CONSTRUCTION OF BORDER CROSSING FACILITY AT TORKHAM
WORK PROGRAMME
Project Construction of Border Crossing Facility at Torkham
Employer Federal Board of Revenue (FBR), Government of Pakistan
PMC Consultant Terra Consultants
EPC Contractor National Logistics Cell (NLC)
CSC Consultants SMEC
Submitted By National Logistics Cell (NLC)
Prepared By
Al-Imam PMC and PID- JV
NLC’s Construction Management Consultants (CMC)
WORK PROGRAM SUMMARY
ActivityID ActivityName Original
Duration
Start Finish
Work Programme Torkham Final (16-Apr-2019)
Work Programme Torkham Final (16-Apr-2019) 1132 15-Feb-19 28-Sep-22
A1000 ProjectStart 0 15-Feb-19
A1020 ProjectEnd 0 28-Sep-22
Design and Costruction Drawings
Design and Costruction Drawings 125 15-Apr-19 06-Sep-19
IPC Schedule (Tentative)
IPC Schedule (Tentative) 1015 01-Jul-19 28-Sep-22
Moblization to the Site
Moblization to the Site 87 15-Feb-19 27-May-19
Area Clearance
Area Clearance 25 26-Apr-19 24-May-19
Site Grading Works Import, export and passengerYards including Rd Network
Site Grading Works Import, export and passengerYards including Rd Network
427 14-May-19 22-Sep-20
Import yard
Import yard 210 14-May-19 13-Jan-20
Cut
Cut 210 14-May-19 13-Jan-20
Fill
Fill 190 06-Jun-19 13-Jan-20
Export yard
Export yard 262 14-May-19 13-Mar-20
Cut
Cut 198 14-May-19 30-Dec-19
Fill
Fill 232 18-Jun-19 13-Mar-20
Site Grading Export yard primary inspection
Site Grading Export yard primary inspection 147 04-Apr-20 22-Sep-20
Site Grading Passenger Terminal
Site Grading Passenger Terminal 66 24-Oct-19 08-Jan-20
Procurement Schedule (Tentative)
Procurement Schedule (Tentative) 918 06-Jun-19 11-May-22
Structure (Concrete & Steel) Work Procurments
Structure (Concrete & Steel) Work Procurments 755 06-Jun-19 02-Nov-21
Civil Finishing Item Procurments
Civil Finishing Item Procurments 781 13-Nov-19 11-May-22
Electrical Procurments
Electrical Procurments 267 06-Feb-20 12-Dec-20
HVAC Procurments
HVAC Procurments 267 29-Jan-20 05-Dec-20
Plumbing Procurments
Plumbing Procurments 189 25-Jan-20 01-Sep-20
Fire Suppression Procurments
Fire Suppression Procurments 189 29-Jan-20 05-Sep-20
Vertical Transport System Procurments
Vertical Transport System Procurments 290 24-Jan-20 26-Dec-20
BAS/ICT Procurments
BAS/ICT Procurments 225 13-Oct-20 01-Jul-21
Security Equipment Procurments
Security Equipment Procurments 472 25-May-20 25-Nov-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Project Finish Date has been extended due to non-availibilty of land.
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 1 of 4 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A- BUILDINGS WORKS
A- BUILDINGS WORKS 904 30-Oct-19 19-Sep-22
Admin Block
Admin Block 460 30-Oct-19 17-Apr-21
Buisness Centre
Buisness Centre 370 30-Oct-19 02-Jan-21
Passenger Terminal Buildings
Passenger Terminal Buildings 463 03-Jan-20 25-Jun-21
SPS/ Quarantine Shed
SPS/ Quarantine Shed 230 14-Jan-20 07-Oct-20
Customs Lab
Customs Lab 176 14-Jan-20 06-Aug-20
Office Block
Office Block 264 10-Mar-20 11-Jan-21
Perishable Goods/ Cold Storage
Perishable Goods/ Cold Storage 213 14-Jan-20 17-Sep-20
Seized Goods Warehouse (Import)
Seized Goods Warehouse (Import) 288 14-Jan-20 14-Dec-20
Seized Goods Warehouse (Export)
Seized Goods Warehouse (Export) 281 12-Dec-19 04-Nov-20
Closed ExaminationArea
Closed ExaminationArea 260 14-Jan-20 11-Nov-20
Open ExaminationArea
Open ExaminationArea 256 14-Jan-20 07-Nov-20
C-Mart
C-Mart 161 01-Aug-20 05-Feb-21
Watch Tower (Import & Export)
Watch Tower (Import & Export) 194 14-Jan-20 26-Aug-20
Canine Main Building
Canine Main Building 153 24-Dec-19 18-Jun-20
Canine Small Units
Canine Small Units 138 24-Mar-20 31-Aug-20
Toll Booth (Single & Double)
Toll Booth (Single & Double) 231 12-Mar-20 07-Dec-20
Bomb Disposal Squad
Bomb Disposal Squad 151 14-Mar-20 07-Sep-20
Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard)
Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) 150 13-Mar-20 03-Sep-20
Canteen/ Driver's RestArea (Export Yard)
Canteen/ Driver's RestArea (Export Yard) 153 01-Aug-20 26-Jan-21
Public Toilets
Public Toilets 140 01-Aug-20 11-Jan-21
Clinic
Clinic 150 01-Aug-20 22-Jan-21
Guard Post
Guard Post 155 14-Mar-20 10-Sep-20
Substation/PMT Kiosk
Substation/PMT Kiosk 160 31-Dec-19 03-Jul-20
Mosque
Mosque 191 01-Aug-20 12-Mar-21
Fire Station
Fire Station 270 14-Jan-20 23-Nov-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 2 of 4 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
Operator's Room (Import & Export)
Operator's Room (Import & Export) 138 31-Dec-19 08-Jun-20
Facilitation Center
Facilitation Center 200 03-Jan-20 22-Aug-20
Gantry Scanner
Gantry Scanner 250 14-Apr-20 29-Jan-21
Bomb Difuse Chamber
Bomb Difuse Chamber 219 14-Apr-20 24-Dec-20
DRC
DRC 224 08-Sep-20 26-May-21
Agent Hall
Agent Hall 188 18-Sep-20 24-Apr-21
Power House (Import Yard & Export Yard)
Power House (Import Yard & Export Yard) 190 14-Jan-20 21-Aug-20
Inspector Examiner Hall
Inspector Examiner Hall 195 14-Jan-20 27-Aug-20
Pass Through Scanner
Pass Through Scanner 176 14-Mar-20 06-Oct-20
Vertical Transport System
Vertical Transport System 195 28-Dec-20 11-Aug-21
MEPAncillary Works
MEPAncillary Works 476 10-Sep-20 19-Mar-22
External Development Works
External Development Works 828 14-Jan-20 05-Sep-22
BAS/ICT Works
BAS/ICT Works 380 02-Jul-21 19-Sep-22
Security System Works
Security System Works 238 26-Nov-21 30-Aug-22
INFRASTRUCTURE WORKS
INFRASTRUCTURE WORKS 1071 15-Feb-19 18-Jul-22
A7840 ProjectStart 0 15-Feb-19
A7850 ProjectEnd 0 18-Jul-22
B- INFRSTRUCTURE DEVELOPMENT WORKS
B- INFRSTRUCTURE DEVELOPMENT WORKS 1016 20-Apr-19 18-Jul-22
ParkingArea ExportTerminal
ParkingArea ExportTerminal 578 14-Mar-20 17-Jan-22
ParkingArea ImportTerminal
ParkingArea ImportTerminal 547 14-Jan-20 12-Oct-21
AncillaryWorks
AncillaryWorks 1016 20-Apr-19 18-Jul-22
RoadFurniture
RoadFurniture 101 23-Mar-22 18-Jul-22
Supportive /Administrative Works
Supportive /Administrative Works 693 20-Apr-19 06-Jul-21
Retainingwalls andRiver TrainingWorks
Retainingwalls andRiver TrainingWorks 370 15-May-19 18-Jul-20
RetainingWalls
RetainingWalls 335 19-Jun-19 13-Jul-20
Surface Drainage
Surface Drainage 370 15-May-19 18-Jul-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 3 of 4 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
PedestrianBridge
PedestrianBridge 121 24-Mar-20 11-Aug-20
Bridge
Bridge 121 24-Mar-20 11-Aug-20
Stairs
Stairs 121 24-Mar-20 11-Aug-20
RoadWorks
RoadWorks 788 18-Jul-19 21-Jan-22
ExportYardRoadNetwork (Cl-200)
ExportYardRoadNetwork (Cl-200) 126 31-Jul-20 24-Dec-20
ImportYardRoadNetwork (Cl-100,101,101A,103,201)
ImportYardRoadNetwork (Cl-100,101,101A,103,201) 776 01-Aug-19 21-Jan-22
ImportYardCulverts for toRoadnetwork (C-2,3,5)
ImportYardCulverts for toRoadnetwork (C-2,3,5) 212 18-Jul-19 20-Mar-20
ExportYardCulverts for Roadnetwork (C-1,4)
ExportYardCulverts for Roadnetwork (C-1,4) 171 04-Apr-20 20-Oct-20
Bridges andFlyover
Bridges andFlyover 360 23-May-19 15-Jul-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 4 of 4 TASK filter: All Activities
© Oracle Corporation
DETAILED WORK PROGRAM
ActivityID ActivityName Original
Duration
Start Finish
Work Programme Torkham Final (16-Apr-2019)
Work Programme Torkham Final (16-Apr-2019) 1132 15-Feb-19 28-Sep-22
A1000 ProjectStart 0 15-Feb-19
A1020 ProjectEnd 0 28-Sep-22
Design and Costruction Drawings
Design and Costruction Drawings 125 15-Apr-19 06-Sep-19
A7190 Detailsand issuance of IFCbyNLC 95 15-Apr-19 02-Aug-19
A7200 Vetting of Design/Construction DrawingsbyCSC 30 29-Jun-19 02-Aug-19
A7210 FinalApprovalof Design/Construction Drawings 30 03-Aug-19 06-Sep-19
IPC Schedule (Tentative)
IPC Schedule (Tentative) 1015 01-Jul-19 28-Sep-22
A4910 Submission of IPC-1 0 01-Jul-19
A4920 Submission of IPC-2 0 02-Sep-19
A4930 Submission of IPC-3 0 01-Nov-19
A4940 Submission of IPC-4 0 01-Jan-20
A4950 Submission of IPC-5 0 02-Mar-20
A4960 Submission of IPC-6 0 01-May-20
A4970 Submission of IPC-7 0 01-Jul-20
A4980 Submission of IPC-8 0 01-Aug-20
A4990 Submission of IPC-9 0 01-Sep-20
A5000 Submission of IPC-10 0 01-Oct-20
A5010 Submission of IPC-11 0 02-Nov-20
A5020 Submission of IPC-12 0 01-Dec-20
A5030 Submission of IPC-13 0 01-Jan-21
A5040 Submission of IPC-14 0 01-Feb-21
A5050 Submission of IPC-15 0 01-Mar-21
A5060 Submission of IPC-16 0 01-Apr-21
A5070 Submission of IPC-17 0 01-Jun-21
A5080 Submission of IPC-18 0 02-Aug-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Project Finish Date has been extended due to non-availibilty of land.
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 1 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A5090 Submission of IPC-19 0 01-Oct-21
A5100 Submission of IPC-20 0 01-Nov-21
A5110 Submission of IPC-21 0 01-Dec-21
A5120 Submission of IPC-22 0 01-Jan-22
A5130 Submission of IPC-23 0 01-Feb-22
A5140 Submission of IPC-24 0 28-Sep-22
Moblization to the Site
Moblization to the Site 87 15-Feb-19 27-May-19
A1009 Mobilization 12 15-Feb-19 28-Feb-19
A1019 Possesion of Land 10 20-Mar-19 30-Mar-19
A1010 JointSurvey 20 17-Apr-19 09-May-19
Investigative Works
Investigative Works 37 15-Apr-19 27-May-19
A2400 GeotechnicalInvestigation forInfrastructure 37 15-Apr-19 27-May-19
A2410 GeotechnicalInvestigation forBuilding works 37 15-Apr-19 27-May-19
Area Clearance
Area Clearance 25 26-Apr-19 24-May-19
A7230 Removalof Tree 10 26-Apr-19 07-May-19
A1030 Clearing and Grubbing 20 02-May-19 24-May-19
Site Grading Works Import, export and passengerYards including Rd Network
Site Grading Works Import, export and passengerYards including Rd Network
427 14-May-19 22-Sep-20
Import yard
Import yard 210 14-May-19 13-Jan-20
Cut
Cut 210 14-May-19 13-Jan-20
A7880 25%cut PKG3 61 14-May-19 23-Jul-19
A7890 25%Cut PKG2 110 14-May-19 18-Sep-19
A7900 25%Cut PKG1 210 14-May-19 13-Jan-20
A7910 25%Cut PKG4 100 19-Sep-19 13-Jan-20
Fill
Fill 190 06-Jun-19 13-Jan-20
A7920 Fill50%PKG2&3 90 06-Jun-19 18-Sep-19
A7930 Fill50%PKG1&4 150 23-Jul-19 13-Jan-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Earth Cut delayed due to non-availibility or partial availibilty of land by FBR.
Earth Fill delayed due to dependency on Earth Cut.
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 2 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
Export yard
Export yard 262 14-May-19 13-Mar-20
Cut
Cut 198 14-May-19 30-Dec-19
A7940 40%CutPKG1 86 14-May-19 21-Aug-19
A7950 30%CutPKG2 58 22-Aug-19 28-Oct-19
A7960 30%CutPKG2 54 29-Oct-19 30-Dec-19
Fill
Fill 232 18-Jun-19 13-Mar-20
A7970 10%fillPKG1 61 18-Jun-19 27-Aug-19
A7980 90%fillPKG2 146 26-Sep-19 13-Mar-20
Site Grading Export yard primary inspection
Site Grading Export yard primary inspection 147 04-Apr-20 22-Sep-20
A7990 Earth cut(Hard ) 147 04-Apr-20 22-Sep-20
A8000 Scarification of existing rigid pavement 69 04-Apr-20 23-Jun-20
A8010 Earth Fillincluding cl200 64 09-May-20 22-Jul-20
Site Grading Passenger Terminal
Site Grading Passenger Terminal 66 24-Oct-19 08-Jan-20
A7860 Earth Cut 61 24-Oct-19 02-Jan-20
A7870 Earth Fill 56 05-Nov-19 08-Jan-20
Procurement Schedule (Tentative)
Procurement Schedule (Tentative) 918 06-Jun-19 11-May-22
Structure (Concrete & Steel) Work Procurments
Structure (Concrete & Steel) Work Procurments 755 06-Jun-19 02-Nov-21
A7680 Preparation of RFP forStructure Material 30 06-Jun-19 10-Jul-19
A7690 Response from Vendors 30 11-Jul-19 14-Aug-19
A7700 Evaluation of Proposals 20 15-Aug-19 06-Sep-19
A7710 Issuance of Purchase 50 07-Sep-19 04-Nov-19
A7720 Supplyof Structure MaterialatSite 625 05-Nov-19 02-Nov-21
Civil Finishing Item Procurments
Civil Finishing Item Procurments 781 13-Nov-19 11-May-22
A7620 Preparation of RFP forCivilFinishing Items 26 13-Nov-19 12-Dec-19
A7630 Response from Vendors 26 13-Dec-19 11-Jan-20
A7640 Evaluation of Proposals 17 11-Jan-20 31-Jan-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Earth Cut delayed due to non-availibility or partial availibilty of land by FBR.
Earth Cut delayed due to non-availibility or partial availibilty of land by FBR.
Earth Cut delayed due to non-availibility or partial availibilty of land by
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 3 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A7650 Issuance of Purchase Orderand LCOpening 56 31-Jan-20 06-Apr-20
A7670 Supplyof CivilFinishing Items 656 06-Apr-20 11-May-22
Electrical Procurments
Electrical Procurments 267 06-Feb-20 12-Dec-20
A7420 Preparation of RFP forElectricalEquipment 26 06-Feb-20 06-Mar-20
A7430 Response from EquipmentManufacturer 25 07-Mar-20 04-Apr-20
A7440 Evaluation of Proposals 17 06-Apr-20 24-Apr-20
A7450 Issuance of Purchase Orderand LCOpening 56 25-Apr-20 30-Jun-20
A7460 Manufacturing of Equipments 86 30-Jun-20 08-Oct-20
A7470 Shipping and Deliveryof Equipments 56 08-Oct-20 12-Dec-20
HVAC Procurments
HVAC Procurments 267 29-Jan-20 05-Dec-20
A7360 Preparation of RFP forHVACEquipment 26 29-Jan-20 28-Feb-20
A7370 Response from EquipmentManufacturer 25 28-Feb-20 28-Mar-20
A7380 Evaluation of Proposals 17 28-Mar-20 17-Apr-20
A7390 Issuance of Purchase Orderand LCOpening 56 17-Apr-20 22-Jun-20
A7400 Manufacturing of Equipments 86 23-Jun-20 30-Sep-20
A7410 Shipping and Deliveryof Equipments 56 01-Oct-20 05-Dec-20
Plumbing Procurments
Plumbing Procurments 189 25-Jan-20 01-Sep-20
A7480 Preparation of RFP forPlumbing Equipment 17 25-Jan-20 13-Feb-20
A7490 Response from EquipmentManufacturer 13 14-Feb-20 28-Feb-20
A7500 Evaluation of Proposals 13 29-Feb-20 14-Mar-20
A7510 Issuance of Purchase Orderand LCOpening 38 16-Mar-20 28-Apr-20
A7520 Manufacturing of Equipments 52 28-Apr-20 27-Jun-20
A7530 Shipping and Deliveryof Equipments 56 27-Jun-20 01-Sep-20
Fire Suppression Procurments
Fire Suppression Procurments 189 29-Jan-20 05-Sep-20
A7540 Preparation of RFP forFire Suppression Equipment 17 29-Jan-20 18-Feb-20
A7550 Response from EquipmentManufacturer 13 18-Feb-20 04-Mar-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 4 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A7560 Evaluation of Proposals 13 04-Mar-20 19-Mar-20
A7570 Issuance of Purchase Orderand LCOpening 38 19-Mar-20 02-May-20
A7580 Manufacturing of Equipments 52 02-May-20 02-Jul-20
A7590 Shipping and Deliveryof Equipments 56 02-Jul-20 05-Sep-20
Vertical Transport System Procurments
Vertical Transport System Procurments 290 24-Jan-20 26-Dec-20
A7300 Preparation of RFP forVerticalTransportSystem 30 24-Jan-20 27-Feb-20
A7310 Response from EquipmentManufacturer 30 28-Feb-20 02-Apr-20
A7320 Evaluation of Proposals 20 03-Apr-20 25-Apr-20
A7330 Issuance of Purchase Orderand LCOpening 60 27-Apr-20 04-Jul-20
A7340 Manufacturing of Equipments 90 06-Jul-20 17-Oct-20
A7350 Shipping and Deliveryof Equipments 60 19-Oct-20 26-Dec-20
BAS/ICT Procurments
BAS/ICT Procurments 225 13-Oct-20 01-Jul-21
A7270 Issuance of Purchase Orderand LCOpening 75 13-Oct-20 07-Jan-21
A7280 Manufacturing of Equipments 90 08-Jan-21 22-Apr-21
A7290 Shipping and Deliveryof Equipments 60 23-Apr-21 01-Jul-21
Security Equipment Procurments
Security Equipment Procurments 472 25-May-20 25-Nov-21
A4770 Issuance of Purchase Orderand LCOpening 163 25-May-20 30-Nov-20
A4780 Manufacturing of Equipments 172 30-Nov-20 18-Jun-21
A4790 Shipping and Deliveryof Equipments 138 18-Jun-21 25-Nov-21
A- BUILDINGS WORKS
A- BUILDINGS WORKS 904 30-Oct-19 19-Sep-22
Admin Block
Admin Block 460 30-Oct-19 17-Apr-21
A5270 GreyStructure Works 220 30-Oct-19 11-Jul-20
A5280 CivilFinishing Works 240 13-Jul-20 17-Apr-21
A5300 Plumbing Works 155 22-Aug-20 18-Feb-21
A5290 HVACWorks 169 25-Aug-20 10-Mar-21
A5320 ElectricalWorks 148 28-Aug-20 16-Feb-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Building Works also delayed due to dependancy on Earth Cut and Earth Fill activities.
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 5 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A5310 Fire Suppression System Works 146 09-Sep-20 25-Feb-21
Buisness Centre
Buisness Centre 370 30-Oct-19 02-Jan-21
A5330 GreyStructure Works 188 30-Oct-19 04-Jun-20
A5340 CivilFinishing Works 245 24-Mar-20 02-Jan-21
A5350 Plumbing Works 159 09-May-20 10-Nov-20
A5360 HVACWorks 160 13-May-20 16-Nov-20
A5380 Fire Suppression System Works 155 13-May-20 10-Nov-20
A5370 ElectricalWorks 176 21-May-20 12-Dec-20
Passenger Terminal Buildings
Passenger Terminal Buildings 463 03-Jan-20 25-Jun-21
A5390 GreyStructure Works 231 03-Jan-20 29-Sep-20
A5400 CivilFinishing Works 275 08-Aug-20 25-Jun-21
A5430 Fire Suppression System Works 185 13-Oct-20 17-May-21
A5410 Plumbing Works 188 21-Oct-20 27-May-21
A5420 HVACWorks 194 24-Oct-20 08-Jun-21
A5440 ElectricalWorks 198 28-Oct-20 15-Jun-21
SPS/ Quarantine Shed
SPS/ Quarantine Shed 230 14-Jan-20 07-Oct-20
A5690 GreyStructure Works 100 14-Jan-20 08-May-20
A5700 CivilFinishing Works 130 09-May-20 07-Oct-20
A5710 Plumbing Works 85 08-Jun-20 14-Sep-20
A5720 HVACWorks 79 15-Jun-20 14-Sep-20
A5740 ElectricalWorks 91 16-Jun-20 30-Sep-20
A5730 Fire Suppression System Works 75 26-Jun-20 22-Sep-20
Customs Lab
Customs Lab 176 14-Jan-20 06-Aug-20
A5870 GreyStructure Works 81 14-Jan-20 17-Apr-20
A5880 CivilFinishing Works 95 17-Apr-20 06-Aug-20
A5890 Plumbing Works 63 09-May-20 21-Jul-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 6 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A5920 ElectricalWorks 66 12-May-20 28-Jul-20
A5900 HVACWorks 54 13-May-20 15-Jul-20
A5910 Fire Suppression System Works 50 23-May-20 21-Jul-20
Office Block
Office Block 264 10-Mar-20 11-Jan-21
A5750 GreyStructure Works 125 10-Mar-20 01-Aug-20
A5760 CivilFinishing Works 139 03-Aug-20 11-Jan-21
A5770 Plumbing Works 94 04-Sep-20 23-Dec-20
A5800 ElectricalWorks 98 09-Sep-20 31-Dec-20
A5780 HVACWorks 85 12-Sep-20 19-Dec-20
A5790 Fire Suppression System Works 81 24-Sep-20 28-Dec-20
Perishable Goods/ Cold Storage
Perishable Goods/ Cold Storage 213 14-Jan-20 17-Sep-20
A5930 GreyStructure Works 100 14-Jan-20 08-May-20
A5940 CivilFinishing Works 113 09-May-20 17-Sep-20
A5950 Plumbing Works 69 30-May-20 19-Aug-20
A5960 HVACWorks 73 03-Jun-20 26-Aug-20
A5980 ElectricalWorks 76 08-Jun-20 04-Sep-20
A5970 Fire Suppression System Works 58 15-Jun-20 20-Aug-20
Seized Goods Warehouse (Import)
Seized Goods Warehouse (Import) 288 14-Jan-20 14-Dec-20
A5450 GreyStructure Works 125 14-Jan-20 06-Jun-20
A5460 CivilFinishing Works 163 08-Jun-20 14-Dec-20
A5480 HVACWorks 88 09-Jul-20 19-Oct-20
A5470 Plumbing Works 85 10-Jul-20 17-Oct-20
A5490 Fire Suppression System Works 81 21-Jul-20 23-Oct-20
A5500 ElectricalWorks 94 05-Aug-20 21-Nov-20
Seized Goods Warehouse (Export)
Seized Goods Warehouse (Export) 281 12-Dec-19 04-Nov-20
A6110 GreyStructure Works 125 12-Dec-19 05-May-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 7 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A6120 CivilFinishing Works 156 06-May-20 04-Nov-20
A6140 HVACWorks 88 06-Jun-20 16-Sep-20
A6130 Plumbing Works 85 08-Jun-20 15-Sep-20
A6150 Fire Suppression System Works 81 18-Jun-20 21-Sep-20
A6160 ElectricalWorks 94 29-Jun-20 15-Oct-20
Closed ExaminationArea
Closed ExaminationArea 260 14-Jan-20 11-Nov-20
A5510 GreyStructure Works 113 14-Jan-20 23-May-20
A5520 CivilFinishing Works 148 23-May-20 11-Nov-20
A5530 Plumbing Works 75 22-Jun-20 17-Sep-20
A5560 ElectricalWorks 96 29-Jun-20 19-Oct-20
A5540 HVACWorks 85 03-Jul-20 10-Oct-20
A5550 Fire Suppression System Works 81 14-Jul-20 16-Oct-20
Open ExaminationArea
Open ExaminationArea 256 14-Jan-20 07-Nov-20
A5570 GreyStructure Works 113 14-Jan-20 23-May-20
A5580 CivilFinishing Works 144 23-May-20 07-Nov-20
A5590 Plumbing Works 75 22-Jun-20 17-Sep-20
A5620 ElectricalWorks 96 29-Jun-20 19-Oct-20
A5600 HVACWorks 85 02-Jul-20 09-Oct-20
A5610 Fire Suppression System Works 81 14-Jul-20 16-Oct-20
C-Mart
C-Mart 161 01-Aug-20 05-Feb-21
A5630 GreyStructure Works 75 01-Aug-20 27-Oct-20
A5640 CivilFinishing Works 86 28-Oct-20 05-Feb-21
A5650 Plumbing Works 59 18-Nov-20 26-Jan-21
A5680 ElectricalWorks 63 21-Nov-20 02-Feb-21
A5660 HVACWorks 54 23-Nov-20 25-Jan-21
A5670 Fire Suppression System Works 56 26-Nov-20 30-Jan-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 8 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
Watch Tower (Import & Export)
Watch Tower (Import & Export) 194 14-Jan-20 26-Aug-20
A5810 GreyStructure Works 119 14-Jan-20 30-May-20
A5820 CivilFinishing Works 156 26-Feb-20 26-Aug-20
A7780 Plumbing Works 119 12-Mar-20 28-Jul-20
A5860 ElectricalWorks 94 17-Apr-20 04-Aug-20
Canine Main Building
Canine Main Building 153 24-Dec-19 18-Jun-20
A5990 GreyStructure Works 84 24-Dec-19 30-Mar-20
A6000 CivilFinishing Works 69 30-Mar-20 18-Jun-20
A6010 Plumbing Works 44 14-Apr-20 03-Jun-20
A6020 HVACWorks 43 16-Apr-20 05-Jun-20
A6040 ElectricalWorks 50 16-Apr-20 13-Jun-20
A6030 Fire Suppression System Works 40 21-Apr-20 06-Jun-20
Canine Small Units
Canine Small Units 138 24-Mar-20 31-Aug-20
A6050 GreyStructure Works 75 24-Mar-20 18-Jun-20
A6060 CivilFinishing Works 63 19-Jun-20 31-Aug-20
A6100 ElectricalWorks 46 29-Jun-20 21-Aug-20
A6080 HVACWorks 41 01-Jul-20 18-Aug-20
A7790 Plumbing Works 44 01-Jul-20 20-Aug-20
A6090 Fire Suppression System Works 38 03-Jul-20 15-Aug-20
Toll Booth (Single & Double)
Toll Booth (Single & Double) 231 12-Mar-20 07-Dec-20
A6170 GreyStructure Works 106 12-Mar-20 14-Jul-20
A6180 CivilFinishing Works 125 14-Jul-20 07-Dec-20
A6190 Plumbing Works 81 12-Aug-20 14-Nov-20
A6200 HVACWorks 84 17-Aug-20 21-Nov-20
A6220 ElectricalWorks 91 19-Aug-20 03-Dec-20
A6210 Fire Suppression System Works 75 26-Aug-20 21-Nov-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 9 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
Bomb Disposal Squad
Bomb Disposal Squad 151 14-Mar-20 07-Sep-20
A6230 GreyStructure Works 75 14-Mar-20 09-Jun-20
A6240 CivilFinishing Works 76 10-Jun-20 07-Sep-20
A6250 Plumbing Works 56 19-Jun-20 24-Aug-20
A6260 HVACWorks 54 24-Jun-20 26-Aug-20
A6280 ElectricalWorks 56 29-Jun-20 02-Sep-20
A6270 Fire Suppression System Works 50 01-Jul-20 28-Aug-20
Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard)
Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) 150 13-Mar-20 03-Sep-20
A6290 GreyStructure Works 60 13-Mar-20 21-May-20
A6300 CivilFinishing Works 90 22-May-20 03-Sep-20
A6310 Plumbing Works 38 01-Jun-20 15-Jul-20
A6340 ElectricalWorks 50 04-Jun-20 01-Aug-20
A6330 Fire Suppression System Works 43 09-Jun-20 28-Jul-20
A6320 HVACWorks 25 04-Jul-20 03-Aug-20
Canteen/ Driver's RestArea (Export Yard)
Canteen/ Driver's RestArea (Export Yard) 153 01-Aug-20 26-Jan-21
A6350 GreyStructure Works 75 01-Aug-20 27-Oct-20
A6360 CivilFinishing Works 76 28-Oct-20 25-Jan-21
A6370 Plumbing Works 59 18-Nov-20 26-Jan-21
A6400 ElectricalWorks 56 18-Nov-20 22-Jan-21
A6380 HVACWorks 54 20-Nov-20 21-Jan-21
A6390 Fire Suppression System Works 50 23-Nov-20 20-Jan-21
Public Toilets
Public Toilets 140 01-Aug-20 11-Jan-21
A6410 GreyStructure Works 60 01-Aug-20 09-Oct-20
A6420 CivilFinishing Works 80 10-Oct-20 11-Jan-21
A6430 Plumbing Works 38 24-Oct-20 07-Dec-20
A6440 HVACWorks 41 31-Oct-20 18-Dec-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 10 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A6460 ElectricalWorks 46 31-Oct-20 24-Dec-20
Clinic
Clinic 150 01-Aug-20 22-Jan-21
A6470 GreyStructure Works 69 01-Aug-20 20-Oct-20
A6480 CivilFinishing Works 81 20-Oct-20 22-Jan-21
A6490 Plumbing Works 50 06-Nov-20 04-Jan-21
A6510 Fire Suppression System Works 46 11-Nov-20 04-Jan-21
A6520 ElectricalWorks 48 11-Nov-20 05-Jan-21
A6500 HVACWorks 54 16-Nov-20 16-Jan-21
Guard Post
Guard Post 155 14-Mar-20 10-Sep-20
A6530 GreyStructure Works 75 14-Mar-20 09-Jun-20
A6540 CivilFinishing Works 80 10-Jun-20 10-Sep-20
A6580 ElectricalWorks 44 17-Jun-20 06-Aug-20
A6550 Plumbing Works 38 18-Jun-20 31-Jul-20
A6560 HVACWorks 35 18-Jun-20 29-Jul-20
A6570 Fire Suppression System Works 31 19-Jun-20 25-Jul-20
Substation/PMT Kiosk
Substation/PMT Kiosk 160 31-Dec-19 03-Jul-20
A6590 GreyStructure Works 75 31-Dec-19 26-Mar-20
A6600 CivilFinishing Works 85 27-Mar-20 03-Jul-20
A6610 Plumbing Works 50 06-Apr-20 03-Jun-20
A6630 Fire Suppression System Works 48 08-Apr-20 02-Jun-20
A6620 HVACWorks 53 10-Apr-20 10-Jun-20
A6640 ElectricalWorks 56 14-Apr-20 18-Jun-20
Mosque
Mosque 191 01-Aug-20 12-Mar-21
A6650 GreyStructure Works 80 01-Aug-20 02-Nov-20
A6660 CivilFinishing Works 90 03-Nov-20 15-Feb-21
A6670 Plumbing Works 94 17-Nov-20 06-Mar-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 11 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A6700 ElectricalWorks 96 20-Nov-20 12-Mar-21
A6680 HVACWorks 89 27-Nov-20 10-Mar-21
A6690 Fire Suppression System Works 88 27-Nov-20 09-Mar-21
Fire Station
Fire Station 270 14-Jan-20 23-Nov-20
A6710 GreyStructure Works 110 14-Jan-20 20-May-20
A6720 CivilFinishing Works 130 21-May-20 19-Oct-20
A6730 Plumbing Works 125 23-Jun-20 16-Nov-20
A6760 ElectricalWorks 131 23-Jun-20 23-Nov-20
A6740 HVACWorks 123 03-Jul-20 23-Nov-20
A6750 Fire Suppression System Works 119 03-Jul-20 19-Nov-20
Operator's Room (Import & Export)
Operator's Room (Import & Export) 138 31-Dec-19 08-Jun-20
A6770 GreyStructure Works 63 31-Dec-19 12-Mar-20
A6780 CivilFinishing Works 75 12-Mar-20 08-Jun-20
A6820 ElectricalWorks 56 27-Mar-20 01-Jun-20
A6810 Fire Suppression System Works 54 28-Mar-20 29-May-20
A6790 Plumbing Works 50 30-Mar-20 27-May-20
A6800 HVACWorks 49 02-Apr-20 28-May-20
Facilitation Center
Facilitation Center 200 03-Jan-20 22-Aug-20
A6830 GreyStructure Works 94 03-Jan-20 21-Apr-20
A6840 CivilFinishing Works 106 21-Apr-20 22-Aug-20
A6850 Plumbing Works 75 01-May-20 28-Jul-20
A6880 ElectricalWorks 85 02-May-20 10-Aug-20
A6870 Fire Suppression System Works 71 06-May-20 28-Jul-20
A6860 HVACWorks 80 13-May-20 14-Aug-20
Gantry Scanner
Gantry Scanner 250 14-Apr-20 29-Jan-21
A6890 GreyStructure Works 120 14-Apr-20 31-Aug-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 12 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A6900 CivilFinishing Works 130 01-Sep-20 29-Jan-21
A7220 Plumbing Works 89 01-Sep-20 12-Dec-20
A7250 HVACWorks 91 12-Sep-20 28-Dec-20
A6940 ElectricalWorks 88 15-Sep-20 25-Dec-20
A6930 Fire Suppression System Works 81 30-Sep-20 02-Jan-21
Bomb Difuse Chamber
Bomb Difuse Chamber 219 14-Apr-20 24-Dec-20
A6950 GreyStructure Works 106 14-Apr-20 15-Aug-20
A6960 CivilFinishing Works 113 15-Aug-20 24-Dec-20
A6970 Plumbing Works 85 26-Aug-20 02-Dec-20
A6990 Fire Suppression System Works 81 27-Aug-20 30-Nov-20
A7000 ElectricalWorks 89 29-Aug-20 11-Dec-20
DRC
DRC 224 08-Sep-20 26-May-21
A7010 GreyStructure Works 109 08-Sep-20 12-Jan-21
A7020 CivilFinishing Works 115 12-Jan-21 26-May-21
A7030 Plumbing Works 88 22-Jan-21 04-May-21
A7050 Fire Suppression System Works 85 23-Jan-21 03-May-21
A7040 HVACWorks 90 26-Jan-21 10-May-21
A7060 ElectricalWorks 95 28-Jan-21 19-May-21
Agent Hall
Agent Hall 188 18-Sep-20 24-Apr-21
A7070 GreyStructure Works 88 18-Sep-20 29-Dec-20
A7080 CivilFinishing Works 100 29-Dec-20 24-Apr-21
A7110 Fire Suppression System Works 63 11-Jan-21 25-Mar-21
A7100 HVACWorks 69 13-Jan-21 02-Apr-21
A7090 Plumbing Works 63 14-Jan-21 27-Mar-21
A7120 ElectricalWorks 75 15-Jan-21 13-Apr-21
Power House (Import Yard & Export Yard)
Power House (Import Yard & Export Yard) 190 14-Jan-20 21-Aug-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 13 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A7130 GreyStructure Works 90 14-Jan-20 27-Apr-20
A7140 CivilFinishing Works 100 28-Apr-20 21-Aug-20
A7240 Plumbing Works 56 28-Apr-20 02-Jul-20
A7810 Fire Suppression System Works 60 28-Apr-20 06-Jul-20
A7180 ElectricalWorks 63 12-May-20 23-Jul-20
A7160 HVACWorks 58 16-May-20 22-Jul-20
Inspector Examiner Hall
Inspector Examiner Hall 195 14-Jan-20 27-Aug-20
A7150 GreyStructure Works 80 14-Jan-20 15-Apr-20
A7740 CivilFinishing Works 95 25-Apr-20 14-Aug-20
A7800 ElectricalWorks 85 09-May-20 15-Aug-20
A7820 Fire Suppression System Works 81 09-May-20 12-Aug-20
A7260 HVACWorks 79 13-May-20 13-Aug-20
A7760 Plumbing Works 88 18-May-20 27-Aug-20
Pass Through Scanner
Pass Through Scanner 176 14-Mar-20 06-Oct-20
A7170 GreyStructure Works 81 14-Mar-20 17-Jun-20
A7750 CivilFinishing Works 94 17-Jun-20 03-Oct-20
A7830 Fire Suppression System Works 66 03-Jul-20 18-Sep-20
A5840 ElectricalWorks 69 04-Jul-20 22-Sep-20
A7770 Plumbing Works 76 09-Jul-20 06-Oct-20
Vertical Transport System
Vertical Transport System 195 28-Dec-20 11-Aug-21
A3210 Installation of PassengerLift 75 28-Dec-20 24-Mar-21
A3240 Installation of Fire Tendersin Fire Station 75 04-Jan-21 01-Apr-21
A3220 Installation of ForkLifter 90 14-Jan-21 28-Apr-21
A3230 Installation of Reach Stacker 90 29-Apr-21 11-Aug-21
A3260 VerticalTransportSystem Completion 0 11-Aug-21
MEPAncillary Works
MEPAncillary Works 476 10-Sep-20 19-Mar-22
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 14 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A7730 Installation of Fire Suppression Equipments,Valves 476 10-Sep-20 19-Mar-22
External Development Works
External Development Works 828 14-Jan-20 05-Sep-22
A3470 Dismentaling of Existing Building 90 14-Jan-20 27-Apr-20
A3480 Formation of Surface Levels 75 12-Feb-20 08-May-20
A3590 G.IFence Installation 175 13-Jun-20 02-Jan-21
A3600 MeralShed Installation 148 01-Aug-20 20-Jan-21
A3490 Reconstruction 180 31-Oct-20 28-May-21
A3510 Weigh Bridge 120 30-Nov-20 17-Apr-21
A3530 Pedestrian WalkWay/UnderPass 150 12-Jan-21 06-Jul-21
A3540 SteelCanopyOverprimaryscanner 125 12-Jan-21 07-Jun-21
A3520 R.C.CBoundryWall(200mm Wide) 150 16-Feb-21 10-Aug-21
A3500 Sewarage,Drainage,Irrigation and Watersupplyworks 250 10-Aug-21 28-May-22
A3570 R.C.CBoundryWall(700mm Wide) 190 10-Aug-21 19-Mar-22
A5180 OHTof DifferentCapacityComplete in allRespect 90 10-Aug-21 23-Nov-21
A5240 UGWTof DifferentCapacityComplete in allRespect 90 10-Aug-21 23-Nov-21
A3610 DieselGeneratorsInstallation 94 10-Aug-21 27-Nov-21
A3620 Substation EquipmentInstallation 120 10-Aug-21 28-Dec-21
A3550 Subgrade and Pavementworks 75 02-Sep-21 29-Nov-21
A3560 ExternalElectrification 240 29-Nov-21 05-Sep-22
A5830 ExternalPlumbing Works 200 29-Nov-21 20-Jul-22
A3580 ExternalDevelopmentWorksFinish Milestone 0 05-Sep-22
BAS/ICT Works
BAS/ICT Works 380 02-Jul-21 19-Sep-22
A3320 Installation of Fire Detection andAlarm System 288 02-Jul-21 02-Jun-22
A3360 Installation ofAccessControlSystem 263 31-Jul-21 02-Jun-22
A3370 Installation of IPCCTV System 238 14-Aug-21 18-May-22
A3380 Installation of ServerRoom Equipment 235 26-Aug-21 27-May-22
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 15 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A3390 Installation of Cable &ManagmentSystem 220 10-Sep-21 24-May-22
A3400 Installation of Voice TelephonyEquipment 190 16-Oct-21 26-May-22
A3410 Installation of WirelessAcessPoints 200 02-Nov-21 23-Jun-22
A3420 Installation of Data Centre Equipment 45 23-Dec-21 12-Feb-22
A3430 Installation of Servers 35 13-Jan-22 23-Feb-22
A3440 Installation of Storage Equipmentsand Devices 35 28-Jan-22 10-Mar-22
A3450 Configuration,Testing and Commisioning 75 23-Jun-22 19-Sep-22
A3460 IBAS/ICTFinish Milestone 0 19-Sep-22
Security System Works
Security System Works 238 26-Nov-21 30-Aug-22
A4800 Installation of SecurityEquipments 238 26-Nov-21 30-Aug-22
A4810 SecuritySystem WorksFinish Milestone 0 30-Aug-22
INFRASTRUCTURE WORKS
INFRASTRUCTURE WORKS 1071 15-Feb-19 18-Jul-22
A7840 ProjectStart 0 15-Feb-19
A7850 ProjectEnd 0 18-Jul-22
B- INFRSTRUCTURE DEVELOPMENT WORKS
B- INFRSTRUCTURE DEVELOPMENT WORKS 1016 20-Apr-19 18-Jul-22
ParkingArea ExportTerminal
ParkingArea ExportTerminal 578 14-Mar-20 17-Jan-22
A1790 Improved Subgrade 95 14-Mar-20 02-Jul-20
A1800 Sub Base 127 28-Apr-20 22-Sep-20
A1820 Rigid Pavement50% 99 09-Nov-20 03-Mar-21
A1840 Rigid Pavement50%(Sqm ) 99 04-Mar-21 26-Jun-21
A1830 Laying of Tuff PaveroverSand Cushion 83 13-Oct-21 17-Jan-22
ParkingArea ImportTerminal
ParkingArea ImportTerminal 547 14-Jan-20 12-Oct-21
A1851 Improved Subgrade 57 14-Jan-20 19-Mar-20
A1852 Sub Base 98 31-Jan-20 23-May-20
A1860 Rigid Pavement 144 25-May-20 07-Nov-20
A1870 Laying of Tuff PaveroverSand Cushion 115 01-Jun-21 12-Oct-21
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 16 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
AncillaryWorks
AncillaryWorks 1016 20-Apr-19 18-Jul-22
RoadFurniture
RoadFurniture 101 23-Mar-22 18-Jul-22
A1699 25%Lane Marking and Signage 25 23-Mar-22 20-Apr-22
A1700 25%Lane Marking and Signage 25 21-Apr-22 20-May-22
A1701 25%Lane Marking and Signage 25 20-May-22 18-Jun-22
A1702 25%Lane Marking and Signage 25 18-Jun-22 18-Jul-22
Supportive /Administrative Works
Supportive /Administrative Works 693 20-Apr-19 06-Jul-21
A1960 Shifting of Utilities 164 20-Apr-19 28-Oct-19
A1980 Construction of Diversions 167 20-Apr-19 31-Oct-19
A1990 Establishmentof Laboratories 84 20-Apr-19 26-Jul-19
A1970 Rehabilitation of TaxiStand 37 25-May-21 06-Jul-21
Retainingwalls andRiver TrainingWorks
Retainingwalls andRiver TrainingWorks 370 15-May-19 18-Jul-20
RetainingWalls
RetainingWalls 335 19-Jun-19 13-Jul-20
A1450 StructuralExcavation 258 19-Jun-19 14-Apr-20
A1460 Lean Concrete 294 06-Jul-19 12-Jun-20
A1470 Plum Concrete 50% 150 10-Aug-19 31-Jan-20
A1480 BackFilling including granularfilterlayer 253 14-Sep-19 04-Jul-20
A1500 Grouted Rip Rap 230 19-Oct-19 13-Jul-20
A1490 Plum Concrete 50% 167 17-Dec-19 27-Jun-20
Surface Drainage
Surface Drainage 370 15-May-19 18-Jul-20
Conduit
Conduit 160 15-May-19 16-Nov-19
A1571 StructuralExcavation 51 15-May-19 12-Jul-19
A1572 Lean Concrete 50 15-Jul-19 10-Sep-19
A1573 ConcreteA-1,underground 36 07-Aug-19 17-Sep-19
A1574 Concrete ClassA-3 36 07-Aug-19 17-Sep-19
A1610 Rip Rap ClassA 59 29-Aug-19 05-Nov-19
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 17 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A1620 GranularBackFill 43 28-Sep-19 16-Nov-19
RoadSide Drains includingcrossingculverts
RoadSide Drains includingcrossingculverts 250 02-Oct-19 18-Jul-20
A1520 StructuralExcavation 129 02-Oct-19 28-Feb-20
A1525 Lean Concrete 165 10-Oct-19 18-Apr-20
A1530 ConcreteA-3 on Ground 167 30-Nov-19 11-Jun-20
A1551 BackFilling 39 04-Jun-20 18-Jul-20
PedestrianBridge
PedestrianBridge 121 24-Mar-20 11-Aug-20
Bridge
Bridge 121 24-Mar-20 11-Aug-20
A1630 Foundation Works 23 24-Mar-20 18-Apr-20
A1640 Fabrication 78 15-Apr-20 14-Jul-20
A1650 Finishes 45 20-Jun-20 11-Aug-20
Stairs
Stairs 121 24-Mar-20 11-Aug-20
A1671 Foundation Works 23 24-Mar-20 18-Apr-20
A1672 Fabrication 78 15-Apr-20 14-Jul-20
A1673 Finishes 45 20-Jun-20 11-Aug-20
RoadWorks
RoadWorks 788 18-Jul-19 21-Jan-22
ExportYardRoadNetwork (Cl-200)
ExportYardRoadNetwork (Cl-200) 126 31-Jul-20 24-Dec-20
A1191 Improved Subgrade 74 31-Jul-20 24-Oct-20
A1192 GranularSub -base 61 28-Aug-20 06-Nov-20
A1193 Lean Concrete 65 02-Oct-20 16-Dec-20
A1196 Concrete A-3 64 12-Oct-20 24-Dec-20
ImportYardRoadNetwork (Cl-100,101,101A,103,201)
ImportYardRoadNetwork (Cl-100,101,101A,103,201) 776 01-Aug-19 21-Jan-22
A1100 Improved Subgrade 77 01-Aug-19 29-Oct-19
A1110 GranularSub -base 65 02-Oct-19 16-Dec-19
A1120 WaterBound Macadam (WBM) 86 18-Nov-19 25-Feb-20
A1140 AsphalticBase Course including prime coat 42 18-Feb-20 06-Apr-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 18 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A1150 AsphalticWearing Course including T
ackCoat 39 08-Dec-21 21-Jan-22
ImportYardCulverts for toRoadnetwork (C-2,3,5)
ImportYardCulverts for toRoadnetwork (C-2,3,5) 212 18-Jul-19 20-Mar-20
A1310 StructuralExcavation in Common Materials 43 18-Jul-19 05-Sep-19
A1311 Stone Soling in Bed 43 26-Jul-19 13-Sep-19
A1320 Lean Concrete 36 03-Sep-19 14-Oct-19
A1340 Concreting ClassA-1 (underground) 71 05-Oct-19 26-Dec-19
A1350 Concreting ClassA-3 (Walls,DeckSlab and Wing Walls) 109 24-Oct-19 27-Feb-20
A1360 GranularBackFill 29 17-Feb-20 20-Mar-20
ExportYardCulverts for Roadnetwork (C-1,4)
ExportYardCulverts for Roadnetwork (C-1,4) 171 04-Apr-20 20-Oct-20
A1901 StructuralExcavation in Common Materials 35 04-Apr-20 14-May-20
A1902 Stone Soling in Bed 50 16-Apr-20 12-Jun-20
A1903 Lean Concrete 59 22-May-20 29-Jul-20
A1904 Concreting ClassA-1 (underground) 51 11-Jun-20 08-Aug-20
A1910 Concreting ClassA-3 (Walls,DeckSlab and Wing Walls) 77 16-Jul-20 13-Oct-20
A1911 GranularBackfill 55 18-Aug-20 20-Oct-20
Bridges andFlyover
Bridges andFlyover 360 23-May-19 15-Jul-20
A1230 Pile load Test 41 23-May-19 09-Jul-19
A1240 Casting of Girders 134 23-May-19 25-Oct-19
A1250 Piles-Boring only 80 15-Jul-19 16-Oct-19
A1255 Concreting of Piles 70 21-Aug-19 09-Nov-19
A1260 Concreting of Piers/AbutmentsinclPile caps 106 26-Aug-19 26-Dec-19
A1270 Construction of Transom 119 07-Oct-19 21-Feb-20
A1280 Launching of Girdersincluding placing of bearing pads 121 11-Nov-19 30-Mar-20
A1290 Construction of DeckSlab 102 02-Mar-20 27-Jun-20
A1300 Bridge related ancillaryworks(barriers,wing walls) 73 16-Apr-20 09-Jul-20
Ramps
Ramps 247 02-Oct-19 15-Jul-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 19 of 20 TASK filter: All Activities
© Oracle Corporation
ActivityID ActivityName Original
Duration
Start Finish
A1740 StructuralExcavation 41 02-Oct-19 18-Nov-19
A1745 Lean Concrete 73 28-Nov-19 20-Feb-20
A1750 Construction of Wallupto Ground Level 77 12-Dec-19 10-Mar-20
A1760 Construction of Wallsabove Ground Level 128 13-Jan-20 09-Jun-20
A1770 Earth Filling to Finish Level 92 13-Mar-20 27-Jun-20
A1780 BackFilling 29 12-Jun-20 15-Jul-20
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16
Remaining Work
ActualWork
CriticalRemaining Work
Milestone
Summary Page 20 of 20 TASK filter: All Activities
© Oracle Corporation

More Related Content

Similar to Torkham Project Work Plan (18-Apr-2019).pdf

Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Planning Inspectorate update: Latest insight and guidance on NSIPs
Planning Inspectorate update: Latest insight and guidance on NSIPsPlanning Inspectorate update: Latest insight and guidance on NSIPs
Planning Inspectorate update: Latest insight and guidance on NSIPsThe Planning Inspectorate
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxsheikhInayat5
 
Work Plan 2023 Final @ 14-03-2023.pptx
Work Plan 2023 Final @ 14-03-2023.pptxWork Plan 2023 Final @ 14-03-2023.pptx
Work Plan 2023 Final @ 14-03-2023.pptxsonutyagi20
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
 
KVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdfKVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdfMohammed83959
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6MUHAMMAD SALEEM
 
Nuberg Corporate Calendar 2015
Nuberg Corporate Calendar 2015Nuberg Corporate Calendar 2015
Nuberg Corporate Calendar 2015Nuberg Engineering
 
Presentation
PresentationPresentation
PresentationKrm Chari
 
Project status report
Project status reportProject status report
Project status reportmaduracamms
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalAhmed Mehrem
 
BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationVijay Pandey
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanOsvaldo Zumba
 
02 all-about-building-services-issue-march-2018 docx
02 all-about-building-services-issue-march-2018 docx02 all-about-building-services-issue-march-2018 docx
02 all-about-building-services-issue-march-2018 docxKevin Wilkinson
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)Jamal Nelson, CCM
 

Similar to Torkham Project Work Plan (18-Apr-2019).pdf (20)

ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Planning Inspectorate update: Latest insight and guidance on NSIPs
Planning Inspectorate update: Latest insight and guidance on NSIPsPlanning Inspectorate update: Latest insight and guidance on NSIPs
Planning Inspectorate update: Latest insight and guidance on NSIPs
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
Work Plan 2023 Final @ 14-03-2023.pptx
Work Plan 2023 Final @ 14-03-2023.pptxWork Plan 2023 Final @ 14-03-2023.pptx
Work Plan 2023 Final @ 14-03-2023.pptx
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
KVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdfKVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdf
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
Student Transcript
Student TranscriptStudent Transcript
Student Transcript
 
Nuberg Corporate Calendar 2015
Nuberg Corporate Calendar 2015Nuberg Corporate Calendar 2015
Nuberg Corporate Calendar 2015
 
Presentation
PresentationPresentation
Presentation
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Project status report
Project status reportProject status report
Project status report
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning Plan
 
02 all-about-building-services-issue-march-2018 docx
02 all-about-building-services-issue-march-2018 docx02 all-about-building-services-issue-march-2018 docx
02 all-about-building-services-issue-march-2018 docx
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
 

Recently uploaded

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

Torkham Project Work Plan (18-Apr-2019).pdf

  • 1. CONSTRUCTION OF BORDER CROSSING FACILITY AT TORKHAM WORK PROGRAMME Project Construction of Border Crossing Facility at Torkham Employer Federal Board of Revenue (FBR), Government of Pakistan PMC Consultant Terra Consultants EPC Contractor National Logistics Cell (NLC) CSC Consultants SMEC Submitted By National Logistics Cell (NLC) Prepared By Al-Imam PMC and PID- JV NLC’s Construction Management Consultants (CMC)
  • 3. ActivityID ActivityName Original Duration Start Finish Work Programme Torkham Final (16-Apr-2019) Work Programme Torkham Final (16-Apr-2019) 1132 15-Feb-19 28-Sep-22 A1000 ProjectStart 0 15-Feb-19 A1020 ProjectEnd 0 28-Sep-22 Design and Costruction Drawings Design and Costruction Drawings 125 15-Apr-19 06-Sep-19 IPC Schedule (Tentative) IPC Schedule (Tentative) 1015 01-Jul-19 28-Sep-22 Moblization to the Site Moblization to the Site 87 15-Feb-19 27-May-19 Area Clearance Area Clearance 25 26-Apr-19 24-May-19 Site Grading Works Import, export and passengerYards including Rd Network Site Grading Works Import, export and passengerYards including Rd Network 427 14-May-19 22-Sep-20 Import yard Import yard 210 14-May-19 13-Jan-20 Cut Cut 210 14-May-19 13-Jan-20 Fill Fill 190 06-Jun-19 13-Jan-20 Export yard Export yard 262 14-May-19 13-Mar-20 Cut Cut 198 14-May-19 30-Dec-19 Fill Fill 232 18-Jun-19 13-Mar-20 Site Grading Export yard primary inspection Site Grading Export yard primary inspection 147 04-Apr-20 22-Sep-20 Site Grading Passenger Terminal Site Grading Passenger Terminal 66 24-Oct-19 08-Jan-20 Procurement Schedule (Tentative) Procurement Schedule (Tentative) 918 06-Jun-19 11-May-22 Structure (Concrete & Steel) Work Procurments Structure (Concrete & Steel) Work Procurments 755 06-Jun-19 02-Nov-21 Civil Finishing Item Procurments Civil Finishing Item Procurments 781 13-Nov-19 11-May-22 Electrical Procurments Electrical Procurments 267 06-Feb-20 12-Dec-20 HVAC Procurments HVAC Procurments 267 29-Jan-20 05-Dec-20 Plumbing Procurments Plumbing Procurments 189 25-Jan-20 01-Sep-20 Fire Suppression Procurments Fire Suppression Procurments 189 29-Jan-20 05-Sep-20 Vertical Transport System Procurments Vertical Transport System Procurments 290 24-Jan-20 26-Dec-20 BAS/ICT Procurments BAS/ICT Procurments 225 13-Oct-20 01-Jul-21 Security Equipment Procurments Security Equipment Procurments 472 25-May-20 25-Nov-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Project Finish Date has been extended due to non-availibilty of land. Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 1 of 4 TASK filter: All Activities © Oracle Corporation
  • 4. ActivityID ActivityName Original Duration Start Finish A- BUILDINGS WORKS A- BUILDINGS WORKS 904 30-Oct-19 19-Sep-22 Admin Block Admin Block 460 30-Oct-19 17-Apr-21 Buisness Centre Buisness Centre 370 30-Oct-19 02-Jan-21 Passenger Terminal Buildings Passenger Terminal Buildings 463 03-Jan-20 25-Jun-21 SPS/ Quarantine Shed SPS/ Quarantine Shed 230 14-Jan-20 07-Oct-20 Customs Lab Customs Lab 176 14-Jan-20 06-Aug-20 Office Block Office Block 264 10-Mar-20 11-Jan-21 Perishable Goods/ Cold Storage Perishable Goods/ Cold Storage 213 14-Jan-20 17-Sep-20 Seized Goods Warehouse (Import) Seized Goods Warehouse (Import) 288 14-Jan-20 14-Dec-20 Seized Goods Warehouse (Export) Seized Goods Warehouse (Export) 281 12-Dec-19 04-Nov-20 Closed ExaminationArea Closed ExaminationArea 260 14-Jan-20 11-Nov-20 Open ExaminationArea Open ExaminationArea 256 14-Jan-20 07-Nov-20 C-Mart C-Mart 161 01-Aug-20 05-Feb-21 Watch Tower (Import & Export) Watch Tower (Import & Export) 194 14-Jan-20 26-Aug-20 Canine Main Building Canine Main Building 153 24-Dec-19 18-Jun-20 Canine Small Units Canine Small Units 138 24-Mar-20 31-Aug-20 Toll Booth (Single & Double) Toll Booth (Single & Double) 231 12-Mar-20 07-Dec-20 Bomb Disposal Squad Bomb Disposal Squad 151 14-Mar-20 07-Sep-20 Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) 150 13-Mar-20 03-Sep-20 Canteen/ Driver's RestArea (Export Yard) Canteen/ Driver's RestArea (Export Yard) 153 01-Aug-20 26-Jan-21 Public Toilets Public Toilets 140 01-Aug-20 11-Jan-21 Clinic Clinic 150 01-Aug-20 22-Jan-21 Guard Post Guard Post 155 14-Mar-20 10-Sep-20 Substation/PMT Kiosk Substation/PMT Kiosk 160 31-Dec-19 03-Jul-20 Mosque Mosque 191 01-Aug-20 12-Mar-21 Fire Station Fire Station 270 14-Jan-20 23-Nov-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 2 of 4 TASK filter: All Activities © Oracle Corporation
  • 5. ActivityID ActivityName Original Duration Start Finish Operator's Room (Import & Export) Operator's Room (Import & Export) 138 31-Dec-19 08-Jun-20 Facilitation Center Facilitation Center 200 03-Jan-20 22-Aug-20 Gantry Scanner Gantry Scanner 250 14-Apr-20 29-Jan-21 Bomb Difuse Chamber Bomb Difuse Chamber 219 14-Apr-20 24-Dec-20 DRC DRC 224 08-Sep-20 26-May-21 Agent Hall Agent Hall 188 18-Sep-20 24-Apr-21 Power House (Import Yard & Export Yard) Power House (Import Yard & Export Yard) 190 14-Jan-20 21-Aug-20 Inspector Examiner Hall Inspector Examiner Hall 195 14-Jan-20 27-Aug-20 Pass Through Scanner Pass Through Scanner 176 14-Mar-20 06-Oct-20 Vertical Transport System Vertical Transport System 195 28-Dec-20 11-Aug-21 MEPAncillary Works MEPAncillary Works 476 10-Sep-20 19-Mar-22 External Development Works External Development Works 828 14-Jan-20 05-Sep-22 BAS/ICT Works BAS/ICT Works 380 02-Jul-21 19-Sep-22 Security System Works Security System Works 238 26-Nov-21 30-Aug-22 INFRASTRUCTURE WORKS INFRASTRUCTURE WORKS 1071 15-Feb-19 18-Jul-22 A7840 ProjectStart 0 15-Feb-19 A7850 ProjectEnd 0 18-Jul-22 B- INFRSTRUCTURE DEVELOPMENT WORKS B- INFRSTRUCTURE DEVELOPMENT WORKS 1016 20-Apr-19 18-Jul-22 ParkingArea ExportTerminal ParkingArea ExportTerminal 578 14-Mar-20 17-Jan-22 ParkingArea ImportTerminal ParkingArea ImportTerminal 547 14-Jan-20 12-Oct-21 AncillaryWorks AncillaryWorks 1016 20-Apr-19 18-Jul-22 RoadFurniture RoadFurniture 101 23-Mar-22 18-Jul-22 Supportive /Administrative Works Supportive /Administrative Works 693 20-Apr-19 06-Jul-21 Retainingwalls andRiver TrainingWorks Retainingwalls andRiver TrainingWorks 370 15-May-19 18-Jul-20 RetainingWalls RetainingWalls 335 19-Jun-19 13-Jul-20 Surface Drainage Surface Drainage 370 15-May-19 18-Jul-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 3 of 4 TASK filter: All Activities © Oracle Corporation
  • 6. ActivityID ActivityName Original Duration Start Finish PedestrianBridge PedestrianBridge 121 24-Mar-20 11-Aug-20 Bridge Bridge 121 24-Mar-20 11-Aug-20 Stairs Stairs 121 24-Mar-20 11-Aug-20 RoadWorks RoadWorks 788 18-Jul-19 21-Jan-22 ExportYardRoadNetwork (Cl-200) ExportYardRoadNetwork (Cl-200) 126 31-Jul-20 24-Dec-20 ImportYardRoadNetwork (Cl-100,101,101A,103,201) ImportYardRoadNetwork (Cl-100,101,101A,103,201) 776 01-Aug-19 21-Jan-22 ImportYardCulverts for toRoadnetwork (C-2,3,5) ImportYardCulverts for toRoadnetwork (C-2,3,5) 212 18-Jul-19 20-Mar-20 ExportYardCulverts for Roadnetwork (C-1,4) ExportYardCulverts for Roadnetwork (C-1,4) 171 04-Apr-20 20-Oct-20 Bridges andFlyover Bridges andFlyover 360 23-May-19 15-Jul-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:13 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 4 of 4 TASK filter: All Activities © Oracle Corporation
  • 8. ActivityID ActivityName Original Duration Start Finish Work Programme Torkham Final (16-Apr-2019) Work Programme Torkham Final (16-Apr-2019) 1132 15-Feb-19 28-Sep-22 A1000 ProjectStart 0 15-Feb-19 A1020 ProjectEnd 0 28-Sep-22 Design and Costruction Drawings Design and Costruction Drawings 125 15-Apr-19 06-Sep-19 A7190 Detailsand issuance of IFCbyNLC 95 15-Apr-19 02-Aug-19 A7200 Vetting of Design/Construction DrawingsbyCSC 30 29-Jun-19 02-Aug-19 A7210 FinalApprovalof Design/Construction Drawings 30 03-Aug-19 06-Sep-19 IPC Schedule (Tentative) IPC Schedule (Tentative) 1015 01-Jul-19 28-Sep-22 A4910 Submission of IPC-1 0 01-Jul-19 A4920 Submission of IPC-2 0 02-Sep-19 A4930 Submission of IPC-3 0 01-Nov-19 A4940 Submission of IPC-4 0 01-Jan-20 A4950 Submission of IPC-5 0 02-Mar-20 A4960 Submission of IPC-6 0 01-May-20 A4970 Submission of IPC-7 0 01-Jul-20 A4980 Submission of IPC-8 0 01-Aug-20 A4990 Submission of IPC-9 0 01-Sep-20 A5000 Submission of IPC-10 0 01-Oct-20 A5010 Submission of IPC-11 0 02-Nov-20 A5020 Submission of IPC-12 0 01-Dec-20 A5030 Submission of IPC-13 0 01-Jan-21 A5040 Submission of IPC-14 0 01-Feb-21 A5050 Submission of IPC-15 0 01-Mar-21 A5060 Submission of IPC-16 0 01-Apr-21 A5070 Submission of IPC-17 0 01-Jun-21 A5080 Submission of IPC-18 0 02-Aug-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Project Finish Date has been extended due to non-availibilty of land. Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 1 of 20 TASK filter: All Activities © Oracle Corporation
  • 9. ActivityID ActivityName Original Duration Start Finish A5090 Submission of IPC-19 0 01-Oct-21 A5100 Submission of IPC-20 0 01-Nov-21 A5110 Submission of IPC-21 0 01-Dec-21 A5120 Submission of IPC-22 0 01-Jan-22 A5130 Submission of IPC-23 0 01-Feb-22 A5140 Submission of IPC-24 0 28-Sep-22 Moblization to the Site Moblization to the Site 87 15-Feb-19 27-May-19 A1009 Mobilization 12 15-Feb-19 28-Feb-19 A1019 Possesion of Land 10 20-Mar-19 30-Mar-19 A1010 JointSurvey 20 17-Apr-19 09-May-19 Investigative Works Investigative Works 37 15-Apr-19 27-May-19 A2400 GeotechnicalInvestigation forInfrastructure 37 15-Apr-19 27-May-19 A2410 GeotechnicalInvestigation forBuilding works 37 15-Apr-19 27-May-19 Area Clearance Area Clearance 25 26-Apr-19 24-May-19 A7230 Removalof Tree 10 26-Apr-19 07-May-19 A1030 Clearing and Grubbing 20 02-May-19 24-May-19 Site Grading Works Import, export and passengerYards including Rd Network Site Grading Works Import, export and passengerYards including Rd Network 427 14-May-19 22-Sep-20 Import yard Import yard 210 14-May-19 13-Jan-20 Cut Cut 210 14-May-19 13-Jan-20 A7880 25%cut PKG3 61 14-May-19 23-Jul-19 A7890 25%Cut PKG2 110 14-May-19 18-Sep-19 A7900 25%Cut PKG1 210 14-May-19 13-Jan-20 A7910 25%Cut PKG4 100 19-Sep-19 13-Jan-20 Fill Fill 190 06-Jun-19 13-Jan-20 A7920 Fill50%PKG2&3 90 06-Jun-19 18-Sep-19 A7930 Fill50%PKG1&4 150 23-Jul-19 13-Jan-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Earth Cut delayed due to non-availibility or partial availibilty of land by FBR. Earth Fill delayed due to dependency on Earth Cut. Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 2 of 20 TASK filter: All Activities © Oracle Corporation
  • 10. ActivityID ActivityName Original Duration Start Finish Export yard Export yard 262 14-May-19 13-Mar-20 Cut Cut 198 14-May-19 30-Dec-19 A7940 40%CutPKG1 86 14-May-19 21-Aug-19 A7950 30%CutPKG2 58 22-Aug-19 28-Oct-19 A7960 30%CutPKG2 54 29-Oct-19 30-Dec-19 Fill Fill 232 18-Jun-19 13-Mar-20 A7970 10%fillPKG1 61 18-Jun-19 27-Aug-19 A7980 90%fillPKG2 146 26-Sep-19 13-Mar-20 Site Grading Export yard primary inspection Site Grading Export yard primary inspection 147 04-Apr-20 22-Sep-20 A7990 Earth cut(Hard ) 147 04-Apr-20 22-Sep-20 A8000 Scarification of existing rigid pavement 69 04-Apr-20 23-Jun-20 A8010 Earth Fillincluding cl200 64 09-May-20 22-Jul-20 Site Grading Passenger Terminal Site Grading Passenger Terminal 66 24-Oct-19 08-Jan-20 A7860 Earth Cut 61 24-Oct-19 02-Jan-20 A7870 Earth Fill 56 05-Nov-19 08-Jan-20 Procurement Schedule (Tentative) Procurement Schedule (Tentative) 918 06-Jun-19 11-May-22 Structure (Concrete & Steel) Work Procurments Structure (Concrete & Steel) Work Procurments 755 06-Jun-19 02-Nov-21 A7680 Preparation of RFP forStructure Material 30 06-Jun-19 10-Jul-19 A7690 Response from Vendors 30 11-Jul-19 14-Aug-19 A7700 Evaluation of Proposals 20 15-Aug-19 06-Sep-19 A7710 Issuance of Purchase 50 07-Sep-19 04-Nov-19 A7720 Supplyof Structure MaterialatSite 625 05-Nov-19 02-Nov-21 Civil Finishing Item Procurments Civil Finishing Item Procurments 781 13-Nov-19 11-May-22 A7620 Preparation of RFP forCivilFinishing Items 26 13-Nov-19 12-Dec-19 A7630 Response from Vendors 26 13-Dec-19 11-Jan-20 A7640 Evaluation of Proposals 17 11-Jan-20 31-Jan-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Earth Cut delayed due to non-availibility or partial availibilty of land by FBR. Earth Cut delayed due to non-availibility or partial availibilty of land by FBR. Earth Cut delayed due to non-availibility or partial availibilty of land by Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 3 of 20 TASK filter: All Activities © Oracle Corporation
  • 11. ActivityID ActivityName Original Duration Start Finish A7650 Issuance of Purchase Orderand LCOpening 56 31-Jan-20 06-Apr-20 A7670 Supplyof CivilFinishing Items 656 06-Apr-20 11-May-22 Electrical Procurments Electrical Procurments 267 06-Feb-20 12-Dec-20 A7420 Preparation of RFP forElectricalEquipment 26 06-Feb-20 06-Mar-20 A7430 Response from EquipmentManufacturer 25 07-Mar-20 04-Apr-20 A7440 Evaluation of Proposals 17 06-Apr-20 24-Apr-20 A7450 Issuance of Purchase Orderand LCOpening 56 25-Apr-20 30-Jun-20 A7460 Manufacturing of Equipments 86 30-Jun-20 08-Oct-20 A7470 Shipping and Deliveryof Equipments 56 08-Oct-20 12-Dec-20 HVAC Procurments HVAC Procurments 267 29-Jan-20 05-Dec-20 A7360 Preparation of RFP forHVACEquipment 26 29-Jan-20 28-Feb-20 A7370 Response from EquipmentManufacturer 25 28-Feb-20 28-Mar-20 A7380 Evaluation of Proposals 17 28-Mar-20 17-Apr-20 A7390 Issuance of Purchase Orderand LCOpening 56 17-Apr-20 22-Jun-20 A7400 Manufacturing of Equipments 86 23-Jun-20 30-Sep-20 A7410 Shipping and Deliveryof Equipments 56 01-Oct-20 05-Dec-20 Plumbing Procurments Plumbing Procurments 189 25-Jan-20 01-Sep-20 A7480 Preparation of RFP forPlumbing Equipment 17 25-Jan-20 13-Feb-20 A7490 Response from EquipmentManufacturer 13 14-Feb-20 28-Feb-20 A7500 Evaluation of Proposals 13 29-Feb-20 14-Mar-20 A7510 Issuance of Purchase Orderand LCOpening 38 16-Mar-20 28-Apr-20 A7520 Manufacturing of Equipments 52 28-Apr-20 27-Jun-20 A7530 Shipping and Deliveryof Equipments 56 27-Jun-20 01-Sep-20 Fire Suppression Procurments Fire Suppression Procurments 189 29-Jan-20 05-Sep-20 A7540 Preparation of RFP forFire Suppression Equipment 17 29-Jan-20 18-Feb-20 A7550 Response from EquipmentManufacturer 13 18-Feb-20 04-Mar-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 4 of 20 TASK filter: All Activities © Oracle Corporation
  • 12. ActivityID ActivityName Original Duration Start Finish A7560 Evaluation of Proposals 13 04-Mar-20 19-Mar-20 A7570 Issuance of Purchase Orderand LCOpening 38 19-Mar-20 02-May-20 A7580 Manufacturing of Equipments 52 02-May-20 02-Jul-20 A7590 Shipping and Deliveryof Equipments 56 02-Jul-20 05-Sep-20 Vertical Transport System Procurments Vertical Transport System Procurments 290 24-Jan-20 26-Dec-20 A7300 Preparation of RFP forVerticalTransportSystem 30 24-Jan-20 27-Feb-20 A7310 Response from EquipmentManufacturer 30 28-Feb-20 02-Apr-20 A7320 Evaluation of Proposals 20 03-Apr-20 25-Apr-20 A7330 Issuance of Purchase Orderand LCOpening 60 27-Apr-20 04-Jul-20 A7340 Manufacturing of Equipments 90 06-Jul-20 17-Oct-20 A7350 Shipping and Deliveryof Equipments 60 19-Oct-20 26-Dec-20 BAS/ICT Procurments BAS/ICT Procurments 225 13-Oct-20 01-Jul-21 A7270 Issuance of Purchase Orderand LCOpening 75 13-Oct-20 07-Jan-21 A7280 Manufacturing of Equipments 90 08-Jan-21 22-Apr-21 A7290 Shipping and Deliveryof Equipments 60 23-Apr-21 01-Jul-21 Security Equipment Procurments Security Equipment Procurments 472 25-May-20 25-Nov-21 A4770 Issuance of Purchase Orderand LCOpening 163 25-May-20 30-Nov-20 A4780 Manufacturing of Equipments 172 30-Nov-20 18-Jun-21 A4790 Shipping and Deliveryof Equipments 138 18-Jun-21 25-Nov-21 A- BUILDINGS WORKS A- BUILDINGS WORKS 904 30-Oct-19 19-Sep-22 Admin Block Admin Block 460 30-Oct-19 17-Apr-21 A5270 GreyStructure Works 220 30-Oct-19 11-Jul-20 A5280 CivilFinishing Works 240 13-Jul-20 17-Apr-21 A5300 Plumbing Works 155 22-Aug-20 18-Feb-21 A5290 HVACWorks 169 25-Aug-20 10-Mar-21 A5320 ElectricalWorks 148 28-Aug-20 16-Feb-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Building Works also delayed due to dependancy on Earth Cut and Earth Fill activities. Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 5 of 20 TASK filter: All Activities © Oracle Corporation
  • 13. ActivityID ActivityName Original Duration Start Finish A5310 Fire Suppression System Works 146 09-Sep-20 25-Feb-21 Buisness Centre Buisness Centre 370 30-Oct-19 02-Jan-21 A5330 GreyStructure Works 188 30-Oct-19 04-Jun-20 A5340 CivilFinishing Works 245 24-Mar-20 02-Jan-21 A5350 Plumbing Works 159 09-May-20 10-Nov-20 A5360 HVACWorks 160 13-May-20 16-Nov-20 A5380 Fire Suppression System Works 155 13-May-20 10-Nov-20 A5370 ElectricalWorks 176 21-May-20 12-Dec-20 Passenger Terminal Buildings Passenger Terminal Buildings 463 03-Jan-20 25-Jun-21 A5390 GreyStructure Works 231 03-Jan-20 29-Sep-20 A5400 CivilFinishing Works 275 08-Aug-20 25-Jun-21 A5430 Fire Suppression System Works 185 13-Oct-20 17-May-21 A5410 Plumbing Works 188 21-Oct-20 27-May-21 A5420 HVACWorks 194 24-Oct-20 08-Jun-21 A5440 ElectricalWorks 198 28-Oct-20 15-Jun-21 SPS/ Quarantine Shed SPS/ Quarantine Shed 230 14-Jan-20 07-Oct-20 A5690 GreyStructure Works 100 14-Jan-20 08-May-20 A5700 CivilFinishing Works 130 09-May-20 07-Oct-20 A5710 Plumbing Works 85 08-Jun-20 14-Sep-20 A5720 HVACWorks 79 15-Jun-20 14-Sep-20 A5740 ElectricalWorks 91 16-Jun-20 30-Sep-20 A5730 Fire Suppression System Works 75 26-Jun-20 22-Sep-20 Customs Lab Customs Lab 176 14-Jan-20 06-Aug-20 A5870 GreyStructure Works 81 14-Jan-20 17-Apr-20 A5880 CivilFinishing Works 95 17-Apr-20 06-Aug-20 A5890 Plumbing Works 63 09-May-20 21-Jul-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 6 of 20 TASK filter: All Activities © Oracle Corporation
  • 14. ActivityID ActivityName Original Duration Start Finish A5920 ElectricalWorks 66 12-May-20 28-Jul-20 A5900 HVACWorks 54 13-May-20 15-Jul-20 A5910 Fire Suppression System Works 50 23-May-20 21-Jul-20 Office Block Office Block 264 10-Mar-20 11-Jan-21 A5750 GreyStructure Works 125 10-Mar-20 01-Aug-20 A5760 CivilFinishing Works 139 03-Aug-20 11-Jan-21 A5770 Plumbing Works 94 04-Sep-20 23-Dec-20 A5800 ElectricalWorks 98 09-Sep-20 31-Dec-20 A5780 HVACWorks 85 12-Sep-20 19-Dec-20 A5790 Fire Suppression System Works 81 24-Sep-20 28-Dec-20 Perishable Goods/ Cold Storage Perishable Goods/ Cold Storage 213 14-Jan-20 17-Sep-20 A5930 GreyStructure Works 100 14-Jan-20 08-May-20 A5940 CivilFinishing Works 113 09-May-20 17-Sep-20 A5950 Plumbing Works 69 30-May-20 19-Aug-20 A5960 HVACWorks 73 03-Jun-20 26-Aug-20 A5980 ElectricalWorks 76 08-Jun-20 04-Sep-20 A5970 Fire Suppression System Works 58 15-Jun-20 20-Aug-20 Seized Goods Warehouse (Import) Seized Goods Warehouse (Import) 288 14-Jan-20 14-Dec-20 A5450 GreyStructure Works 125 14-Jan-20 06-Jun-20 A5460 CivilFinishing Works 163 08-Jun-20 14-Dec-20 A5480 HVACWorks 88 09-Jul-20 19-Oct-20 A5470 Plumbing Works 85 10-Jul-20 17-Oct-20 A5490 Fire Suppression System Works 81 21-Jul-20 23-Oct-20 A5500 ElectricalWorks 94 05-Aug-20 21-Nov-20 Seized Goods Warehouse (Export) Seized Goods Warehouse (Export) 281 12-Dec-19 04-Nov-20 A6110 GreyStructure Works 125 12-Dec-19 05-May-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 7 of 20 TASK filter: All Activities © Oracle Corporation
  • 15. ActivityID ActivityName Original Duration Start Finish A6120 CivilFinishing Works 156 06-May-20 04-Nov-20 A6140 HVACWorks 88 06-Jun-20 16-Sep-20 A6130 Plumbing Works 85 08-Jun-20 15-Sep-20 A6150 Fire Suppression System Works 81 18-Jun-20 21-Sep-20 A6160 ElectricalWorks 94 29-Jun-20 15-Oct-20 Closed ExaminationArea Closed ExaminationArea 260 14-Jan-20 11-Nov-20 A5510 GreyStructure Works 113 14-Jan-20 23-May-20 A5520 CivilFinishing Works 148 23-May-20 11-Nov-20 A5530 Plumbing Works 75 22-Jun-20 17-Sep-20 A5560 ElectricalWorks 96 29-Jun-20 19-Oct-20 A5540 HVACWorks 85 03-Jul-20 10-Oct-20 A5550 Fire Suppression System Works 81 14-Jul-20 16-Oct-20 Open ExaminationArea Open ExaminationArea 256 14-Jan-20 07-Nov-20 A5570 GreyStructure Works 113 14-Jan-20 23-May-20 A5580 CivilFinishing Works 144 23-May-20 07-Nov-20 A5590 Plumbing Works 75 22-Jun-20 17-Sep-20 A5620 ElectricalWorks 96 29-Jun-20 19-Oct-20 A5600 HVACWorks 85 02-Jul-20 09-Oct-20 A5610 Fire Suppression System Works 81 14-Jul-20 16-Oct-20 C-Mart C-Mart 161 01-Aug-20 05-Feb-21 A5630 GreyStructure Works 75 01-Aug-20 27-Oct-20 A5640 CivilFinishing Works 86 28-Oct-20 05-Feb-21 A5650 Plumbing Works 59 18-Nov-20 26-Jan-21 A5680 ElectricalWorks 63 21-Nov-20 02-Feb-21 A5660 HVACWorks 54 23-Nov-20 25-Jan-21 A5670 Fire Suppression System Works 56 26-Nov-20 30-Jan-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 8 of 20 TASK filter: All Activities © Oracle Corporation
  • 16. ActivityID ActivityName Original Duration Start Finish Watch Tower (Import & Export) Watch Tower (Import & Export) 194 14-Jan-20 26-Aug-20 A5810 GreyStructure Works 119 14-Jan-20 30-May-20 A5820 CivilFinishing Works 156 26-Feb-20 26-Aug-20 A7780 Plumbing Works 119 12-Mar-20 28-Jul-20 A5860 ElectricalWorks 94 17-Apr-20 04-Aug-20 Canine Main Building Canine Main Building 153 24-Dec-19 18-Jun-20 A5990 GreyStructure Works 84 24-Dec-19 30-Mar-20 A6000 CivilFinishing Works 69 30-Mar-20 18-Jun-20 A6010 Plumbing Works 44 14-Apr-20 03-Jun-20 A6020 HVACWorks 43 16-Apr-20 05-Jun-20 A6040 ElectricalWorks 50 16-Apr-20 13-Jun-20 A6030 Fire Suppression System Works 40 21-Apr-20 06-Jun-20 Canine Small Units Canine Small Units 138 24-Mar-20 31-Aug-20 A6050 GreyStructure Works 75 24-Mar-20 18-Jun-20 A6060 CivilFinishing Works 63 19-Jun-20 31-Aug-20 A6100 ElectricalWorks 46 29-Jun-20 21-Aug-20 A6080 HVACWorks 41 01-Jul-20 18-Aug-20 A7790 Plumbing Works 44 01-Jul-20 20-Aug-20 A6090 Fire Suppression System Works 38 03-Jul-20 15-Aug-20 Toll Booth (Single & Double) Toll Booth (Single & Double) 231 12-Mar-20 07-Dec-20 A6170 GreyStructure Works 106 12-Mar-20 14-Jul-20 A6180 CivilFinishing Works 125 14-Jul-20 07-Dec-20 A6190 Plumbing Works 81 12-Aug-20 14-Nov-20 A6200 HVACWorks 84 17-Aug-20 21-Nov-20 A6220 ElectricalWorks 91 19-Aug-20 03-Dec-20 A6210 Fire Suppression System Works 75 26-Aug-20 21-Nov-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 9 of 20 TASK filter: All Activities © Oracle Corporation
  • 17. ActivityID ActivityName Original Duration Start Finish Bomb Disposal Squad Bomb Disposal Squad 151 14-Mar-20 07-Sep-20 A6230 GreyStructure Works 75 14-Mar-20 09-Jun-20 A6240 CivilFinishing Works 76 10-Jun-20 07-Sep-20 A6250 Plumbing Works 56 19-Jun-20 24-Aug-20 A6260 HVACWorks 54 24-Jun-20 26-Aug-20 A6280 ElectricalWorks 56 29-Jun-20 02-Sep-20 A6270 Fire Suppression System Works 50 01-Jul-20 28-Aug-20 Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) Canteen/ Prayer/ C-Mart/ Toilets/ Clinic (Import Yard) 150 13-Mar-20 03-Sep-20 A6290 GreyStructure Works 60 13-Mar-20 21-May-20 A6300 CivilFinishing Works 90 22-May-20 03-Sep-20 A6310 Plumbing Works 38 01-Jun-20 15-Jul-20 A6340 ElectricalWorks 50 04-Jun-20 01-Aug-20 A6330 Fire Suppression System Works 43 09-Jun-20 28-Jul-20 A6320 HVACWorks 25 04-Jul-20 03-Aug-20 Canteen/ Driver's RestArea (Export Yard) Canteen/ Driver's RestArea (Export Yard) 153 01-Aug-20 26-Jan-21 A6350 GreyStructure Works 75 01-Aug-20 27-Oct-20 A6360 CivilFinishing Works 76 28-Oct-20 25-Jan-21 A6370 Plumbing Works 59 18-Nov-20 26-Jan-21 A6400 ElectricalWorks 56 18-Nov-20 22-Jan-21 A6380 HVACWorks 54 20-Nov-20 21-Jan-21 A6390 Fire Suppression System Works 50 23-Nov-20 20-Jan-21 Public Toilets Public Toilets 140 01-Aug-20 11-Jan-21 A6410 GreyStructure Works 60 01-Aug-20 09-Oct-20 A6420 CivilFinishing Works 80 10-Oct-20 11-Jan-21 A6430 Plumbing Works 38 24-Oct-20 07-Dec-20 A6440 HVACWorks 41 31-Oct-20 18-Dec-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 10 of 20 TASK filter: All Activities © Oracle Corporation
  • 18. ActivityID ActivityName Original Duration Start Finish A6460 ElectricalWorks 46 31-Oct-20 24-Dec-20 Clinic Clinic 150 01-Aug-20 22-Jan-21 A6470 GreyStructure Works 69 01-Aug-20 20-Oct-20 A6480 CivilFinishing Works 81 20-Oct-20 22-Jan-21 A6490 Plumbing Works 50 06-Nov-20 04-Jan-21 A6510 Fire Suppression System Works 46 11-Nov-20 04-Jan-21 A6520 ElectricalWorks 48 11-Nov-20 05-Jan-21 A6500 HVACWorks 54 16-Nov-20 16-Jan-21 Guard Post Guard Post 155 14-Mar-20 10-Sep-20 A6530 GreyStructure Works 75 14-Mar-20 09-Jun-20 A6540 CivilFinishing Works 80 10-Jun-20 10-Sep-20 A6580 ElectricalWorks 44 17-Jun-20 06-Aug-20 A6550 Plumbing Works 38 18-Jun-20 31-Jul-20 A6560 HVACWorks 35 18-Jun-20 29-Jul-20 A6570 Fire Suppression System Works 31 19-Jun-20 25-Jul-20 Substation/PMT Kiosk Substation/PMT Kiosk 160 31-Dec-19 03-Jul-20 A6590 GreyStructure Works 75 31-Dec-19 26-Mar-20 A6600 CivilFinishing Works 85 27-Mar-20 03-Jul-20 A6610 Plumbing Works 50 06-Apr-20 03-Jun-20 A6630 Fire Suppression System Works 48 08-Apr-20 02-Jun-20 A6620 HVACWorks 53 10-Apr-20 10-Jun-20 A6640 ElectricalWorks 56 14-Apr-20 18-Jun-20 Mosque Mosque 191 01-Aug-20 12-Mar-21 A6650 GreyStructure Works 80 01-Aug-20 02-Nov-20 A6660 CivilFinishing Works 90 03-Nov-20 15-Feb-21 A6670 Plumbing Works 94 17-Nov-20 06-Mar-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:15 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 11 of 20 TASK filter: All Activities © Oracle Corporation
  • 19. ActivityID ActivityName Original Duration Start Finish A6700 ElectricalWorks 96 20-Nov-20 12-Mar-21 A6680 HVACWorks 89 27-Nov-20 10-Mar-21 A6690 Fire Suppression System Works 88 27-Nov-20 09-Mar-21 Fire Station Fire Station 270 14-Jan-20 23-Nov-20 A6710 GreyStructure Works 110 14-Jan-20 20-May-20 A6720 CivilFinishing Works 130 21-May-20 19-Oct-20 A6730 Plumbing Works 125 23-Jun-20 16-Nov-20 A6760 ElectricalWorks 131 23-Jun-20 23-Nov-20 A6740 HVACWorks 123 03-Jul-20 23-Nov-20 A6750 Fire Suppression System Works 119 03-Jul-20 19-Nov-20 Operator's Room (Import & Export) Operator's Room (Import & Export) 138 31-Dec-19 08-Jun-20 A6770 GreyStructure Works 63 31-Dec-19 12-Mar-20 A6780 CivilFinishing Works 75 12-Mar-20 08-Jun-20 A6820 ElectricalWorks 56 27-Mar-20 01-Jun-20 A6810 Fire Suppression System Works 54 28-Mar-20 29-May-20 A6790 Plumbing Works 50 30-Mar-20 27-May-20 A6800 HVACWorks 49 02-Apr-20 28-May-20 Facilitation Center Facilitation Center 200 03-Jan-20 22-Aug-20 A6830 GreyStructure Works 94 03-Jan-20 21-Apr-20 A6840 CivilFinishing Works 106 21-Apr-20 22-Aug-20 A6850 Plumbing Works 75 01-May-20 28-Jul-20 A6880 ElectricalWorks 85 02-May-20 10-Aug-20 A6870 Fire Suppression System Works 71 06-May-20 28-Jul-20 A6860 HVACWorks 80 13-May-20 14-Aug-20 Gantry Scanner Gantry Scanner 250 14-Apr-20 29-Jan-21 A6890 GreyStructure Works 120 14-Apr-20 31-Aug-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 12 of 20 TASK filter: All Activities © Oracle Corporation
  • 20. ActivityID ActivityName Original Duration Start Finish A6900 CivilFinishing Works 130 01-Sep-20 29-Jan-21 A7220 Plumbing Works 89 01-Sep-20 12-Dec-20 A7250 HVACWorks 91 12-Sep-20 28-Dec-20 A6940 ElectricalWorks 88 15-Sep-20 25-Dec-20 A6930 Fire Suppression System Works 81 30-Sep-20 02-Jan-21 Bomb Difuse Chamber Bomb Difuse Chamber 219 14-Apr-20 24-Dec-20 A6950 GreyStructure Works 106 14-Apr-20 15-Aug-20 A6960 CivilFinishing Works 113 15-Aug-20 24-Dec-20 A6970 Plumbing Works 85 26-Aug-20 02-Dec-20 A6990 Fire Suppression System Works 81 27-Aug-20 30-Nov-20 A7000 ElectricalWorks 89 29-Aug-20 11-Dec-20 DRC DRC 224 08-Sep-20 26-May-21 A7010 GreyStructure Works 109 08-Sep-20 12-Jan-21 A7020 CivilFinishing Works 115 12-Jan-21 26-May-21 A7030 Plumbing Works 88 22-Jan-21 04-May-21 A7050 Fire Suppression System Works 85 23-Jan-21 03-May-21 A7040 HVACWorks 90 26-Jan-21 10-May-21 A7060 ElectricalWorks 95 28-Jan-21 19-May-21 Agent Hall Agent Hall 188 18-Sep-20 24-Apr-21 A7070 GreyStructure Works 88 18-Sep-20 29-Dec-20 A7080 CivilFinishing Works 100 29-Dec-20 24-Apr-21 A7110 Fire Suppression System Works 63 11-Jan-21 25-Mar-21 A7100 HVACWorks 69 13-Jan-21 02-Apr-21 A7090 Plumbing Works 63 14-Jan-21 27-Mar-21 A7120 ElectricalWorks 75 15-Jan-21 13-Apr-21 Power House (Import Yard & Export Yard) Power House (Import Yard & Export Yard) 190 14-Jan-20 21-Aug-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 13 of 20 TASK filter: All Activities © Oracle Corporation
  • 21. ActivityID ActivityName Original Duration Start Finish A7130 GreyStructure Works 90 14-Jan-20 27-Apr-20 A7140 CivilFinishing Works 100 28-Apr-20 21-Aug-20 A7240 Plumbing Works 56 28-Apr-20 02-Jul-20 A7810 Fire Suppression System Works 60 28-Apr-20 06-Jul-20 A7180 ElectricalWorks 63 12-May-20 23-Jul-20 A7160 HVACWorks 58 16-May-20 22-Jul-20 Inspector Examiner Hall Inspector Examiner Hall 195 14-Jan-20 27-Aug-20 A7150 GreyStructure Works 80 14-Jan-20 15-Apr-20 A7740 CivilFinishing Works 95 25-Apr-20 14-Aug-20 A7800 ElectricalWorks 85 09-May-20 15-Aug-20 A7820 Fire Suppression System Works 81 09-May-20 12-Aug-20 A7260 HVACWorks 79 13-May-20 13-Aug-20 A7760 Plumbing Works 88 18-May-20 27-Aug-20 Pass Through Scanner Pass Through Scanner 176 14-Mar-20 06-Oct-20 A7170 GreyStructure Works 81 14-Mar-20 17-Jun-20 A7750 CivilFinishing Works 94 17-Jun-20 03-Oct-20 A7830 Fire Suppression System Works 66 03-Jul-20 18-Sep-20 A5840 ElectricalWorks 69 04-Jul-20 22-Sep-20 A7770 Plumbing Works 76 09-Jul-20 06-Oct-20 Vertical Transport System Vertical Transport System 195 28-Dec-20 11-Aug-21 A3210 Installation of PassengerLift 75 28-Dec-20 24-Mar-21 A3240 Installation of Fire Tendersin Fire Station 75 04-Jan-21 01-Apr-21 A3220 Installation of ForkLifter 90 14-Jan-21 28-Apr-21 A3230 Installation of Reach Stacker 90 29-Apr-21 11-Aug-21 A3260 VerticalTransportSystem Completion 0 11-Aug-21 MEPAncillary Works MEPAncillary Works 476 10-Sep-20 19-Mar-22 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 14 of 20 TASK filter: All Activities © Oracle Corporation
  • 22. ActivityID ActivityName Original Duration Start Finish A7730 Installation of Fire Suppression Equipments,Valves 476 10-Sep-20 19-Mar-22 External Development Works External Development Works 828 14-Jan-20 05-Sep-22 A3470 Dismentaling of Existing Building 90 14-Jan-20 27-Apr-20 A3480 Formation of Surface Levels 75 12-Feb-20 08-May-20 A3590 G.IFence Installation 175 13-Jun-20 02-Jan-21 A3600 MeralShed Installation 148 01-Aug-20 20-Jan-21 A3490 Reconstruction 180 31-Oct-20 28-May-21 A3510 Weigh Bridge 120 30-Nov-20 17-Apr-21 A3530 Pedestrian WalkWay/UnderPass 150 12-Jan-21 06-Jul-21 A3540 SteelCanopyOverprimaryscanner 125 12-Jan-21 07-Jun-21 A3520 R.C.CBoundryWall(200mm Wide) 150 16-Feb-21 10-Aug-21 A3500 Sewarage,Drainage,Irrigation and Watersupplyworks 250 10-Aug-21 28-May-22 A3570 R.C.CBoundryWall(700mm Wide) 190 10-Aug-21 19-Mar-22 A5180 OHTof DifferentCapacityComplete in allRespect 90 10-Aug-21 23-Nov-21 A5240 UGWTof DifferentCapacityComplete in allRespect 90 10-Aug-21 23-Nov-21 A3610 DieselGeneratorsInstallation 94 10-Aug-21 27-Nov-21 A3620 Substation EquipmentInstallation 120 10-Aug-21 28-Dec-21 A3550 Subgrade and Pavementworks 75 02-Sep-21 29-Nov-21 A3560 ExternalElectrification 240 29-Nov-21 05-Sep-22 A5830 ExternalPlumbing Works 200 29-Nov-21 20-Jul-22 A3580 ExternalDevelopmentWorksFinish Milestone 0 05-Sep-22 BAS/ICT Works BAS/ICT Works 380 02-Jul-21 19-Sep-22 A3320 Installation of Fire Detection andAlarm System 288 02-Jul-21 02-Jun-22 A3360 Installation ofAccessControlSystem 263 31-Jul-21 02-Jun-22 A3370 Installation of IPCCTV System 238 14-Aug-21 18-May-22 A3380 Installation of ServerRoom Equipment 235 26-Aug-21 27-May-22 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 15 of 20 TASK filter: All Activities © Oracle Corporation
  • 23. ActivityID ActivityName Original Duration Start Finish A3390 Installation of Cable &ManagmentSystem 220 10-Sep-21 24-May-22 A3400 Installation of Voice TelephonyEquipment 190 16-Oct-21 26-May-22 A3410 Installation of WirelessAcessPoints 200 02-Nov-21 23-Jun-22 A3420 Installation of Data Centre Equipment 45 23-Dec-21 12-Feb-22 A3430 Installation of Servers 35 13-Jan-22 23-Feb-22 A3440 Installation of Storage Equipmentsand Devices 35 28-Jan-22 10-Mar-22 A3450 Configuration,Testing and Commisioning 75 23-Jun-22 19-Sep-22 A3460 IBAS/ICTFinish Milestone 0 19-Sep-22 Security System Works Security System Works 238 26-Nov-21 30-Aug-22 A4800 Installation of SecurityEquipments 238 26-Nov-21 30-Aug-22 A4810 SecuritySystem WorksFinish Milestone 0 30-Aug-22 INFRASTRUCTURE WORKS INFRASTRUCTURE WORKS 1071 15-Feb-19 18-Jul-22 A7840 ProjectStart 0 15-Feb-19 A7850 ProjectEnd 0 18-Jul-22 B- INFRSTRUCTURE DEVELOPMENT WORKS B- INFRSTRUCTURE DEVELOPMENT WORKS 1016 20-Apr-19 18-Jul-22 ParkingArea ExportTerminal ParkingArea ExportTerminal 578 14-Mar-20 17-Jan-22 A1790 Improved Subgrade 95 14-Mar-20 02-Jul-20 A1800 Sub Base 127 28-Apr-20 22-Sep-20 A1820 Rigid Pavement50% 99 09-Nov-20 03-Mar-21 A1840 Rigid Pavement50%(Sqm ) 99 04-Mar-21 26-Jun-21 A1830 Laying of Tuff PaveroverSand Cushion 83 13-Oct-21 17-Jan-22 ParkingArea ImportTerminal ParkingArea ImportTerminal 547 14-Jan-20 12-Oct-21 A1851 Improved Subgrade 57 14-Jan-20 19-Mar-20 A1852 Sub Base 98 31-Jan-20 23-May-20 A1860 Rigid Pavement 144 25-May-20 07-Nov-20 A1870 Laying of Tuff PaveroverSand Cushion 115 01-Jun-21 12-Oct-21 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 16 of 20 TASK filter: All Activities © Oracle Corporation
  • 24. ActivityID ActivityName Original Duration Start Finish AncillaryWorks AncillaryWorks 1016 20-Apr-19 18-Jul-22 RoadFurniture RoadFurniture 101 23-Mar-22 18-Jul-22 A1699 25%Lane Marking and Signage 25 23-Mar-22 20-Apr-22 A1700 25%Lane Marking and Signage 25 21-Apr-22 20-May-22 A1701 25%Lane Marking and Signage 25 20-May-22 18-Jun-22 A1702 25%Lane Marking and Signage 25 18-Jun-22 18-Jul-22 Supportive /Administrative Works Supportive /Administrative Works 693 20-Apr-19 06-Jul-21 A1960 Shifting of Utilities 164 20-Apr-19 28-Oct-19 A1980 Construction of Diversions 167 20-Apr-19 31-Oct-19 A1990 Establishmentof Laboratories 84 20-Apr-19 26-Jul-19 A1970 Rehabilitation of TaxiStand 37 25-May-21 06-Jul-21 Retainingwalls andRiver TrainingWorks Retainingwalls andRiver TrainingWorks 370 15-May-19 18-Jul-20 RetainingWalls RetainingWalls 335 19-Jun-19 13-Jul-20 A1450 StructuralExcavation 258 19-Jun-19 14-Apr-20 A1460 Lean Concrete 294 06-Jul-19 12-Jun-20 A1470 Plum Concrete 50% 150 10-Aug-19 31-Jan-20 A1480 BackFilling including granularfilterlayer 253 14-Sep-19 04-Jul-20 A1500 Grouted Rip Rap 230 19-Oct-19 13-Jul-20 A1490 Plum Concrete 50% 167 17-Dec-19 27-Jun-20 Surface Drainage Surface Drainage 370 15-May-19 18-Jul-20 Conduit Conduit 160 15-May-19 16-Nov-19 A1571 StructuralExcavation 51 15-May-19 12-Jul-19 A1572 Lean Concrete 50 15-Jul-19 10-Sep-19 A1573 ConcreteA-1,underground 36 07-Aug-19 17-Sep-19 A1574 Concrete ClassA-3 36 07-Aug-19 17-Sep-19 A1610 Rip Rap ClassA 59 29-Aug-19 05-Nov-19 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 17 of 20 TASK filter: All Activities © Oracle Corporation
  • 25. ActivityID ActivityName Original Duration Start Finish A1620 GranularBackFill 43 28-Sep-19 16-Nov-19 RoadSide Drains includingcrossingculverts RoadSide Drains includingcrossingculverts 250 02-Oct-19 18-Jul-20 A1520 StructuralExcavation 129 02-Oct-19 28-Feb-20 A1525 Lean Concrete 165 10-Oct-19 18-Apr-20 A1530 ConcreteA-3 on Ground 167 30-Nov-19 11-Jun-20 A1551 BackFilling 39 04-Jun-20 18-Jul-20 PedestrianBridge PedestrianBridge 121 24-Mar-20 11-Aug-20 Bridge Bridge 121 24-Mar-20 11-Aug-20 A1630 Foundation Works 23 24-Mar-20 18-Apr-20 A1640 Fabrication 78 15-Apr-20 14-Jul-20 A1650 Finishes 45 20-Jun-20 11-Aug-20 Stairs Stairs 121 24-Mar-20 11-Aug-20 A1671 Foundation Works 23 24-Mar-20 18-Apr-20 A1672 Fabrication 78 15-Apr-20 14-Jul-20 A1673 Finishes 45 20-Jun-20 11-Aug-20 RoadWorks RoadWorks 788 18-Jul-19 21-Jan-22 ExportYardRoadNetwork (Cl-200) ExportYardRoadNetwork (Cl-200) 126 31-Jul-20 24-Dec-20 A1191 Improved Subgrade 74 31-Jul-20 24-Oct-20 A1192 GranularSub -base 61 28-Aug-20 06-Nov-20 A1193 Lean Concrete 65 02-Oct-20 16-Dec-20 A1196 Concrete A-3 64 12-Oct-20 24-Dec-20 ImportYardRoadNetwork (Cl-100,101,101A,103,201) ImportYardRoadNetwork (Cl-100,101,101A,103,201) 776 01-Aug-19 21-Jan-22 A1100 Improved Subgrade 77 01-Aug-19 29-Oct-19 A1110 GranularSub -base 65 02-Oct-19 16-Dec-19 A1120 WaterBound Macadam (WBM) 86 18-Nov-19 25-Feb-20 A1140 AsphalticBase Course including prime coat 42 18-Feb-20 06-Apr-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 18 of 20 TASK filter: All Activities © Oracle Corporation
  • 26. ActivityID ActivityName Original Duration Start Finish A1150 AsphalticWearing Course including T ackCoat 39 08-Dec-21 21-Jan-22 ImportYardCulverts for toRoadnetwork (C-2,3,5) ImportYardCulverts for toRoadnetwork (C-2,3,5) 212 18-Jul-19 20-Mar-20 A1310 StructuralExcavation in Common Materials 43 18-Jul-19 05-Sep-19 A1311 Stone Soling in Bed 43 26-Jul-19 13-Sep-19 A1320 Lean Concrete 36 03-Sep-19 14-Oct-19 A1340 Concreting ClassA-1 (underground) 71 05-Oct-19 26-Dec-19 A1350 Concreting ClassA-3 (Walls,DeckSlab and Wing Walls) 109 24-Oct-19 27-Feb-20 A1360 GranularBackFill 29 17-Feb-20 20-Mar-20 ExportYardCulverts for Roadnetwork (C-1,4) ExportYardCulverts for Roadnetwork (C-1,4) 171 04-Apr-20 20-Oct-20 A1901 StructuralExcavation in Common Materials 35 04-Apr-20 14-May-20 A1902 Stone Soling in Bed 50 16-Apr-20 12-Jun-20 A1903 Lean Concrete 59 22-May-20 29-Jul-20 A1904 Concreting ClassA-1 (underground) 51 11-Jun-20 08-Aug-20 A1910 Concreting ClassA-3 (Walls,DeckSlab and Wing Walls) 77 16-Jul-20 13-Oct-20 A1911 GranularBackfill 55 18-Aug-20 20-Oct-20 Bridges andFlyover Bridges andFlyover 360 23-May-19 15-Jul-20 A1230 Pile load Test 41 23-May-19 09-Jul-19 A1240 Casting of Girders 134 23-May-19 25-Oct-19 A1250 Piles-Boring only 80 15-Jul-19 16-Oct-19 A1255 Concreting of Piles 70 21-Aug-19 09-Nov-19 A1260 Concreting of Piers/AbutmentsinclPile caps 106 26-Aug-19 26-Dec-19 A1270 Construction of Transom 119 07-Oct-19 21-Feb-20 A1280 Launching of Girdersincluding placing of bearing pads 121 11-Nov-19 30-Mar-20 A1290 Construction of DeckSlab 102 02-Mar-20 27-Jun-20 A1300 Bridge related ancillaryworks(barriers,wing walls) 73 16-Apr-20 09-Jul-20 Ramps Ramps 247 02-Oct-19 15-Jul-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 19 of 20 TASK filter: All Activities © Oracle Corporation
  • 27. ActivityID ActivityName Original Duration Start Finish A1740 StructuralExcavation 41 02-Oct-19 18-Nov-19 A1745 Lean Concrete 73 28-Nov-19 20-Feb-20 A1750 Construction of Wallupto Ground Level 77 12-Dec-19 10-Mar-20 A1760 Construction of Wallsabove Ground Level 128 13-Jan-20 09-Jun-20 A1770 Earth Filling to Finish Level 92 13-Mar-20 27-Jun-20 A1780 BackFilling 29 12-Jun-20 15-Jul-20 Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 Work Programme Torkham Final (16-Apr-2019) Classic Schedule Layout 17-Apr-19 19:16 Remaining Work ActualWork CriticalRemaining Work Milestone Summary Page 20 of 20 TASK filter: All Activities © Oracle Corporation