SlideShare a Scribd company logo
NYLEX STRIPDRAIN™
Road Drainage Edition
With Project Site Pictures
and the we-tell-you-how
INTRODUCTION
PRODUCT OVERVIEW
DIMENSIONS
PACKING DETAILS
STRIPDRAIN
 is a prefabricated & flexible subsoil drainage system to
remove underground seepage water
 consists of a HDPE inner drain core completely wrapped
with a non woven geotextile filter
 alternative to conventional perforated pipe-gravel-geotextile
systems
 mainly used for sport fields, roads, highways, parks, golf
courses, horse racing tracks, gardens, slopes
CONVENTIONAL
SUBSOIL DRAIN
Aggregates
Geotextiles overwrapped around
subsoil pipe (Optional)
Perforated Subsoil
Pipe
Geotextiles overwrapped
around aggregates
Sand Blanket
Top Soil
STRIPDRAIN
STANDARD CROSS SECTION
Sand
Backfilling
Sand Blanket
Top Soil
Nylex Stripdrain
Compacted Earth
ADVANTAGES OF NYLEX STRIPDRAIN
 unique “Deep-fin” geometry ensures complete
interception of seepage
 very effective for lowering of ground water table
 more than 90% surface area is permeable to water
provides higher rate of drainage
 prefabrication offers fast installation time
 narrow trench width of 150mm requires less backfill
 uses coarse sand backfill instead of gravel
 cheaper system compare to pipe-gravel systems
STANDARD SIZES
Product Code Size (Width x Thickness x Length)
SD100x40 100mm x 40mm x 50m
SD200x40 200mm x 40mm x 50m
SD300x40 300mm x 40mm x 50m
SD400x40 400mm x 40mm x 50m
SD500x40 500mm x 40mm x 25m
DESIGN
Estimation of in-flow into subsoil drain
The discharge capacity of Stripdrain
The outlet distance using Stripdrain
THREE IMPORTANT FACTORS
IN DESIGNING SUBSOIL DRAINAGE FOR ROAD HIGHWAYS
Estimation of in-flow
into subsoil drain
The discharge
capacity of
Stripdrain
The outlet distance
using Stripdrain
ESTIMATION OF IN-FLOW INTO SUB-SOIL DRAIN
• Sub-soil drainage is provided at the edge of the highway or in the median and shoulder.
• Installed near the surface, they alter the ground water regime so as to offer protection to
the road structure and sub-grade.
• The in-flow rate of water into these sub-surface drainage systems can be estimated by
considering the following sources of water:
a) Infiltration through the pavement
b) Infiltration through the shoulder or median
c) Ground water movements
(a) (a)
(b) (b) (b)
(c)
TOTAL IN-FLOW INTO SUB-SOIL DRAIN
• From the estimation of the water sources, the total in-flow to the sub-soil drainage system
can be estimated.
• Consider the total in-flow to the two types of sub-soil drain locations, namely the side-
table and the median.
The side table
The median
TOTAL IN-FLOW INTO SUB-SOIL DRAIN (THE SIDE-TABLE)
• The possible sources of water for the side-table are;
a) Qpm, transmitted through one pavement ie. (a2)
b) Qsm, infiltration through shoulder ie. (b3)
c) Qsp, interception of cut slope seepage ie. from (c)
• Therefore, the total in-flow is, Qtot = Qpm + Qsm + Qsp [l/min]
(a1) (a2)
(b1)
(c)
(b2) (b3)
TOTAL IN-FLOW INTO SUB-SOIL DRAIN (THE MEDIAN)
• The possible sources of water for the side-table are;
a) 2 x Qpm, transmitted through TWO pavement ie. (a1) & (a2)
b) Qsm, infiltration through median surface ie. (b2)
c) 2 x Qsp, if seepage from water table control from two sides
• Therefore, the total in-flow is, Qtot = 2(Qpm) + Qsm + 2(Qsp) [l/min]
(a1) (a2)
(b1)
(c)
(b2) (b3)
THE DISCHARGE CAPACITY OF STRIPDRAIN
• The discharge capacity of Nylex Stripdrain can be determined from the following
hydraulic equation which has been simplified from Manning’s formula;
Discharge capacity, Qsd = C x W x g^0.5 m3/s
= C x W x g^0.5 x 60000 l/min
C = constant taking into account Manning’s roughness factor n,
hydraulic radius Rh, etc…
For Stripdrain 40mm, C = 0.0213
W = width of Stripdrain in meter
g = gradient of Stripdrain
• A safety factor could be applied to Qsd to account for any siltation and reduction of the
cross-sectional area which might occur when Stripdrain is buried in the ground. The
recommended safety factor is F = 0.8.
THE DISCHARGE CAPACITY OF STRIPDRAIN
• The example of discharge capacity of Nylex Stripdrain installed at various gradients with a
safety factor of F = 0.8 is shown below;
STRIPDRAIN DISCHARGE CAPACITY [l/min]
GRADIENT g% 1% 2% 3% 4% 5%
300mm 31 43 53 61 68
400mm 41 58 71 82 91
0
10
20
30
40
50
60
70
80
90
100
1% 2% 3% 4% 5%
SD300x40 SD400x40
*Data collected from KL-Seremban Highway Project, PLUS BERHAD, MAY 1991
THE OUTLET DISTANCE USING STRIPDRAIN
• The maximum outletting distance, Lmax, for the Stripdrain system considering the total
rate of in-flow as determined earlier can now be computed as follow;
Lmax = Qsd / Qtot
• Table below give the values of Lmax for Stripdrain 300mm and 400mm at various installed
gradients;
STRIPDRAIN 300mm DISCHARGE CAPACITY [l/min]
GRADIENT g% 1% 2% 3% 4% 5%
MEDIAN 247 349 427 493 551
STRIPDRAIN 400mm DISCHARGE CAPACITY [l/min]
GRADIENT g% 1% 2% 3% 4% 5%
SHOULDER 540 764 936 1081 1199
*Data collected from KL-Seremban Highway Project, PLUS BERHAD, MAY 1991
INSTALLATION GUIDE
CONNECTIONS & DETAILS
CONNECTIONS AND OUTLETS
Cut slot in pipe approximately 3 mm
narrower than cross-section of core being
used, in order to hold the drain in place as
shown. All pipe-to-geotextile joints must be
sealed with tapes
Stripdrain can be connected to concrete
pipe by cutting a hole in the pipe wall and
sealing around the Stripdrains with mortar
Stripdrain can be discharged into an
open ditch using a flume to protect the
open end. Alternatively, Stripdrain can be
discharged directly into a gravel-filled
trench
CONNECTION
TO SUMPS
Seal around
the Stripdrain
in the sump’s
opening with
mortar &
geotextile
FINAL LOOK OF
STRIPDRAIN END
AT THE SUMP
The sump wall fully plastered
Sump cover
CONNECTION
TO COLLECTOR PIPE
Seal filter
with tape
STRIPDRAlN upstream ends must be covered
over to ensure that soil cannot enter the drain. This
is done simply by cutting back the geotextile for
75-100mm and pulling back to expose the core. A
section of core is removed and the geotextile
folded back and taped (suggested tape: PVC
adhesive tape).
STRIPDRAIN is joined simply by slitting the filter
fabric for 75-100mm and overlapping the core. The
filter fabric is then pulled back over the joint and
taped to prevent soil entry.
PROJECT REFERENCES
and pictures
PROJECT REFERENCES LIST
• North-South Trunk Road Rehabilitation Works, Perak JKR Perak
• Temerloh Mentakab By-Pass, Pahang Ledan Nippon
• Ulu Perak Border Road Project Phase I& II KTA
• Jalan Santung Dungun, Terengganu JKR Dungun
• Jerangau Jabor Highway, Terengganu JKR Terengganu
• Jalan Pecah Rotan, Terengganu JKR Terengganu
• Felda Roads, Jempol District, Negeri Sembilan JKR Unit Felda
• Kemaman Roadworks, Terengganu JKR Kemaman
• Access Road to Taman Peransang, Selayang, Selangor Berakan Jurutera Perunding
• Tasik Titiwangsa Roads Kuala Lumpur DBKL
• Roadwork in Kuching, Sarawak Hevision
KL-SEREMBAN
HIGHWAY
CAHAYA SPK
SHAH ALAM
THE ENDVisit our website for more
www.nylexpolymer.com
NYLEX (M) BERHAD
Lot 16, Persiaran Selangor, Section 15,
40910 Shah Alam, Selangor Darul Ehsan
T: (603) 5519 1706
F: (603) 5519 9821
For enquiry, please call:
Mr Loh T: +6013-3460 520 E: lhl@nylex.com
Mr Naza T: +6017-3399 135 E:
nazaruddin@nylex.com

More Related Content

What's hot

Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Muhammad Irfan
 
Unit 1 cement
Unit 1  cementUnit 1  cement
Unit 1 cement
kiransomase1
 
Proctor Compaction Test
Proctor Compaction TestProctor Compaction Test
Proctor Compaction Test
A K
 
stress distribution in soils
stress distribution in soilsstress distribution in soils
stress distribution in soils
MUHAMMADSYAHMIFADZIL
 
Consolidation
ConsolidationConsolidation
Consolidation
MRINALJYOTI ADHYAPOK
 
Grouting
GroutingGrouting
Grouting
astraeaeos
 
Determination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil EngineeringDetermination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil Engineering
Abdullah Hayat Khan
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
sarhad university peshawer
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
Abdul Mutakaber Tareen
 
Class 7 Consolidation Test ( Geotechnical Engineering )
Class 7    Consolidation Test ( Geotechnical Engineering )Class 7    Consolidation Test ( Geotechnical Engineering )
Class 7 Consolidation Test ( Geotechnical Engineering )
Hossam Shafiq I
 
The role and importance of geotechnical engineering for a mining operation (1)
The role and importance of geotechnical engineering for a mining operation (1)The role and importance of geotechnical engineering for a mining operation (1)
The role and importance of geotechnical engineering for a mining operation (1)
Dr. Alex Vyazmensky
 
Effective stress
Effective stressEffective stress
Effective stress
sudheerKumarY1
 
Ground improvement technioques for high ways
Ground improvement technioques for high waysGround improvement technioques for high ways
Ground improvement technioques for high ways
AMIT SHIDURKAR
 
Control Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTSControl Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTS
comsats
 
Slope stability
Slope stabilitySlope stability
Slope stability
Dr. Pallavi Badry
 
Foundations
FoundationsFoundations
Foundations
Julian Swindell
 
Bearing capacity estimation rocks for foundation
Bearing capacity estimation rocks for foundationBearing capacity estimation rocks for foundation
Bearing capacity estimation rocks for foundation
FajruSied
 
Project report on pervious concrete
Project report on pervious concreteProject report on pervious concrete
Project report on pervious concrete
MDZAFARHASIB
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
SantistebanCampos
 
pre consolidation pressure
pre consolidation pressurepre consolidation pressure
pre consolidation pressure
Nachiketa Mithaiwala
 

What's hot (20)

Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
Geotechnical Engineering-II [Lec #8: Boussinesq Method - Rectangular Areas]
 
Unit 1 cement
Unit 1  cementUnit 1  cement
Unit 1 cement
 
Proctor Compaction Test
Proctor Compaction TestProctor Compaction Test
Proctor Compaction Test
 
stress distribution in soils
stress distribution in soilsstress distribution in soils
stress distribution in soils
 
Consolidation
ConsolidationConsolidation
Consolidation
 
Grouting
GroutingGrouting
Grouting
 
Determination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil EngineeringDetermination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil Engineering
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
 
Class 7 Consolidation Test ( Geotechnical Engineering )
Class 7    Consolidation Test ( Geotechnical Engineering )Class 7    Consolidation Test ( Geotechnical Engineering )
Class 7 Consolidation Test ( Geotechnical Engineering )
 
The role and importance of geotechnical engineering for a mining operation (1)
The role and importance of geotechnical engineering for a mining operation (1)The role and importance of geotechnical engineering for a mining operation (1)
The role and importance of geotechnical engineering for a mining operation (1)
 
Effective stress
Effective stressEffective stress
Effective stress
 
Ground improvement technioques for high ways
Ground improvement technioques for high waysGround improvement technioques for high ways
Ground improvement technioques for high ways
 
Control Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTSControl Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTS
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Foundations
FoundationsFoundations
Foundations
 
Bearing capacity estimation rocks for foundation
Bearing capacity estimation rocks for foundationBearing capacity estimation rocks for foundation
Bearing capacity estimation rocks for foundation
 
Project report on pervious concrete
Project report on pervious concreteProject report on pervious concrete
Project report on pervious concrete
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
pre consolidation pressure
pre consolidation pressurepre consolidation pressure
pre consolidation pressure
 

Similar to (2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)

(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
Nazaruddin Hairazi
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
rohinibjn
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
Sukhdarshan Singh
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
Shashank Gaurav
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
Groundwater Engineering Ltd
 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.ppt
AliGlal
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
Application of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwideApplication of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwide
Apollo Techno Industries Pvt Ltd
 
Technical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and WorldwideTechnical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and Worldwide
Apollo Techno Industries Pvt Ltd
 
Dust control measures
Dust control measuresDust control measures
Dust control measures
Safdar Ali
 
Well.Construction.pptx
Well.Construction.pptxWell.Construction.pptx
Dewatering
DewateringDewatering
Dewatering
Madhusudhan Reddy
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
kumarrajagp
 
Field control of compaction and compaction Equipment
Field control of compaction and compaction EquipmentField control of compaction and compaction Equipment
Field control of compaction and compaction Equipment
aishgup
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
Hassan Mohammed Hassan
 
Exploitation.pptx
Exploitation.pptxExploitation.pptx
Exploitation.pptx
Tribhuwan University
 
Road bridge & railway construction pdf
Road bridge & railway construction pdfRoad bridge & railway construction pdf
Road bridge & railway construction pdf
Saqib Imran
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
Abhimanyu Saraswat
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
Elsayed Amer
 
Cutter Suction Dredger
Cutter Suction DredgerCutter Suction Dredger
Cutter Suction Dredger
K Dibyajyoti Mohanta
 

Similar to (2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016) (20)

(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
(2) NYLEX STRIPDRAIN - SPORTFIELD EDITION (JULY15)
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.ppt
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Application of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwideApplication of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwide
 
Technical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and WorldwideTechnical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and Worldwide
 
Dust control measures
Dust control measuresDust control measures
Dust control measures
 
Well.Construction.pptx
Well.Construction.pptxWell.Construction.pptx
Well.Construction.pptx
 
Dewatering
DewateringDewatering
Dewatering
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Field control of compaction and compaction Equipment
Field control of compaction and compaction EquipmentField control of compaction and compaction Equipment
Field control of compaction and compaction Equipment
 
Compaction grouting hassan
Compaction  grouting hassanCompaction  grouting hassan
Compaction grouting hassan
 
Exploitation.pptx
Exploitation.pptxExploitation.pptx
Exploitation.pptx
 
Road bridge & railway construction pdf
Road bridge & railway construction pdfRoad bridge & railway construction pdf
Road bridge & railway construction pdf
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Cutter Suction Dredger
Cutter Suction DredgerCutter Suction Dredger
Cutter Suction Dredger
 

(2) NYLEX STRIPDRAIN - ROAD EDITION(JUN2016)

  • 1. NYLEX STRIPDRAIN™ Road Drainage Edition With Project Site Pictures and the we-tell-you-how
  • 3. STRIPDRAIN  is a prefabricated & flexible subsoil drainage system to remove underground seepage water  consists of a HDPE inner drain core completely wrapped with a non woven geotextile filter  alternative to conventional perforated pipe-gravel-geotextile systems  mainly used for sport fields, roads, highways, parks, golf courses, horse racing tracks, gardens, slopes
  • 4. CONVENTIONAL SUBSOIL DRAIN Aggregates Geotextiles overwrapped around subsoil pipe (Optional) Perforated Subsoil Pipe Geotextiles overwrapped around aggregates Sand Blanket Top Soil
  • 5. STRIPDRAIN STANDARD CROSS SECTION Sand Backfilling Sand Blanket Top Soil Nylex Stripdrain Compacted Earth
  • 6. ADVANTAGES OF NYLEX STRIPDRAIN  unique “Deep-fin” geometry ensures complete interception of seepage  very effective for lowering of ground water table  more than 90% surface area is permeable to water provides higher rate of drainage  prefabrication offers fast installation time  narrow trench width of 150mm requires less backfill  uses coarse sand backfill instead of gravel  cheaper system compare to pipe-gravel systems
  • 7. STANDARD SIZES Product Code Size (Width x Thickness x Length) SD100x40 100mm x 40mm x 50m SD200x40 200mm x 40mm x 50m SD300x40 300mm x 40mm x 50m SD400x40 400mm x 40mm x 50m SD500x40 500mm x 40mm x 25m
  • 8. DESIGN Estimation of in-flow into subsoil drain The discharge capacity of Stripdrain The outlet distance using Stripdrain
  • 9. THREE IMPORTANT FACTORS IN DESIGNING SUBSOIL DRAINAGE FOR ROAD HIGHWAYS Estimation of in-flow into subsoil drain The discharge capacity of Stripdrain The outlet distance using Stripdrain
  • 10. ESTIMATION OF IN-FLOW INTO SUB-SOIL DRAIN • Sub-soil drainage is provided at the edge of the highway or in the median and shoulder. • Installed near the surface, they alter the ground water regime so as to offer protection to the road structure and sub-grade. • The in-flow rate of water into these sub-surface drainage systems can be estimated by considering the following sources of water: a) Infiltration through the pavement b) Infiltration through the shoulder or median c) Ground water movements (a) (a) (b) (b) (b) (c)
  • 11. TOTAL IN-FLOW INTO SUB-SOIL DRAIN • From the estimation of the water sources, the total in-flow to the sub-soil drainage system can be estimated. • Consider the total in-flow to the two types of sub-soil drain locations, namely the side- table and the median. The side table The median
  • 12. TOTAL IN-FLOW INTO SUB-SOIL DRAIN (THE SIDE-TABLE) • The possible sources of water for the side-table are; a) Qpm, transmitted through one pavement ie. (a2) b) Qsm, infiltration through shoulder ie. (b3) c) Qsp, interception of cut slope seepage ie. from (c) • Therefore, the total in-flow is, Qtot = Qpm + Qsm + Qsp [l/min] (a1) (a2) (b1) (c) (b2) (b3)
  • 13. TOTAL IN-FLOW INTO SUB-SOIL DRAIN (THE MEDIAN) • The possible sources of water for the side-table are; a) 2 x Qpm, transmitted through TWO pavement ie. (a1) & (a2) b) Qsm, infiltration through median surface ie. (b2) c) 2 x Qsp, if seepage from water table control from two sides • Therefore, the total in-flow is, Qtot = 2(Qpm) + Qsm + 2(Qsp) [l/min] (a1) (a2) (b1) (c) (b2) (b3)
  • 14. THE DISCHARGE CAPACITY OF STRIPDRAIN • The discharge capacity of Nylex Stripdrain can be determined from the following hydraulic equation which has been simplified from Manning’s formula; Discharge capacity, Qsd = C x W x g^0.5 m3/s = C x W x g^0.5 x 60000 l/min C = constant taking into account Manning’s roughness factor n, hydraulic radius Rh, etc… For Stripdrain 40mm, C = 0.0213 W = width of Stripdrain in meter g = gradient of Stripdrain • A safety factor could be applied to Qsd to account for any siltation and reduction of the cross-sectional area which might occur when Stripdrain is buried in the ground. The recommended safety factor is F = 0.8.
  • 15. THE DISCHARGE CAPACITY OF STRIPDRAIN • The example of discharge capacity of Nylex Stripdrain installed at various gradients with a safety factor of F = 0.8 is shown below; STRIPDRAIN DISCHARGE CAPACITY [l/min] GRADIENT g% 1% 2% 3% 4% 5% 300mm 31 43 53 61 68 400mm 41 58 71 82 91 0 10 20 30 40 50 60 70 80 90 100 1% 2% 3% 4% 5% SD300x40 SD400x40 *Data collected from KL-Seremban Highway Project, PLUS BERHAD, MAY 1991
  • 16. THE OUTLET DISTANCE USING STRIPDRAIN • The maximum outletting distance, Lmax, for the Stripdrain system considering the total rate of in-flow as determined earlier can now be computed as follow; Lmax = Qsd / Qtot • Table below give the values of Lmax for Stripdrain 300mm and 400mm at various installed gradients; STRIPDRAIN 300mm DISCHARGE CAPACITY [l/min] GRADIENT g% 1% 2% 3% 4% 5% MEDIAN 247 349 427 493 551 STRIPDRAIN 400mm DISCHARGE CAPACITY [l/min] GRADIENT g% 1% 2% 3% 4% 5% SHOULDER 540 764 936 1081 1199 *Data collected from KL-Seremban Highway Project, PLUS BERHAD, MAY 1991
  • 18. CONNECTIONS AND OUTLETS Cut slot in pipe approximately 3 mm narrower than cross-section of core being used, in order to hold the drain in place as shown. All pipe-to-geotextile joints must be sealed with tapes Stripdrain can be connected to concrete pipe by cutting a hole in the pipe wall and sealing around the Stripdrains with mortar Stripdrain can be discharged into an open ditch using a flume to protect the open end. Alternatively, Stripdrain can be discharged directly into a gravel-filled trench
  • 19. CONNECTION TO SUMPS Seal around the Stripdrain in the sump’s opening with mortar & geotextile
  • 20. FINAL LOOK OF STRIPDRAIN END AT THE SUMP The sump wall fully plastered Sump cover
  • 22. Seal filter with tape STRIPDRAlN upstream ends must be covered over to ensure that soil cannot enter the drain. This is done simply by cutting back the geotextile for 75-100mm and pulling back to expose the core. A section of core is removed and the geotextile folded back and taped (suggested tape: PVC adhesive tape).
  • 23. STRIPDRAIN is joined simply by slitting the filter fabric for 75-100mm and overlapping the core. The filter fabric is then pulled back over the joint and taped to prevent soil entry.
  • 25. PROJECT REFERENCES LIST • North-South Trunk Road Rehabilitation Works, Perak JKR Perak • Temerloh Mentakab By-Pass, Pahang Ledan Nippon • Ulu Perak Border Road Project Phase I& II KTA • Jalan Santung Dungun, Terengganu JKR Dungun • Jerangau Jabor Highway, Terengganu JKR Terengganu • Jalan Pecah Rotan, Terengganu JKR Terengganu • Felda Roads, Jempol District, Negeri Sembilan JKR Unit Felda • Kemaman Roadworks, Terengganu JKR Kemaman • Access Road to Taman Peransang, Selayang, Selangor Berakan Jurutera Perunding • Tasik Titiwangsa Roads Kuala Lumpur DBKL • Roadwork in Kuching, Sarawak Hevision
  • 28. THE ENDVisit our website for more www.nylexpolymer.com NYLEX (M) BERHAD Lot 16, Persiaran Selangor, Section 15, 40910 Shah Alam, Selangor Darul Ehsan T: (603) 5519 1706 F: (603) 5519 9821 For enquiry, please call: Mr Loh T: +6013-3460 520 E: lhl@nylex.com Mr Naza T: +6017-3399 135 E: nazaruddin@nylex.com