Activity ID Activity Name Remaining
Duration
Start Finish
Hot Strip MillHot Strip Mill 249 03-Jun-11 A 07-Mar-15
6. HOT STRIP MILL6. HOT STRIP MILL 249 03-Jun-11 A 07-Mar-15
HSM-10000 Issue LOI of Main Mill Package 0 03-Jun-11 A
HSM-10010 Start Milestone 0 01-Nov-11 A
INPUT MILESTONESINPUT MILESTONES 147 01-Jul-14 A 26-Nov-14
From Utility & Water SystemFrom Utility & Water System 72 01-Jul-14 A 01-Nov-14
A162202 Requirement of Dry Compressed air for HSM 0 01-Jul-14 A
A162180 Requirement of Chilled Water to HSM 0 20-Aug-14*
A162160 Requirement of LP Nitrogen to HSM from ASU (Alternate to be in position till ASU is in opn.) 0 30-Sep-14*
A162172 Requirement of Make-up Water to HSM 0 30-Sep-14*
A162190 Requirement of Mixed Gas to HSM 0 20-Oct-14*
A162210 Requirement of Propane 0 01-Nov-14*
From PDSFrom PDS 0 02-Jul-14 02-Jul-14
A162150 Requirement of Power from MSDS to HSM 0 02-Jul-14*
From SMSFrom SMS 0 26-Nov-14 26-Nov-14
A162140 SLAB to HSM 0 26-Nov-14*
OUTPUT MILESTONESOUTPUT MILESTONES 73 01-Nov-11 A 27-Nov-14
HSM-10110 Start of HSM 0 01-Nov-11 A
HSM-10090 Mill Line readiness 0 17-Oct-14*
HSM-10095 Cold test 35 15-Sep-14 30-Oct-14*
HSM-10100 Mill Integrated trail 26 31-Oct-14 26-Nov-14*
HSM-10080 1st coil from HSM - Target date 0 27-Nov-14*
Furnace +Roll shop + ECR1+ Slab Yard + Rolls + SaddlesFurnace +Roll shop + ECR1+ Slab Yard + Rolls + Saddles 208 07-Dec-11 A 25-Jan-15
Furnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop PipingFurnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop Piping 124 10-May-12 A 02-Nov-14
Civil Building & Foundation WorksCivil Building & Foundation Works 91 10-May-12 A 30-Sep-14
Slab Yard-QR /26-14Slab Yard-QR /26-14 0 10-May-12 A 20-Apr-13 A
SY-10000 Drawing Inputs (Building Column) 0 10-May-12 A 31-Oct-12 A
SY-10010 Building Column 0 09-Aug-12 A 20-Apr-13 A
Slab Yard-QR/14-9Slab Yard-QR/14-9 60 10-May-12 A 31-Aug-14
SY-10020 Drawing Inputs (Building Column) 0 10-May-12 A 28-Sep-12 A
SY-10030 Building Column 0 18-Feb-13 A 30-Apr-14 A
SY-10100 Equipment Foundation 60 31-May-14 A 31-Aug-14
Heavy Spares Storage Area- A/7-13Heavy Spares Storage Area- A/7-13 91 24-Sep-12 A 30-Sep-14
HSS-10000 Drawing Inputs (Building Column) 0 24-Sep-12 A 31-Dec-12 A
HSS-10010 Building Column 0 17-Sep-13 A 15-Feb-14 A
HSS-10020 Flooring & Misc Works 91 01-May-14 A 30-Sep-14*
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
Structural Building & Technological WorksStructural Building & Technological Works 124 13-Oct-12 A 02-Nov-14
SLAB Yard PQR /26-14SLAB Yard PQR /26-14 101 05-Nov-12 A 10-Oct-14
SY-10040 Drawing Inputs 0 05-Nov-12 A 17-Dec-13 A
SY-10050 Fabrication 0 11-Jan-13 A 23-May-14 A
SY-10120 Structural work complition to give front to EOT Erection 20 09-Mar-13 A 26-Jul-14
SY-10060 Complition of structural work & sheeting 101 09-Mar-13 A 10-Oct-14*
Slab Yard-PQR/14-9Slab Yard-PQR/14-9 109 05-Nov-12 A 18-Oct-14
SY-10070 Drawing Inputs 0 05-Nov-12 A 28-Feb-13 A
SY-10080 Fabrication 0 15-Mar-13 A 14-Mar-14 A
SY-10090 Erection (including sheeting) 109 08-Apr-13 A 18-Oct-14*
Heavy Spares Storage Area A/ 7-13Heavy Spares Storage Area A/ 7-13 81 13-Oct-12 A 23-Oct-14
HSS-10030 Drawing Inputs 0 13-Oct-12 A 05-Jul-13 A
HSS-10040 Fabrication 0 03-Sep-13 A 28-Mar-14 A
HSS-10050 Erection (including sheeting) 81 28-Sep-13 A 23-Oct-14
EOT CRANESEOT CRANES 99 14-Dec-13 A 02-Nov-14
Heavy Spare Storage Area (Axis 13 to 7)EOTHeavy Spare Storage Area (Axis 13 to 7)EOT 33 01-Oct-14 02-Nov-14
Crane (20T Bay A-B)Crane (20T Bay A-B) 33 01-Oct-14 02-Nov-14
HSS-EOT-10000 Bldg readiness for crane erection 0 01-Oct-14
HSS-EOT-10010 EOT Erection 30 01-Oct-14 30-Oct-14
HSS-EOT-10020 Test & Commisioning 3 31-Oct-14 02-Nov-14
16T Crane at C-E Bay16T Crane at C-E Bay 0 14-Dec-13 A 11-Mar-14 A
EOT-10030 Strl building readiness for crane erection 0 14-Dec-13 A
EOT-10040 EOT Erection &Testing of crane 0 16-Dec-13 A 11-Mar-14 A
2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays 96 27-Jul-14 30-Oct-14
HSS-EOT-10050 Strl building readiness for crane erection 0 27-Jul-14
HSS-EOT-10060 EOT Erection &Testing of crane (Required during operation) 77 15-Aug-14 30-Oct-14*
Slab Charging EquipmentSlab Charging Equipment 59 16-Aug-14 30-Oct-14
SY-10110 Erection and alingment of Slab Charging Equipment 59 16-Aug-14* 30-Oct-14
Furnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for FurnaceFurnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for Furnace 61 12-Apr-12 A 31-Aug-14
Civil Building & Foundation WorksCivil Building & Foundation Works 27 12-Apr-12 A 28-Jul-14
B-E/13-10 (Furnace - 1 area)B-E/13-10 (Furnace - 1 area) 0 12-Apr-12 A 10-Dec-13 A
FCE-10020 Excavation by Blasting 0 13-Jul-12 A 31-Jan-13 A
FCE-10030 Building Column 0 16-Oct-12 A 25-Mar-13 A
FCE-10010 Drawing Inputs incl. Equipment foundation 0 12-Apr-12 A 31-May-13 A
FCE-10040 Furnace Raft, Wall, Pedestral & Beam 0 30-Oct-12 A 10-Dec-13 A
B-E/10-8 (Furnace - 2 area)B-E/10-8 (Furnace - 2 area) 21 09-May-12 A 28-Jul-14
FCE-10060 Excavation by Blasting 0 08-Aug-12 A 29-Nov-12 A
FCE-10070 Building Column 0 15-Nov-12 A 25-Mar-13 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
FCE-10050 Drawing Inputs incl. Equipment foundation 0 09-May-12 A 31-May-13 A
FCE-10080 Furnace Raft, Wall, Pedestral & Beam 21 08-Aug-12 A 28-Jul-14
Structural Building & Technological WorksStructural Building & Technological Works 61 20-Aug-12 A 31-Aug-14
B-E/14-8 (Furnace - 1 &2 area)B-E/14-8 (Furnace - 1 &2 area) 40 20-Aug-12 A 10-Aug-14
FCE-10090 Drawing Inputs 0 20-Aug-12 A 24-Oct-12 A
FCE-10100 Fabrication 0 15-Dec-12 A 09-Jan-14 A
FCE-10110 Erection (including sheeting) 40 02-Jan-13 A 10-Aug-14*
B-E/8-4 (Furnace - 3&4 area)B-E/8-4 (Furnace - 3&4 area) 61 27-Sep-12 A 31-Aug-14
FCE-10120 Drawing Inputs 0 27-Sep-12 A 31-Oct-12 A
FCE-10160 Structural erection to give front for EOT erection 0 05-Apr-13 A 12-Dec-13 A
FCE-10130 Fabrication 0 01-Jan-13 A 03-Mar-14 A
FCE-10140 Erection (including sheeting) 61 05-Apr-13 A 31-Aug-14*
Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping)Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping) 208 20-Jan-14 A 25-Jan-15
Mechanical & RefractoryMechanical & Refractory 208 20-Jan-14 A 25-Jan-15
Furnace -1--Eqpt Erection by TenovaFurnace -1--Eqpt Erection by Tenova 145 20-Jan-14 A 24-Nov-14
FCE-10650 Clearence after Fdn & Building constn for Eqpt erection 0 20-Jan-14 A
Furnace Equipment ErectionFurnace Equipment Erection 118 12-Mar-14 A 28-Oct-14
Furnace Box and mechanismFurnace Box and mechanism 89 12-Mar-14 A 29-Sep-14
FCE1-10670 Inclined ramps 0 12-Mar-14 A 25-Mar-14 A
FCE1-10680 Lifting and travelling cylinders supports 0 15-Apr-14 A 20-Apr-14 A
FCE1-10690 Lifting frame cylinders and centering device 14 20-May-14 A 16-Jul-14
FCE1-10700 Travelling frame and cylinder 15 12-May-14 A 17-Jul-14
FCE1-10730 Side platforms and walkways level - 2250 mm 17 08-Jul-14* 25-Jul-14
FCE1-10720 Erection of Water seals 25 02-Jul-14 27-Jul-14
FCE1-10750 Erection of Fixed skid upright 7 20-Jul-14* 27-Jul-14
FCE1-10710 Erection of Moving skids uprights 29 02-Jul-14* 31-Jul-14
FCE1-10760 Lay down horizontal skids on the fixed hearth 5 27-Jul-14 01-Aug-14
FCE1-10770 Side and front, walls 10 28-Jul-14 07-Aug-14
FCE1-10740 Hearth frames and scale hoppers 14 25-Jul-14 08-Aug-14
FCE1-10800 Roof IPE 100 8 07-Aug-14* 15-Aug-14
FCE1-10790 Roof main beams 10 07-Aug-14* 17-Aug-14
FCE1-10810 Horizontal skids (Charge section) alignment & levelling 15 20-Aug-14 04-Sep-14
FCE1-10640 Side platforms and walkways Level +500 mm 25 15-Aug-14 09-Sep-14
FCE1-10820 Horizontal skids (Middle section) alignment & levelling 12 31-Aug-14 12-Sep-14
FCE1-10620 Horizontal skids (Discharge section) alignment & levelling 12 01-Sep-14 13-Sep-14
FCE1-10630 Final setting of water seals and paddles 15 03-Sep-14 18-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
FCE1-10780 Side doors 46 07-Aug-14 22-Sep-14
FCE1-10650 Roof stairs and walkways 20 09-Sep-14 29-Sep-14
FCE1-10660 Completion of Furnace box and Mechanism 0 29-Sep-14*
Waste Gas Duct & StacksWaste Gas Duct & Stacks 46 10-Aug-14 25-Sep-14
WG-10150 Downtake 3 10-Aug-14* 13-Aug-14
WG-10160 Waste gas ducts upsteam recuperator 25 13-Aug-14 07-Sep-14
WG-10170 Recuperator casing 9 01-Sep-14 10-Sep-14
WG-10180 Waste gas ducts downsteam recuperator & pressure valve 15 01-Sep-14 16-Sep-14
WG-10190 Stack (lot no-1,2,3) 8 17-Sep-14 25-Sep-14
Handling EquipmentHandling Equipment 68 13-Jun-14 A 08-Sep-14
HE-10060 Discharge machine 11 13-Jun-14 A 13-Jul-14
HE-10070 Charging machine 30 15-Jul-14* 14-Aug-14
HE-10080 Charging and discharging doors mechanism and doors 5 03-Sep-14 08-Sep-14
Refractory & InsulationRefractory & Insulation 112 05-Jul-14 25-Oct-14
REF-10310 Side doors lining 6 25-Aug-14* 31-Aug-14
REF-10320 Charging and discharging doors lining 6 25-Aug-14* 31-Aug-14
REF-10360 Recu casing - lining 20 25-Aug-14* 14-Sep-14
REF-10340 Skids-lining 30 25-Aug-14* 24-Sep-14
REF-10390 Piping insulation 40 25-Aug-14* 04-Oct-14
REF-10350 Down take and waste gas duct upstream recu lining 30 16-Sep-14 16-Oct-14
REF-10370 Waste gas duct downstream recu lining 30 24-Sep-14 24-Oct-14
REF-10330 Furnace box - lining 60 25-Aug-14* 24-Oct-14
REF-10380 Stack refractory ining 30 25-Sep-14 25-Oct-14
REF-10400 Complete insulation & lining 0 25-Oct-14
Equipment & PipingEquipment & Piping 100 05-Jul-14 13-Oct-14
EQP-10570 Combustion air fans (3 nos with scilencer & connecting pipe) 8 05-Jul-14* 13-Jul-14
EQP-10500 Hydraulic station and valve stand 10 15-Jul-14* 25-Jul-14
EQP-10490 Water sealing piping 15 27-Jul-14 11-Aug-14
EQP-10530 Lubricating piping system 20 25-Jul-14 14-Aug-14
EQP-10560 Burners (lateral & roof) 15 05-Aug-14* 20-Aug-14
EQP-10580 Combustion air piping & support 40 13-Jul-14 22-Aug-14
EQP-10510 Hydraulic Piping 30 25-Jul-14 24-Aug-14
EQP-10620 Compressed air system 30 02-Aug-14* 01-Sep-14
EQP-10520 Hydraulic piping flushing 15 24-Aug-14 08-Sep-14
EQP-10480 Skids cooling water piping and supports 45 02-Aug-14 16-Sep-14*
EQP-10550 Recuperators 10 14-Sep-14 24-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 4 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
EQP-10590 Mixed gas piping and support 45 13-Aug-14 27-Sep-14
EQP-10600 Nitrogen piping and supports 20 19-Sep-14 09-Oct-14
EQP-10610 Pilot and frame control system 15 27-Sep-14 12-Oct-14*
EQP-10540 Pressure test 30 13-Sep-14 13-Oct-14
Electrical SystemsElectrical Systems 93 27-Jul-14 28-Oct-14
EE-10410 MCC boards and local panels 15 16-Aug-14* 31-Aug-14
EE-10420 Erection of cable trays 30 01-Aug-14 31-Aug-14
EE-10430 Field instruments 45 27-Jul-14 10-Sep-14
EE-10440 Cable laying 45 06-Aug-14 20-Sep-14
EE-10450 Cable termination 30 26-Aug-14 25-Sep-14
EE-10460 CCTV system 15 13-Oct-14 28-Oct-14
EE-10470 Complete installation of electrical & instrumentation 0 28-Oct-14
Testing & CommissioningTesting & Commissioning 30 25-Oct-14 24-Nov-14
TEST-12430 Cold test & commissioning 17 25-Oct-14 11-Nov-14
TEST-12440 Heating and dry up 12 11-Nov-14 23-Nov-14
TEST-12450 1st Hot slab 0 24-Nov-14*
Furnace-2--Eqpt Erection by TenovaFurnace-2--Eqpt Erection by Tenova 205 05-Jul-14 25-Jan-15
FCE-10000 Clearence after Fdn & Building constn for Eqpt erection 0 29-Jul-14
Equipment Receipt at site (Furnace 2)Equipment Receipt at site (Furnace 2) 60 05-Jul-14 02-Sep-14
FCE-10250 Receipt at site (Furnace 2) 60 05-Jul-14* 02-Sep-14
Furnace Box and MechanismFurnace Box and Mechanism 119 30-Jul-14 25-Nov-14
FCE-10260 Equipment Erection 119 30-Jul-14 25-Nov-14
Waste gas ducts & StackWaste gas ducts & Stack 63 23-Aug-14 24-Oct-14
FCE-10270 Equipment Erection 63 23-Aug-14 24-Oct-14
Refractory and InsulationRefractory and Insulation 67 18-Oct-14 23-Dec-14
FCE-10280 Refractory work 67 18-Oct-14 23-Dec-14
Furnace Electrical systemFurnace Electrical system 70 21-Sep-14 29-Nov-14
FCE-10290 Equipment Erection 70 21-Sep-14 29-Nov-14
Test & CommissioningTest & Commissioning 56 01-Dec-14 25-Jan-15
FCE-10300 Individual trial 30 01-Dec-14 30-Dec-14
FCE-10310 Integrated trial 19 31-Dec-14 18-Jan-15
FCE-10320 Furnace Dry out 7 19-Jan-15 25-Jan-15
FCE-10330 Furnace-2 Ready 0 25-Jan-15*
Piping WorksPiping Works 100 23-Aug-14 30-Nov-14
Furnace-2Furnace-2 100 23-Aug-14 30-Nov-14
FCE-10350 Piping Erection 100 23-Aug-14 30-Nov-14
ECR-1 & FCE area Auxiliary Electrical System incl tunnelsECR-1 & FCE area Auxiliary Electrical System incl tunnels 80 07-Dec-11 A 20-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 5 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
Civil Building & Foundation WorksCivil Building & Foundation Works 0 07-Dec-11 A 31-Mar-14 A
ECR1-10000 Civil clearance ground floor 0 17-Nov-13 A
ECR1-10010 Base ment availability 0 14-Dec-13 A
ECR-1ECR-1 0 07-Dec-11 A 31-Mar-14 A
ECR1-10030 Base Raft 0 07-Mar-12 A 23-May-12 A
ECR1-10040 Basement Wall & Column 0 23-May-12 A 07-Oct-12 A
ECR1-10050 Ground Floor Slab 0 08-Aug-12 A 25-Oct-12 A
ECR1-10020 Drawing Inputs 0 07-Dec-11 A 28-Nov-12 A
ECR1-10060 Columns 0 20-Dec-12 A 31-Jan-13 A
ECR1-10070 Roof Slab 0 11-Feb-13 A 31-May-13 A
ECR1-10080 Other Finishing Work 0 13-Feb-13 A 16-Mar-14 A
ECR1-10130 Tranformer Foundation 0 22-Feb-14 A 31-Mar-14 A
Structural Building & Technological WorksStructural Building & Technological Works 0 02-Mar-14 A 19-Apr-14 A
Crane LCSS-1Crane LCSS-1 0 02-Mar-14 A 19-Apr-14 A
LCSS1-10000 LCSS panels(3) 0 02-Mar-14 A 11-Mar-14 A
LCSS1-10010 Transformer(3sets) 0 11-Apr-14 A 19-Apr-14 A
Cable Tunnel ECR1 to ECR2Cable Tunnel ECR1 to ECR2 0 15-Apr-13 A 25-May-14 A
ECR1-10090 Drawing availabilty 0 15-Apr-13 A 08-Jul-13 A
ECR1-10100 Civil Works 0 02-Dec-13 A 25-May-14 A
Electrical & Automation WorksElectrical & Automation Works 80 24-Feb-14 A 20-Sep-14
RTDBsRTDBs 0 02-May-14 A 19-May-14 A
RTDB-10000 Slab RTDB 1 0 02-May-14 A 02-May-14 A
RTDB-10010 Slab RTDB 2 0 02-May-14 A 03-May-14 A
RTDB-10020 Slab RTDB 3 0 03-May-14 A 05-May-14 A
RTDB-10030 Slab RTDB 4 0 05-May-14 A 05-May-14 A
RTDB-10040 Slab RTDB 5 0 05-May-14 A 06-May-14 A
RTDB-10050 Slab RTDB 6 0 06-May-14 A 07-May-14 A
RTDB-10060 Slab RTDB 7 0 07-May-14 A 07-May-14 A
RTDB-10070 Fce RTDB 1 0 08-May-14 A 08-May-14 A
RTDB-10080 Fce RTDB 2 0 08-May-14 A 09-May-14 A
RTDB-10090 Fce RTDB 3 0 09-May-14 A 10-May-14 A
RTDB-10100 Fce RTDB 4 0 10-May-14 A 10-May-14 A
RTDB-10110 Fce RTDB 5 0 10-May-14 A 12-May-14 A
RTDB-10120 Fce RTDB 6 0 12-May-14 A 13-May-14 A
RTDB-10130 Fce RTDB 7 0 13-May-14 A 14-May-14 A
RTDB-10140 Fce RTDB 8 0 14-May-14 A 14-May-14 A
RTDB-10150 RTDB1 0 14-May-14 A 15-May-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 6 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RTDB-10160 RTDB2 0 15-May-14 A 16-May-14 A
RTDB-10170 RTDB3 0 16-May-14 A 16-May-14 A
RTDB-10180 RTDB4 0 17-May-14 A 17-May-14 A
RTDB-10190 RTDB24 0 17-May-14 A 19-May-14 A
Other WorksOther Works 80 24-Feb-14 A 20-Sep-14
EE-10010 LCSS 0 19-May-14 A 20-May-14 A
EE-10020 PDB2 0 20-May-14 A 20-May-14 A
EE-10030 MLDB 0 20-May-14 A 21-May-14 A
EE-10040 ELDB 0 21-May-14 A 22-May-14 A
EE-10050 Converter transformer room 0 22-May-14 A 23-May-14 A
EE-10060 Converter 0 23-May-14 A 23-May-14 A
EE-10070 Inverter 0 23-May-14 A 24-May-14 A
EE-10080 UPS 0 24-May-14 A 26-May-14 A
EE-10090 Battery 0 26-May-14 A 26-May-14 A
EE-10100 Slab transfer car drive 0 27-May-14 A 27-May-14 A
EE-10110 Ventilation MCC 0 27-May-14 A 28-May-14 A
EE-10120 SYMS room 0 28-May-14 A 29-May-14 A
EE-10130 AHU room 0 29-May-14 A 29-May-14 A
EE-10140 Earthing pits(14) 0 29-May-14 A 30-May-14 A
EE-10150 RIO 0 30-May-14 A 31-May-14 A
EE-10160 Amenities 0 31-May-14 A 02-Jun-14 A
EE-10000 tray support fabrication & erection 0 24-Feb-14 A 30-Jun-14 A
EE-10170 cable tray erection 36 30-Jun-14 A 07-Aug-14
EE-10180 cable laying & termination 30 28-Jul-14 27-Aug-14
EE-10190 Trial & Testing 10 08-Sep-14 20-Sep-14
Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping)Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping) 141 16-Jun-12 A 19-Nov-14
Civil Building & Foundation WorksCivil Building & Foundation Works 29 24-Sep-12 A 30-Jul-14
Roll Shop-A/45-14Roll Shop-A/45-14 29 24-Sep-12 A 30-Jul-14
RS-10000 Drawing Inputs 0 24-Sep-12 A 17-Jul-13 A
RS-10010 Building Columns 0 12-Apr-13 A 04-Apr-14 A
RS-10020 Equipment Foundations 14a-24 18 10-Apr-14 A 19-Jul-14
RS-10040 Equipment Foundations 32-45 29 30-Apr-14 A 30-Jul-14
RS-10030 Equipment Foundations 24-32 29 10-May-14 A 30-Jul-14*
Structural Building & Technological WorksStructural Building & Technological Works 120 16-Jun-12 A 30-Oct-14
Roll Shop-A/45-14Roll Shop-A/45-14 84 16-Jun-12 A 23-Sep-14
RS-10050 Drawing Inputs 0 16-Jun-12 A 11-Oct-12 A
RS-10060 Erection32-45 to give front for EOT erection 0 07-Jan-14 A 27-Feb-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 7 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RS-10080 Fabrication 0 01-Jul-13 A 20-May-14 A
RS-10070 Erection 14a-24 (including sheeting) 30 20-Sep-13 A 31-Jul-14*
RS-10090 Erection 24-31 (including sheeting) 65 13-Jul-13 A 23-Sep-14
RS-10065 Complition Erection32-45 (including sheeting) 65 07-Jan-14 A 23-Sep-14*
EOT CraneEOT Crane 120 11-Mar-14 A 30-Oct-14
120 T EOT Crane (Roll Shop)120 T EOT Crane (Roll Shop) 15 11-Mar-14 A 16-Jul-14
RS-EOT-10000 Erection of crane 0 11-Mar-14 A
RS-EOT-10010 Test & Commisioning 15 04-Apr-14 A 16-Jul-14
37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop)37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop) 68 02-Aug-14 30-Oct-14
RS-EOT-10020 EOT Erection 38 02-Aug-14* 20-Sep-14
RS-EOT-10030 Test & Commisioning 30 20-Sep-14 30-Oct-14*
ROLL SHOPROLL SHOP 30 04-Jul-13 A 08-Aug-14
RS-10100 Delivery of Equipment at Site of-Roll Shop 30 04-Jul-13 A 08-Aug-14
Mechanical & Piping WorksMechanical & Piping Works 96 15-Aug-14 19-Nov-14
Equipment ErectionEquipment Erection 96 15-Aug-14 19-Nov-14
RS-10110 Front readiness by Civil/ Strl & Crane for mechanical erection 0 15-Aug-14
RS-10130 Erection of priority Roll Grinders 46 16-Aug-14 30-Sep-14*
RS-10120 Erection of Roll Shop equipment (other than priority grinders) 60 01-Sep-14 30-Oct-14
RS-10150 Roll grinding 0 19-Nov-14
Roll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shopRoll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shop 115 05-Sep-14 29-Dec-14
Roll Shop - Test & TrialsRoll Shop - Test & Trials 60 31-Oct-14 29-Dec-14
RS-10140 Test & Commissioning of priority Roll Grinders 20 31-Oct-14 19-Nov-14
RS-10160 Test & Commissioning Roll Shop Eqpt (other than priority grinders) 60 31-Oct-14 29-Dec-14
Roll Shop-Pulpit Area:Roll Shop-Pulpit Area: 42 05-Sep-14 30-Oct-14
RS-10170 clearance 0 05-Sep-14 05-Sep-14
RS-10200 Equipment availablity & Drawing 1 06-Sep-14 08-Sep-14
RS-10180 Fabrication & erection of cable tray & supports 15 05-Sep-14 25-Sep-14
RS-10190 Installation of I/O Panels and HMI, Network cabinet, etc. 15 06-Sep-14 25-Sep-14
RS-10210 Cable Laying up to field equipment 15 25-Sep-14 15-Oct-14
RS-10220 Panel Earthing 27 20-Sep-14 27-Oct-14
RS-10230 Cable Glanding & Termination 10 17-Oct-14 30-Oct-14
Edger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + LabEdger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + Lab 121 01-Nov-11 A 30-Oct-14
FCE Charging & Discharge Table, Primary Descalar, R1 (incl R1 Ent Table to R1 Del Table)FCE Charging & Discharge Table, Primary Descalar, R1 (incl R1 Ent Table to R1 Del Table) 108 31-Mar-12 A 17-Oct-14
Civil Building & Foundation WorksCivil Building & Foundation Works 47 31-Mar-12 A 30-Aug-14
Charging Aisle &Stack-E-F/ 1-14Charging Aisle &Stack-E-F/ 1-14 47 31-Mar-12 A 30-Aug-14
FCE-10360 Drawing Inputs incl. Equipment foundation 0 31-Mar-12 A 29-Sep-12 A
FCE-10370 Building Column - Furnace Bay (B-C-E-F/2-13) 0 02-Jul-12 A 26-Feb-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 8 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
FCE-10390 Stack Foundation 0 05-Mar-14 A 15-Apr-14 A
FCE-10380 Charging Roller Table Equip Foundation 13-10 0 28-Mar-13 A 17-Apr-14 A
FCE-10400 Charging Roller Table Equip Foundation 10-4 47 15-Jul-13 A 30-Aug-14
Structural Building & Technological WorksStructural Building & Technological Works 42 11-Sep-12 A 12-Aug-14
Charging Aisle &Stack-E-F/ 1-13Charging Aisle &Stack-E-F/ 1-13 33 11-Sep-12 A 12-Aug-14
FCE-10410 Drawing Inputs 0 11-Sep-12 A 17-Dec-12 A
FCE-10420 Fabrication 0 15-Dec-12 A 01-Mar-14 A
FCE-10440 Erection 8-1 to give front to EOT erection 0 10-Sep-13 A 31-Mar-14 A
FCE-10430 Erection 13-8 (including sheeting) 7 15-Jul-13 A 10-Jul-14
FCE-10445 Erection 8-1 (including sheeting) 33 15-Jul-13 A 12-Aug-14
40 (on tong)/16T Crane at E-F Bay40 (on tong)/16T Crane at E-F Bay 20 31-Mar-14 A 21-Jul-14
FCE-EOT-10000 Strl building readiness for crane erection 0 31-Mar-14 A
FCE-EOT-10010 EOT Erection &Testing of crane 20 10-Apr-14 A 21-Jul-14
Receipt of Equipment at siteReceipt of Equipment at site 0 05-Jul-13 A 26-May-14 A
RM-10000 Receipt at site (Sojitz scope) 0 05-Jul-13 A 10-Mar-14 A
FCE-10450 Receipt at site (TGS scope) 0 19-Jul-13 A 23-Apr-14 A
RM-10010 Receipt at site (TGS scope) 0 15-Jul-13 A 26-May-14 A
Mechanical & Piping WorksMechanical & Piping Works 108 15-Feb-14 A 17-Oct-14
MILL MAIN EQUIPMENT ERECTIONMILL MAIN EQUIPMENT ERECTION 108 15-Feb-14 A 17-Oct-14
FRONT#1 (FURNACE ENTRY SIDE)FRONT#1 (FURNACE ENTRY SIDE) 88 27-Apr-14 A 17-Oct-14
FCE-10460 SLAB WEIGHER 8 22-Jul-14 29-Jul-14
FURNACE ENTRYTABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS)FURNACE ENTRYTABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS) 88 27-Apr-14 A 17-Oct-14
FCE-10470 MOTOR ALLIGNMENT (169 MOTORS) 19 02-Sep-14 20-Sep-14
FCE-10480 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 11 15-Sep-14 25-Sep-14
PREPARATIONPREPARATION 6 27-Apr-14 A 27-Jul-14
RM-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 27-Apr-14 A 01-May-14 A
RM-10030 ERECTION OF TABLE BEAM 1 22-Jul-14 22-Jul-14
RM-10040 INSTALLATION OF MOTOR FRAME 1 23-Jul-14 23-Jul-14
RM-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE1 24-Jul-14 24-Jul-14
RM-10060 INSTALLATION OF MOTOR 1 25-Jul-14 25-Jul-14
RM-10070 SETTING THE ANCHOR BOLTSAND NUTS 1 26-Jul-14 26-Jul-14
RM-10080 ANCHOR GROUTING AND CURING. 1 27-Jul-14 27-Jul-14
ALLIGNMENTALLIGNMENT 6 28-Jul-14 02-Aug-14
RM-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 2 28-Jul-14 29-Jul-14
RM-10100 CHECK THE LEVELNESS 2 30-Jul-14 31-Jul-14
RM-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 2 01-Aug-14 02-Aug-14
e.REMAINING WORKSe.REMAINING WORKS 22 25-Sep-14 17-Oct-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 9 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM-10120 INSTALLATION OF MOTOR COVER 1 25-Sep-14 26-Sep-14
RM-10130 INSTALLATION OF SPLASH GUARD 1 26-Sep-14 27-Sep-14
RM-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 27-Sep-14 28-Sep-14
RM-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 20 27-Sep-14 17-Oct-14
FRONT#2 (FURNACE DELIVERY SIDE)FRONT#2 (FURNACE DELIVERY SIDE) 83 05-May-14 A 28-Sep-14
FURNACE DELIVERYTABLE (34 TABLES, 86 ROLLS)FURNACE DELIVERYTABLE (34 TABLES, 86 ROLLS) 55 05-May-14 A 02-Sep-14
FCE-10490 MOTOR ALLIGNMENT (86 MOTORS) 1 10-Jul-14* 10-Jul-14
FCE-10500 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 1 11-Jul-14 11-Jul-14
a. PREPARATIONa. PREPARATION 0 05-May-14 A 10-Jun-14 A
FCE-10510 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 05-May-14 A 05-May-14 A
FCE-10520 ERECTION OF TABLE BEAM 0 06-May-14 A 06-May-14 A
FCE-10530 INSTALLATION OF MOTOR FRAME 0 06-Jun-14 A 06-Jun-14 A
FCE-10540 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 07-Jun-14 A 07-Jun-14 A
FCE-10550 INSTALLATION OF MOTOR 0 08-Jun-14 A 08-Jun-14 A
FCE-10560 SETTING THE ANCHOR BOLTSAND NUTS 0 09-Jun-14 A 09-Jun-14 A
FCE-10570 ANCHOR GROUTING AND CURING. 0 10-Jun-14 A 10-Jun-14 A
b.ALLIGNMENTb.ALLIGNMENT 0 11-Jun-14 A 13-Jun-14 A
FCE-10580 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 11-Jun-14 A 11-Jun-14 A
FCE-10590 CHECK THE LEVELNESS 0 12-Jun-14 A 12-Jun-14 A
FCE-10600 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 13-Jun-14 A 13-Jun-14 A
e.REMAINING WORKSe.REMAINING WORKS 53 12-Jul-14 02-Sep-14
FCE-10610 INSTALLATION OF MOTOR COVER 5 12-Jul-14 16-Jul-14
FCE-10620 INSTALLATION OF SPLASH GUARD 15 17-Jul-14 31-Jul-14
FCE-10630 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 3 01-Aug-14 03-Aug-14
FCE-10640 ATTACHED PIPING AND OTHER REMAINING WORKS. 30 04-Aug-14 02-Sep-14
HSB ROLLER TABLE (3 TABLES, 18 ROLLS)HSB ROLLER TABLE (3 TABLES, 18 ROLLS) 62 29-Jul-14 28-Sep-14
HSB-10000 MOTOR ALLIGNMENT (18 MOTORS) 10 07-Sep-14 16-Sep-14
HSB-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 10 12-Sep-14 21-Sep-14
a. PREPARATIONa. PREPARATION 25 29-Jul-14 22-Aug-14
HSB-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 1 29-Jul-14 29-Jul-14
HSB-10030 ERECTION OF TABLE BEAM 2 30-Jul-14 31-Jul-14
HSB-10040 INSTALLATION OF MOTOR FRAME 5 01-Aug-14 05-Aug-14
HSB-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE5 06-Aug-14 10-Aug-14
HSB-10060 INSTALLATION OF MOTOR 5 11-Aug-14 15-Aug-14
HSB-10070 SETTING THE ANCHOR BOLTSAND NUTS 4 16-Aug-14 19-Aug-14
HSB-10080 ANCHOR GROUTING AND CURING. 3 20-Aug-14 22-Aug-14
b.ALLIGNMENTb.ALLIGNMENT 15 23-Aug-14 06-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 10 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
HSB-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 5 23-Aug-14 27-Aug-14
HSB-10100 CHECK THE LEVELNESS 5 28-Aug-14 01-Sep-14
HSB-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 5 02-Sep-14 06-Sep-14
e.REMAINING WORKSe.REMAINING WORKS 7 22-Sep-14 28-Sep-14
HSB-10120 INSTALLATION OF MOTOR COVER 1 22-Sep-14 22-Sep-14
HSB-10130 INSTALLATION OF SPLASH GUARD 1 23-Sep-14 23-Sep-14
HSB-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 24-Sep-14 24-Sep-14
HSB-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 4 25-Sep-14 28-Sep-14
HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 11 25-Jul-14 04-Aug-14
HSB-10160 INSTALLATION OF DESCALING BOX 2 26-Jul-14* 27-Jul-14
HSB-10170 INSTALLATION OF SPLASH GUARD 1 28-Jul-14 28-Jul-14
HSB-10180 ATTACHED PIPING 5 29-Jul-14 02-Aug-14
HSB-10190 INSTALLTION OF PX SENSOR 1 03-Aug-14 03-Aug-14
a. PREPARATIONa. PREPARATION 0 25-Jul-14 25-Jul-14
HSB-10200 PREPARATION 0 25-Jul-14
HSB-10210 CONFIRM THE COMPLETION OF ALIGNMENT OF HSB TABLE 0 25-Jul-14*
HSB-10220 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 0 25-Jul-14
b. INSTALLATION OF BOTTOM HEADERb. INSTALLATION OF BOTTOM HEADER 1 25-Jul-14 25-Jul-14
HSB-10230 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)1 25-Jul-14 25-Jul-14
g. INSTALLTION OF DESCALING NOZZLEg. INSTALLTION OF DESCALING NOZZLE 1 04-Aug-14 04-Aug-14
HSB-10240 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 1 04-Aug-14 04-Aug-14
ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS)ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS) 63 02-Jun-14 A 08-Sep-14
RM2-10000 MOTOR ALLIGNMENT (62 MOTORS) 20 08-Jul-14* 27-Jul-14
RM2-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 35 28-Jul-14 31-Aug-14
a. PREPARATIONa. PREPARATION 0 02-Jun-14 A 14-Jun-14 A
RM2-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 02-Jun-14 A 03-Jun-14 A
RM2-10030 ERECTION OF TABLE BEAM 0 03-Jun-14 A 04-Jun-14 A
RM2-10040 INSTALLATION OF MOTOR FRAME 0 05-Jun-14 A 06-Jun-14 A
RM2-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 07-Jun-14 A 08-Jun-14 A
RM2-10060 INSTALLATION OF MOTOR 0 09-Jun-14 A 10-Jun-14 A
RM2-10070 SETTING THE ANCHOR BOLTSAND NUTS 0 11-Jun-14 A 12-Jun-14 A
RM2-10080 ANCHOR GROUTING AND CURING. 0 13-Jun-14 A 14-Jun-14 A
b.ALLIGNMENTb.ALLIGNMENT 0 15-Jun-14 A 19-Jun-14 A
RM2-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 15-Jun-14 A 15-Jun-14 A
RM2-10100 CHECK THE LEVELNESS 0 16-Jun-14 A 17-Jun-14 A
RM2-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 18-Jun-14 A 19-Jun-14 A
e.REMAINING WORKSe.REMAINING WORKS 8 01-Sep-14 08-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 11 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-10120 INSTALLATION OF MOTOR COVER 2 01-Sep-14 02-Sep-14
RM2-10130 INSTALLATION OF SPLASH GUARD 2 03-Sep-14 04-Sep-14
RM2-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 2 05-Sep-14 06-Sep-14
RM2-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 2 07-Sep-14 08-Sep-14
FRONT#3 (DELAY TABLE)FRONT#3 (DELAY TABLE) 91 15-Feb-14 A 30-Sep-14
DT-10000 COBBLE PUSHER 91 31-Mar-14 A 30-Sep-14
DELAY TABLE (9 TABLE, 58 ROLLS)DELAY TABLE (9 TABLE, 58 ROLLS) 0 15-Feb-14 A 03-May-14 A
DT-10010 MOTOR ALLIGNMENT (58 MOTORS) 0 27-Mar-14 A 10-Apr-14 A
DT-10020 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 13-Apr-14 A
a. PREPARATIONa. PREPARATION 0 15-Feb-14 A 18-Mar-14 A
DT-10030 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 15-Feb-14 A 16-Feb-14 A
DT-10040 ERECTION OF TABLE BEAM 0 18-Feb-14 A 19-Feb-14 A
DT-10050 INSTALLATION OF MOTOR FRAME 0 07-Mar-14 A 08-Mar-14 A
DT-10060 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 09-Mar-14 A 10-Mar-14 A
DT-10070 INSTALLATION OF MOTOR 0 11-Mar-14 A 13-Mar-14 A
DT-10080 SETTING THE ANCHOR BOLTSAND NUTS 0 14-Mar-14 A 15-Mar-14 A
DT-10090 ANCHOR GROUTING AND CURING. 0 16-Mar-14 A 18-Mar-14 A
b.ALLIGNMENTb.ALLIGNMENT 0 20-Mar-14 A 24-Mar-14 A
DT-10100 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 20-Mar-14 A 20-Mar-14 A
DT-10110 CHECK THE LEVELNESS 0 21-Mar-14 A 22-Mar-14 A
DT-10120 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 23-Mar-14 A 24-Mar-14 A
e.REMAINING WORKSe.REMAINING WORKS 0 13-Apr-14 A 03-May-14 A
DT-10130 INSTALLATION OF MOTOR COVER 0 13-Apr-14 A 14-Apr-14 A
DT-10140 INSTALLATION OF SPLASH GUARD 0 15-Apr-14 A 16-Apr-14 A
DT-10150 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 17-Apr-14 A 18-Apr-14 A
DT-10160 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 19-Apr-14 A 03-May-14 A
MILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTIONMILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTION 90 15-Apr-14 A 29-Sep-14
ERECTION OF G2ERECTION OF G2 53 01-Aug-14 22-Sep-14
MILL-AUX-10000 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14* 01-Aug-14
MILL-AUX-10010 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14
MILL-AUX-10020 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14
ERECTION OF G3ERECTION OF G3 53 01-Aug-14 22-Sep-14
MILL-AUX-10030 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14
MILL-AUX-10040 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14
MILL-AUX-10050 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14
ERECTION OF G4ERECTION OF G4 51 01-Aug-14 20-Sep-14
MILL-AUX-10060 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 12 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
MILL-AUX-10080 FLUSHING OF GREASE PIPES 4 02-Aug-14 05-Aug-14
MILL-AUX-10070 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14
ERECTION OF G5ERECTION OF G5 55 01-Aug-14 24-Sep-14
MILL-AUX-10100 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10090 ERECTION OF GREASE PIPING 50 01-Aug-14 19-Sep-14
MILL-AUX-10110 FLUSHING OF GREASE PIPES 5 20-Sep-14 24-Sep-14
ERECTION OF G6ERECTION OF G6 60 01-Aug-14 29-Sep-14
MILL-AUX-10120 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10130 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14
MILL-AUX-10140 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14
ERECTION OF G7ERECTION OF G7 60 01-Aug-14 29-Sep-14
MILL-AUX-10150 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10160 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14
MILL-AUX-10170 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14
ERECTION OF G8ERECTION OF G8 60 01-Aug-14 29-Sep-14
MILL-AUX-10180 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10190 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14
MILL-AUX-10200 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14
ERECTION OF G9ERECTION OF G9 60 01-Aug-14 29-Sep-14
MILL-AUX-10210 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10220 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14
MILL-AUX-10230 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14
ERECTION OF G10ERECTION OF G10 60 01-Aug-14 29-Sep-14
MILL-AUX-10240 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14
MILL-AUX-10250 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14
MILL-AUX-10260 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14
ERECTION OF RL1 (R1 GEAR LUB) SYSTEMERECTION OF RL1 (R1 GEAR LUB) SYSTEM 55 02-Jul-14 25-Aug-14
MILL-AUX-10350 Electrical Work (Sensor Erection & Termination) 30 02-Jul-14 31-Jul-14
MILL-AUX-10270 Lowering of the tank and placing at the pedestal 1 01-Aug-14* 01-Aug-14
MILL-AUX-10280 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14
MILL-AUX-10290 Alignment of tank unit 2 03-Aug-14 04-Aug-14
MILL-AUX-10300 Alignment of pump unit 2 05-Aug-14 06-Aug-14
MILL-AUX-10310 Installation of centrifuge 1 07-Aug-14 07-Aug-14
MILL-AUX-10320 Installation of Strainer and heat exchanger 10 08-Aug-14 17-Aug-14
MILL-AUX-10330 Installation of instruments at pump and tank unit 8 18-Aug-14 25-Aug-14
ERECTION OF ML1 (R1 WR BEARING LUB) SYSTEMERECTION OF ML1 (R1 WR BEARING LUB) SYSTEM 47 02-Jul-14 17-Aug-14
MILL-AUX-10440 Electrical Work (Sensor Erection & Termination) 20 02-Jul-14 21-Jul-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 13 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
MILL-AUX-10370 Lowering of the pump unit and placing at the pedestal 1 31-Jul-14 31-Jul-14
MILL-AUX-10360 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14
MILL-AUX-10380 Alignment of tank unit 2 01-Aug-14 02-Aug-14
MILL-AUX-10390 Alignment of pump unit 2 03-Aug-14 04-Aug-14
MILL-AUX-10400 Installation of centrifuge 1 05-Aug-14 05-Aug-14
MILL-AUX-10410 Installation of Strainer and heat exchanger 7 06-Aug-14 12-Aug-14
MILL-AUX-10420 Installation of instruments at pump and tank unit 15 03-Aug-14 17-Aug-14
ERECTION OF RL2 (R2 GEAR LUB) SYSTEMERECTION OF RL2 (R2 GEAR LUB) SYSTEM 51 02-Jul-14 21-Aug-14
MILL-AUX-10530 Electrical Work (Sensor Erection & Termination) 30 02-Jul-14 31-Jul-14
MILL-AUX-10450 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14
MILL-AUX-10460 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14
MILL-AUX-10470 Alignment of tank unit 2 03-Aug-14 04-Aug-14
MILL-AUX-10480 Alignment of pump unit 3 05-Aug-14 07-Aug-14
MILL-AUX-10490 Installation of centrifuge 2 08-Aug-14 09-Aug-14*
MILL-AUX-10500 Installation of Strainer and heat exchanger 2 10-Aug-14 11-Aug-14
MILL-AUX-10510 Installation of instruments at pump and tank unit 10 12-Aug-14 21-Aug-14
ERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEMERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEM 23 19-May-14 A 24-Jul-14
MILL-AUX-10540 Lowering of the tank and placing at the pedestal 0 19-May-14 A 19-May-14 A
MILL-AUX-10550 Lowering of the pump unit and placing at the pedestal 0 20-May-14 A 21-May-14 A
MILL-AUX-10560 Alignment of tank unit 0 22-May-14 A 23-May-14 A
MILL-AUX-10570 Alignment of pump unit 0 24-May-14 A 25-May-14 A
MILL-AUX-10580 Installation of centrifuge 0 26-May-14 A 27-May-14 A
MILL-AUX-10590 Installation of Strainer and heat exchanger 0 28-May-14 A 01-Jun-14 A
MILL-AUX-10600 Installation of instruments at pump and tank unit 0 02-Jun-14 A 09-Jun-14 A
MILL-AUX-10620 Electrical Work (Sensor Erection & Termination) 23 30-Jun-14 A 24-Jul-14
ERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEMERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 38 30-Jul-14 05-Sep-14
MILL-AUX-10640 Lowering of the pump unit and placing at the pedestal 1 03-Aug-14 03-Aug-14
MILL-AUX-10650 Alignment of tank unit 1 04-Aug-14 04-Aug-14
MILL-AUX-10660 Alignment of pump unit (Oil booster,metering pump) 1 05-Aug-14 05-Aug-14
MILL-AUX-10670 Installation of centrifuge 1 05-Aug-14 05-Aug-14
MILL-AUX-10680 Installation of Strainer and heat exchanger 1 06-Aug-14 06-Aug-14
MILL-AUX-10690 Installation of instruments at pump and tank unit 2 07-Aug-14 08-Aug-14
MILL-AUX-10700 Installation of valve Stands 10 30-Jul-14 08-Aug-14
MILL-AUX-10710 Electrical Work (Sensor Erection & Termination) 28 09-Aug-14 05-Sep-14
ERECTION OF DE-SCALING SYSTEMERECTION OF DE-SCALING SYSTEM 34 18-Jun-14 A 15-Sep-14
MILL-AUX-10720 Erection of Surge Tank 0 18-Jun-14 A 20-Jun-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 14 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
MILL-AUX-10730 Erection of Accumulator stands 2 23-Aug-14 24-Aug-14
MILL-AUX-10740 Erection of Descaling Pump units 2 25-Aug-14 26-Aug-14
MILL-AUX-10750 Erection of valve stands 10 27-Aug-14 05-Sep-14
MILL-AUX-10760 Electrical Work (Sensor Erection & Termination) 34 13-Aug-14 15-Sep-14
ERECTION OF HA1 (RM AUX HYD) SYSTEMERECTION OF HA1 (RM AUX HYD) SYSTEM 34 15-Apr-14 A 12-Aug-14
MILL-AUX-10830 Installation of accumulator stand 0 15-Apr-14 A 16-Apr-14 A
MILL-AUX-10770 Lowering of the tank and placing at the pedestal 0 16-May-14 A 18-May-14 A
MILL-AUX-10780 Lowering of the pump unit and placing at the pedestal 0 19-May-14 A 22-May-14 A
MILL-AUX-10790 Alignment of tank unit 0 22-May-14 A 27-May-14 A
MILL-AUX-10800 Alignment of pump unit 0 27-May-14 A 01-Jun-14 A
MILL-AUX-10810 Installation of filter circulation unit 0 01-Jun-14 A 06-Jun-14 A
MILL-AUX-10840 Installation of instruments at pump and tank unit 4 21-Jul-14* 24-Jul-14
MILL-AUX-10850 Installation of valve Stands 15 10-Jul-14* 24-Jul-14
MILL-AUX-10820 Installation of return filter line 4 01-Aug-14 04-Aug-14
MILL-AUX-10860 Electrical Work (Sensor Erection & Termination) 19 25-Jul-14 12-Aug-14
ERECTION OF HS1 (RM SERVO HYD) SYSTEMERECTION OF HS1 (RM SERVO HYD) SYSTEM 45 02-Jul-14 15-Aug-14
MILL-AUX-10870 Lowering of the tank and placing at the pedestal 3 02-Jul-14* 04-Jul-14
MILL-AUX-10880 Lowering of the pump unit and placing at the pedestal 1 05-Jul-14 05-Jul-14
MILL-AUX-10890 Alignment of tank unit 1 06-Jul-14 06-Jul-14
MILL-AUX-10900 Alignment of pump unit 1 07-Jul-14 07-Jul-14
MILL-AUX-10910 Installation of filter circulation unit 1 08-Jul-14 08-Jul-14
MILL-AUX-10920 Installation of return filter line 1 09-Jul-14 09-Jul-14
MILL-AUX-10930 Installation of accumulator stand 1 10-Jul-14 10-Jul-14
MILL-AUX-10940 Installation of instruments at pump and tank unit 10 11-Jul-14 20-Jul-14
MILL-AUX-10950 Installation of valve Stands (Incl servo valve) 10 21-Jul-14 30-Jul-14
MILL-AUX-10960 Electrical Work (Sensor Erection & Termination) 16 31-Jul-14 15-Aug-14*
Mill Elect portion & Local ElectricsMill Elect portion & Local Electrics 66 11-Jul-14 06-Oct-14
Electrical & Automation WorksElectrical & Automation Works 66 11-Jul-14 06-Oct-14
ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE)ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE) 60 11-Jul-14 27-Sep-14
B&S-10000 POWER CABLE GLANDING 20 11-Jul-14 06-Aug-14
B&S-10010 POWER CABLE SOCKETING & TERMINATION 40 06-Aug-14 27-Sep-14
ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE)ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE) 20 08-Sep-14 04-Oct-14
B&S-10020 INSTRUMENT INSTALLATION 9 08-Sep-14 19-Sep-14
B&S-10030 CABLE DUCTING LAYING & TERMINATION 5 27-Sep-14 04-Oct-14*
ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1)ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1) 28 29-Aug-14 04-Oct-14
B&S-10040 INSTRUMENT INSTALLATION 20 29-Aug-14 24-Sep-14
B&S-10050 CABLE DUCTING LAYING & TERMINATION 23 04-Sep-14 04-Oct-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 15 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2)ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2) 30 06-Aug-14 15-Sep-14
B&S-10060 INSTRUMENT INSTALLATION 7 06-Aug-14 16-Aug-14
B&S-10070 CABLE DUCTING LAYING & TERMINATION 23 16-Aug-14 15-Sep-14
ELECTRICAL WORK (FRONT#5--> DELAYTABLE)ELECTRICAL WORK (FRONT#5--> DELAYTABLE) 43 09-Aug-14 06-Oct-14
B&S-10080 INSTRUMENT INSTALLATION 30 09-Aug-14 18-Sep-14
B&S-10090 CABLE DUCTING LAYING & TERMINATION 10 22-Sep-14 06-Oct-14*
ELECTRICAL WORK (FRONT#6--> CROPSHEAR)ELECTRICAL WORK (FRONT#6--> CROPSHEAR) 43 09-Aug-14 06-Oct-14
B&S-10100 INSTRUMENT INSTALLATION 28 09-Aug-14 15-Sep-14
B&S-10110 CABLE DUCTING LAYING & TERMINATION 12 19-Sep-14 06-Oct-14*
INDIVIDUAL TRIALSINDIVIDUAL TRIALS 85 24-Jul-14 17-Oct-14
B&S-10150 FRONT#2 (FURNACE DELIVERY SIDE) INDIVIDUAL TRIAL 10 05-Oct-14 15-Oct-14
B&S-10130 FRONT#6 (CROP SHEAR) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14
B&S-10120 FRONT#5 (DELAYTABLE) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14
B&S-10140 FRONT#1 (FURNACE ENTRYSIDE) INDIVIDUAL TRIAL 7 09-Oct-14 17-Oct-14
Online FlushingOnline Flushing 58 24-Jul-14 08-Oct-14
B&S-10170 ONLINE FLUSHING OF ML2 (R2 BUR BEARING LUB) SYSTEM 11 24-Jul-14 07-Aug-14
B&S-10210 ONLINE FLUSHING OF HA1 (RM AUX HYD) SYSTEM 4 12-Aug-14 18-Aug-14
B&S-10190 ONLINE FLUSHING OF HS1 (RM SERVO HYD) SYSTEM 11 08-Sep-14 22-Sep-14*
B&S-10230 ONLINE FLUSHING OF RL1 (R1 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14*
B&S-10160 ONLINE FLUSHING OF ML1 (R1 WR BEARING LUB) SYSTEM 10 09-Sep-14 22-Sep-14*
B&S-10220 ONLINE FLUSHING OF RL2 (R2 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14*
B&S-10200 ONLINE FLUSHING OF DE-SCALING SYSTEM 16 17-Sep-14 08-Oct-14*
B&S-10180 ONLINE FLUSHING OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 10 25-Sep-14 08-Oct-14*
R2 (Incl R2 Entry Table to CS Entry Table) and TGS equipmentR2 (Incl R2 Entry Table to CS Entry Table) and TGS equipment 6 01-Nov-11 A 07-Jul-14
Civil Building & Foundation WorksCivil Building & Foundation Works 0 01-Nov-11 A 10-May-14 A
Roughing-AreaRoughing-Area 0 01-Nov-11 A 10-May-14 A
RM2-11880 Blasting 0 08-Aug-12 A 15-Sep-12 A
RM2-11860 Scale Flume 0 04-Feb-12 A 31-Oct-12 A
RM2-11850 Building Column 0 01-Feb-12 A 31-Jan-13 A
RM2-11840 Drawing Inputs incl. Equipment foundation 0 01-Nov-11 A 31-Jul-13 A
RM2-11870 Roughing Mill Equip Foundation-R2 incl. scale flume wall upto top 0 29-Apr-12 A 12-Feb-14 A
RM2-11890 Roughing Mill Equip Foundation-R1 incl. scale flume wall upto top 0 02-Nov-12 A 10-May-14 A
STRUCTURAL - RM 1 & 2 - B-C /14a - 32STRUCTURAL - RM 1 & 2 - B-C /14a - 32 5 25-Aug-12 A 07-Jul-14
RM2-11900 Drawing Inputs 0 25-Aug-12 A 31-Oct-12 A
RM2-11910 Fabrication 0 15-Jan-13 A 25-Dec-13 A
RM2-11930 Erection B-C/24-32 0 15-Sep-12 A 27-Feb-14 A
RM2-11920 Erection B-C/14-24 0 16-Feb-13 A 30-Mar-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 16 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-11940 Sheeting B-C/14-32 5 18-Jan-14 A 07-Jul-14*
RM Pulpits, LAB & Roll bite lub systemRM Pulpits, LAB & Roll bite lub system 83 03-Jan-14 A 17-Oct-14
R1-Pulpit Area:R1-Pulpit Area: 83 03-Jan-14 A 17-Oct-14
RM1-PUL-10000 Equipment availablity & Drawing 0 03-Jan-14 A 20-Jan-14 A
RM1-PUL-10010 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 19-May-14 A
RM1-PUL-10050 Panel Erection & Earthing 5 19-May-14 A 08-Jul-14
RM1-PUL-10030 Installation of I/O Panels and HMI, Network cabinet, etc. 10 15-Sep-14 27-Sep-14
RM1-PUL-10040 Cable Laying up to field equipment 50 13-Aug-14 17-Oct-14
RM1-PUL-10060 Cable Glanding & Termination 15 27-Sep-14 17-Oct-14
R2-Pulpit Area:R2-Pulpit Area: 61 03-Jan-14 A 27-Sep-14
RM2-PUL-10080 Equipment availablity & Drawing 0 03-Jan-14 A 24-Jan-14 A
RM2-PUL-10070 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 14-Apr-14 A
RM2-PUL-10110 Panel Earthing 0 14-Apr-14 A 05-Jun-14 A
RM2-PUL-10100 Installation of I/O Panels and HMI, Network cabinet, etc. 25 11-Jul-14 12-Aug-14
RM2-PUL-10120 Cable Laying up to field equipment 20 02-Sep-14 27-Sep-14
RM2-PUL-10130 Cable Glanding & Termination 20 02-Sep-14 27-Sep-14
Structural Building & Technological WorksStructural Building & Technological Works 58 23-Jun-14 A 15-Sep-14
RM2-PUL-10140 Structural & Interior Woks-R-2-Pulpits 8 23-Jun-14 A 11-Jul-14*
RM2-PUL-10150 Structural & Interior Woks-R-1-Pulpits 35 31-Jul-14* 15-Sep-14
Civil Building & Foundation WorksCivil Building & Foundation Works 17 10-May-14 A 31-Jul-14
RM2-PUL-10160 Civil Works-R-2-Pulpits 0 10-May-14 A 21-Jun-14 A
RM2-PUL-10170 Civil Works-R-1-Pulpits 17 09-Jul-14* 31-Jul-14
LABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTSLABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTS 79 03-Feb-14 A 13-Oct-14
LAB-10000 Issue LOI/Order of LABORATORY EQUIPMENT 0 03-Feb-14 A
LAB-10010 Receipt of Equipment at Site of LABORATORYEQUIPMENT 0 03-Feb-14 A 09-May-14 A
LAB-10020 Equipment Erection Work of- LABORATORY EQUIPMENT 59 09-May-14 A 16-Sep-14
LAB-10030 Cold Test of- LABORATORY EQUIPMENT 20 16-Sep-14 13-Oct-14
R1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting systemR1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting system 108 18-Jan-14 A 17-Oct-14
Mechanical & Piping WorksMechanical & Piping Works 108 18-Jan-14 A 17-Oct-14
FRONT#4 (ROUGHING MILL#1)FRONT#4 (ROUGHING MILL#1) 98 21-Apr-14 A 07-Oct-14
HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 87 02-Jul-14 26-Sep-14
FSB-10000 INSTALLATION OF DESCALING BOX 2 12-Jul-14 13-Jul-14
FSB-10010 INSTALLATION OF SPLASH GUARD 10 04-Jul-14 13-Jul-14
FSB-10020 ATTACHED PIPING 70 02-Jul-14 09-Sep-14
FSB-10030 INSTALLTION OF PX SENSOR 10 31-Aug-14 09-Sep-14
PREPARATIONPREPARATION 7 02-Jul-14 08-Jul-14
FSB-10040 PREPARATION 1 02-Jul-14 02-Jul-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 17 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
FSB-10050 CONFIRM THE ERECTION & ALIGNMENT OF HSB TABLE 5 03-Jul-14 07-Jul-14
FSB-10060 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 1 08-Jul-14 08-Jul-14
INSTALLATION OF BOTTOM HEADERINSTALLATION OF BOTTOM HEADER 3 09-Jul-14 11-Jul-14
FSB-10070 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)3 09-Jul-14 11-Jul-14
INSTALLTION OF DESCALING NOZZLEINSTALLTION OF DESCALING NOZZLE 77 12-Jul-14 26-Sep-14
FSB-10080 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 38 12-Jul-14 18-Aug-14
FSB-10090 Individual Trial of HSB 5 20-Sep-14 26-Sep-14*
RM SHOE PLATERM SHOE PLATE 0 21-Apr-14 A 16-May-14 A
RM1-10010 FOUNDATION CHECKING 0 21-Apr-14 A 21-Apr-14 A
RM1-10020 FOUNDATION CHIPPING AND PADDING 0 22-Apr-14 A 23-Apr-14 A
RM1-10040 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 15-May-14 A 15-May-14 A
RM1-10050 GROUTING & CURING 0 16-May-14 A 16-May-14 A
RM HOUSINGRM HOUSING 32 07-Jun-14 A 02-Aug-14
RM1-10060 FINAL MEASUREMENT OF HSG WITH PIANNO WIREAND TIGHTENING OF HSG AND SEPARATOR BOLT.0 07-Jun-14 A 15-Jun-14 A
RM1-10070 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 32 16-Jun-14 A 02-Aug-14
DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 07-Jun-14 A 07-Jun-14 A
RM1-10140 ERECTION OF DS HOUSING 0 07-Jun-14 A 07-Jun-14 A
WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 08-Jun-14 A 08-Jun-14 A
RM1-10180 ERECTION OF WS HOUSING 0 08-Jun-14 A 08-Jun-14 A
BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 09-Jun-14 A 09-Jun-14 A
RM1-10240 ERECTION OF BOTTOM SEPARATOR 0 09-Jun-14 A 09-Jun-14 A
TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 10-Jun-14 A 12-Jun-14 A
RM1-10280 ERECTION OF TOP SEPARATOR 0 10-Jun-14 A 10-Jun-14 A
RM1-10290 ALLIGNMENT OF RM-1 HOUSING 0 10-Jun-14 A 12-Jun-14 A
E1 HOUSING & PROPERE1 HOUSING & PROPER 12 02-Jul-14 13-Jul-14
EDG1-10000 E1 HOUSNG ERECTION &ASSEMBLY. 2 02-Jul-14 03-Jul-14
EDG1-10010 AWC & PULL BACK CYLINDER 1 04-Jul-14 04-Jul-14
EDG1-10020 REDUCER & MOTOR ERECTION AND ALLIGNMENT 1 08-Jul-14 08-Jul-14
EDG1-10030 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 1 13-Jul-14 13-Jul-14
ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 3 05-Jul-14 07-Jul-14
EDG1-10080 INSERT ROLL ADJUST FRAME IN HSG 1 05-Jul-14 05-Jul-14
EDG1-10090 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 1 06-Jul-14 06-Jul-14
EDG1-10100 INSTALL DRAG CHAIN 1 07-Jul-14 07-Jul-14
ROLL DRIVE FRAMEROLL DRIVE FRAME 1 08-Jul-14 08-Jul-14
EDG1-10110 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 1 08-Jul-14 08-Jul-14
EDG1-10120 INSTALL DRIVEASSEMBLY ON R1 HSG. 1 08-Jul-14 08-Jul-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 18 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
EDG1-10130 TIGHTEN BOLT BY REGULATED TORQUE 1 08-Jul-14 08-Jul-14
EDG1-10140 CONNECT SUPPORT FOR DRIVE. 1 08-Jul-14 08-Jul-14
SPINDLE INSTALLATIONSPINDLE INSTALLATION 1 08-Jul-14 08-Jul-14
EDG1-10150 CONNECT SPINDLEAFTER ALLIGNMENT OF REDUCER AND MOTOR 1 08-Jul-14 08-Jul-14
RM SCREW DOWNRM SCREW DOWN 7 13-Jul-14 19-Jul-14
RM1-10370 INSTALLATION AND ALLIGNMENT OF CASING 1 13-Jul-14 13-Jul-14
RM1-10340 INSTALL MOTOR BRACKET ON HOUSING 1 13-Jul-14 13-Jul-14
RM1-10350 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.1 13-Jul-14 13-Jul-14
RM1-10360 FIX THE STUD BOLT FOR MOUNTING THE CASING 1 13-Jul-14 13-Jul-14
RM1-10380 FASTENING OF CASING BOLTS. 1 14-Jul-14 14-Jul-14
RM1-10390 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 1 15-Jul-14 15-Jul-14
RM1-10400 SENSOR ASSEMBLYAND REMAINING WORKS. 1 16-Jul-14 16-Jul-14
RM1-10410 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 1 17-Jul-14 17-Jul-14
RM1-10420 INSTALLATION OF D/S SCREW & NUTASSEMBLY 1 18-Jul-14 18-Jul-14
RM1-10430 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 1 19-Jul-14 19-Jul-14
R1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 1 19-Jul-14 19-Jul-14
RM1-10460 ENTRYAND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 1 19-Jul-14 19-Jul-14
RM1-10470 ENTRYAND DELIVERY TOP STRIPPER. 1 19-Jul-14 19-Jul-14
RM1-10480 TOP WR COOLANT HEADER AND HOSE 1 19-Jul-14 19-Jul-14
RM1-10490 ATTACHED DESCALING & ROLL COOLANT PIPES 1 19-Jul-14 19-Jul-14
RM1-10500 FEED ROLLER DRIVE UNIT 1 19-Jul-14 19-Jul-14
RM1-10510 ENRTY& DELIVERYSTRIPPER CYLINDERS 1 19-Jul-14 19-Jul-14
RM1-10520 DELIVERY TOP & BOTTOM DESCALING HEADER 1 19-Jul-14 19-Jul-14
RM1-10530 INSTALLATION OF LOADING CYLINDERS 1 19-Jul-14 19-Jul-14
RM1-10540 REMAINING ASSEMBLIES (Inside rails) 1 19-Jul-14 19-Jul-14
RM1-10440 ENTRY& DELIVERY/TOP & BOTTOM STRIPPER BASE. 1 19-Jul-14 19-Jul-14
RM1-10450 ENTRYAND DELIVERY BOTTOM WR COLLANT HEADER 1 19-Jul-14 19-Jul-14
R1 SPINDLE CARRIERR1 SPINDLE CARRIER 1 20-Jul-14 20-Jul-14
RM1-10590 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14
RM1-10600 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14
RM1-10610 ATTACHED PIPING 0 20-Jul-14*
RM1-10550 INSTALLATION OF CARRIER STAND 1 20-Jul-14 20-Jul-14
RM1-10560 ALLIGNMENT OF CARRIER STAND 1 20-Jul-14 20-Jul-14
RM1-10570 BASE GROUT (including curing) 1 20-Jul-14 20-Jul-14
RM1-10580 ASSEMBLING OF SPINDLE BEARING (Offiline) 1 20-Jul-14 20-Jul-14
R1 ENT TABLE (4-Tables, 22 Rolls)R1 ENT TABLE (4-Tables, 22 Rolls) 23 02-Jul-14 24-Jul-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 19 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM1-10620 MOTOR ALLIGNMENT (22 MOTORS) 8 11-Jul-14 18-Jul-14
RM1-10630 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 2 18-Jul-14 20-Jul-14
PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14
RM1-10640 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14
RM1-10650 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14
RM1-10660 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14
RM1-10670 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE1 04-Jul-14 04-Jul-14
RM1-10680 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14
RM1-10690 SETTING THE ANCHOR BOLTSAND NUTS 1 06-Jul-14 06-Jul-14
RM1-10700 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14
ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14
RM1-10710 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14
RM1-10720 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14
RM1-10730 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 1 09-Jul-14 09-Jul-14
REMAINING WORKSREMAINING WORKS 4 20-Jul-14 24-Jul-14
RM1-10740 INSTALLATION OF MOTOR COVER 1 20-Jul-14 20-Jul-14
RM1-10750 INSTALLATION OF SPLASH GUARD 1 21-Jul-14 21-Jul-14
RM1-10760 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 21-Jul-14 22-Jul-14
RM1-10770 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 22-Jul-14 23-Jul-14
RM1-10780 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 1 23-Jul-14 24-Jul-14
R1 DEL TABLE (3 TABLES, 17 ROLLS)R1 DEL TABLE (3 TABLES, 17 ROLLS) 92 02-Jul-14 01-Oct-14
RM1-10790 MOTOR ALLIGNMENT (17 MOTORS) 34 10-Jul-14 12-Aug-14
RM1-10800 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 47 13-Aug-14 28-Sep-14
PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14
RM1-10810 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14
RM1-10820 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14
RM1-10830 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14
RM1-10840 TEMPORARY INSTALLATION AND TEMPORARYALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.1 04-Jul-14 04-Jul-14
RM1-10850 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14
RM1-10860 SETTLING THE ANCHOR BOLTS AND NUTS 1 06-Jul-14 06-Jul-14
RM1-10870 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14
ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14
RM1-10880 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14
RM1-10890 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14
RM1-10900 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 1 09-Jul-14 09-Jul-14
REMAINING WORKSREMAINING WORKS 3 29-Sep-14 01-Oct-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 20 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM1-10910 INSTALLATION OF MOTOR COVER 1 29-Sep-14 29-Sep-14
RM1-10920 INSTALLATION OF SPLASH GUARD 1 29-Sep-14 29-Sep-14
RM1-10930 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 30-Sep-14 30-Sep-14
RM1-10940 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 01-Oct-14 01-Oct-14
R1 ENT SIDE GUIDER1 ENT SIDE GUIDE 36 24-Jul-14 29-Aug-14
RM1-10950 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 24-Jul-14 26-Jul-14
RM1-10960 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 26-Jul-14 28-Jul-14
RM1-10970 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 01-Aug-14 02-Aug-14
RM1-10980 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)1 02-Aug-14 03-Aug-14
RM1-10990 CONNECTION OF GEAR COUPLING 1 03-Aug-14 04-Aug-14
ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 28-Jul-14 30-Jul-14
PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 28-Jul-14 29-Jul-14
RM1-11000 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-Jul-14 28-Jul-14
RM1-11010 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-Jul-14 28-Jul-14
RM1-11020 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-Jul-14 29-Jul-14
RM1-11030 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 29-Jul-14 29-Jul-14
MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 29-Jul-14 30-Jul-14
RM1-11040 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-Jul-14 29-Jul-14
RM1-11050 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-Jul-14 29-Jul-14
RM1-11060 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©1 30-Jul-14 30-Jul-14
ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 30-Jul-14 01-Aug-14
RM1-11070 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 30-Jul-14 30-Jul-14
RM1-11080 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-Jul-14 30-Jul-14
RM1-11090 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 31-Jul-14 31-Jul-14
RM1-11100 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 31-Jul-14 31-Jul-14
RM1-11110 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-Jul-14 31-Jul-14
RM1-11120 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 01-Aug-14 01-Aug-14
MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 25 04-Aug-14 29-Aug-14
RM1-11130 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 04-Aug-14 05-Aug-14
RM1-11140 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 05-Aug-14 05-Aug-14
RM1-11150 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 29-Aug-14 29-Aug-14
R1 DEL SIDE GUIDER1 DEL SIDE GUIDE 45 04-Aug-14 17-Sep-14
RM1-11160 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m4 04-Aug-14* 07-Aug-14
RM1-11170 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 07-Aug-14 09-Aug-14
RM1-11180 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 3 12-Aug-14 15-Aug-14
RM1-11190 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 15-Aug-14 18-Aug-14*
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 21 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 09-Aug-14 11-Aug-14
PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 09-Aug-14 10-Aug-14
RM1-11200 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 09-Aug-14 09-Aug-14
RM1-11210 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 09-Aug-14 09-Aug-14
RM1-11220 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 10-Aug-14 10-Aug-14
RM1-11230 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 10-Aug-14 10-Aug-14
MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 10-Aug-14 11-Aug-14
RM1-11240 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 10-Aug-14 10-Aug-14
RM1-11250 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 10-Aug-14 10-Aug-14
RM1-11260 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 11-Aug-14 11-Aug-14
ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 10-Aug-14 12-Aug-14
RM1-11270 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 10-Aug-14 10-Aug-14
RM1-11280 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 10-Aug-14 10-Aug-14
RM1-11290 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 11-Aug-14 11-Aug-14
RM1-11300 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 11-Aug-14 11-Aug-14
RM1-11310 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 11-Aug-14 11-Aug-14
RM1-11320 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 12-Aug-14 12-Aug-14
MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 30 18-Aug-14 17-Sep-14
RM1-11330 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 18-Aug-14 19-Aug-14
RM1-11340 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 19-Aug-14 19-Aug-14
RM1-11350 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 17-Sep-14 17-Sep-14
R1 WR CHANGING DEVICER1 WR CHANGING DEVICE 80 20-Jul-14 07-Oct-14
RM1-11360 INSTALLATION OF AIR CYLINDER 2 05-Aug-14* 06-Aug-14
RM1-11370 ALLIGNMENT OF AIR CYLINDER 2 07-Aug-14 08-Aug-14
PREPARATIONPREPARATION 20 20-Jul-14 08-Aug-14
RM1-11380 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 8 20-Jul-14 27-Jul-14
RM1-11390 CHECKING OF FOUNDATION 3 28-Jul-14 30-Jul-14
RM1-11400 CHIPPING AND PADDING 3 06-Aug-14 08-Aug-14
INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 12 09-Aug-14 20-Aug-14
RM1-11410 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 6 09-Aug-14 14-Aug-14
RM1-11420 INSTALL RAIL,HYD. CYLINDER BASEAND RAIL BASE FOR FOR THE ROLL TRASVERSE. 6 15-Aug-14 20-Aug-14
ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 20 21-Aug-14 09-Sep-14
RM1-11430 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 4 21-Aug-14 24-Aug-14
RM1-11440 POSITIONING FROM R1 MILL CENTRE LINE 4 25-Aug-14 28-Aug-14
RM1-11450 ADJUSTING THETOP OF RAILAND ALLIGNMENT OF CYLINDER BASE. 4 29-Aug-14 01-Sep-14
RM1-11460 WELDING THE RAIL STOPPER PLATE. 8 02-Sep-14 09-Sep-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 22 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 6 10-Sep-14 15-Sep-14
RM1-11470 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 1 10-Sep-14 10-Sep-14
RM1-11480 POSITIONING FROM CENTRE OF DATUM RAIL 1 11-Sep-14 11-Sep-14
RM1-11490 POSITIONING FROM R1 MILL CENTRE LINE 1 12-Sep-14 12-Sep-14
RM1-11500 ADJUSTING THETOP OF RAIL FROM BENCHMARK 1 13-Sep-14 13-Sep-14
RM1-11510 WELDING THE RAIL STOPPER PLATE 1 14-Sep-14 14-Sep-14
RM1-11520 ADJUSTING THE CYLINDER CENTRE 1 15-Sep-14 15-Sep-14
ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 5 16-Sep-14 20-Sep-14
RM1-11530 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 2 16-Sep-14 17-Sep-14
RM1-11540 POSITIONING FROM SIDE SHIFT CAR CENTRE 1 18-Sep-14 18-Sep-14
RM1-11550 POSITIONING FROM MILL CENTRE 1 19-Sep-14 19-Sep-14
RM1-11560 WELDING THE CYLINDER STOPPER PLATE 1 20-Sep-14 20-Sep-14
INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 17 21-Sep-14 07-Oct-14
RM1-11570 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 1 21-Sep-14 21-Sep-14
RM1-11580 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 1 22-Sep-14 22-Sep-14
RM1-11590 CONNECT CYLINDER WITH SIDE SHIFT CAR 1 23-Sep-14 23-Sep-14
RM1-11600 INSTALL THE FLOOR PLATES 14 24-Sep-14 07-Oct-14
FRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIALFRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIAL 30 17-Sep-14 17-Oct-14
B&S-10240 ROUGHING MILL TRIAL 30 17-Sep-14* 17-Oct-14
FRONT#5 (ROUGHING MILL#2)FRONT#5 (ROUGHING MILL#2) 80 15-Feb-14 A 24-Sep-14
RM2-10160 SAFETY SCAFFOLDING INSTALLATION 0 28-Feb-14 A 02-Mar-14 A
RM SHOE PLATERM SHOE PLATE 0 15-Feb-14 A 22-Feb-14 A
RM2-10170 FOUNDATION CHECKING 0 15-Feb-14 A 16-Feb-14 A
RM2-10180 FOUNDATION CHIPPING AND PADDING 0 17-Feb-14 A 18-Feb-14 A
RM2-10190 PREPARATION OF INSTALLATION 0 17-Feb-14 A 18-Feb-14 A
RM2-10200 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 19-Feb-14 A 20-Feb-14 A
RM2-10210 GROUTING 0 21-Feb-14 A 22-Feb-14 A
RM HOUSINGRM HOUSING 0 23-Feb-14 A 24-Mar-14 A
RM2-10220 FINAL MEASUREMENT OF HSG WITH PIANNO WIREAND TIGHTENING OF HSG AND SEPARATOR BOLT.0 22-Mar-14 A 22-Mar-14 A
RM2-10230 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 0 23-Mar-14 A 24-Mar-14 A
PREPARATIONPREPARATION 0 23-Feb-14 A 23-Feb-14 A
RM2-10280 HSG SURFACE TRIMMING 0 23-Feb-14 A 23-Feb-14 A
RM2-10290 SETUP OF HSG VERTICALLITY MEASUREMENT JIGS AND SCALFOLDING 0 23-Feb-14 A 23-Feb-14 A
RM2-10240 ASSEMBLY OF HOUSING LIFTING BEAM &TRIAL OF THE SAME WITH BOTH THE 120 TON CRANE0 23-Feb-14 A 23-Feb-14 A
RM2-10250 TRANSPORTING AND POSITIONING HSG AS REFERED IN MANUAL 0 23-Feb-14 A 23-Feb-14 A
RM2-10260 INSTALLATION OF MILLATTACHED PIPING WHICH EVER POSIBLE 0 23-Feb-14 A 23-Feb-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 23 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-10270 INSTALLATION OF TEMPORARY SCALFOLDING AND LADDER FOR THE ACCESSTO THE MILL TOP0 23-Feb-14 A 23-Feb-14 A
DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 26-Feb-14 A 26-Feb-14 A
RM2-10300 LIFTING THE DS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREATO INSTALL POSITION0 26-Feb-14 A 26-Feb-14 A
RM2-10310 PUTTING HSG ON SHOE PLATEAND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 26-Feb-14 A 26-Feb-14 A
RM2-10320 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BYFOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAMEAS DRAWING0 26-Feb-14 A 26-Feb-14 A
RM2-10330 PUSH THE HSG TO THE DELIVERY SIDE SHOE PLATEAND VERIFY THE ZERO GAPS BETWEEN HSG AND SHOE PLATESAND TIGHTEN THE FOO0 26-Feb-14 A 26-Feb-14 A
WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 04-Mar-14 A 09-Mar-14 A
RM2-10340 LIFTING THE WS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREATO INSTALL POSITION0 04-Mar-14 A 04-Mar-14 A
RM2-10350 PUTTING HSG ON SHOE PLATEAND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 05-Mar-14 A 05-Mar-14 A
RM2-10360 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BYFOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAMEAS DRAWING0 06-Mar-14 A 06-Mar-14 A
RM2-10370 PUSH THE HSG TO THE ENTRY SIDE SHOE PLATEAND VERIFYTHE ZERO GAPS BETWEEN THE HSG AND SHOE PLATESAND TIGHTEN THE FOO0 07-Mar-14 A 07-Mar-14 A
RM2-10380 INSTALL LINER BETWEEN ENTRY SIDE SHOE PLATE AND HSG. 0 08-Mar-14 A 08-Mar-14 A
RM2-10390 VERIFYTHE FINAL CLEARANCE. 0 09-Mar-14 A 09-Mar-14 A
BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 10-Mar-14 A 13-Mar-14 A
RM2-10400 PULL IN THE BOTTOM SEPARATOR BOLTS IN HSG AND TEMPORARY SETTING BOTTOM SEPARATOR INTO THE HSG0 10-Mar-14 A 11-Mar-14 A
RM2-10410 VERIFYTHE ZERO GAPS FOR CONTACT SURFACE OF SEPARATOR TO DS HSG. 0 12-Mar-14 A 12-Mar-14 A
RM2-10420 VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF WS HSG TO SHOE PLATE. 0 12-Mar-14 A 12-Mar-14 A
RM2-10430 FINAL TIGHTNING OF HSG FOOT BOLTSAND SEPARATOR BOLTSAFTER COMPLETING THEALLIGNMENT OF MILL HOUSING0 13-Mar-14 A 13-Mar-14 A
TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 14-Mar-14 A 21-Mar-14 A
RM2-10440 ASSEMBLING THETEMPORARYSCALFOLDING FOT THE INSTALLATION AREA 0 14-Mar-14 A 14-Mar-14 A
RM2-10450 SETTING THE JACK BETWEEN DS HSG AND WS HSG 0 15-Mar-14 A 15-Mar-14 A
RM2-10460 INSTALL THE TOP SEPARATOR TO THE HSG STEPPED SURFACE 0 16-Mar-14 A 16-Mar-14 A
RM2-10470 INSERT THE BOLT AND REMOVE THE JACK 0 17-Mar-14 A 17-Mar-14 A
RM2-10480 ALLIGN THE CENTRE OF THE COTTER PIN SLOTS OF THE DSAND WS HSG 0 18-Mar-14 A 19-Mar-14 A
RM2-10490 FINAL TIGHTNING OF HSG FOOT BOLTSAND SEPARATOR BOLTSAFTER COMPLETING THEALLIGNMENT OF MILL HOUSING0 20-Mar-14 A 21-Mar-14 A
E2 PROPERE2 PROPER 0 08-Apr-14 A 05-May-14 A
EDG1-10160 E1 HOUSNG ASSEMBLY(Offline) 0 08-Apr-14 A 09-Apr-14 A
EDG1-10170 AWC & PULL BACK CYLINDER 0 14-Apr-14 A 15-Apr-14 A
EDG1-10190 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 0 30-Apr-14 A 03-May-14 A
EDG1-10180 REDUCER & MOTOR ERECTION AND ALLIGNMENT 0 05-May-14 A 05-May-14 A
E2 HOUSING ERECTIONE2 HOUSING ERECTION 0 10-Apr-14 A 13-Apr-14 A
EDG1-10200 INSTALL & VERIFYTHE ZERO GAPS FOR CONTACT SURFACE OF HSG TO TOPOF INSTALATION LINER0 10-Apr-14 A 10-Apr-14 A
EDG1-10210 PUSH THE HSG TO DELIVERY SIDE AND CONTACT TO R1 HSG. 0 11-Apr-14 A 11-Apr-14 A
EDG1-10220 MEASURE THE RAIL TOP SURFACE WITH STRAIGHT EDGEAND PRECISION LEVEL. 0 12-Apr-14 A 12-Apr-14 A
EDG1-10230 FINAL TIGHTENING THE HSG FOOT BOLTS AND JOINT BOLTSAFTER COMPLETING THEALIGNMENT OF E1.0 13-Apr-14 A 13-Apr-14 A
ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 0 16-Apr-14 A 18-Apr-14 A
EDG1-10240 INSERT ROLL ADJUST FRAME IN HSG 0 16-Apr-14 A 16-Apr-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 24 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
EDG1-10250 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 0 17-Apr-14 A 17-Apr-14 A
EDG1-10260 INSTALL DRAG CHAIN 0 18-Apr-14 A 18-Apr-14 A
ROLL DRIVE FRAMEROLL DRIVE FRAME 0 20-Apr-14 A 23-Apr-14 A
EDG1-10270 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 0 20-Apr-14 A 20-Apr-14 A
EDG1-10280 INSTALL DRIVEASSEMBLY ON R1 HSG. 0 21-Apr-14 A 21-Apr-14 A
EDG1-10290 TIGHTEN BOLT BY REGULATED TORQUE 0 22-Apr-14 A 22-Apr-14 A
EDG1-10300 CONNECT SUPPORT FOR DRIVE. 0 23-Apr-14 A 23-Apr-14 A
SPINDLE INSTALLATIONSPINDLE INSTALLATION 0 28-Apr-14 A 29-Apr-14 A
EDG1-10310 CONNECT SPINDLEAFTER ALLIGNMENT OF REDUCER AND MOTOR 0 28-Apr-14 A 29-Apr-14 A
RM SCREW DOWNRM SCREW DOWN 0 31-Mar-14 A 19-Apr-14 A
RM2-10500 INSTALL MOTOR BRACKET ON HOUSING 0 31-Mar-14 A 31-Mar-14 A
RM2-10510 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.0 07-Apr-14 A 07-Apr-14 A
RM2-10520 FIX THE STUD BOLT FOR MOUNTING THE CASING 0 07-Apr-14 A 07-Apr-14 A
RM2-10530 INSTALLATION AND ALLIGNMENT OF CASING 0 08-Apr-14 A 09-Apr-14 A
RM2-10540 FASTENING OF CASING BOLTS. 0 10-Apr-14 A 10-Apr-14 A
RM2-10550 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 0 11-Apr-14 A 12-Apr-14 A
RM2-10560 SENSOR ASSEMBLYAND REMAINING WORKS. 0 13-Apr-14 A 13-Apr-14 A
RM2-10570 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 0 14-Apr-14 A 15-Apr-14 A
RM2-10580 INSTALLATION OF D/S SCREW & NUTASSEMBLY 0 16-Apr-14 A 17-Apr-14 A
RM2-10590 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 0 18-Apr-14 A 19-Apr-14 A
R2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 0 20-Apr-14 A 13-May-14 A
RM2-10600 ENTRY& DELIVERY/TOP & BOTTOM STRIPPER BASE. 0 20-Apr-14 A 21-Apr-14 A
RM2-10610 ENTRYAND DELIVERY BOTTOM WR COLLANT HEADER 0 22-Apr-14 A 23-Apr-14 A
RM2-10620 ENTRYAND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 0 24-Apr-14 A 25-Apr-14 A
RM2-10630 ENTRYAND DELIVERY TOP STRIPPER. 0 26-Apr-14 A 28-Apr-14 A
RM2-10640 TOP WR COOLANT HEADER AND HOSE 0 29-Apr-14 A 30-Apr-14 A
RM2-10650 ATTACHED DESCALING & ROLL COOLANT PIPES 0 01-May-14 A 03-May-14 A
RM2-10660 FEED ROLLER DRIVE UNIT 0 04-May-14 A 05-May-14 A
RM2-10670 ENRTY& DELIVERYSTRIPPER CYLINDERS 0 06-May-14 A 07-May-14 A
RM2-10680 DELIVERY TOP & BOTTOM DESCALING HEADER 0 08-May-14 A 09-May-14 A
RM2-10690 INSTALLATION OF LOADING CYLINDERS 0 10-May-14 A 11-May-14 A
RM2-10700 REMAINING ASSEMBLIES (Inside rails) 0 12-May-14 A 13-May-14 A
R2 SPINDLE CARRIERR2 SPINDLE CARRIER 0 14-May-14 A 26-May-14 A
RM2-10710 INSTALLATION OF CARRIER STAND 0 14-May-14 A 15-May-14 A
RM2-10720 ALLIGNMENT OF CARRIER STAND 0 16-May-14 A 18-May-14 A
RM2-10730 BASE GROUT (including curing) 0 19-May-14 A 20-May-14 A
RM2-10740 ASSEMBLING OF SPINDLE BEARING (Offiline) 0 21-May-14 A 25-May-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 25 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-10750 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A
RM2-10760 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A
RM2-10770 ATTACHED PIPING 0 26-May-14 A
R2 ENT TABLE (4-Tables, 22 Rolls)R2 ENT TABLE (4-Tables, 22 Rolls) 0 25-Mar-14 A 24-May-14 A
RM2-10780 MOTOR ALLIGNMENT (22 MOTORS) 0 19-Apr-14 A 12-May-14 A
RM2-10790 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 12-May-14 A 20-May-14 A
PREPARATIONPREPARATION 0 25-Mar-14 A 06-May-14 A
RM2-10800 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 25-Mar-14 A 26-Mar-14 A
RM2-10810 ERECTION OF TABLE BEAM 0 28-Mar-14 A 11-Apr-14 A
RM2-10820 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A
RM2-10830 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 02-May-14 A 03-May-14 A
RM2-10840 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A
RM2-10850 SETTING THE ANCHOR BOLTSAND NUTS 0 04-May-14 A 05-May-14 A
RM2-10860 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A
ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 A
RM2-10870 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A
RM2-10880 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A
RM2-10890 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 08-May-14 A 08-May-14 A
REMAINING WORKSREMAINING WORKS 0 20-May-14 A 24-May-14 A
RM2-10900 INSTALLATION OF MOTOR COVER 0 20-May-14 A 20-May-14 A
RM2-10910 INSTALLATION OF SPLASH GUARD 0 21-May-14 A 21-May-14 A
RM2-10920 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 21-May-14 A 22-May-14 A
RM2-10930 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 22-May-14 A 23-May-14 A
RM2-10940 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 0 23-May-14 A 24-May-14 A
R2 DEL TABLE (3 TABLES, 17 ROLLS)R2 DEL TABLE (3 TABLES, 17 ROLLS) 0 20-Mar-14 A 31-May-14 A
RM2-10950 MOTOR ALLIGNMENT (17 MOTORS) 0 23-Apr-14 A 20-May-14 A
RM2-10960 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 0 20-May-14 A 28-May-14 A
PREPARATIONPREPARATION 0 20-Mar-14 A 06-May-14 A
RM2-10970 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 20-Mar-14 A 22-Mar-14 A
RM2-10980 ERECTION OF TABLE BEAM 0 26-Mar-14 A 16-Apr-14 A
RM2-10990 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A
RM2-11000 TEMPORARY INSTALLATION AND TEMPORARYALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.0 02-May-14 A 03-May-14 A
RM2-11010 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A
RM2-11020 SETTLING THE ANCHOR BOLTS AND NUTS 0 04-May-14 A 05-May-14 A
RM2-11030 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A
ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 A
RM2-11040 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 26 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-11050 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A
RM2-11060 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 0 08-May-14 A 08-May-14 A
REMAINING WORKSREMAINING WORKS 0 28-May-14 A 31-May-14 A
RM2-11070 INSTALLATION OF MOTOR COVER 0 28-May-14 A 28-May-14 A
RM2-11080 INSTALLATION OF SPLASH GUARD 0 29-May-14 A 29-May-14 A
RM2-11090 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 29-May-14 A 30-May-14 A
RM2-11100 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 30-May-14 A 31-May-14 A
R2 ENT SIDE GUIDER2 ENT SIDE GUIDE 9 28-May-14 A 15-Jul-14
RM2-11110 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 07-Jul-14* 08-Jul-14
RM2-11120 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 09-Jul-14 10-Jul-14
RM2-11130 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 11-Jul-14 11-Jul-14
RM2-11140 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)2 12-Jul-14 13-Jul-14
RM2-11150 CONNECTION OF GEAR COUPLING 2 14-Jul-14 15-Jul-14*
ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 0 28-May-14 A 30-May-14 A
PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 0 28-May-14 A 29-May-14 A
RM2-11160 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-May-14 A 28-May-14 A
RM2-11170 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-May-14 A 28-May-14 A
RM2-11180 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-May-14 A 29-May-14 A
RM2-11190 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 29-May-14 A 29-May-14 A
MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 0 29-May-14 A 30-May-14 A
RM2-11200 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-May-14 A 29-May-14 A
RM2-11210 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-May-14 A 29-May-14 A
RM2-11220 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©0 30-May-14 A 30-May-14 A
ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 0 30-May-14 A 01-Jun-14 A
RM2-11230 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 30-May-14 A 30-May-14 A
RM2-11240 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-May-14 A 30-May-14 A
RM2-11250 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 31-May-14 A 31-May-14 A
RM2-11260 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME0 31-May-14 A 31-May-14 A
RM2-11270 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-May-14 A 31-May-14 A
RM2-11280 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 0 01-Jun-14 A 01-Jun-14 A
MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 0 06-Jun-14 A 08-Jun-14 A
RM2-11290 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 0 06-Jun-14 A 07-Jun-14 A
RM2-11300 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL0 07-Jun-14 A 07-Jun-14 A
RM2-11310 CONNECT THE TOP RACK BARS WITH CYLINDERS 0 08-Jun-14 A 08-Jun-14 A
R2 DEL SIDE GUIDER2 DEL SIDE GUIDE 79 08-Jul-14 24-Sep-14
RM2-11320 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 08-Jul-14* 09-Jul-14
RM2-11330 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 10-Jul-14 11-Jul-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 27 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-11340 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 18-Sep-14 19-Sep-14
RM2-11350 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 19-Sep-14 22-Sep-14
ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 47 02-Aug-14 17-Sep-14
PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 46 02-Aug-14 16-Sep-14
RM2-11360 REMOVE UPPER PART COVER OF SUPPORT FRAME 1 02-Aug-14* 02-Aug-14
RM2-11370 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 1 03-Aug-14 03-Aug-14
RM2-11380 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 1 04-Aug-14 04-Aug-14
RM2-11390 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION4 12-Sep-14 16-Sep-14*
MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 16-Sep-14 17-Sep-14
RM2-11400 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 16-Sep-14 17-Sep-14
RM2-11410 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 17-Sep-14 17-Sep-14
RM2-11420 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 17-Sep-14 17-Sep-14
ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 16-Sep-14 18-Sep-14
RM2-11430 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 16-Sep-14 17-Sep-14
RM2-11440 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 17-Sep-14 17-Sep-14
RM2-11450 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 17-Sep-14 17-Sep-14
RM2-11460 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 17-Sep-14 18-Sep-14
RM2-11470 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 18-Sep-14 18-Sep-14
RM2-11480 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 18-Sep-14 18-Sep-14
MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 2 22-Sep-14 24-Sep-14
RM2-11490 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 22-Sep-14 23-Sep-14
RM2-11500 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 23-Sep-14 24-Sep-14
RM2-11510 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 24-Sep-14 24-Sep-14
R2 WR CHANGING DEVICER2 WR CHANGING DEVICE 0 20-May-14 A 13-Jun-14 A
RM2-11520 INSTALLATION OF AIR CYLINDER 0 12-Jun-14 A 12-Jun-14 A
RM2-11530 ALLIGNMENT OF AIR CYLINDER 0 13-Jun-14 A 13-Jun-14 A
PREPARATIONPREPARATION 0 20-May-14 A 22-May-14 A
RM2-11540 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 0 20-May-14 A 20-May-14 A
RM2-11550 CHECKING OF FOUNDATION 0 21-May-14 A 21-May-14 A
RM2-11560 CHIPPING AND PADDING 0 22-May-14 A 22-May-14 A
INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 0 23-May-14 A 24-May-14 A
RM2-11570 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 0 23-May-14 A 23-May-14 A
RM2-11580 INSTALL RAIL,HYD. CYLINDER BASEAND RAIL BASE FOR FOR THE ROLL TRASVERSE. 0 24-May-14 A 24-May-14 A
ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 0 25-May-14 A 28-May-14 A
RM2-11590 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 25-May-14 A 25-May-14 A
RM2-11600 POSITIONING FROM R1 MILL CENTRE LINE 0 26-May-14 A 26-May-14 A
RM2-11610 ADJUSTING THETOP OF RAILAND ALLIGNMENT OF CYLINDER BASE. 0 27-May-14 A 27-May-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 28 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
RM2-11620 WELDING THE RAIL STOPPER PLATE. 0 28-May-14 A 28-May-14 A
ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 0 29-May-14 A 03-Jun-14 A
RM2-11630 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 29-May-14 A 29-May-14 A
RM2-11640 POSITIONING FROM CENTRE OF DATUM RAIL 0 30-May-14 A 30-May-14 A
RM2-11650 POSITIONING FROM R1 MILL CENTRE LINE 0 31-May-14 A 31-May-14 A
RM2-11660 ADJUSTING THETOP OF RAIL FROM BENCHMARK 0 01-Jun-14 A 01-Jun-14 A
RM2-11670 WELDING THE RAIL STOPPER PLATE 0 02-Jun-14 A 02-Jun-14 A
RM2-11680 ADJUSTING THE CYLINDER CENTRE 0 03-Jun-14 A 03-Jun-14 A
ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 0 04-Jun-14 A 07-Jun-14 A
RM2-11690 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 0 04-Jun-14 A 04-Jun-14 A
RM2-11700 POSITIONING FROM SIDE SHIFT CAR CENTRE 0 05-Jun-14 A 05-Jun-14 A
RM2-11710 POSITIONING FROM MILL CENTRE 0 06-Jun-14 A 06-Jun-14 A
RM2-11720 WELDING THE CYLINDER STOPPER PLATE 0 07-Jun-14 A 07-Jun-14 A
INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 0 08-Jun-14 A 11-Jun-14 A
RM2-11730 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 0 08-Jun-14 A 08-Jun-14 A
RM2-11740 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 0 09-Jun-14 A 09-Jun-14 A
RM2-11750 CONNECT CYLINDER WITH SIDE SHIFT CAR 0 10-Jun-14 A 10-Jun-14 A
RM2-11760 INSTALL THE FLOOR PLATES 0 11-Jun-14 A 11-Jun-14 A
R2 BUR CHANGING DEVICER2 BUR CHANGING DEVICE 0 12-May-14 A 19-May-14 A
SLED BASE RAIL INSTALLATIONSLED BASE RAIL INSTALLATION 0 12-May-14 A 15-May-14 A
RM2-11770 POSITIONING FROM PASS LINE CENTRE 0 12-May-14 A 12-May-14 A
RM2-11780 POSITIONING FROM MILL CENTRE 0 13-May-14 A 13-May-14 A
RM2-11790 ADJUST AND MEASURE THE TOPOF RAIL WRT BENCH MARK 0 14-May-14 A 14-May-14 A
RM2-11800 WELDING THE RAIL BASE PLATE 0 15-May-14 A 15-May-14 A
SLED TRAVERCE CYLINDERSLED TRAVERCE CYLINDER 0 17-May-14 A 19-May-14 A
RM2-11810 POSITION FROM LINE CENTRE 0 17-May-14 A 17-May-14 A
RM2-11820 POSITION FROM MILL CENTRE 0 18-May-14 A 18-May-14 A
RM2-11830 MEASURE AND ADJUST THE CENTRE OF TRUNION FROM BENCH MARK. 0 19-May-14 A 19-May-14 A
FRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIALFRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIAL 30 15-Sep-14 15-Oct-14
B&S-10250 ROUGHING MILL TRIAL 30 15-Sep-14* 15-Oct-14
FRONT#6 (CROP SHEAR)FRONT#6 (CROP SHEAR) 46 18-Jan-14 A 16-Aug-14
CROP SHEARCROP SHEAR 46 18-Jan-14 A 16-Aug-14
CS-10000 INSTALLATION AND ALIGNMENT OF GEAR, REDUCER & MOTOR 0 22-Feb-14 A 23-Apr-14 A
CS-10010 INSTALLTION OF COUPLING SUPPORT & COUPLING 0 23-Apr-14 A 03-Jun-14 A
CS-10020 REMAINING WORKS AND ATTACHED PIPING 46 02-Jul-14 16-Aug-14
SHOE PLATE ALIGNMENTSHOE PLATE ALIGNMENT 0 18-Jan-14 A 18-Feb-14 A
Safety measure for openingSafety measure for opening 0 18-Jan-14 A 18-Feb-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 29 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
CS-10030 Since the lower part is crop chute, install a scaffolding with enough strength. 0 18-Jan-14 A
CS-10040 Lashing of scaffolding board should use the annealing wire. 0 18-Feb-14 A
Foundation checkFoundation check 0 19-Jan-14 A 25-Jan-14 A
CS-10050 Check foundation and anchor bolts according to JIMS and " Instruction Manual for Erection (10065148-2002072-WP001)"0 19-Jan-14 A 19-Jan-14 A
CS-10060 Measure the position of foundation bolts from Line center and Crop Shear center. 0 20-Jan-14 A 20-Jan-14 A
CS-10070 Measure the height of foundation bolts from reference level. 0 22-Jan-14 A 23-Jan-14 A
CS-10080 Measure the clearance of Crop Shear Assembly installing area. Verify the no interference foundation to crop shear0 24-Jan-14 A 25-Jan-14 A
Foundation Chipping (Roughing Foundation) and PaddingFoundation Chipping (Roughing Foundation) and Padding 0 12-Feb-14 A 14-Feb-14 A
CS-10090 Chipping whole surface of grouting area. 0 12-Feb-14 A 13-Feb-14 A
CS-10100 Sprinkle water and avoid dust. 0 14-Feb-14 A
CS-10110 Cleaning the chipping surface (ex. dust, water, etc.) after completion of the chipping. 0 14-Feb-14 A
PaddingPadding 0 14-Feb-14 A 15-Feb-14 A
CS-10120 Execute padding according to Work Procedure by " Grouting Pad method" in "Instruction Manual for Erection (10065148-20 14-Feb-14 A 15-Feb-14 A
Preparation of InstallationPreparation of Installation 0 28-Jan-14 A 28-Jan-14 A
CS-10130 Remove the rust-preventive coating of the surface, which is contacted on the concrete grouting and required for insta0 28-Jan-14 A
CS-10140 Pre-assembly and disassembly, if any. Assembly or remove the parts required for installation. When removing the parts0 28-Jan-14 A
CS-10150 Taper liner should be set and adjusted the upper surface level. (4 points or more) 0 28-Jan-14 A 28-Jan-14 A
Installtion and Alignment for Shoe PlateInstalltion and Alignment for Shoe Plate 0 28-Jan-14 A 28-Jan-14 A
CS-10160 Shoe plate temporary placing 0 28-Jan-14 A 28-Jan-14 A
CS-10170 After confirming the accuracy of the liner, install the delivery side shoe plate and check the center match mark is a0 28-Jan-14 A 28-Jan-14 A
Installation and alignment of Shoe PlateInstallation and alignment of Shoe Plate 0 28-Jan-14 A 28-Jan-14 A
CS-10210 Install the foundation bolt cover. Apply sufficient grease to the foundation bolts and fit the foundation bolts then0 28-Jan-14 A 28-Jan-14 A
CS-10180 After verify the accuracy of the delivery side shoe plate, to be confirmed inside the entry side shoe plate using th0 28-Jan-14 A 28-Jan-14 A
CS-10190 Ensure that the upper surface (machined surface) of the shoe plate is covered with plastic sheet to protect from dirt0 28-Jan-14 A
CS-10200 Cut the foundation bolts, if any. 0 28-Jan-14 A 28-Jan-14 A
GroutingGrouting 0 28-Jan-14 A 29-Jan-14 A
CS-10260 Check and ensure that grouting shall be poured successively from one direction so as not to leave air pockets and ens0 28-Jan-14 A
CS-10220 Set wooden frame and check its rigidity can support the grout load, and the depth shall conforms to the specification0 28-Jan-14 A 29-Jan-14 A
CS-10230 Clear the surface area to be grouted from dust/foreign particle and clean with compressed air. Wipe out dry any oil s0 28-Jan-14 A 29-Jan-14 A
CS-10240 Check if surface is properly saturated with water. Remove excess water. 0 28-Jan-14 A 29-Jan-14 A
CS-10250 Check grouting materials and its mixing ratio if according to the specification or otherwise shall conform to JIMS D-0 28-Jan-14 A 29-Jan-14 A
CS-10270 After finishing curing, check hardness. 0 28-Jan-14 A 29-Jan-14 A
ERECTION OF CROP SHEARERECTION OF CROP SHEAR 0 30-Jan-14 A 02-Feb-14 A
PreparationPreparation 0 30-Jan-14 A 30-Jan-14 A
CS-10280 Preparation 0 30-Jan-14 A
CS-10290 Before erecting the Crop Shear Assembly, install its parts to be installed during erection period, listed as follows:0 30-Jan-14 A
CS-10300 HSG surface trimming. Clean and remove the damage portion of HSG machined surfaces that will contact with the shoe pl0 30-Jan-14 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 30 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
CS-10310 Work prior to Crop Shear Assembly erection. A) Complete installation of shoe plates b) Prepare the foot bolts and nut0 30-Jan-14 A
Crop shear Erection and AlignmentCrop shear Erection and Alignment 0 31-Jan-14 A 02-Feb-14 A
CS-10320 When erecting Crop Shear Assembly onto the shoe plates, lower the Assembly into position slowly, and carefully obser0 31-Jan-14 A
Crop ShearAssembly onto the shoe plateCrop ShearAssembly onto the shoe plate 0 02-Feb-14 A 02-Feb-14 A
CS-10330 Lifting Crop Shear Assembly by lifting beam with overhead cranes. b) HSG surface trimming 0 02-Feb-14 A 02-Feb-14 A
CS-10340 Crop shear assembly onto the shoe plates. 0 02-Feb-14 A 02-Feb-14 A
CS-10350 Verify the zero gaps for contact surface of HSG to top of shoe plate. 0 02-Feb-14 A 02-Feb-14 A
CS-10360 Temporary bolting HSG with shoe plate by foot bolts. (Don't use hammer, only soft tighten by hand) 0 02-Feb-14 A 02-Feb-14 A
CS-10370 Adjust the Assembly position from line center same as drawing dimension. 0 02-Feb-14 A 02-Feb-14 A
CS-10380 Positioning Crop Shear Assembly. The Assembly push to the delivery side and verify the zero gaps between HSG and s0 02-Feb-14 A 02-Feb-14 A
MEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACYMEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACY 0 02-Feb-14 A 02-Feb-14 A
CS-10390 Prepare the scaffolding, if any, and piano wire according to the drawing on the right and the measurement procedure.0 02-Feb-14 A 02-Feb-14 A
CS-10400 Final tighten the foot bolts after completion the alignment of Crop Shear Assembly. 0 02-Feb-14 A 02-Feb-14 A
CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS)CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS) 0 20-Mar-14 A 12-Apr-14 A
CS-10410 MOTOR ALLIGNMENT (6 MOTORS) 0 05-Apr-14 A 10-Apr-14 A
CS-10420 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 10-Apr-14 A
PREPARATIONPREPARATION 0 20-Mar-14 A 03-Apr-14 A
CS-10430 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 20-Mar-14 A 21-Mar-14 A
CS-10440 ERECTION OF TABLE BEAM 0 22-Mar-14 A 23-Mar-14 A
CS-10450 INSTALLATION OF MOTOR FRAME 0 24-Mar-14 A 25-Mar-14 A
CS-10460 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 26-Mar-14 A 29-Mar-14 A
CS-10470 INSTALLATION OF MOTOR 0 02-Apr-14 A 02-Apr-14 A
CS-10480 SETTING THE ANCHOR BOLTSAND NUTS 0 02-Apr-14 A 02-Apr-14 A
CS-10490 ANCHOR GROUTING AND CURING. 0 03-Apr-14 A 03-Apr-14 A
ALLIGNMENTALLIGNMENT 0 03-Apr-14 A 04-Apr-14 A
CS-10500 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 03-Apr-14 A 03-Apr-14 A
CS-10510 CHECK THE LEVELNESS 0 04-Apr-14 A 04-Apr-14 A
CS-10520 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 04-Apr-14 A 04-Apr-14 A
REMAINING WORKSREMAINING WORKS 0 10-Apr-14 A 12-Apr-14 A
CS-10530 INSTALLATION OF MOTOR COVER 0 10-Apr-14 A 11-Apr-14 A
CS-10540 INSTALLATION OF SPLASH GUARD 0 11-Apr-14 A 11-Apr-14 A
CS-10550 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 11-Apr-14 A 11-Apr-14 A
CS-10560 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 11-Apr-14 A 12-Apr-14 A
Shop piping including water & UtilitiesShop piping including water & Utilities 94 19-Nov-12 A 30-Oct-14
Mechanical & Piping WorksMechanical & Piping Works 94 19-Nov-12 A 30-Oct-14
UTILITY PIPING Works (Shop Piping)UTILITY PIPING Works (Shop Piping) 94 19-Nov-12 A 30-Oct-14
Water SystemWater System 94 19-Nov-12 A 30-Oct-14
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 31 of 81 Filter: All Activity
Activity ID Activity Name Remaining
Duration
Start Finish
SP-10000 Drawing Inputs 0 19-Nov-12 A 10-May-14 A
SP-10010 Fabrication of Piping spools 12 04-Mar-13 A 17-Jul-14
SP-10030 Run out table Piping 30 03-Feb-14 A 08-Aug-14
SP-10070 Strip Cooling (WDS1) 32 02-Sep-13 A 11-Aug-14
SP-10110 Drainage Pumps. (WA1) 35 03-Feb-14 A 14-Aug-14
SP-10120 Drain for Down Coiler 25 30-Jul-14 01-Sep-14
SP-10080 High Pressure Water. (WH) 54 02-Sep-13 A 09-Sep-14
SP-10060 Direct Cooling Water 55 02-Sep-13 A 11-Sep-14
SP-10090 Indirect Cooling Water (W1) 59 02-Sep-13 A 16-Sep-14
SP-10050 Make up Water 60 02-Sep-13 A 17-Sep-14
SP-10040 Fire Fighting 63 02-Sep-13 A 20-Sep-14
SP-10020 Drinking Water. 94 02-Sep-13 A 30-Oct-14
Finishing Mill & ROT (including Crop shear, SD) + CFL + Transfer carFinishing Mill & ROT (including Crop shear, SD) + CFL + Transfer car 106 27-Dec-11 A 15-Oct-14
F1 to F7 (equipment), B&S coordination & Mechanical ErectionF1 to F7 (equipment), B&S coordination & Mechanical Erection 106 27-Dec-11 A 15-Oct-14
Civil Building & Foundation WorksCivil Building & Foundation Works 0 27-Dec-11 A 16-Dec-13 A
B-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 27-Dec-11 A 20-Aug-13 A
FM-10010 Building Column 0 27-Mar-12 A 31-Oct-12 A
FM-10020 Scale Sluice 0 08-May-12 A 31-Oct-12 A
FM-10000 Drawing Inputs incl. Equipment foundation 0 27-Dec-11 A 25-Jul-13 A
FM-10030 Finishing Mill Equip Foundation Including Scale flume wall 0 16-Jul-12 A 20-Aug-13 A
B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 16-Dec-13 A
FM-10050 Building Column 0 02-Jul-12 A 15-Oct-12 A
FM-10040 Drawing Inputs incl. Equipment foundation 0 03-Apr-12 A 15-Jul-13 A
FM-10060 Run out table Equip foundation 0 31-Aug-12 A 16-Dec-13 A
Structural Building & Technological WorksStructural Building & Technological Works 0 03-Apr-12 A 25-Mar-14 A
B-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 15-Jun-12 A 04-Nov-13 A
FM-10070 Drawing Inputs 0 15-Jun-12 A 03-Sep-12 A
FM-10080 Fabrication 0 17-Sep-12 A 30-Apr-13 A
FM-10090 Erection (including sheeting) 0 16-Oct-12 A 04-Nov-13 A
B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 25-Mar-14 A
FM-LC-10000 Drawing Inputs 0 03-Apr-12 A 31-Oct-12 A
FM-LC10010 Fabrication 0 02-Jul-12 A 30-Apr-13 A
FM-LC-10020 Erection 0 17-Sep-12 A 13-Nov-13 A
FM-LC-10030 Sheeting 0 02-Aug-13 A 25-Mar-14 A
Mechanical & Piping WorksMechanical & Piping Works 56 15-Feb-13 A 26-Aug-14
Mill Preconditions for ErectionMill Preconditions for Erection 0 23-May-13 A 03-Feb-14 A
FM-10170 Availability of Fire extinguisher equipments 0 05-Jul-13 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2014 2015
Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 32 of 81 Filter: All Activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity

More Related Content

Similar to HSM 2nd July Schedule -All activity

Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
MehmanNasibov1
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdfMEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
ssuser7bbf24
 
AMTPJ-Critical Path-Lvl1-Feb 2011
AMTPJ-Critical Path-Lvl1-Feb 2011AMTPJ-Critical Path-Lvl1-Feb 2011
AMTPJ-Critical Path-Lvl1-Feb 2011Robert (Bob) Owens
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Arun Bharadwaj
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
Adi Manurung
 
Act
ActAct
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
WaqarHussain183
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Programacion 4 semanas
Programacion 4 semanasProgramacion 4 semanas
Programacion 4 semanas
Aresi2016
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0Ahmed Mehrem
 
RECOVERY MASTER SCHEDULE - System-1 - R2.pptx
RECOVERY MASTER SCHEDULE - System-1 - R2.pptxRECOVERY MASTER SCHEDULE - System-1 - R2.pptx
RECOVERY MASTER SCHEDULE - System-1 - R2.pptx
ssuser56273f
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1Eko Untung
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
AhmedSaidGhonemy
 

Similar to HSM 2nd July Schedule -All activity (20)

Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdfMEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
MEP Works Planning Baseline Schedule 419482120-MEP-Schedule.pdf
 
AMTPJ-Critical Path-Lvl1-Feb 2011
AMTPJ-Critical Path-Lvl1-Feb 2011AMTPJ-Critical Path-Lvl1-Feb 2011
AMTPJ-Critical Path-Lvl1-Feb 2011
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Act
ActAct
Act
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Programacion 4 semanas
Programacion 4 semanasProgramacion 4 semanas
Programacion 4 semanas
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
RECOVERY MASTER SCHEDULE - System-1 - R2.pptx
RECOVERY MASTER SCHEDULE - System-1 - R2.pptxRECOVERY MASTER SCHEDULE - System-1 - R2.pptx
RECOVERY MASTER SCHEDULE - System-1 - R2.pptx
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1
 
NNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graphNNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graph
 
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
OHL1.pdf ejehejeur iurrrj iiuj4j4i4 jrj4
 

HSM 2nd July Schedule -All activity

  • 1. Activity ID Activity Name Remaining Duration Start Finish Hot Strip MillHot Strip Mill 249 03-Jun-11 A 07-Mar-15 6. HOT STRIP MILL6. HOT STRIP MILL 249 03-Jun-11 A 07-Mar-15 HSM-10000 Issue LOI of Main Mill Package 0 03-Jun-11 A HSM-10010 Start Milestone 0 01-Nov-11 A INPUT MILESTONESINPUT MILESTONES 147 01-Jul-14 A 26-Nov-14 From Utility & Water SystemFrom Utility & Water System 72 01-Jul-14 A 01-Nov-14 A162202 Requirement of Dry Compressed air for HSM 0 01-Jul-14 A A162180 Requirement of Chilled Water to HSM 0 20-Aug-14* A162160 Requirement of LP Nitrogen to HSM from ASU (Alternate to be in position till ASU is in opn.) 0 30-Sep-14* A162172 Requirement of Make-up Water to HSM 0 30-Sep-14* A162190 Requirement of Mixed Gas to HSM 0 20-Oct-14* A162210 Requirement of Propane 0 01-Nov-14* From PDSFrom PDS 0 02-Jul-14 02-Jul-14 A162150 Requirement of Power from MSDS to HSM 0 02-Jul-14* From SMSFrom SMS 0 26-Nov-14 26-Nov-14 A162140 SLAB to HSM 0 26-Nov-14* OUTPUT MILESTONESOUTPUT MILESTONES 73 01-Nov-11 A 27-Nov-14 HSM-10110 Start of HSM 0 01-Nov-11 A HSM-10090 Mill Line readiness 0 17-Oct-14* HSM-10095 Cold test 35 15-Sep-14 30-Oct-14* HSM-10100 Mill Integrated trail 26 31-Oct-14 26-Nov-14* HSM-10080 1st coil from HSM - Target date 0 27-Nov-14* Furnace +Roll shop + ECR1+ Slab Yard + Rolls + SaddlesFurnace +Roll shop + ECR1+ Slab Yard + Rolls + Saddles 208 07-Dec-11 A 25-Jan-15 Furnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop PipingFurnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop Piping 124 10-May-12 A 02-Nov-14 Civil Building & Foundation WorksCivil Building & Foundation Works 91 10-May-12 A 30-Sep-14 Slab Yard-QR /26-14Slab Yard-QR /26-14 0 10-May-12 A 20-Apr-13 A SY-10000 Drawing Inputs (Building Column) 0 10-May-12 A 31-Oct-12 A SY-10010 Building Column 0 09-Aug-12 A 20-Apr-13 A Slab Yard-QR/14-9Slab Yard-QR/14-9 60 10-May-12 A 31-Aug-14 SY-10020 Drawing Inputs (Building Column) 0 10-May-12 A 28-Sep-12 A SY-10030 Building Column 0 18-Feb-13 A 30-Apr-14 A SY-10100 Equipment Foundation 60 31-May-14 A 31-Aug-14 Heavy Spares Storage Area- A/7-13Heavy Spares Storage Area- A/7-13 91 24-Sep-12 A 30-Sep-14 HSS-10000 Drawing Inputs (Building Column) 0 24-Sep-12 A 31-Dec-12 A HSS-10010 Building Column 0 17-Sep-13 A 15-Feb-14 A HSS-10020 Flooring & Misc Works 91 01-May-14 A 30-Sep-14* May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 81 Filter: All Activity
  • 2. Activity ID Activity Name Remaining Duration Start Finish Structural Building & Technological WorksStructural Building & Technological Works 124 13-Oct-12 A 02-Nov-14 SLAB Yard PQR /26-14SLAB Yard PQR /26-14 101 05-Nov-12 A 10-Oct-14 SY-10040 Drawing Inputs 0 05-Nov-12 A 17-Dec-13 A SY-10050 Fabrication 0 11-Jan-13 A 23-May-14 A SY-10120 Structural work complition to give front to EOT Erection 20 09-Mar-13 A 26-Jul-14 SY-10060 Complition of structural work & sheeting 101 09-Mar-13 A 10-Oct-14* Slab Yard-PQR/14-9Slab Yard-PQR/14-9 109 05-Nov-12 A 18-Oct-14 SY-10070 Drawing Inputs 0 05-Nov-12 A 28-Feb-13 A SY-10080 Fabrication 0 15-Mar-13 A 14-Mar-14 A SY-10090 Erection (including sheeting) 109 08-Apr-13 A 18-Oct-14* Heavy Spares Storage Area A/ 7-13Heavy Spares Storage Area A/ 7-13 81 13-Oct-12 A 23-Oct-14 HSS-10030 Drawing Inputs 0 13-Oct-12 A 05-Jul-13 A HSS-10040 Fabrication 0 03-Sep-13 A 28-Mar-14 A HSS-10050 Erection (including sheeting) 81 28-Sep-13 A 23-Oct-14 EOT CRANESEOT CRANES 99 14-Dec-13 A 02-Nov-14 Heavy Spare Storage Area (Axis 13 to 7)EOTHeavy Spare Storage Area (Axis 13 to 7)EOT 33 01-Oct-14 02-Nov-14 Crane (20T Bay A-B)Crane (20T Bay A-B) 33 01-Oct-14 02-Nov-14 HSS-EOT-10000 Bldg readiness for crane erection 0 01-Oct-14 HSS-EOT-10010 EOT Erection 30 01-Oct-14 30-Oct-14 HSS-EOT-10020 Test & Commisioning 3 31-Oct-14 02-Nov-14 16T Crane at C-E Bay16T Crane at C-E Bay 0 14-Dec-13 A 11-Mar-14 A EOT-10030 Strl building readiness for crane erection 0 14-Dec-13 A EOT-10040 EOT Erection &Testing of crane 0 16-Dec-13 A 11-Mar-14 A 2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays 96 27-Jul-14 30-Oct-14 HSS-EOT-10050 Strl building readiness for crane erection 0 27-Jul-14 HSS-EOT-10060 EOT Erection &Testing of crane (Required during operation) 77 15-Aug-14 30-Oct-14* Slab Charging EquipmentSlab Charging Equipment 59 16-Aug-14 30-Oct-14 SY-10110 Erection and alingment of Slab Charging Equipment 59 16-Aug-14* 30-Oct-14 Furnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for FurnaceFurnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for Furnace 61 12-Apr-12 A 31-Aug-14 Civil Building & Foundation WorksCivil Building & Foundation Works 27 12-Apr-12 A 28-Jul-14 B-E/13-10 (Furnace - 1 area)B-E/13-10 (Furnace - 1 area) 0 12-Apr-12 A 10-Dec-13 A FCE-10020 Excavation by Blasting 0 13-Jul-12 A 31-Jan-13 A FCE-10030 Building Column 0 16-Oct-12 A 25-Mar-13 A FCE-10010 Drawing Inputs incl. Equipment foundation 0 12-Apr-12 A 31-May-13 A FCE-10040 Furnace Raft, Wall, Pedestral & Beam 0 30-Oct-12 A 10-Dec-13 A B-E/10-8 (Furnace - 2 area)B-E/10-8 (Furnace - 2 area) 21 09-May-12 A 28-Jul-14 FCE-10060 Excavation by Blasting 0 08-Aug-12 A 29-Nov-12 A FCE-10070 Building Column 0 15-Nov-12 A 25-Mar-13 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 2 of 81 Filter: All Activity
  • 3. Activity ID Activity Name Remaining Duration Start Finish FCE-10050 Drawing Inputs incl. Equipment foundation 0 09-May-12 A 31-May-13 A FCE-10080 Furnace Raft, Wall, Pedestral & Beam 21 08-Aug-12 A 28-Jul-14 Structural Building & Technological WorksStructural Building & Technological Works 61 20-Aug-12 A 31-Aug-14 B-E/14-8 (Furnace - 1 &2 area)B-E/14-8 (Furnace - 1 &2 area) 40 20-Aug-12 A 10-Aug-14 FCE-10090 Drawing Inputs 0 20-Aug-12 A 24-Oct-12 A FCE-10100 Fabrication 0 15-Dec-12 A 09-Jan-14 A FCE-10110 Erection (including sheeting) 40 02-Jan-13 A 10-Aug-14* B-E/8-4 (Furnace - 3&4 area)B-E/8-4 (Furnace - 3&4 area) 61 27-Sep-12 A 31-Aug-14 FCE-10120 Drawing Inputs 0 27-Sep-12 A 31-Oct-12 A FCE-10160 Structural erection to give front for EOT erection 0 05-Apr-13 A 12-Dec-13 A FCE-10130 Fabrication 0 01-Jan-13 A 03-Mar-14 A FCE-10140 Erection (including sheeting) 61 05-Apr-13 A 31-Aug-14* Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping)Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping) 208 20-Jan-14 A 25-Jan-15 Mechanical & RefractoryMechanical & Refractory 208 20-Jan-14 A 25-Jan-15 Furnace -1--Eqpt Erection by TenovaFurnace -1--Eqpt Erection by Tenova 145 20-Jan-14 A 24-Nov-14 FCE-10650 Clearence after Fdn & Building constn for Eqpt erection 0 20-Jan-14 A Furnace Equipment ErectionFurnace Equipment Erection 118 12-Mar-14 A 28-Oct-14 Furnace Box and mechanismFurnace Box and mechanism 89 12-Mar-14 A 29-Sep-14 FCE1-10670 Inclined ramps 0 12-Mar-14 A 25-Mar-14 A FCE1-10680 Lifting and travelling cylinders supports 0 15-Apr-14 A 20-Apr-14 A FCE1-10690 Lifting frame cylinders and centering device 14 20-May-14 A 16-Jul-14 FCE1-10700 Travelling frame and cylinder 15 12-May-14 A 17-Jul-14 FCE1-10730 Side platforms and walkways level - 2250 mm 17 08-Jul-14* 25-Jul-14 FCE1-10720 Erection of Water seals 25 02-Jul-14 27-Jul-14 FCE1-10750 Erection of Fixed skid upright 7 20-Jul-14* 27-Jul-14 FCE1-10710 Erection of Moving skids uprights 29 02-Jul-14* 31-Jul-14 FCE1-10760 Lay down horizontal skids on the fixed hearth 5 27-Jul-14 01-Aug-14 FCE1-10770 Side and front, walls 10 28-Jul-14 07-Aug-14 FCE1-10740 Hearth frames and scale hoppers 14 25-Jul-14 08-Aug-14 FCE1-10800 Roof IPE 100 8 07-Aug-14* 15-Aug-14 FCE1-10790 Roof main beams 10 07-Aug-14* 17-Aug-14 FCE1-10810 Horizontal skids (Charge section) alignment & levelling 15 20-Aug-14 04-Sep-14 FCE1-10640 Side platforms and walkways Level +500 mm 25 15-Aug-14 09-Sep-14 FCE1-10820 Horizontal skids (Middle section) alignment & levelling 12 31-Aug-14 12-Sep-14 FCE1-10620 Horizontal skids (Discharge section) alignment & levelling 12 01-Sep-14 13-Sep-14 FCE1-10630 Final setting of water seals and paddles 15 03-Sep-14 18-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 3 of 81 Filter: All Activity
  • 4. Activity ID Activity Name Remaining Duration Start Finish FCE1-10780 Side doors 46 07-Aug-14 22-Sep-14 FCE1-10650 Roof stairs and walkways 20 09-Sep-14 29-Sep-14 FCE1-10660 Completion of Furnace box and Mechanism 0 29-Sep-14* Waste Gas Duct & StacksWaste Gas Duct & Stacks 46 10-Aug-14 25-Sep-14 WG-10150 Downtake 3 10-Aug-14* 13-Aug-14 WG-10160 Waste gas ducts upsteam recuperator 25 13-Aug-14 07-Sep-14 WG-10170 Recuperator casing 9 01-Sep-14 10-Sep-14 WG-10180 Waste gas ducts downsteam recuperator & pressure valve 15 01-Sep-14 16-Sep-14 WG-10190 Stack (lot no-1,2,3) 8 17-Sep-14 25-Sep-14 Handling EquipmentHandling Equipment 68 13-Jun-14 A 08-Sep-14 HE-10060 Discharge machine 11 13-Jun-14 A 13-Jul-14 HE-10070 Charging machine 30 15-Jul-14* 14-Aug-14 HE-10080 Charging and discharging doors mechanism and doors 5 03-Sep-14 08-Sep-14 Refractory & InsulationRefractory & Insulation 112 05-Jul-14 25-Oct-14 REF-10310 Side doors lining 6 25-Aug-14* 31-Aug-14 REF-10320 Charging and discharging doors lining 6 25-Aug-14* 31-Aug-14 REF-10360 Recu casing - lining 20 25-Aug-14* 14-Sep-14 REF-10340 Skids-lining 30 25-Aug-14* 24-Sep-14 REF-10390 Piping insulation 40 25-Aug-14* 04-Oct-14 REF-10350 Down take and waste gas duct upstream recu lining 30 16-Sep-14 16-Oct-14 REF-10370 Waste gas duct downstream recu lining 30 24-Sep-14 24-Oct-14 REF-10330 Furnace box - lining 60 25-Aug-14* 24-Oct-14 REF-10380 Stack refractory ining 30 25-Sep-14 25-Oct-14 REF-10400 Complete insulation & lining 0 25-Oct-14 Equipment & PipingEquipment & Piping 100 05-Jul-14 13-Oct-14 EQP-10570 Combustion air fans (3 nos with scilencer & connecting pipe) 8 05-Jul-14* 13-Jul-14 EQP-10500 Hydraulic station and valve stand 10 15-Jul-14* 25-Jul-14 EQP-10490 Water sealing piping 15 27-Jul-14 11-Aug-14 EQP-10530 Lubricating piping system 20 25-Jul-14 14-Aug-14 EQP-10560 Burners (lateral & roof) 15 05-Aug-14* 20-Aug-14 EQP-10580 Combustion air piping & support 40 13-Jul-14 22-Aug-14 EQP-10510 Hydraulic Piping 30 25-Jul-14 24-Aug-14 EQP-10620 Compressed air system 30 02-Aug-14* 01-Sep-14 EQP-10520 Hydraulic piping flushing 15 24-Aug-14 08-Sep-14 EQP-10480 Skids cooling water piping and supports 45 02-Aug-14 16-Sep-14* EQP-10550 Recuperators 10 14-Sep-14 24-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 4 of 81 Filter: All Activity
  • 5. Activity ID Activity Name Remaining Duration Start Finish EQP-10590 Mixed gas piping and support 45 13-Aug-14 27-Sep-14 EQP-10600 Nitrogen piping and supports 20 19-Sep-14 09-Oct-14 EQP-10610 Pilot and frame control system 15 27-Sep-14 12-Oct-14* EQP-10540 Pressure test 30 13-Sep-14 13-Oct-14 Electrical SystemsElectrical Systems 93 27-Jul-14 28-Oct-14 EE-10410 MCC boards and local panels 15 16-Aug-14* 31-Aug-14 EE-10420 Erection of cable trays 30 01-Aug-14 31-Aug-14 EE-10430 Field instruments 45 27-Jul-14 10-Sep-14 EE-10440 Cable laying 45 06-Aug-14 20-Sep-14 EE-10450 Cable termination 30 26-Aug-14 25-Sep-14 EE-10460 CCTV system 15 13-Oct-14 28-Oct-14 EE-10470 Complete installation of electrical & instrumentation 0 28-Oct-14 Testing & CommissioningTesting & Commissioning 30 25-Oct-14 24-Nov-14 TEST-12430 Cold test & commissioning 17 25-Oct-14 11-Nov-14 TEST-12440 Heating and dry up 12 11-Nov-14 23-Nov-14 TEST-12450 1st Hot slab 0 24-Nov-14* Furnace-2--Eqpt Erection by TenovaFurnace-2--Eqpt Erection by Tenova 205 05-Jul-14 25-Jan-15 FCE-10000 Clearence after Fdn & Building constn for Eqpt erection 0 29-Jul-14 Equipment Receipt at site (Furnace 2)Equipment Receipt at site (Furnace 2) 60 05-Jul-14 02-Sep-14 FCE-10250 Receipt at site (Furnace 2) 60 05-Jul-14* 02-Sep-14 Furnace Box and MechanismFurnace Box and Mechanism 119 30-Jul-14 25-Nov-14 FCE-10260 Equipment Erection 119 30-Jul-14 25-Nov-14 Waste gas ducts & StackWaste gas ducts & Stack 63 23-Aug-14 24-Oct-14 FCE-10270 Equipment Erection 63 23-Aug-14 24-Oct-14 Refractory and InsulationRefractory and Insulation 67 18-Oct-14 23-Dec-14 FCE-10280 Refractory work 67 18-Oct-14 23-Dec-14 Furnace Electrical systemFurnace Electrical system 70 21-Sep-14 29-Nov-14 FCE-10290 Equipment Erection 70 21-Sep-14 29-Nov-14 Test & CommissioningTest & Commissioning 56 01-Dec-14 25-Jan-15 FCE-10300 Individual trial 30 01-Dec-14 30-Dec-14 FCE-10310 Integrated trial 19 31-Dec-14 18-Jan-15 FCE-10320 Furnace Dry out 7 19-Jan-15 25-Jan-15 FCE-10330 Furnace-2 Ready 0 25-Jan-15* Piping WorksPiping Works 100 23-Aug-14 30-Nov-14 Furnace-2Furnace-2 100 23-Aug-14 30-Nov-14 FCE-10350 Piping Erection 100 23-Aug-14 30-Nov-14 ECR-1 & FCE area Auxiliary Electrical System incl tunnelsECR-1 & FCE area Auxiliary Electrical System incl tunnels 80 07-Dec-11 A 20-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 5 of 81 Filter: All Activity
  • 6. Activity ID Activity Name Remaining Duration Start Finish Civil Building & Foundation WorksCivil Building & Foundation Works 0 07-Dec-11 A 31-Mar-14 A ECR1-10000 Civil clearance ground floor 0 17-Nov-13 A ECR1-10010 Base ment availability 0 14-Dec-13 A ECR-1ECR-1 0 07-Dec-11 A 31-Mar-14 A ECR1-10030 Base Raft 0 07-Mar-12 A 23-May-12 A ECR1-10040 Basement Wall & Column 0 23-May-12 A 07-Oct-12 A ECR1-10050 Ground Floor Slab 0 08-Aug-12 A 25-Oct-12 A ECR1-10020 Drawing Inputs 0 07-Dec-11 A 28-Nov-12 A ECR1-10060 Columns 0 20-Dec-12 A 31-Jan-13 A ECR1-10070 Roof Slab 0 11-Feb-13 A 31-May-13 A ECR1-10080 Other Finishing Work 0 13-Feb-13 A 16-Mar-14 A ECR1-10130 Tranformer Foundation 0 22-Feb-14 A 31-Mar-14 A Structural Building & Technological WorksStructural Building & Technological Works 0 02-Mar-14 A 19-Apr-14 A Crane LCSS-1Crane LCSS-1 0 02-Mar-14 A 19-Apr-14 A LCSS1-10000 LCSS panels(3) 0 02-Mar-14 A 11-Mar-14 A LCSS1-10010 Transformer(3sets) 0 11-Apr-14 A 19-Apr-14 A Cable Tunnel ECR1 to ECR2Cable Tunnel ECR1 to ECR2 0 15-Apr-13 A 25-May-14 A ECR1-10090 Drawing availabilty 0 15-Apr-13 A 08-Jul-13 A ECR1-10100 Civil Works 0 02-Dec-13 A 25-May-14 A Electrical & Automation WorksElectrical & Automation Works 80 24-Feb-14 A 20-Sep-14 RTDBsRTDBs 0 02-May-14 A 19-May-14 A RTDB-10000 Slab RTDB 1 0 02-May-14 A 02-May-14 A RTDB-10010 Slab RTDB 2 0 02-May-14 A 03-May-14 A RTDB-10020 Slab RTDB 3 0 03-May-14 A 05-May-14 A RTDB-10030 Slab RTDB 4 0 05-May-14 A 05-May-14 A RTDB-10040 Slab RTDB 5 0 05-May-14 A 06-May-14 A RTDB-10050 Slab RTDB 6 0 06-May-14 A 07-May-14 A RTDB-10060 Slab RTDB 7 0 07-May-14 A 07-May-14 A RTDB-10070 Fce RTDB 1 0 08-May-14 A 08-May-14 A RTDB-10080 Fce RTDB 2 0 08-May-14 A 09-May-14 A RTDB-10090 Fce RTDB 3 0 09-May-14 A 10-May-14 A RTDB-10100 Fce RTDB 4 0 10-May-14 A 10-May-14 A RTDB-10110 Fce RTDB 5 0 10-May-14 A 12-May-14 A RTDB-10120 Fce RTDB 6 0 12-May-14 A 13-May-14 A RTDB-10130 Fce RTDB 7 0 13-May-14 A 14-May-14 A RTDB-10140 Fce RTDB 8 0 14-May-14 A 14-May-14 A RTDB-10150 RTDB1 0 14-May-14 A 15-May-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 6 of 81 Filter: All Activity
  • 7. Activity ID Activity Name Remaining Duration Start Finish RTDB-10160 RTDB2 0 15-May-14 A 16-May-14 A RTDB-10170 RTDB3 0 16-May-14 A 16-May-14 A RTDB-10180 RTDB4 0 17-May-14 A 17-May-14 A RTDB-10190 RTDB24 0 17-May-14 A 19-May-14 A Other WorksOther Works 80 24-Feb-14 A 20-Sep-14 EE-10010 LCSS 0 19-May-14 A 20-May-14 A EE-10020 PDB2 0 20-May-14 A 20-May-14 A EE-10030 MLDB 0 20-May-14 A 21-May-14 A EE-10040 ELDB 0 21-May-14 A 22-May-14 A EE-10050 Converter transformer room 0 22-May-14 A 23-May-14 A EE-10060 Converter 0 23-May-14 A 23-May-14 A EE-10070 Inverter 0 23-May-14 A 24-May-14 A EE-10080 UPS 0 24-May-14 A 26-May-14 A EE-10090 Battery 0 26-May-14 A 26-May-14 A EE-10100 Slab transfer car drive 0 27-May-14 A 27-May-14 A EE-10110 Ventilation MCC 0 27-May-14 A 28-May-14 A EE-10120 SYMS room 0 28-May-14 A 29-May-14 A EE-10130 AHU room 0 29-May-14 A 29-May-14 A EE-10140 Earthing pits(14) 0 29-May-14 A 30-May-14 A EE-10150 RIO 0 30-May-14 A 31-May-14 A EE-10160 Amenities 0 31-May-14 A 02-Jun-14 A EE-10000 tray support fabrication & erection 0 24-Feb-14 A 30-Jun-14 A EE-10170 cable tray erection 36 30-Jun-14 A 07-Aug-14 EE-10180 cable laying & termination 30 28-Jul-14 27-Aug-14 EE-10190 Trial & Testing 10 08-Sep-14 20-Sep-14 Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping)Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping) 141 16-Jun-12 A 19-Nov-14 Civil Building & Foundation WorksCivil Building & Foundation Works 29 24-Sep-12 A 30-Jul-14 Roll Shop-A/45-14Roll Shop-A/45-14 29 24-Sep-12 A 30-Jul-14 RS-10000 Drawing Inputs 0 24-Sep-12 A 17-Jul-13 A RS-10010 Building Columns 0 12-Apr-13 A 04-Apr-14 A RS-10020 Equipment Foundations 14a-24 18 10-Apr-14 A 19-Jul-14 RS-10040 Equipment Foundations 32-45 29 30-Apr-14 A 30-Jul-14 RS-10030 Equipment Foundations 24-32 29 10-May-14 A 30-Jul-14* Structural Building & Technological WorksStructural Building & Technological Works 120 16-Jun-12 A 30-Oct-14 Roll Shop-A/45-14Roll Shop-A/45-14 84 16-Jun-12 A 23-Sep-14 RS-10050 Drawing Inputs 0 16-Jun-12 A 11-Oct-12 A RS-10060 Erection32-45 to give front for EOT erection 0 07-Jan-14 A 27-Feb-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 7 of 81 Filter: All Activity
  • 8. Activity ID Activity Name Remaining Duration Start Finish RS-10080 Fabrication 0 01-Jul-13 A 20-May-14 A RS-10070 Erection 14a-24 (including sheeting) 30 20-Sep-13 A 31-Jul-14* RS-10090 Erection 24-31 (including sheeting) 65 13-Jul-13 A 23-Sep-14 RS-10065 Complition Erection32-45 (including sheeting) 65 07-Jan-14 A 23-Sep-14* EOT CraneEOT Crane 120 11-Mar-14 A 30-Oct-14 120 T EOT Crane (Roll Shop)120 T EOT Crane (Roll Shop) 15 11-Mar-14 A 16-Jul-14 RS-EOT-10000 Erection of crane 0 11-Mar-14 A RS-EOT-10010 Test & Commisioning 15 04-Apr-14 A 16-Jul-14 37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop)37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop) 68 02-Aug-14 30-Oct-14 RS-EOT-10020 EOT Erection 38 02-Aug-14* 20-Sep-14 RS-EOT-10030 Test & Commisioning 30 20-Sep-14 30-Oct-14* ROLL SHOPROLL SHOP 30 04-Jul-13 A 08-Aug-14 RS-10100 Delivery of Equipment at Site of-Roll Shop 30 04-Jul-13 A 08-Aug-14 Mechanical & Piping WorksMechanical & Piping Works 96 15-Aug-14 19-Nov-14 Equipment ErectionEquipment Erection 96 15-Aug-14 19-Nov-14 RS-10110 Front readiness by Civil/ Strl & Crane for mechanical erection 0 15-Aug-14 RS-10130 Erection of priority Roll Grinders 46 16-Aug-14 30-Sep-14* RS-10120 Erection of Roll Shop equipment (other than priority grinders) 60 01-Sep-14 30-Oct-14 RS-10150 Roll grinding 0 19-Nov-14 Roll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shopRoll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shop 115 05-Sep-14 29-Dec-14 Roll Shop - Test & TrialsRoll Shop - Test & Trials 60 31-Oct-14 29-Dec-14 RS-10140 Test & Commissioning of priority Roll Grinders 20 31-Oct-14 19-Nov-14 RS-10160 Test & Commissioning Roll Shop Eqpt (other than priority grinders) 60 31-Oct-14 29-Dec-14 Roll Shop-Pulpit Area:Roll Shop-Pulpit Area: 42 05-Sep-14 30-Oct-14 RS-10170 clearance 0 05-Sep-14 05-Sep-14 RS-10200 Equipment availablity & Drawing 1 06-Sep-14 08-Sep-14 RS-10180 Fabrication & erection of cable tray & supports 15 05-Sep-14 25-Sep-14 RS-10190 Installation of I/O Panels and HMI, Network cabinet, etc. 15 06-Sep-14 25-Sep-14 RS-10210 Cable Laying up to field equipment 15 25-Sep-14 15-Oct-14 RS-10220 Panel Earthing 27 20-Sep-14 27-Oct-14 RS-10230 Cable Glanding & Termination 10 17-Oct-14 30-Oct-14 Edger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + LabEdger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + Lab 121 01-Nov-11 A 30-Oct-14 FCE Charging & Discharge Table, Primary Descalar, R1 (incl R1 Ent Table to R1 Del Table)FCE Charging & Discharge Table, Primary Descalar, R1 (incl R1 Ent Table to R1 Del Table) 108 31-Mar-12 A 17-Oct-14 Civil Building & Foundation WorksCivil Building & Foundation Works 47 31-Mar-12 A 30-Aug-14 Charging Aisle &Stack-E-F/ 1-14Charging Aisle &Stack-E-F/ 1-14 47 31-Mar-12 A 30-Aug-14 FCE-10360 Drawing Inputs incl. Equipment foundation 0 31-Mar-12 A 29-Sep-12 A FCE-10370 Building Column - Furnace Bay (B-C-E-F/2-13) 0 02-Jul-12 A 26-Feb-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 8 of 81 Filter: All Activity
  • 9. Activity ID Activity Name Remaining Duration Start Finish FCE-10390 Stack Foundation 0 05-Mar-14 A 15-Apr-14 A FCE-10380 Charging Roller Table Equip Foundation 13-10 0 28-Mar-13 A 17-Apr-14 A FCE-10400 Charging Roller Table Equip Foundation 10-4 47 15-Jul-13 A 30-Aug-14 Structural Building & Technological WorksStructural Building & Technological Works 42 11-Sep-12 A 12-Aug-14 Charging Aisle &Stack-E-F/ 1-13Charging Aisle &Stack-E-F/ 1-13 33 11-Sep-12 A 12-Aug-14 FCE-10410 Drawing Inputs 0 11-Sep-12 A 17-Dec-12 A FCE-10420 Fabrication 0 15-Dec-12 A 01-Mar-14 A FCE-10440 Erection 8-1 to give front to EOT erection 0 10-Sep-13 A 31-Mar-14 A FCE-10430 Erection 13-8 (including sheeting) 7 15-Jul-13 A 10-Jul-14 FCE-10445 Erection 8-1 (including sheeting) 33 15-Jul-13 A 12-Aug-14 40 (on tong)/16T Crane at E-F Bay40 (on tong)/16T Crane at E-F Bay 20 31-Mar-14 A 21-Jul-14 FCE-EOT-10000 Strl building readiness for crane erection 0 31-Mar-14 A FCE-EOT-10010 EOT Erection &Testing of crane 20 10-Apr-14 A 21-Jul-14 Receipt of Equipment at siteReceipt of Equipment at site 0 05-Jul-13 A 26-May-14 A RM-10000 Receipt at site (Sojitz scope) 0 05-Jul-13 A 10-Mar-14 A FCE-10450 Receipt at site (TGS scope) 0 19-Jul-13 A 23-Apr-14 A RM-10010 Receipt at site (TGS scope) 0 15-Jul-13 A 26-May-14 A Mechanical & Piping WorksMechanical & Piping Works 108 15-Feb-14 A 17-Oct-14 MILL MAIN EQUIPMENT ERECTIONMILL MAIN EQUIPMENT ERECTION 108 15-Feb-14 A 17-Oct-14 FRONT#1 (FURNACE ENTRY SIDE)FRONT#1 (FURNACE ENTRY SIDE) 88 27-Apr-14 A 17-Oct-14 FCE-10460 SLAB WEIGHER 8 22-Jul-14 29-Jul-14 FURNACE ENTRYTABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS)FURNACE ENTRYTABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS) 88 27-Apr-14 A 17-Oct-14 FCE-10470 MOTOR ALLIGNMENT (169 MOTORS) 19 02-Sep-14 20-Sep-14 FCE-10480 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 11 15-Sep-14 25-Sep-14 PREPARATIONPREPARATION 6 27-Apr-14 A 27-Jul-14 RM-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 27-Apr-14 A 01-May-14 A RM-10030 ERECTION OF TABLE BEAM 1 22-Jul-14 22-Jul-14 RM-10040 INSTALLATION OF MOTOR FRAME 1 23-Jul-14 23-Jul-14 RM-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE1 24-Jul-14 24-Jul-14 RM-10060 INSTALLATION OF MOTOR 1 25-Jul-14 25-Jul-14 RM-10070 SETTING THE ANCHOR BOLTSAND NUTS 1 26-Jul-14 26-Jul-14 RM-10080 ANCHOR GROUTING AND CURING. 1 27-Jul-14 27-Jul-14 ALLIGNMENTALLIGNMENT 6 28-Jul-14 02-Aug-14 RM-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 2 28-Jul-14 29-Jul-14 RM-10100 CHECK THE LEVELNESS 2 30-Jul-14 31-Jul-14 RM-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 2 01-Aug-14 02-Aug-14 e.REMAINING WORKSe.REMAINING WORKS 22 25-Sep-14 17-Oct-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 9 of 81 Filter: All Activity
  • 10. Activity ID Activity Name Remaining Duration Start Finish RM-10120 INSTALLATION OF MOTOR COVER 1 25-Sep-14 26-Sep-14 RM-10130 INSTALLATION OF SPLASH GUARD 1 26-Sep-14 27-Sep-14 RM-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 27-Sep-14 28-Sep-14 RM-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 20 27-Sep-14 17-Oct-14 FRONT#2 (FURNACE DELIVERY SIDE)FRONT#2 (FURNACE DELIVERY SIDE) 83 05-May-14 A 28-Sep-14 FURNACE DELIVERYTABLE (34 TABLES, 86 ROLLS)FURNACE DELIVERYTABLE (34 TABLES, 86 ROLLS) 55 05-May-14 A 02-Sep-14 FCE-10490 MOTOR ALLIGNMENT (86 MOTORS) 1 10-Jul-14* 10-Jul-14 FCE-10500 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 1 11-Jul-14 11-Jul-14 a. PREPARATIONa. PREPARATION 0 05-May-14 A 10-Jun-14 A FCE-10510 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 05-May-14 A 05-May-14 A FCE-10520 ERECTION OF TABLE BEAM 0 06-May-14 A 06-May-14 A FCE-10530 INSTALLATION OF MOTOR FRAME 0 06-Jun-14 A 06-Jun-14 A FCE-10540 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 07-Jun-14 A 07-Jun-14 A FCE-10550 INSTALLATION OF MOTOR 0 08-Jun-14 A 08-Jun-14 A FCE-10560 SETTING THE ANCHOR BOLTSAND NUTS 0 09-Jun-14 A 09-Jun-14 A FCE-10570 ANCHOR GROUTING AND CURING. 0 10-Jun-14 A 10-Jun-14 A b.ALLIGNMENTb.ALLIGNMENT 0 11-Jun-14 A 13-Jun-14 A FCE-10580 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 11-Jun-14 A 11-Jun-14 A FCE-10590 CHECK THE LEVELNESS 0 12-Jun-14 A 12-Jun-14 A FCE-10600 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 13-Jun-14 A 13-Jun-14 A e.REMAINING WORKSe.REMAINING WORKS 53 12-Jul-14 02-Sep-14 FCE-10610 INSTALLATION OF MOTOR COVER 5 12-Jul-14 16-Jul-14 FCE-10620 INSTALLATION OF SPLASH GUARD 15 17-Jul-14 31-Jul-14 FCE-10630 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 3 01-Aug-14 03-Aug-14 FCE-10640 ATTACHED PIPING AND OTHER REMAINING WORKS. 30 04-Aug-14 02-Sep-14 HSB ROLLER TABLE (3 TABLES, 18 ROLLS)HSB ROLLER TABLE (3 TABLES, 18 ROLLS) 62 29-Jul-14 28-Sep-14 HSB-10000 MOTOR ALLIGNMENT (18 MOTORS) 10 07-Sep-14 16-Sep-14 HSB-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 10 12-Sep-14 21-Sep-14 a. PREPARATIONa. PREPARATION 25 29-Jul-14 22-Aug-14 HSB-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 1 29-Jul-14 29-Jul-14 HSB-10030 ERECTION OF TABLE BEAM 2 30-Jul-14 31-Jul-14 HSB-10040 INSTALLATION OF MOTOR FRAME 5 01-Aug-14 05-Aug-14 HSB-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE5 06-Aug-14 10-Aug-14 HSB-10060 INSTALLATION OF MOTOR 5 11-Aug-14 15-Aug-14 HSB-10070 SETTING THE ANCHOR BOLTSAND NUTS 4 16-Aug-14 19-Aug-14 HSB-10080 ANCHOR GROUTING AND CURING. 3 20-Aug-14 22-Aug-14 b.ALLIGNMENTb.ALLIGNMENT 15 23-Aug-14 06-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 10 of 81 Filter: All Activity
  • 11. Activity ID Activity Name Remaining Duration Start Finish HSB-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 5 23-Aug-14 27-Aug-14 HSB-10100 CHECK THE LEVELNESS 5 28-Aug-14 01-Sep-14 HSB-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 5 02-Sep-14 06-Sep-14 e.REMAINING WORKSe.REMAINING WORKS 7 22-Sep-14 28-Sep-14 HSB-10120 INSTALLATION OF MOTOR COVER 1 22-Sep-14 22-Sep-14 HSB-10130 INSTALLATION OF SPLASH GUARD 1 23-Sep-14 23-Sep-14 HSB-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 24-Sep-14 24-Sep-14 HSB-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 4 25-Sep-14 28-Sep-14 HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 11 25-Jul-14 04-Aug-14 HSB-10160 INSTALLATION OF DESCALING BOX 2 26-Jul-14* 27-Jul-14 HSB-10170 INSTALLATION OF SPLASH GUARD 1 28-Jul-14 28-Jul-14 HSB-10180 ATTACHED PIPING 5 29-Jul-14 02-Aug-14 HSB-10190 INSTALLTION OF PX SENSOR 1 03-Aug-14 03-Aug-14 a. PREPARATIONa. PREPARATION 0 25-Jul-14 25-Jul-14 HSB-10200 PREPARATION 0 25-Jul-14 HSB-10210 CONFIRM THE COMPLETION OF ALIGNMENT OF HSB TABLE 0 25-Jul-14* HSB-10220 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 0 25-Jul-14 b. INSTALLATION OF BOTTOM HEADERb. INSTALLATION OF BOTTOM HEADER 1 25-Jul-14 25-Jul-14 HSB-10230 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)1 25-Jul-14 25-Jul-14 g. INSTALLTION OF DESCALING NOZZLEg. INSTALLTION OF DESCALING NOZZLE 1 04-Aug-14 04-Aug-14 HSB-10240 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 1 04-Aug-14 04-Aug-14 ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS)ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS) 63 02-Jun-14 A 08-Sep-14 RM2-10000 MOTOR ALLIGNMENT (62 MOTORS) 20 08-Jul-14* 27-Jul-14 RM2-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 35 28-Jul-14 31-Aug-14 a. PREPARATIONa. PREPARATION 0 02-Jun-14 A 14-Jun-14 A RM2-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 02-Jun-14 A 03-Jun-14 A RM2-10030 ERECTION OF TABLE BEAM 0 03-Jun-14 A 04-Jun-14 A RM2-10040 INSTALLATION OF MOTOR FRAME 0 05-Jun-14 A 06-Jun-14 A RM2-10050 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 07-Jun-14 A 08-Jun-14 A RM2-10060 INSTALLATION OF MOTOR 0 09-Jun-14 A 10-Jun-14 A RM2-10070 SETTING THE ANCHOR BOLTSAND NUTS 0 11-Jun-14 A 12-Jun-14 A RM2-10080 ANCHOR GROUTING AND CURING. 0 13-Jun-14 A 14-Jun-14 A b.ALLIGNMENTb.ALLIGNMENT 0 15-Jun-14 A 19-Jun-14 A RM2-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 15-Jun-14 A 15-Jun-14 A RM2-10100 CHECK THE LEVELNESS 0 16-Jun-14 A 17-Jun-14 A RM2-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 18-Jun-14 A 19-Jun-14 A e.REMAINING WORKSe.REMAINING WORKS 8 01-Sep-14 08-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 11 of 81 Filter: All Activity
  • 12. Activity ID Activity Name Remaining Duration Start Finish RM2-10120 INSTALLATION OF MOTOR COVER 2 01-Sep-14 02-Sep-14 RM2-10130 INSTALLATION OF SPLASH GUARD 2 03-Sep-14 04-Sep-14 RM2-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 2 05-Sep-14 06-Sep-14 RM2-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 2 07-Sep-14 08-Sep-14 FRONT#3 (DELAY TABLE)FRONT#3 (DELAY TABLE) 91 15-Feb-14 A 30-Sep-14 DT-10000 COBBLE PUSHER 91 31-Mar-14 A 30-Sep-14 DELAY TABLE (9 TABLE, 58 ROLLS)DELAY TABLE (9 TABLE, 58 ROLLS) 0 15-Feb-14 A 03-May-14 A DT-10010 MOTOR ALLIGNMENT (58 MOTORS) 0 27-Mar-14 A 10-Apr-14 A DT-10020 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 13-Apr-14 A a. PREPARATIONa. PREPARATION 0 15-Feb-14 A 18-Mar-14 A DT-10030 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 15-Feb-14 A 16-Feb-14 A DT-10040 ERECTION OF TABLE BEAM 0 18-Feb-14 A 19-Feb-14 A DT-10050 INSTALLATION OF MOTOR FRAME 0 07-Mar-14 A 08-Mar-14 A DT-10060 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 09-Mar-14 A 10-Mar-14 A DT-10070 INSTALLATION OF MOTOR 0 11-Mar-14 A 13-Mar-14 A DT-10080 SETTING THE ANCHOR BOLTSAND NUTS 0 14-Mar-14 A 15-Mar-14 A DT-10090 ANCHOR GROUTING AND CURING. 0 16-Mar-14 A 18-Mar-14 A b.ALLIGNMENTb.ALLIGNMENT 0 20-Mar-14 A 24-Mar-14 A DT-10100 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 20-Mar-14 A 20-Mar-14 A DT-10110 CHECK THE LEVELNESS 0 21-Mar-14 A 22-Mar-14 A DT-10120 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 23-Mar-14 A 24-Mar-14 A e.REMAINING WORKSe.REMAINING WORKS 0 13-Apr-14 A 03-May-14 A DT-10130 INSTALLATION OF MOTOR COVER 0 13-Apr-14 A 14-Apr-14 A DT-10140 INSTALLATION OF SPLASH GUARD 0 15-Apr-14 A 16-Apr-14 A DT-10150 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 17-Apr-14 A 18-Apr-14 A DT-10160 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 19-Apr-14 A 03-May-14 A MILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTIONMILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTION 90 15-Apr-14 A 29-Sep-14 ERECTION OF G2ERECTION OF G2 53 01-Aug-14 22-Sep-14 MILL-AUX-10000 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14* 01-Aug-14 MILL-AUX-10010 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14 MILL-AUX-10020 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14 ERECTION OF G3ERECTION OF G3 53 01-Aug-14 22-Sep-14 MILL-AUX-10030 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14 MILL-AUX-10040 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14 MILL-AUX-10050 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14 ERECTION OF G4ERECTION OF G4 51 01-Aug-14 20-Sep-14 MILL-AUX-10060 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 12 of 81 Filter: All Activity
  • 13. Activity ID Activity Name Remaining Duration Start Finish MILL-AUX-10080 FLUSHING OF GREASE PIPES 4 02-Aug-14 05-Aug-14 MILL-AUX-10070 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14 ERECTION OF G5ERECTION OF G5 55 01-Aug-14 24-Sep-14 MILL-AUX-10100 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10090 ERECTION OF GREASE PIPING 50 01-Aug-14 19-Sep-14 MILL-AUX-10110 FLUSHING OF GREASE PIPES 5 20-Sep-14 24-Sep-14 ERECTION OF G6ERECTION OF G6 60 01-Aug-14 29-Sep-14 MILL-AUX-10120 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10130 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14 MILL-AUX-10140 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14 ERECTION OF G7ERECTION OF G7 60 01-Aug-14 29-Sep-14 MILL-AUX-10150 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10160 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14 MILL-AUX-10170 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14 ERECTION OF G8ERECTION OF G8 60 01-Aug-14 29-Sep-14 MILL-AUX-10180 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10190 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14 MILL-AUX-10200 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14 ERECTION OF G9ERECTION OF G9 60 01-Aug-14 29-Sep-14 MILL-AUX-10210 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10220 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14 MILL-AUX-10230 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14 ERECTION OF G10ERECTION OF G10 60 01-Aug-14 29-Sep-14 MILL-AUX-10240 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14 MILL-AUX-10250 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14 MILL-AUX-10260 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14 ERECTION OF RL1 (R1 GEAR LUB) SYSTEMERECTION OF RL1 (R1 GEAR LUB) SYSTEM 55 02-Jul-14 25-Aug-14 MILL-AUX-10350 Electrical Work (Sensor Erection & Termination) 30 02-Jul-14 31-Jul-14 MILL-AUX-10270 Lowering of the tank and placing at the pedestal 1 01-Aug-14* 01-Aug-14 MILL-AUX-10280 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14 MILL-AUX-10290 Alignment of tank unit 2 03-Aug-14 04-Aug-14 MILL-AUX-10300 Alignment of pump unit 2 05-Aug-14 06-Aug-14 MILL-AUX-10310 Installation of centrifuge 1 07-Aug-14 07-Aug-14 MILL-AUX-10320 Installation of Strainer and heat exchanger 10 08-Aug-14 17-Aug-14 MILL-AUX-10330 Installation of instruments at pump and tank unit 8 18-Aug-14 25-Aug-14 ERECTION OF ML1 (R1 WR BEARING LUB) SYSTEMERECTION OF ML1 (R1 WR BEARING LUB) SYSTEM 47 02-Jul-14 17-Aug-14 MILL-AUX-10440 Electrical Work (Sensor Erection & Termination) 20 02-Jul-14 21-Jul-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 13 of 81 Filter: All Activity
  • 14. Activity ID Activity Name Remaining Duration Start Finish MILL-AUX-10370 Lowering of the pump unit and placing at the pedestal 1 31-Jul-14 31-Jul-14 MILL-AUX-10360 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14 MILL-AUX-10380 Alignment of tank unit 2 01-Aug-14 02-Aug-14 MILL-AUX-10390 Alignment of pump unit 2 03-Aug-14 04-Aug-14 MILL-AUX-10400 Installation of centrifuge 1 05-Aug-14 05-Aug-14 MILL-AUX-10410 Installation of Strainer and heat exchanger 7 06-Aug-14 12-Aug-14 MILL-AUX-10420 Installation of instruments at pump and tank unit 15 03-Aug-14 17-Aug-14 ERECTION OF RL2 (R2 GEAR LUB) SYSTEMERECTION OF RL2 (R2 GEAR LUB) SYSTEM 51 02-Jul-14 21-Aug-14 MILL-AUX-10530 Electrical Work (Sensor Erection & Termination) 30 02-Jul-14 31-Jul-14 MILL-AUX-10450 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14 MILL-AUX-10460 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14 MILL-AUX-10470 Alignment of tank unit 2 03-Aug-14 04-Aug-14 MILL-AUX-10480 Alignment of pump unit 3 05-Aug-14 07-Aug-14 MILL-AUX-10490 Installation of centrifuge 2 08-Aug-14 09-Aug-14* MILL-AUX-10500 Installation of Strainer and heat exchanger 2 10-Aug-14 11-Aug-14 MILL-AUX-10510 Installation of instruments at pump and tank unit 10 12-Aug-14 21-Aug-14 ERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEMERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEM 23 19-May-14 A 24-Jul-14 MILL-AUX-10540 Lowering of the tank and placing at the pedestal 0 19-May-14 A 19-May-14 A MILL-AUX-10550 Lowering of the pump unit and placing at the pedestal 0 20-May-14 A 21-May-14 A MILL-AUX-10560 Alignment of tank unit 0 22-May-14 A 23-May-14 A MILL-AUX-10570 Alignment of pump unit 0 24-May-14 A 25-May-14 A MILL-AUX-10580 Installation of centrifuge 0 26-May-14 A 27-May-14 A MILL-AUX-10590 Installation of Strainer and heat exchanger 0 28-May-14 A 01-Jun-14 A MILL-AUX-10600 Installation of instruments at pump and tank unit 0 02-Jun-14 A 09-Jun-14 A MILL-AUX-10620 Electrical Work (Sensor Erection & Termination) 23 30-Jun-14 A 24-Jul-14 ERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEMERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 38 30-Jul-14 05-Sep-14 MILL-AUX-10640 Lowering of the pump unit and placing at the pedestal 1 03-Aug-14 03-Aug-14 MILL-AUX-10650 Alignment of tank unit 1 04-Aug-14 04-Aug-14 MILL-AUX-10660 Alignment of pump unit (Oil booster,metering pump) 1 05-Aug-14 05-Aug-14 MILL-AUX-10670 Installation of centrifuge 1 05-Aug-14 05-Aug-14 MILL-AUX-10680 Installation of Strainer and heat exchanger 1 06-Aug-14 06-Aug-14 MILL-AUX-10690 Installation of instruments at pump and tank unit 2 07-Aug-14 08-Aug-14 MILL-AUX-10700 Installation of valve Stands 10 30-Jul-14 08-Aug-14 MILL-AUX-10710 Electrical Work (Sensor Erection & Termination) 28 09-Aug-14 05-Sep-14 ERECTION OF DE-SCALING SYSTEMERECTION OF DE-SCALING SYSTEM 34 18-Jun-14 A 15-Sep-14 MILL-AUX-10720 Erection of Surge Tank 0 18-Jun-14 A 20-Jun-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 14 of 81 Filter: All Activity
  • 15. Activity ID Activity Name Remaining Duration Start Finish MILL-AUX-10730 Erection of Accumulator stands 2 23-Aug-14 24-Aug-14 MILL-AUX-10740 Erection of Descaling Pump units 2 25-Aug-14 26-Aug-14 MILL-AUX-10750 Erection of valve stands 10 27-Aug-14 05-Sep-14 MILL-AUX-10760 Electrical Work (Sensor Erection & Termination) 34 13-Aug-14 15-Sep-14 ERECTION OF HA1 (RM AUX HYD) SYSTEMERECTION OF HA1 (RM AUX HYD) SYSTEM 34 15-Apr-14 A 12-Aug-14 MILL-AUX-10830 Installation of accumulator stand 0 15-Apr-14 A 16-Apr-14 A MILL-AUX-10770 Lowering of the tank and placing at the pedestal 0 16-May-14 A 18-May-14 A MILL-AUX-10780 Lowering of the pump unit and placing at the pedestal 0 19-May-14 A 22-May-14 A MILL-AUX-10790 Alignment of tank unit 0 22-May-14 A 27-May-14 A MILL-AUX-10800 Alignment of pump unit 0 27-May-14 A 01-Jun-14 A MILL-AUX-10810 Installation of filter circulation unit 0 01-Jun-14 A 06-Jun-14 A MILL-AUX-10840 Installation of instruments at pump and tank unit 4 21-Jul-14* 24-Jul-14 MILL-AUX-10850 Installation of valve Stands 15 10-Jul-14* 24-Jul-14 MILL-AUX-10820 Installation of return filter line 4 01-Aug-14 04-Aug-14 MILL-AUX-10860 Electrical Work (Sensor Erection & Termination) 19 25-Jul-14 12-Aug-14 ERECTION OF HS1 (RM SERVO HYD) SYSTEMERECTION OF HS1 (RM SERVO HYD) SYSTEM 45 02-Jul-14 15-Aug-14 MILL-AUX-10870 Lowering of the tank and placing at the pedestal 3 02-Jul-14* 04-Jul-14 MILL-AUX-10880 Lowering of the pump unit and placing at the pedestal 1 05-Jul-14 05-Jul-14 MILL-AUX-10890 Alignment of tank unit 1 06-Jul-14 06-Jul-14 MILL-AUX-10900 Alignment of pump unit 1 07-Jul-14 07-Jul-14 MILL-AUX-10910 Installation of filter circulation unit 1 08-Jul-14 08-Jul-14 MILL-AUX-10920 Installation of return filter line 1 09-Jul-14 09-Jul-14 MILL-AUX-10930 Installation of accumulator stand 1 10-Jul-14 10-Jul-14 MILL-AUX-10940 Installation of instruments at pump and tank unit 10 11-Jul-14 20-Jul-14 MILL-AUX-10950 Installation of valve Stands (Incl servo valve) 10 21-Jul-14 30-Jul-14 MILL-AUX-10960 Electrical Work (Sensor Erection & Termination) 16 31-Jul-14 15-Aug-14* Mill Elect portion & Local ElectricsMill Elect portion & Local Electrics 66 11-Jul-14 06-Oct-14 Electrical & Automation WorksElectrical & Automation Works 66 11-Jul-14 06-Oct-14 ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE)ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE) 60 11-Jul-14 27-Sep-14 B&S-10000 POWER CABLE GLANDING 20 11-Jul-14 06-Aug-14 B&S-10010 POWER CABLE SOCKETING & TERMINATION 40 06-Aug-14 27-Sep-14 ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE)ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE) 20 08-Sep-14 04-Oct-14 B&S-10020 INSTRUMENT INSTALLATION 9 08-Sep-14 19-Sep-14 B&S-10030 CABLE DUCTING LAYING & TERMINATION 5 27-Sep-14 04-Oct-14* ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1)ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1) 28 29-Aug-14 04-Oct-14 B&S-10040 INSTRUMENT INSTALLATION 20 29-Aug-14 24-Sep-14 B&S-10050 CABLE DUCTING LAYING & TERMINATION 23 04-Sep-14 04-Oct-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 15 of 81 Filter: All Activity
  • 16. Activity ID Activity Name Remaining Duration Start Finish ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2)ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2) 30 06-Aug-14 15-Sep-14 B&S-10060 INSTRUMENT INSTALLATION 7 06-Aug-14 16-Aug-14 B&S-10070 CABLE DUCTING LAYING & TERMINATION 23 16-Aug-14 15-Sep-14 ELECTRICAL WORK (FRONT#5--> DELAYTABLE)ELECTRICAL WORK (FRONT#5--> DELAYTABLE) 43 09-Aug-14 06-Oct-14 B&S-10080 INSTRUMENT INSTALLATION 30 09-Aug-14 18-Sep-14 B&S-10090 CABLE DUCTING LAYING & TERMINATION 10 22-Sep-14 06-Oct-14* ELECTRICAL WORK (FRONT#6--> CROPSHEAR)ELECTRICAL WORK (FRONT#6--> CROPSHEAR) 43 09-Aug-14 06-Oct-14 B&S-10100 INSTRUMENT INSTALLATION 28 09-Aug-14 15-Sep-14 B&S-10110 CABLE DUCTING LAYING & TERMINATION 12 19-Sep-14 06-Oct-14* INDIVIDUAL TRIALSINDIVIDUAL TRIALS 85 24-Jul-14 17-Oct-14 B&S-10150 FRONT#2 (FURNACE DELIVERY SIDE) INDIVIDUAL TRIAL 10 05-Oct-14 15-Oct-14 B&S-10130 FRONT#6 (CROP SHEAR) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14 B&S-10120 FRONT#5 (DELAYTABLE) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14 B&S-10140 FRONT#1 (FURNACE ENTRYSIDE) INDIVIDUAL TRIAL 7 09-Oct-14 17-Oct-14 Online FlushingOnline Flushing 58 24-Jul-14 08-Oct-14 B&S-10170 ONLINE FLUSHING OF ML2 (R2 BUR BEARING LUB) SYSTEM 11 24-Jul-14 07-Aug-14 B&S-10210 ONLINE FLUSHING OF HA1 (RM AUX HYD) SYSTEM 4 12-Aug-14 18-Aug-14 B&S-10190 ONLINE FLUSHING OF HS1 (RM SERVO HYD) SYSTEM 11 08-Sep-14 22-Sep-14* B&S-10230 ONLINE FLUSHING OF RL1 (R1 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14* B&S-10160 ONLINE FLUSHING OF ML1 (R1 WR BEARING LUB) SYSTEM 10 09-Sep-14 22-Sep-14* B&S-10220 ONLINE FLUSHING OF RL2 (R2 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14* B&S-10200 ONLINE FLUSHING OF DE-SCALING SYSTEM 16 17-Sep-14 08-Oct-14* B&S-10180 ONLINE FLUSHING OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 10 25-Sep-14 08-Oct-14* R2 (Incl R2 Entry Table to CS Entry Table) and TGS equipmentR2 (Incl R2 Entry Table to CS Entry Table) and TGS equipment 6 01-Nov-11 A 07-Jul-14 Civil Building & Foundation WorksCivil Building & Foundation Works 0 01-Nov-11 A 10-May-14 A Roughing-AreaRoughing-Area 0 01-Nov-11 A 10-May-14 A RM2-11880 Blasting 0 08-Aug-12 A 15-Sep-12 A RM2-11860 Scale Flume 0 04-Feb-12 A 31-Oct-12 A RM2-11850 Building Column 0 01-Feb-12 A 31-Jan-13 A RM2-11840 Drawing Inputs incl. Equipment foundation 0 01-Nov-11 A 31-Jul-13 A RM2-11870 Roughing Mill Equip Foundation-R2 incl. scale flume wall upto top 0 29-Apr-12 A 12-Feb-14 A RM2-11890 Roughing Mill Equip Foundation-R1 incl. scale flume wall upto top 0 02-Nov-12 A 10-May-14 A STRUCTURAL - RM 1 & 2 - B-C /14a - 32STRUCTURAL - RM 1 & 2 - B-C /14a - 32 5 25-Aug-12 A 07-Jul-14 RM2-11900 Drawing Inputs 0 25-Aug-12 A 31-Oct-12 A RM2-11910 Fabrication 0 15-Jan-13 A 25-Dec-13 A RM2-11930 Erection B-C/24-32 0 15-Sep-12 A 27-Feb-14 A RM2-11920 Erection B-C/14-24 0 16-Feb-13 A 30-Mar-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 16 of 81 Filter: All Activity
  • 17. Activity ID Activity Name Remaining Duration Start Finish RM2-11940 Sheeting B-C/14-32 5 18-Jan-14 A 07-Jul-14* RM Pulpits, LAB & Roll bite lub systemRM Pulpits, LAB & Roll bite lub system 83 03-Jan-14 A 17-Oct-14 R1-Pulpit Area:R1-Pulpit Area: 83 03-Jan-14 A 17-Oct-14 RM1-PUL-10000 Equipment availablity & Drawing 0 03-Jan-14 A 20-Jan-14 A RM1-PUL-10010 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 19-May-14 A RM1-PUL-10050 Panel Erection & Earthing 5 19-May-14 A 08-Jul-14 RM1-PUL-10030 Installation of I/O Panels and HMI, Network cabinet, etc. 10 15-Sep-14 27-Sep-14 RM1-PUL-10040 Cable Laying up to field equipment 50 13-Aug-14 17-Oct-14 RM1-PUL-10060 Cable Glanding & Termination 15 27-Sep-14 17-Oct-14 R2-Pulpit Area:R2-Pulpit Area: 61 03-Jan-14 A 27-Sep-14 RM2-PUL-10080 Equipment availablity & Drawing 0 03-Jan-14 A 24-Jan-14 A RM2-PUL-10070 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 14-Apr-14 A RM2-PUL-10110 Panel Earthing 0 14-Apr-14 A 05-Jun-14 A RM2-PUL-10100 Installation of I/O Panels and HMI, Network cabinet, etc. 25 11-Jul-14 12-Aug-14 RM2-PUL-10120 Cable Laying up to field equipment 20 02-Sep-14 27-Sep-14 RM2-PUL-10130 Cable Glanding & Termination 20 02-Sep-14 27-Sep-14 Structural Building & Technological WorksStructural Building & Technological Works 58 23-Jun-14 A 15-Sep-14 RM2-PUL-10140 Structural & Interior Woks-R-2-Pulpits 8 23-Jun-14 A 11-Jul-14* RM2-PUL-10150 Structural & Interior Woks-R-1-Pulpits 35 31-Jul-14* 15-Sep-14 Civil Building & Foundation WorksCivil Building & Foundation Works 17 10-May-14 A 31-Jul-14 RM2-PUL-10160 Civil Works-R-2-Pulpits 0 10-May-14 A 21-Jun-14 A RM2-PUL-10170 Civil Works-R-1-Pulpits 17 09-Jul-14* 31-Jul-14 LABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTSLABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTS 79 03-Feb-14 A 13-Oct-14 LAB-10000 Issue LOI/Order of LABORATORY EQUIPMENT 0 03-Feb-14 A LAB-10010 Receipt of Equipment at Site of LABORATORYEQUIPMENT 0 03-Feb-14 A 09-May-14 A LAB-10020 Equipment Erection Work of- LABORATORY EQUIPMENT 59 09-May-14 A 16-Sep-14 LAB-10030 Cold Test of- LABORATORY EQUIPMENT 20 16-Sep-14 13-Oct-14 R1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting systemR1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting system 108 18-Jan-14 A 17-Oct-14 Mechanical & Piping WorksMechanical & Piping Works 108 18-Jan-14 A 17-Oct-14 FRONT#4 (ROUGHING MILL#1)FRONT#4 (ROUGHING MILL#1) 98 21-Apr-14 A 07-Oct-14 HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 87 02-Jul-14 26-Sep-14 FSB-10000 INSTALLATION OF DESCALING BOX 2 12-Jul-14 13-Jul-14 FSB-10010 INSTALLATION OF SPLASH GUARD 10 04-Jul-14 13-Jul-14 FSB-10020 ATTACHED PIPING 70 02-Jul-14 09-Sep-14 FSB-10030 INSTALLTION OF PX SENSOR 10 31-Aug-14 09-Sep-14 PREPARATIONPREPARATION 7 02-Jul-14 08-Jul-14 FSB-10040 PREPARATION 1 02-Jul-14 02-Jul-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 17 of 81 Filter: All Activity
  • 18. Activity ID Activity Name Remaining Duration Start Finish FSB-10050 CONFIRM THE ERECTION & ALIGNMENT OF HSB TABLE 5 03-Jul-14 07-Jul-14 FSB-10060 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 1 08-Jul-14 08-Jul-14 INSTALLATION OF BOTTOM HEADERINSTALLATION OF BOTTOM HEADER 3 09-Jul-14 11-Jul-14 FSB-10070 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)3 09-Jul-14 11-Jul-14 INSTALLTION OF DESCALING NOZZLEINSTALLTION OF DESCALING NOZZLE 77 12-Jul-14 26-Sep-14 FSB-10080 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 38 12-Jul-14 18-Aug-14 FSB-10090 Individual Trial of HSB 5 20-Sep-14 26-Sep-14* RM SHOE PLATERM SHOE PLATE 0 21-Apr-14 A 16-May-14 A RM1-10010 FOUNDATION CHECKING 0 21-Apr-14 A 21-Apr-14 A RM1-10020 FOUNDATION CHIPPING AND PADDING 0 22-Apr-14 A 23-Apr-14 A RM1-10040 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 15-May-14 A 15-May-14 A RM1-10050 GROUTING & CURING 0 16-May-14 A 16-May-14 A RM HOUSINGRM HOUSING 32 07-Jun-14 A 02-Aug-14 RM1-10060 FINAL MEASUREMENT OF HSG WITH PIANNO WIREAND TIGHTENING OF HSG AND SEPARATOR BOLT.0 07-Jun-14 A 15-Jun-14 A RM1-10070 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 32 16-Jun-14 A 02-Aug-14 DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 07-Jun-14 A 07-Jun-14 A RM1-10140 ERECTION OF DS HOUSING 0 07-Jun-14 A 07-Jun-14 A WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 08-Jun-14 A 08-Jun-14 A RM1-10180 ERECTION OF WS HOUSING 0 08-Jun-14 A 08-Jun-14 A BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 09-Jun-14 A 09-Jun-14 A RM1-10240 ERECTION OF BOTTOM SEPARATOR 0 09-Jun-14 A 09-Jun-14 A TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 10-Jun-14 A 12-Jun-14 A RM1-10280 ERECTION OF TOP SEPARATOR 0 10-Jun-14 A 10-Jun-14 A RM1-10290 ALLIGNMENT OF RM-1 HOUSING 0 10-Jun-14 A 12-Jun-14 A E1 HOUSING & PROPERE1 HOUSING & PROPER 12 02-Jul-14 13-Jul-14 EDG1-10000 E1 HOUSNG ERECTION &ASSEMBLY. 2 02-Jul-14 03-Jul-14 EDG1-10010 AWC & PULL BACK CYLINDER 1 04-Jul-14 04-Jul-14 EDG1-10020 REDUCER & MOTOR ERECTION AND ALLIGNMENT 1 08-Jul-14 08-Jul-14 EDG1-10030 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 1 13-Jul-14 13-Jul-14 ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 3 05-Jul-14 07-Jul-14 EDG1-10080 INSERT ROLL ADJUST FRAME IN HSG 1 05-Jul-14 05-Jul-14 EDG1-10090 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 1 06-Jul-14 06-Jul-14 EDG1-10100 INSTALL DRAG CHAIN 1 07-Jul-14 07-Jul-14 ROLL DRIVE FRAMEROLL DRIVE FRAME 1 08-Jul-14 08-Jul-14 EDG1-10110 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 1 08-Jul-14 08-Jul-14 EDG1-10120 INSTALL DRIVEASSEMBLY ON R1 HSG. 1 08-Jul-14 08-Jul-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 18 of 81 Filter: All Activity
  • 19. Activity ID Activity Name Remaining Duration Start Finish EDG1-10130 TIGHTEN BOLT BY REGULATED TORQUE 1 08-Jul-14 08-Jul-14 EDG1-10140 CONNECT SUPPORT FOR DRIVE. 1 08-Jul-14 08-Jul-14 SPINDLE INSTALLATIONSPINDLE INSTALLATION 1 08-Jul-14 08-Jul-14 EDG1-10150 CONNECT SPINDLEAFTER ALLIGNMENT OF REDUCER AND MOTOR 1 08-Jul-14 08-Jul-14 RM SCREW DOWNRM SCREW DOWN 7 13-Jul-14 19-Jul-14 RM1-10370 INSTALLATION AND ALLIGNMENT OF CASING 1 13-Jul-14 13-Jul-14 RM1-10340 INSTALL MOTOR BRACKET ON HOUSING 1 13-Jul-14 13-Jul-14 RM1-10350 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.1 13-Jul-14 13-Jul-14 RM1-10360 FIX THE STUD BOLT FOR MOUNTING THE CASING 1 13-Jul-14 13-Jul-14 RM1-10380 FASTENING OF CASING BOLTS. 1 14-Jul-14 14-Jul-14 RM1-10390 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 1 15-Jul-14 15-Jul-14 RM1-10400 SENSOR ASSEMBLYAND REMAINING WORKS. 1 16-Jul-14 16-Jul-14 RM1-10410 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 1 17-Jul-14 17-Jul-14 RM1-10420 INSTALLATION OF D/S SCREW & NUTASSEMBLY 1 18-Jul-14 18-Jul-14 RM1-10430 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 1 19-Jul-14 19-Jul-14 R1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 1 19-Jul-14 19-Jul-14 RM1-10460 ENTRYAND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 1 19-Jul-14 19-Jul-14 RM1-10470 ENTRYAND DELIVERY TOP STRIPPER. 1 19-Jul-14 19-Jul-14 RM1-10480 TOP WR COOLANT HEADER AND HOSE 1 19-Jul-14 19-Jul-14 RM1-10490 ATTACHED DESCALING & ROLL COOLANT PIPES 1 19-Jul-14 19-Jul-14 RM1-10500 FEED ROLLER DRIVE UNIT 1 19-Jul-14 19-Jul-14 RM1-10510 ENRTY& DELIVERYSTRIPPER CYLINDERS 1 19-Jul-14 19-Jul-14 RM1-10520 DELIVERY TOP & BOTTOM DESCALING HEADER 1 19-Jul-14 19-Jul-14 RM1-10530 INSTALLATION OF LOADING CYLINDERS 1 19-Jul-14 19-Jul-14 RM1-10540 REMAINING ASSEMBLIES (Inside rails) 1 19-Jul-14 19-Jul-14 RM1-10440 ENTRY& DELIVERY/TOP & BOTTOM STRIPPER BASE. 1 19-Jul-14 19-Jul-14 RM1-10450 ENTRYAND DELIVERY BOTTOM WR COLLANT HEADER 1 19-Jul-14 19-Jul-14 R1 SPINDLE CARRIERR1 SPINDLE CARRIER 1 20-Jul-14 20-Jul-14 RM1-10590 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14 RM1-10600 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14 RM1-10610 ATTACHED PIPING 0 20-Jul-14* RM1-10550 INSTALLATION OF CARRIER STAND 1 20-Jul-14 20-Jul-14 RM1-10560 ALLIGNMENT OF CARRIER STAND 1 20-Jul-14 20-Jul-14 RM1-10570 BASE GROUT (including curing) 1 20-Jul-14 20-Jul-14 RM1-10580 ASSEMBLING OF SPINDLE BEARING (Offiline) 1 20-Jul-14 20-Jul-14 R1 ENT TABLE (4-Tables, 22 Rolls)R1 ENT TABLE (4-Tables, 22 Rolls) 23 02-Jul-14 24-Jul-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 19 of 81 Filter: All Activity
  • 20. Activity ID Activity Name Remaining Duration Start Finish RM1-10620 MOTOR ALLIGNMENT (22 MOTORS) 8 11-Jul-14 18-Jul-14 RM1-10630 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 2 18-Jul-14 20-Jul-14 PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14 RM1-10640 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14 RM1-10650 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14 RM1-10660 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14 RM1-10670 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE1 04-Jul-14 04-Jul-14 RM1-10680 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14 RM1-10690 SETTING THE ANCHOR BOLTSAND NUTS 1 06-Jul-14 06-Jul-14 RM1-10700 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14 ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14 RM1-10710 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14 RM1-10720 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14 RM1-10730 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 1 09-Jul-14 09-Jul-14 REMAINING WORKSREMAINING WORKS 4 20-Jul-14 24-Jul-14 RM1-10740 INSTALLATION OF MOTOR COVER 1 20-Jul-14 20-Jul-14 RM1-10750 INSTALLATION OF SPLASH GUARD 1 21-Jul-14 21-Jul-14 RM1-10760 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 21-Jul-14 22-Jul-14 RM1-10770 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 22-Jul-14 23-Jul-14 RM1-10780 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 1 23-Jul-14 24-Jul-14 R1 DEL TABLE (3 TABLES, 17 ROLLS)R1 DEL TABLE (3 TABLES, 17 ROLLS) 92 02-Jul-14 01-Oct-14 RM1-10790 MOTOR ALLIGNMENT (17 MOTORS) 34 10-Jul-14 12-Aug-14 RM1-10800 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 47 13-Aug-14 28-Sep-14 PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14 RM1-10810 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14 RM1-10820 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14 RM1-10830 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14 RM1-10840 TEMPORARY INSTALLATION AND TEMPORARYALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.1 04-Jul-14 04-Jul-14 RM1-10850 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14 RM1-10860 SETTLING THE ANCHOR BOLTS AND NUTS 1 06-Jul-14 06-Jul-14 RM1-10870 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14 ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14 RM1-10880 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14 RM1-10890 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14 RM1-10900 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 1 09-Jul-14 09-Jul-14 REMAINING WORKSREMAINING WORKS 3 29-Sep-14 01-Oct-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 20 of 81 Filter: All Activity
  • 21. Activity ID Activity Name Remaining Duration Start Finish RM1-10910 INSTALLATION OF MOTOR COVER 1 29-Sep-14 29-Sep-14 RM1-10920 INSTALLATION OF SPLASH GUARD 1 29-Sep-14 29-Sep-14 RM1-10930 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 30-Sep-14 30-Sep-14 RM1-10940 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 01-Oct-14 01-Oct-14 R1 ENT SIDE GUIDER1 ENT SIDE GUIDE 36 24-Jul-14 29-Aug-14 RM1-10950 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 24-Jul-14 26-Jul-14 RM1-10960 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 26-Jul-14 28-Jul-14 RM1-10970 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 01-Aug-14 02-Aug-14 RM1-10980 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)1 02-Aug-14 03-Aug-14 RM1-10990 CONNECTION OF GEAR COUPLING 1 03-Aug-14 04-Aug-14 ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 28-Jul-14 30-Jul-14 PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 28-Jul-14 29-Jul-14 RM1-11000 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-Jul-14 28-Jul-14 RM1-11010 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-Jul-14 28-Jul-14 RM1-11020 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-Jul-14 29-Jul-14 RM1-11030 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 29-Jul-14 29-Jul-14 MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 29-Jul-14 30-Jul-14 RM1-11040 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-Jul-14 29-Jul-14 RM1-11050 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-Jul-14 29-Jul-14 RM1-11060 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©1 30-Jul-14 30-Jul-14 ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 30-Jul-14 01-Aug-14 RM1-11070 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 30-Jul-14 30-Jul-14 RM1-11080 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-Jul-14 30-Jul-14 RM1-11090 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 31-Jul-14 31-Jul-14 RM1-11100 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 31-Jul-14 31-Jul-14 RM1-11110 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-Jul-14 31-Jul-14 RM1-11120 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 01-Aug-14 01-Aug-14 MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 25 04-Aug-14 29-Aug-14 RM1-11130 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 04-Aug-14 05-Aug-14 RM1-11140 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 05-Aug-14 05-Aug-14 RM1-11150 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 29-Aug-14 29-Aug-14 R1 DEL SIDE GUIDER1 DEL SIDE GUIDE 45 04-Aug-14 17-Sep-14 RM1-11160 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m4 04-Aug-14* 07-Aug-14 RM1-11170 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 07-Aug-14 09-Aug-14 RM1-11180 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 3 12-Aug-14 15-Aug-14 RM1-11190 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 15-Aug-14 18-Aug-14* May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 21 of 81 Filter: All Activity
  • 22. Activity ID Activity Name Remaining Duration Start Finish ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 09-Aug-14 11-Aug-14 PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 09-Aug-14 10-Aug-14 RM1-11200 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 09-Aug-14 09-Aug-14 RM1-11210 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 09-Aug-14 09-Aug-14 RM1-11220 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 10-Aug-14 10-Aug-14 RM1-11230 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 10-Aug-14 10-Aug-14 MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 10-Aug-14 11-Aug-14 RM1-11240 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 10-Aug-14 10-Aug-14 RM1-11250 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 10-Aug-14 10-Aug-14 RM1-11260 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 11-Aug-14 11-Aug-14 ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 10-Aug-14 12-Aug-14 RM1-11270 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 10-Aug-14 10-Aug-14 RM1-11280 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 10-Aug-14 10-Aug-14 RM1-11290 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 11-Aug-14 11-Aug-14 RM1-11300 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 11-Aug-14 11-Aug-14 RM1-11310 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 11-Aug-14 11-Aug-14 RM1-11320 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 12-Aug-14 12-Aug-14 MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 30 18-Aug-14 17-Sep-14 RM1-11330 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 18-Aug-14 19-Aug-14 RM1-11340 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 19-Aug-14 19-Aug-14 RM1-11350 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 17-Sep-14 17-Sep-14 R1 WR CHANGING DEVICER1 WR CHANGING DEVICE 80 20-Jul-14 07-Oct-14 RM1-11360 INSTALLATION OF AIR CYLINDER 2 05-Aug-14* 06-Aug-14 RM1-11370 ALLIGNMENT OF AIR CYLINDER 2 07-Aug-14 08-Aug-14 PREPARATIONPREPARATION 20 20-Jul-14 08-Aug-14 RM1-11380 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 8 20-Jul-14 27-Jul-14 RM1-11390 CHECKING OF FOUNDATION 3 28-Jul-14 30-Jul-14 RM1-11400 CHIPPING AND PADDING 3 06-Aug-14 08-Aug-14 INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 12 09-Aug-14 20-Aug-14 RM1-11410 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 6 09-Aug-14 14-Aug-14 RM1-11420 INSTALL RAIL,HYD. CYLINDER BASEAND RAIL BASE FOR FOR THE ROLL TRASVERSE. 6 15-Aug-14 20-Aug-14 ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 20 21-Aug-14 09-Sep-14 RM1-11430 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 4 21-Aug-14 24-Aug-14 RM1-11440 POSITIONING FROM R1 MILL CENTRE LINE 4 25-Aug-14 28-Aug-14 RM1-11450 ADJUSTING THETOP OF RAILAND ALLIGNMENT OF CYLINDER BASE. 4 29-Aug-14 01-Sep-14 RM1-11460 WELDING THE RAIL STOPPER PLATE. 8 02-Sep-14 09-Sep-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 22 of 81 Filter: All Activity
  • 23. Activity ID Activity Name Remaining Duration Start Finish ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 6 10-Sep-14 15-Sep-14 RM1-11470 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 1 10-Sep-14 10-Sep-14 RM1-11480 POSITIONING FROM CENTRE OF DATUM RAIL 1 11-Sep-14 11-Sep-14 RM1-11490 POSITIONING FROM R1 MILL CENTRE LINE 1 12-Sep-14 12-Sep-14 RM1-11500 ADJUSTING THETOP OF RAIL FROM BENCHMARK 1 13-Sep-14 13-Sep-14 RM1-11510 WELDING THE RAIL STOPPER PLATE 1 14-Sep-14 14-Sep-14 RM1-11520 ADJUSTING THE CYLINDER CENTRE 1 15-Sep-14 15-Sep-14 ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 5 16-Sep-14 20-Sep-14 RM1-11530 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 2 16-Sep-14 17-Sep-14 RM1-11540 POSITIONING FROM SIDE SHIFT CAR CENTRE 1 18-Sep-14 18-Sep-14 RM1-11550 POSITIONING FROM MILL CENTRE 1 19-Sep-14 19-Sep-14 RM1-11560 WELDING THE CYLINDER STOPPER PLATE 1 20-Sep-14 20-Sep-14 INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 17 21-Sep-14 07-Oct-14 RM1-11570 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 1 21-Sep-14 21-Sep-14 RM1-11580 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 1 22-Sep-14 22-Sep-14 RM1-11590 CONNECT CYLINDER WITH SIDE SHIFT CAR 1 23-Sep-14 23-Sep-14 RM1-11600 INSTALL THE FLOOR PLATES 14 24-Sep-14 07-Oct-14 FRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIALFRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIAL 30 17-Sep-14 17-Oct-14 B&S-10240 ROUGHING MILL TRIAL 30 17-Sep-14* 17-Oct-14 FRONT#5 (ROUGHING MILL#2)FRONT#5 (ROUGHING MILL#2) 80 15-Feb-14 A 24-Sep-14 RM2-10160 SAFETY SCAFFOLDING INSTALLATION 0 28-Feb-14 A 02-Mar-14 A RM SHOE PLATERM SHOE PLATE 0 15-Feb-14 A 22-Feb-14 A RM2-10170 FOUNDATION CHECKING 0 15-Feb-14 A 16-Feb-14 A RM2-10180 FOUNDATION CHIPPING AND PADDING 0 17-Feb-14 A 18-Feb-14 A RM2-10190 PREPARATION OF INSTALLATION 0 17-Feb-14 A 18-Feb-14 A RM2-10200 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 19-Feb-14 A 20-Feb-14 A RM2-10210 GROUTING 0 21-Feb-14 A 22-Feb-14 A RM HOUSINGRM HOUSING 0 23-Feb-14 A 24-Mar-14 A RM2-10220 FINAL MEASUREMENT OF HSG WITH PIANNO WIREAND TIGHTENING OF HSG AND SEPARATOR BOLT.0 22-Mar-14 A 22-Mar-14 A RM2-10230 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 0 23-Mar-14 A 24-Mar-14 A PREPARATIONPREPARATION 0 23-Feb-14 A 23-Feb-14 A RM2-10280 HSG SURFACE TRIMMING 0 23-Feb-14 A 23-Feb-14 A RM2-10290 SETUP OF HSG VERTICALLITY MEASUREMENT JIGS AND SCALFOLDING 0 23-Feb-14 A 23-Feb-14 A RM2-10240 ASSEMBLY OF HOUSING LIFTING BEAM &TRIAL OF THE SAME WITH BOTH THE 120 TON CRANE0 23-Feb-14 A 23-Feb-14 A RM2-10250 TRANSPORTING AND POSITIONING HSG AS REFERED IN MANUAL 0 23-Feb-14 A 23-Feb-14 A RM2-10260 INSTALLATION OF MILLATTACHED PIPING WHICH EVER POSIBLE 0 23-Feb-14 A 23-Feb-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 23 of 81 Filter: All Activity
  • 24. Activity ID Activity Name Remaining Duration Start Finish RM2-10270 INSTALLATION OF TEMPORARY SCALFOLDING AND LADDER FOR THE ACCESSTO THE MILL TOP0 23-Feb-14 A 23-Feb-14 A DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 26-Feb-14 A 26-Feb-14 A RM2-10300 LIFTING THE DS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREATO INSTALL POSITION0 26-Feb-14 A 26-Feb-14 A RM2-10310 PUTTING HSG ON SHOE PLATEAND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 26-Feb-14 A 26-Feb-14 A RM2-10320 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BYFOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAMEAS DRAWING0 26-Feb-14 A 26-Feb-14 A RM2-10330 PUSH THE HSG TO THE DELIVERY SIDE SHOE PLATEAND VERIFY THE ZERO GAPS BETWEEN HSG AND SHOE PLATESAND TIGHTEN THE FOO0 26-Feb-14 A 26-Feb-14 A WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 04-Mar-14 A 09-Mar-14 A RM2-10340 LIFTING THE WS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREATO INSTALL POSITION0 04-Mar-14 A 04-Mar-14 A RM2-10350 PUTTING HSG ON SHOE PLATEAND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 05-Mar-14 A 05-Mar-14 A RM2-10360 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BYFOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAMEAS DRAWING0 06-Mar-14 A 06-Mar-14 A RM2-10370 PUSH THE HSG TO THE ENTRY SIDE SHOE PLATEAND VERIFYTHE ZERO GAPS BETWEEN THE HSG AND SHOE PLATESAND TIGHTEN THE FOO0 07-Mar-14 A 07-Mar-14 A RM2-10380 INSTALL LINER BETWEEN ENTRY SIDE SHOE PLATE AND HSG. 0 08-Mar-14 A 08-Mar-14 A RM2-10390 VERIFYTHE FINAL CLEARANCE. 0 09-Mar-14 A 09-Mar-14 A BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 10-Mar-14 A 13-Mar-14 A RM2-10400 PULL IN THE BOTTOM SEPARATOR BOLTS IN HSG AND TEMPORARY SETTING BOTTOM SEPARATOR INTO THE HSG0 10-Mar-14 A 11-Mar-14 A RM2-10410 VERIFYTHE ZERO GAPS FOR CONTACT SURFACE OF SEPARATOR TO DS HSG. 0 12-Mar-14 A 12-Mar-14 A RM2-10420 VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF WS HSG TO SHOE PLATE. 0 12-Mar-14 A 12-Mar-14 A RM2-10430 FINAL TIGHTNING OF HSG FOOT BOLTSAND SEPARATOR BOLTSAFTER COMPLETING THEALLIGNMENT OF MILL HOUSING0 13-Mar-14 A 13-Mar-14 A TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 14-Mar-14 A 21-Mar-14 A RM2-10440 ASSEMBLING THETEMPORARYSCALFOLDING FOT THE INSTALLATION AREA 0 14-Mar-14 A 14-Mar-14 A RM2-10450 SETTING THE JACK BETWEEN DS HSG AND WS HSG 0 15-Mar-14 A 15-Mar-14 A RM2-10460 INSTALL THE TOP SEPARATOR TO THE HSG STEPPED SURFACE 0 16-Mar-14 A 16-Mar-14 A RM2-10470 INSERT THE BOLT AND REMOVE THE JACK 0 17-Mar-14 A 17-Mar-14 A RM2-10480 ALLIGN THE CENTRE OF THE COTTER PIN SLOTS OF THE DSAND WS HSG 0 18-Mar-14 A 19-Mar-14 A RM2-10490 FINAL TIGHTNING OF HSG FOOT BOLTSAND SEPARATOR BOLTSAFTER COMPLETING THEALLIGNMENT OF MILL HOUSING0 20-Mar-14 A 21-Mar-14 A E2 PROPERE2 PROPER 0 08-Apr-14 A 05-May-14 A EDG1-10160 E1 HOUSNG ASSEMBLY(Offline) 0 08-Apr-14 A 09-Apr-14 A EDG1-10170 AWC & PULL BACK CYLINDER 0 14-Apr-14 A 15-Apr-14 A EDG1-10190 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 0 30-Apr-14 A 03-May-14 A EDG1-10180 REDUCER & MOTOR ERECTION AND ALLIGNMENT 0 05-May-14 A 05-May-14 A E2 HOUSING ERECTIONE2 HOUSING ERECTION 0 10-Apr-14 A 13-Apr-14 A EDG1-10200 INSTALL & VERIFYTHE ZERO GAPS FOR CONTACT SURFACE OF HSG TO TOPOF INSTALATION LINER0 10-Apr-14 A 10-Apr-14 A EDG1-10210 PUSH THE HSG TO DELIVERY SIDE AND CONTACT TO R1 HSG. 0 11-Apr-14 A 11-Apr-14 A EDG1-10220 MEASURE THE RAIL TOP SURFACE WITH STRAIGHT EDGEAND PRECISION LEVEL. 0 12-Apr-14 A 12-Apr-14 A EDG1-10230 FINAL TIGHTENING THE HSG FOOT BOLTS AND JOINT BOLTSAFTER COMPLETING THEALIGNMENT OF E1.0 13-Apr-14 A 13-Apr-14 A ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 0 16-Apr-14 A 18-Apr-14 A EDG1-10240 INSERT ROLL ADJUST FRAME IN HSG 0 16-Apr-14 A 16-Apr-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 24 of 81 Filter: All Activity
  • 25. Activity ID Activity Name Remaining Duration Start Finish EDG1-10250 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 0 17-Apr-14 A 17-Apr-14 A EDG1-10260 INSTALL DRAG CHAIN 0 18-Apr-14 A 18-Apr-14 A ROLL DRIVE FRAMEROLL DRIVE FRAME 0 20-Apr-14 A 23-Apr-14 A EDG1-10270 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 0 20-Apr-14 A 20-Apr-14 A EDG1-10280 INSTALL DRIVEASSEMBLY ON R1 HSG. 0 21-Apr-14 A 21-Apr-14 A EDG1-10290 TIGHTEN BOLT BY REGULATED TORQUE 0 22-Apr-14 A 22-Apr-14 A EDG1-10300 CONNECT SUPPORT FOR DRIVE. 0 23-Apr-14 A 23-Apr-14 A SPINDLE INSTALLATIONSPINDLE INSTALLATION 0 28-Apr-14 A 29-Apr-14 A EDG1-10310 CONNECT SPINDLEAFTER ALLIGNMENT OF REDUCER AND MOTOR 0 28-Apr-14 A 29-Apr-14 A RM SCREW DOWNRM SCREW DOWN 0 31-Mar-14 A 19-Apr-14 A RM2-10500 INSTALL MOTOR BRACKET ON HOUSING 0 31-Mar-14 A 31-Mar-14 A RM2-10510 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.0 07-Apr-14 A 07-Apr-14 A RM2-10520 FIX THE STUD BOLT FOR MOUNTING THE CASING 0 07-Apr-14 A 07-Apr-14 A RM2-10530 INSTALLATION AND ALLIGNMENT OF CASING 0 08-Apr-14 A 09-Apr-14 A RM2-10540 FASTENING OF CASING BOLTS. 0 10-Apr-14 A 10-Apr-14 A RM2-10550 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 0 11-Apr-14 A 12-Apr-14 A RM2-10560 SENSOR ASSEMBLYAND REMAINING WORKS. 0 13-Apr-14 A 13-Apr-14 A RM2-10570 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 0 14-Apr-14 A 15-Apr-14 A RM2-10580 INSTALLATION OF D/S SCREW & NUTASSEMBLY 0 16-Apr-14 A 17-Apr-14 A RM2-10590 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 0 18-Apr-14 A 19-Apr-14 A R2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 0 20-Apr-14 A 13-May-14 A RM2-10600 ENTRY& DELIVERY/TOP & BOTTOM STRIPPER BASE. 0 20-Apr-14 A 21-Apr-14 A RM2-10610 ENTRYAND DELIVERY BOTTOM WR COLLANT HEADER 0 22-Apr-14 A 23-Apr-14 A RM2-10620 ENTRYAND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 0 24-Apr-14 A 25-Apr-14 A RM2-10630 ENTRYAND DELIVERY TOP STRIPPER. 0 26-Apr-14 A 28-Apr-14 A RM2-10640 TOP WR COOLANT HEADER AND HOSE 0 29-Apr-14 A 30-Apr-14 A RM2-10650 ATTACHED DESCALING & ROLL COOLANT PIPES 0 01-May-14 A 03-May-14 A RM2-10660 FEED ROLLER DRIVE UNIT 0 04-May-14 A 05-May-14 A RM2-10670 ENRTY& DELIVERYSTRIPPER CYLINDERS 0 06-May-14 A 07-May-14 A RM2-10680 DELIVERY TOP & BOTTOM DESCALING HEADER 0 08-May-14 A 09-May-14 A RM2-10690 INSTALLATION OF LOADING CYLINDERS 0 10-May-14 A 11-May-14 A RM2-10700 REMAINING ASSEMBLIES (Inside rails) 0 12-May-14 A 13-May-14 A R2 SPINDLE CARRIERR2 SPINDLE CARRIER 0 14-May-14 A 26-May-14 A RM2-10710 INSTALLATION OF CARRIER STAND 0 14-May-14 A 15-May-14 A RM2-10720 ALLIGNMENT OF CARRIER STAND 0 16-May-14 A 18-May-14 A RM2-10730 BASE GROUT (including curing) 0 19-May-14 A 20-May-14 A RM2-10740 ASSEMBLING OF SPINDLE BEARING (Offiline) 0 21-May-14 A 25-May-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 25 of 81 Filter: All Activity
  • 26. Activity ID Activity Name Remaining Duration Start Finish RM2-10750 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A RM2-10760 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A RM2-10770 ATTACHED PIPING 0 26-May-14 A R2 ENT TABLE (4-Tables, 22 Rolls)R2 ENT TABLE (4-Tables, 22 Rolls) 0 25-Mar-14 A 24-May-14 A RM2-10780 MOTOR ALLIGNMENT (22 MOTORS) 0 19-Apr-14 A 12-May-14 A RM2-10790 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 12-May-14 A 20-May-14 A PREPARATIONPREPARATION 0 25-Mar-14 A 06-May-14 A RM2-10800 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 25-Mar-14 A 26-Mar-14 A RM2-10810 ERECTION OF TABLE BEAM 0 28-Mar-14 A 11-Apr-14 A RM2-10820 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A RM2-10830 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 02-May-14 A 03-May-14 A RM2-10840 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A RM2-10850 SETTING THE ANCHOR BOLTSAND NUTS 0 04-May-14 A 05-May-14 A RM2-10860 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 A RM2-10870 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A RM2-10880 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A RM2-10890 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 08-May-14 A 08-May-14 A REMAINING WORKSREMAINING WORKS 0 20-May-14 A 24-May-14 A RM2-10900 INSTALLATION OF MOTOR COVER 0 20-May-14 A 20-May-14 A RM2-10910 INSTALLATION OF SPLASH GUARD 0 21-May-14 A 21-May-14 A RM2-10920 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 21-May-14 A 22-May-14 A RM2-10930 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 22-May-14 A 23-May-14 A RM2-10940 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 0 23-May-14 A 24-May-14 A R2 DEL TABLE (3 TABLES, 17 ROLLS)R2 DEL TABLE (3 TABLES, 17 ROLLS) 0 20-Mar-14 A 31-May-14 A RM2-10950 MOTOR ALLIGNMENT (17 MOTORS) 0 23-Apr-14 A 20-May-14 A RM2-10960 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 0 20-May-14 A 28-May-14 A PREPARATIONPREPARATION 0 20-Mar-14 A 06-May-14 A RM2-10970 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 20-Mar-14 A 22-Mar-14 A RM2-10980 ERECTION OF TABLE BEAM 0 26-Mar-14 A 16-Apr-14 A RM2-10990 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A RM2-11000 TEMPORARY INSTALLATION AND TEMPORARYALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.0 02-May-14 A 03-May-14 A RM2-11010 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A RM2-11020 SETTLING THE ANCHOR BOLTS AND NUTS 0 04-May-14 A 05-May-14 A RM2-11030 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 A RM2-11040 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 26 of 81 Filter: All Activity
  • 27. Activity ID Activity Name Remaining Duration Start Finish RM2-11050 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A RM2-11060 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 0 08-May-14 A 08-May-14 A REMAINING WORKSREMAINING WORKS 0 28-May-14 A 31-May-14 A RM2-11070 INSTALLATION OF MOTOR COVER 0 28-May-14 A 28-May-14 A RM2-11080 INSTALLATION OF SPLASH GUARD 0 29-May-14 A 29-May-14 A RM2-11090 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 29-May-14 A 30-May-14 A RM2-11100 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 30-May-14 A 31-May-14 A R2 ENT SIDE GUIDER2 ENT SIDE GUIDE 9 28-May-14 A 15-Jul-14 RM2-11110 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 07-Jul-14* 08-Jul-14 RM2-11120 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 09-Jul-14 10-Jul-14 RM2-11130 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 11-Jul-14 11-Jul-14 RM2-11140 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)2 12-Jul-14 13-Jul-14 RM2-11150 CONNECTION OF GEAR COUPLING 2 14-Jul-14 15-Jul-14* ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 0 28-May-14 A 30-May-14 A PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 0 28-May-14 A 29-May-14 A RM2-11160 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-May-14 A 28-May-14 A RM2-11170 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-May-14 A 28-May-14 A RM2-11180 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-May-14 A 29-May-14 A RM2-11190 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION0 29-May-14 A 29-May-14 A MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 0 29-May-14 A 30-May-14 A RM2-11200 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-May-14 A 29-May-14 A RM2-11210 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-May-14 A 29-May-14 A RM2-11220 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©0 30-May-14 A 30-May-14 A ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 0 30-May-14 A 01-Jun-14 A RM2-11230 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 30-May-14 A 30-May-14 A RM2-11240 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-May-14 A 30-May-14 A RM2-11250 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 31-May-14 A 31-May-14 A RM2-11260 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME0 31-May-14 A 31-May-14 A RM2-11270 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-May-14 A 31-May-14 A RM2-11280 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 0 01-Jun-14 A 01-Jun-14 A MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 0 06-Jun-14 A 08-Jun-14 A RM2-11290 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 0 06-Jun-14 A 07-Jun-14 A RM2-11300 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL0 07-Jun-14 A 07-Jun-14 A RM2-11310 CONNECT THE TOP RACK BARS WITH CYLINDERS 0 08-Jun-14 A 08-Jun-14 A R2 DEL SIDE GUIDER2 DEL SIDE GUIDE 79 08-Jul-14 24-Sep-14 RM2-11320 PREPARATION (Measurement of foundation bolt position, Installation liner position and height & Installation of bench m2 08-Jul-14* 09-Jul-14 RM2-11330 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 10-Jul-14 11-Jul-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 27 of 81 Filter: All Activity
  • 28. Activity ID Activity Name Remaining Duration Start Finish RM2-11340 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 18-Sep-14 19-Sep-14 RM2-11350 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 19-Sep-14 22-Sep-14 ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 47 02-Aug-14 17-Sep-14 PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 46 02-Aug-14 16-Sep-14 RM2-11360 REMOVE UPPER PART COVER OF SUPPORT FRAME 1 02-Aug-14* 02-Aug-14 RM2-11370 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 1 03-Aug-14 03-Aug-14 RM2-11380 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 1 04-Aug-14 04-Aug-14 RM2-11390 REMOVE FITTING FOR GREASETUBE OF GEAR FRAME, REMOVETHE UPPER COVER AND PINION4 12-Sep-14 16-Sep-14* MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 16-Sep-14 17-Sep-14 RM2-11400 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 16-Sep-14 17-Sep-14 RM2-11410 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 17-Sep-14 17-Sep-14 RM2-11420 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 17-Sep-14 17-Sep-14 ASSEMBLYOF RACK BARASSEMBLYOF RACK BAR 2 16-Sep-14 18-Sep-14 RM2-11430 ASSEMBLE BOTTOM RACK BAR & CONFIRMTHE MARK POSITION OF THE RACK BAR 0 16-Sep-14 17-Sep-14 RM2-11440 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 17-Sep-14 17-Sep-14 RM2-11450 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACKAND PINION 0 17-Sep-14 17-Sep-14 RM2-11460 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 17-Sep-14 18-Sep-14 RM2-11470 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 18-Sep-14 18-Sep-14 RM2-11480 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 18-Sep-14 18-Sep-14 MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 2 22-Sep-14 24-Sep-14 RM2-11490 PULL BOTTOM RACK BAR(ENTRY& DELIVERYTOGETHER) WITH CHAIN BLOCK 1 22-Sep-14 23-Sep-14 RM2-11500 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERYAT DIFFERENT POSITIONS TO CHECK PARALLEL1 23-Sep-14 24-Sep-14 RM2-11510 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 24-Sep-14 24-Sep-14 R2 WR CHANGING DEVICER2 WR CHANGING DEVICE 0 20-May-14 A 13-Jun-14 A RM2-11520 INSTALLATION OF AIR CYLINDER 0 12-Jun-14 A 12-Jun-14 A RM2-11530 ALLIGNMENT OF AIR CYLINDER 0 13-Jun-14 A 13-Jun-14 A PREPARATIONPREPARATION 0 20-May-14 A 22-May-14 A RM2-11540 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 0 20-May-14 A 20-May-14 A RM2-11550 CHECKING OF FOUNDATION 0 21-May-14 A 21-May-14 A RM2-11560 CHIPPING AND PADDING 0 22-May-14 A 22-May-14 A INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 0 23-May-14 A 24-May-14 A RM2-11570 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 0 23-May-14 A 23-May-14 A RM2-11580 INSTALL RAIL,HYD. CYLINDER BASEAND RAIL BASE FOR FOR THE ROLL TRASVERSE. 0 24-May-14 A 24-May-14 A ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 0 25-May-14 A 28-May-14 A RM2-11590 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 25-May-14 A 25-May-14 A RM2-11600 POSITIONING FROM R1 MILL CENTRE LINE 0 26-May-14 A 26-May-14 A RM2-11610 ADJUSTING THETOP OF RAILAND ALLIGNMENT OF CYLINDER BASE. 0 27-May-14 A 27-May-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 28 of 81 Filter: All Activity
  • 29. Activity ID Activity Name Remaining Duration Start Finish RM2-11620 WELDING THE RAIL STOPPER PLATE. 0 28-May-14 A 28-May-14 A ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 0 29-May-14 A 03-Jun-14 A RM2-11630 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 29-May-14 A 29-May-14 A RM2-11640 POSITIONING FROM CENTRE OF DATUM RAIL 0 30-May-14 A 30-May-14 A RM2-11650 POSITIONING FROM R1 MILL CENTRE LINE 0 31-May-14 A 31-May-14 A RM2-11660 ADJUSTING THETOP OF RAIL FROM BENCHMARK 0 01-Jun-14 A 01-Jun-14 A RM2-11670 WELDING THE RAIL STOPPER PLATE 0 02-Jun-14 A 02-Jun-14 A RM2-11680 ADJUSTING THE CYLINDER CENTRE 0 03-Jun-14 A 03-Jun-14 A ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 0 04-Jun-14 A 07-Jun-14 A RM2-11690 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 0 04-Jun-14 A 04-Jun-14 A RM2-11700 POSITIONING FROM SIDE SHIFT CAR CENTRE 0 05-Jun-14 A 05-Jun-14 A RM2-11710 POSITIONING FROM MILL CENTRE 0 06-Jun-14 A 06-Jun-14 A RM2-11720 WELDING THE CYLINDER STOPPER PLATE 0 07-Jun-14 A 07-Jun-14 A INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 0 08-Jun-14 A 11-Jun-14 A RM2-11730 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 0 08-Jun-14 A 08-Jun-14 A RM2-11740 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 0 09-Jun-14 A 09-Jun-14 A RM2-11750 CONNECT CYLINDER WITH SIDE SHIFT CAR 0 10-Jun-14 A 10-Jun-14 A RM2-11760 INSTALL THE FLOOR PLATES 0 11-Jun-14 A 11-Jun-14 A R2 BUR CHANGING DEVICER2 BUR CHANGING DEVICE 0 12-May-14 A 19-May-14 A SLED BASE RAIL INSTALLATIONSLED BASE RAIL INSTALLATION 0 12-May-14 A 15-May-14 A RM2-11770 POSITIONING FROM PASS LINE CENTRE 0 12-May-14 A 12-May-14 A RM2-11780 POSITIONING FROM MILL CENTRE 0 13-May-14 A 13-May-14 A RM2-11790 ADJUST AND MEASURE THE TOPOF RAIL WRT BENCH MARK 0 14-May-14 A 14-May-14 A RM2-11800 WELDING THE RAIL BASE PLATE 0 15-May-14 A 15-May-14 A SLED TRAVERCE CYLINDERSLED TRAVERCE CYLINDER 0 17-May-14 A 19-May-14 A RM2-11810 POSITION FROM LINE CENTRE 0 17-May-14 A 17-May-14 A RM2-11820 POSITION FROM MILL CENTRE 0 18-May-14 A 18-May-14 A RM2-11830 MEASURE AND ADJUST THE CENTRE OF TRUNION FROM BENCH MARK. 0 19-May-14 A 19-May-14 A FRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIALFRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIAL 30 15-Sep-14 15-Oct-14 B&S-10250 ROUGHING MILL TRIAL 30 15-Sep-14* 15-Oct-14 FRONT#6 (CROP SHEAR)FRONT#6 (CROP SHEAR) 46 18-Jan-14 A 16-Aug-14 CROP SHEARCROP SHEAR 46 18-Jan-14 A 16-Aug-14 CS-10000 INSTALLATION AND ALIGNMENT OF GEAR, REDUCER & MOTOR 0 22-Feb-14 A 23-Apr-14 A CS-10010 INSTALLTION OF COUPLING SUPPORT & COUPLING 0 23-Apr-14 A 03-Jun-14 A CS-10020 REMAINING WORKS AND ATTACHED PIPING 46 02-Jul-14 16-Aug-14 SHOE PLATE ALIGNMENTSHOE PLATE ALIGNMENT 0 18-Jan-14 A 18-Feb-14 A Safety measure for openingSafety measure for opening 0 18-Jan-14 A 18-Feb-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 29 of 81 Filter: All Activity
  • 30. Activity ID Activity Name Remaining Duration Start Finish CS-10030 Since the lower part is crop chute, install a scaffolding with enough strength. 0 18-Jan-14 A CS-10040 Lashing of scaffolding board should use the annealing wire. 0 18-Feb-14 A Foundation checkFoundation check 0 19-Jan-14 A 25-Jan-14 A CS-10050 Check foundation and anchor bolts according to JIMS and " Instruction Manual for Erection (10065148-2002072-WP001)"0 19-Jan-14 A 19-Jan-14 A CS-10060 Measure the position of foundation bolts from Line center and Crop Shear center. 0 20-Jan-14 A 20-Jan-14 A CS-10070 Measure the height of foundation bolts from reference level. 0 22-Jan-14 A 23-Jan-14 A CS-10080 Measure the clearance of Crop Shear Assembly installing area. Verify the no interference foundation to crop shear0 24-Jan-14 A 25-Jan-14 A Foundation Chipping (Roughing Foundation) and PaddingFoundation Chipping (Roughing Foundation) and Padding 0 12-Feb-14 A 14-Feb-14 A CS-10090 Chipping whole surface of grouting area. 0 12-Feb-14 A 13-Feb-14 A CS-10100 Sprinkle water and avoid dust. 0 14-Feb-14 A CS-10110 Cleaning the chipping surface (ex. dust, water, etc.) after completion of the chipping. 0 14-Feb-14 A PaddingPadding 0 14-Feb-14 A 15-Feb-14 A CS-10120 Execute padding according to Work Procedure by " Grouting Pad method" in "Instruction Manual for Erection (10065148-20 14-Feb-14 A 15-Feb-14 A Preparation of InstallationPreparation of Installation 0 28-Jan-14 A 28-Jan-14 A CS-10130 Remove the rust-preventive coating of the surface, which is contacted on the concrete grouting and required for insta0 28-Jan-14 A CS-10140 Pre-assembly and disassembly, if any. Assembly or remove the parts required for installation. When removing the parts0 28-Jan-14 A CS-10150 Taper liner should be set and adjusted the upper surface level. (4 points or more) 0 28-Jan-14 A 28-Jan-14 A Installtion and Alignment for Shoe PlateInstalltion and Alignment for Shoe Plate 0 28-Jan-14 A 28-Jan-14 A CS-10160 Shoe plate temporary placing 0 28-Jan-14 A 28-Jan-14 A CS-10170 After confirming the accuracy of the liner, install the delivery side shoe plate and check the center match mark is a0 28-Jan-14 A 28-Jan-14 A Installation and alignment of Shoe PlateInstallation and alignment of Shoe Plate 0 28-Jan-14 A 28-Jan-14 A CS-10210 Install the foundation bolt cover. Apply sufficient grease to the foundation bolts and fit the foundation bolts then0 28-Jan-14 A 28-Jan-14 A CS-10180 After verify the accuracy of the delivery side shoe plate, to be confirmed inside the entry side shoe plate using th0 28-Jan-14 A 28-Jan-14 A CS-10190 Ensure that the upper surface (machined surface) of the shoe plate is covered with plastic sheet to protect from dirt0 28-Jan-14 A CS-10200 Cut the foundation bolts, if any. 0 28-Jan-14 A 28-Jan-14 A GroutingGrouting 0 28-Jan-14 A 29-Jan-14 A CS-10260 Check and ensure that grouting shall be poured successively from one direction so as not to leave air pockets and ens0 28-Jan-14 A CS-10220 Set wooden frame and check its rigidity can support the grout load, and the depth shall conforms to the specification0 28-Jan-14 A 29-Jan-14 A CS-10230 Clear the surface area to be grouted from dust/foreign particle and clean with compressed air. Wipe out dry any oil s0 28-Jan-14 A 29-Jan-14 A CS-10240 Check if surface is properly saturated with water. Remove excess water. 0 28-Jan-14 A 29-Jan-14 A CS-10250 Check grouting materials and its mixing ratio if according to the specification or otherwise shall conform to JIMS D-0 28-Jan-14 A 29-Jan-14 A CS-10270 After finishing curing, check hardness. 0 28-Jan-14 A 29-Jan-14 A ERECTION OF CROP SHEARERECTION OF CROP SHEAR 0 30-Jan-14 A 02-Feb-14 A PreparationPreparation 0 30-Jan-14 A 30-Jan-14 A CS-10280 Preparation 0 30-Jan-14 A CS-10290 Before erecting the Crop Shear Assembly, install its parts to be installed during erection period, listed as follows:0 30-Jan-14 A CS-10300 HSG surface trimming. Clean and remove the damage portion of HSG machined surfaces that will contact with the shoe pl0 30-Jan-14 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 30 of 81 Filter: All Activity
  • 31. Activity ID Activity Name Remaining Duration Start Finish CS-10310 Work prior to Crop Shear Assembly erection. A) Complete installation of shoe plates b) Prepare the foot bolts and nut0 30-Jan-14 A Crop shear Erection and AlignmentCrop shear Erection and Alignment 0 31-Jan-14 A 02-Feb-14 A CS-10320 When erecting Crop Shear Assembly onto the shoe plates, lower the Assembly into position slowly, and carefully obser0 31-Jan-14 A Crop ShearAssembly onto the shoe plateCrop ShearAssembly onto the shoe plate 0 02-Feb-14 A 02-Feb-14 A CS-10330 Lifting Crop Shear Assembly by lifting beam with overhead cranes. b) HSG surface trimming 0 02-Feb-14 A 02-Feb-14 A CS-10340 Crop shear assembly onto the shoe plates. 0 02-Feb-14 A 02-Feb-14 A CS-10350 Verify the zero gaps for contact surface of HSG to top of shoe plate. 0 02-Feb-14 A 02-Feb-14 A CS-10360 Temporary bolting HSG with shoe plate by foot bolts. (Don't use hammer, only soft tighten by hand) 0 02-Feb-14 A 02-Feb-14 A CS-10370 Adjust the Assembly position from line center same as drawing dimension. 0 02-Feb-14 A 02-Feb-14 A CS-10380 Positioning Crop Shear Assembly. The Assembly push to the delivery side and verify the zero gaps between HSG and s0 02-Feb-14 A 02-Feb-14 A MEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACYMEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACY 0 02-Feb-14 A 02-Feb-14 A CS-10390 Prepare the scaffolding, if any, and piano wire according to the drawing on the right and the measurement procedure.0 02-Feb-14 A 02-Feb-14 A CS-10400 Final tighten the foot bolts after completion the alignment of Crop Shear Assembly. 0 02-Feb-14 A 02-Feb-14 A CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS)CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS) 0 20-Mar-14 A 12-Apr-14 A CS-10410 MOTOR ALLIGNMENT (6 MOTORS) 0 05-Apr-14 A 10-Apr-14 A CS-10420 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 10-Apr-14 A PREPARATIONPREPARATION 0 20-Mar-14 A 03-Apr-14 A CS-10430 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 20-Mar-14 A 21-Mar-14 A CS-10440 ERECTION OF TABLE BEAM 0 22-Mar-14 A 23-Mar-14 A CS-10450 INSTALLATION OF MOTOR FRAME 0 24-Mar-14 A 25-Mar-14 A CS-10460 PRELIMINARY LEVELING &ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRETO LINE CENTRE0 26-Mar-14 A 29-Mar-14 A CS-10470 INSTALLATION OF MOTOR 0 02-Apr-14 A 02-Apr-14 A CS-10480 SETTING THE ANCHOR BOLTSAND NUTS 0 02-Apr-14 A 02-Apr-14 A CS-10490 ANCHOR GROUTING AND CURING. 0 03-Apr-14 A 03-Apr-14 A ALLIGNMENTALLIGNMENT 0 03-Apr-14 A 04-Apr-14 A CS-10500 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 03-Apr-14 A 03-Apr-14 A CS-10510 CHECK THE LEVELNESS 0 04-Apr-14 A 04-Apr-14 A CS-10520 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 04-Apr-14 A 04-Apr-14 A REMAINING WORKSREMAINING WORKS 0 10-Apr-14 A 12-Apr-14 A CS-10530 INSTALLATION OF MOTOR COVER 0 10-Apr-14 A 11-Apr-14 A CS-10540 INSTALLATION OF SPLASH GUARD 0 11-Apr-14 A 11-Apr-14 A CS-10550 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 11-Apr-14 A 11-Apr-14 A CS-10560 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 11-Apr-14 A 12-Apr-14 A Shop piping including water & UtilitiesShop piping including water & Utilities 94 19-Nov-12 A 30-Oct-14 Mechanical & Piping WorksMechanical & Piping Works 94 19-Nov-12 A 30-Oct-14 UTILITY PIPING Works (Shop Piping)UTILITY PIPING Works (Shop Piping) 94 19-Nov-12 A 30-Oct-14 Water SystemWater System 94 19-Nov-12 A 30-Oct-14 May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 31 of 81 Filter: All Activity
  • 32. Activity ID Activity Name Remaining Duration Start Finish SP-10000 Drawing Inputs 0 19-Nov-12 A 10-May-14 A SP-10010 Fabrication of Piping spools 12 04-Mar-13 A 17-Jul-14 SP-10030 Run out table Piping 30 03-Feb-14 A 08-Aug-14 SP-10070 Strip Cooling (WDS1) 32 02-Sep-13 A 11-Aug-14 SP-10110 Drainage Pumps. (WA1) 35 03-Feb-14 A 14-Aug-14 SP-10120 Drain for Down Coiler 25 30-Jul-14 01-Sep-14 SP-10080 High Pressure Water. (WH) 54 02-Sep-13 A 09-Sep-14 SP-10060 Direct Cooling Water 55 02-Sep-13 A 11-Sep-14 SP-10090 Indirect Cooling Water (W1) 59 02-Sep-13 A 16-Sep-14 SP-10050 Make up Water 60 02-Sep-13 A 17-Sep-14 SP-10040 Fire Fighting 63 02-Sep-13 A 20-Sep-14 SP-10020 Drinking Water. 94 02-Sep-13 A 30-Oct-14 Finishing Mill & ROT (including Crop shear, SD) + CFL + Transfer carFinishing Mill & ROT (including Crop shear, SD) + CFL + Transfer car 106 27-Dec-11 A 15-Oct-14 F1 to F7 (equipment), B&S coordination & Mechanical ErectionF1 to F7 (equipment), B&S coordination & Mechanical Erection 106 27-Dec-11 A 15-Oct-14 Civil Building & Foundation WorksCivil Building & Foundation Works 0 27-Dec-11 A 16-Dec-13 A B-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 27-Dec-11 A 20-Aug-13 A FM-10010 Building Column 0 27-Mar-12 A 31-Oct-12 A FM-10020 Scale Sluice 0 08-May-12 A 31-Oct-12 A FM-10000 Drawing Inputs incl. Equipment foundation 0 27-Dec-11 A 25-Jul-13 A FM-10030 Finishing Mill Equip Foundation Including Scale flume wall 0 16-Jul-12 A 20-Aug-13 A B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 16-Dec-13 A FM-10050 Building Column 0 02-Jul-12 A 15-Oct-12 A FM-10040 Drawing Inputs incl. Equipment foundation 0 03-Apr-12 A 15-Jul-13 A FM-10060 Run out table Equip foundation 0 31-Aug-12 A 16-Dec-13 A Structural Building & Technological WorksStructural Building & Technological Works 0 03-Apr-12 A 25-Mar-14 A B-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 15-Jun-12 A 04-Nov-13 A FM-10070 Drawing Inputs 0 15-Jun-12 A 03-Sep-12 A FM-10080 Fabrication 0 17-Sep-12 A 30-Apr-13 A FM-10090 Erection (including sheeting) 0 16-Oct-12 A 04-Nov-13 A B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 25-Mar-14 A FM-LC-10000 Drawing Inputs 0 03-Apr-12 A 31-Oct-12 A FM-LC10010 Fabrication 0 02-Jul-12 A 30-Apr-13 A FM-LC-10020 Erection 0 17-Sep-12 A 13-Nov-13 A FM-LC-10030 Sheeting 0 02-Aug-13 A 25-Mar-14 A Mechanical & Piping WorksMechanical & Piping Works 56 15-Feb-13 A 26-Aug-14 Mill Preconditions for ErectionMill Preconditions for Erection 0 23-May-13 A 03-Feb-14 A FM-10170 Availability of Fire extinguisher equipments 0 05-Jul-13 A May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 32 of 81 Filter: All Activity