Topics to cover in 2nd part
Topics Chapters # of lectures
1. Project Management 8 2
2. Inventory 16 1.5
3. Decision Analysis 12 1.5
4. Queuing 13 1
(to p2)
2
Chapter 8 - Project Management
Chapter Topics
Date Topics
Mar 11 1.The Elements of Project
Management
2.The Project Network Probabilistic
Activity Times
Mar 25 1.Project Crashing and Time-Cost
Trade-Off
2.Formulating the CPM/PERT
Network as a Linear
Programming Model (to p3)
3
Project Management
Questions:
1. Why do we need to study Project
Management?
2. How does a project management
technique work?
(to p4)
(to p5)
4
Objective
• The main purpose is to govern the
operations of a project such that all
activities involved are well administrated
and that we can also control its
completion time
(to p3)
5
Project management technique
Steps to solve a project management
problem:
1. to represent a ‘project problem”
graphically
2. to determine its completion time
3. to carry out sensitivity analysis, if any
(to p6)
(to p12)
(to p29)
6
1. Represent a ‘project problem”
graphically
Steps:
1. Gather all information and
organize them in a table
format that consists of: event,
processing time, and
precedent constraints as
follows:
2. Draw a semantic network to
represent them
Special case!
Event Processing
Time
Precedent
constraints
A
B
C
20
30
10
--
A
B
(to p7)
(to p9)
(to p4)
7
Semantic network to represent them
Here, we use three symbols:
node to represent stage
line/branch to represent event
arrow to represent precedent
constraint
Example (to p8)
(to p6)
8
Example
1 2 3
Path Event Proc
Time
Pred
Const
1-2
2-3
3-4
A
B
C
20
30
10
--
A
B
A
4
C
B
20 30 10
Rule1: All nodes must starts from one
Node and ends with one node
(to p7)
9
Special case!
• When two or events
taken places in the
same time interval
• (known an concurrent
events)
• Consider the following
example!
• How to draw it?
Event Processing
Time
Precedent
constraints
A
B
C
3
5
7
--
A
A
(to p10)
10
Case 1
1 2 3
A B
C
3
5
7
Wrong!
Rule2: no node can have
two outcomes and end
with the same note
Solution (to p11)
11
Solutions for Rule 2
Three ways to draw it:
1 2
3
4
5
A
B
C
Dummy 1=0
Dummy 2 = 0
1 2
3
4
A B
C
Dummy = 0
1 2
3
4
A
B
C
Dummy = 0
Solution 1:
Solution 2:
Solution 3:
What one
is better?
A dummy activity shows
a precedence relationship
Reflects no processing time
(to p6)
12
2. Determine its completion time
Consider the project network as shown in
next slide
Question: Is it an easy way to find out the
solution?
Answer: YES, it knows as
Critical Path Method (CPM)
(to p15)
(to p13)
13
The Project Network
All Possible Paths for Obtaining a Solution
Figure 8.3
Expanded network
for building a house
showing
concurrent activities.
Table 8.1
Possible Paths to
complete the
House-Building
Network
Then the completion time for paths A, B, C and D can be computed as
(to p14)
14
The Project Network
Completion time for:
path A: 12  3  4  6  7, 3 + 2 + 0 + 3 + 1 = 9 months (Critical Path)
path B: 1  2  3  4  5  6  7, 3 + 2 + 0 + 1 + 1 + 1 = 8 months
path C: 1  2  4  6  7, 3 + 1 + 3 + 1 = 8 months
path D: 1  2  4  5  6  7, 3 + 1 + 1 + 1 + 1 = 7 months
The critical path is the longest path through the network; the minimum time the network can be completed.
Figure 8.5
Alternative paths in the
network
This is the
Solution!
(to p12)
15
Critical Path Method (CPM)
• General concepts:
– For each branch of the project network, we firstly
determine four values of ES, EF, LS and LF
– For each branch, we compute their slack time,
• Slack time = (LS-ES) or (LF-EF)
– The critical path is located at branch that has
slack time = 0
(Do you know the reason why?)
How it works? (to p16)
16
How CPM works?
Steps:
1. Prepare the project
network
2. Construct a table as
follows:
3. Compute ES and EF
4. Compute LS and LF
5. Compute LS-ES or LF-
EF
Branch
ES EF LS LF
ESij = max (EFi) EFij = ESi + tij
with EF1=0
Critical path when LS-ES=0
(to p4)
(to p17)
(to p26)
(to p22)
17
Compute ES and EF
Note:
When computing these values, the pattern
is like moving zic-zac format by firstly
computer ES12 and then adding it to EF12
and move to next branch by copying the
max values of the branch 1-2 to say, 2-3
We compute them from top to bottom!
Their relationship :
Example 1:
(to p18)
(to p22)
(to p19)
18
The starting point of ES and EF
Consider:
Then
EF1 = 0
ES12 = max (EF1) EF12 = ES12 + t12
= 0 = 0 + t12
1 2
t12
(to p17)
19
Branches ESij = max(EFi) EFij=ESij+tij
1-2
2-3
2-4
3-4
4-5
4-6
5-6
6-7
ES12= max(EF1)=
ES23=max(EF2)=
ES24=max(EF2)=
ES34=max(EF3)=
ES45=max(EF4)=
ES46=max(EF4)=
ES56=max(EF5)=
ES67=max(EF6)=
EF12=ES12+t12=
EF23=ES23+t23=
EF24=
EF34=
EF45=
EF46=
EF56=
EF67=
The overall computation is shown in next slide
(to p20)
20
Branch ESij = max (EFi ) EFij = ESij + tij
1 -2
2-3
ES12 = max (EF1) = 0
ES23 = max (EF2) = 3
EF12 = ES12 + t12
= 0 + 3 =3
EF23=ES23+t23
= 3 + 2 = 5
2-4
3-4
4 -5
ES24 = max(EF2) = 3
ES34= max (EF3) = 5
ES45= max (ES4) = 5
EF24=ES24+t24
=3 + 1 = 4
EF34=ES34 + t34
= 5 + 0 = 5
EF45 = ES45 + t45
= 5 + 1 = 6
4 -6
5-6
6-7
ES46=max(EF4) = 5
ES56=max(EF5) = 6
ES67=max(EF6) =8
EF46=ES46+t46
=5 + 3 = 8
EF56=ES56 +t56
=6 + 1 = 7
EF67=ES67+t67
= 8+ 1 = 9
- ES is the earliest time an activity can start. ESij = Maximum (EFi)
- EF is the earliest start time plus the activity time. EFij = ESij + tij
(note:you can compute these values and show in the network diagram as well)
Add all t to note 4 and
take the longest time
Max (node 3+t34,
node2+t24)
max (5+0, 3+1)
=max(5,4)=5
add all ti for
note 2
Max(node4+t46,node5+t56
=max(5+3,5+1)=8
Complete solution
(to p4)
(to p21)
21
The Project Network
Activity Scheduling- Earliest Times
- ES is the earliest time an activity can start. ESij = Maximum (EFi)
- EF is the earliest start time plus the activity time. EFij = ESij + tij
Figure 8.6
Earliest activity start and finish times
(to p20)
22
Compute LS and LF
Note: We compute these values from the
bottom to top, with assigning:
LSij = LFi -tij LFij = min LSj
with
the end of LFij = EFij
Example: computing Figure 8.3 (to p23)
23
Branches LSij = LFij-tij LFij=min(LSj)
1-2
2-3
2-4
3-4
4-5
4-6
5-6
6-7
LS12 = Li12-t12 =
LS23 = LF23-t23 =
LS24 = LF24-t24 =
LS34 = LF34-t34 =
LS45 = LF45-t45 =
LS46 = LF46-i46 =
LS56 = LF56-t56 =
LS67 = LF67-t67 =
LF12=min(LS2)=
LF23=min(LS3)=
LF24=min(LS4)=
LF34=min(LS4)=
LF45=min(LS5)=
LF46=min(LS6)=
LF56=min(LS6)=
LF67=min(LS7)=
The overall computational is shown in next slide
(to p24)
24
- LS is the latest time an activity can start without delaying critical path time. LSij = LFij - tij
- LF is the latest finish time LFij = Minimum (LSj)
Branches LSij=LFij-tij LFij=min LSj
1-2
2-3
2-4
LS12=LF12-t12 = 3-3 =0
LS23=LF23-t23=5-2=3
LS24=LF24-t24=5-1=4
LF12 = Min(LS2) =3
LF23=Min(LS3) = 5
LF24=Min(LS4)=5
3-4
4-5
4-6
LS34=LF34-t34=5-0 = 5
LS45=LF45-t45 = 7-1=6
LS46=LF46-t46=8-3=5
LF34=Min(LS4) = 5
LF45=Min(LS5)=7
LF46=Min(LS6)=8
5-6
6-7
LS56=LF56-t56=8-1=7
LS67=LF67-t67=9-1=8
LF56=Min(LS6)=8
LF67=Min(LS67)=9
Start with the end node first
Same as EF67
from the previous slide
Again, you can place these values onto the branches
Min(node 6-t46,node5-t45)
=Min(8-3,7-1)
=Min(5,6)=5
Min(node3-t23,node4-t24)
=Min(5-2,5-1)=Min(3,4)=3
Min(node 7-t67)
=Min(9-1)=8
(to p25) (to p22)
25
The Project Network
Activity Scheduling - Latest Times
- LS is the latest time an activity can start without delaying critical path time. LSij = LFij - tij
- LF is the latest finish time LFij = Minimum (LSj)
Figure 8.7
Latest activity start and finish times
(to p24)
26
Compute LS-ES or LF-EF
Two ways you can achieve it:
1. by compiling slack, Sij
2. by showing branches
(to p27)
(to p28)
(to p16)
27
The Project Network
Calculating Activity Slack Time
- Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij
Table 8.2
Activity Slack
Figure 8.9
Activity Slack
*
What does it mean?
(to p26)
28
The Project Network
Activity Slack
• Slack is the amount of time an activity can be delayed without delaying the project.
• Slack time exists for those activities not on the critical path for which the earliest and latest star
times are not equal.
• Shared slack is slack available for a sequence of activities.
Figure 8.8
Earliest activity start and finish times
(to p26)
29
Sensitivity Analysis
• Today, we only consider one case –
“Probabilistic Activity Times”
• Refer to activity time estimates usually can
not be made with certainty
• PERT is known as the solution method
(to p30)
30
PERT
• In PERT, three different time estimations are
applied:
most likely time (m),
the optimistic time (a) , and
the pessimistic time (b).
• How do we make use of these three values?
(to p31)
31
Probabilistic Activity Times
•We used these values to estimate the mean and variance of a beta distribution:
mean (expected time):
variance:
How to use these values to solve a project network problem?
6
b
4m
a
t



2
6
a
-
b











v
(to p32)
32
PERT
• We simply apply t values in CPM and determine the
values of:
• ES
• EF
• LS
• LF
• S
and branches with slack = 0 still consider as critical paths
• Example. (to p33)
33
Procedures for PERT
Step 1: based on the values of a, b and m,
determine the t and v values for each path
Step 2: determine the critical path by using t
values in the CPM
Step 3: compute its corresponding means and
standard deviations according.
Example
Result implication
Applications
(to p34)
(to p38)
(to p39)
34
PERT Example
• Step 1: computer t and v values
• Step 2: determine the CPM
• Step 3: determine v value
(to p35)
(to p36)
(to p37)
(to p33)
35
Step 1: computer t and v values
Figure 8.11
Network with mean activity times and variances
Table 8.3
Activity Time Estimates for
Figure 8.10
6
b
4m
a
t



2
6
a
-
b











v
(to p34)
36
Step 2: determine the CPM
Figure 8.12
Earliest and latest activity times
Table 8.4
Activity Earliest and
Latest Times and Slack
(to p34)
37
Step 3: determine v value
• The expected project time is the sum of the expected times of the critical path activities.
• The project variance is the sum of the variances of the critical path activities.
• The expected project time is assumed to be normally distributed (based on central limit
theorum).
In example, expected project time (tp) and variance (vp) interpreted as the mean () and
variance (2) of a normal distribution:
 = 25 weeks
2 = 6.9 weeks
Critical Path Activity Variance
1  3
3  5
5  7
7 9
1
1/9
16/9
4
total 62/9
(to p34)
38
Probability Analysis of the Project Network
- Using normal distribution, probabilities are determined by computing number of standard
deviations (Z) a value is from the mean.
- Value is used to find corresponding probability in Table A.1, App. A.
Figure 8.13
Normal distribution of network duration Critical value
(to p33)
39
Consider when
x = 30
x = 22
Tutorial Assignment
(to p40)
(to p41)
(to p42)
40
Probability Analysis of the Project Network
Example 1
2 = 6.9  = 2.63
Z = (x-)/  = (30 -25)/2.63 = 1.90
-Z value of 1.90 corresponds to probability of .4713 in Appendix A of p715. Probability
of completing project in 30 weeks or less : (.5000 + .4713) = .9713,
or 97.13% (Why so high a probability rate?)
Figure 8.14
Probability the network will be
completed in 30 weeks or less
(to p39)
41
Probability Analysis of the Project Network
Example 2
Z = (22 - 25)/2.63 = -1.14
Z value of 1.14 (ignore negative) corresponds to probability of .3729 in Table A.1, appendix A.
Probability that customer will be retained is .1271 (= 0.5- 0.3729) , or 12.71%
(Again, why so low probability rate?)
Figure 8.15
Probability the network
will be completed in 22
weeks or less
(to p39)
42
Tutorial Assignment
• Try to use QM to solve CPM/PERT
problems (see slide 19)
• Exercises (Chapter 8)
– Old: 8, 10, 17
– New: 4, 6, 11
(to p43)
43
Probability Analysis of the Project Network
CPM/PERT Analysis with QM for Windows
Exhibit 8.1
(to p16)
44
The Project Network
Activity Slack
• Slack is the amount of time an activity can be delayed without delaying the project.
• Slack time exists for those activities not on the critical path for which the earliest and latest star
times are not equal.
• Shared slack is slack available for a sequence of activities.
Figure 8.8
Earliest activity start and finish times
45
The Project Network
Calculating Activity Slack Time
- Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij
Table 8.2
Activity Slack
Figure 8.9
Activity Slack
*

More Related Content

Similar to pert_n_cpm.ppt

Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
Data Structure & Algorithms - Mathematical
Data Structure & Algorithms - MathematicalData Structure & Algorithms - Mathematical
Data Structure & Algorithms - Mathematicalbabuk110
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 
algorithmanalysis and effciency.pptx
algorithmanalysis and effciency.pptxalgorithmanalysis and effciency.pptx
algorithmanalysis and effciency.pptxChSreenivasuluReddy
 
ALGORITHM-ANALYSIS.ppt
ALGORITHM-ANALYSIS.pptALGORITHM-ANALYSIS.ppt
ALGORITHM-ANALYSIS.pptsapnaverma97
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM maggieget
 
4.9 cpm network calculations
4.9 cpm network calculations4.9 cpm network calculations
4.9 cpm network calculationsVishal Tidake
 
Lecture 3 time complexity
Lecture 3 time complexityLecture 3 time complexity
Lecture 3 time complexityAbirami A
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Critical path method with detailed description
Critical path method with detailed descriptionCritical path method with detailed description
Critical path method with detailed descriptionTalhaManasiya
 
Parallel sorting algorithm
Parallel sorting algorithmParallel sorting algorithm
Parallel sorting algorithmRicha Kumari
 
CS-102 DS-class_01_02 Lectures Data .pdf
CS-102 DS-class_01_02 Lectures Data .pdfCS-102 DS-class_01_02 Lectures Data .pdf
CS-102 DS-class_01_02 Lectures Data .pdfssuser034ce1
 
Introduction to data structures and complexity.pptx
Introduction to data structures and complexity.pptxIntroduction to data structures and complexity.pptx
Introduction to data structures and complexity.pptxPJS KUMAR
 
Chapter One.pdf
Chapter One.pdfChapter One.pdf
Chapter One.pdfabay golla
 

Similar to pert_n_cpm.ppt (20)

Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Data Structure & Algorithms - Mathematical
Data Structure & Algorithms - MathematicalData Structure & Algorithms - Mathematical
Data Structure & Algorithms - Mathematical
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Lecture#9
Lecture#9Lecture#9
Lecture#9
 
Critical path method
Critical path methodCritical path method
Critical path method
 
algorithmanalysis and effciency.pptx
algorithmanalysis and effciency.pptxalgorithmanalysis and effciency.pptx
algorithmanalysis and effciency.pptx
 
ALGORITHM-ANALYSIS.ppt
ALGORITHM-ANALYSIS.pptALGORITHM-ANALYSIS.ppt
ALGORITHM-ANALYSIS.ppt
 
Design and analysis of algorithms
Design and analysis of algorithmsDesign and analysis of algorithms
Design and analysis of algorithms
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
 
4.9 cpm network calculations
4.9 cpm network calculations4.9 cpm network calculations
4.9 cpm network calculations
 
Lecture 3 time complexity
Lecture 3 time complexityLecture 3 time complexity
Lecture 3 time complexity
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Critical path method with detailed description
Critical path method with detailed descriptionCritical path method with detailed description
Critical path method with detailed description
 
Parallel sorting algorithm
Parallel sorting algorithmParallel sorting algorithm
Parallel sorting algorithm
 
Ch07 linearspacealignment
Ch07 linearspacealignmentCh07 linearspacealignment
Ch07 linearspacealignment
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
CS-102 DS-class_01_02 Lectures Data .pdf
CS-102 DS-class_01_02 Lectures Data .pdfCS-102 DS-class_01_02 Lectures Data .pdf
CS-102 DS-class_01_02 Lectures Data .pdf
 
Introduction to data structures and complexity.pptx
Introduction to data structures and complexity.pptxIntroduction to data structures and complexity.pptx
Introduction to data structures and complexity.pptx
 
Chapter One.pdf
Chapter One.pdfChapter One.pdf
Chapter One.pdf
 

More from chandrasekarnatraj

More from chandrasekarnatraj (10)

unit-5-1.ppt
unit-5-1.pptunit-5-1.ppt
unit-5-1.ppt
 
unit-5-1.ppt
unit-5-1.pptunit-5-1.ppt
unit-5-1.ppt
 
unit_-_3.ppt
unit_-_3.pptunit_-_3.ppt
unit_-_3.ppt
 
project_life_cycles_models.ppt
project_life_cycles_models.pptproject_life_cycles_models.ppt
project_life_cycles_models.ppt
 
project_plan_execution_activities.ppt
project_plan_execution_activities.pptproject_plan_execution_activities.ppt
project_plan_execution_activities.ppt
 
human_resource_planning_staff_acquisition_and_team_development.ppt
human_resource_planning_staff_acquisition_and_team_development.ppthuman_resource_planning_staff_acquisition_and_team_development.ppt
human_resource_planning_staff_acquisition_and_team_development.ppt
 
Operating Systems EduEngg.pdf
Operating Systems EduEngg.pdfOperating Systems EduEngg.pdf
Operating Systems EduEngg.pdf
 
pert_n_cpm.ppt
pert_n_cpm.pptpert_n_cpm.ppt
pert_n_cpm.ppt
 
project_control.ppt
project_control.pptproject_control.ppt
project_control.ppt
 
CS8493-OS-Unit-5.pdf
CS8493-OS-Unit-5.pdfCS8493-OS-Unit-5.pdf
CS8493-OS-Unit-5.pdf
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

pert_n_cpm.ppt

  • 1. 1 Topics to cover in 2nd part Topics Chapters # of lectures 1. Project Management 8 2 2. Inventory 16 1.5 3. Decision Analysis 12 1.5 4. Queuing 13 1 (to p2)
  • 2. 2 Chapter 8 - Project Management Chapter Topics Date Topics Mar 11 1.The Elements of Project Management 2.The Project Network Probabilistic Activity Times Mar 25 1.Project Crashing and Time-Cost Trade-Off 2.Formulating the CPM/PERT Network as a Linear Programming Model (to p3)
  • 3. 3 Project Management Questions: 1. Why do we need to study Project Management? 2. How does a project management technique work? (to p4) (to p5)
  • 4. 4 Objective • The main purpose is to govern the operations of a project such that all activities involved are well administrated and that we can also control its completion time (to p3)
  • 5. 5 Project management technique Steps to solve a project management problem: 1. to represent a ‘project problem” graphically 2. to determine its completion time 3. to carry out sensitivity analysis, if any (to p6) (to p12) (to p29)
  • 6. 6 1. Represent a ‘project problem” graphically Steps: 1. Gather all information and organize them in a table format that consists of: event, processing time, and precedent constraints as follows: 2. Draw a semantic network to represent them Special case! Event Processing Time Precedent constraints A B C 20 30 10 -- A B (to p7) (to p9) (to p4)
  • 7. 7 Semantic network to represent them Here, we use three symbols: node to represent stage line/branch to represent event arrow to represent precedent constraint Example (to p8) (to p6)
  • 8. 8 Example 1 2 3 Path Event Proc Time Pred Const 1-2 2-3 3-4 A B C 20 30 10 -- A B A 4 C B 20 30 10 Rule1: All nodes must starts from one Node and ends with one node (to p7)
  • 9. 9 Special case! • When two or events taken places in the same time interval • (known an concurrent events) • Consider the following example! • How to draw it? Event Processing Time Precedent constraints A B C 3 5 7 -- A A (to p10)
  • 10. 10 Case 1 1 2 3 A B C 3 5 7 Wrong! Rule2: no node can have two outcomes and end with the same note Solution (to p11)
  • 11. 11 Solutions for Rule 2 Three ways to draw it: 1 2 3 4 5 A B C Dummy 1=0 Dummy 2 = 0 1 2 3 4 A B C Dummy = 0 1 2 3 4 A B C Dummy = 0 Solution 1: Solution 2: Solution 3: What one is better? A dummy activity shows a precedence relationship Reflects no processing time (to p6)
  • 12. 12 2. Determine its completion time Consider the project network as shown in next slide Question: Is it an easy way to find out the solution? Answer: YES, it knows as Critical Path Method (CPM) (to p15) (to p13)
  • 13. 13 The Project Network All Possible Paths for Obtaining a Solution Figure 8.3 Expanded network for building a house showing concurrent activities. Table 8.1 Possible Paths to complete the House-Building Network Then the completion time for paths A, B, C and D can be computed as (to p14)
  • 14. 14 The Project Network Completion time for: path A: 12  3  4  6  7, 3 + 2 + 0 + 3 + 1 = 9 months (Critical Path) path B: 1  2  3  4  5  6  7, 3 + 2 + 0 + 1 + 1 + 1 = 8 months path C: 1  2  4  6  7, 3 + 1 + 3 + 1 = 8 months path D: 1  2  4  5  6  7, 3 + 1 + 1 + 1 + 1 = 7 months The critical path is the longest path through the network; the minimum time the network can be completed. Figure 8.5 Alternative paths in the network This is the Solution! (to p12)
  • 15. 15 Critical Path Method (CPM) • General concepts: – For each branch of the project network, we firstly determine four values of ES, EF, LS and LF – For each branch, we compute their slack time, • Slack time = (LS-ES) or (LF-EF) – The critical path is located at branch that has slack time = 0 (Do you know the reason why?) How it works? (to p16)
  • 16. 16 How CPM works? Steps: 1. Prepare the project network 2. Construct a table as follows: 3. Compute ES and EF 4. Compute LS and LF 5. Compute LS-ES or LF- EF Branch ES EF LS LF ESij = max (EFi) EFij = ESi + tij with EF1=0 Critical path when LS-ES=0 (to p4) (to p17) (to p26) (to p22)
  • 17. 17 Compute ES and EF Note: When computing these values, the pattern is like moving zic-zac format by firstly computer ES12 and then adding it to EF12 and move to next branch by copying the max values of the branch 1-2 to say, 2-3 We compute them from top to bottom! Their relationship : Example 1: (to p18) (to p22) (to p19)
  • 18. 18 The starting point of ES and EF Consider: Then EF1 = 0 ES12 = max (EF1) EF12 = ES12 + t12 = 0 = 0 + t12 1 2 t12 (to p17)
  • 19. 19 Branches ESij = max(EFi) EFij=ESij+tij 1-2 2-3 2-4 3-4 4-5 4-6 5-6 6-7 ES12= max(EF1)= ES23=max(EF2)= ES24=max(EF2)= ES34=max(EF3)= ES45=max(EF4)= ES46=max(EF4)= ES56=max(EF5)= ES67=max(EF6)= EF12=ES12+t12= EF23=ES23+t23= EF24= EF34= EF45= EF46= EF56= EF67= The overall computation is shown in next slide (to p20)
  • 20. 20 Branch ESij = max (EFi ) EFij = ESij + tij 1 -2 2-3 ES12 = max (EF1) = 0 ES23 = max (EF2) = 3 EF12 = ES12 + t12 = 0 + 3 =3 EF23=ES23+t23 = 3 + 2 = 5 2-4 3-4 4 -5 ES24 = max(EF2) = 3 ES34= max (EF3) = 5 ES45= max (ES4) = 5 EF24=ES24+t24 =3 + 1 = 4 EF34=ES34 + t34 = 5 + 0 = 5 EF45 = ES45 + t45 = 5 + 1 = 6 4 -6 5-6 6-7 ES46=max(EF4) = 5 ES56=max(EF5) = 6 ES67=max(EF6) =8 EF46=ES46+t46 =5 + 3 = 8 EF56=ES56 +t56 =6 + 1 = 7 EF67=ES67+t67 = 8+ 1 = 9 - ES is the earliest time an activity can start. ESij = Maximum (EFi) - EF is the earliest start time plus the activity time. EFij = ESij + tij (note:you can compute these values and show in the network diagram as well) Add all t to note 4 and take the longest time Max (node 3+t34, node2+t24) max (5+0, 3+1) =max(5,4)=5 add all ti for note 2 Max(node4+t46,node5+t56 =max(5+3,5+1)=8 Complete solution (to p4) (to p21)
  • 21. 21 The Project Network Activity Scheduling- Earliest Times - ES is the earliest time an activity can start. ESij = Maximum (EFi) - EF is the earliest start time plus the activity time. EFij = ESij + tij Figure 8.6 Earliest activity start and finish times (to p20)
  • 22. 22 Compute LS and LF Note: We compute these values from the bottom to top, with assigning: LSij = LFi -tij LFij = min LSj with the end of LFij = EFij Example: computing Figure 8.3 (to p23)
  • 23. 23 Branches LSij = LFij-tij LFij=min(LSj) 1-2 2-3 2-4 3-4 4-5 4-6 5-6 6-7 LS12 = Li12-t12 = LS23 = LF23-t23 = LS24 = LF24-t24 = LS34 = LF34-t34 = LS45 = LF45-t45 = LS46 = LF46-i46 = LS56 = LF56-t56 = LS67 = LF67-t67 = LF12=min(LS2)= LF23=min(LS3)= LF24=min(LS4)= LF34=min(LS4)= LF45=min(LS5)= LF46=min(LS6)= LF56=min(LS6)= LF67=min(LS7)= The overall computational is shown in next slide (to p24)
  • 24. 24 - LS is the latest time an activity can start without delaying critical path time. LSij = LFij - tij - LF is the latest finish time LFij = Minimum (LSj) Branches LSij=LFij-tij LFij=min LSj 1-2 2-3 2-4 LS12=LF12-t12 = 3-3 =0 LS23=LF23-t23=5-2=3 LS24=LF24-t24=5-1=4 LF12 = Min(LS2) =3 LF23=Min(LS3) = 5 LF24=Min(LS4)=5 3-4 4-5 4-6 LS34=LF34-t34=5-0 = 5 LS45=LF45-t45 = 7-1=6 LS46=LF46-t46=8-3=5 LF34=Min(LS4) = 5 LF45=Min(LS5)=7 LF46=Min(LS6)=8 5-6 6-7 LS56=LF56-t56=8-1=7 LS67=LF67-t67=9-1=8 LF56=Min(LS6)=8 LF67=Min(LS67)=9 Start with the end node first Same as EF67 from the previous slide Again, you can place these values onto the branches Min(node 6-t46,node5-t45) =Min(8-3,7-1) =Min(5,6)=5 Min(node3-t23,node4-t24) =Min(5-2,5-1)=Min(3,4)=3 Min(node 7-t67) =Min(9-1)=8 (to p25) (to p22)
  • 25. 25 The Project Network Activity Scheduling - Latest Times - LS is the latest time an activity can start without delaying critical path time. LSij = LFij - tij - LF is the latest finish time LFij = Minimum (LSj) Figure 8.7 Latest activity start and finish times (to p24)
  • 26. 26 Compute LS-ES or LF-EF Two ways you can achieve it: 1. by compiling slack, Sij 2. by showing branches (to p27) (to p28) (to p16)
  • 27. 27 The Project Network Calculating Activity Slack Time - Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij Table 8.2 Activity Slack Figure 8.9 Activity Slack * What does it mean? (to p26)
  • 28. 28 The Project Network Activity Slack • Slack is the amount of time an activity can be delayed without delaying the project. • Slack time exists for those activities not on the critical path for which the earliest and latest star times are not equal. • Shared slack is slack available for a sequence of activities. Figure 8.8 Earliest activity start and finish times (to p26)
  • 29. 29 Sensitivity Analysis • Today, we only consider one case – “Probabilistic Activity Times” • Refer to activity time estimates usually can not be made with certainty • PERT is known as the solution method (to p30)
  • 30. 30 PERT • In PERT, three different time estimations are applied: most likely time (m), the optimistic time (a) , and the pessimistic time (b). • How do we make use of these three values? (to p31)
  • 31. 31 Probabilistic Activity Times •We used these values to estimate the mean and variance of a beta distribution: mean (expected time): variance: How to use these values to solve a project network problem? 6 b 4m a t    2 6 a - b            v (to p32)
  • 32. 32 PERT • We simply apply t values in CPM and determine the values of: • ES • EF • LS • LF • S and branches with slack = 0 still consider as critical paths • Example. (to p33)
  • 33. 33 Procedures for PERT Step 1: based on the values of a, b and m, determine the t and v values for each path Step 2: determine the critical path by using t values in the CPM Step 3: compute its corresponding means and standard deviations according. Example Result implication Applications (to p34) (to p38) (to p39)
  • 34. 34 PERT Example • Step 1: computer t and v values • Step 2: determine the CPM • Step 3: determine v value (to p35) (to p36) (to p37) (to p33)
  • 35. 35 Step 1: computer t and v values Figure 8.11 Network with mean activity times and variances Table 8.3 Activity Time Estimates for Figure 8.10 6 b 4m a t    2 6 a - b            v (to p34)
  • 36. 36 Step 2: determine the CPM Figure 8.12 Earliest and latest activity times Table 8.4 Activity Earliest and Latest Times and Slack (to p34)
  • 37. 37 Step 3: determine v value • The expected project time is the sum of the expected times of the critical path activities. • The project variance is the sum of the variances of the critical path activities. • The expected project time is assumed to be normally distributed (based on central limit theorum). In example, expected project time (tp) and variance (vp) interpreted as the mean () and variance (2) of a normal distribution:  = 25 weeks 2 = 6.9 weeks Critical Path Activity Variance 1  3 3  5 5  7 7 9 1 1/9 16/9 4 total 62/9 (to p34)
  • 38. 38 Probability Analysis of the Project Network - Using normal distribution, probabilities are determined by computing number of standard deviations (Z) a value is from the mean. - Value is used to find corresponding probability in Table A.1, App. A. Figure 8.13 Normal distribution of network duration Critical value (to p33)
  • 39. 39 Consider when x = 30 x = 22 Tutorial Assignment (to p40) (to p41) (to p42)
  • 40. 40 Probability Analysis of the Project Network Example 1 2 = 6.9  = 2.63 Z = (x-)/  = (30 -25)/2.63 = 1.90 -Z value of 1.90 corresponds to probability of .4713 in Appendix A of p715. Probability of completing project in 30 weeks or less : (.5000 + .4713) = .9713, or 97.13% (Why so high a probability rate?) Figure 8.14 Probability the network will be completed in 30 weeks or less (to p39)
  • 41. 41 Probability Analysis of the Project Network Example 2 Z = (22 - 25)/2.63 = -1.14 Z value of 1.14 (ignore negative) corresponds to probability of .3729 in Table A.1, appendix A. Probability that customer will be retained is .1271 (= 0.5- 0.3729) , or 12.71% (Again, why so low probability rate?) Figure 8.15 Probability the network will be completed in 22 weeks or less (to p39)
  • 42. 42 Tutorial Assignment • Try to use QM to solve CPM/PERT problems (see slide 19) • Exercises (Chapter 8) – Old: 8, 10, 17 – New: 4, 6, 11 (to p43)
  • 43. 43 Probability Analysis of the Project Network CPM/PERT Analysis with QM for Windows Exhibit 8.1 (to p16)
  • 44. 44 The Project Network Activity Slack • Slack is the amount of time an activity can be delayed without delaying the project. • Slack time exists for those activities not on the critical path for which the earliest and latest star times are not equal. • Shared slack is slack available for a sequence of activities. Figure 8.8 Earliest activity start and finish times
  • 45. 45 The Project Network Calculating Activity Slack Time - Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij - EFij Table 8.2 Activity Slack Figure 8.9 Activity Slack *