PROJECT MANAGEMENT AND
NETWORK MODEL
The procedure of determining the critical path
 Step 1. List all activities and then draw arrow (network) diagram.
 Step2. Indicate the normal time (tij) for each activity ( i,j) above the
arrow which is deterministic.
 Step 3. Calculate the earliest start, the earliest finish, the latest finish
and latest start times for each event.
 Step 4. Indicate the various times computed above on the arrow
diagram.
 Step 5. Determine the total float for each activity by taking the
difference between the earliest start and the latest start time.
 Step 6. Identify the critical activities and connect them by double line
arrows.
 Step 7. Calculate the project duration.
CONT’D
Example:
 A small maintenance project consists of the following jobs
whose precedence relationship is given below.
Required:
A. Draw an arrow diagram representing the project.
B. Find the total float for each activity.
C. Find the critical path and the total project duration
Jobs 1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7
Duration (
days)
15 15 3 5 8 12 1 14 3 14
SOLUTION
A. THE NETWORK DIAGRAM THAT REPRESENTS THE PROJECT IS AS FOLLOWS
CONT’D
 The paths of the network are:
 Path: 1 – 2 –5 -6 -7=>37days
 Path: 1 – 2 – 3– 4 – 5 – 6– 7 =>44days
 Path: 1 – 2 – 3– 4 – 6– 7 =>54days- Critical Path Length
 Path: 1 – 3– 4– 5 – 6 – 7 =>41days
 Path: 1 – 3– 4 – 6 – 7 =>51days
 Path: 1 – 3–6 – 7 =>41days
B. The total float for each activity
 To determine the total float first the earliest start and finish; late
start and finish should be computed.
 This calls for the forward pass and backward pass computation.
CONT’D
 Forward pass calculation
 Finding ES and EF times involves a “forward pass” through the
network.
 The method associated with finding ES and EF is called
forward pass method.
 ES: the earliest time the activity can start, assuming all
preceding activities start as early as possible.
 EF: The earliest time the activity can finish.
EF = ES + t
 Esj is given by:
 ESj= Max (ESj, ti-j)
 Where Esi is the earliest time and tij is the normal time for the
activity (i,j).
 ES1=0
 ES2= ES1 + t1-5= 0 + 15=15
 ES3= Max (ES 2 + t2-3, Es1 + 13)
 = Max (15 +3, 0+15) = 18
 ES4= ES3+ t34 = 18+8 = 26
 ES5 = Max (ES2 + 25, ES4 + t4-5)
 = Max (15 +5, 26+1) = 27
 ES6 = Max (ES3+t3-6, ES4+ t4-6, ES5+t5-6)
 = Max (18+12, 26+24, 27+3)
 = 40
 ES7 = ES6 + t6-7 = 40 +14 = 54
CONT’D
 Backward pass Calculation
 Finding LS and LF times involves a “backward pass” through
the network.
 The method of computing LS and LF is called backward pass
method.
 LS, the latest time the activity can start and not delay the
project.
 LF, the latest time the activity can finish and not delay the
project
 Computation of the latest starting and finishing times is aided
by the use two rules.
 LS = LF -t
 The latest starting (LS) time for each activity is equal to its
latest finishing (LF) time minus its expected duration
CONT’D
 2.For nodes with one leaving arrows: LF for arrows
entering that node equals the LS of the leaving arrow.
 For nodes with multiple leaving arrows: LF for arrows
entering that node equals the smallest LS of leaving
arrows.
 LFi is given by:
 LFi = Min ( LFj-ti-j) where LFj is the latest finish time for the
event j.
 LF7 = 54
 LF6= LF7 = t6-7 = 54-14 = 40
 LF5= LS6-t5-6= 40-3 = 37
 LF4 = Min (LS5-t4-5, LS6-t4-6)
 = Min (37-1, 40-14) = 26

 LF3 = Min (LF4-t3-4, LF6-t3-5)
 = Min (26-8, 40-12) = 18
 LF2 = Min (LF5 - t2-5, LF3-t2-3)
 = Min (37-5, 18-3) = 15
 LF1 = Min (LF3-t1-3, LF2-t1-2)
 = Min (18-15, 15-15)=0
 The following table gives the summarized calculation for
critical path and total float.
CONT’D
Activity
Normal
time
Earliest Latest
Total float LFj-
ESj or LFi-ESi
Start Finisgh Start Finish
ESi ESj LSi LFj
1-2 15 0 15 0 15 0
1-3 15 0 15 3 18 3
2-3 3 15 18 15 18 0
2-5 5 15 20 32 37 17
3-4 8 18 26 18 26 0
3-6 12 18 30 28 40 10
4-5 1 26 40 26 40 0
5-6 3 27 30 37 40 10
6-7 14 40 54 40 54 0
CONT’D
c)The Critical Path
 From the above table we observe that the activities 1-2, 2-
3, 3-4, 4-6, 6-7 are the critical activities.
 The critical path is given by, 1-2-3-4-6-7
 The total project completion time (duration)is given by 54
days.
Project Evaluation and Review Technique (PERT)
 PERT is a time-oriented technique designated to cater for
projects where it is not possible to estimate the exact
duration of the activity.
 It uses statistical theory to estimate how long a project is
likely to last, and the probability of completing the project
by a particular date.
 It helps to address situations which require a probabilistic
approach
CONT’D
 The probabilistic approach involves three times estimates
for each activity instead of one:
 1) Optimistic time: - The length of time required under
optimum conditions.
 It is represented be type represented by the letter “a”.
 2) Pessimistic time: - The amount of time that will be
required under the worst conditions.
 It is represented by the letter “b”.
 3) Most – likely time: - the most probable amount of time
required.
 It is represented by the letter “m”.
CONT’D
The β– distribution is commonly used to describe the inherent variability in time estimates.
te
m b
a
0
Activity
start
Optimistic
time Most-likelytime
(Mode)
Pessimistic time
CONT’D
 β – Distribution can be symmetrical or skewed to either
the right or left according to the nature of the activity.
 The mean and variance of the β-distribution can be found
from the three time estimates.
 β – Distribution is unimodal with a high concentration of
probability surrounding the most-likely time estimate.
 The important issue in network analysis is the average of
expected time for each activity, te, and the variance of
each activity time,δ_i^2.
CONT’D

CONT’D

CONT’D
Activity Optimistic
time
Most likely
time
Pessimistic
time
1-2 3 5 7
2-3 4 8 12
3-4 2 4 6
3-5 3 6 9
3-6 3 6 9
4-5 2 4 6
4-6 1 3 6
5-6 2 5 8
6-7 2 5 14
7-8 4 7 10
CONT’D
 Given the above information, compute the following:
A. Find the expected duration and variance of each
activity
B. Find the expected duration of the project.
C. Calculate the variance and standard deviation of
project length and what is the probability that the
project will be completed:
i.at least 4 days earlier than expected?
ii.no more than 4 days later than expected?
C. If the project due date is 41 days what is the probability
of meeting the due date.
Solution for a) and b)
Paths Activity to tm tp
Ze
To+4tm+
tp
6
Expected
path
length
(E the
path)
S2
1-2-3-5-
6-7-8
1-2 3 5 7 5 37 4/9
2-3 4 8 12 8 16/9
3-5 3 6 9 6 1
5-6 2 5 8 5 1
6-7 2 5 14 6 4
7-8 4 7 10 7 1
1-2-3-4-
5-6-7-8
1-2 3 5 7 5 39
Critical
path
4/9
2-3 4 8 12 8 16/9
3-4 2 4 6 4 4/9
4-5 2 4 6 4 4/9
5-6 2 5 8 5 1
CONT’D
Path Activity (
2
path)  Path
1-2-3-5-6-7-8 1-2
83/9
2-3
3-5
5-6
6-7
7-8
1-2-3-4-5-6-7-8 1-2
82/9
Project variance
2-3
3-4
4-5
5-6
6-7
7-8
1-2-3-4-6-7-8 1-2
285/
36
2-3
3-4
4-6
6-7
7-8
1-2-3-6-7-8 1-2
74/9
2-3
3-6
6-7
7-8
9
/
83 9
/
82 36
/
2859
/
74
CONT’D

CONT’D

CONT’D

darla
/smb
s/vit
25
NETWORK EXAMPLE
Illustration of network analysis of a minor redesign of a product and its associated
packaging.
The key question is: How long will it take to complete this project ?
darla
/smb
s/vit
26
FORWARD PASS
 Earliest Start Time (ES)
 earliest time an activity can start
 ES = maximum EF of immediate predecessors
 Earliest finish time (EF)
 earliest time an activity can finish
 earliest start time plus activity time
EF= ES + t
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Backward Pass
EXAMPLE 2
SUPPOSE A CIVIL ENGINEERING FIRM HAS TO BID FOR THE CONSTRUCTION OF A DAM. THE ACTIVITIES
AND TIME ESTIMATES ARE GIVEN BELOW. DO THE NEXT REQUIREMENTS.
Activity a m b
1-2 (a) 1 3 4
1-3 (b) 2 4 6
1-4 (c) 2 3 5
2-5 (d) 3 4 5
3-6 (e) 3 5 7
4- 7 (f) 5 7 9
5-8 (g) 2 3 6
6-8 (h) 4 6 8
7-8 (I) 3 4 6
CONT……….
REQUIRED:
a) Draw the project network and identify all the paths.
b) Compute the expected time for each activity and the expected
duration for each path.
c) Determine the expected project length.
d) Identify the critical path and critical activities.
e) Compute the variance for each activity and the variance for
path .
SOLUTION
A)
CONT…..
Solution
B)
Path Activity
Times
a m b te = a+4m+b
6
Path total
1-2-5-8 a
b
c
1 3 4
2 4 6
2 3 5
2.83
4.00
3.17
10.00
1-3-6-8 d
e
f
3 4 5
3 5 7
5 7 9
4.00
5.00
7.00
16.00
1-4-7-8 g
h
i
2 3 6
4 6 8
3 4 6
3.33
6.00
4.17
13.5
CONT…..
C) The critical path is path 1-3-6-8, since it has the longest expected
duration.
Path
Activity
Times
a m b δ=activity=(b-a)2
36
δ2 path δ path
1-2-5-8 a
b
c
1 3 4
2 4 6
2 3 5
(4-1)2/36=9/36
(6-2)2/36=16/36
(5-2)2/36=9/36
34/36=0.944 0.97
1-3-6-8 d
e
f
3 4 5
3 5 7
5 7 9
(5-3)2/36=4/36
(7-3)2/36=16/36
(9-5)2/36=16/36
36/36=1.00 1.00
1-4-7-8 g
h
i
2 3 6
4 6 8
3 4 6
(6-2)2/36=16/36
(8-4)2/36=16/36
(6-3)2/36=9/36
41/36=1.139 1.07

More Related Content

Similar to 470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt

CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
LJay7
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
Ishan Gandhi
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
AKSHAYA0000
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
ShwetaMahdole
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Vignesh Jayakumar
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
Salahudin Babar
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
cairo university
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
AmitLokhande16
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
Cpm pert
Cpm pertCpm pert
Cpm pert
Ashutosh Rai
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
BetshaTizazu2
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
Cpmprt
CpmprtCpmprt
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
Shashank Kapoor
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
UpulHettiarachchi5
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
BLESSY ALOSHIOUS
 
Project management
Project managementProject management
Project management
Kwesi Kissiedu
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
licpn03
 

Similar to 470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt (20)

CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Project management
Project managementProject management
Project management
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 

Recently uploaded

clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
สมใจ จันสุกสี
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
paigestewart1632
 

Recently uploaded (20)

clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
 

470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt

  • 2. The procedure of determining the critical path  Step 1. List all activities and then draw arrow (network) diagram.  Step2. Indicate the normal time (tij) for each activity ( i,j) above the arrow which is deterministic.  Step 3. Calculate the earliest start, the earliest finish, the latest finish and latest start times for each event.  Step 4. Indicate the various times computed above on the arrow diagram.  Step 5. Determine the total float for each activity by taking the difference between the earliest start and the latest start time.  Step 6. Identify the critical activities and connect them by double line arrows.  Step 7. Calculate the project duration.
  • 3. CONT’D Example:  A small maintenance project consists of the following jobs whose precedence relationship is given below. Required: A. Draw an arrow diagram representing the project. B. Find the total float for each activity. C. Find the critical path and the total project duration Jobs 1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7 Duration ( days) 15 15 3 5 8 12 1 14 3 14
  • 4. SOLUTION A. THE NETWORK DIAGRAM THAT REPRESENTS THE PROJECT IS AS FOLLOWS
  • 5. CONT’D  The paths of the network are:  Path: 1 – 2 –5 -6 -7=>37days  Path: 1 – 2 – 3– 4 – 5 – 6– 7 =>44days  Path: 1 – 2 – 3– 4 – 6– 7 =>54days- Critical Path Length  Path: 1 – 3– 4– 5 – 6 – 7 =>41days  Path: 1 – 3– 4 – 6 – 7 =>51days  Path: 1 – 3–6 – 7 =>41days B. The total float for each activity  To determine the total float first the earliest start and finish; late start and finish should be computed.  This calls for the forward pass and backward pass computation.
  • 6. CONT’D  Forward pass calculation  Finding ES and EF times involves a “forward pass” through the network.  The method associated with finding ES and EF is called forward pass method.  ES: the earliest time the activity can start, assuming all preceding activities start as early as possible.  EF: The earliest time the activity can finish. EF = ES + t  Esj is given by:  ESj= Max (ESj, ti-j)  Where Esi is the earliest time and tij is the normal time for the activity (i,j).
  • 7.  ES1=0  ES2= ES1 + t1-5= 0 + 15=15  ES3= Max (ES 2 + t2-3, Es1 + 13)  = Max (15 +3, 0+15) = 18  ES4= ES3+ t34 = 18+8 = 26  ES5 = Max (ES2 + 25, ES4 + t4-5)  = Max (15 +5, 26+1) = 27  ES6 = Max (ES3+t3-6, ES4+ t4-6, ES5+t5-6)  = Max (18+12, 26+24, 27+3)  = 40  ES7 = ES6 + t6-7 = 40 +14 = 54
  • 8. CONT’D  Backward pass Calculation  Finding LS and LF times involves a “backward pass” through the network.  The method of computing LS and LF is called backward pass method.  LS, the latest time the activity can start and not delay the project.  LF, the latest time the activity can finish and not delay the project  Computation of the latest starting and finishing times is aided by the use two rules.  LS = LF -t  The latest starting (LS) time for each activity is equal to its latest finishing (LF) time minus its expected duration
  • 9. CONT’D  2.For nodes with one leaving arrows: LF for arrows entering that node equals the LS of the leaving arrow.  For nodes with multiple leaving arrows: LF for arrows entering that node equals the smallest LS of leaving arrows.  LFi is given by:  LFi = Min ( LFj-ti-j) where LFj is the latest finish time for the event j.  LF7 = 54  LF6= LF7 = t6-7 = 54-14 = 40  LF5= LS6-t5-6= 40-3 = 37  LF4 = Min (LS5-t4-5, LS6-t4-6)  = Min (37-1, 40-14) = 26 
  • 10.  LF3 = Min (LF4-t3-4, LF6-t3-5)  = Min (26-8, 40-12) = 18  LF2 = Min (LF5 - t2-5, LF3-t2-3)  = Min (37-5, 18-3) = 15  LF1 = Min (LF3-t1-3, LF2-t1-2)  = Min (18-15, 15-15)=0  The following table gives the summarized calculation for critical path and total float.
  • 11. CONT’D Activity Normal time Earliest Latest Total float LFj- ESj or LFi-ESi Start Finisgh Start Finish ESi ESj LSi LFj 1-2 15 0 15 0 15 0 1-3 15 0 15 3 18 3 2-3 3 15 18 15 18 0 2-5 5 15 20 32 37 17 3-4 8 18 26 18 26 0 3-6 12 18 30 28 40 10 4-5 1 26 40 26 40 0 5-6 3 27 30 37 40 10 6-7 14 40 54 40 54 0
  • 12. CONT’D c)The Critical Path  From the above table we observe that the activities 1-2, 2- 3, 3-4, 4-6, 6-7 are the critical activities.  The critical path is given by, 1-2-3-4-6-7  The total project completion time (duration)is given by 54 days. Project Evaluation and Review Technique (PERT)  PERT is a time-oriented technique designated to cater for projects where it is not possible to estimate the exact duration of the activity.  It uses statistical theory to estimate how long a project is likely to last, and the probability of completing the project by a particular date.  It helps to address situations which require a probabilistic approach
  • 13. CONT’D  The probabilistic approach involves three times estimates for each activity instead of one:  1) Optimistic time: - The length of time required under optimum conditions.  It is represented be type represented by the letter “a”.  2) Pessimistic time: - The amount of time that will be required under the worst conditions.  It is represented by the letter “b”.  3) Most – likely time: - the most probable amount of time required.  It is represented by the letter “m”.
  • 14. CONT’D The β– distribution is commonly used to describe the inherent variability in time estimates. te m b a 0 Activity start Optimistic time Most-likelytime (Mode) Pessimistic time
  • 15. CONT’D  β – Distribution can be symmetrical or skewed to either the right or left according to the nature of the activity.  The mean and variance of the β-distribution can be found from the three time estimates.  β – Distribution is unimodal with a high concentration of probability surrounding the most-likely time estimate.  The important issue in network analysis is the average of expected time for each activity, te, and the variance of each activity time,δ_i^2.
  • 18. CONT’D Activity Optimistic time Most likely time Pessimistic time 1-2 3 5 7 2-3 4 8 12 3-4 2 4 6 3-5 3 6 9 3-6 3 6 9 4-5 2 4 6 4-6 1 3 6 5-6 2 5 8 6-7 2 5 14 7-8 4 7 10
  • 19. CONT’D  Given the above information, compute the following: A. Find the expected duration and variance of each activity B. Find the expected duration of the project. C. Calculate the variance and standard deviation of project length and what is the probability that the project will be completed: i.at least 4 days earlier than expected? ii.no more than 4 days later than expected? C. If the project due date is 41 days what is the probability of meeting the due date. Solution for a) and b)
  • 20. Paths Activity to tm tp Ze To+4tm+ tp 6 Expected path length (E the path) S2 1-2-3-5- 6-7-8 1-2 3 5 7 5 37 4/9 2-3 4 8 12 8 16/9 3-5 3 6 9 6 1 5-6 2 5 8 5 1 6-7 2 5 14 6 4 7-8 4 7 10 7 1 1-2-3-4- 5-6-7-8 1-2 3 5 7 5 39 Critical path 4/9 2-3 4 8 12 8 16/9 3-4 2 4 6 4 4/9 4-5 2 4 6 4 4/9 5-6 2 5 8 5 1
  • 21. CONT’D Path Activity ( 2 path)  Path 1-2-3-5-6-7-8 1-2 83/9 2-3 3-5 5-6 6-7 7-8 1-2-3-4-5-6-7-8 1-2 82/9 Project variance 2-3 3-4 4-5 5-6 6-7 7-8 1-2-3-4-6-7-8 1-2 285/ 36 2-3 3-4 4-6 6-7 7-8 1-2-3-6-7-8 1-2 74/9 2-3 3-6 6-7 7-8 9 / 83 9 / 82 36 / 2859 / 74
  • 25. darla /smb s/vit 25 NETWORK EXAMPLE Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 26. darla /smb s/vit 26 FORWARD PASS  Earliest Start Time (ES)  earliest time an activity can start  ES = maximum EF of immediate predecessors  Earliest finish time (EF)  earliest time an activity can finish  earliest start time plus activity time EF= ES + t Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors Backward Pass
  • 27. EXAMPLE 2 SUPPOSE A CIVIL ENGINEERING FIRM HAS TO BID FOR THE CONSTRUCTION OF A DAM. THE ACTIVITIES AND TIME ESTIMATES ARE GIVEN BELOW. DO THE NEXT REQUIREMENTS. Activity a m b 1-2 (a) 1 3 4 1-3 (b) 2 4 6 1-4 (c) 2 3 5 2-5 (d) 3 4 5 3-6 (e) 3 5 7 4- 7 (f) 5 7 9 5-8 (g) 2 3 6 6-8 (h) 4 6 8 7-8 (I) 3 4 6
  • 28. CONT………. REQUIRED: a) Draw the project network and identify all the paths. b) Compute the expected time for each activity and the expected duration for each path. c) Determine the expected project length. d) Identify the critical path and critical activities. e) Compute the variance for each activity and the variance for path .
  • 30. CONT….. Solution B) Path Activity Times a m b te = a+4m+b 6 Path total 1-2-5-8 a b c 1 3 4 2 4 6 2 3 5 2.83 4.00 3.17 10.00 1-3-6-8 d e f 3 4 5 3 5 7 5 7 9 4.00 5.00 7.00 16.00 1-4-7-8 g h i 2 3 6 4 6 8 3 4 6 3.33 6.00 4.17 13.5
  • 31. CONT….. C) The critical path is path 1-3-6-8, since it has the longest expected duration. Path Activity Times a m b δ=activity=(b-a)2 36 δ2 path δ path 1-2-5-8 a b c 1 3 4 2 4 6 2 3 5 (4-1)2/36=9/36 (6-2)2/36=16/36 (5-2)2/36=9/36 34/36=0.944 0.97 1-3-6-8 d e f 3 4 5 3 5 7 5 7 9 (5-3)2/36=4/36 (7-3)2/36=16/36 (9-5)2/36=16/36 36/36=1.00 1.00 1-4-7-8 g h i 2 3 6 4 6 8 3 4 6 (6-2)2/36=16/36 (8-4)2/36=16/36 (6-3)2/36=9/36 41/36=1.139 1.07