SlideShare a Scribd company logo
Activity ID Activity Name Activity %
Complete
Original
Duration
BL1 Start BL1 Finish Start Finish
RL Waste Water Disposal Wells_2L-65ZRL Waste Water Disposal Wells_2L-65ZRL Waste Water Disposal Wells_2L-65Z 84 23-May-15 31-Aug-15 23-May-1531-Aug-15
A1000 2L-65Z 0% 1 23-May-15 23-May-15 23-May-1523-May-15
EARTHWORK & CIVILEARTHWORK & CIVILEARTHWORK & CIVIL 84 23-May-15 31-Aug-15 23-May-1531-Aug-15
EarthworksEarthworksEarthworks 84 23-May-15 31-Aug-15 23-May-1531-Aug-15
15334 Earthworks Fill from Company Designated Location, Haul & Compacted (with hauling distance from 0.5 KM to 15 KM)0% 16 24-May-15 08-Jun-15 24-May-15*08-Jun-15
15337 Earthworks Cut/Excavation 0% 1 11-Jun-15 11-Jun-15 11-Jun-15*11-Jun-15
15339 Earthworks Clearing & Grubbing 0% 1 23-May-15 23-May-15 23-May-15*23-May-15
15341 Mud Pit Excavation/Construction 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15
15342 Mud Pit Closing, Exclude Additional Dirt Fill 0% 1 31-Aug-15 31-Aug-15 31-Aug-15*31-Aug-15
15344 Dress-up Road & Well Pad 0% 1 31-Aug-15 31-Aug-15 31-Aug-15*31-Aug-15
Concrete WorksConcrete WorksConcrete Works 1 10-Jun-15 10-Jun-15 10-Jun-1510-Jun-15
15366 Install Pre Cast Concrete Box Culvert 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15
Structural steel WorksStructural steel WorksStructural steel Works 68 10-Jun-15 28-Aug-15 10-Jun-1528-Aug-15
15421 Install Steel/Wooden Cellar Box 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15
15422 Dismantle Steel/Wooden Cellar Box 0% 1 28-Aug-15 28-Aug-15 28-Aug-15*28-Aug-15
MiscallaneousMiscallaneousMiscallaneous 68 10-Jun-15 28-Aug-15 10-Jun-1528-Aug-15
15455 Install Conductor Pipe 24" 0% 1 15-Jun-15 15-Jun-15 15-Jun-15*15-Jun-15
15457 Install HDPE Geomembrane 0% 1 12-Jun-15 12-Jun-15 12-Jun-15*12-Jun-15
15458 Install Crane Mats (Wooden or Concrete or Steel or Other) Foundation0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15
15458-1 Crane Mats (Wooden or Concrete or Steel or Other) Foundation0% 1 28-Aug-15 28-Aug-15 28-Aug-15*28-Aug-15
SURVEYSURVEYSURVEY 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15
Survey WorkSurvey WorkSurvey Work 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15
15705 Survey Works - Topographical Survey and As Built Drawings 0% 1 09-Jun-15 09-Jun-15 09-Jun-15*09-Jun-15
SOIL & CIVIL TESTINGSOIL & CIVIL TESTINGSOIL & CIVIL TESTING 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15
Field TestingField TestingField Testing 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15
15707 Handheld Dynamic Cone Penetrometer Test, ASTM D7380 0% 1 09-Jun-15 09-Jun-15 09-Jun-15*09-Jun-15
RIG SCHEDULERIG SCHEDULERIG SCHEDULE 12 16-Aug-15 27-Aug-15 16-Aug-1527-Aug-15
A1010 Drilling 0% 12 16-Aug-15 27-Aug-15 16-Aug-15*27-Aug-15
May Jun Jul Aug Sep
Qtr 2, 2015 Qtr 3, 2015
31-Aug-15,...
31-Aug-15,...
31-Aug-15,...
10-Jun-15,...
28-Aug-15,...
28-Aug-15,...
09-Jun-15,...
09-Jun-15,...
09-Jun-15,...
09-Jun-15,...
27-Aug-15,...
RL Waste Water Disposal Wells_2L-65Z ADK HO OU 04-Jun-15 13:21
Actual Level of Effort
Project Baseline Bar
Primary Baseline
Actual Work
Remaining Work
Baseline Milestone
Milestone
% Complete
Summary
PT. Chevron Pacific Indonesia
Heavy Oil Operating Unit
Duri, Riau - Sumatera
TASK filter: All Activities
© Oracle Corporation

More Related Content

What's hot

Trend analysis 2016 17
Trend analysis 2016 17Trend analysis 2016 17
Trend analysis 2016 17
Guru Maruthi
 
المعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديكالمعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديك
Hani Saad
 
BASE FRAME FOR GIS & 13.8KV SWGR-3500MM
BASE FRAME FOR GIS & 13.8KV SWGR-3500MMBASE FRAME FOR GIS & 13.8KV SWGR-3500MM
BASE FRAME FOR GIS & 13.8KV SWGR-3500MMSYED BAKHTIARY
 
Oee mining
Oee miningOee mining
Oee mining
piyawut
 
Prtc project ppt.
Prtc project ppt.Prtc project ppt.
Prtc project ppt.
21403515
 
BE Project Presentation - Energy Conservation (Bosch Pune)
BE Project Presentation - Energy Conservation (Bosch Pune)BE Project Presentation - Energy Conservation (Bosch Pune)
BE Project Presentation - Energy Conservation (Bosch Pune)
Viknesh Subramaniyan
 
Tester utilisation definitions
Tester utilisation definitionsTester utilisation definitions
Tester utilisation definitionsStone Striker
 
Tester utilisation definitions
Tester utilisation definitionsTester utilisation definitions
Tester utilisation definitionsStone Striker
 
MPI Power Project October - Current Overview
MPI Power Project October - Current OverviewMPI Power Project October - Current Overview
MPI Power Project October - Current Overviewfasawe oluwafemi
 
Tech481_ProjectPresentation_GroupB - Copy
Tech481_ProjectPresentation_GroupB - CopyTech481_ProjectPresentation_GroupB - Copy
Tech481_ProjectPresentation_GroupB - CopyKyle Malec
 
Creative journey
Creative journeyCreative journey
Creative journey
Henry Kissick
 
Rotap sieve shaker
Rotap sieve shakerRotap sieve shaker
Rotap sieve shaker
Acmas Technologies Pvt. Ltd.
 
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
ARC research group
 
Gantt chart of Project schedule and management
Gantt chart of Project schedule and managementGantt chart of Project schedule and management
Gantt chart of Project schedule and management
adeel hamid
 
Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)dgonano
 

What's hot (20)

Trend analysis 2016 17
Trend analysis 2016 17Trend analysis 2016 17
Trend analysis 2016 17
 
X11
X11X11
X11
 
المعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديكالمعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديك
 
SALCO Presentation (KAPSARC)
SALCO Presentation (KAPSARC)SALCO Presentation (KAPSARC)
SALCO Presentation (KAPSARC)
 
BASE FRAME FOR GIS & 13.8KV SWGR-3500MM
BASE FRAME FOR GIS & 13.8KV SWGR-3500MMBASE FRAME FOR GIS & 13.8KV SWGR-3500MM
BASE FRAME FOR GIS & 13.8KV SWGR-3500MM
 
Oee mining
Oee miningOee mining
Oee mining
 
Prtc project ppt.
Prtc project ppt.Prtc project ppt.
Prtc project ppt.
 
BE Project Presentation - Energy Conservation (Bosch Pune)
BE Project Presentation - Energy Conservation (Bosch Pune)BE Project Presentation - Energy Conservation (Bosch Pune)
BE Project Presentation - Energy Conservation (Bosch Pune)
 
Tester utilisation definitions
Tester utilisation definitionsTester utilisation definitions
Tester utilisation definitions
 
Tester utilisation definitions
Tester utilisation definitionsTester utilisation definitions
Tester utilisation definitions
 
MPI Power Project October - Current Overview
MPI Power Project October - Current OverviewMPI Power Project October - Current Overview
MPI Power Project October - Current Overview
 
Tech481_ProjectPresentation_GroupB - Copy
Tech481_ProjectPresentation_GroupB - CopyTech481_ProjectPresentation_GroupB - Copy
Tech481_ProjectPresentation_GroupB - Copy
 
Creative journey
Creative journeyCreative journey
Creative journey
 
Rotap sieve shaker
Rotap sieve shakerRotap sieve shaker
Rotap sieve shaker
 
Rashid C_Synopsis_R6
Rashid C_Synopsis_R6Rashid C_Synopsis_R6
Rashid C_Synopsis_R6
 
Northgate Parking Rates
Northgate Parking RatesNorthgate Parking Rates
Northgate Parking Rates
 
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
Jordina Vidal, Oriol Vidal Enginyeria, Barcelona, Spain.
 
Additional Conveyor Project
Additional Conveyor ProjectAdditional Conveyor Project
Additional Conveyor Project
 
Gantt chart of Project schedule and management
Gantt chart of Project schedule and managementGantt chart of Project schedule and management
Gantt chart of Project schedule and management
 
Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)Mahoning Valley Connector Spillway Bridge (11-05-10)
Mahoning Valley Connector Spillway Bridge (11-05-10)
 

Similar to 2 l 65z

Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0Ahmed Mehrem
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Ahmed Mehrem
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Ahmed Mehrem
 
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdfMEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
ssuser7bbf24
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)Baig Ali
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
SajidMumtazGurmani
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
WaqarHussain183
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6MUHAMMAD SALEEM
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25Tofik Nazirov, B.Sc., PhD
 

Similar to 2 l 65z (20)

Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdfMEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
ScheduleRev- 6
ScheduleRev- 6ScheduleRev- 6
ScheduleRev- 6
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
 
Dashboard
DashboardDashboard
Dashboard
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 

Recently uploaded

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

2 l 65z

  • 1. Activity ID Activity Name Activity % Complete Original Duration BL1 Start BL1 Finish Start Finish RL Waste Water Disposal Wells_2L-65ZRL Waste Water Disposal Wells_2L-65ZRL Waste Water Disposal Wells_2L-65Z 84 23-May-15 31-Aug-15 23-May-1531-Aug-15 A1000 2L-65Z 0% 1 23-May-15 23-May-15 23-May-1523-May-15 EARTHWORK & CIVILEARTHWORK & CIVILEARTHWORK & CIVIL 84 23-May-15 31-Aug-15 23-May-1531-Aug-15 EarthworksEarthworksEarthworks 84 23-May-15 31-Aug-15 23-May-1531-Aug-15 15334 Earthworks Fill from Company Designated Location, Haul & Compacted (with hauling distance from 0.5 KM to 15 KM)0% 16 24-May-15 08-Jun-15 24-May-15*08-Jun-15 15337 Earthworks Cut/Excavation 0% 1 11-Jun-15 11-Jun-15 11-Jun-15*11-Jun-15 15339 Earthworks Clearing & Grubbing 0% 1 23-May-15 23-May-15 23-May-15*23-May-15 15341 Mud Pit Excavation/Construction 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15 15342 Mud Pit Closing, Exclude Additional Dirt Fill 0% 1 31-Aug-15 31-Aug-15 31-Aug-15*31-Aug-15 15344 Dress-up Road & Well Pad 0% 1 31-Aug-15 31-Aug-15 31-Aug-15*31-Aug-15 Concrete WorksConcrete WorksConcrete Works 1 10-Jun-15 10-Jun-15 10-Jun-1510-Jun-15 15366 Install Pre Cast Concrete Box Culvert 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15 Structural steel WorksStructural steel WorksStructural steel Works 68 10-Jun-15 28-Aug-15 10-Jun-1528-Aug-15 15421 Install Steel/Wooden Cellar Box 0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15 15422 Dismantle Steel/Wooden Cellar Box 0% 1 28-Aug-15 28-Aug-15 28-Aug-15*28-Aug-15 MiscallaneousMiscallaneousMiscallaneous 68 10-Jun-15 28-Aug-15 10-Jun-1528-Aug-15 15455 Install Conductor Pipe 24" 0% 1 15-Jun-15 15-Jun-15 15-Jun-15*15-Jun-15 15457 Install HDPE Geomembrane 0% 1 12-Jun-15 12-Jun-15 12-Jun-15*12-Jun-15 15458 Install Crane Mats (Wooden or Concrete or Steel or Other) Foundation0% 1 10-Jun-15 10-Jun-15 10-Jun-15*10-Jun-15 15458-1 Crane Mats (Wooden or Concrete or Steel or Other) Foundation0% 1 28-Aug-15 28-Aug-15 28-Aug-15*28-Aug-15 SURVEYSURVEYSURVEY 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15 Survey WorkSurvey WorkSurvey Work 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15 15705 Survey Works - Topographical Survey and As Built Drawings 0% 1 09-Jun-15 09-Jun-15 09-Jun-15*09-Jun-15 SOIL & CIVIL TESTINGSOIL & CIVIL TESTINGSOIL & CIVIL TESTING 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15 Field TestingField TestingField Testing 1 09-Jun-15 09-Jun-15 09-Jun-1509-Jun-15 15707 Handheld Dynamic Cone Penetrometer Test, ASTM D7380 0% 1 09-Jun-15 09-Jun-15 09-Jun-15*09-Jun-15 RIG SCHEDULERIG SCHEDULERIG SCHEDULE 12 16-Aug-15 27-Aug-15 16-Aug-1527-Aug-15 A1010 Drilling 0% 12 16-Aug-15 27-Aug-15 16-Aug-15*27-Aug-15 May Jun Jul Aug Sep Qtr 2, 2015 Qtr 3, 2015 31-Aug-15,... 31-Aug-15,... 31-Aug-15,... 10-Jun-15,... 28-Aug-15,... 28-Aug-15,... 09-Jun-15,... 09-Jun-15,... 09-Jun-15,... 09-Jun-15,... 27-Aug-15,... RL Waste Water Disposal Wells_2L-65Z ADK HO OU 04-Jun-15 13:21 Actual Level of Effort Project Baseline Bar Primary Baseline Actual Work Remaining Work Baseline Milestone Milestone % Complete Summary PT. Chevron Pacific Indonesia Heavy Oil Operating Unit Duri, Riau - Sumatera TASK filter: All Activities © Oracle Corporation