This document contains a project schedule for the Al Ain Water Distribution Network project. It lists activities with original durations, start and finish dates, and budgets. Key activities and milestones include signing agreements by December 2009, advance payment by January 2010, completion of design by June 2011, delivery and installation of pump units from February to October 2011, and completion of the project and issuance of the Final Acceptance Certificate by October 2013. The document provides detailed schedules for project phases like design and engineering, mechanical works, and pipe installation.