. Other new technology conductors conforming to International
standards and specifications may also be used depending on system requirements.
Earthwire
The earthwire of appropriate size to cater to predicted and design fault currents and
lightning shall be used. The earthwire shall be either of galvanized stranded steel (GSS) or
alternatively ACSR or AACSR conductor type. Optical fiber ground wires may also be used as
earthwire. Other new technology earthwires conforming to international standards and
specifications may also be used. Generally, one earthwire shall be used for transmission
lines up to 220 kV.
Towers
The towers shall be self-supporting lattice steel type and shall be a fully galvanized
structure. The standard drawings for the Towers are available with the owner & the
Contractor shall supply the towers as per the standard drawings. The Type of towers, design
and ruling span, wind & weight spans, extension and truncation provisions, Live-metal
clearances, mid-span clearance, shielding angle etc. shall be decided as per prudent utility
practices following applicable standards and codes and keeping in view electrical system
parameters and requirements, line altitude and other service conditions and factors.
Ground clearance shall be as per requirements of Central Electricity Authority (Measures
relating to Safety and Electricity Supply) Regulations as and when these are notified by the
Authority.
The loads at conductor and earthwire points under different loading conditions viz.
reliability conditions (normal condition), security conditions (broken wire condition), safety
conditions, anti-cascading condition etc. (as per relevant IS or IEC Standards) considering
various combinations of design temperatures, wind and snow loads shall be calculated
accordingly.
Tower Materials
Mild steel and high tensile steel sections of tested quality in conformity with relevant IS
shall be generally used in towers and their extensions. Other equivalent grade of
structural steel angle sections and plates conforming to International Standards may also
be used.
Fasteners, bolts and nuts shall be generally as per relevant IS.
3. Project Management
S.Rajagopalan
PGXPM VI Term-IV
3
Tower fabrication
Tower fabrication shall generally conform to relevant IS. Tower parts shall be galvanized
as per relevant IS.
(iv) Tower accessories
Various tower accessories viz. danger plates, number plates, phase plates, circuit plates,
anti-climbing devices, bird guards etc. shall be provided conforming to relevant IS.
Remedial measures shall be taken by the Owner to put spike type Bird guards on the
Upper (tie members), Lower main members and also on Plan bracings in the barrel of the
tower at all the cross arm levels to prevent birds from making nests. This measure will
also help to improve the performance and availability of the system.
Earthing
Each tower shall be earthed such that tower footing resistance does not exceed 10 ohms.
Pipe type or Counterpoise type earthing shall be provided in accordance with relevant IS.
Aviation requirements and warning signals
Day and/or night visual aids and markers for denoting transmission line or structures as
per requirements of Directorate of Flight Safety or relevant IS or ICAO shall be provided.
Insulators, Insulator Strings and Hardware Fittings
Requisite type of suspension and tension insulator strings with disc insulators or long rod
insulators offering equivalent performance shall be used. The Drawings for the Insulators
shall be provided by the owner. Number of insulators and creepage distance shall be
selected based on electrical system parameters and requirements taking into account
other factors and conditions viz. line altitude, expected environmental and pollution
conditions etc. However, for critical locations with high pollution level, antifog type
insulators or polymer insulators may be used for better performance.
Insulators shall generally conform to relevant IS or IEC standards. Polymer or composite
insulators conforming to relevant IEC or other international standards may also be used.
Insulator strings shall be complete with all required hardware fittings. The fittings shall
generally conform to relevant IS.
Accessories for Conductor and Earthwire
The accessories required for the conductor and earthwire viz. mid-span compression
joints, repair sleeve, T-connector, flexible copper bond, vibration dampers, spacer or
4. Project Management
S.Rajagopalan
PGXPM VI Term-IV
4
spacer-dampers, earthwire clamps etc. shall be used as suitable for type and size of
conductor and earthwire used for the transmission line. The accessories shall generally
conform to relevant IS.
Quality Assurance
The Quality Management System to be followed should be built around a philosophy of
"prevention" rather "detection and cure". The quality Management system is time tested
and may have an ISO-9001 certification. The Various Steps involved in the Quality System
Management are given below:
Inclusion of Quality Requirement in the Contract.
Selection of good quality vendors/sub vendors.
Approval of unambiguous Manufacturing Quality Plan (MQP)
Finalization of Field Quality Plan (FQP)
Ensuring regular, timely and consistent inspection at various stages, viz. Raw material,
during in- process stage and final inspection and testing prior to dispatch.
Implementation of Quality Systems and Procedures as per ISO – 9001.
System of Vendor and Sub Vendor Approvals
The list of approved sub vendors is maintained for all the sub vendors irrespective of the
fact whether the Technical Qualifying Requirements are specified in the contract or not.
The contractors can choose any sub vendor from the list possessing a large number of sub
vendors to choose from, with full transparency. The list is continuously revised based on
the feedback obtained from the inspection reports, surveillance audits and failure reports,
etc.
Manufacturing Quality Plan
A standard format is developed for the approval of Manufacturing Quality Plan (MQP)
which includes the quality requirements at the raw material stage, in process testing and
final inspection and testing requirements as per Technical specifications of the contract,
National and International Standards and Manufacturer’s internal plant standards and well
known good engineering practices of the industry. This document has to be self-sufficient
and it should include sample size, acceptance norms, place of testing, requirements of test
reports and hold point beyond which the work can progress only after clearance from the
owner. By standardizing the various testing requirements and procedures it is to be
ensured that it is not biased towards any particular manufacturer. These MQP(s) may be
approved for a period of three years instead of approval on contract-to-contract basis; this
alone could reduce the project execution time substantially by eliminating the
requirements of submission of MQP, discussions and approval for each contract.
5. Project Management
S.Rajagopalan
PGXPM VI Term-IV
5
Inspection
Customer Inspection Points (CIP) are identified in MQPs to be carried out at various stages
such as raw material stage, in-process stage and final stage. A certificate known as CIP is to
be issued at each stage; if the material/product/Sub System meets the various
requirements specified in the specification, Standards, Approved data sheets/Drawings etc.
In other words issuance of CIP certifies the various routine checks and technical features.
However it does not certify the various contractual obligations, which are necessary for
release of payment. Material Inspection and Clearance Certificate (MICC) is to be issued for
all billable items as per contract after all the CIP stages, type tests, Bill of Quantities and
other requirement are checked by the inspection engineer. Issuance of MICC does not
require any inspection of the equipment but it requires checking of other contractual
documents. It is a responsible job as it enables dispatch and payment to the contractor.
Inspection is most critical and important activity in the quality system
Field Quality Plan
Field Quality Plans (FQP) should be followed for various construction activities at site like
Survey, Civil Construction, Tower Erection, Insulator Hoisting, and Stringing & Earthing. The
FQP(s) describe the various stages for checks and testing requirements at each stage. The
FQP defines the requirement with regard to proper unloading/receipt of equipment and
material at site, storage, testing requirements of erection material, sampling and
acceptance norms, test report requirements, pre commissioning checks. The responsibility
of implementation FQPs is with the site organizations, which are ensuring its
implementation through Project Managers responsible for construction.
Qualifying Requirements -
The eligibility criterion for the bidder is so designed that only those companies which
possess minimum technical & commercial capability are allowed to bid so as to ensure that
the project is executed without any technical or financial problem.
The Qualifying Requirement of the Bidders consists of two requirements
i. Technical - This criterion defines the minimum technical experience which the
prospective bidder should posses to participate in the bid. This is defined in terms
of the minimum of projects of similar nature which has been successfully
completed & is in commercial operation for a minimum period of at least two
years.
ii. Financial - This defines the financial capability which the prospective bidder
should possess so as to enable him to execute the project successfully without
6. Project Management
S.Rajagopalan
PGXPM VI Term-IV
6
having to face financial problem during the execution of the projects. This is
defined in terms of the net worth & the turnover of the prospective bidder of the
past three years.
7. Project Management
S.Rajagopalan
PGXPM VI Term-IV
7
Bidding System - Once the Technical Specifications are finalized & the necessary approvals
are in place for the bid, the next step is initiation the process for inviting bids.
For such bids first the number of packages are decided which can be either one for the
entire scope or split the numbers into two three etc. one for Conductors supplies one for
insulators & the one for the balance supplies & turnkey execution of the project. In the
instant case the entire scope is defined as one package.
For such type of tenders Single Stage one envelope or single stage two envelope process is
adopted.
The following Bid documents for the bid are prepared
VOLUME- I COMMERCIAL REQUIREMENTS
Section – I Invitation for Bids - IFB
Section – II Instruction to Bidders - ITB
Section – III General Terms and Conditions
of the Contract - GCC
Section – IV Erection Conditions of Contract - ECC
Section – V Special Conditions of Contract - SCC
Section – VI ANNEXURE - ANNEX
VOLUME-II TECHNICAL REQUIREMENTS
VOLUME- III BID PROPOSAL SHEETS
The bidders are to submit their bids based on the above documents in two sections as below.
Section – I TECHNO COMMERCIAL SHEETS
Section – II PRICE SHEETS
The documents are prepared on the following basis
1. Define the pre qualifications of the eligible parties based on the project complexity,
the prospective bidders’ past experience, financial & technical capabilities required
for faithful execution of the project.
2. Modalities of bidding i.e. International Competitive Bid or Domestic Bid.
3. Bid Validity Period - Based on the anticipated time required for evaluation &
placement of orders, the Bidders are advised to submit their offers valid for a
specific period.
8. Project Management
S.Rajagopalan
PGXPM VI Term-IV
8
4. Payment terms are so made that the materials are sequentially supplied to the
project as per the project needs. The payments for supplies are staggered so as
ensure commercial interest of the Parties at the same time ensure that their
financial needs in execution of the project is taken care of.
5. The Bidders shall be given access to the prospective Project sites to familiarize
themselves with the site conditions.
6. Suitable time is also given to the bidders to go through the documents & seek
clarifications or deviations which they propose. Once all the comments are received
then clarifications are issued to all the parties to establish a level playing field. If
required a pre bid meeting is also arranged.
PREFERENCE TO DOMESTIC BIDDERS –
In single responsibility turnkey, a margin of preference shall be applied to the domestically
manufactured goods in accordance with the following provisions:
(a) The margin of preference shall not be applied to the whole package but only to the
domestically manufactured goods within the package
(b) Goods offered from outside the territory of the Borrower shall be quoted CIF and goods
offered domestically shall be offered ex-factory or ex-works (free of sales and similar taxes)
(c) All other cost components, such as design as well as works, installation and supervision,
shall be quoted separately
(d) In the comparison of bids only the CIF price in each bid of the goods offered from
outside the territory of the Borrower shall be increased by the applicable duty and other
taxes payable by a non exempt importer or by 15 percent, whichever is less
9. Project Management
S.Rajagopalan
PGXPM VI Term-IV
9
(e) If duties vary from item to item within a package, the appropriate tariff for each item
shall apply
(f) No margin of preference shall be applied to any associated services or works included in
the package
(g) Bidders will not be permitted or required to modify the mix of domestic and foreign
goods after bid opening.
Bidders applying for the preference shall provide evidence necessary to establish the
eligibility of a bid for the preference.
The bidding documents shall clearly indicate the preference to be granted, the information
required to establish the eligibility of a bid for the preference claimed, and the procedures
to be followed in the comparison of bids, all as set forth above.
BID EVALUATION -
The bid is evaluated in four stages
Stage 1 - In stage 1, the basic data & the record of the bid opening & the preliminary
completeness of the bid is prepared.
Stage 2 - In stage 2, the detailed examination of the bid is done to evaluate the substantial
responsiveness of bid. The substantial responsiveness is done for commercial terms &
conditions as well as technical requirements. Various points like major deviations, on
commercial terms, execution period, non availability of signatures by authorized personnel,
submission of bid security, conditional bids, deviations technical parameters, type test
reports etc. are examined to eliminate bidders who are substantially unresponsive.
Stage 3 - In Stage 3 detailed evaluation of all substantive responsive bids are done on
Commercial & Technical Terms.
a. The Commercial Terms list all the important commercial conditions specified in the
bidding documents such as the bid security amount and validity period, terms of
payment, liquidated damages etc., and list any deviations from requirements of the
bidding documents. Further, it should be stated whether a financial adjustment to
the bid is considered necessary as a consequence of any minor deviation.
b. The Technical Requirements sets out the scope of supply, delivery or work schedule,
the important technical specifications of all major items of equipment and material
and warranty period. Every bid being evaluated should then be scrutinized in detail
and its salient features entered into the table against the listed items of the bidding
documents. As in the detailed evaluation of commercial terms, any substantial
deviations from the technical requirements of the bidding documents should be
10. Project Management
S.Rajagopalan
PGXPM VI Term-IV
10
listed and it should be determined whether a financial adjustment to the bid is
necessary or the bid should be rejected as nonresponsive.
c.
Financial Adjustment of Bid Prices (Commercial Aspects) Bid price comparison is the
final and most critical step in due bid evaluation process.
The bid prices are adjusted for the purpose of bid comparison for those deviations
which are permissible and which can be "translated" fairly into monetary values in
the manner specified in the bidding documents.
All the adjustment factors and the basis of price comparison specified in the bidding
documents must be taken into account. Factors not listed in the bidding documents
shall not be introduced during the bid evaluation.
As a standard practice bids deviating in the terms of payment or Delivery schedule
are not accepted. Any bidder offering such deviation is asked to withdraw such
deviations failing which they are considered substantially non responsive & rejected.
Financial Adjustment of Bid Prices (Technical Aspects)
Major deviations from the technical requirements which will result in the rejection of
bids are discussed in Stage 2 of this Evaluation Procedure. Other deviations,
classified as minor or non substantive, which will not have any effect on price or
quality of the goods and services offered, can be accepted for evaluation purposes
without a price adjustment. Other deviations, which will affect the cost, should be
expressed in monetary terms and added to the bid price for purposes of evaluation.
All cost adjustments should be made by without any consultations with the bidder
regarding the justification for the amount of the adjustment.
Adjustment for Completeness in Scope of Supply
The cost of minor omissions or missing items in the scope of supply, services, etc.
should be added to the bid price to allow for bid comparison on an equal basis. The
price adjustment should be based on a reasonable estimate of the cost by the
Owner, taking into consideration the corresponding quoted prices from other
conforming bids. The price adjustment should be based on the fair price of the
omitted item. In the event of uncertainty, the average quoted price by the other
responsive bidders may be used.
Adjustment for Technical Compliance
Similarly, a minor deficiency in technical compliance should not be a cause for
rejection of the bid.
11. Project Management
S.Rajagopalan
PGXPM VI Term-IV
11
STAGE 4: DETERMINATION OF THE LOWEST EVALUATED SUBSTANTIALLY RESPONSIVE BID
After going through the above stages, the lowest evaluated substantially responsive bid
shall be determined in accordance with the provisions of the bidding documents. As a final
step prior to award, the Owner should always ensure that the bidder whose bid has been
evaluated as the lowest evaluated substantially responsive bid has the financial and
technical capability to execute the contract satisfactorily. If this is determined as positive,
the contract shall be awarded to the bidder which submitted the lowest evaluated
substantially responsive bid.
ADB Guiding Principles –
The Bid Evaluation Report should include such information and documentation to establish
to the satisfaction of the ADB that principles pursuant to the Loan Agreement and the
Procurement Guidelines are satisfied in the bidding and bid evaluation process, and the
proposed award of contract. These principles are as follows:
(i) goods, services and works are sourced from the eligible member countries of
the ADB
(ii) the transparency of the bidding process has provided adequate, fair and equal
opportunity to manufacturers, suppliers and contractors from all the eligible
member countries of the ADB and
(iii) The principle of economy and efficiency has been applied in the bidding and
in the bid evaluation process by establishing the lowest evaluated
substantially responsive bid.
The information and documentation to be submitted as part of, or with, the Evaluation
Report should include the following:
a) Basic Data Sheet
b) A photocopy of the Invitation for Bids advertised in an English language local
newspaper of wide circulation and evidence of copies of the Invitation for Bids
transmitted to designated addresses of the ADB's member countries
c) The Record of Bid Opening including the attendance sheet of the representatives of
bidders
d) Tables of Bidders and Bid Prices including discounts offered as submitted and as
corrected for arithmetical errors; if substantial arithmetical error corrections are
involved, evidence that corrections for arithmetical errors have been accepted by
the bidders concerned
e) Table of Substantive Responsiveness showing the bidders' compliance with major
commercial terms and conditions
12. Project Management
S.Rajagopalan
PGXPM VI Term-IV
12
f) Table of Detailed Evaluation of Bids with respect to salient commercial features of
the bids, showing for each bid the adjustments made to the bid prices for deviations
with references to the clauses in the bidding documents on which they are based,
and indicating the methods used in computing the adjustments
g) Table of Detailed Evaluation of Bids with respect to salient technical features of the
bids, showing for each bid the adjustments made to the bid prices for deviations
with references to the clauses in the bidding documents on which they are based,
and indicating the methods used in computing the adjustments
h) Table of Bid Price Comparison showing all bids selected for detailed evaluation, the
bid price as opened, discounts if any, the arithmetically corrected bid prices, the
financial adjustments for commercial terms and conditions, the financial
adjustments for technical requirements to obtain the total evaluated prices for all
bids concerned
i) Records of discussions and/or copies of correspondence with bidders relating to
clarifications of their bids
j) Recommendation for award of contract
The evaluation report should include a narrative section in which information not suitable
for presentation in the form of tables is presented, together with any supplementary
explanations and information necessary for a complete understanding of all the factors
considered during bid evaluation. Particularly, the reasons for rejection of bids which are
considered non-responsive to the bidding documents should be fully explained and
justified in the narrative section. Similarly, the basis for adjustments in the bid prices
should be adequately explained and, where appropriate, cross references made to the
relevant provisions in the bidding documents. Finally, there must be a clear statement
setting out fully the rationale for the recommendation for contract award.
The recommended amount for award of contract should be the bid price submitted by
the bidder as corrected for arithmetical errors plus the additional amount to make good
any deficiencies in the scope of supply or technical compliance. In agreeing with the
successful bidder to make good any minor deviations in the contract price for scope of
supply or technical compliance, the Owner should note the following.
The cost of making good the minor deviations should be included in the contract price
The final amount agreed between the Owner and the successful bidder should not exceed
the bid price (as corrected for arithmetical errors plus the amount to make good any
13. Project Management
S.Rajagopalan
PGXPM VI Term-IV
13
minor deviations in the scope of supply and technical compliance) of the second lowest
evaluated substantially responsive bidder.
The bid evaluation report and recommendation for contract award should be sent to the
ADB as early as possible. In any event, no later than 30 days prior to expiration of bid
validity, the ADB should be furnished with three copies of the complete bid evaluation
report together with a covering letter. This is necessary to enable the ADB to review
thoroughly the report and recommendation in order to obtain the necessary formal
approval within the ADB for transmission to the Owner.
Utilization of knowledge available with the bidders- It is possible that some bidder may
offer solutions which could be better than the one proposed by the owner. In such case if a
better technical solution is anticipated then it is better to go for Two Stage Bidding Process.
In the Two-Stage bidding procedure, the bidders first of all submit their technical proposals,
in accordance with the specifications, but without prices. The technical proposals are
opened at the date and time advised in the bidding documents. The technical proposals are
evaluated by the Owner and discussed with the bidders. Any deficiencies, extraneous
provisions and unsatisfactory technical features are pointed out to the bidders whose
comments are carefully evaluated the bidders are allowed to revise or adjust their technical
proposals to meet the requirements of the Owner. The objective of the exercise is to
ensure that all technical proposals conform to the same acceptable technical standard and
meet the technical requirements of the Owner Bids of bidders who are unable or not
prepared to amend their technical bids so as to conform to the technical standard required
by the Owner may be rejected, as deficient bids. After the evaluation of technical proposals
has been approved, the second stage is to invite bidders to submit revised technical
proposals and to submit price proposals based on the Bid Evaluation Procedure revised and
agreed upon technical proposals. The price proposals and revised technical proposals are
opened in public at a date and time advised by the Owner. In setting the date, the Owner
should allow sufficient time for bidders to prepare price proposals and incorporate the
changes required in the technical proposals. The price proposals and revised technical
proposals are evaluated and, the award of contract is made to the lowest evaluated
substantially responsive bidder.
Ambiguities -
As far as possible all ambiguities should be cleared & clarified at pre bid stage itself so as to
maintain fairness & transparency. However if any ambiguity is still existing in bidding stage
the same should be removed at techno commercial stage before price opening.
PREBID STAGE-
14. Project Management
S.Rajagopalan
PGXPM VI Term-IV
14
The following steps are taken to ensure a level playing field & all the ambiguities are
addressed & evaluation done in a fair manner.
Suitable time is also given to the bidders to go through the documents & seek clarifications
or deviations which they propose. Once all the comments are received then clarifications
are issued to all the parties to establish a level playing field. If required a pre bid meeting is
also arranged wherein all such issues are addressed.
All data required for the purpose of bidding like the topography, climate conditions & other
information are provided to the bidders.
The Bidders shall be given access to the prospective Project sites to familiarize themselves
with the site conditions.
POST BID STAGE -
Even after addressing all possible ambiguities at pre bid stage, if some issues crop up at
post bid stage, every effort is made to resolve it prior to opening the price bid. Minor issues
which do not materially affect the bid in substance or price can be accepted. All such
clarifications are properly documented & recorded.
Deviation in Bidder’s Proposal - In case if a bidder has submitted which is otherwise good
by deviates from some specification then the following methodology is adopted
In case of major deviations, on commercial terms, execution period, non availability of
signatures by authorized personnel, submission of bid security, conditional bids, deviations
in major technical parameters, type test reports etc. are not acceptable & the bids are
rejected. However in case of any minor deviations the same is examined in detail & the bid
prices are adjusted for the purpose of bid comparison for those deviations which are
permissible and which can be "translated" fairly into monetary values in the manner
specified in the bidding documents. All the adjustment factors and the basis of price
comparison specified in the bidding documents must be taken into account. Factors not
listed in the bidding documents shall not be introduced during the bid evaluation. As a
standard practice bids deviating in the terms of payment or Delivery schedule are not
accepted. Any bidder offering such deviation is asked to withdraw such deviations failing
which they are considered substantially non responsive & rejected. The cost of minor
omissions or missing items in the scope of supply, services, etc. should be added to the bid
price to allow for bid comparison on an equal basis. The price adjustment should be based
on a reasonable estimate of the cost by the Owner, consultant or bid evaluation
committee, taking into consideration the corresponding quoted prices from other
conforming bids. The price adjustment should be based on the fair price of the omitted
item. In the event of uncertainty, the average quoted price by the other responsive bidders
may be used.